PROJECT E-SCHOOLS MANAGEMENT SYSTEMS – PHASE II
JOSE PERALES, ROSALINDA CASTILLO, MATTHEW LONGORIA
Project E-Schools Management Systems J. Perales, R. Castillo, M. Longoria
1
Contents Requirements Traceability Matrix ................................................................................................................ 2
Project Scope Statement .............................................................................................................................. 3
Work Breakdown Structure (WBS) ............................................................................................................... 5
WBS Dictionary ............................................................................................................................................. 6
Activity List .................................................................................................................................................... 7
Milestone List ................................................................................................................................................ 8
Activity Duration ........................................................................................................................................... 9
Gantt Chart ................................................................................................................................................. 10
Project Cost Estimate .................................................................................................................................. 11
Project Cost Baseline .................................................................................................................................. 12
Progress Report ........................................................................................................................................... 13
Project E-Schools Management Systems J. Perales, R. Castillo, M. Longoria
2
Requirements Traceability Matrix Requirement
No.
Name Category Source Status
1 Stakeholders
ID
Project
Initiation
Team Lead Complete
2 Stakeholder
Register
Project
Initiation
Faculty/Staff/Student/Parent
support
Complete
3 Project Charter Project
Initiation
Team Lead Complete
4 RTM Project
Planning
Team Lead/Members Complete
5 Scope
Statement
Project
Planning
Team Members Complete
6 Work
Breakdown
Structure
Project
Planning
Team Lead/Members Complete
7 User Input
Code
Project
Execution
Visual Basic Coding for
teacher/staff input data
In Progress
8 User Output
Code
Project
Execution
HTML Coding for
parent/student output data
In Progress
9 Code Testing Project
Execution
Team Lead/Members Not
Complete
10 Update School
Servers
Project
Execution
On-site upgrades if
necessary
Not
Complete
12 Software
Deployment
Project
Execution
Install software on all
classroom computers
Not
Complete
13 Post
Deployment
Testing
Project
Execution
Team testing Not
Complete
14 User Training Project
Execution
Team Lead/Members will
train faculty, staff, and
parents
Not
Complete
15 Support
Documentation
Project
Execution
Release support documents
for
faculty/staff/students/parents
Not
Complete
16 Software
Updates
Post
Execution
Release updates to software
as bugs are discovered
Future
Project E-Schools Management Systems J. Perales, R. Castillo, M. Longoria
3
Project Scope Statement
Project Title: E-schools Management Systems
Date: October 12, 2015 Prepared by: Jose Perales, Matthew Longoria, Rosalinda
Castillo
Project Justification: This new e-school management system will provide access to student
grades, attendance, and schedules, for parents to view at their convenience. Parents will be
able to access and update student information once they are logged on.
Parents will be able to stay informed in regards to their child’s academics. This system will
save time and money. Teachers can focus on the academics and will save time and paper by
not having to run copies and waste paper.
.
Product Characteristics and Requirements:
1. Server to run the e-school software
o Enrolls Users
o Gives the user a username and password
o Updates according to input from staff/administrators
o Security from outside network attacks
2. Internet access through a VPN or ISP
o A VPN to the server can be setup for direct access
o The user and server must have internet access to login
3. User Accounts for each parent/student to login
o Unique ID will be setup for each student
o Parents will be emailed and notified of these accounts
o Login will require navigation to webpage
o A password will be assigned and changed upon first login
4. Graphical User Interface for easy navigation
o Easy to use navigation even for the computer illiterate Tabs for
Grades, Attendance, Contact Info, etc.
o Very “light” feel to the webpage
Project E-Schools Management Systems J. Perales, R. Castillo, M. Longoria
4
Summary of Project Deliverables
Project management-related deliverables: business case, charter, team contract, scope
statement, WBS, schedule, cost baseline, status reports, final project presentation, final project
report, lessons-learned report, and any other documents required to manage the project.
Product-related deliverables: research reports, design documents, software code, hardware,
etc.
1. School District servers will need to be updated to run the new software
2. More storage space will be needed therefore larger hard drives must
incorporated to support the amount of data inputted
3. Research shows parents will be more involved with their child’s academic
success with e-school management systems
4. Visual Basic will be used desktop versions
5. HTML will be used for mobile applications
6. Implementation of the software on the network would require setting up Static
IP addresses and a VPN for security encrypted access
Project Success Criteria: This project will be determined successful if it is user friendly,
and runs smoothly enough for staff and parents to access. Student success is very
important to the school district, therefore success would require improvement in student
attendance and grades.
5
Project E-Schools Management System
J.Perales, R. Castillo, M. Longoria
Work Breakdown Structure (WBS)
Att
Project E-School Management Systems
Phase I
Team Contract
Stakeholder Register(a)
Project Charter
Phase II
Project Management
Project Management Plan
Scope Statement
Project Schedule
Risk Plan
Change Plan
Site Design(b)
Site Map(c)
Graphic Design(d)
Features(e)
Records(f)
Grades(g)
Schedule(h)
Attendance(i)
Student Info(j)
Project E-Schools Management System J.Perales, R. Castillo, M. Longoria
6
WBS Dictionary a. The stakeholder register must include all parties involved in the E-Schools Management
System, including district administrators, campus administrators, campus staff, teachers,
students, as well as members of the IT team (IT Lead and secondary members).
b. Site design will be the suggested layout for the input and output forms for the
management system; team members will need to discuss with students, parents, and
teachers with what should be listed.
c. Site map must include all requests from the site design brainstorming suggestions.
d. Graphic design will be conducted using Visual Basic for the teachers and staff to input
student records and data. It will be outputted in HTML so that parents can use a unique
logon on their children’s school’s website to look up current records for their
child/children.
e. Features must include options to request e-mails be sent to parents when their children
fail an exam, miss a school day, or when a teacher requests a face-to-face meeting.
f. Records should list information such as district and school name, active administration,
counselors, phone numbers, and address.
g. Grades must be easily accessible for all parents and be updated weekly with added
emphasis after each six weeks period.
h. Each student’s current daily/weekly schedule should be listed, as well as any extra-
curricular activities the student will be participating in.
i. Each student’s current year-to-date attendance record will be listed. Include all absences
(excused/unexcused) as well as recorded tardiness.
j. Student info will show name, homeroom, assigned counselor, grade level, contact phone
number, current address, adults assigned permission to withdraw student from class.
Project E-Schools Management System J.Perales, R. Castillo, M. Longoria
7
Activity List Process Group Integration Management
Process
Major Output
Project
Initiation
Identify Project
Stakeholders
List of project stakeholders and project roles
Develop Project Charter Reason for project
Project
Planning
Write Scope Statement Detailed information of project needs
Pre-Team Meeting
Planning
Discuss project
Develop Project Plan Have a plan for the project
Project
Execution
Project Execution
Meeting
Discuss execution of project
Write and Test Code This will be the actual e-school management software making and testing
stage
Procure VPN/ISP Establish connection for users to school webpage login for the e-school
management
Update School Servers Any necessary hardware/software upgrades needed for the school servers to
accompany the new e-school system
Purchase addition Storage Needed for the new amount of data input to the severs
Pre-Deployment Testing Use a small LAN to provide testing of software
Deploy District-Wide Actual rollout of software to school servers
Post-Deployment Testing Making sure everything is running accordingly
User Training Training staff and parents on new software
Project
Control
Project Management Oversee the project status and making sure everything is moving along to
finish by deadline
Team Meetings Meetings for project status
Risk Management Discuss project risks
Project
Closeout
Final Documentation Document the final status of the project and wrap up
Updates Periodically rollout updates to software as need
Project E-Schools Management System J.Perales, R. Castillo, M. Longoria
8
Milestone List Milestone Due Date Who’s Responsible
Identify Project Stakeholder Completed Jose Perales
Develop Project Charter Completed Jose Perales
Scope Statement Completed Rosalinda Castillo
Project Planning Team Meeting Completed I.T. Department
Develop Project Plan Completed I.T. Department
Project Execution
Team Meeting
Completed I.T. Department
Coding and Testing 11/8/15 Matthew Longoria
Procure VPN/ISP 11/15/15 Jose Perales
Update School Servers 11/20/15 Jose Perales
Purchase Additional Storage 11/12/15 Gabby De La Rosa
Testing Phase (Pre-Deployment) 11/30/15 I.T. Department
Deploy District Wide 12/9/15 I.T. Department
Testing Phase
(Post-Deployment)
12/19/15 I.T. Department
User Training 12/31/15 Rosalinda Castillo
Project Management Constant Through Project Jose Perales
Project Status Meetings Beginning and Middle of Each
Month
I.T. Department
Risk Management Meetings 1st and 3rd Week of Each Month I.T. Department
Post Risks Assessment End of Each Month Jose Perales
Final Documentation 12/10/15 Jose Perales
Updates 12/31/15 I.T. Department
Project E-Schools Management System J. Perales, R. Castillo, M. Longoria
9
Activity Duration
Expected Duration: 4 Months
Start: Aug 1st, 2015 End: Nov 30st, 2015
Actual Duration: 5 Months
District In-service Thanksgiving Holiday Christmas Holiday
Start: Aug 1st, 2015 End: Dec 31st, 2015
75%50%25%
75%50%25%
Project E-Schools Management System J.Perales, R. Castillo, M. Longoria
10
Gantt Chart
Project E-Schools Management System J.Perales, R. Castillo, M. Longoria
11
Project Cost Estimate # Units/Hr. Cost/Unit/Hr. Subtotals Level 2 Totals % of Total
Project
Management
$78,000 36%
Project Manager 960 $50 $48,000
Project Team
Members
1500 $20 $30,000
Program Design $23,000 10%
Software Coding 750 $20 $15,000
Software Beta
Testing
400 $20 $8,000
Project Execution $110,000 50%
VPN/ISP Upgrade 12 $5,000 $60,000
Data Storage 5 $10,000 $50,000
Post Roll-out
Testing
200 $20 $4,000 $4,000 2%
Training, Rollout
and Support
200 $20 $4,000 $4,000 2%
Total Cost
Estimate
$219,000 100%
Project E-Schools Management System J.Perales, R. Castillo, M. Longoria
12
Project Cost Baseline 1 2 3 4 5 Totals
Project
Management
Project Manager $9,600 $9,600 $9,600 $9,600 $9,600 $48,000
Project Team
Members
$6,000 $6,000 $6,000 $6,000 $6,000 $30,000
Program
Design
Software Coding $3,750 $3,750 $3,750 $3,750 $15,000
Software Beta
Testing
$2,667 $2,667 $2,666 $8,000
Project
Execution
VPN/ISP
Upgrade
$15,000 $15,000 $15,000 $15,000 $60,000
Data Storage $25,000 $25,000 $50,000
Post Roll-out
Testing
$4,000 $4,000
Training,
Rollout and
Support
$4,000 $4,000
Totals $15,600 $34,350 $37,017 $62,017 $70,017
$219,000
Project E-Schools Management System J.Perales, R. Castillo, M. Longoria
13
Progress Report
Project Name: Project E-Schools Management System
Team Member Names: Jose Perales, Matthew Longoria, Rosalinda Castillo
Date: September 20, 2015
Work completed this reporting period:
- Phase II completed
- Project Scope Management
- Project Time Management
- Project Cost Management
Work to complete next reporting period: Work for Phase III
- Project Quality Management
- Project Human Resource Management
- Project Communications Management
What’s going well and why:
- The team supports the group leader’s decisions and has managed to complete all project
assignments by the due date.
What’s not going well and why:
- The team has not yet been able to successfully manage the separation of duties within the
group. While team work is getting completed, some team members are unfairly burdened
with extra tasks.
Suggestions/Issues:
- Conduct group conferences more often through text, e-mail, online chat, and face to face.
- Divide work better between individuals.
- Require entire team approval before signing off on project material.
- Group needs to communicate more often and more efficiently.
Project changes
- The team will need to more effectively communicate between members so that the success
of this project continues on schedule. The team will need to better communicate to better
distribute and complete project tasks.