project: development of skills for industry … english original: english african development fund...

37
Language: English Original: English AFRICAN DEVELOPMENT FUND PROJECT: Development of Skills for Industry COUNTRY: Ghana PROJECT APPRAISAL REPORT Date: April 2012 Appraisal Team Team Leader: Mr. Joseph Muvawala, Principal Education Economist, OSHD.2 Team Members: Ms. Muriel Kei-Boguinard, Principal Legal Counsel, GECL.1 Ms. Amissah-Arthur Efua, Social Development Specialist, GHFO Ms. Irene Brefo-Sekyere, Procurement Officer, GHFO Mr. Jonathan Nyamukapa, Financial Management Specialist, GHFO Mr. Jemima Tettey, Disbursement Assistant, GHFO Ms. Lydia Chatizembwa, Senior Portfolio Data Analyst, OSHD.0 Ms. Reinhilde Lambrechts, Consultant Architect, OSHD.2 Sector Manager: Dr. Boukary Savadogo Sector Director: Dr. Agnes Soucat Regional Director: Mr. J. K. Litse Peer Reviewers Mr. Corbin Michel Guedegbe, Chief Education Analyst, OSHD.2 Ms. Maimouna Diop-Ly, Principal Health Specialist, OSHD.3/GHFO Mr. Benedict Kunene, Principal Education Specialist, OSHD.2 Mr. Jason Mochache, Principal Architect, OSHD.2/UGFO Mr. Amadou Bachir Diallo, Senior Socio Economist, OSHD.1 Mr. Francis Ndem, Senior Education Economist, OSHD.2 Ms. Anne Sophie Olsen, Consultant OSHD.0

Upload: hoangtuyen

Post on 21-May-2018

221 views

Category:

Documents


5 download

TRANSCRIPT

Language: English

Original: English

AFRICAN DEVELOPMENT FUND

PROJECT: Development of Skills for Industry

COUNTRY: Ghana

PROJECT APPRAISAL REPORT

Date: April 2012

Appraisal Team

Team Leader: Mr. Joseph Muvawala, Principal Education Economist,

OSHD.2

Team Members: Ms. Muriel Kei-Boguinard, Principal Legal Counsel, GECL.1 Ms. Amissah-Arthur Efua, Social Development Specialist, GHFO Ms. Irene Brefo-Sekyere, Procurement Officer, GHFO Mr. Jonathan Nyamukapa, Financial Management Specialist, GHFO Mr. Jemima Tettey, Disbursement Assistant, GHFO Ms. Lydia Chatizembwa, Senior Portfolio Data Analyst, OSHD.0 Ms. Reinhilde Lambrechts, Consultant Architect, OSHD.2

Sector Manager: Dr. Boukary Savadogo Sector Director: Dr. Agnes Soucat Regional Director: Mr. J. K. Litse

Peer Reviewers

Mr. Corbin Michel Guedegbe, Chief Education Analyst, OSHD.2 Ms. Maimouna Diop-Ly, Principal Health Specialist, OSHD.3/GHFO Mr. Benedict Kunene, Principal Education Specialist, OSHD.2 Mr. Jason Mochache, Principal Architect, OSHD.2/UGFO Mr. Amadou Bachir Diallo, Senior Socio Economist, OSHD.1 Mr. Francis Ndem, Senior Education Economist, OSHD.2 Ms. Anne Sophie Olsen, Consultant OSHD.0

TABLE OF CONTENTS

CURRENCY EQUIVALENTS, FISCAL YEAR, WEIGHTS AND MEASURES,

ACRONYMS AND ABBREVIATIONS, LOAN AND GRANT INFORMATION,

PROJECT SUMMARY, RESULTS-BASED LOGICAL FRAMEWORK, PROJECT

TIMEFRAME ...................................................................................................................... i-viii

I – STRATEGIC THRUST & RATIONALE ............................................................................ 1

1.1. Project linkages with country strategy and objectives .................................................... 1

1.2. Rationale for Bank’s involvement .................................................................................. 2

1.3. Donors coordination........................................................................................................ 3

II – PROJECT DESCRIPTION…..………………………………………………………….. 4

2.1. Project components ......................................................................................................... 4

2.2. Technical solution retained and other alternatives explored ........................................... 6

2.3. Project type ..................................................................................................................... 6

2.4. Project cost and financing arrangements ........................................................................ 7

2.5. Project’s target area and population ................................................................................ 9

2.6. Participatory process for project identification, design and implementation ................. 9

2.7. Bank Group experience, lessons reflected in project design ........................................ 10

2.8. Key performance indicators .......................................................................................... 10

III – PROJECT FEASIBILITY ............................................................................................... 11

3.1. Economic and financial performance ........................................................................... 11

3.2. Environmental and social impacts ................................................................................ 11

IV – IMPLEMENTATION ...................................................................................................... 14

4.1. Implementation arrangements ....................................................................................... 14

4.2. Monitoring .................................................................................................................... 16

4.3. Governance ................................................................................................................... 17

4.4. Sustainability................................................................................................................. 17

4.5. Risk management .......................................................................................................... 18

4.6. Knowledge building ...................................................................................................... 19

V – LEGAL INSTRUMENTS AND AUTHORITY............................................................... 19

5.1. Legal instruments .......................................................................................................... 19

5.2. Conditions associated with Bank’s intervention ........................................................... 19

5.3. Compliance with Bank’s Policies ................................................................................. 20

VI – RECOMMENDATION ................................................................................................... 20

Appendix I. Ghana’s comparative socio-economic indicators ................................................ 21

Appendix II. Table of ADB’s portfolio in Ghana ................................................................... 21

Appendix III. Related projects financed by the Bank and other development partners in the

country ..................................................................................................................................... 23

Appendix IV. Map of the Project Area .................................................................................... 24

Appendix V. Procurement Arrangements of the Project.…………………...………………25

Appendix VI. ESMP Summary.…………………….……………………………………….27

LIST OF FIGURES AND TABLES

Title Page

Figure 1: Projected Financing of Education by Sub-Sector (2010 – 2020) …………………... 2

Figure 2: Employment Sectors for Graduates…………………………………………………. 2

Figure 3: Ghana Current Enrolment and Projections by Level of Education (2009-2010)…… 3

Table 1.3: Donors’ Interventions in Skills Development (SD)………………………….......... 4

Table 2.1: Project Components……………………………………………………………….. 5

Table 2.2: Project alternatives considered and reasons for rejection………………………….. 6

Table 2.4 (a): Summary of Project Costs by Component………………………………………. 7

Table 2.4 (b): Sources of Finance (UA million)…………………………………………......... 8

Table 2.4 (c): Project Costs by source of financing by Component……………………….......... 8

Table 2.4 (d): Summary of Project Costs by Category of Expenditure……………………….. 8

Table 2.4 (e): Sources of Finance by Category of Expenditure (UA million)………………… 8

Table 2.4 (f): Expenditure schedule by component (UA Million)…………...………………... 9

Table 4.2: Monitoring Schedule…………………………………………………………......... 17

Table 4.5: Risks and Mitigation Measures………………………………………………...........

19

Currency Equivalents

As of January 2012

1 UA = GHS 2.43

1 USD = GHS 1.58

1 UA = USD 1.54

Fiscal Year

1st January – 31

st December

Weights and Measures

1metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 meter (m) = 3.28 feet (ft)

1 millimeter (mm) = 0.03937 inch (“)

1 kilometer (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

Acronyms and Abbreviations

ADB = African Development Bank ADF = African Development Fund CBT = Competence Based Training COTVET = Council for Technical and Vocational Education and

Training CSP = Country Strategy Paper DPs = Development Partners DSIP = Development of Skills for Industry Project EMIS = Education Management Information System ESP = Education Sector Plan GDP = Gross Domestic Product GES = Ghana Education Service GoG = Government of Ghana GSGDS = Ghana Shared Growth Development Strategy HEST = Higher Education Science and Technology JAS = Joint Assistance Strategy JHS = Junior High School MIC = Middle Income Country MoE = Ministry of Education NQAF = National Qualifications and Assessment Framework NVTI = National Vocational Training Institutes PSU = Project Support Unit PCR = Project Completion Report PSC = Project Steering Committee RAS = Regional Assistance Strategy SHS = Senior High School SDF = Skills Development Fund TERP = Tertiary Education Rehabilitation Project TI = Technical Institute TOT = Training of Trainers TVET = Technical and Vocational Education and Training

ii

Loan and Grant Information

Client’s information

BORROWER: Government of Ghana (GoG)

EXECUTING AGENCY: Council for Technical and Vocational Education and Training (COTVET)

Financing plan

Source Amount (UA) Instrument

ADF

45.00 25.00

Loan Grant

GoG 7.70 Counterpart Funds

TOTAL COST 77.70

ADB’s key financing information

Loan currency

UA

Tenor 50 years

Grace period 10 years

Commitment fee 0.5% (50 basis

points) Other fees 0.75% (service fees)

Timeframe - Main Milestones (expected)

Preparation Mission December 2010

Concept Note Approval September 2011

Appraisal Mission December 2011

Project Approval June 2012

Effectiveness December 2012

Completion June 2017

Last Date of Disbursement June 2018

iii

Project Summary

1. Project Overview: The Development of Skills for Industry Project (DSIP) is designed to

reinforce the Government of Ghana’s efforts to reform Technical and Vocational Education

and Training (TVET). The intervention consists of a loan of UA 45.00 million, an ADF grant of

UA 25.00 million and a Government of Ghana (GoG) contribution of UA 7.70 million. It will be

implemented within a 5 year period and will focus on supporting key reform areas in the TVET

subsector to improve equitable access, quality and relevance and efficient management of TVET

delivery in the formal and informal sectors. The project will contribute to the achievement of the

following key outcomes: improved teaching and learning environment in the 13 beneficiary

public TVET institutions; increased participation levels in TVET; increased female participation

in science related TVET courses; and efficient and effective policy, planning quality control

systems for TVET established at the coordination level. It will also help achieve key outputs of

the TVET reform, including (i) preparation of a costed strategic plan to guide the development of

skills in Ghana; (ii) increasing the supply of high caliber middle level technicians and TVET

instructors; (iii) reviewing the instructor training curriculum; (iv) strengthening the capacity of

the Council for Technical and Vocational Education and Training (COTVET); and (vi)

operationalizing the prior learning mechanism and the accreditation system for TVET.

2. Needs Assessment: Relative weaknesses in technology and innovation as well as labour

market inefficiencies have negatively affected the competitiveness of the Ghanaian

economy. Ghana has transited from a low income country to a low level middle income status,

but still faces a competitive challenge. Ghana’s lack of competitiveness appears to stem from

poor productivity exacerbated by limited supply of equitable and quality training opportunities to

match the needs of the rapidly growing youth population and the demands of the key emerging

economic sectors. Skills delivery is characterised by poor and uneven quality of teaching and

learning coupled with inadequate funding. Only about 1% of the education budget is allocated to

TVET. Consequently, there is an urgent need to address the technical and financial deficiencies.

3. Bank’s Added Value: With the proposed project, the Bank is contributing to easing the

financial constraints that have limited the speed and depth of the reforms in the TVET

subsector in Ghana. Financial resource constraints have limited the speed of reforming the skills

development sector in Ghana and are hindering the subsector’s capacity to respond to the needs

of the economy. The proposed project will provide GoG with resources and the technical

expertise available to support the reform of the TVET subsector by improving equitable access

and quality of TVET delivery. The strengthening of the TVET regulatory framework for quality

envisaged under the project will boost Government’s ability to increase the effectiveness of the

resources invested in TVET by the private sector and non-governmental organisations that

accounts for about 50% of TVET delivery in the country.

4. Knowledge Management: The project will facilitate the creation, transfer and

dissemination of knowledge in the area of TVET. The processes and interventions funded by

the project will entail the creation of knowledge and a system to manage and share the

information. The key interventions that will generate knowledge will include: (i) tracer studies;

(ii) the study on youth unemployment; and (iii) impact evaluation study targeting financial and

non-financial incentives intended to increase female participation in TVET. This information will

enhance decision making in the country and the Bank regarding the functioning of the TVET

system and as well as reflect the impact of specific interventions.

iv

Results-based Logical Framework Country and Project Name: GHANA – Development of Skills for Industry Project (DSIP)

Purpose of the project: To support the development of high quality middle level technical and vocational skills needed in the Ghanaian economy

RESULTS CHAIN PERFORMANCE INDICATORS Means of Verification

RISKS /

MITIGATION MEASURES

Indicator

(including CSI)

Baseline

(2010) Target

IMP

AC

T

Availability of highly skilled human

capital

Economic growth rate

% of graduates employed within six

months of graduation

% of graduates setting up their own

businesses

7.7% (non oil)

10%

20%

9% in 2016

20% in 2017

30% in 2017

Reports from pre-tertiary (technical

institutes) institutions, labour market

statistics, Ghana Statistical Service, surveys, tracer studies, COTVET,

Household Survey (s); Ghana Poverty

Reduction Strategy periodic reports; Common Performance Assessment

Framework (CPAF) proxy indicators on employment

O

UT

CO

ME

S

Outcome 1. Improved teaching and learning environment

in the 13 beneficiary public TVET institutions.

% of qualified instructors in TI’s

Number of students graduating with the

requisite qualifications and skills including

the needy.

84.3% (81% female)

26%

95% (90% female) in

2017

60% (40% female) in

2017

Reports from pre-tertiary (technical

institutes) institutions, labour market statistics, Ghana Statistical Service,

labour market surveys, tracer studies,

National Plan and Development

Commission, COTVET information

systems.

Risks: Lack of resources to meet recurrent

costs (equipment and maintenance.)

Mitigation: Integrated financing for recurrent

expenses in the budget for 2012/ 2013 and the

medium term.

Outcome 2. Increased participation levels in TVET

% of students completing JHS and SHS

enrolling for TVET programmes

7% (30% female)

20% (40% female) in

2017

COTVET Annual reports, TVET EMIS,

project quarterly progress reports

Risk: Unstable in flow of students (female and

male) with the required grades.

Mitigation: Institutionalization of career

guidance and role model programs at JHS and SSH level and improving the image of TVET

through improved teaching and learning

environment.

Outcome 3

increased female participation in science

related TVET courses

% of female enrolled in science related

TVET courses

30%

40% in 2017

COTVET Annual reports, TVET EMIS,

project quarterly progress reports

Risk: Unstable in flow of female students with

the required grades.

Mitigation : Institutionalization of career

guidance and role model programs at JHS and

SSH level and implementation of the teacher improvement intervention at the same level

v

Outcome 4.

Efficient and effective policy, planning quality control systems for TVET established

at the coordination level

% of qualified staff members at COTVET

No. of tracer studies conducted

Costed strategic plan for TVET developed, approved and implemented

40 % of current staff

establishment None available

None available

80 % of the optimal

staff in 2015 Two tracer studies by

2015.

Costed strategic plan for TVET approved by

December 2013

Exit interviews and surveys, quarterly

progress reports, annual performance reports, staff surveys and appraisals.

Risk(s): Possible delays in expansion of

COTVET to reflect the institutional plans and staff needs necessary to facilitate its role

Mitigating Measure(s): Project provision of technical assistance to augment COTVET

technical capacity to perform its key roles.

O

UT

PU

TS

Component 1: Expanding equitable access

to TVET

-Teaching and learning environment improved

-Increased learning opportunities for the

informal sector and needy students in TI’s

- Number of institutions upgraded and

improved

- Number of the bursaries for needy

students

2 TI’s out of 38 TIs

5000 apprentice and zero

bursaries in TVET

15 institutions

completed and

equipped by 2017 1550 bursaries for TI’s

and 7500 apprentices

(60% female) by 2017

Annual COTVET progress report and

project quarterly progress report

Risk: Cost overruns during implementation due

to unforeseen delays in implementation of

construction activities.

Mitigating measure: construction design and

key preparation activities being undertaken

before project approval to ensure adherence to the project’s implementation schedule.

Component 2: Building human and

institutional capacity for TVET

- Reinforced policy and planning for TVET

- Improved quality control mechanism at the

central level

- TVET institutions managed efficiently

-Strategic plan for TVET developed.

- Improved working environment for

COTVET.

- TVET Information System developed.

- Management and leadership course for

TVET developed.

- Number of managers trained.

-Number of faculty trained.

- Number instructors trained in technical

training.

No strategic Plan for

TVET

500 square meters of

sitting space available

TVET MIS not developed.

No specific management

training for TVET

No baseline available

160 out 213 Lecturer have Masters Degree and 30 out

of 72 seniors lecturers have

PhDs

3510 (84%) out 4166

instructors in TVET

Strategic plan

developed by December 2013

4000 square meters

sitting space available

TVET MIS developed

and functional by

December 2014 Management course

developed by

December 2013

50 senior managers of

public and private TI’s trained by 2015

20 additional faculty members upgraded to

master level and 5 to

PhDs

200 additional

instructor trained (30 % for females) by 2016

Annual COTVET progress report and

project quarterly progress report

vi

Component 3:

Improving quality and relevance of TVET - Curriculum development and review to competency based training (CBT)

- National qualifications and accreditation Framework operationalised

- Production of training materials and manuals

-HIV/AIDS materials provided

-Training of guidance and counselling instructors

-Establishment of guidance and counselling

units

- Master craftsmen trained

- No. of trades covered by CBT

- Operational national qualification (NQAF) and accreditation framework

- student textbook ratio

- HIV/AIDS materials developed and

supplied to training institutions

- Number of core career guidance and counselling instructors trained

- Number of counselling centres set up

- number of master craftsmen trained

Three (3) trades

NQAF not operational

1:20

No. HIV/AIDS materials

mainstreamed in TI’s

None trained

0 counseling centre

150 master craftsmen

Six (6) trades by 2016

NQAF operational by December 2013

1:5 by 2017

13 TI’s provided with

IEC materials in

HIV/AIDS by 2017.

100 core career guidance counsellor (50

% females) by 2016.

13 centres set up by

2017

500 additional master

craftsmen trained by

2017

Annual COTVET progress report and project quarterly progress report

Risk(s): Delays in operationalization of the NQAF and the legal framework for registration

and accreditation.

Mitigating Measure(s): The draft accreditation

laws and qualification framework has been

drafted in advance of project approval by the Board. In addition, the establishment for NQF

and accreditation secretariats have been

approved by the public service and filling of

the position is under way.

Component 4: Project management

- Facilitation for project management

- Impact evaluation mechanism developed and

piloted

-Functional project management frame

work for coordination

-Impact evaluation study conducted

PSU is in place but not

adequately staffed

None done

PSU is in place and

adequately staffed

One impact evaluation

conducted and results

published by 2016

Annual COTVET progress report and project quarterly progress report

vii

Project Timeframe

1

REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE ADB GROUP

TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO GHANA FOR THE

SUPPORT TO THE DEVELOPMENT OF SKILLS FOR INDUSTRY PROJECT

Management submits the following report and recommendation on a proposed loan for UA

45.00 million and a grant for UA 25.00 million to finance the Development of Skills for

Industry Project (DSIP) in Ghana.

I – STRATEGIC THRUST & RATIONALE

1.1 Project linkages with country strategy and objectives

1.1.1 The proposed Development of Skills for Industry Project is designed within the

context of the human capital development priorities of the country. It supports the

Government of Ghana’s (GoG’s) efforts to resolve a key development challenge of low quality

skills produced by the Technical, Vocational Education and Training (TVET) subsector. The

proposed project is aligned with the priorities of Ghana’s development agenda which

emphasizes the enhancement of the competitiveness of goods and services produced in the

country. This is to be achieved through improved production of human capital that is critical

for growth and poverty reduction. The project is consistent with the Ghana’s Shared Growth

Development Strategy (GSGDS). The GSGDS highlights policy interventions that underscore

the importance of providing support to the TVET subsector with linkages to employment

generation. The link to employment generation also emphasized in the Employment and

Industrial Policy of 2006 and 2011, respectively, is a major focus of this project. At the sector

level, the project objectives resonate with the objectives of the Education Sector Development

Plan- ESDP (2003-2015) which, among others, emphasizes the provision of equitable access

and the improvement of the quality of TVET.

1.1.2 Technical and Vocational Education is a priority investment sector1 for Ghana.

The 2011 budget statement emphasized GoG’s commitment to sustain growth for development

and job creation notes the need to improve skills for the youth through TVET. The ESDP

(2003-2015) projects that if TVET provision is improved, the number of students joining the

TVET stream will increase by 50% by 2016, due to increased completion rates at basic

education level. This policy intent represents a deliberate attempt by GoG to increase the

number of middle level skills produced in the country. In addition, GoG has prioritized TVET

as one of the sectors for which it will borrow to address the shortage of a skilled workforce.

1.1.3 The reform of TVET and the capacity building of the training institutions with

the aim of strengthening entrepreneurship are at the core of the GoG’s employment

policy. Ghana’s employment policy focuses on enhancing technical and vocational education

and training to support employment creation through skills development programmes for the

unemployed youth. The policy also provides a roadmap for skills upgrading for those in

employment and the improvement of the quality and quantity of the workforce, including the

financing of TVET and the provision of guidance and counseling services. The policy further

promotes the strengthening of the structures responsible for governance and delivery of TVET

as well as the promotion of a national system of apprenticeship. It further proposes business

development and management through improving the organization of entrepreneurship training

in pre-tertiary and TVET institutions. These key human capital development interventions

contained in the policy are at the core of the design of the proposed project.

1 The Budget Statement and Economic Policy of the Government of Ghana (Financial year 2011 pg.130 )

2

Figure 2: The non-formal sector absorbs more

graduates

1.1.4 The project conforms to the key policies of the Bank and its assistance strategy

for Ghana. The Country Strategy Paper (CSP) (2012 - 2016) for Ghana seeks to assist the

country in addressing human resources challenges through activities that will contribute to the

building of an optimal level of the human capital stock required to achieve sustainable growth.

It is also in line with Bank’s priorities as stated in its Medium-Term Strategy (MTS) of 2008-

2012 and the Higher Education, Science and Technology (HEST) Strategy, that emphasizes the

need for the Bank to invest in vocational training, higher education, science and technology.

1.2 Rationale for Bank’s involvement

1.2.1 The financing of the project will speed up

TVET reform in Ghana. Inadequate financial resources

coupled with insufficient prioritisation of TVET in the

national budget constrain the speed of the reform of TVET

in Ghana. As shown in figure 1, a review of the public

expenditure projections for 2010-2020 for education

shows that basic education is allocated 57% compared to

TVET at only 1%, with the balance going to secondary

education, Higher Education, Special Education and

management. The allocation to TVET is not projected to

grow in the medium term. Salaries constitute over 80% of

the budget allocated to this subsector thus crowding out

expenditures for inputs to improve quality. This funding

falls far short of the estimated USD 4502 million in the

medium term required by the TVET subsector alone for

bringing the GoG institutions to an acceptable level. Due

to this inadequate funding situation, GoG is unable to

implement key elements of the reforms in the TVET subsector. In line with the HEST strategy,

the project will provide the much needed financial and technical support with a view to

deepening the reform of the TVET subsector.

1.2.2 The Ghanaian labour market is

characterized by a quantitative and a qualitative

mismatch of skills supply and demand. Employment

growth averaging about 3.1% in the past decade lags

behind economic growth currently at 7.7% (excluding

oil) and labour force growth averaging 5.8% in the same

period. As indicated in Figure 2, an estimated 68% of the

labour force are self-employed, thus the prospects of

generating additional jobs or employment opportunities

for the growing youth is very low. The situation is

accentuated by the high population growth rate

(averaging 2.7% in the last decade), a reduction in public

sector jobs and a contraction of private sector jobs. The

lack of structural transformation of the Ghanaian economy has constrained the development of

new productive employment and the efficient utilization of the labour force.

2 COTVET preliminary financing simulation 2010

Source: ESP 2010-2020: Financial Simulation

Projections

Figure 1: Funding for TVET is inadequate

Source: Ghana Employment Policy 2007

3

1.2.3 Ghana has an education system that

eliminates large numbers of youth at two key

transitional levels (Junior High School and Senior

High School). This creates a pool of unemployed and

mostly semi-literate youth with unemployable skills.

Access to TVET as shown in figure 3 is limited

compared to the number of students graduating at JHS

and SHS levels. The enrolment in TVET is projected

to grow by 1% point from 3% in 2012 to 4% in 2020

without the project invention. This growth is matched

by a higher participation rate of 24% and 10% at JHS

and SHS level respectively, further aggravating the

unemployment situation due to the lack of appropriate

skills of the graduates.

1.2.4 The Ghana National Employment Policy (2006) notes that the job market in the

country has limited absorptive capacity. The economy cannot absorb the more than 300,000

students graduating from tertiary institutions annually. The supply side of labour in the country

is exacerbated by the fact that the graduates produced by the TVET system are perceived by

employers to be technically incompetent and unsuitable for the world of work due to the

mismatch between the training and the needs of the labour market. The result has been the

increasing unemployment of university and polytechnic graduates now estimated at 21%. There

is a need to focus on supporting the improvement of the learning environment and increasing

the capacity of TVET institutions to train graduates and empower them to create jobs. This

entails embarking on curriculum review activities that will ensure linkages of the training to the

needs of the private sector and designing and implementing a students’ business model to

enhance entrepreneurial abilities of TVET graduates.

1.2.5 The growth in demand for quality TVET graduates for the services sector is

projected to grow at about 20% in the medium term. The annual employment elasticity for

the agriculture sector is less than a unit (i.e. 0.57) compared to 2.12 and 1.22 for industry and

services sectors, respectively. This growth presents an immense opportunity for economic

growth and employment, particularly in sectors such as tourism, Information Communication

Technology (ICT), light industry based on textile and garments and metallic and non-metallic

minerals. However, employers in Ghana repeatedly cite lack of specific skills as a problem.

Companies and manufacturers claim they do not have the required numbers of skilled workers

and technical personnel needed for increased production. The GoG has embarked on the TVET

reform to urgently address the quality challenge faced in the delivery of TVET. The Bank’s

contribution to addressing this challenge is at the core of the proposed intervention.

1.3 Donors coordination

1.3.1 Donor coordination mechanisms for the education sector in Ghana are strong

and are led by the Government. The Bank is a member of the Development Partners (DP)

supporting the Education Sector Development Plan (ESDP) together with the World Bank,

USAID, DANIDA, JICA, GIZ and DfID. The DPs operate within a SWAp arrangement

supporting the ESDP which is monitored trough the annual Education Sector Reviews. The

leadership of the DPs group is chaired on a rotational basis with common communication

mechanisms. Available budget figures indicate an increasing interest to support skills

development with a number of initiatives started and/or already under way. Table 1.3 presents

Figure 3: TVET enrollments are too low to

support the size of the economy

Source: Ghana Education Sector Development

Plan

4

the ongoing projects funded by the DP’s and the level of dialogue in the TVET sector and show

that the Bank is a lead contributor (53%). For details on the DPs’ focus on the Education

Sector refer to Technical Annex: A2.15.

1.3.2 Critical interventions that focus on improving quality of TVET particularly

supported by the development budget are underfunded. An analysis of the TVET budget

shows that the available funding to the sector amounts to less than 40% of the estimated

USD450 million required for improving delivery of TVET in the Education Ministry alone.

Due to the funding gap for the TVET subsector, critical soft interventions required to reform

the TVET subsector remain unfunded hence the need for more targeted financing.

Table 1.3: Donor Interventions in Skills Development (SD)

II– PROJECT DESCRIPTION

2.1 Project components

The development objective of the project is to support the development of high quality

middle level technical and vocational skills needed in the Ghanaian economy. The project

addresses a key issue of human capital development through increasing the capacity of the

country to produce high calibre technical skills. It has three specific objectives which include:

(i) Expanding equitable access to public institutions targeting females and the rural poor; (ii)

Improving relevance and quality of TVET delivery; and (iii) Improving management of TVET

at the coordination (COTVET) and school based institutional levels. To achieve these

objectives, the project will have the following components as shown in Table 2.1:

Budget Players – Public annual expenditure SD (Average 2011- 2015) – USD millions

Intervention area(s) Donor % Donor

Contribution

Amount

CBT, Capacity Building, Infrastructure Development for TIs and COTVET ADB

53% 124

Informal Sector, CBT, Equipment GIZ (Germany) 9% 21

Master craftsperson training and SDF DANIDA 6% 14.2

CBT, Infrastructure, Equipment for selected TIs; informal sector, studies- Oil

and Gas Capacity Building

World Bank 2% 4.7

CBT, Skills Development Fund, Informal Sector, Studies, Equipment (limited),

Capacity Building- Ghana Skills and Technology Development Project

World Bank 30% 70

TOTAL 233.9

Existence of Thematic Working Groups Yes

Existence of SWAPs or Integrated Sector Approaches Yes

ADB’S Involvement in Donor Coordination Member

5

Table 2.1: Project Components

Nr. Component Component Description

1. Expanding

Equitable Access

to TVET

(Amount:

UA62.12 million)

Sub-Component 1: Increasing the participation of disadvantaged groups in TVET

The subcomponent will finance: A 3 year bursary scheme for each of the 1,550

disadvantaged students with particularly focus on female students and stipends for 2,500

additional apprentices and the development and implementation of a role model program to

encourage female students to join TVET courses offered at both the junior and senior

secondary levels.

Sub-Component 2: Strengthening of teaching and learning environment and the

capacity of TI’s

The sub component will finance: (i) Strengthening of the teaching and learning environment

and the capacities of 13 existing technical institutions (10 TI’s, College of Technology

Education Kumasi –University of Education Winneba and 2 Polytechnics (Takoradi and

Accra); (ii) Supply of modern equipment and inputs (ICT equipment, internet connectivity,

modern teaching aids and sports facilities); (iii) supply of reference textbooks; (iv)

improvement of water supply and sanitation, and the provision of electricity and solar power

systems. The project will specifically support the construction of digital libraries and

Information Technology (IT) centers in all beneficiary schools to supplement government

efforts to mainstream the use of IT for teaching and learning.

2. Building Human

and institutional

Capacity for

TVET

(Amount: UA

4.21 million)

The component will support interventions that aim to build human and institutional capacity

of COTVET and training institutions involved in the delivery of TVET.

The component will finance: (i) refresher training programmes for pedagogy of 200 TVET

instructors (30 % females); (ii) training of 500 master craftsmen to support skills delivery in

the traditional apprentice program; (iii) design and implementation of a management course

for 50 TVET managers of TI (5% female) and master’s degree training of 25 faculty

members (20% female); (iv) provision of 5000 sq meters office space for COTVET; (v)

support the preparation of a costed strategic plan to guide the delivery of TVET; (vi)

strengthening M&E systems and TVET MIS at COTVET; and (vii) training of staff of

COTVET in selected areas of TVET policy, planning, advocacy, budgeting, information

systems, curriculum review and quality control.

3 Component 3:

Improving

quality and

relevance of

TVET

(Amount: UA

7.02 million)

The component will support interventions that aim to improve the quality and relevance of

TVET delivery. The following activities will be funded: (i) the review of curriculum through

expansion of CBT programs to cover three trade areas (i.e. wielding, electronics and plant

engineering, production of training materials); (ii) review of instructor trainers’ curriculum to

align it to the CBT delivery mode and the demand of industry; (iii) development and

operationalization of a mechanism that recognizes prior learning; (iv) development and

operationalization of a national qualifications and accreditation mechanism for training

institutions; (v) support to institutionalization of production units using demand driven

competitive investment grants; (vi) setting up of career guidance and counseling units in

beneficiary institutions and training of core counselors; (vii) development of a system for

tracer studies and their institutionalization at COTVET; (viii) support to institutionalization

of entrepreneurship training through the development and implementation of a student’s

business model.

4. Project

Management

(Amount: UA

4.35 million)

This component will provide the necessary support for the effective implementation of the

project through COTVET. It will finance the development of an impact evaluation mechanism

in the area of financial and non-financial incentives with regard to increasing the participation

of females in TVET. It will also finance operational costs for monitoring of the project,

technical support, audit services, advocacy and communication, marketing, and Mid Term

Review (MTR) and Project Completion Report (PCR) costs.

6

2.2 Technical solution retained and other alternatives explored

The design of the project considered four technical solutions out of which one was retained. The one that was retained presents a coherent, integrated and feasible approach to

dealing with the challenges facing TVET provision in Ghana. It involves the design of a

multi-component investment project that focuses on improving the teaching and learning

conditions of selected institutions. These are distributed regionally and are covering a wider

range of trades, and therefore will produce skilled middle level technicians for more sectors

of the economy including for oil and gas. The solution balances interventions that deal with

the hardware and software constraints to the delivery of formal and informal TVET in the

country. Table 2.2 below shows the three alternatives that were not accepted and the reasons

for their rejection.

Table 2.2: Project alternatives considered and reasons for rejection

Alternative name Brief description

Reasons for rejection

An investment project

that creates a few TVET

centers of excellence

with specialized areas of

study and capacity

building to COTVET.

The alternative involves

establishment of a few centers of

excellence with specialized areas

of study.

The alternative imposes a huge financial burden

for the country given that it covers a limited area.

It does not present a holistic approach to dealing

with the challenges of skills development and does

not adequately address issues of sustainability and

equitable access facing the TVET subsector.

Earmarked Budget

Support to the TVET

subsector.

The financing modality involves

contributing to the budget of the

Ministry of Education

specifically targeting TVET

reform.

The TVET subsector does not have a well-

designed and costed strategic plan already

prepared, through a fully participatory process to

guide the implementation of earmarked budget

support operation.

The monitoring and evaluation framework

required to assure results for a sector budget

support operation is still weak and may not

support a successful implementation of an

earmarked budget support operation.

Contribution to the Skills

Development Fund

(SDF)

The financing modality involves

contributing to the SDF already

funded by World Bank and

DANIDA and subscribing to the

same guidelines and standards of

the fund. The SDF supports soft

intervention for the TVET

reform through a demand driven

mechanism.

The SDF does not support the breadth of policy

interventions required to enhance the improvement

of access, quality and relevance of TVET (for

example school infrastructure).

GoG decided to evaluate the effectiveness of the

first phrase of SDF before considering expansion

of the SDF. This would have pushed the

implementation of the project to a later period

against the urgent need to address the challenges

faced by the TVET subsector.

2.3 Project type

This specific investment project will assist in financing the implementation of an agreed

reform to increase access and quality of TVET delivery in Ghana. Government policy

allows three types of operations: (i) general budget support; (ii) sector budget support; and

(iii) investment projects. The option of an investment project implemented within the existing

SWAp arrangements was the favoured choice for the GoG since the DSIP is a well-targeted

and focused operation. Given its clear focus and design to deal with specific constraints and

7

deliverables to TVET, the GoG considers that this project offers a most efficient and effective

tool to attain the sector objectives. The project mode guarantees that earmarked resources will

be used for the intended purpose, hence it is deemed to be the most feasible and practical

option. The existing capacity and institutional arrangements are fully operational and

effective to manage the project.

2.4 Project cost and financing arrangements

2.4.1 The total project cost is estimated at UA 77.7 million. This amount is net of taxes

and duties, of which UA 55.4 million (71%) is in foreign currency and UA 22.3 million

(29%) is in local currency. The cost estimate includes a 7% physical contingency for works

category. Price escalation has been calculated based on a 2.5% annual price increase for

foreign currency and 3.0% for local currency throughout the five-year implementation period

for all categories of expenditure. For the purpose of costing, all items have been priced in

United States Dollars and converted into UA at the exchange rate applicable for the month of

November 2011. A summary of the costs by component of the project is presented in Table

2.4 (a).

Table 2.4(a): Summary of Project Costs by Component

2.4.2 The project will be financed by an ADF loan, ADF Grant and GoG will

contribute 10% of the total project cost. ADF financing will amount to UA 70 million

(USD 112.06 million) of which UA 45 million will be an ADF loan, and UA 25 million an

ADF grant. GoG will contribute UA 7.7 million (USD 12.33 million) as indicated in Table

2.4 (b). The ADF Loan will finance 58% of the total project costs, and will comprise UA 41.1

million in foreign exchange, representing 52.9% of total project costs, and UA 3.9 million in

local costs, representing 5.1% of total project costs. The ADF Grant will finance 32% of the

total project costs, and will comprise UA 14.3 million in foreign exchange, representing

18.4% of total project costs, and UA 10.7 million in local costs, representing 13.8% of total

project costs. All foreign exchange requirements of the project will be borne by the ADF

funds. The GoG's contribution of UA 7.7 million in local costs, representing 10% of the total

project costs, will partially finance the categories of expenditure for works (11.2%), goods

(4.1%), services (6%) and operating costs (29.9%). For details on categories of expenditure

per component and activities to be funded by the loan, grant and GoG see Technical Annexes

section B2.17 to 19 and Annex C3, respectively. Tables 2.4 (b), 2.4 (c), 2.4 (d), 2.4 (e) and

2.4 (f) present the sources of financing, project costs by source of finance, summary of

project costs by category of expenditure, sources of finance by category of expenditure and

expenditure schedule respectively.

COMPONENT

Millions UA

Foreign

Exchange

Local

Costs

Total

Costs

% F.E.

1 - Expanding Equitable Access to TVET 44.83 11.82 56.65 79%

2- Building Institutional & Human Capacity for TVET 2.53 1.32 3.85 66%

3 - Enhancing Quality of TVET Delivery System 1.06 5.37 6.43 16%

4 - Strengthening Project Management and Coordination

Framework

2.02 1.96 3.98 51%

Total Base Cost 50.44 20.47 70.91 71%

Physical Contingency 3.50 1.25 4.74 74%

Price Contingency 1.50 0.54 2.03 74%

Total Project Cost 55.4 22.3 77.7 71%

8

Table 2.4 (b): Sources of Finance (UA million)

Table 2.4(c): Project cost by source of financing by Component

Table 2.4(d): Summary of Project Costs by Category of Expenditure

Table 2.4(e): Sources of Finance by Category of Expenditure (UA million)

SOURCE Foreign

Exchange

Local Costs Total Costs %

ADF LOAN 41.1 3.9 45.0 58%

ADF GRANT 14.3 10.7 25.0 32%

GOG 0.0 7.7 7.7 10%

TOTAL 55.4 22.3 77.70 100%

COMPONENT

ADF Loan ADF Grant GOV TOTAL %

Comp

F.E L.C Total F.E L.C Total Local

Costs

F.E L.C Total

Costs

1 - Expanding Equitable

Access to TVET

36.73 2.97 39.69 12.54 4.80 17.34 5.09 49.26 12.85 62.12 80%

2- Building Institutional

& Human Capacity for

TVET

2.18 0.73 2.91 0.60 0.30 0.90 0.40 2.78 1.43 4.21 5%

3- Enhancing Quality of

TVET Delivery System

0.00 0.00 0.00 1.17 5.05 6.23 0.79 1.17 5.84 7.02 9%

4- Project Management 2.21 0.19 2.40 0.02 0.52 0.53 1.42 2.22 2.13 4.35 6%

Total 41.12 3.88 45.00 14.3 10.67 25.00 7.70 55.44 22.26 77.70 100%

CATEGORY OF

EXPENDITURE

Millions UA

% T.C.

% F.E. Foreign

Exchange

Local Costs Total Costs

A. Goods 11.4 2.12 13.54 17% 84%

B. Works 33.23 8.08 41.30 53% 80%

C. Services 4.89 3.41 8.30 11% 59%

D. Operating cost 0.91 3.53 4.44 6% 21%

E. Miscellaneous 0.00 3.34 3.34 4% 0%

Total Base Cost 50.44 20.48 70.93 91% 71%

Physical Contingencies 3.50 1.25 4.74 6% 74%

Price Contingencies 1.50 0.54 2.03 3% 74%

Total Project Cost 55.44 22.26 77.7 100% 71%

CATEGORY OF

EXPENDITURE

ADF Loan ADF Grant GoG TOTAL %

Cat. F.E L.C T.C F.E L.C T.C L.C F.E L. C TC

A. Goods 0.00 0.00 0.00 12.55 1.69 14.24 0.61 12.55 2.31 14.86 19.1

%

B. Works 36.51 3.69 40.21 0.00 0.00 0.00 5.09 36.51 8.78 45.29 58.3

%

C. Services 4.60 0.19 4.79 0.77 2.95 3.72 0.57 5.37 3.71 9.08 11.7

%

D. Operating cost 0.00 0.00 0.00 1.00 2.40 3.41 1.43 1.00 3.83 4.84 6.2%

E. Miscellaneous 0.00 0.00 0.00 0.00 3.63 3.63 0.00 0.00 3.63 3.63 4.7%

Total 41.12 3.88 45.00 14.32 10.67 25.0 7.70 55.44 22.26 77.7 100%

9

Table 2.4 (f): Expenditure schedule by component (UA million)

Component Year 1 Year 2 Year 3 Year 4 Year 5

1 - Expanding Equitable Access to TVET 0.00 13.84 28.38 18.22 1.48 62.12

2- Building Institutional & Human Capacity for

TVET

1.08 1.74 1.35 0.03 0.02 4.21

3- Enhancing Quality of TVET Delivery System 1.92 2.32 1.07 1.43 0.60 7.02

4- Project Management 1.02 0.79 0.80 0.84 0.83 4.35

Total Project Cost 4.0 18.7 31.6 20.6 2.83 77.7

Note: Exchange rates are provided in the introduction of this report (page (i))

2.5 Project’s target area and population

2.5.1 A broad scope of beneficiaries is targeted by the project in all the regions of

Ghana. The project will cover 10 out of the 38 technical institutions, 2 polytechnics and the

College of Technology Education Kumasi – University of Education Winneba under the

Ministry of Education. The targeted institutions are evenly situated at various regions of the

country and were selected on the basis of regional and rural balance. Initially, the principal

beneficiaries of the project will be the current and future students in the TI’s currently

estimated at 15,694 of which 34% are female and are estimated to increase to 21,967 by 2014

(40% female) in the medium term in the beneficiary schools. The students will benefit from

improved teaching and learning conditions which will enhance their probability of being

employed and or create their own enterprises.

2.5.2 Other beneficiaries of the project include the families of all students, the teaching

staff and prospective employers. The families of students who succeed in completing their

studies in the TI’s will have enhanced possibilities of increased lifetime earnings. Twenty

five (25) instructors (5 PhDs and 20 Masters) at the Kumasi College of Education

Technology and 200 instructors and 50 senior managers in TI’s will have their skills

upgraded. Employers and industries will benefit from the strengthened capacity and improved

quality of TVET delivery by having access to high caliber labour that will be graduating from

the institutions.

2.6 Participatory process for project identification, design and implementation

2.6.1 The project has been developed through an extensive participation of key

stakeholders. Throughout the stages of identification, preparation and appraisal of the

project, the project team consulted widely with the view to enhancing ownership of the

project. The participation and input from representatives of the Ministry of Finance,

COTVET, Ministry of Education and all the beneficiary institutions, Ministry of Local

Government, Ministry of Labor and Welfare, Civil Society, selected Private Sector Operators

and other Development Partners was ensured. There was wide support for the project at all

levels. All 13 beneficiary institutions were visited and needs assessments were undertaken.

During the needs assessments and field visits, extensive discussions were carried out with the

management of the institutions, staff and the students. Presentations on the development

plans and site plans of each institution were made to the project team, and the data obtained

was incorporated in the design of the project.

10

2.6.2 The participatory approach was reinforced by the involvement of the beneficiary

institutions and COTVET in the design of the project. The project was discussed during a

workshop that was attended by the principals and by the programme heads of the different

institutions, during which the proposed designs of the buildings and the components of the

project were discussed and validated. This participatory approach will be maintained

throughout project implementation.

2.7 Bank Group experience, lessons reflected in project design

2.7.1 The implementation of the three previous education sector and other projects in

the portfolio funded by the Bank has resulted in valuable lessons. The implementation

and outcomes of the education projects in particular and other projects in the portfolio have

been rated as satisfactory. Education projects have contributed to increasing access to

secondary education by up to 40% and improving quality in beneficiary schools through the

provision of refresher courses to 3,656 core subject teachers. This figure represents 60% of

the total core subject teachers at the SHS level. The PCR for the Education II project and

progress reports of other projects in the portfolio highlight four key lessons: (i) the

identification of user needs is crucial to designing a comprehensive project that addresses all

crosscutting issues including gender, social, economic and environmental aspects; (ii) full

involvement of the executing agency and beneficiary institutions in the design and

implementation of project activities is critical to ensuring realization of quality output and

sustainability of outcomes; (iii) the existence of a mainstreamed stable and effective project

management team is crucial; and (iv) extensive supervision of the project activities by the

Bank, Ministry of Finance and the Project Coordination Unit coupled with the empowering of

the heads of the beneficiary institutions and their staff to monitor progress is the key to

successful project implementation. These lessons as well as the experiences gained from

interventions funded by other development partners have been incorporated in the design of

the proposed project.

2.7.2 The incorporation of lessons learnt in the design of the project was done through

several steps. The design ensured that: (i) key stakeholders, for example COTVET and TI’s,

participated fully in all stages of developing the project; (ii) all project activities are fully

harmonized with activities funded by other DPs; (iii) a thorough needs assessment to

determine the needs of individual institutions was done before appraisal of the project to

enhance effectiveness of the limited funds; (iv) all preparatory activities that will ensure

quick disbursement of the project were discussed and agreed with the Government and a

mechanism for tracking their completion before the commencement of project activities was

put in place; (v) the implementation of the project is mainstreamed in COTVET; and (vi) the

agreed monitoring and evaluation (M&E) system of the project incorporates mandatory

monthly site meeting that will be attended by all stakeholders. The heads of institutions or

their authorized representatives will be involved in the approval of certificates for works and

acceptance certificates for goods and services. This will ensure quality of the outputs,

ownership of project activities and the sustainability of results.

2.8 Key performance indicators

The key indicators of the project are aligned with those of the National Development

Plan, ESDP, the CSP for Ghana and the work plan for the reform of TVET. The key

performance indicators for monitoring progress in achieving the project objectives are

described in the project logical framework. These indicators will also form part of the

11

Strategic Plan for TVET to be prepared as part of this project. These include output indicators

such as the number of institutions whose learning environment is improved, number of

instructors trained, establishment and operationalization of the national qualification and

accreditation framework. The outcome indicators include the percentage of students

qualifying from TVET institutions with the requisite skills disaggregated by gender; the

percentage of graduates employed within six months of completing their training and the

percentage of students setting up their own enterprises at completion of their courses.

III – PROJECT FEASIBILITY

3.1 Economic and financial performance

3.1.1 The project has positive economic benefits. Investments in TVET in Ghana have a

positive Net Present Value (NPV). The NPV at a 10% discount rate is USD 63,866,126. The

Internal Rate of Return (IRR) of the project is 20.2%. The NPV and IRR were calculated on

basis of a continuation of the policy that encourages parents to contribute to the delivery of

TVET. Shocks applied to the financial simulation through application of more conservative

assumptions. For example, an application of a 50% reduction in the tuition level and

compensation to graduates still yielded a positive NPV. Refer to section B.7 of the Technical

Annexes for the key underlying assumptions of the financial simulation model.

3.1.2 The project will contribute to enhancing the development prospects of the

country. From a development prospects perspective, the project has two key factors that will

contribute to the economic outcomes of the country. The project will enhance Ghana’s ability

to implement its Local Content laws (for example for oil and gas and other sectors that

require high caliber skills). At the moment, due to inadequate supply and quality of labour,

investors have to import this highly skilled labour. This scenario has two key effects; (i) it

reduces the benefits from the productive sectors to the population and the economy and (ii)

reduces the capacity of industry to upgrade technology due to lack of technicians familiar

with new technologies. Weak human capital with low skills constrains the ability of workers

to acquire new skills as markets change and thus slows down both investment and market

adjustment to new technology.

3.1.3 The project will enhance business and technological innovation by improving the

capacity of workers. The qualitative improvements in the training offered in the TIs by the

project will enable the workers who will go through the improved courses to apply and adapt

existing as well as new technologies and processes. Therefore the outcomes of the project

will not only lead to higher worker productivity, but may significantly enhance the flexibility

and efficiency of the labour market to use new technologies. The Ghanaian economy

currently suffers from low productivity of the workers as a result of the ineffective skills

training mechanisms. This productivity deficiency and a cause of non-competitiveness of the

economy will be mitigated by the conscious investment in TVET that the proposed project

will provide.

3.2 Environmental and Social impacts

3.2.1 Environment: The project is classified as category II according to the Bank’s

environmental guidelines and an Environmental and Social Management Plan (ESMP)

has been prepared. The activities to be implemented under the project include new

construction and rehabilitation of workshops, laboratories, libraries, lecture theaters,

12

dormitory facilities and toilet facilities at the 13 beneficiary institutes and the construction of

an office block at COTVET. The information provided in the ESMP includes mechanisms for

identifying adverse environmental and social impacts associated with the implementation of

activities supported by the project. It also contains measures that need to be taken to mitigate

the adverse impacts and actions that can assist in improving the physical and social

environment of the institutions. Appendix VI gives the Environmental and Social

Management Plan’s (ESMP) summary.

3.2.2 Climate Change: Several measures are envisaged under the project to alleviate the

likely impact on climate change and address capacity challenges in this area. These

include: (i) promoting the use of sustainable building technologies, reducing the impact on

the environment and reducing recurrent costs; (ii) incorporating sustainable measures

appropriate for the different regions in standard designs for civil works; (iii) using design

consultants who are knowledgeable in sustainable building technology and institutions; (iv)

building capacity in sustainable development and specific areas such as waste management,

recycling, sanitation and the use of sustainable technologies; and (v) incorporating climate

change aspects like energy conservation, the design of buildings that are energy efficient, and

the use of building materials that have less impact on climate change in the revised

curriculum for TVET. The review will also ensure the coverage of water conservation and

renewable energy education for all TVET trades.

3.2.3 Gender: The GoG is firmly committed to gender equality. The constitution of

Ghana enshrines gender equality and an ambitious legal reform process is supported by the

GoG. However, the enforcement of relevant provisions in the constitution and passing of

enabling laws to ensure the full participation of women still remains a challenge. The

Ministry of Education has managed to mainstream gender equality more effectively in other

subsectors, but the challenge still remains with respect to increasing the enrollment of female

students in the science related courses. Female enrolment stands at 26% for engineering and

17% for applied science courses. Except for the pre-primary level, enrolment of girls is lower

than that of boys at all levels of the formal education system. At the primary, middle and

secondary levels, girls make 48.7%, 47% and 44.7% of the net enrolments respectively.3 The

share of girls is even lower in the technical vocational training and at the tertiary level as it

accounts for only 34% of the total enrollment.

3.2.4 The project will contribute to reducing the gender disparity that

disproportionately affects women’s employability in the formal sector. It is estimated that

a total of 150,000 JHS annual graduates do not have an opportunity either for formal

education or for training; the majority of these are girls. Evidence suggests that the area of

skills development has been neglected for many years and many of the trainees come from

needy families. Reasons given for the lower level of participation of females in the formal

education system compared to males include: inadequate number of schools in rural areas

with the attendant problem of long distances to schools, parental reluctance to send girls to

school in some regions, shortage of female teachers especially at the secondary and technical

education levels especially in science related courses to act as role models for girls and early

marriages. Ensuring a reduction in the constraints to the participation of females in TVET are

at the core of the DSI project.

3 Source : 2009/10 Statistics, Education Sector Performance Report September 2010, Ministry of Education

(Ghana)

13

3.2.5 The project takes account of interventions that aim to increase and sustain the

participation of female at all levels of education. As provided for by the Education Sector

Development Program (ESDP), to increase the number of schools, the project contributes to

increasing the scope of interventions aimed at to increasing the participation of girls at all

levels of education especially in rural areas. This involves increasing participation of females

in TVET by expanding intakes as well as reducing walking distances through the provision of

boarding facilities in the beneficiary institutions. Boarding facilities especially for girls will

improve the school environment and reduce the risk of exposure while they walk long

distances to school. This will encourage parents to be more likely to allow girls to attend

school when the distance to travel is relatively short.

3.2.6 Other measures taken to improve access of girls to education include the

provision of separate sanitary facilities. The project will provide a bursary scheme that will

target increasing female students in male dominated trades at TVET level. To sustain the

flow of female students a role model program will be funded by the project at the JHS and

SHS levels to encourage female students to opt for TVET related courses. This will increase

the number of female students and teachers at TVET level, which will act as an incentive for

female learners to aspire to higher levels of learning. At present, only 2% of the faculty

teachings at the technical institutions, particularly in male dominated courses, are females.

3.2.7 Social: Technical and vocational education contributes to social transformation

and development. International studies confirm that technical education produce significant

social benefits and acknowledge that it is essential for both personal success and economic

growth. It can bring better job opportunities, higher earnings, and even improved health. It

promotes democracy and sustainable growth, making the potential for social participation of

students substantial. Technical institutions play a major role of technology infusion,

innovation and application and thus can contribute to the intellectual, social, cultural and

economic development of societies and communities.

3.2.8 The project supports the GoG’s commitment to increasing access to and

improving the quality and relevance of TVET as an instrument for poverty alleviation.

Poverty and education are highly correlated with poverty being both the cause and effect of

low levels of education. Currently 50.65% of students at TVET level are from the rural

areas. Families have to contribute an average of USD 500 to both recurrent and development

expenses. Consequently, it is estimated that about 40% of the children from poor households

dropout of TVET due to financial reasons. The project will contribute to the provision of a

proportion of the resources that will assist the TIs cover some of the development costs. This

will reduce in the cost of TVET in the beneficiary institutions thus enhancing its social

impact on the society particularly the poor.

3.2.9 The project will also provide bursaries for female students and those from poor

households to increase their participation in TVET. This will increase their probability of

increased life time earnings. Those who successfully complete their training will have the

skills to serve the growing industry. They will become educated fathers and mothers, who

would, in turn, educate their own children. They will be tax payers, instructors in institutions,

extension workers to communities, managers of private sector activities as well as support the

creation and timely application of new knowledge. The project will also finance the

provision of Information and Education Communication (IEC) materials and setting up of

guidance counseling units at the institutional level to increase awareness of HIV/AIDS and

thus reduce its prevalence among the students and the instructors.

14

3.2.10 The project will have a direct impact on employment in the short, medium term

and long run. In the short run, the project will generate an estimated 1,600 jobs for

engineers, technicians and laborers. In the medium term, the project will generate an

estimated 1,060 jobs for lecturers, instructors, workshop assistants, master craftsmen and

internal verifiers. In addition, due to the quality of the graduates and the focus on

entrepreneurship, there will be more opportunities for creating individual small scale

businesses and jobs. The details on the potential job are provided in table 7.2 in Technical

AnnexB7.

3.2.11 Involuntary resettlement: There will be no people who will be displaced by the

project. The activities supported by the project will be taking place in already existing

institutions.

IV – IMPLEMENTATION

4.1 Implementation arrangements

Institutional Arrangements

4.1.1 The implementation arrangements of the project are mainstreamed into

COTVET which is the Executing Agency (EA). COTVET will be responsible for efficient

management of all project activities. COTVET has a Project Support Unit (PSU) mandated to

handle all projects in the TVET subsector, including the proposed DSI project. The capacity

of COTVET to implement the project has been assessed and found to be satisfactory based on

the compliment of staff in the PSU. The technical staff of the PSU comprises a project

Coordinator, who reports to the Executive Director of COTVET, a Procurement Specialist,

Monitoring and Evaluation (M&E) Specialist, Financial Management Specialist, Project

Accountant and Project Assistants. The PSU team will be strengthened by the recruitment of

a National Technical Assistant to support the implementation of the soft components, an

Architect, Civil Engineer and a Quantity Surveyor who will be responsible for the civil works

and also support with the procurement functions. In addition, the following support staff will

be added; a Project Accountant, a Procurement Assistant, an M&E Assistant, an

Administrative Secretary and Drivers.

4.1.2 The Executive Director of COTVET will oversee the execution of the project.

This will include approving work plans and reviewing progress, as well as ensuring that the

PSU and TIs responsible for the implementation of the project carry out their duties. The PSU

coordinator, under the direction of the Executive Director of the COTVET, will be

responsible for the implementation of the operational activities related to the project,

including preparation of work plans and progress reports and supervision of the project staff.

The Training of Trainers (ToT) sub components of the project will be implemented in close

collaboration with the institutions. TI’s and polytechnics will fully participate in the planning

and implementation of the training activities.

4.1.3 The Project Steering Committee (PSC) of the COTVET Board will be

responsible for Policy and operational oversight of the project. The composition of the

PSC includes all stakeholders as defined by the ACT 178 that established COTVET. In order

to reinforce stakeholder participation, two (2) representatives of the Ministry of Finance and

one (1) from each of the beneficiary institutions will be co-opted to the PSC. The TIs will

15

also participate in the quality control of civil works, specification of equipment, training

programmes and selection of beneficiaries for the training of lecturers. In addition, they will

provide technical support in the preparation of work programs, selection of candidates for

training, bursaries and monitoring the implementation of construction activities.

Procurement Arrangements

4.1.4 All procurement of works, goods and services financed by the Bank will be in

accordance with the Bank's Rules, using the relevant Standard Bidding Documents.

These include the Rules of Procedure for Procurement of Goods and Works or, as

appropriate, Rules of Procedure for the Use of Consultants. COTVET will be responsible for

the procurement of goods, works and services. The Ghana national procurement system will

be used for National Competitive Bidding (NCB) contracts provided the identified deviations

in the Procurement Act and national Standard Bidding Documents (SDBs), including the

modalities are carried out through a side letter (Annex III) to the financing agreement of this

project. COTVET shall prepare a Procurement Plan

acceptable and submit it to the Bank

before presentation of the project to the Board. The procurement arrangements for the project

are summarized in table 2.8 of Appendix V of this Project Appraisal Report (PAR) and the

details are provided in Technical Annex B5.

4.1.5 The GoG will request advance contracting (AC) of works, goods and services to

accelerate the implementation of the project. AC will be limited to procurement of the

construction of COTVET’s office block and related furniture, recruitment of design and

supervision consulting firms, training firms and implementation Technical Assistants, and a

consultant for the preparation of the operation manual.

Financial Management Arrangements

4.1.6 Project financial management will be the responsibility of the Project Support

Unit (PSU) already established by existing donors (the World Bank, DANIDA) within

COTVET. Supporting the Project Coordinator in the PSU is a Financial Management

Specialist, an Accountant, and an Internal Auditor (to be hired). Additional FM staff will be

considered as the number of donors (and thus possible activities) increases. Sun accounting

software system has been installed for the PSU, and staff will be trained on the software.

4.1.7 The assessment of the PSU concluded that there is not sufficient capacity to meet

the accounting and reporting requirements of the proposed project. A detailed

assessment of the staff requirements revealed that additional financial management (FM)

staff, and separate accounting software for use by the project are required. In an effort to

address the FM capacity, COTVET has hired a Director of Finance and Administration. It

will need time to develop its in-house Finance Department, staff it, and develop acceptable

procedures and systems. The existing donor projects include a COTVET capacity building

component to help achieve this. The Bank will monitor these developments and take

appropriate action to safeguard the project’s resources if required.

4.1.8 Three disbursement methods will be used by the project. These include: (i) the

special account method, (ii) the direct payment method, and (iii) the reimbursement guarantee

method. The Special Account method (SA) shall be used for payments of goods, services and

operating costs, while Direct Payments shall be used for payments under the works, services

and goods category. The reimbursement guarantee method will be used for imported goods in

16

case the suppliers choose to complete the transaction by way of letter of credit. The USD

Special Account will be opened specifically for the project in a commercial bank acceptable

to the Bank and will be managed by the PSU, which is already managing the Special Account

for the funding from the World Bank. The PSU will also open a local currency (Ghana Cedi)

Project Account to support the operation of the Special Account and facilitate payments in

local currency. In addition, a Ghana Cedi account will be opened to house the counterpart

contribution. All disbursement will follow the procedures outlined in the Bank’s

Disbursement Handbook.

4.1.9 An initial deposit for an amount corresponding to six months of activities as

justified by a work program approved by the Bank will be made in the SA. Subsequent

replenishments of the SA will be subject to the PSU having provided sufficient justifications

for the use of at least 50% of the previous deposit and upon production of an agreed work

program for the following six months in line with the Bank’s disbursement rules and

procedures. To ensure adherence to agreed financial regulations, the special accounts will be

monitored by the ADF financial supervision and AUDIT missions.

4.1.10 The Ghana Audit Service (GAS) will be the statutory auditor of the project.

However the GAS outsources the audit of donor projects to private audit firms. Thus an

auditor for the project will be selected based on Terms of Reference (TORs) to be agreed

between the participating donors (currently the WB, DANIDA, and the AfDB), so that the

PSU has only one auditor for all the different participating financiers at any one time. The

PSU will ensure that the audited project financial statements, inclusive of the accompanying

audit management letter, will be submitted to the Bank annually within 6 months after the

end of the preceding financial year.

4.2 Monitoring

4.2.1 COTVET will be responsible for monitoring and evaluation of project activities.

It will submit to ADF Quarterly Project Progress Reports (QPPR) in accordance with the

established format covering all aspects of the project and agreed actions in the ESMP, within

30 days following the end of each quarter. The QPPR will cover progress measured against

indicators in the project log frame. The project management will also prepare and submit a

project completion report in accordance with the format recommended by ADF. Additional

reports and clarifications will be submitted to the Fund as required.

4.2.2 The GoG monitoring system will be complemented by supervision missions

conducted by the Bank. To assess progress and provide implementation support, the Bank

will conduct at least two supervision missions per year. A mid-term review will also be

conducted after two years to evaluate progress. ADF will be responsible for undertaking the

review in collaboration with the COTVET and TIs. A participatory approach will be built

around the relevant institutions of Government supported by the Ghana Field Office in the

review process. The Ghana Field Office will support the implementation of the project. Table

4.2 presents the main monitoring milestones for the implementation of the projects.

17

Table 4.2: Monitoring Schedule

Timeframe Milestone Monitoring process / feedback loop

June 2012 Commencement of the strengthening of

the Executing Agency with additional

staff.

Field supervision reports, final design document

and tender document for advance procurement.

January

2013

Project is launched. Launching mission is organized with adequate skills

mix.

March 2013 Preparation of the strategic plan for

TVET begins. Approval of selection

criteria for Traditional Apprentice, master

craftsmen and verifiers, academic

programs for upgrading of lecturers

begin.

Inception report for preparation of the strategic

plan, the enrolment of the first batch of instructors

for training students, and approved selection

guidelines.

May 2013 Technical architectural detail and tender

document issued.

Field supervision reports, final design document

and tender documents.

October

2013

Construction begins. Construction contracts with the contractor.

April 2015 Construction completed. Quarterly Progress Reports

Supervision missions.

June 2015 Equipping the TI’s completed. Quarterly Progress Reports

Supervision missions.

December

2017

Project completed. Last Quarterly Progress Reports, PCR mission and

audit.

4.3 Governance

The Bank’s experience in implementing projects in Ghana has shown that the

governance practices and control systems in place are satisfactory. In each of the projects

financed, the procurement and the financial procedures required by the Bank as well as the

management of the contracts have been observed by the project management units. The audit

and supervision reports of the on-going education project have not reported any major

irregularities that would compromise fiduciary assurance. In this project the Bank’s

supervision and audit system will be proactive throughout the implementation period and will

provide the desired guidance on improvements in internal control systems. The executing

agency will also have an internal auditor to provide sound advice on financial management.

4.4 Sustainability

4.4.1 The probability of sustaining outcomes of the project is high. The sustainability of

project outcomes is enhanced by five factors as discussed below. The project is owned by the

political leadership and the beneficiary institutions. The level of ownership is high because

the project supports the priority of the GoG in the area of investing in human capital. It is part

of the national TVET reform agenda and is captured as in the reforms work plan. The design

of the project has extensively involved the beneficiary institutions and thus reduced the level

of information asymmetries which is a key factor in assuring the quality of outputs and their

sustainability. The fact that GoG considers skill development to be at the core of facilitating

economic growth and poverty alleviation and its placing of the TVET sector high in its

development agenda gives confidence that the project will be fully supported and sustained

by the Government.

18

4.4.2 The strengthening of the capacity of COTVET in the key areas of policy

formulation and quality control will guarantee the sustainability of TVET investments.

A well-functioning COTVET will contribute to ensuring improved quality teaching and

graduates leading to improvement of the image of TVET. As a consequence of the production

of high caliber graduates through enhanced quality control mechanism, the external

efficiency of the TVET system will be assured thus leveraging the participation of industry

and the private sector which are both the main demanders of graduates as well as a key

source of funding. In addition, the recognition of prior learning will enhance the

inclusiveness of the TVET delivery system and make it attractive to those in the informal

sectors of the economy. The proposed project has included the support to building of the

capacity COTVET to perform its core roles as a major component because of its importance

to ensuring quality and relevance thus sustainability of future TVET investments.

4.4.3 The project supports GoG’s efforts to stamp out the mismanagement of TVET

institutions. Mismanagement of TVET institutions is one of the key causes of the failure to

maintain existing facilities. To deal with matter, the project will fund capacity building

activities at the institutional level. These will include the development and delivery of

management training for Managers of public institutions in areas related to

developing/managing demand driven technical training, fostering, human resources

management, budgeting for maintenance activities, institutionalization of production units in

all TI’s and maintaining linkages with industry. The institutional development activity was

included in the project to ensure that the investments in beneficiary institutions are sustained

over a longer period of time.

4.4.4. The training institutions generate adequate recurrent costs to maintain the

facilities constructed under the project. The project will generate an estimated recurrent

cost of about 1.0% of the capital investment amounting to about USD 54,700 on average per

beneficiary institution, starting in the third year after completion of the construction.

Financial simulation based on data collected during the need assessment from the beneficiary

institutions and projected increase in capacities due to the projects’ interventions indicates

that each beneficiary institution will generate a total of about USD 170,000 per year from

internal sources of funds alone. In addition, Government has already approved an increase in

the share of TVET of the total education budget from 1% to 1.5% on account of providing

funding for recurrent expenditures in TVET institutions. Based on the aforementioned, it can

thus be concluded that the institutions will have the capacity to meet the recurrent costs

generated by the project. The rehabilitation activities of the project in addition to the

sustainable construction designs will significantly reduce the costs of maintenance in the first

five years. On the other hand, instructor salary costs that will accrue due to the expansion of

programmes at institutional level will be provided by GoG’s recurrent budget according to

the number of students and thus does not constitute a major sustainability risk.

4.5 Risk Management

During the project formulation process, a thorough assessment of potential risks was

conducted. The project builds on lessons learned from the five previous operations by the

Bank in the Education sector to present including mapping of risks. The potential risks and

mitigation measures are shown in Table 4.5 below.

19

Table 4.5 Risks and Mitigation Measures

Risk Rating Mitigation Measures

Likelihood that the cost of the

replacement and maintenance of project

physical inputs will rise.

M MoE Strategic Plan provides an integrated financial

framework in which both the capital expenditure required for

the program components and the associated recurrent cost

implications are taken into account. The DSIP recurrent costs

will work within the integrated financial framework.

Unstable inflow of students (female and

male) with the required grades.

M Institutionalization of career guidance and role model

programs at JHS and SHS level and implementation of the

teacher improvement intervention. The provision of

scholarship incentives and boarding facilities for female

students to join TVET will encourage more participation of

female and students from poor households.

Possible delays in expansion of

COTVET to reflect the institutional

plans and staff needs necessary to

facilitate its role.

M The Project has a provision for technical assistance services to

augment COTVET technical capacity to perform some of its

key roles at the beginning.

Cost overruns due to delays in

implementation of construction

activities resulting in reduction of

outputs.

L The appraisal process ensured that the designs and other

preparation activities that may cause delay are finalised before

approval of the project by the Board, thus mitigating the cost

of price escalation to the project since implementation will

begin as scheduled.

Delays in operationalization of the

NQF and the legal framework for

Registration and Accreditation.

M The draft accreditation laws and qualification framework has

been drafted in advance of project approval by the Board. In

addition the establishment for NQAF and its secretariat has

been approved by public service and the filling of the position

is under way.

Note: “M”: moderate; “L: low”

4.6 Knowledge building

The project will contribute to knowledge building in the country and for the Bank. The

project will finance key interventions that will contribute to building knowledge in the area of

TVET. These interventions include; the review of the instructors’ curriculum, the preparation

of the strategic plan for TVET, tracer studies, the strengthening of the M&E system and the

impact evaluation of the financial, and non-financial incentives with regard to addressing

female enrolment at TVET. The successful completion of the above interventions and an

impact evaluation will generate knowledge particularly on what works and what does not

with regard to access to TVET particularly of females. In addition, the training particularly at

masters and PhD level will enhance the research capacity of beneficiary institutions to

generate new knowledge. Similarly, knowledge gained from the project will be valuable for

the design and implementation of future Bank and GoG TVET programs.

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Financing instrument and conditions

The financing instruments proposed are a Loan and a Grant. A Loan Agreement will be

signed with the Republic of Ghana for the Loan and a Protocol of Agreement will be signed

for the Grant.

5.2 Conditions associated with Bank’s intervention

A. Conditions Precedent to Entry into Force of the Loan and the Protocol of

Agreement

20

5.2.1 The Loan Agreement of the project shall enter into force upon the fulfillment of the

Borrower of the provisions of section 12.01 of General conditions applicable to loans.

5.2.2 The protocol of Agreement shall enter into force upon signature.

B. Conditions Precedent to First Disbursement

5.2.3 The obligations of the Fund to make the first disbursement of the Loan and Grant shall

be conditional upon entry into force of the Agreement in accordance with Section 4.01 and 3.01

of the Loan agreement and Protocol of agreement and upon the Government of Ghana

submitting evidence in form and substance satisfactory to the Fund of:

(i) The opening of two foreign currency accounts and a local currency account

(the “Special Accounts”) in a bank acceptable to the Fund to receive the

deposit of proceeds of the loan and the grant;

(ii) The opening of two separate local currency accounts in a bank acceptable to

the Fund to receive the counterpart contribution to be provided by the

Recipient.

C. Other Condition

5.2.4 The Government of Ghana shall submit to the Fund, not later than June 2013

satisfactory evidence acceptable that two (2) representatives of the Ministry of Finance and

Economic Planning and two (2) from the beneficiary institutions have been co-opted to the

Project Steering Committee.

D. Undertaking for the Loan

5.2.5 The Borrower shall undertake to submit, by December 2014, a Confirmation Letter

attesting that the staff establishment of COTVET has been increased by sixteen (16) officers

to support the operationalized qualification and accreditation secretariats.

5.3 Compliance with Bank Policies

This project complies with all applicable Bank policies. The proposed project is consistent

with the Bank’s education sector policy and its Higher Education and Science Technology

Strategy. It is also in line with the Bank Group’s Country Strategy Paper for Ghana.

VI – RECOMMENDATION

The proposed project will help meet key challenges of the TVET subsector by

contributing to increasing equitable access and improving quality and relevance.

Management therefore recommends that the Board of Directors approve the proposed loan of

UA 45 million and Grant of UA 25 million to the Government of Ghana for the purposes and

subject to the conditions stipulated in this report.

21

Appendix I: Ghana’s comparative socio-economic indicators

Social Indicators

Ghana

Africa Developing

countries 1990 2011 *

Area ( '000 Km²) 239 30,323 80,976

Total Population (millions) 14.8 25.0 1,044.3 5,732.2

Population growth (annual %) 2.7 2.3 2.3 1.3

Life expectancy at birth, total (years) 57.2 57.1 56.0 67.1

Mortality rate, infant (per 1,000 live births) 74.4 70.9 78.6 46.9

Physicians per 100,000 People … 9.0 58.3 109.5

Births attended by skilled health staff (% of total) … 58.7 50.2 64.1

Immunization, measles (% of children ages 12-23 months) 61.0 93.0 77.9 80.7

School enrolment, primary (% gross) 70.5 107.3 100.4 107.2

Ratio of girls to boys in primary education (%) 84.7 99.8 90.9 100.0

Literacy rate, adult total (% of people ages 15 and above) … 66.6 65.1 80.3

Access to Safe Water (% of Population) 56.0 82.0 64.5 84.3

Access to Sanitation (% of Population) 6.0 13.0 41.0 53.6

Human Develop. (HDI) Rank (Over 187 Countries) … 135 n.a n.a

Human Poverty Index (% of Population) … 28.1 34.7 …

Economy 2000 2009 2010 2011

GNI per capita, Atlas method (current US$) 346 1,191 1,227 …

GDP (current Million US$) 4,980 25,978 27,898 34,440

GDP growth (annual %) 3.8 4.0 7.7 13.5

Per capita GDP growth (annual %) 1.4 1.6 5.2 10.9

Gross Domestic Investment (% of GDP) 24.0 20.7 19.4 19.3

Inflation (annual %) 25.2 19.3 10.8 8.4

Budget surplus/deficit (% of GDP) -7.9 -3.5 -6.2 -3.5

Trade, External Debt and Financial Flows 2000 2009 2010 2011

Export Growth, volume (%) -2.5 13.4 55.2 84.2

Import Growth, volume (%) -2.8 -36.0 51.0 54.6

Terms of Trade (% change from previous year) 13.4 -20.1 -11.9 -3.8

Trade Balance ( M US$) -822 -2,207 -3,263 -3,058

Trade balance (% of GDP) -16.5 -8.5 -11.7 -8.9

Current Account ( M US$) -387 -1,198 -3,017 -3,664

Current Account (% of GDP) -7.8 -4.6 -10.8 -10.6

Debt Service (% of Exports) 23.1 4.6 3.9 2.8

External Debt (% of GDP) 145.5 28.0 31.0 30.7

Net Total Inflows (M US$) 517.8 2,123.8 … …

Net Total Official Development Assistance (M US$) 597.5 1,582.8 … …

Foreign Direct Investment Inflows (M US$) 165.9 1,684.7 2,527.4 …

Private Sector Development & Infrastructure 2000 2005 2010 2011

Time required to start a business (days) … 18 12 12

Investor Protection Index (0-10) … 6 6 6

Main Telephone Lines (per 1000 people) 11.1 14.9 11.4 …

Mobile Cellular Subscribers (per 1000 people) 6.8 132.8 714.9 …

Internet users (000) 1.6 18.5 85.3 …

22

Appendix II: BANK GROUP PORTFOLIO IN GHANA MARCH 2012

Project name Loan/grant

amount (UA)

Date of

approval

Date of

signature

Amount

disbursed

% disbursed

(January 2012)

Closing

date Status

Export Market And Quality Awareness Programme 17 000 000 13.07.2005 29.07.2005 8 550 975 50.3 31.12.2013 PP

Afram Plains Rural Development Project 19 970 000 31.05.2006 29.06.2006 13 897 400 69.6 31.12.2012 non PPP

Northern Rural Growth Program 40 000 000 17.12.2007 04.03.2008 2 161 362 5.4 31.12.2015 PP

Agriculture Sub-Total 76 970 000 24 609 737 32

Health Services Rehabilitation Iii 17 640 000 30.10.2002 04.06.2003 10 833 714 61.4 31.03.2012 Non PPP

Urban Poverty Reduction Project 25 000 000 12.10.2005 23.11.2005 16 366 196 65.5 30.06.2012 Non PPP

Gender Responsive Skills & Community Development 5 950 000 19.12.2007 14.05.2008 1 070 777 18.0 31.12.2012 Non PPP

Gender Responsive Skills & Community Development 2 360 000 19.12.2007 14.05.2008 638 310 27.0 31.12.2012 Non PPP

Social Sub-Total 50 950 000 - - 28 908 996 57

Tema-Aflao Road Rehabilitation Project 14 700 000 17.04.2002 02.08.2002 10 584 272 72.0 30.06.2012 Non PPP

Tema-Aflao Road Rehabilitation Project - Supplement 25 400 000 16.12.2008 10.06.2009 6 254 669 24.6 31.12.2013 Non PPP

Akatsi-Dzodze-Noepe Road(Akatsi-Akanu) 12 720 000 20.12.2002 18.07.2003 9 332 492 73.4 30.06.2012 PPP

Akatsi-Dzodze-Noepe Road(Akatsi-Akanu) - Supplem 13 400 000 16.12.2008 10.06.2009 7 249 125 54.1 31.12.2013

Road Infrastructure Project 2003 18 000 000 17.09.2003 01.04.2004 10 457 388 58.1 30.06.2012 PPP

Awoshie-Pokuase Road & Community Development 53 590 000 14.10.2009 01.04.2010 5 030 398 9.4 31.12.2015

Fufulso-Sawla Road 109 720 000 24.11.2010 02.12.2010 9 921 559 9.0 31.12.2015 PPP

Transport Sub-Total 247 530 000 - 58 829 902 24

Accra Sewerage Improvement Project (Asip) 46 000 000 26.04.2006 19.05.2006 8 221 863 17.9 31.12.2013

Improved Sanitation And Water Supply Service 1 825 191 18.09.2009 15.01.2010 520 438 28.5 15.01.2012 Non PPP

Design For Re-Use 441 325 28.07.2010 19.10.2010 177 305 40.2 30.06.2013

Reoptimization Study Of Akosombo & Kpong Dams 1 608 994 02.08.2010 07.01.2011 30.09.2013 PPP

Water/Sanitation Sub-Total 49 875 510 8 919 606 18

Invasive Aquatic Weeds - Ghana 1 680 000 22.09.2004 13.10.2004 1 135 696 67.6 30.06.2012

Ghana - Prom Of Science And Tech. For Agric. Devt. 15 581 000 29.11.2006 18.12.2006 7 677 863 49.3 31.12.2013 Non PPP

Uemoa Ghana Road Programme 64 500 000 19.11.2003 18.12.2003 45 358 503 70.3 31.12.2012 Non PPP

Uemoa Ghana Road Programme (Supplementary) 4 300 000 16.12.2008 10.06.2009 890 386 20.7 30.12.2013 Non PPP

Ghana - Togo -Benin Power Interconnect 14 870 000 04.04.2007 17.05.2007 1 031 632 6.9 31.12.2012 Non PPP

Multinational Sub-Total 100 931 000 - - 56 094 081 56

Budget support

Fourth Budget Support 26 000 000 13.07.2011 20.12.2011 13 000 000 50.0 31.12.2013 Non PPP

Fourth Budget Support 44 000 000 13.07.2011 20.12.2011 22 000 000 50.0 31.12.2013 PP

Multisector Sub-Total 70 000 000 - - 35 000 000 50

Power Systems Re-Inforcement Project 27 600 000 28.11.2007 04.03.2008 10 826 232 39.2 31.12.2014 Non PPP

Power Sub-Total 27 600 000 - - 10 826 232 39.2

Active Portfolio (Disbursing) 677 656 510 266 874 641 36

23

Appendix III: Related Projects Financed by the Bank and Other Development partners in the country

Area of intervention Development Partner Amount( USD

000000)

1 Informal Sector, CBT, Equipment GTZ (Germany) 21

2 Master craftsperson training DANIDA 1.2

3 Skills Development Fund DANIDA 30

4 CBT, Infrastructure, Equipment for selected TIs; informal

sector, studies

World Bank – Oil and Gas

Capacity Building

4.7

5 CBT, Skills Development Fund, Informal Sector, Studies,

Equipment (limited), Capacity Building

World Bank – Ghana Skills and

Technology Development Project

70

6 African Development Fund Gender Responsive Skills 29.5

Total 156.22

24

Appendix IV: Map of the Project Area

This map was provided by the African Development exclusively for the use of readers of the report to which it is attached. The names used and

borders shown do not imply on the Bank and its members any judgment concerning the legal status of territory nor any approval or acceptance of these borders.

25

Appendix V: Procurement Arrangements of the Project

PROJECT CATEGORIES UA '000 000

ICB NCB Other Short listing Total

1. WORKS

1.1 13 Technical Institutions & COTVET Building 45.29 [40.21] 45.29 [40.21]

2. GOODS

2.1 Furniture for 13 Existing TI's 0.98 [0.98] 0.98 [0.98]

2.2 Equipment for 13 TI's 1125 [11.25] 11.25 [11.25]

2.3 Books and reference Materials 13 TI's 0.51 [0.51] 0.51 [0.51]

2.4 Reference Materials for HIV counselling 0.01 [0.01] 0.01 [0.01]

2.5 Vehicles for Supervision & Monitoring 0.199 [0.199] 0.199 [0.199]

2.6 Equipment Project Management 0.33 [ 0.33 ] 0.33 [ 0.33 ]

2.7 Furniture and Equipment COTVET 0.40 [ 0.00 ] 0.40 [ 0.00 ]

2.8 Equipment -CBT Expansion 0.21 [ 0.00] 0.21 [ 0.00]

2.9 Equipment and Tools Traditional Apprentice 1.06 [1.06 ] 1.06 [1.06 ]

3. SERVICES

3.1 Design and Supervision of 13 TI's & COTVET 2.27 [2.27] 2.27 [2.27]

3.2 Preparation of strategic plan for TVET 0.27 [0.27] 0.27 [0.27]

3.3 Youth unemployment study 0.11 [0.11] 0.11 [0.11]

3.4 Devt and implementation of role model program 0.28 [0.28] 0.28 [0.28]

3.5 Marketing and Advocacy 0.03 [0.03] 0.03 [0.03]

3.6 Project Management Services 2.01 [2.01] 2.01 [2.01]

3.7 Development of Project Management Manual 0.02 [0.02] 0.02 [0.02]

3.8 Devt of computerized monitoring system 0.07 [0.07] 0.07 [0.07]

3.9 Equipment Specialist 0.03 [0.03] 0.03 [0.03]

Training

3.10 Upgrading of instructors and lecturers 1.30 [1.30] 1.30 [1.30]

3.11 Mainstreaming HIV and Career Guidance 0.42 [0.42] 0.42 [0.42]

3.12 TVET Mgt training and content Development 0.59 [0.59] 0.59 [0.59]

Technical Assistance

3.13 External Auditor for 5 years 0.17 [0.17] 0.17 [0.17]

3.14 Project Mid- term Review 0.07 [0.07] 0.07

[0.07]

3.15 Project summative Evaluation 0.07 [0.07] 0.07 [0.07]

3.16 CBT program expansion 0.07 [0.07] 0.17 [0.17]

3.17 Development of NTVETQF and Accreditation Frame

work 0.07 [0.07] 0.07

[0.07]

3.18 Impact evaluation and tracer studies 0.26 [0.26] 0.26 [0.26]

4. OPERATING COSTS

4.1 Strategic plan Preparation 0.30 [0.30] 0.30 [0.30]

4.2 CBT Expansion Program 0.58 [0.58] 0.58 [0.58]

4.3 Support to TVET Services 3.07 [2.49] 3.07 [2.49]

4.4 Traditional Apprentice Program 0.36 [0.36] 0.36 [0.36]

4.5 Project Management 1.35 [0.00] 1.35 [0.00]

26

[ ] Amounts financed by ADB ‘Other’ refers to Shopping, Direct Negotiation, Operating Cost

5. Miscellaneous

5.1 Bursary Scheme for female 3.11 [3.11] 3.11 [3.11]

5.2 Traditional Apprentice Program 0.52 [0.52] 0.52 [0.52]

TOTAL COST 59.32 [54.02] 0.94 [0.53] 10.83 [8.84] 6.89 [6.61] 77.70 [70.00]

27

Appendix VI: ESMP SUMMARY

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN SUMMARY Project Title: Development of Skills for Industry Project Number: P-GH-IAE-001

Country: Ghana

Department: OSHD Division: OSHD. 2

a) Brief Description of the Project and Key environmental and social components

Rehabilitation and expansion of I 3 existing technical schools and construction of COTVET building

b) Major environmental and social impacts

Positive Impacts

Improved safe drinking water in the technical schools;

Reduced incidence of water-borne diseases like cholera;

Improved sanitation facilities through the provision of ventilated latrines; and

Improved learning environment.

Potential Negative Impacts:

New construction and rehabilitation at the existing sites will lead to de-vegetation, soil erosion, dust emission and

noise, and

Slight risk of pollution of ground water and soil contamination.

Enhancement and mitigation program

The following mitigation measures represent the main outline of the ESMP and will form an integral part of the project:

VIP latrines will be built in the schools to provide for proper disposal of solid waste;

To avoid the contamination of water resources, the water points will be designed and constructed in such a way as to

ensure proper drainage of waste water so as to prevent any possibility of water stagnation, which may pose the risk of

groundwater contamination and development of breeding grounds for mosquitoes, flies and other insects;

Existing trees on the school sites will be preserved to protect the soils, provide shade and serve as wind shields; and

Grounds will be landscaped and storm water drains will be provided.

c) Monitoring program and complementary initiatives

The school authorities and the relevant ministry will follow up on all the issues relating to protection of the

environment in the both the new and existing technical schools;

Bank supervision missions will follow up the implementation of the ESMP.

d) Institutional arrangements and capacity building requirements

The PMU, under the guidance of the Ministry of Education will direct all consultants to adhere to guidelines designed

to safeguard and improve on the physical environment.

_________________________________________________________________________________________________

e) Public consultations and disclosure requirements

The PMU guided by the Ministry of Education and the authorities of the project districts will occasionally organise

events to publicise project activities

The project is designed to operate in a participatory approach manner where all activities will be implemented in close

collaboration with local communities to increase their sense of ownership of the improved facilities to provide under

the project.

f) Estimated Cost

US$ 521,000 for EIA and monitoring for 5 years

g) Implementation schedule and reporting

The environmental management and monitoring plan will be implemented on the basis of the project implementation schedule, as

all activities are mainstreamed in the project design. Problems which will be reported in the QPPR reports should be promptly

addressed by the project management and the Bank.