project evaluation criteria mf 807: corporate finance professor thomas chemmanur

26
1 Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

Upload: gavin-hopkins

Post on 03-Jan-2016

226 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1

Project Evaluation Criteria

MF 807: Corporate FinanceProfessor Thomas Chemmanur

Page 2: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

22

Corporate Finance

1. Investment Decision

(a) Capital Budgeting

(b) Long-term Investment Strategy 2. Financing Decision

(a) How Should Investment Be Financed? Internal or External Financing What is the Menu of Securities to Use for External

Financing? Stocks, Bonds, Preferred Stock, Convertible Debt

(b) Interactions between financing and investment decisions 3. Dividend or Payout Decision

Page 3: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

33

Corporate Finance

(a) Of Total Earnings, How Much (What Fraction) Should Be Paid Out and How Much Retained (Retained Earnings)?

(b) Once the Payout Ratio is Decided, What is the Method of Payout?

Cash Dividends Stock Repurchases

Open Market Repurchases Tender Offers

Fixed Price Dutch Auction

Page 4: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

44

Objective of Firm Manager

The objective of a firm manager is to maximize shareholder wealth

Equivalent to maximizing total value of the firm’s equity, or its stock price

The above can be thought of as a benchmark; there may be in deviations in practice

E.g. agency problems However, if the deviations are too much, the CEO can be fired,

by the board. Takeovers and leveraged buyouts can also discipline firm

management

Page 5: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

55

Capital Budgeting

Capital Expenditures Expected to generate cash benefits lasting longer than a year

Operating Expenditures Expected to generate benefits for less than a year

Capital expenditures are incurred to obtain capital assets used in the production of goods and services; summarized in capital budget

New machinery, real estate, construction of factories, replace machinery, expand product line

Page 6: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

66

Capital Budgeting is a Complex Process

1. Searching for new projects 2. Marketing and production analysis – cash flow

estimates 3. Preparation of cash budgets 4. Evaluation of project proposals 5. Control and monitoring of past projects

Page 7: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

77

Steps Involved in Evaluating Project Proposals

1. Estimate the cash flows involved at various points in time.

Include not only the benefits, but the investment required

2. Estimate the riskiness in project cash flows, and thus the appropriate discount rate to use.

3. Select projects, and amounts to be invested in each using appropriate evaluation criteria.

Keep in mind limitations in amount of investment

Page 8: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

88

Project Evaluation Criteria

Project Evaluation Criteria:• 1. NPV rule• 2. Internal Rate of Return• 3. Benefit to Cost Ratio

Ad-hoc Project Evaluation Rules• 4. Payback Period Rule• 5. Discounted Payback Period Rule• 6. Average Return on Book Value

Page 9: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

99

The Net Present Value Rule

If we assume a flat term structure:

Decision Rule:

i. Under No Capital Rationing: accept all projects with a positive net present value

ii. Under Capital Rationing: accept that combination of projects that gives the highest net present value

1 20 2

1 2

...(1 ) (1 ) (1 )

nn

n

CC CNPV I

r r r

1 2 3 ..... nr r r r r

Page 10: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1010

Example

NPVA+B = NPVA + NPVB

Investment Amount (Total) = $10,000.00 Optimal Combination I, III, IV. Why? NPV = $1450.00 Combination of I & III NPV = $1250.00 < $1450.00

Project Investment Required

NPV

I $5000.00 $800.00

II $5000.00 $400.00

III $3000.00 $350.00

IV $2000.00 $300.00

Page 11: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1111

Internal Rate of Return (IRR)

It is that rate of return at which this equation holds:

I.e. IRR is that discounting rate at which the net present value equals zero

Decision Rule:i. Under No Capital Rationing: Accept all projects with an

IRR above a certain cut-off of return, which depends on the riskiness of the project

ii. Under Capital Rationing: Accept that combination of available projects which satisfies the investment constraint and gives the highest IRR

1 20 2

...(1 ) (1 ) (1 )

nn

CC CI

IRR IRR IRR

Page 12: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1212

Example

I0 = $10,000; C1=$4,000; C2 = $3000 = C3 = C4 = C5

NPV at r = 12%

t = 0 1 2 3 4 5

-10,000 4000 3000 3000 3000 3000

4 ,12%

4000 110,000 3000 PVIFA

1.12 1.121

10,000 3571.43 3000 3.03731.12

$1707.05 0 ACCEPT PROJECT

yrsNPV

NPV

NPV

Page 13: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1313

Example

NPV @ 14%

NPV @ 15%

4 ,14%

4000 110,000 3000 PVIFA

1.14 1.141

10,000 3508.77 3000 2.91371.12

$1176.43 0 ACCEPT PROJECT

yrsNPV

NPV

NPV

4 ,15%

4000 110,000 3000 PVIFA

1.15 1.151

10,000 3478.26 3000 2.85501.15

$926.22 0 ACCEPT PROJECT

yrsNPV

NPV

NPV

Page 14: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1414

Example

Similarly: NPV @ 16% = $685.12 > 0 NPV @ 18% = $229.24 > 0 NPV @ 20% = -$195.05 < 0

Thus, IRR = 19% > Cutoff (Say 12%)

12 14 16 18 20

IRR 19%Discount Rate %

NPV($)

2000 -

1000 -

-1000 -

Note that, by definition, NPV falls to zero at the IRR discount rate

Page 15: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1515

Comparison of NPV and IRR

1. IRR Cannot Distinguish Between Lending and Borrowing In some cases (e.g. when initial cash flows are positive), this

may lead to acceptance of negative net present value projects: Example:

When we lend, we like a high return. When we borrow, we want to pay a low return.

Project C0 C1 IRR NPV@10%

A -1000 +1500 50% +364

B +1000 -1500 50% -364

Page 16: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1616

Comparison of NPV and IRR

2. Multiple IRRs when there is more than one change in the sign of project cash flows

Most projects have only one change in sign from negative to positive cash flow

Some projects may have negative cash flows later more than one change in sign, generating as many IRRs as there are changes in sign. (“Descartes Rule of Signs”)

What is the real IRR then? We have to appeal to NPV then.

C0 C1 C2 IRR NPV@10%

-4000 +25,000 -25,000 25% & 400%

-1934

Page 17: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1717

Comparison of NPV and IRR

25% 400% Rate of Return %

NPV($)

0

TWO SOLUTIONS TO THIS EQUATION: 25% and 400%

2

25,000 25,0004,000 0

(1 ) (1 )NPV

r r

Page 18: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1818

Comparison of NPV and IRR

3. Gives wrong rankings for mutually exclusive projects This is the case when the timing of cash flows of the two

projects under consideration is dissimilar

Project C0 C1 IRR NPV@10%

F -10,000 +20,000 100% +8182

G +20,000 +35,000 75% +11,818

75% 100% Rate of Return %

NPV($)

0

G

F

Fisher’s intersection

Page 19: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

1919

Comparison of NPV and IRR

If the cost of capital is lower than the discount rate at the Fisher’s intersection, then choosing the project with the highest IRR means choosing the project that contributes the least to the firm’s equity value

4. Difficult to apply IRR when the term structure of interest rates is not flat unlike NPV, where this can easily be done.

Advantages of IRR No need to estimate cost of capital, at least in initial stages. It is a measure of profitability, accounting for the timing of cash

flows Of course, we do need a cost of capital estimate to decide on the

accept / reject threshold that we compare with the project IRR.

Page 20: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

2020

Profitability Index or Benefit to Cost Ratio

P.I. = Present Value of Benefits from the Project

Present Value of Investment in the Project Decision Rule

i. Under No Capital Rationing: Accept All Projects with P.I. > 1

ii. Under Capital Rationing: Accept that combination of projects that satisfies the investment constraint and gives the highest P.I.

Example: Consider a project with initial investment of $35,000 and net

cash inflows of $9,000 per year for 6 years. The cost of capital is 12%

Page 21: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

2121

Profitability Index or Benefit to Cost Ratio

Solution: PV of Benefits = 9000 [PVIFA: 12%, 6yrs]

= 9000[4.1114]

= $37,002.6 P.I. = 37,002 / 35,000 = 1.057 > 1 ACCEPT NPV = 37002.6 – 35,000 = 2000.6 > 0 ACCEPT IRR: That discount rate “r” at which

• 35,000 = 9000 [PVIFA: r, 6yrs]

• PVIFA = 35,000 / 9000 = 3.888

• IRR 14% > 12% ACCEPT

Page 22: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

2222

The Payback Period Rule

1. Payback Period Number of periods required for project cash flows to add up to initial investment; i.e. smallest “n” for which: C1 + C2 + … + Cn > I0, holds.

Decision Rule: Accept projects with pay-back period less than a cut-off value.

Problems: (i) No discounting.(ii) Choice of cut-off period is arbitrary rejects positive NPV projects with cash flows after the

cut-off.

E.g. with a 2 year cutoff, Project A is accepted & B is rejected!Project I0 C1 C2 C3 Payback NPV @ 10%

A (400) 300 100 20 2 years -29.6

B (400) 100 100 500 <3 years +149.19

Page 23: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

2323

Discounted Payback Period

Number of periods it takes for the sum of the present values of project cash flows to equal the initial investment. However, the problem of ignoring all cash flows after the cut-off remains.

PV of C1 = 300(PVIF) = 300/1.1 = 272.72

PV of C2 = 100(PVIF) = 100/1.12 = 82.64

PV of C3 = 20(PVIF) = 20/1.13 = 15.03

Note we would correctly reject Project A but we might also reject Project B if the payback period was only 2 years.

Project I0 C1 C2 C3 Payback NPV @ 10%

PV of A (400) 272.72 82.64 15.03 No Payback -29.6

PV of B (400) 90.90 82.64 375.65 <3 years +149.19

Page 24: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

2424

Average Return on Book Value

Average return on book value: = average forecasted net income

average annual net book value of project investment

Example:Initial outlay = 6,000; straight-line depreciation Projected Income Statement:

Average annual net income = (500+600+1000)/3 = 700

Year 1 Year 2 Year 3

Revenue 2,500 2,600 3,000

Depreciation 2,000 2,000 2,000

500 600 1,000

Page 25: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

2525

Example: Average Return on Book Value

It is assumed that depreciation takes place at the end of the year

Average of beginning and ending book values

Date 0 Date 1 Date 2 Date 3

Gross book value of investment 6,000 6,000 6,000 6,000

Accumulated Depreciation 0 2,000 4,000 6,000

Net book value 6000 4000 2,000 0

Year 1 Year 2 Year 3

Ave. Book value 5,000 3,000 1,000

Page 26: Project Evaluation Criteria MF 807: Corporate Finance Professor Thomas Chemmanur

2626

Example: Average Return on Book Value

Average book value = (6,000 + 4,000 + 2,000 + 0)/4 = 3,000 Average book rate of return = 700/3,000 = 23.33% This project would be undertaken if the target book rate of

return was less than 23.33% There are a number of problems with this criterion:

It considers only average return on book investment. No allowance is made for the fact that immediate receipts are more valuable than distant ones.

Average return does not depend on cash flows; it depends on the accounting concepts of net income and net book value. These in turn depend on arbitrary conventions adopted for depreciation and so on by the account.