project duration case study

50
HERVE BARON Project Duration Laws Welcome to the presentation of the stunning EPC Project critical path and duration laws Case study These laws are invaluable and should be known by all! These are empirical laws, i.e., proven by experience. For the full explanation and justification, please refer to my new publication “The Oil & Gas Engineering Guide”, 2 nd Edition, Editions Technip, 2015. Hervé

Upload: h-g-baron

Post on 15-Jul-2015

1.311 views

Category:

Engineering


9 download

TRANSCRIPT

Page 1: Project duration case study

HERVE

BARON

Project Duration Laws

Welcome to the presentation of the stunning

EPC Project critical path and duration laws

Case study

These laws are invaluable and should be known by all!

These are empirical laws, i.e., proven by experience.

For the full explanation and justification, please refer to my new publication “The Oil & Gas Engineering Guide”, 2nd Edition, Editions Technip, 2015.

Hervé

Page 2: Project duration case study

HERVE

BARON

Project Duration Laws

Page 3: Project duration case study

HERVE

BARON

Project Duration Laws

Page 4: Project duration case study

HERVE

BARON

Project Duration Laws

Page 5: Project duration case study

HERVE

BARON

Project Duration Laws

Page 6: Project duration case study

HERVE

BARON

Project Duration Laws

For the explanation of these laws, please refer to:

2nd Edition published in March 2015.

http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html

Page 7: Project duration case study

HERVE

BARON

Project Duration Laws

For the explanation of these laws, please refer to:

Page 8: Project duration case study

HERVE

BARON

Project Duration Laws

For the explanation of these laws, please refer to:

Page 9: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

An On-Shore EPC Project requires 250,000 Engineering manhours

The estimated tonnage of piping is 2,000 tons

The FEED was well done which allows to have 50% Equipment Purchase Orders placed by Project Month 6.

What will be the Project duration (from start to Mechanical completion)?

Page 10: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment

+ 2 months

+ Time for Engineering to progress from 20 to 80%

+ Time for Piping erection and completion

Page 11: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment

+ 2 months

+ Time for Engineering to progress from 20 to 80%

+ Time for Piping erection and completion

Page 12: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

Page 13: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

Page 14: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

+ Time for Engineering to progress from 20 to 80%

Page 15: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

+ Time for Engineering to progress from 20 to 80%

Page 16: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

+ Time for Engineering to progress from 20 to 80% 8 months

Page 17: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

+ Time for Engineering to progress from 20 to 80% 8 months

+ Time for Piping erection and completion

Page 18: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

+ Time for Engineering to progress from 20 to 80% 8 months

+ Time for Piping erection and completion

Page 19: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

+ Time for Engineering to progress from 20 to 80% 8 months

+ Time for Piping erection and completion 17 months

Page 20: Project duration case study

HERVE

BARON

Project Duration Laws

Case study

Project duration =

Time it takes to order 50% Equipment 6 months

+ 2 months 2 months

+ Time for Engineering to progress from 20 to 80% 8 months

+ Time for Piping erection and completion 17 months

=========================================================

From Project start to Mechanical Completion 33 months

Page 21: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide - 2nd edition

Find out much more in:

Page 22: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide - 2nd edition

Discipline presentation: activities and deliverables

Table of Contents

The overall process

Methods & tools

Page 23: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Discipline presentation: activities and deliverables

Page 24: Project duration case study

HERVE

BARON

The work of each Engineering discipline is

described

Page 25: Project duration case study

HERVE

BARON

Design activities are explained, e.g., Plant

Equipment layout

Page 26: Project duration case study

HERVE

BARON

Complex activities, such as QRA, are explained through a practical

example.

Page 27: Project duration case study

HERVE

BARON

How are materials of construction selected ?

Page 28: Project duration case study

HERVE

BARON

How and when are Piping Materials ordered?

Page 29: Project duration case study

HERVE

BARON

A sample of all common Engineering documents is

included

Page 30: Project duration case study

HERVE

BARON

A sample of all common Engineering documents is

included

Use this to specify what you want to your

Engineering supplier !

Page 31: Project duration case study

HERVE

BARON

Verify the contents of engineering documents

with check lists.

Page 32: Project duration case study

HERVE

BARON

Difference between Engineering and Shop

drawings

Page 33: Project duration case study

HERVE

BARON

Understand the main technical aspects, e.g.,

DCS vs ESD

Page 34: Project duration case study

HERVE

BARON

The common 2 types of package control

Page 35: Project duration case study

HERVE

BARON

The different Plant drainage systems

Page 36: Project duration case study

HERVE

BARON

The dynamic forces to which an Off-Shore

Plant is subject

Page 37: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

The overall process

Page 38: Project duration case study

HERVE

BARON

Use this as standard, question deviations.

Page 39: Project duration case study

HERVE

BARON

Understand the new 3D-model centered engineering process

Page 40: Project duration case study

HERVE

BARON

Know the interfaces between disciplines...

and with Vendors

Page 41: Project duration case study

HERVE

BARON

Understand what drives the Project

schedule

Page 42: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide - 2nd edition

Table of Contents

Methods & tools

Page 43: Project duration case study

HERVE

BARON

Use these methods as standard, question

deviations.

Page 44: Project duration case study

HERVE

BARON

Implement powerful procedures

Page 45: Project duration case study

HERVE

BARON

Request meaningful progress reports

Page 46: Project duration case study

HERVE

BARON

Implement effective Project Control

Page 47: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide - 2nd edition

This book is destined to both:

Oil & Gas companies Project execution personnel

Oil & Gas contractors Project execution personnel

Page 48: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide

2nd edition

If your are on the Client side, i.e., contracting Engineering services, this book will help you to:

Specify to an Engineering supplier what you want: what deliverables and with what contents,

Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.

Specify the progress report you want, with the meaningful indicators,

Ask the right questions to assess the true progress,

Page 49: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide

2nd edition

If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:

Understand the work of each discipline and the overall picture,

Challenge what one discipline tells you,

Understand the critical areas,

Put in place the right methods to be successful,

Page 50: Project duration case study

HERVE

BARON

The Oil & Gas Engineering Guide

2nd edition

Ordeer direct on the publisher website:

http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html