Page 1: Project Orion Release C Market Communication Session 17 August 2007

Copyright© JSE Limited 2005 www.jse.co.za

Project OrionRelease C

Market Communication Session

17 August 2007

Leanne Parsons

Page 2: Project Orion Release C Market Communication Session 17 August 2007

© 2

Market Communication Session Agenda

Part 1 – General Communication Session 14:00 – 14:45− Timeline− Market Dress Rehearsal Objectives− Market Dress Rehearsal Pre – Requisites− Market Dress Rehearsal Success Criteria− Market Dress Rehearsal Participant Responsibilities− Market Dress Rehearsal Data Guidelines− Market Dress Rehearsal Communication− Market Dress Rehearsal Connectivity− Market Dress Rehearsal Tracking− Conformance

Part 2 – Technical Workgroup Session 14:45 – 15:30− Status and Follow up on the first TWG− Mandatory Conformance Testing− General Discussion and overview

Page 3: Project Orion Release C Market Communication Session 17 August 2007

© 3

July 07 August 07 September 07

Week of

9 – 13

Week of

16 – 20

Week of

23 – 27

Week of

30 - 03

Week of

06 – 10

Week of

13 – 17

Week of

20 – 24

Week of

27 – 31

Week of

03 - 07

Week of

10 - 14

Week of

17 – 21

Week of

24 - 28

TINT API User Conformance

Pre-Prod UAT

18th

Internal DR

18th

Internal DR

25th

External DR 1

Final UAT

29th

External DR 2

29th

External DR 1

Green shadesDenote Agri Derivatives

Blue shadesDenote Equity

Derivatives

Final UAT

TimelineWe are here

Page 4: Project Orion Release C Market Communication Session 17 August 2007

© 4

October 07 November 07 December 07

Week of

01 – 05

Week of

08 – 12

Week of

15 – 19

Week of

22 – 26

Week of

29 -02

Week of

05 – 09

Week of

12 – 16

Week of

19 – 23

Week of

26 – 30

Week of

03 – 07

Week of

10 - 14

Week of

24 – 28

Week of

31 - 08

29th

External DR 2

29th

External DR 1

6th

Prov DR

13th

// run

15th

ADGo Live

Cont. 1

Go Live DR

Cont. 2

5th29th

//RUN

10th

ExternalDR 2

Go Live DR

12th

ED Go Live

3rd

Cont 2

27th

26th

Cont 1

Page 5: Project Orion Release C Market Communication Session 17 August 2007

© 5

Market Dress Rehearsals Objectives

Practice the cut over activities required for Go Live

Simulate selected trading on the new Derivatives Trading Platforms

Gauge overall level of readiness across all Stakeholders

Identify any critical issues that need to be addressed prior to Go Live

Provide Users with an opportunity to test their front-end solutions and related systems on the production environment

Provide API developers with opportunity to prove systems in the production environment

Prove EOD processes and other after market activities in the production environment

Note: Apart from a brief, scheduled period of volume testing (Functional Testing Schedule) the overall objective of the JSE Release C Derivatives Markets Dress Rehearsal is NOT that of a stress test.

Page 6: Project Orion Release C Market Communication Session 17 August 2007

© 6

Market Dress Rehearsal Pre-Requisites

Trading and Clearing Members must have attended training or be familiar with the respective new front-end applications

All users must have IT support on site during dress rehearsals

Clearing Members must have on-site support for the Friday evening activities as well for Sat at end of DRs for balancing

Network connectivity to production environment configured on IP

Successful log on to production environment (at least 3 days before dress rehearsal)

Key responsible person identified and communicated to the JSE 3 days before the first dress rehearsal

Must have passed Conformance by 28 September 2007

Page 7: Project Orion Release C Market Communication Session 17 August 2007

© 7

Ability to connect and trade

Ability to receive public data

100% interactive participation throughout the test period

Adherence to the test schedule and conditions

Adherence to realistic order details and prices

Adherence to normal trading and volume activity - except for volume testing period

Completed and signed test checklists / results returned to the JSE

Completed and signed declaration that functionality and data integrity was intact

All issues are logged

No excessive re-requests of data during the tests

Market Dress Rehearsals Success Criteria

Page 8: Project Orion Release C Market Communication Session 17 August 2007

© 8

Market Dress Rehearsal User Responsibilities

Users are responsible for all of their own environment preparations, connectivity and reference data download

All users to log on and participate in the test

Users must monitor communication channels throughout the test

All errors must be logged following the error logging procedure

Please refer to http://www.jse.co.za/po_relc_external_test.jsp for the error logging procedure and template. Any other issue encountered during Dress Rehearsals must be logged with JSE Client Services (011-520 7777)

Page 9: Project Orion Release C Market Communication Session 17 August 2007

© 9

Market Dress Rehearsal Data Guidelines

Valid user codes and passwords must be used for all application access

− External test environment usernames apply

− Passwords reset will be prompted by the system on first login

Realistic prices and volumes must be entered

Data will be converted from production for the Dress Rehearsals

Before testing, check all clients available in the system are accurate and all positions reflect as at COB Friday before Dress Rehearsal

Page 10: Project Orion Release C Market Communication Session 17 August 2007

© 10

Market Dress Rehearsals Schedule - Friday

A Balancing of environments

Clearing Members to balance current production against Release C environment

Clearing Members to notify JSE that they balance

19h00 – 21h00

B Backup of environments

Clearing Members and JSE technical teams to perform backup of their Release C environments

Clearing Members to follow their standard internal processes for this

21h00 – 23h00

Friday evening – Clearing Members and JSE only

Page 11: Project Orion Release C Market Communication Session 17 August 2007

© 11

Market Dress Rehearsals Schedule - Saturdays

A JSE Market Startup

Market startup procedure at JSE 08h00 – 09h00

B Continuous Trading

Users login, Open Order Period, Auction Period, Continuous Trading

All traders onsite

Use of realistic prices and volumes only

09h00 – 12h00

C Volume Testing Simulated Futures Closeout Volumes only 12h00 – 12h30

D Admin Period Deal Management and Report only trades 12h30 – 13h00

E Balancing to Clearing Members

MTM and Margining

MTM file available for download

End of Test for Trading Members and Information Subscribers business staff

Clearing Members download and balance

End of Test for Clearing Members business staff

13h00 – 14h00

Page 12: Project Orion Release C Market Communication Session 17 August 2007

© 12

Market Dress Rehearsals Schedule – Saturday (continued)

F End of day Processing and Downloads

End of day structured products available

Reports available on website

JSE internal processing

14h00 – 15h00

G Rollback of Release C environment

All users and JSE roll back environments to pre-dress rehearsal state

End of Test for Users Technical staff

15h00 – 17h00

Page 13: Project Orion Release C Market Communication Session 17 August 2007

© 13

Market Dress Rehearsal Communication

The JSE will communicate progress, issues and status of the tests with all users in a number of different ways:

A message via the front end

An email to all known email addresses

An SMS to known cell phone numbers

Web page to be found on: http://www.jse.co.za/project_tracking/OrionRelC.jsp

Page 14: Project Orion Release C Market Communication Session 17 August 2007

© 14

Market Dress Rehearsal Connectivity

Production environment

Production Equity Derivatives and Agricultural Derivatives Trading Systems:

Proxy host address: 10.3.5.131

TCP port (Financials): 2003

TCP port (Agriculturals): 2210

Download Server for updates:

Download Server host address: 10.3.5.13

TCP port (Financials and Agriculturals): 4410

Please note – the latest User Connectivity document is available from the JSE website. All stakeholders to ensure that access to the new Release C Production IP addresses is configured by all before the 1st Dress Rehearsal.

Page 15: Project Orion Release C Market Communication Session 17 August 2007

© 15

Market Dress Rehearsals Tracking

The JSE Release C Derivative Market Dress Rehearsal Detailed Checklist will be used as a measure of success of a participant in Market Dress Rehearsal. The checklist must be completed by a nominated representative and must be signed off by both the Head of Derivatives Trading and an IT representative.

The completed Detailed Checklist must be submitted electronically or be faxed to the JSE by the latest 10h00, the Monday post the Dress Rehearsal Weekend.

The contact details are provided below:

E-mail: [email protected]

Fax: 011 - 520 8141 / 8880 / 8883

Page 16: Project Orion Release C Market Communication Session 17 August 2007

© 16

Conformance

Conformance slots will be available daily from 20 August 2007. Please ensure you book sufficient conformance slots before the Dress Rehearsals

Conformance testing will occur in the External Test Environment. Please note the external test environment is also available for users to test their API solutions

Users will follow the conformance test scripts applicable to their software.

The JSE will monitor the Conformance tests and issue a pass or fail once the test results and logs have been analysed

For detailed conformance information please refer to the Conformance test pack

Must have passed Conformance by 28 September 2007

Page 17: Project Orion Release C Market Communication Session 17 August 2007

Copyright© JSE Limited 2005 www.jse.co.za

Questions?

Please refer all derivative queries to [email protected]

Page 18: Project Orion Release C Market Communication Session 17 August 2007

Copyright© JSE Limited 2005 www.jse.co.za

Thank you

Page 19: Project Orion Release C Market Communication Session 17 August 2007

© 19

Release C TWG

Status and Follow up on the previous TWG

• Known API issues and resolutions communicated regularly to API user group

• FAQ’s document updated and published

• Release C API specification document updated

Mandatory Conformance Testing

• Conformance slots to be booked by all software providers according to conformance pack

• Conformance slots are available from 20 August 2007

• Conformance for both markets must be completed by 28 September 2007