project periodic report - cordis · 2017-04-22 · 2 declaration by the scientific representative...
TRANSCRIPT
![Page 1: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/1.jpg)
PERIODIC REPORT – ISENSE - 2011
PROJECT PERIODIC REPORT
Grant Agreement number: 250072
Project acronym: ISENSE
Project title: Integrated Quantum Sensors
Funding Scheme: STREP (ICT-FET-Open)
Date of latest version of Annex I against which the assessment will be made: 4. March 2011
Periodic report: 1st x 2nd □ 3rd □ 4th □
Period covered: from 1. July 2010 to 30. June 2011
Name, title and organisation of the scientific representative of the project's coordinator1:
Professor Kai Bongs, College of Engineering and Physical Sciences, School of Physics and Astronomy, University of Birmingham
Tel: +44 121 414 8278
Fax: +44 121 414 8277
E-mail: [email protected]
Project website2 address: http://www.isense-gravimeter.com/
1 Usually the contact person of the coordinator as specified in Art. 8.1. of the grant agreement
2 The home page of the website should contain the generic European flag and the FP7 logo which are available in
electronic format at the Europa website (logo of the European flag: http://europa.eu/abc/symbols/emblem/index_en.htm
; logo of the 7th FP: http://ec.europa.eu/research/fp7/index_en.cfm?pg=logos). The area of activity of the project should
also be mentioned.
![Page 2: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/2.jpg)
2
Declaration by the scientific representative of the project coordinator1
I, as scientific representative of the coordinator1 of this project and in line with the obligations as stated in Article II.2.3 of the Grant Agreement declare that:
The attached periodic report represents an accurate description of the work carried out in this project for this reporting period;
The project (tick as appropriate):
X has fully achieved its objectives and technical goals for the period;
□ has achieved most of its objectives and technical goals for the period with relatively minor deviations3;
□ has failed to achieve critical objectives and/or is not at all on schedule4.
The public website is up to date.
To my best knowledge, the financial statements which are being submitted as part of this report are in line with the actual work carried out and are consistent with the report on the resources used for the project (section 6) and if applicable with the certificate on financial statement.
All beneficiaries, in particular non-profit public bodies, secondary and higher education establishments, research organisations and SMEs, have declared to have verified their legal status. Any changes have been reported under section 5 (Project Management) in accordance with Article II.3.f of the Grant Agreement.
Name of scientific representative of the Coordinator1: ........Kai Bongs...........
Date: 30/09/2011
Signature of scientific representative of the Coordinator1: ................................................................
3 If either of these boxes is ticked, the report should reflect these and any remedial actions taken.
4 If either of these boxes is ticked, the report should reflect these and any remedial actions taken.
![Page 3: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/3.jpg)
3
1. Publishable summary
iSense – INTEGRATED QUANTUM SENSORS
Project objectives
The iSense project aims to bring the latest developments in ultracold atom science to practical
applications by developing the technology that will turn laboratory-based instrumentation into
portable and robust instruments and sensors.
State-of-the-art ultracold atom experiments, which cool down a cloud of atoms to temperatures
close to the absolute zero with the aid of lasers, have demonstrated an exquisite degree of control
over matter. At record-low temperatures, close to the absolute zero, it is now possible to harness the
quantum nature of matter in order to develop futuristic applications involving delicate sensing or
secure communications.
In this context, the goal of iSense is two-fold. First, it develops a set of tools and technologies that
can be used as basic blocks to build a robust and portable device based on ultracold atoms. Second
it aims to demonstrate this new technology platform by realising an ultracold-atom-based
instrument able to measure the gravitational field with a precision comparable to the best
commercial instrument, but in a more compact and portable format.
In the future, we hope that iSense will open the door to the integration of ultracold atom technology
to fields as diverse as geodesy, mineral prospection, satellite communications, portable atomic
clocks, secure quantum communications, and fundamental research.
A typical ultracold atom experiment is complex enough to fill a room. It is composed of a vacuum
chamber that contains the gas of ultracold atoms, a number of lasers with their stabilisation optics
and electronics, electromagnets to create magnetic fields and an optical table to hold all this
equipment. It also consumes a lot of energy, more than a powerful electric heater.
The challenge of iSense is to reduce the size and the energy consumption of the apparatus to make it
fit in a volume that could be manipulated and carried around by a single person, something like the
size and weight of a large backpack. It should also be autonomous.
Work performed since the beginning of the project
During the first period of the project, we have initiated the design and/or tested the concept of all
the components of the technology platform required to build the iSense gravimeter. This includes an
integrated optical system, micro-integrated laser modules, electronics modules, an atom chip and a
vacuum chamber. The general interfaces between all the components have been determined, leaving
room for optimisation at the module level.
![Page 4: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/4.jpg)
4
The project website, internal project Wiki and communication tools have been established.
Main results achieved so far
Micro-integrated laser systems
Laser cooling of atoms requires high-quality lasers
with significant power. We are improving the
technology of semiconductor lasers (laser diodes)
to make them suitable for ultracold atom sensors.
The micro-integrated laser production is well in
schedule. DFB-RW lasers have been produced
with the required parameters. The power amplifier
wafers have been processed and we are awaiting
first measurements. The development and design
of extended cavity diode lasers, which have a
narrow linewidth, has been completed and
components sent out to manufacture. First
prototypes are expected in late August 2011.
Miniaturized spectroscopy cells, which allow the
lasers to stay tuned to the atomic resonances, have
been produced and tested. Fibre coupling methods
and Zerodur baseplate technologies have been
tested on track for integration of the entire laser
system.
Integrated optical splitter device
The iSense project seeks to drastically reduce the footprint of the optical system by combining the
optical elements on a single semiconductor chip. It will integrate the guiding, splitting, combining
and switching of the laser beams.
Nottingham has taken over the tasks assigned to QinetiQ in the original Annex-I and has
successfully started modelling work for integrated devices. First samples shall be produced in
autumn 2011. The work on an alternative free-space optical delivery module has started ahead of
schedule with a preliminary system design and some component tests.
Electronics
The optical set up is composed of many active components, such as the lasers, switches, frequency
modulators, that require their own electronic drivers and need to be run synchronously.
The ongoing development of small electronics modules is on track. Several modules such as high-
current power amplifier drivers, temperature controllers, a switching module and a housekeeping
module have been finalised.
Atom Chip
The trapping of ultracold atoms requires a magnetic field in addition to the lasers. A modern
approach consists in generating the magnetic field with copper tracks running on a small substrate, a
so-called atom chip.
![Page 5: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/5.jpg)
5
A first generation stand-alone atom chip has been demonstrated to trap atoms in a magneto-optical
trap with a power consumption below 5W, although a current requirement of 100 A. A second
generation chip has been designed with a current requirement of 20 A and will be fabricated within
the next months.
Science Chamber
Ultracold atoms needs to be perfectly insulated from the rest of the world and are therefore placed
in a vacuum chamber. The chamber is an assembly of glass parts, to let the laser light in, and metal
part, to hold pumps and various electrical connexions.
Various glass-metal bonding techniques have been tested. Non-glue techniques have proven
susceptible to failure, such that the decision was taken to base the iSense vacuum chamber on
modern gluing technology.
Interrogation Schemes
Quantum sensing with ultracold atoms is based on atom interferometry, where matter waves replace
the light waves found in conventional interferometers. We develop new interferometry schemes
aiming at reducing the amount of space required and therefore reducing the final size of the sensor.
Wannier-Stark, Modulation and Levitation interferometry schemes have been implemented and
tested. The optimization of the sensitivity and accuracy of these schemes is under way, although a
preliminary analysis indicates that the Levitation scheme is unlikely to reach the iSense sensitivity
target.
Dissemination and collaboration
The iSense consortium has installed a website, published 4 papers and contributed to 14
conferences. In particular the iSense project was also represented at the FET11 conference.
Expected final results
At the end of the project, we expect to have developed a general technology platform proven by the
demonstration of a self-contained backpack-size, “turn-key” quantum system. In particular we
expect the following final results:
- iSense will create a set of integrated optics integrating beamsplitting and amplitude modulation
functions for cold atom applications at 780nm using GaAs technology.
- iSense will create a step-change in laser technology based on the novel optical microbench
technology used by the partner FBH with a factor of 100-1000 volume size reduction as
compared to the current state-of-the-art. iSense will deliver narrow linewidth MOPA-lasers and
ECDLs in microbench technology also going to more complex systems, like ECDLs with an
atomic reference cell integrated on the micro-bench.
- iSense will realize novel low-power atom chips, which can operate without external coils and
will investigate optimization for sensor operation and transparent conductor technology.
- iSense will realize novel compact and fully UHV compatible systems with full anti-reflection
coating as necessary for ultra-precise sensor applications. The size of below 0.001 m3 will be
more than 1order of magnitude smaller than the current state-of-the-art
- iSense will develop a SMD-based electronics platform with coherent computer control, such
that fully autonomous operation of cold atom experiments will be possible for the first time. As
![Page 6: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/6.jpg)
6
a particular point, iSense will develop a compact precision radiofrequency reference source for
application in atom sensors.
- iSense will develop and optimize “trapped” schemes for highest precision measurements –
removing the need for free-fall distances and allowing for compact local shielding of magnetic
fields and other external disturbances. In particular schemes based on Wannier Stark states,
Bloch oscillations or levitation by repeated Bragg diffraction will be studied. - Isense will realize a force sensor with 10
-9g sensitivity potential in a volume <0.1m
3
Potential impact and use
The field of cold atom research is currently facing a paradigm change, in which interest shifts from
the quantum gas as such to its exploitation in precision sensors, quantum simulation and quantum
ICT. With research and innovation now focusing on these applications, there is an emerging need
for a small, robust and reliable technology platform delivering cold atoms as a readily available
quantum resource.
The iSense project will provide an enabling platform for the development and exploitation of
commercial cold atom quantum sensor applications. In addition to being of potential benefit to the
entire cold atom research community, this platform will also deliver the underpinning technology
for a novel approach to quantum ICT research. In particular, the iSense integrated gravity sensor
technology, which will allow us to “see” what the underground is made of, has the potential to
revolutionize geophysical exploration and geophysics research. It would provide superior sensitivity
for mapping of e.g. oil fields, mineral deposits or monitoring of carbon capture sites, helping to
secure future energy supply as well as controlling CO2 emissions. On satellite missions as currently
discussed by ESA (e.g. APPIA project) cold atom gravity sensors could provide a new quality of
global geodetic data allowing e.g. to monitor water circulation at an unprecedented level and thus
providing crucial tests to current climate models. In addition iSense lays the foundations for
broadening of its technology platform to small scale optical frequency standards, which could
provide ultra-precise timing in future high-capacity communication networks.
Scientifically, the iSense project will provide new insights into the major factors influencing “local”
cold atom inertial sensing schemes, including sensitivity scaling, fundamental decoherence effects
and technical noise limitations. Using these schemes the iSense project aims at precision
measurements of h/m for Rubidium atoms, the measurement of the Casimir force and the search for
novel forces leading to deviations from the 1/r2 gravitational potential. Furthermore, iSense will
investigate the 83Sr isotope as well as various Yb isotopes with respect to collisional parameters
and the possibility to create a quantum degenerate sample as a potential resource for frequency
sensor applications. In addition iSense will advance the state of knowledge and ensure a leading
position of EC research in mobile quantum sensing activities.
Contact and further details: http://www.isense-gravimeter.com/
![Page 7: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/7.jpg)
7
2. Project objectives for the period
The below overview lists all the task-related objectives, which were due to be started/completed
during the reporting period.
WP1 – Integrated laser system:
Task 1.1 – Transfer telecom technology integrated optics to 780nm operation (months 7-16).
Fabrication of passive test structures to determine dependencies of loss processes, mode
control and polarisation properties of optical GaAs waveguide structures working at 780nm.
In particular dependencies on material parameters and geometry shall be tested, including
layer thickness, Al concentration and waveguide shape.
Task 1.2 – Micro-integrated extended cavity diode lasers for Rb spectroscopy (months 1-20).
The laser diode chip, the optical grating, collimation micro-optics, and miniature optical
isolators will be integrated on a microbench with a volume of 5 x 2.5 x 1 cm3. The lasers
will provide 50 mW output power with a short-term (10 μs) linewidth of 100 kHz. The
lasers will be tuneable by +/- 50 GHz.
Task 1.3 – Evaluation of waveguide to fibre coupling methods (months 1-16).
The aim will be to achieve a coupling efficiency above 70% from waveguide to fibre with
linear polarisation to be maintained to better than 1:100.
WP2 – Science chamber and scheme:
Task 2.1 – Realization of gravity measurements with three different schemes (months 1-18)
We are aiming at a sensitivity better than 10 μgal/Hz1/2
while keeping the atoms in a probe
volume below 1 cm3 with the following schemes:
Wannier Stark interferometer. The interferometer will be realized with atoms trapped in
a far detuned optical lattice, and manipulated thanks to two-photon Raman transitions.
The beam splitting process will be optimized for large wavepacket separations and
increased interferometer sensitivity.
Realization of Bloch oscillations in optical lattices. Sources of decoherence will be
investigated. Comparison with Bloch oscillations with Sr atoms
Realization of the Atomic Leviation scheme. This scheme will impart to free falling
atoms repeated momentum transfers with two photon transitions, allowing them to
levitate. Comparison of “classical” and “quantum” levitation schemes.
Task 2.2 – Layout of low power chip design and support structure (months 1-12)
Layout of a chip design with power consumption below 1W and no external coil
requirement. This design will focus on providing a number of microwire based magnetic
traps, optimized for fast and efficient loading and cooling of more than 107 Rb atoms and
transfer of more than 104 atoms to optical lattices used in the sensor. Design of a chip
support structure fitting in a volume of 100 cm3 and weighing below 500g when fitted with
the chip. This structure will encompass a replaceable header structure that will be directly
attached to the atom chip, an integrated larger (millimetre sized) copper trapping structure
and broad current sheets for generating homogeneous fields for both chip based and support
structure based magnetic traps.
Task 2.3 – Investigation of glass-glass and glass-metal bonding for vacuum chamber (months 1-12)
The main purpose of this task is to investigate glass/metal and glass/titanium bonding with
the aim to achieve window seals with a leak rate below 10-12
mbar l/s.
– Investigation of the mechanical interface between vacuum chamber and optical/magnetic
components (months 1-24)
![Page 8: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/8.jpg)
8
Aim is a total volume of the science chamber including all interfaces below 10l with a
weight below 5kg.
Task 2.4 – Demonstration of alkali-earth apparatus (months 1-12)
This task will be focused on the demonstration of experimental apparatus for cooling and
trapping of more than 105 Sr and Yb atoms based on current technology developed for
compact and transportable setups.
WP3 – Integrated Sensor
Task 3.1 – Determination of types of modules and their specification and quantities (months 1-4)
– Develop basic electronic modules which are computer controlled (months 1-18)
This involves modules like Diode-laser current source, temperature controllers, RF
frequency generators, demodulation for frequency offset locking, demodulation for
spectroscopy locking.
– Develop FPGA based laser frequency control methods (months 1-24)
– Develop a compact frequency reference chain operating at 6.8 GHz (months 1-27)
Task 3.2 – Sensor design workshop (month 4)
– Design specifications for vacuum chamber and chip design (month 1-24)
WP4 – Dissemination
Task 4.1 – Public web page (months 1-48)
– Internal web page (months 1-48)
– Communications tools (logo, business cards, power point template) (months 1-3)
Task 4.3 – Outreach campaigns (months 1-48)
Task 4.4 – Contribution to portfolio and concertation activities at FET-Open level (months 1-48)
Task 4.7 – Use and dissemination of foreground (months 1-48)
WP5 – Management
Task 5.1 – Consortium Start-up (months 1-3)
Task 5.2 – Interface workshop (month 4)
Task 5.3 – Yearly review meetings
Task 5.4 – Project management (months 1-48)
Task 5.5 – Communication management (months 1-48)
![Page 9: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/9.jpg)
9
3. Work progress and achievements during the period
WP 1- Integrated Laser System
Work package leader: UHH
Introduction
In work package 1 we aim for the realization of a highly miniaturized but nevertheless flexible laser
system for cooling neutral atoms. The laser system can be described by three main components.
That is the laser itself, the splitting module and the connection to the rest of the world, i.e. the
coupling of the light into optical fibres which will work as connection between laser system and
vacuum system.
To achieve the realization of all this, the work package has been divided into five tasks, which are
listed in the table below. Task-Nr. Task Task Leader
1.1 Integrated optics modules optimised for 780nm UNOTT
1.2 Micro-integrated diode lasers for cold atom applications FBH
1.3 Integration of the entire optical system for the iSense sensor UHH
1.4 Evaluation of GaN integrated optical technologies Bham
1.5 Review of the technologies to realize visible wavelength diode laser based
laser systems, including micro-integrated frequency doubled laser systems
FBH
Task 1.4 and 1.5 are not starting prior to month 12.
Summary of progress towards objectives
DFB Diodes have been tested and show single mode operation or at most experience a single mode
hop over the full current tuning range of 400mA. This diode can be operated at high output powers
at the wavelength of the Rubidium D2-line, and have a FWHM linewidth of slightly over 1 MHz
depending on the injected current, and an intrinsic linewidth of 25 kHz.
Power amplifiers have been processed and characterization will start in the mid of July.
The development phase for the master lasers based on an extended cavity design is finished and first
prototyped are expected in the mid of August.
Miniaturized Rubidium gas cells have been tested in Hamburg and delivered to the FBH for
integration into the spectroscopy module. The development of the concept for the spectroscopy
module for the frequency stabilization of the master laser has been started.
On the fibre coupling side there have been two concepts designed and one of them has already been
tested and could reach a maximal fibre coupling efficiency of up to 80%. After these tests a second
version has been designed, is currently in the workshop and should be ready for testing in the next
weeks.
There have also been tests on fibre coupling on a Zerodur base plate and we could reach a
temperature stability of the fibre coupling of less than 1% per °C in the range of 20-35°C.
Furthermore first studies on GaAs/AlGaAs waveguides are carried out and the engineering
specifications of an integrated optics device are determined.
![Page 10: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/10.jpg)
10
The development of the laser system and the fibre coupling is well on time but due to some delays
in the processing of the amendments to Annex-I in discussion with the EC and shift of resources for
the University of Nottingham, there is a delay of approximately 2 months in the start of the
investigation of waveguide structures. However it is anticipated that this delay can be compensated
by focussing of resources, such that the first waveguide-related task can be delivered by month 16
as foreseen in Annex-I.
Details for each task
Task 1.1 Integrated Optics Modules optimized for 780nm
First design studies of the GaAs/AlGaAs waveguide are carried out and the engineering
specifications of the integrated optics device are determined.
We have also undertaken preliminary computer modelling (i.e. we have set up and successfully run
calculations for the geometries required) of the rib wave guides and Mach-Zehnder interferometers
needed for on-chip realisation of the laser optics.
Task 1.2 Micro-integrated diode lasers for cold atom applications
(i) DFB-RW lasers DFB-RW laser were fabricated and tested at
the FBH. To characterize these laser diodes the
optical output power, the spectrum and the
linewidth have been recorded.
Typical characteristics of DFB-Diodes from
this charge are illustrated on right side. The
measurement of the optical spectrum indicated
single mode operation over a current tuning
range of 350mA, and it is possible to be
operated at the Rb D2-line at a high output
power of more than 200mW.
Measurements of the linewidth of the laser
diodes revealed a FWHM linewidth of 1.2
MHz and an intrinsic linewidth of 25 kHz.
(ii) Power Amplifiers
Power Amplifiers have been processed and are
currently being AR-coated. A characterization
of the PA chips will start in the mid of July.
(iii) Extended cavity diode lasers
A design of an extended cavity diode laser is illustrated below. The design includes the laser chip,
optics for collimating the output beam, a volume holographic Bragg grating (VHBG) for the
feedback, optical isolators, micro peltier elements for temperature control, temperature sensors and
the electronic interface, all on a footprint of 25 x 80mm².
![Page 11: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/11.jpg)
11
The tuning of the wavelength is done by tuning the temperature of the VHBG.
The electronic interface supports two-section RW laser chips with a gain section and a modulation
section. The modulation section allow for a low frequency modulation of up the 10MHz for
frequency modulation spectroscopy and also a direct µ-wave modulation of the laser diode for
providing multiple frequencies (e.g. for Raman interferometry).
The development phase of these ECDLs is completed and the components are currently being
manufactured by an external supplier. Delivery of a first prototype is expected in August 2011.
(iv) Rubidium spectroscopy module
For frequency stabilization of the master laser a spectroscopy module is being designed and the
concept is depicted above.
It consists of a miniaturized Rubidium gas cell from the UHH, an electro optical modulator, a
retarder, photodiodes, optical components for beam guidance and an electronic interface which
includes EOM drivers, electronics for photodiodes and a demodulation circuit. So it will be possible
to generate the error signal for frequency stabilization directly on this module. Modulation transfer
spectroscopy has been chosen as preferred method of stabilization.
(v) Miniaturized spectroscopy cells
Miniaturized spectroscopy cells with a length of 20 mm and a diameter of 5 mm have been tested.
These cells are designated to be used in the Rubidium spectroscopy module.
![Page 12: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/12.jpg)
12
Tests showed that even with these short cells an absorption signal of the D2-line of
85Rb can be
obtained. Depicted above are the obtained error signals with a normal sized spectroscopy cell
(length: 100mm, diameter: 25mm) on the left side, and a miniaturized one on the right side.
Additionally it was possible to stabilize a laser on an atomic transition by using one of the
miniaturized spectroscopy cells.
Task 1.3 Integration of the entire optical system for the iSense sensor
(i) Fibre coupling methods
A literature research on different methods for waveguide-to-fibre coupling has been performed and
the equipment for the micro-adjustment has been set up. Waveguide-to-fibre-coupling has not yet
been explored practically as the first passive waveguide structures are only expected at the
beginning of year 2 of the project.
Based on the knowledge on working with Zerodur obtained within the QUANTUS project a first
approach on realizing stable fibre couplers were made by designing, fabricating and testing a free
space fibre coupler made of Zerodur.
These tests showed a high maximal fibre coupling efficiency of up to 80% for the coupling of light
coming out of one fibre into another. But long term tests indicated a stability lower than expected.
So another concept has been designed, one that is more relying on screws to keep the fibre in
position while gluing.
Both designs are depicted in the pictures below, the first approach on the left and the latter one on
the right.
On other coupling methods such as butt-coupling and/or lensed fibres there has been some literature
research going on, and work on these other methods will be starting as soon as a waveguide is
available.
![Page 13: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/13.jpg)
13
(ii) Stability of fibre coupling on a low expansion base plate
To prepare the integration of the whole system on
a low expansion base first tests have been made
using a Zerodur based laser module. This module
makes use of a Zerodur base plate in combination
with a commercially available fibre coupler from
“Schäfter+Kirchhoff”. To test the temperature
stability of this setup the base plate was put on a
hot plate and the change of fibre coupling
efficiency was observed. And as depicted on the
right, the coupling efficiency changed by less than
10% while varying the temperature from 20°C to
35°C and back.
Task 1.4 Alternative free-space optical delivery system
We have started the following work on a fibre-optics based hybrid integrated splitter solution:
- Market research on fibre optics components suitable for iSense. Identified companies for
integrated fibre splitters, fibre switches and fibre coupled acousto-optic modulators
- Purchased sample devices for all of the above and started testing them for performance
- Started design work for hybrid fibre splitter solution
Clearly significant results
- The production of narrow-linewidth DFB-RW laser diodes is unique and ensures that iSense
technology is at the forefront of technical feasibility.
- The miniaturized spectroscopy cells are a crucial step needed for the micro-integrated laser
systems.
- The Zerodur-based baseplate technology is unique for the realisation of active optical
systems.
![Page 14: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/14.jpg)
14
Deviations from Annex I and their impact on other tasks, available resources and planning
NA
Reasons for failing to achieve critical objectives and/or not being on schedule and explain the
impact on other tasks as well as on available resources
Due to some delays in the processing of the amendments to Annex-I in discussion with the EC and
shift of resources for the University of Nottingham, there is a delay of approximately 2 months in
the start of the investigation of waveguide structures. However it is anticipated that this delay can
be compensated by focussing of resources, such that the first waveguide-related task can be
delivered by month 16 as foreseen in Annex-I. We do not expect any significant impact on other
tasks or the project as a whole.
Statement on the use of resources, highlighting and explaining deviations between actual and
planned person-months per work package and per beneficiary in Annex 1 Except for some delay as explained above in hiring a researcher to work on waveguide processing
the use of resources is in general agreement with Annex-I.
![Page 15: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/15.jpg)
15
WP 2- Science Chamber and Scheme
Work package leader: CNRS-SYRTE
Introduction
The overall objective of this work package is to establish and optimize the technological steps
necessary to realize a guided atomic quantum sensor, in which atoms are either trapped in optical
lattices or levitate thanks to sequences of laser pulses. The feasibility of this technology for gravity
sensing will be demonstrated, a small scale (< 1liter) vacuum chamber and an adapted low power
atom chip developed. The work will be carried out keeping two main constraints into account: the
physical principle has to operate in a reduced volume, the chosen species for the technology
demonstrator is Rb. In addition we will lay the foundations to broaden the iSense platform to
include further species, which are in particular interesting as optical time and frequency standards
or for quantum information applications. Particular attention will be devoted on the evaluation of
performances of interferometric schemes applied on alkali-earth species in comparison with alkali
atoms.
The work package is organised by subdivision in four tasks, which are listed in the table below. Task-Nr. Task Task Leader
2.1 Interferometer scheme CNRS-SYRTE
2.2 Low power atom chip UNOTT
2.3 Small scale vacuum chamber CNRS-IOGS
2.4 Alternative atoms and schemes for future sensors UNIFI
Summary of progress towards objectives
Demonstration of a Ramsey type Wannier Stark interferometer, with preliminary sensitivity of
6 10-5
g at 1s
- Comparison between lattice amplitude and phase modulation schemes, coherence time
larger than 28s
- Study of dephasing effects in levitation scheme
- Definitive results of glass-glass connections based on silicate bounding : the resulting
assembly does not comply with the required mechanical specifications
- Study of alternative design based on gluing a glass cell on a metal flange
- Optimized production of 84Sr BEC with up to 4x106 atoms at IQOQI-OEAW
- Detection and manipulation of nuclear spin states of 87Sr at IQOQI-OEAW
- Operation of a Sr 3D-MOT on the 1S0-
1P1 transition at 461 nm at UNIFI
- Yb 2D-MOT system setup completed at UHH
The preliminary results indicate that the target sensitivity of 10 μgal/Hz1/2
is out of reach for the
present implementation of the bouncing gravimeter, both considering the classical and the quantum
one. The reported sensitivity in the proof-of-concept experiment is δg/g ~10-4
/Hz-1/2
, or four orders
of magnitude from the targeted one.
With some improvements a scale up of 1 or 2 orders of magnitude can be foreseen.
An alternative way to realize the mirrors has been proposed in Phys. Rev. A 80, 031602 (2009): it
uses Raman transitions to implement a multiple paths levitated interferometer.
The results of the tests conducted on glass/glass and glass/metal are absolutely not satisfactory.
![Page 16: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/16.jpg)
16
As for the glass to metal interface, feasible and already experimented alternative solutions are under
consideration. This does not have important impact on other tasks, since the solutions envisaged
comply with the sensor requirements (compactness, weight, robustness, optical access).
Details for each task;
Task 2.1 Interferometer scheme
(i) Wannier-Stark interferometer scheme
So far the investigations at CNRS-SYRTE have delivered the following results:
- Demonstration of a Ramsey type WS interferometer, with up to 50% contrast for T=400 ms
- Best relative sensitivity on the measurement of the Bloch frequency : 6 10-5
at 1 s
- Investigation of noise sources
- Frequency locking of the lattice laser
- Modification of the Raman laser system
- Calculation of the energy levels and the metastable states of an atom trapped in a vertical
optical standing wave (Wannier-Stark states)
- Model of the modification of these energy levels and states in presence of a surface taking
into account the Casimir-Polder effect in proximity of it
- Investigation of the shifts produced by a hypothetical Yukawa-type gravitational potential
and discussion on their experimental observability
(ii) Modulation scheme
So far the investigations at UNIFI have delivered the following results:
- Experimental comparison between phase modulation and amplitude modulation to induce
resonant tunneling of Sr atoms in an optical lattice.
- Detection of resonance tunneling spectra with Fourier limited resolution up to the fifth
harmonic
- Demonstration of reversible coherent transport with amplitude-modulation induced
tunneling
- ~ 28 s lower limit to coherence time, limited by background gas collisions
- application of resonant phase modulation of lattice for narrowing the atomic momentum
distribution
- Investigation of main sources of decoherence
(iii) Levitation scheme
So far the investigations at CNRS-IOGS have delivered the following results:
- Analysis of the multiple order diffraction paths presented in EPL 89 10002 (2010),
considering the contributes of the sets of trajectories with equal phase contribution; this
allows to interpret the switch between the classical and quantum regime, and for the latter to
quantitatively describe the narrowing and deformation effect of the fringes as a function to
the number of bounces.
- Study of the dephasing effects, related to the power amplitude fluctuations of the Bragg
mirrors, as well as to the presence of interfering paths with phase contributions
incommensurable to that given by the single high-order diffraction contribute. The last
effect poses a limits on the maximum number of bounces, and thus to the achievable
precision.
![Page 17: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/17.jpg)
17
CNRS-IOGS has been able to deduce the following preliminary conclusions:
- The preliminary results indicate that the target sensitivity of 10 μgal/Hz1/2
is out of reach for
the present implementation of the bouncing gravimeter, both considering the classical and
the quantum one. The reported sensitivity in the proof-of-concept experiment is δg/g ~10-
4/Hz
-1/2, or four orders of magnitude from the targeted one.
- Several improvements can be implemented: a power stabilization for the diffraction beams;
pulse shaping to optimize the diffraction amplitude of the interfering paths; adopt a colder
atomic source to increase the number of bounces. With these improvements a scale up of 1
or 2 orders of magnitude can be foreseen.
- A further improvement of the sensitivity will require to adopt a lighter atom for the
levitation: this will increase the period associated to the classic trajectory (which narrows
the interfringe by the mass ratio); reduce the effect of the initial energy distribution, since
the recoil energy associated to the reflection is bigger (this means a reduction of the atom
loss during the sequence). Changing the atomic species is not viable on the present setup.
- An alternative way to realize the mirrors has been proposed in Phys. Rev. A 80, 031602
(2009): it uses Raman transitions to implement a multiple paths levitated interferometer.
Task 2.2 Low power atom chip
We have designed, constructed and tested an integrated platform for laser cooling of Rb-87 near a
reflecting atom chip. We were able to produce all magnetic fields needed with Cu wire structures
that are integrated into the chip mount and have corss sections of a few mm^2. Their overall size is
a few cm^3, we dissipate less than 5W in the working model, but at the moment at currents in
excess of 100A. After consultation with other iSense members a second generation design was
started that is aimed at <20A and similarly low power consumption. With the working model, we
will attempt magnetic trapping and evaporative cooling. The new design for a second generation
low power atom chip under structure is finished including a systematic consideration of the design
parameters and calculations of the produced trapping field.
The design for the second generation under structure consists of a single current carrying sheet of
copper, with a periodically varying width as shown in the figure below.
Figure. Two complete layers of the second generation under structure before winding. The sheet
can be replicated as many times as desired to produce more layers.
By considering the effects of altering the different parameters the field was decided to be optimal
when wS=44mm, wU=5mm, hB=10mm, nL=20 and I=20A. These values were chosen to produce a
field minimum which was as far away from the surface of the chip as possible whilst maintaining
steep enough trapping gradients. The U bar width was first set to be as wide as possible whilst
remaining in the region where the effects of its width and height first become apparent. This
allowed for the benefits of a using a wide sheet to start to become apparent in the shape of the field
whilst the strength of a field produced by in infinitely small wire remained. The width of the
WU Ws
![Page 18: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/18.jpg)
18
current sheet was then manipulated until 4.5<rT<6.5mm and then further adjusted until the field
gradients had a magnitude exceeding 10G/cm in each direction. The separation between the sheets
was then finely tuned to give the best highest gradient strength to rT ratio. The figure below shows
the quadrupole field that would be produced in the xy plane using these parameters when the side
wire current is set to zero.
Figure. The field produced in the xy plane when wS=44mm, wU=5mm, hB=10mm, nL=20 and
I=20A. The low and high gold blocks show the size and position of the current sheet and the U bar
respectively and the grey area represents the insulting block. It should be noted that the width of
both the current sheet and the block extend further than the edges of the figure. The black area
represents the space between the under structure and the chip surface which would be along the
surface of the black area. The green circle shows the position of the minimum of the field and the
red lines show the axis of the quadrupole. The white lines run at 45o to the surface of the chip and
show the laser beam paths, the green +’s show the distance along these axis that the acceptable
field distance extends. The colour bar scale is in Tesla.
The field has a minimum 5mm above the chip surface at y = 19mm and x = 0. The trapping
gradients in the x’ and y’ directions have a magnitude of 11.39 G/cm and the acceptable field
distance is 7.07mm. This quadrupole has large enough gradients and a large enough acceptable field
distance to meet the minimum criteria desired for the second generation under structure. The z
direction confinement is created with a side wire, which was also optimised.
The second generation chip is now under production and the design process for an optimized under
structure was started.
x position (m)
y po
sition
(m
)
![Page 19: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/19.jpg)
19
Task 2.3 Small scale vacuum chamber
Tests have been conducted on the feasibility of vacuum systems based on glass/glass connections
using silicate bonding. The definitive results is that the resulting assembly does not comply with the
required mechanical specifications, especially concerning the resistance to bending stress during the
screwing operation of the glass part to the metal one. The vacuum cells broke even using very soft
gaskets (annealed ductile copper or indium), and before we could reach the UHV regime (better
pressure 10-5
mbar). We cannot asses then the limit vacuum pressures for the silicate bonding.
We started considering alternative designs, where a glass cell is glued on a metal flange. Two
alternative approaches are studied: one consists in realizing a hole in the flange where to fit the cell
(required machining precision 1/10 to 1/100 mm), and filling the gap with UHV-compatible glue
(e.g. UHVGLUE-H77 from Caburn-MDC has been tested below 10-10
mbar). The second approach
consists in using a commercial metal to glass adaptor (e.g. FGA-025-2 from Caburn-MDC) and a
high quality glass cell. The last solution has been implemented with success in the group of P.
Treutlein, where one face of the cell even consists of the glued atom chip.
The results of the tests conducted on glass/glass and glass/metal are absolutely not satisfactory.
Feasible and already experimented alternative solutions are under consideration. This does not have
important impact on other tasks, since the solutions envisaged comply with the sensor requirements
(compactness, weight, robustness, optical access).
Task 2.4 Alternative atoms and schemes for future sensors
UNIFI:
Optimization of SHG for the 461 nm laser source (1S0-
1P1).
Optimization of transverse cooling of the atomic beam.
Laser system at 461 nm locked to the 1S0-
1P1 transition via fluorescence spectroscopy in the
transverse cooling region.
Operation of Zeeman slower.
Operation of 3D-MOT on the 1S0-
1P1 transition at 461 nm.
UHH:
Spectroscopy beam apparatus on-line.
Laser system at 399 nm locked to the 1S0-
1P1 transition via fluorescence spectroscopy at the
beam apparatus
Photomultiplier for detection of fluorescence on the 1S0-
1P1 transition installed.
2D-MOT system setup completed.
Active cooling of the 2D-MOT coils allows for field gradients exceeding 50 G/cm.
Vapour detected in 2D-MOT cell via fluorescence confirmed functionality of dispenser sources
in the 2D-MOT configuration.
IQOQI-OEAW:
Optimized production of 84
Sr BEC. We have produce 84
Sr BECs with 4x106 atoms, 25 times the
atom number of our first Sr BECs. Essential ingredients for this improvement were: a pancake
shaped large volume dipole trap, increased stability and accuracy of the intercombination line laser,
and an improved dipole trap loading scheme. The production of 84
Sr BECs with large atom number
provides a solid foundation for future research with this isotope and also improves the starting point
for the production of isotopic or elemental mixtures with 84
Sr.
![Page 20: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/20.jpg)
20
Detection and manipulation of nuclear spin states of 87
Sr. We have implemented two
complementary methods to characterize the nuclear spin state mixture of an ultracold cloud of 87
Sr:
optical Stern-Gerlach state separation and state-selective absorption imaging. These methods have
been used to prepare a variety of spin-state mixtures by optical pumping and to measure an upper
bound of the 87
Sr spin relaxation rate. Spin state detection and manipulation is essential for any
application of 87
Sr.
Mott insulator of 84
Sr. We have implemented an optical lattice and observed the superfluid to
Mott-insulator transition with 84
Sr. The Mott insulator of 84
Sr will be the starting point for
numerous studies ranging from the characterization of Sr properties, the implementation of quantum
simulations with Sr, to the production of RbSr ground-state molecules.
Our increased skillset in handling Sr will increase the design space of future Sr interferometers and
help us to characterize properties of Sr relevant for iSense.
Clearly significant results
- All interferometer schemes have been demonstrated and first evaluations have been
performed. The indication that the Levitation scheme is likely to miss the iSense sensitivity
targets is an important input for the further planning of activities towards scheme selection.
- A low-power “stand-alone” atom chip has been demonstrated, underlining the feasibility of
the iSense approach and being a key step towards low power consumption of the entire
system.
- Manipulation and precision measurement methods for Sr have been developed to a high
standard.
Deviations from Annex I and their impact on other tasks, available resources and planning
NA
Reasons for failing to achieve critical objectives and/or not being on schedule and explain the
impact on other tasks as well as on available resources There is a slight delay of roughly 2 months in the work towards demonstrating laser cooling in the
Yb earth alkali apparatus. By the time of writing this report, the experiment was well on the way of
catching up and we do not foresee any implications for other tasks.
Statement on the use of resources, highlighting and explaining deviations between actual and
planned person-months per work package and per beneficiary in Annex 1 The use of resources is in general agreement with Annex-I.
![Page 21: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/21.jpg)
21
WP 3- Integrated Sensor
Work package leader: Bham
Introduction
The overall objective is to demonstrate the iSense technology platform in a proof-of-principle
instrument and to include all electronic modules needed to operate and control the lasers, mag-netic
field coils, and other components. The particular instrument chosen is an optical lattice based cold
atom gravity sensor, which will bring together all aspects of the technology platform and all
expertise generated.
The work package is organised in two tasks, which are listed in the table below. Task-Nr. Task Task Leader
3.1 Electronics LUH
3.2 Integrated gravity sensor Bham
Summary of progress towards objectives and details for each task;
Task 3.1 Electronics
- The development of an electronic module for switching components like ventilators is
finished. This allows the iSense gravimeter instrument to have the ventilation on only during
non-critical times.
- The development of a dual high current driver for tapered amplifiers is finished. This
module can deliver up to 3 A of current.
- The development of the dual temperature controller is finished. This module can stabilize up
to 2 lasers. It connects to 4 NTC temperature sensors (2 stabilized, 2 auxiliary) and 2 peltier
elements.
- The development of a NTC & photodiode input module is finished. This module is for
housekeeping and diagnostic purposes. It has 25 channels and a resolution of 16 bits.
Task 3.2 Integrated gravity sensor
We initialized a full system design including laser system, optical system, electronics, science
chamber, atom chip and mounting hardware, which will be an evolving work document taking
developments and new knowledge into account until the final design is to be fixed by month 24 of
the project. The current design status is:
![Page 22: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/22.jpg)
22
Clearly significant results
Overall the sensor design is progressing well. The most significant result so far is that there have
not been any major obstacles occurring.
Deviations from Annex I and their impact on other tasks, available resources and planning
NA
Reasons for failing to achieve critical objectives and/or not being on schedule and explain the
impact on other tasks as well as on available resources NA
Statement on the use of resources, highlighting and explaining deviations between actual and
planned person-months per work package and per beneficiary in Annex 1 Due to a delay in hiring a PhD student at Bham, the man months from this side are slightly lower
than planned, however the main activities on the integrated sensor in WP3 are still to come with
first parts being delivered from other partners in the next year. This is in part compensated by a
postdoc hired with Bham resources, who has spent 3 months on the project so far. A student has
been hired 1.July 2011, such that the cumulative man-month over the project will be in line with the
planning.
Otherwise the resources are in general agreement with Annex-I.
![Page 23: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/23.jpg)
23
WP 4 - Dissemination
Work package leader: LUH
Introduction
The objectives of this workpackage are:
• Dissemination of the project results to partners outside the consortium
• To make the scientific, professional and general public aware of the iSense project and its plans,
results and potential benefits that can be derived from S&T achievements
• To attract additional RTD funds in order to make the iSense consortium operational and
prosperous after the end of the project.
The work package is organised in seven tasks, which are listed in the table below. Task-Nr. Task Task Leader
4.1 Communication tools LUH
4.2 iSense film LUH
4.3 Outreach campaigns and education LUH
4.4 Contribution to portfolio and concertation activities at FET-Open level Bham
4.5 Marketing LUH
4.6 Sensor deployment Bham
4.7 Use and dissemination of foreground Bham
Summary of progress towards objectives and details for each task;
Task 4.1 Communication tools
completed, maintenance & updates remaining
Task 4.2 iSense film
Pending (planned for month 24-36)
Task 4.3 Outreach campaigns and education
Workshop is in Preparation, timeslot determined (9.-12.06.2012) desired Speakers identified,
Invitations pending
Task 4.4 Contribution to portfolio and concertation activities at FET-Open level
A webpage was created as a platform to disseminate project results to the general public.
The iSense project was represented by K. Bongs and P. Bouyer using a Poster and personal
discussion at the FET11 conference 4th
-6th
May 2011 in Budapest. The discussions have led to 7
new cross-disciplinary contacts, with the intention to initiate future international collaborations
related to the iSense project. These contacts have all been followed up by e-mail. One contact with
the Glasgow Centre for Nanoscience led to a visit including further discussion and a seminar by
Prof. Charles Ironside from the School of Engineering at the University of Glasgow on the 29th
July
2011.
In addition there has been a good number of publications and conference presentations related to
iSense, as listed in section 5.
Task 4.5 Marketing
Pending (planned for months 24-48)
![Page 24: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/24.jpg)
24
Task 4.6 Sensor deployment
Pending (planned for months 42-48)
Task 4.7 Use and dissemination of foreground
Pending
Clearly significant results
See publications in section 5
Deviations from Annex I and their impact on other tasks, available resources and planning
NA
Reasons for failing to achieve critical objectives and/or not being on schedule and explain the
impact on other tasks as well as on available resources NA
Statement on the use of resources, highlighting and explaining deviations between actual and
planned person-months per work package and per beneficiary in Annex 1 The resources are in general agreement with Annex-I
![Page 25: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/25.jpg)
25
4. Deliverables and milestones tables
Deliverables (excluding the periodic and final reports)
TABLE 1. DELIVERABLES
Del. no.
Deliverable name WP no. Lead beneficiary
Nature
Dissemination level
Delivery date from Annex I (proj month)
Delivered Yes/No
Actual / Forecast delivery date
Comments
4.1 Project Website 4 LUH others public 6 yes 6 Please see http://www.isense-
gravimeter.com/
![Page 26: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/26.jpg)
26
Milestones
TABLE 2. MILESTONES
Milestone no.
Milestone name Work package no Lead beneficiary
Delivery date from Annex I
Achieved Yes/No
Actual / Forecast achievement date
Comments
MS6 Web page
online
4 6 (LUH) 6 yes 6 http://www.isense-gravimeter.com/
![Page 27: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/27.jpg)
27
5. Project management
Management tasks and achievements;
Management tools
Management of the consortium involves several mechanisms. Each participant is required to
provide the respective workpackage leader with a quarterly status update on the tasks he has
carried out. The quarterly status updates are composed into quarterly status update reports for
each workpackage prodiced by the respective workpackage leader. They summarize the
preceding three months’ of research and in particular highlight if the workpackage is on course
to deliver the deliverables and milestones as prescribed in the proposal. If not on course they
discuss the reasons and what remedies a sought to improve the situation and what potential
knock-on effects there will be on other workpackages.
The project coordinator holds meetings with individual workpackage leaders as required to
monitor progress and problems, and apply corrective actions where necessary. They are also
utilised by the coordinator to identify points where workpackages meet and there are
consequent impacts on integration. The level of detail in individual meetings is much higher
than achievable in an hour long meeting of the STEM comittee. In addition some
workpackages involving several sites have individual meetings as required to keep the
workflow going smoothly (e.g. WP1). Overall, there have been ~30 such meetings in the first
year of the project.
Most of the meetings are using electronic communication tools such as Skype, Webex and
email extensively. Important documents from meetings are posted regularly on the project wiki.
Research coordination visits between partners
Date (from and to) Visiting partner Visited Partner Number travelling
22/10/2010 UNOTT FBH 1
16-17/11/2010 LUH, UHH FBH 2
19/11/2010 Bham CNRS 1
22/11/2010 UNOTT FBH 1
24-26/02/2011 Bham,UHH UNIFI 2
03/03/2011 LUH FBH 1
22-24/03/2011 Bham, FBH,
LUH
UHH 4
15/04/2011 Bham CNRS 1
04/05/2011 LUH FBH 1
06/06/2011 LUH FBH 1
08-09/06/2011 LUH FBH 1
27-28/06/2011 Bham, FBH,
LUH
UHH 6
In addition we had numerous visits with discussions relevant to iSense between UNott and
Bham within the Midlands Ultracold Atom Research Centre, between UHH, LUH and FBH
within the QUANTUS collaboration as well as between the different subgroups included
under CNRS (in particular SYRTE and IOGS).
![Page 28: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/28.jpg)
28
Co-operation with other projects/programmes
An essential component if the iSense collaboration is to build on the existing expertise and
foster synergies between fragmented related programmes across Europe, in particular the
FINAQS, QUANTUS, SAI, ICE and SOC projects. We co-operate with these projects via
the direct involvement of iSense partners. This ensures that iSense technology developments
are gauged by the up-to-date needs of the community and will find rapid and sustained use.
Problems which have occurred and how they were solved or envisaged solutions; At the beginning of the project partner QinetiQ has performed an internal restructuring,
which lead to closing down their Emerging Technology group which was central to their
participitation in iSense. As they did not start their assigned tasks and removed all capability
to do so the project steering committee had to declare them in breach of the grant agreement
and requested their removal from the project team by the EC. Their participitation was
effectively terminated by month 6 of the project. This process lead to a redistribution of
tasks and adaptation of Annex-I of the project, to the version dated from 4. March 2011. The
consortium has performed a careful evaluation of the internal and external potential to take
over the tasks of partner QinetiQ including a critical review of the current state-of-the-art of
integrated optics technologies. The results were that although many interesting integrated
optics technologies are currently under development, none of them can yet provide the
power handling and amplitude modulation capabilities required by iSense. Together with
experts from QinetiQ, the University of Nottingham was identified as having the
manufacturing and design capabilities to take over the tasks of QinetiQ, although with a
slight shift in the workplan timing caused by the delayed start. In order to maintain the time
plan for all other work packages and to mitigate development risks it was decided to pursue
an additional connector-compatible hybrid optical-fibre/acousto-optical modulator splitter
solution at the coordinating institution. This solution will allow to start the work on laser
system and sensor integration while the fully integrated GaAs splitter is still under
development and to keep the overall project synchronized. The respective resources were
freed by shifting the work on GaN waveguide technology beyond the duration of the project.
Changes in the consortium, if any;
As discussed above partner QinetiQ was removed from the consortium and its tasks taken
over by the University of Nottingham and the University of Birmingham.
List of project meetings, dates and venues;
Date Venue Purpose N attending
13/7/2010 Teleconference Kick-off and debrief 12
6/10-7/10/2010 Birmingham Interface Workshop and STEM meeting 16
30/11/2010 Teleconference STEM-meeting, declaration of QinetiQ
to be in breach of grant agreement and
discuss redistribution of tasks
11
24/5/2011 Teleconference Integration 14
Project planning and status;
The project is meeting its scientific goals, and has hit all the Milestones to date. Following the
review meeting there will be a meeting to plan integration once more late in 2011, a meeting of
the STEM will be needed Feb or March 2012, and a summer school together with the Geodesy
community is planned to take place in Bad Honnef in summer 2012.
![Page 29: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/29.jpg)
29
Impact of possible deviations from the planned milestones and deliverables, if any; The impact of the restructuring and termination of partner QinetiQ as discussed above has
been addressed by redistributing tasks and amending Annex-I to the version dated March 4th
2011, which this report is referring to. The project is in line with this Annex-I.
Any changes to the legal status of any of the beneficiaries, in particular non-profit public
bodies, secondary and higher education establishments, research organisations and
SMEs;
We can confirm that there have been no legal changes to the status of any of the beneficiaries.
Development of the Project website, if applicable;
The project has two web interfaces: an internal wiki and a globally accessible website. The
wiki is being used extensively to support management activities. Project meeting minutes,
documents on integration, slides from presentations and many other documents are stored on
the wiki. The global website summarizes the project, introduces its members and disseminates
new results. It is planned to expand this website during the next year.
Use of foreground and dissemination activities during this period (if applicable).
Publications
1. S. Stellmer, M. K. Tey1, R. Grimm and F. Schreck, Bose-Einstein condensation of 86
Sr,
Phys. Rev. A 82, 041602(R) (2010); http://lanl.arxiv.org/abs/1009.1701
2. R. Messina, S. Pelisson, M.-C. Angonin, and P. Wolf, Atomic states in optical traps
near a planar surface,
Phys. Rev. A 83, 052111 (2011); http://lanl.arxiv.org/abs/1103.1581
3. Q. Beaufils, G. Tackmann, X. Wang, B. Pelle, S. Pélisson, P. Wolf and F. Pereira dos
Santos, Laser controlled tunneling in a vertical optical lattice,
Phys. Rev. Lett. 106, 213002 (2011); http://lanl.arxiv.org/abs/1102.5326
4. S. Stellmer, R. Grimm and F. Schreck, Detection and manipulation of nuclear spin
states in fermionic strontium, http://arxiv.org/abs/1108.2807
Proceedings
1. B. Pelle, G. Tackmann, Q. Beaufils, X. Wang, A. Hilico and F. Pereira dos Santos,
S. Pélisson, R. Messina, M.-C. Angonin and P. Wolf, Forca-G: a trapped atom
interferometer for the measurement of short range forces, Proceedings of the
Rencontres de Moriond and GPhys Colloquium, 2011
2. M. de Angelis, M. C. Angonin, Q. Beaufils, Ch. Becker, A. Bertoldi, K. Bongs, T. Bourdel, P.
Bouyer, V. Boyer, T. Fernholz, M. Fromhold, W. Herr, P. Krüger, Ch. Kürbis, C. Mellor, F.
Pereira Dos Santos, A. Peters, N. Poli, M. Popp, M. Prevedelli, E. M. Rasel, J. Rudolph, F.
Schreck, K. Sengstock, F. Sorrentino, S. Stellmer, G. Tino, T. Valenzuela, T. Wendrich, A.
Wicht, P. Windpassinger, P. Wolf; iSense: a portable ultracold-atom-based gravimeter;
FET11 conference proceedings, Elsevier 2011
Conference/Workshop talks
1. F. Pereira Dos Santos, Q. Beaufils, X. Wang, S. Pélisson, M.-Ch. Angonin, P. Wolf, R.
Messina, A. Lambrecht, Un interféromètre à atomes guidés pour des mesures de forces
à faible distance, PAMO 2010, Orsay, France, 29 June-02 July 2010.
2. G. Tackmann, Q. Beaufils, B. Pelle, X. Wang, S. Pélisson, M.-Ch. Angonin, P. Wolf
and F. Pereira dos Santos, Trapped atomic accelerometer for short range
![Page 30: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/30.jpg)
30
measurements, Young Atom Opticians Conference (YAO) 2011, Hanover (Germany),
11-19 February 2011.
3. G. Tackmann, Q. Beaufils, B. Pelle, X. Wang, S. Pélisson, M.-Ch. Angonin, P. Wolf
and F. Pereira dos Santos, Trapped atomic accelerometer for short range
measurements, Frühjahrstagung der Deutschen Physikalischen Gesellschaft 2011,
Dresden (Germany), 13-18 March 2011.
4. F. Schreck, Double-degenerate Bose-Fermi mixture of strontium, APS March Meeting,
Dallas, TX, USA, March 21-25, 2011.
5. B. Pelle, Q. Beaufils, G. Tackmann, X. Wang, A. Hilico and F. Pereira dos Santos, S.
Pélisson, R. Messina, M.-Ch. Angonin and P. Wolf, Forca-G : A trapped atom
interferometer for the measurement of short range forces, Gravitational Waves and
Experimental Gravity, Rencontres de Moriond and GPhyS Colloquium, La Thuile, 20 -
27 March 2011
6. F. Schreck, Quantum Degenerate Strontium, IFRAF-Fermix Meeting, E.N.S., Paris,
France, April 13-15 2011.
7. P. Bouyer, Heterodyne non-demolition measurements on cold atomic samples, Quantum
Science and Technologies Workshop, Rovereto, Italy, 8-12 May 2011.
8. F. Schreck, Quantum Degenerate Strontium, Fermions from Cold Atoms to Neutron
Stars: Benchmarking the Many-Body Problem, INT, Seattle, USA, 16 - 20 May 2011.
9. T. Vanderbruggen, Nondestructive measurements and all-optical Bose-Einstein
condensation in a high-finesse cavity , ICOLS Student Workshop, Hannover, Germany,
June 2011.
10. F. Schreck, Quantum Degenerate Strontium, Gordon Research Conference an Atomic
Physics, West Dover, VT, USA, , June 26- July 1, 2011.
Conference/Workshop posters
1. B. Pelle, Q. Beaufils, G. Tackmann, X. Wang, S. Pelisson, M.-Ch. Angonin, P. Wolf
and F. Pereira dos Santos, Forca-G : from a trapped atom interferometer to the measure
of Casimir-Polder force and an eventual deviation of Newton's law, Young Atom
Opticians Conference (YAO) 2011, Hanover (Germany), 11-19 February 2011.
2. K. Bongs, T. Valenzuela and Y. Singh, STE-QUEST & Cold atoms in space, UK Space
Agency Microgravity Workshop, Harwell Oxford, UK, 14-15 March 2011.
3. K. Bongs, T. Valenzuela and Y. Singh, STE-QUEST & Cold atoms in space,
Fundamental Physics at Low Energies, Durham, 5th-7th April 2011
4. V. Boyer, T. Valenzuela and K. Bongs for the iSense Consortium, iSense: a portable
ultracold-atom-based gravimeter, FET11 conference, Budapest, Hungary, 4-6 May
2011.
![Page 31: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/31.jpg)
31
6. Explanation of the use of the resources
TABLE 6.1 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 1 FOR THE PERIOD Work Package Item description Amount Explanations
1,2,3,4,5 Personnel costs 10,906 € Salaries of two permanent staff, Dr Vincent Boyer and Prof Kai Bongs working in total 1.7 man months.
Subcontracting 0 €
1,2,3,4,5 Equipment’ 1,153 € Depreciation over 36 months on: Hexapod 6-axis parallel kinematics microrobot with 6D hexapod controller; 1HT101820 HONEYCOMB TABLE TOP 1000; Pneumatic vibration isolation system;
1,2,3,4,5 Consumable 3,586€ Electronic components, catering for project meetings, clamps and lens and accessories for equipment, equipment maintenance,
Travel 1,845€ Travel to collaboration workshop in Florence, Italy, 24-26/2/11 T Valenzuela and travel to FET11 conference in Budapest 3-6/5/11 Prof K Bongs.
Dissemination 0€
TOTAL DIRECT COSTS 17,490€
TABLE 6.2 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 2 (QINETIQ – LEFT THE PROJECT) FOR THE PERIOD
Work Package Item description Amount Explanations
TOTAL DIRECT COSTS 0
![Page 32: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/32.jpg)
32
TABLE 6.3 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 3 (UHH) FOR THE PERIOD
Work Package Item description Amount Explanations
2 Personnel costs 28968 € Salaries of two doctoral students: –Andreas Bick 9092 € at 2.25 person months (Design of 2D- and 3D-MOT coils, optimization of blue lasers system for Yb MOT operation) –Sören-Erik Dörscher 19876 € at 4.5 person months (Design and setup of green laser system for production of ultracold Yb mixtures; Design of optical traps for Yb mixtures)
2 Equipment 150 € –Arbitrary Waveform Generator 50MHz RS23, linear depreciation of 5 years beginning Feb. 2011, purchase price 1152 €, Modulation of a diode laser’s current to generate sidebands for FM spectroscopy –954P fixed ratio coupler, 50/50 @ 780nm, linear depreciation of 5 years beginning Apr. 2011, purchase price 1088 €, Monitoring of fiber coupling efficiencies at two outputs
1 Consumables 360 € Rubidium Vapor Cell 5x10mm
1,2 Travel 410 € Attendance for one person, Hannes Duncker, at project meeting in Birmingham 06.10.-7.10.2010 . Breakdown of costs: flight 321 € / hotel 68 € / subsistence 21 €
TOTAL DIRECT COSTS 29.888 €
TABLE 6.4 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 4 (CNRS) FOR THE PERIOD
Work Package Item description Amount Explanations
2,3,4 Personnel costs 130.381,05 € F. Pereira dos Santos, Cost 26451.64 €, Res., 3.88 M P. Wolf, Cost 28 445.91 €, Researcher, 3.48 Months P. Bouyer, Cost 25 766.00 €, Researcher, 1.90 Months T. Bourdel, Cost 20 204.80 €, Researcher, 3.86 Months A. Villing, Cost 29 512.70 €, Engineer, 3.33 Months
2 Equipment 11.540,00 € Depreciation of a VERDI Laser, Total cost 57 700,00€, Depreciation over 5 years
2,4 Travel 1.329,70 € First iSense Meeting, in Birmingham (UK), 6-7 October 2010 Flights 411.78 €, subsistence and accommodation 280.1 € Persons attending : Quentin Beaufils, Franck Pereira dos Santos Moriond Conference, la Thuile (Italy), 20-27 March 2011 Flights 522.32 €, subsistence and accommodation 115.5 € Persons attending : Bruno Pelle, Sophie Pélisson, Riccardo Messina 2 talks and 1 poster presenting work related to the project
TOTAL DIRECT COSTS 143.250,75 €
![Page 33: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/33.jpg)
33
TABLE 6.5 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 5 (UNIFI) FOR THE PERIOD
Work Package Item description Amount Explanations
2 Personnel costs 29.506,30 € Salary of 1 Full Professor (Guglielmo Maria Tino) for 2.02 Man Months: 17.553,52 euros. Salary of 1 Temporary Researcher (Nicola Poli) for 3.06 Man Months: 11.952,78 euros.
Equipment -
2 Consumables 1.272,45€ Optics and opto-mechanics for experimental activities in WP2.4
2 Travel 612,41 € Dr. Nicola Poli, iSense meeting in Birmingham (UK), October 06 – 07, 2010: 612,41 euros (flight: 432,00 euros; hotel: 132,56 euros; subsistence: 7,58 euros; other costs: 40,27 euros).
TOTAL DIRECT COSTS 31.391,16 €
TABLE 6.6 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 6 (LUH) FOR THE PERIOD
Work Package Item description Amount Explanations
3,4 Personnel costs 22193 Manuel Popp, researcher, dissemination administrator – 7 month Michael Senkler, research assistant – 1 month Lisa Tessen, research assistant – 1 month
2 Consumables 113 Spare part
4 Dissemination 504 Frontend hardware for website maintenance License fee for Top Level Domain (webpage)
2,3,4 Travel 1241 E. M. Rasel and T. Wendrich, iSense meeting Birmingham, 06. – 07.10.2010 ( 564 €) M. Popp, representing iSense at the DPG spring meeting, Dresden, 13. – 18.03.2011 (619 €) M. Popp, iSense meeting, Brussels, 13.–16.09.2011 (air ticket, 58€)
TOTAL DIRECT COSTS 24051
![Page 34: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/34.jpg)
34
TABLE 6.7 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 7 (IQOQI-OEAW) FOR THE PERIOD
Work Package Item description Amount Explanations
2,4 Personnel costs 4686€ Salary of PI (Florian Schreck) for activities directly related to iSense (0.8 man months)
TOTAL DIRECT COSTS 4686€
TABLE 6.8 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 8 (FBH) FOR THE PERIOD
Work Package Item description Amount Explanations
1 Personnel costs 31.143,11 € Salary of 1 postdoctoral student for 12 months
1 Subcontracting 2.585,00 € SIMS-Analysis
1 Consumables 1.265,33 € 2” Wafer, components and Cu-Plate
1 Travel 159,23 € 893,69 €
Attendance Mr. Kürbis at project meeting in Hannover Attendance Dr. Wicht at project meeting in Birmingham, UK.
TOTAL DIRECT COSTS 36.046,36 €
TABLE 6.9 PERSONNEL, SUBCONTRACTING AND OTHER MAJOR DIRECT COST ITEMS FOR
BENEFICIARY 9 (UNOTT) FOR THE PERIOD
Work Package Item description Amount Explanations
1 Travel 700 P. Krüger – Travel to FBH Berlin in order to discuss taking over tasks formerly designated to QinetiQ, November 2010 M. Fromhold – Travel to an S&I meeting in Birmingham in order to discuss splitter design work with K. Bongs, February 2011
1 Consumables 6757 Semiconductor processing costs
TOTAL DIRECT COSTS 7457
![Page 35: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/35.jpg)
35
7. Financial statements – Form C and Summary financial report
See NEF
![Page 36: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/36.jpg)
36
8. Certificates
List of Certificates which are due for this period, in accordance with Article II.4.4 of the Grant
Agreement.
Beneficiary Organisation
short name
Certificate on
the financial
statements
provided?
Yes / no
Any useful comment, in
particular if a certificate is not
provided
1 Bham no Expenditure threshold not reached
2 QINETIQ no Withdrawn
3 UHH no Expenditure threshold not reached
4 CNRS No Expenditure threshold not reached
4 third party UPMC No Expenditure threshold not reached
5 UNIFI No Expenditure threshold not reached
6 LUH No Expenditure threshold not reached
7 IQOQI-OEAW No Expenditure threshold not reached
8 FBH No Expenditure threshold not reached
9 UNOTT No Expenditure threshold not reached
![Page 37: PROJECT PERIODIC REPORT - CORDIS · 2017-04-22 · 2 Declaration by the scientific representative of the project coordinator1 I, as scientific representative of the coordinator1 of](https://reader034.vdocuments.site/reader034/viewer/2022042303/5ece10078eebef2c8329a542/html5/thumbnails/37.jpg)
37
Appendix 1 Distribution of Person Months by Partner and Work-package
For ease of reference we include a complete table of the actual and planned person months. The “actual” values include only the months claimed
as eligible costs, and do not include considerable additional months paid for by the partners, which are included in the “planned” values. Please
note that the “planned” values correspond to the total project duration.
Person-Month Status Table
iSense
PERIOD:1.7.2010 to 30.6.2011 TOTALS BHAM UHH CNRS UNIFI LUH OAEW FBH UNOTT
WP1: Integrated Laser Actual WP total: 24.62 0.62 24
System Planned WP total: 84 19 5 2 2 30 26
WP 2: Science Chamber Actual WP total: 28.68 0.10 6.75 15.95 5.08 0.8
and Scheme Planned WP total: 211 3 27 76 45 12 14 34
WP 3: Integrated Sensor Actual WP total: 7.3 0.2 0.1 7
Planned WP total: 26 3 11 4 17 1 1
WP 4: Dissemination Actual WP total: 26 0.01 0.4 2
Planned WP total: 16 3 1 4 1 5 1 1
WP 5: Management Actual WP total: 0.77 0.77
Planned WP total: 12 12
Actual total: 87.37 1.7 6.75 16.45 5.08 9 0.8 24 0
Total Project Person-month Planned total: 349 37 36 91 52 36 15 31 62