PROJECT PROGRESS REPORTJANUARY 2019
QUESTIONS? Contact:Dr. Dennis Pauli, District Administrator
WHAT’S NEW?Since voter approval of the November 2018 referendums, the District has kicked-off the planning and design process. The Core Planning Team (CPT), made up of district staff and administrators, has begun meeting with Bray Architects and JP Cullen to refine floor plans at the high School and elementary school, and is making progress on the secure entries at both Yahara Valley Elementary and the middle school.
WHAT’S NEXT?In the month ahead, the District will be working with Bray Architects to establish subcommittees made up of staff from both the high school and Community Elementary. These subcommittees will be charged with providing guidance and feedback on the daily operations of each of the buildings in regards to the proposed floor plans. The District and its design/construction partners are also working on scheduling tours of schools for the CPT and subcommittees to get a sense of what other districts in the area are doing.
WHEN WILL CONSTRUCTION BEGIN?Construction is scheduled to run from June 2019 through August 2020. The projects will be completed in phases to keep as much of the buildings operational as possible during the construction process.
In an effort to keep the community, students and staff informed and engaged throughout the process, the District will continue to provide monthly progress reports throughout the design and construction phases.
Updates will be shared on the district website: www.edgerton.k12.wi.us
2018 2019 2020OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
COMMUNITY ELEMENTARY SCHOOL (A,B + C)
DESIGN
BIDDING
CONSTRUCTION
» SITE IMPROVEMENTS (C)
» ADDITION & AREA A RENOVATION (A)
» AREA B RENOVATION (B)
MOVE-IN / OCCUPANCY
EDGERTON HIGH SCHOOL (E + D)
DESIGN
BIDDING
CONSTRUCTION
» ADDITION (E)
» ALL RENOVATION* (E + D)
MOVE-IN / OCCUPANCY
YAHARA / MIDDLE SCHOOL SECURE ENTRIES
DESIGN
BIDDING
CONSTRUCTION (F + G)
MOVE-IN / OCCUPANCY
PRELIMINARY PROJECT SCHEDULES
The schedules above are preliminary and are subject to change.
*Note that we are comfortable working with the district to see if we can advance the science wing renovation to hit the first summer.
Denotes summer months.
bray architects solid foundation. forward thinking.
Project #: 3349
Additions - June 2019 - August 2020 Remodel - May 2020 - August 2020
Note: Some work at night & break between January 2020 & May 2020
KEY
A Community Addition/Area A Renovation B Community Renovation Area B C Site D High School - Science, Math, Library Renovation
E Commons/Band/Entry Addition & Renovation F Middle School - Secure Entry G Yahara Elementary - Secure Entry
Site Plan SCALE: Not to Scale
Edgerton School District Edgerton, WI
January 10, 2019