Page 1: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Project Oasis

West Des Moines, IowaPresentation

January 30, 2013

Page 2: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Project Description

• Project Area: 40 acres.

• Project Location: South side of Booneville Road, and west of future 105th Street.

• Project Size: 100,000-150,000 sq. ft.

• Property taxable valuation: $50,000,000.

Page 3: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Map of Site

Page 4: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

InfrastructureElectric• The project site is located approximately

between the Booneville Substation to the west and the West Grand Substation to the east.

• MidAmerican Energy is currently in the process of seeking approval from the City for the construction of the new Sugar Creek Substation located just west of the West Grand Substation.

• MidAmerican Energy’s electric transmission lines are located on the southern boundary of the project site.

Page 5: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Map of Electric Facilities

Page 6: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Infrastructure

Fiber Optic• Currently, AT&T, Level 3, Sprint, and

CenturyLink have long haul fiber optic lines running along the right-of-way of Raccoon River Drive, located approximately ¼ mile to the south of the project site.

• AT&T also has fiber optic cable running within the right-of-way of MidAmerican Energy’s transmission lines located along the southern portion of the project site.

Page 7: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Map of Fiber Optic Cable Locations

Page 8: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Infrastructure

Sanitary Sewer• Extension of a 36 inch line from the WRA’s Sugar

Creek line located at the intersection of future Grand Avenue alignment and Sugar Creek.

• Estimated cost approximately $2,782,500.

Page 9: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Map of Sanitary Sewer

Page 10: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Infrastructure

Water (Primary)• Extension of a 12 inch water line from 88th and

Grand Avenue westerly along the future alignment of Grand Avenue.

• Estimated cost $1,420,000.

Water (Secondary)• Extension of a 12 inch water line from the

intersection of Booneville Road and 88th Street westerly along the right-of-way of Booneville Road.

• Estimated cost $1,420,000.

Page 11: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Map of Primary Water Line

Page 12: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Infrastructure

Streets• Extension of 105th Street from its intersection at

Raccoon River Drive northerly to Booneville Road.

• Estimated cost $9,670,000.

Page 13: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Map of Streets

Page 14: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Business Assistance

• Expedited permit processing of site plan, zone change and platting of 60-90 days to approval.

• The City’s first review comments on project submittals of one week or less.

• Assigned case planner to act as your liaison.

Page 15: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

IncentivesBased upon an estimated $50,000,000 of property tax valuation, (the Microsoft Phase II project was 110,000 sq. ft. and had a value of $53,100,000):• The City of West Des Moines would construct the

sanitary truck lines necessary to service the project: $2,782,500;

• West Des Moines Water Works would construct the water line along future Grand Avenue to service the site: $1,420,000;

• West Des Moines Water Works would construct the secondary water line along Booneville Road necessary to serve the site: $1,420,000; and

Page 16: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Incentives (continued)

• The City of West Des Moines would construct 105th Street from Raccoon River Drive to Booneville Road: $9,670,000.

• Total value of incentives: $15,292,500.

Page 17: Project Oasis West Des Moines, Iowa Presentation January 30, 2013

Questions?