DB International GmbH
Qatar Integrated Railway Project (QIRP)Qatar Railways in Future – Design and Build under Special Conditions
Cottbus, 11.02.2013
J. Marienhagen
International Projects
Project PresentationFebruary 11th, 2013, BTU Cottbus
Qatar Integrated Railway Project (QIRP)
DB International GmbH1
Content
Introduction: Where is Qatar?
QRDP Project Overview
Important QRDP / QIRP Project Milestones
Role of DB International
Present Main Topic: Tender Documents
Time Schedule
Project Organisation
Management Approach
Milestones in Project Management
Technical Spotlights
Qatar Integrated Railway Project (QIRP)
DB International GmbH2
Content
Introduction: Where is Qatar?
Qatar Integrated Railway Project (QIRP)
DB International GmbH3
World Map
Source: public domain
Qatar Integrated Railway Project (QIRP)
DB International GmbH4
Map Qatar
BerlinBerlin
DohaDoha
Source: public domain
Qatar Integrated Railway Project (QIRP)
DB International GmbH5
Doha, Map and Impressions
Map Source: public domainPictures: © J. Marienhagen
Qatar Integrated Railway Project (QIRP)
DB International GmbH6
Content
QRDP Project Overview
Qatar Integrated Railway Project (QIRP)
DB International GmbH7
Bauboom in Qatar – Middle East Economic Digest
1. Ein 4 Mrd. USD Stadion-Bauprogramm sieht den Bau von neun umweltfreundlichen, innovativen Fußballstadien vor sowie den Ausbau von drei existierenden Stadien.
2. Das umfassende Straßenausbau- und Verbesserungs-programm von 20 Mrd. USD beinhaltet den Lusail Expressway, Doha Expressway, Dukhan Freeway sowie die Doha Bay Kreuzung.
3. Weitere 25 Mrd. USD decken den Bau einer Stadtbahn, einer Hochgeschwindigkeitsstrecke zwischen NDIA, Stadtzentrum Doha und dem vorgesehenem Qatar Causeway nach Bahrein ab.
4. Zusätzlich soll eine Strecke für den Güterverkehr entstehen, die an die GCC Staaten anknüpfen wird.
Die beiden Punkte 3. und 4. werden im Qatar Rail Development Programme (QRDP) zusammengefasst.
Source logo: FIFA
Qatar Integrated Railway Project (QIRP)
DB International GmbH8
Qatar Railway Development Program
Qatar Integrated Railway Project (QIRP)Metro and Long Distance Network scheme
Metro NetworkPhase 1 (FIFA 2022)
Long Distance Network
9
Qatar Integrated Railway Project (QIRP)
DB International GmbH10
Content
Important QRDP / QIRP Project Milestones
Qatar Integrated Railway Project (QIRP)
Long Distance NetworkPhases 1, 2, 3 and 4 to be specified
2012 203020222020 20252014
Important QRDP Project Milestones
Metro Network Phase 2Metro Network Phase 1 (FIFA 2022)
Main technical solutions
Important, time-critical Tenders
Organisational basis
2018
Inauguration Freight Network
Inauguration Test Section
Inauguration First Line Section
11
Qatar Integrated Railway Project (QIRP)
DB International GmbH12
Content
Role of DB International
Qatar Integrated Railway Project (QIRP)Role of DBI Branch Qatar
The Role of the DBI within this phase of the project is the
„Lead Consultant“.
DBI Branch Qatar workforce consists of two different kinds of Employees:
DB (I) staff contracted as „secondees“ for Qatar Railways (approximately 40 employees)
DBI staff located in the branch office (approximately 30 employees)
Depending of the workload, all other DBI ressources as well as many subconsultants are supporting this staff. In 2012, more than approx. 150 engineers and technicians worked in parallel for the design works.
Branch Qatar
13
Qatar Integrated Railway Project (QIRP)
DB International GmbH14
Content
Milestones in Project Management
Qatar Integrated Railway Project (QIRP)
15
Concept
Feasibility Study
Preliminary Design
Detailed Design/ Shop Drawings
Construction and Installation
Testing
Commissioning
Maintenance/ Operation
Time
Definition
Integration
Implementation
Verification
Validation
Typical Phasing of a Project
Specification
Handover
Qatar Integrated Railway Project (QIRP)Sidestep: FIDIC
International Federation of Consulting Engineers FIDIC
16
Die Aufteilung der Vergabe ist ganz anders geregelt als in Deutschland in der HOAI.
Für verschiedene Auftrags- (Vergabe-) arten kommen verschiedene FIDIC- Rahmen-verträge zur Anwendung. Diese sind in jedem Einzelfall gesondert zu verhandeln und präzisie auf den jeweiligen Vertrag anzupassen.
Bezogen auf das aktuelle Projekt sind das Yellow BookYellow Book(Plant and Design-Build, designed by the Contractor) sowie das Red Book Red Book (Construction, designed by the Employer)vergleichbar mit unseren bekannten Vergabeverfahren.
Qatar Integrated Railway Project (QIRP)
17
Concept
Feasibility Study
Preliminary Design
Detailed Design/ Shop Drawings
Construction and Installation
Testing
Commissioning
Maintenance/ Operation
Time
Typical Tendering Procedures
Handover
Tender
Tender
Definition
Integration
Implementation
Verification
ValidationSpecification
Qatar Integrated Railway Project (QIRP)
DB International GmbH18
Content
Present Main Topic: Tender Documents
Qatar Integrated Railway Project (QIRP)
DB International GmbH19
Scope of Work: DBI 2012
WO#01Civil
forTunnels
WO#04Civil @Grade
& Elevated
WO#05TrackWorks
WO#07*Operation & Maintenance
WO#08RailwaySystems
RollingStock
MEP
DBI scope
Scope to be assigned
LEGEND:WO#08 RAMS Management
Qatar Rail RAMS Management
MEP
Third Party(e.g. road
authority, civil constructions,
NDIA, ...)
Other Rail projects (e.g. LRT and LD)
DBI RAMS Management
DepotsICC/ECC
MEP scope
Scope of Work 2012: Tender Design / Tender Documents for different „Work Orders“
Qatar Integrated Railway Project (QIRP)
DB International GmbH20
WO#01Civil
forTunnels
WO#04Civil @Grade
& Elevated
WO#05TrackWorks
WO#07*Operation & Maintenance
WO#08RailwaySystems
RollingStock
MEP
DBI scope
Scope to be assigned
LEGEND: WO#08 RAMS Management
Qatar Rail RAMS Management
MEP
Third Party(e.g. road
authority, civil constructions,
NDIA, ...)
Other Rail projects (e.g. LRT and LD)
DBI RAMS Management
DepotsICC/ECC
MEP scope
WP S: SignallingInfraOn-board
WP T: TelecomRadioFixedSCADA BACS
WP E: EnergySPSTPS3rd railSCADA PCSS
WP V: Tunnel Ventilation
Study
WO#08 RAMS Management
EMC Management
Interface Management
Scope of Work: Work Order 8 „Railway Systems“
Qatar Integrated Railway Project (QIRP)
21
RAM and Safety Management
EMC Management
Interface Management
Energy Telecom Signalling Tunnel Ventilation
Railway Systems: Subsystems Overview
Project Management
Qatar Integrated Railway Project (QIRP)
DB International GmbH22
Content
Time Schedule
Qatar Integrated Railway Project (QIRP)
DB International GmbH23
Projektphasen:
Angebotsvorbereitung / Akquise
Angebotsbearbeitung
Verhandlung
Angebotsüberarbeitung
Abschließende Verhandlung
Beauftragung durch ‚Notice to proceed‘
Beauftragung durch Vertrag
Bearbeitung
Prüfung / Überarbeitung
Projektabschluss
From Aquisition to Project Finalisation
Zeitlicher Ablauf:
10/2010 – 11/2011
11/2011 – 03/2012
02/2012 – 05/2012
03/2012 – 05/2012
Ende 05/2012
01.06.2012
01.08.2012
03/2012 – 11/2012
11/2012 – 01/2013
31.01.2013
Qatar Integrated Railway Project (QIRP)
DB International GmbH24
Contract Award
Project Execution Plan +2 weeks
Inception Report +6 weeks
Conceptual Design +4 months
Tender Design +7 months
Reviewed Tender Design +8 months
Milestones within the design project
Qatar Integrated Railway Project (QIRP)
Time schedule, milestones and deliverables due date
25
Project Execution Plan 20.06.12
Inception Report, Assumptions Register 12.07.12
Conceptual design 11.09.12
Tender Design 30.11.12
Reviewed Tender Design 31.12.12
DezAug Sep Oct NovJun JulMay
Milestones within the design project
Qatar Integrated Railway Project (QIRP)
DB International GmbH26
Content
Project Organisation
Qatar Integrated Railway Project (QIRP)
DB International GmbH27
Organisational Chart
Lines of Communication: Official project communication will be between Director Systems and PM Technical communication will be initiated by PM
Consultancy Services for Tender Design Railway Systems (WO #8)
Client:
Consultant:
SignallingA. Heneka
Branch Qatar
CTOD. Leckel
Director SystemsM. Olschewski
Q A T A R R A I L C P O / S P M
TelecomO. Matthäi
EnergyR. Geisendorf
EMCH. Neumann
Tunnel VentilationDr. P. Reinke
Quality ManagementDocument Management
Project Controlling
Project ManagementJ. Marienhagen
A. Winter / A. Linssen
Qatar Integrated Railway Project (QIRP)
DB International GmbH28
Organisational Chart (detailled)
Branch Management
M. Ahlgrimm
contractual technical
Client:
Consultant:
Chief Technical OfficerD. Leckel
Director SystemsM. Olschewski
SignallingA. Heneka
K. Tahmassebi
Q A T A R R A I L
TelecomO. MatthäiA. Winter
EnergyR. GeisendorfJ. von Lingen
EMCH. Neumann
R. Kadhim
Administrative ServicesLegal Advice
N. Henckel
Contract ManagementP. BethgeD. Golz
Project ManagementJ. Marienhagen
A. Linssen / A. Winter
WP C1: EMC Managmt.Dr. R. Hietzke*
R. Arlt +
WP C2: EMC Design H. Neumann*J. Thiemig+
WP T1: Radio SystemsN. Vu
B. Klingenberg
WP T2: Fixed SystemsV. Vaxevanakis
O. Matthäi
WP S1: Metro Infrastr.A. Heneka , M. Franke
P. Czerkewski*
WP S2: Req. On-boardA. TahmassebiM. Marschollek*
WP T3: SCADA BACSM. KuhneF. Hein
WP E2: SPSDr. A. Frenzel+
R. Zillmer+
WP E4: Sys Rq. 3rd RailF. Helms, F. König
WP E3: DC TPSF. Helms, F. König
T. Scherrans*, M. Gumprecht*
WP E5: SCADA-PCSSF. König
WP C3: Proof of EMC Dr. K.-H. Kuypers
Dr. S. Röhlig +
* … Subcontractor IfB+ ... Subcontractor KEMA/ELBAS◦ … Subcontractor HBI
RAM & SafetyT. Ploeg+
P. Franck+
Quality ManagementDr. K. HofmannU. Kohlenberger
Document ManagementT. Germann
TVS Dr. P. Reinke◦
Technical ServiceSupport / CADU. Engelhardt
S. HelmsA. Souradny
N.N.*N.N.+
Project ManagementAssistanceJ. Drescher
p.u.
Qatar Integrated Railway Project (QIRP)
DB International GmbH29
Technical Counterparts – tailored project organisation
Qatar Integrated Railway Project (QIRP)
DB International GmbH30
Average presence
rateneeded in Doha
50%
0
5
10
15
20
25
30
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3
Num
ber
of P
erso
nnel
Calendar Week
Staffing Concept per Week
Germany
Qatar
Staffing Concept (Plan)
Qatar Integrated Railway Project (QIRP)
DB International GmbH31
Content
Management Approach
Qatar Integrated Railway Project (QIRP)
DB International GmbH32
Management Approach (1): Thinking Ahead
Different design stages within a project require a different project management attention
Project PhaseProject Management Technical Workforce
Project Initiaon Phase
Project Execution Plan
Inception Report
Conceptual D
esign
Tender Docum
entation
Rew
ork Phase
Project Closure
Aquisition
Qatar Integrated Railway Project (QIRP)
DB International GmbH33
Management Approach (2): Leading Documents
The project starts with creating a Project Execution Plan (PEP). It can be updated and revised through whole the technical
processes phase. The PEP is based upon the definitions given by the „System Engineering Process“ (ISO/IEC 15288).
Qatar Integrated Railway Project (QIRP)
DB International GmbH34
Management Approach (2): Leading Documents
After analysing the scope in very detail, the first ideas for fulfilling the work has to compiled and discussed with the Client.
Therefore, an Inception Report (IR) has to be issued.
Inception Report
Qatar Integrated Railway Project (QIRP)
DB International GmbH35
Management Approach (3): Conceptual Design as Presentation Event
Within the project progress, many detailed technical discussions were held.
Presenting the Conceptual Design as one of the most important milestones / results within the technical progress has to be an outstanding, memorable event. In order to avoid a “normal” presentation, we decided to organise this 2-day event as a splitted performance.
Day 1: presentation event in a hotel, one hour per technical discipline including short discussion
Day 2: “After Show Parties” for discussion of the technical issues in parallel and in the needed degree of detail.
Result: concentrated project progress involving all technical work packages
Qatar Integrated Railway Project (QIRP)
DB International GmbH36
Management Approach (4): Completion of Tender Documentation
After getting a “no objection” notice by the Client to the technical approach and the presented level of detail within the tender documentation, the Conceptual Design was transferred into a comprehensive technical documentation.
These documents consist of technical descriptions as well as some generic drawings.
The resulting documents are intended to form the “particular employers requirements”according to FIDIC regulations.
A Review Phase, incorporating all the comments of the Client as well of some independent checking authorities, is the last activity of the actual project.
Qatar Integrated Railway Project (QIRP)
DB International GmbH37
Content
Technical Spotlights
Qatar Integrated Railway Project (QIRP)
38
Technical Spotlights: Grades of Automation
The performance of mass transit systems is largely dependent on the performance of the train control. With increasing automation, the responsibility for operation management is passing from the driver to the system. A train control system comprises functions for supervision, operation and control of the entire operational process. It can feature different degrees of automation such as manual train operation, semi-automated train operation and unattended operation.
These types of operation are referred to as Grade of Automation
reference:
Qatar Integrated Railway Project (QIRP)
39
Objectives / Functional requirementsTVS integral element of metro system to ensure:acceptable level of tunnel air temperaturelimited air pressure and pressure transients in tunnels and inside trains sufficient air exchange rates for sufficient air quality (smell, pollution, humidity) smoke free areas during fire
Technical Spotlights: Tunnel Ventilation System (TVS)
Source: HBI Haerter AG
Qatar Integrated Railway Project (QIRP)
DB International GmbH40
Technical Spotlights: Tunnel Ventilation System (TVS)
add. extreme value analysis
Qatar Integrated Railway Project (QIRP)
41
Principle IllustrationMode
Water drop/ Fog curtain (wet cooling)
Emergency
Congested
Cold air supply (dry cooling)
Maintenance
Technical Spotlights: Tunnel Ventilation System (TVS)
Qatar Integrated Railway Project (QIRP)
DB International GmbH42
Assumptions Register – verification process
Each technical definition requires an agreement from different sides.
In any case where this agreement cannot reached (due to a missing counterpart or a missing definition), an assumption has to be made.
These assumptions are consolidated in a “Assumptions Register”, which is a living document .
The aim is to solve all these assumptions before tendering.
Qatar Integrated Railway Project (QIRP)Hazard Analysis
43
Hazard identification
Qualitative Risk Assessment
Definition of risk mitigation
This means hazards of the system itself (track works) but also hazards in relation to interfaces with other work orders will be identified
Determining the likelihood of an event in combination with the severity of the outcome (Inherent Risk Ranking)
Determining for the risks which have an to high inherent Risk Ranking what mitigating measures could reduce the risk ranking.
Qatar Integrated Railway Project (QIRP)
DB International GmbH44
Interface Management
Qatar Integrated Railway Project (QIRP)
DB International GmbH45
Interfaces to disciplines out of DBI scope
Qatar Integrated Railway Project (QIRP)
DB International GmbH46
Levels of authorizationPrepared
Checked
Approved
Authorized for issue
by a competent Person who produces the design document, complying with codes and standards governing that work.
Generally speaking this will be the Project Manager or formally advised delegate.
Documents may only be approved for issue by the authorized person as defined in the Engineering Standards.
by a competent person able to undertake a formal detailed check of design methods, codes and standards used, deliverables, calculations, drawings, and technical specifications produced by another member of the Engineering Team. This role will be undertaken by a competent person of the same discipline, not the Preparer, but can be a member of the same team for a Category I check
Quality Gate / EPLASS workflow
Qatar Integrated Railway Project (QIRP)
DB International GmbH47Doha, Museum of Islamic Art / Skyline of West Bay __ © J. Marienhagen
Thank you for your attention!