Page 1: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

1

Global Environmental

Fund

Ministry of Education and Science of the

RF

United Nations Development Programme

PROJECT Ministry of Education and Science of the

RF/UNDP/GEF Standards and Labels for Promoting Energy

Efficiency in the Russian Federation Goals. Outcomes

Page 2: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

2

Project Period: 2010 - 2014

GHG emission reduction through less energy

consumption by industrial, residential and public

buildings

EE equipment promotion using EE standards and

labeling.

Goal Objective

Page 3: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Federal Laws and Resolutions by Government and Ministries RF

3

Requirements to labeling defined by Federal Law 261 (2009): On Energy Saving and Improving Energy Efficiency

In pursuance of FL 261 Resolution 1222 was approved by Government RF in 2009 to list the products subject to EE labeling. Executive Orders 767, 769 and 798 by Ministry of Industry and Trade RF set EE product classes, definitions, labeling rules, etc.

Page 4: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

4

Equipment of Project Competence

Equipment Group Power consumption, TWh/year

Industrial equipment used in buildings

Water pumps 12,800

Industrial air-conditioners and ventilators (VAC) 2,900

Cooling systems for central air-conditioning 850

Household appliances

Refrigerators and freezers 31,600

Washing machines 7,300

Page 5: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Initial Obstacles and Removal Action

1. Absence of methodological materials for project implementation

• Detailed guidelines drafted on tendering, applications and implementation following UNDP procedures

• Score tables made • Reporting formats devised 2. Absence of development procedures and document

formats, i.e. action plans, terms of references, acceptance certificates, etc.

• Appropriate procedures and formats drafted and approved by National Project Manager

3. Actual Project start: 2011

5

Page 6: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Project Objectives

1. Development of legislative base 2. Development of standards and other regulations 3. Raising awareness of manufacturers and other

market players in high EE-class equipment promotion 4. Raising awareness of end users in EE promotion

Various stakeholder groups have different interests

6

Project is complex with 4 sections

Page 7: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

7

Key Deliverables(Section 1) Development of legislative base

• Amendments to laws and regulations drafted and submitted to Ministry of Energy RF

• Amendments to Federal Law 261 passed first hearing at State Duma • Draft resolution by Government RF and draft executive order by ME RF

submitted to ME RF for approval

• Pilot region’s legislation (Moscow) reviewed • Draft laws and regulations on EE labeling submitted to Moscow

government • 8 draft documents in total submitted to Moscow government

• Requirements developed on EE labeling and minimal requirements to EE characteristics for public procurement of HHA and TBE

• Drafts submitted to Moscow government for approval

Page 8: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Pilot Region’s Deliverables (Moscow)

On balance, an EE-labeling toolkit has been

created and is in wide use presently in the pilot region for energy saving.

The Project is to be continued in the 2nd pilot

region, i.e. Nizhniy Novgorod.

8

Page 9: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

9

Key Deliverables (Section 2) Developing the State Standards (GOST)

• 8 GOST standards drafted • 5 GOSTs approved by Gosstandart RF in 2012 • 3 GOSTs to be adopted by Gosstandart RF in 2013 • Standard setting is ongoing • All the standards developed comply with EU standards

• Legal framework completed to enact in Russia Customs Union’s technical regulation: On Consumer Notice of Energy-Consuming Devices’ EE

Page 10: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

10

Key Deliverables (Section 3) Manufacturer & Sales Staff Information &

Training

• Guidelines and info materials developed for TBE sales staff • Training provided to HHA/TBE sales staff on labeling to build up

higher EE-class equipment sales • Training to be continued on a regular basis

• Guidelines and info materials developed for manufacturers • Training provided to HHA/TBE manufacturers on EE labeling • Trainees included principal HHA/TBE manufacturers’ personnel • Training to be continued on a regular basis

Page 11: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

11

Key Deliverables (Section 4) End User Education

Market studied and data received on sales across EE classes. A steady trend revealed to power consumption and GHG emission reduction.

Project web-site created with detailed Project data, also on EE labeling.

Information and training events held for various stakeholder groups.

Page 12: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

12

Key Deliverables (Section 4) End User Education (continued)

Training provided to major companies and their purchasing staff.

Training provided to HHA/TBE sales staff.

Manuals developed on HHA EE and improved EE for schools. Training provided on a regular basis.

Educational campaign on HHA EE held for household consumers and at schools About 4 500 persons trained in total in all categories.

Page 13: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Key Deliverables (Section 4) End User Education (continued)

A training programme is to be developed in 2013 on improved EE audit for universities:

Labeling for Improved TBE EE for Energy Audit of Various Facilities.

The programme will be based upon previous Project outcomes.

The programme will include:

- Federal requirements to energy audit of buildings and facilities; - Regulatory framework;

- EE class determination methods for buildings, equipment, etc.

13

Page 14: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Outcomes (energy consumption and СО₂ monitoring)

2012 – 2013: monitoring implemented of energy consumption and СО₂ emission reduction.

Positive trend revealed for both HHA and TBE. Monitoring to be continued.

14

Page 15: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Outcomes (energy consumption and СО₂ monitoring)

СО₂ emission decline in 2009 - 2011: • Russia – 1,508,000 t • Pilot region (Moscow) – 240,000 t

15

Page 16: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Progress Project Performance Evaluation in 2013

16

• Progress performance evaluation is required by UNDP and GEF procedures to streamline projects, if appropriate.

Progress evaluation conclusions: • Changes required to Project strategy and activities. • Ongoing education/training required for stakeholders. • Project deliverables to be approved sooner. • Project extension required through 2016, with respective

budget adjustments for improved performance and effectiveness.

Page 17: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

Key Lessons Learnt Main Barriers

• 1. Multitude of market player groups and their conflicting interests regarding both HHA and TBE.

• 2. Too complicated Russian legislation, with a long approval process.

• 3. Lack of robust and quality data on Project scope at Government level.

• 4. Low market player awareness of EE labeling as a tool for improved EE.

• 5. High prices for high EE-class equipment. • 6. Complicated and long UNDP procedures at all Project

implementation phases, etc.

17

Page 18: PROJECT Ministry of Education and Science of the RF/UNDP ......GEF procedures to streamline projects, if appropriate. Progress evaluation conclusions: • Changes required to Project

18

International Project Ministry of Education and Science of the RF,

UNDP/GEF Standards and Labels for Promoting EE in the

Russian Federation

http://www.label-ee.ru/

G.A. Smaga, Senior Project Expert on Standards and Labels

Thank you for your attention!