project design review plan · web viewgeneral, factual observations about material presented which...
TRANSCRIPT
In partnership with: India/DAEItaly/INFNUK/STFCFrance/CEA/Irfu, CNRS/IN2P3
PIP-II 800 MeV Booster Injection/Beam Absorber David Johnson, Proton Source DepartmentInjection Absorber Preliminary Technical Design Review 11 - 20 - 2019
2 11/20/2019
Outline
D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
• Current 400 MeV injection layout & Booster Operation
• Brief Introduction to 800 MeV Booster Injection System– Injection parameters– Geometry (Limited space) {existing and new}– Layout– Phase space painting
• Injection Design Constraints/Considerations– Lorentz stripping– Stripping efficiency– Excited states on neutral hydrogen– Injection Loss Budget summary
• Injection Absorber requirements
• Plan for Absorber Design– Potential further Optimization
• Collimation in Beam line– Accident scenario
• ES&H Considerations
• Quality Management considerations
• Schedule
• Summary
Current level of operation
11/20/20193
B:BPL1HA 336 W
Includes stripping eff 99.9%0.1% H0 -> 4.5W -> <350 mrem/hr @1’> max of 700 mr/hr@1’Plus ~ 1% parasitic hits
*
*
D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
injection 4.70E+12 3.008E+02 4.437E+03
Energy rep rate 14.75[eV] efficiency loss survive lost joules watts
injection 4.00E+08 98.700% 1.300% 4.6389E+12 6.11E+10 3.910E+00 5.768E+01bunching 4.00E+08 97.500% 2.500% 4.5229E+12 1.1597E+11 7.422E+00 1.095E+02Notching 4.00E+08 99.000% 1.000% 4.4777E+12 4.5229E+10 2.895E+00 4.270E+01transition 4.30E+09 99.900% 0.100% 4.5184E+12 4.5229E+09 3.112E+00 4.590E+01Extraction 8.00E+09 99.900% 0.100% 4.5139E+12 4.5184E+09 5.784E+00 8.531E+01
TOTAL 95.1% 5.0% 2.31E+11 2.312E+01 3.411E+02
CurrentStripping Efficiency 4.00E+08 9.990E-01
lossLorentz Stripping 4.00E+08 0.00E+00Neutrals to absorber 4.00E+08 1.00E-03H- to absorber (?) 4.00E+08 1.25E-04coulomb scattering 4.00E+08 6.00E-03Nuclear collisions 4.00E+08 6.25E-03excited states 4.00E+08 0.00E+00
TOTAL 1.34E-02
Parameter Before PIP Current PIP-II Units
Injection Energy 400 400 800 MeVRep Rate 7.5 15 20 HzPPP Injected 2 4.7 6.7 E12Protons/hr 0.54 2.538 4.824 E17# turns 1 to 12 1 to 19 292 turnsinjection time 2.2 to 26.4 2.2 to 41.8 550 us
Injected power 0.96 4.512 17.152 kW
11/20/20194
Still limited to 500W (5 min average) loss rate ( i.e 25 J @ 20 Hz) PIP-II will require injection phase space painting due to small linac emittance PIP-II will utilize micro-bunch to bucket injection Increase in injected beam power will require dedicated injection absorber
Current and PIP-II Operational Parameters
D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
5
5.68 m (f-f)
ORBUMPS
Harmonic corrector
foil changer
Inj beam
diagnostics
vacuum bypassBPM
Existing Booster Injection Straight section (L1)
Beam CL” 34” x 48”
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
H+ & H
0
Was
te b
eam
~4 to 4.5W 350 to 700 mrem/hr
11/20/20196
800 MeV Booster Injection System Key features: Straight increased by 1 meter Reduce GM length by ~0.75 m (to be further optimized) Vertical Injection
Elevation of inj beam at foil dy (ORBUMP)+dy(V paint)
Absorber moved away from aperture Opened up ORBUMP aperture for a single magnet design Dedicated phase space painting outside injection straight Painting design complete Foil heating checked, not an issue Include vacuum bypass Lattice distortion negligible Convoy electron handling - TBD Excited states of H0
D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
H-
H+
H0
H-
foilGradientMagnet
GradientMagnet
ORB
UM
P
ORB
UM
P
ORB
UM
P
ORB
UM
P
ABSO
RBER co
rrec
torBPM
MW
SWBPM
PWC
7
Increase Injection Straight Section Length (move to L11)
• Reduce length of “D” gradient magnet ~30%.
• Increase # turns
• Run on GMPS
• Increase straight by 1 m
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
190.5mm165.1mm211.5mm Beam pipe f = 31.5mm
H- sX,Y < 2 mm
0.4717m
Lattice with new insert
11/20/20198
Booster lattice with reduced length gradient magnet
Injection Insert
D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
Painting bump
Long 11Long 10 Long 12
Hs09
= 0
.22
mr (
53 G
)
Hs01
0 =
0.30
8 m
r (73
G)
Hs11
= 0
.31
mr (
74
G)
Hs12
= 0
.22
mr (
53 G
)
Vp(m
s10)
= 3
.03
mr
(742
G)
Vp(m
s) =
-1.4
mr
(335
G)
VP(m
s) =
-1.0
9 m
r (26
1 G)
Vp(m
s11)
= 3
.03
mr
(742
G)
Phase Space painting Magnets
11/20/2019 D. Johnson PIP-II Booster njection Absorber Preliminary Design Review9
Painting magnets dual function: phase space painting removing beam from foil
Horizontal painting: Booster correctors <4A , 40A max
Vertical painting : new correctors & supply
10 11/20/2019
Injection Design Constraints: Lorentz Stripping
18 mW1.8 mW
D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
• ORBUMP Fields– Make geometry work– Don’t strip incoming H-– 3rd magnet and excited
states
• Foil Issues– Matching to minimize
parasitic hits from circ. Beam
– Stripping eff. (foil thickness)– Electron handling (~9W)– Single coulomb scattering– Nuclear collisions– Energy straggling
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review11
12
Compare Calculated vs measured n=3 excited state
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
0 100 200 300 400 500 600 7001.00E+00
1.00E+01
f(x) = 0.0867031472423275 exp( − 0.0131937414808663 x )R² = 0.999529324101823f(x) = − 0.000560769943866339 ln(x) + 0.00635198225090449Calculated Yield of n=1+2,3, & H+ based on Gully parameters for 800 MeV
n=3 Logarithmic (n=3) Logarithmic (n=3)Logarithmic (n=3) Logarithmic (n=3) n=3 thick>200Exponential (n=3 thick>200) n=1+2 ProtonsGully data fig 10
Foil Thickness [ug/cm^2]
Yiel
d
Data from Gulley
800 MeV
13
Yield of Stark States (n=3,4,5,6)
Foil Thickness
n 535 mg/cm2 600 mg/cm2
3 1.4 W 0.60 W
4 1.04 W 0.51 W
5 1.01 W 0.53 W
6 0.62 W 0.35 W
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
100 200 300 400 500 600 700 8000.00010
0.00100
0.01000
f(x) = 0.0762893547730512 exp( − 0.0126796838648273 x )
f(x) = 0.00448791148148148 exp( − 0.00901786749658085 x )
f(x) = 0.0124634109691961 exp( − 0.010402114100661 x )
f(x) = 0.0219478737997257 exp( − 0.0106467692829036 x )
Predicted yield for n =3-6 vs foil thickness
n=4
Exponential (n=4)
n=5
Exponential (n=5)
n=6
Exponential (n=6)
n=3
Exponential (n=3)
Series9
Foil thickness [ug/cm^2]
Abso
lute
yie
ld
Solid data points from: n=3 Gulley Fig. 9
n=4-6 Gully Fig. 10
2.032E-05
2.979E-05
0.00463
300
201102210
003030
021120
012111
Yield depend on foil thickness600 ug/cm2 Yield n=3: 3.5E-5
Yield n=4: 3.0E-5 Yield n=5: 3.0E-5 Yield n=6: 2.0E-5Lost power: n=4: 0.5 W n=5: 0.54 W n=6: 0.35 W(n=4) 10 nondegenerate Stark statesStatistical population uniform: so each state-> 10% total
Time to travel 1m
Assume 17 kW
d = 0.303 m
d = 0.075 m
d = 0.023 mFOIL
N=4 80% (0.5W) 400 mW
not stripped
Opti
mal
pea
k
Curr
ent s
oluti
on
Time to travel 3m
d = 1.0 m
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review14
n=6 n=4n=5
Stripping of H0* in downstream ORBUMP n=1,2,3 Not Stripped
15
Losses due to LA Coulomb Scattering & Nuclear Scattering
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
Loss = 1.6E-4 * 17 kW = 2.8W Loss = 2.15E-5 * 17 kW = 0.37 W
Loss Budget Summary at Injection
11/20/201916
As a point of reference:current injection 4.5 kWstripping eff 99.9% 4.5 W in neutrals H- missing foil ~10% power or neutralsavg. residual activation 350 mrem/hr @1’max. residual activation 700 mrem/hr@1’on downstream GM
*
Neutrals n=1,2,3 and some fraction n=4Min. pwr. Handling of injection absorber
n = 5 & 6 will go into halo for collimation
define ~1% miss foil*
*
Parameters associated with peak ORBUMP field
Administrative Loss Limit 500 W 25 J at 20Hz for entire cycle
Dependent on foil thickness andNumber of foil hits/particle & cross setion
From Salah
D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
injection 6.70E+12 rep rate 20 Hz 8.576E+02 1.715E+04Energy edfficicncy loss lost injected
Stripping Efficiency 8.00E+08 99.8300% 1.70E-03 1.14E+10 6.69E+12loss lost joules watts
Lorentz Stripping 8.00E+08 1.00E-06 6.70E+06 8.576E-04 1.715E-02Neutrals to absorber 8.00E+08 1.70E-03 1.14E+10 1.458E+00 2.916E+01H- to absorber (?) 8.00E+08 1.00E-02 6.70E+10 8.576E+00 1.715E+02coulomb scattering 8.00E+08 2.15E-05 1.44E+08 1.844E-02 3.688E-01Nuclear collisions 8.00E+08 1.61E-04 1.08E+09 1.381E-01 2.761E+00excited states 8.00E+08 8.68E-05 5.82E+08 7.444E-02 1.489E+00
2.007E+02TOTAL 1.20E-02 9.88E-01 8.02E+10 1.027E+01 2.053E+02
800 MeV PIP-II Injection loss budget
beam power to absorber
Now, Let’s move on to the Injection Absorber Requirements
17
Injection Absorber Requirements
Power Handling 200 W @ 800 MeV & 20 Hz 170 W H- missing the foil initial design assumption 30 W H0 generated from foil due to stripping conservative value
One of the Largest constraints IS space. Taking into account the ORBUMPS required to bring the beam into meet the foil AND the diagnostics,
foil changer, and the Booster corrector (full field multipole) we are left with 0.8 meters MAX.
Must meet strict Radiological constraints determined by EPA/DOE/FNAL
Should require no active water cooling
Should be able to withstand limited pulse accident condition (to be defined) This scenario should be protected vie loss monitors / chipmunks and connected to safety permit system
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
18
Absorber Design Philosophy Recall, Total Space available is 80 cm MAX (if we can do it in less space even better) The absorber must stop primary protons want a high density material, like Tungsten But, Tungsten is a very good spallation target … Booo! Excessive generation of
spallation neutrons ! Fall back to standard stainless steel
unless there is some other magic material Or some hybrid or sandwich techniques
Need to contain showers Minimize residual activation So, general philosophy (at this point) is to utilize stainless steel surrounded by marble
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
19
Initial Geometry for Mars Modeling (local model)
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
20
Absorber Design Plans
• Absorber & shielding design to meet design Residual Activation requirements using local model (part of radiological requirements)– Risk: if requirements cannot be met, investigate potential mitigations
• Increasing ORBUMP field (to make more room for absorber) • Removing harmonic corrector (or replace it with smaller H&V dipole only)• Reducing halo or removing the amount of H- missing foil collimation in beam line• Limit intensity • Lower injection energy
• Insert model into Booster tunnel and soil geometry – Model Prompt dose– Model activation of tunnel walls and air– Model the production of 3H and 22Na (for ground and surface water)
• Once we are satisfied with the Radiological Requirements are met , move on to mechanical model… Not anticipating any major issues
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
• All activities in compliance with– PIP-II IESH Management Plan– Fermilab FESHM and FRCM– Division Safety processes and procedures
• The main Radiological Safety Concern in the current design is the reduction of accelerator component activation and minimization of personnel exposure during access periods (ALARA).– Dedicated waste beam absorber
• Typically, the hottest regions in circular accelerators are the injection, collimation, and extraction regions.– New Injection Insert - we will incorporate design features to minimize exposure during
maintenance periods through judicious use of • Shielding (permanent as well as moveable personnel shielding if required)• Quick disconnects
• Fermilab “Prevention through Design” top priority in all aspects of design, manufacturing, installation, commissioning, and maintenance.
• Interlock absorber losses to Radiation safety system through LM’s and external chipmunk
ESH
11/20/2019 D. Johnson PIP-II Booster njection Absorber Preliminary Design Review21
11/20/2019 D. Johnson PIP-II Booster njection Absorber Preliminary Design Review22
Identifier
Potential Hazzard Description
Life Cycle Stage
Who is at risk? What is at risk?
Pre-Mitigation
Severity
Pre-MitigationProbability
Pre-MitigationRisk Score
Mitigations Post-Mitigation
Severity
Post-MitigationProbability
Post-MitigationRisk Score
Status of Mitigation
Implementation
Overexposure to radiation from machine operations
Operations Personnel on access in beamline enclosure
Critical A - Almost Certain
1 - Very High Global requirement to supply a radiation safety interlock system. Technical specification for system to be compliant with FRCM Chapter 10.
Critical E - Rare 3 - Moderate
Integrated into Design
Exposure to radiation from the front face of the Beam Absorber during instrumentation inspection.
Operations Personnel on access in beamline enclosure
Medium C - Possible 3 - Moderate Install marble shielding to reduce the radiation exposure.
Low D - Unlikely 4 - Low Integrated into Design
Exposure to radiation in the case we will have to replace the Booster Injection absorber.
Operations Personnel on Access
High D - Unlikely 3 - Moderate Monolithic absorber shielding design. Integrate shielding into absorber's block.
Low E - Rare 5 - Negligible
Integrated into Design
Exposure to radiation trying to replace the Booster corrector downsream of the absorber.
Multiple Contractors and Maintenance
personnel
High C - Possible 2 - High Minimize the radiation exposure by utilizing marble shielding around the absorber. Utilize quick disconnects for fast replacements of the correctors.
Low C - Possible 3 - Moderate
Integrated into Design
Environmental impact in Raw Water.
Operations Enviroment Cooling ponds and waters of
the state
High B - Likely 1 - Very High Use appropriate shielding around the Beam Absorber.
Minimal C - Possible 4 - Low Integrated into Design
Exposure to radiation from replacing the downstream ORBUMP magnet
Operations Contractors and Maintenance
personnel
High C - Possible 2 - High Utilize quick disconnect with crane handling.
Low C - Possible 3 - Moderate
Integrated into Design
• All major components used in the upgrade will be Fermilab designed and fabricated either in APS-TD or AD.– Both divisions are committed to Quality Control and have standard
operating procedures (SOP) of • Incoming inspections (QC)• Acceptance testing (where appropriate) • Travelers • Final testing to verify performance
– Prior to commencement of fabrication• Final Design review• Production Readiness Review
– The proposed absorber design is not too different from what Fermilab has produced in the past. With each new design lessons learned are incorporated in all phases of design and manufacturing.
• Application of Lesson Learned in all phases of design, fabrication, and installation
Quality
11/20/2019 D. Johnson PIP-II Booster njection Absorber Preliminary Design Review23
• The final design review for the Injection Absorber is scheduled Sept 2022• Fabricate Injection absorber in time frame March 2024 thru August 2025
Schedule
11/20/2019 D. Johnson PIP-II Booster njection Absorber Preliminary Design Review24
25
Summary
• Very ambitious effort to convert the 50 year old Booster RCS to 800 MeV multi-turn injection during a 0.5 ms injection period and 17 kW injected power.
• Must take into account uncontrolled losses and controlled losses losses to Absorber
• We have defined the capacity and radiological requirements for the absorber
• Mechanical design will follow modeling
• Vitaly Pronskikh will describe our MARS modeling to date and discuss future plans
• Jesse Batko will discuss results of the ANSYS thermal model
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
26 11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
Thank you for your Attention
Questions?
27
Phase Space Painting• Initial Phase Space painting simulations utilizing Mathcad (V. Lebedev)
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
𝛽𝐿
𝛽𝐵≥ ¿
Assume ¼ wave single pass Sin/cos painting
Linac beam centroid ~2.57s from foil edge gives 1% beam missing foil 170 W
Go to injection dump
Distribution of parasitic and primary hits on foil
Want to minimize parasitic hits on foil and minimize H- missing foil Implies that we need to do a good job in beamline collimation
At 2.57s dx = 1.95mm dy = 3.5 mm Nhits =6 LACS = 2.8W 1% miss 170 WAt 3.0s dx = 2.27mm dy = 4.1 mm Nhits =8.1 LACS = 3.6W 0.25% miss 43 W
28
Beamline Collimation
• Based upon the results with MARS look at how to eliminate H- missing foil.
• Beamline collimation with foil/absorber (SNS) technique
• Looking at both movable foil and absorber
• First order collimation w Tracewin
• Followed by more detailed simulation with TRACK– Follow multiple charge states– Get distribution of protons on Absorber
• Evaluate Absorber with MARS for – Radiological results– And out scattering (impact parameter)
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
𝑜𝑓𝑓𝑠𝑒𝑡 = 𝑥𝑓𝑜𝑖𝑙 +(𝑥𝑓𝑜𝑖𝑙' +𝜃𝑞𝑢𝑎𝑑 +𝜃𝑓𝑜𝑖𝑙𝑟𝑚𝑠)𝐿𝑑𝑟𝑖𝑓𝑡
29
Add in collimators to straight section
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review
Phase advance ~ 90 deg/cell
30
Initial Collimation (with Tracewin) 2H & 2V with “foils at 3s
11/20/2019D. Johnson PIP-II Booster njection Absorber Preliminary Design Review