project controls expo - 31st oct 2012 - the practical use of earned value for real-time forecast and...
TRANSCRIPT
![Page 1: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/1.jpg)
Copyright @ 2011. All rights reserved
Session B2
The Prac0cal use of Earned Value for real-‐0me forecast and control
Project Controls Expo -‐ 31st Oct 2012 Twickenham Stadium, London
Speaker – David Birch
![Page 2: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/2.jpg)
Copyright @ 2011. All rights reserved
About the Speaker
§ David Birch -‐ 35 years experience in the delivery of high profile UK and interna@onal projects and Programmes for world leading Engineering/Construc@on contractors.
§ 25 years of Project Controls and Opera@onal Management experience § Since 2008 responsible for the London 2012 Programme Controls group
for CLM, the delivery partner to the Olympic Delivery Authority (ODA). § Previously, delivered projects numerous industry sectors including:
ü UK & Interna@onal Oil and Gas ü UK Nuclear decommissioning and clean-‐up ü Conven@onal and Nuclear Energy ü Water ü Telecoms ü Industrial and Infrastructure
![Page 3: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/3.jpg)
Copyright @ 2011. All rights reserved
Good decisions require good informa@on. To deliver a complex project to @me and cost requires a proper understanding, at regular stages and at an appropriate level of detail, of the rela@onships between: work done, progress against plan, cost incurred against budget, cash spent and cost to come. Combining this data leads to an understanding of the actual value of what has been achieved and prevents managers from being either too op@mis@c or unduly pessimis@c about the situa@on. It enables them to make appropriate judgements as to what correc@ve ac@ons need to be taken in good @me.
Sir John Armi+ Chairman -‐ Olympic Delivery Authority
EVM -‐ APM Guidelines Forward
![Page 4: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/4.jpg)
Copyright @ 2011. All rights reserved
Baseline
Corre
ct
Analyse
Measure
Project Controls Cycle
Where are we?
Where are we going to end
up?
How do we get on track again?
Classic Project Control Cycle
![Page 5: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/5.jpg)
Copyright @ 2011. All rights reserved
1. Organisa@on (1-‐5) 2. Planning, Scheduling and Budge@ng (6-‐15) 3. Actual Costs (16-‐21) 4. Analysis and Repor@ng (22-‐27) 5. Change Management (28-‐32)
EVM System (32 Criteria)
Geang the system right leads to: Informed, effec>ve management and decision making by knowing:
• What has been achieved of the plan • What it has cost to achieve the planned work • If the work achieved is cos@ng more or less than was planned • If the project is ahead of or behind the planned schedule
![Page 6: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/6.jpg)
Copyright @ 2011. All rights reserved
1 -‐ Organisa0on
• Essen@al to understand scope and how it will be broken down and delivered (Work Element Defini@on)
• Key is then to create the Work Breakdown Structure (WBS) and progressively develop the Contract Work Breakdown Structure (CWBS)
• Who will deliver and be responsible for delivery Organisa>onal Breakdown Structure (OBS)
• Ensure that the systems (WBS, CWBS and OBS) will support each other and are integrated (via coding)
![Page 7: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/7.jpg)
Copyright @ 2011. All rights reserved
WBS Example
![Page 8: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/8.jpg)
Copyright @ 2011. All rights reserved
2 – Planning, Scheduling and Budge0ng
• Essen@al to Schedule all the work logically • Iden@fy the Project Milestone set and the Key Milestones
within that set • Cost Loaded Schedule ac@vi@es should be aligned with Cost
Accounts within the WBS elements • Establish how the progress will be measured • Iden@fy Level of Effort (LOE) ac@vi@es (management,
management reserves, prelim’s/overheads, etc.) • Create the Project Es@mates and fix the Budgets • Baseline and implement Change Control
![Page 9: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/9.jpg)
London 2012 06/11/2012
100k 100k 50k 50k 50k 50k
50k 50k 75k 75k
50k 50k 50k 50k
100k 100k 100k 100k
50k 50k 75k 75k
50k 50k 50k 50k
Structures – Work Breakdown Structure (WBS)
Activity
Activity
850k
400k
250k
200k Activity
100k 100k 150k 150k 100k 100k 75k 75k
Activity
Activity
850k
400k
250k
200k Activity
100k 100k 100k 100k 125k 125k 50k 50k 50k 50k WBS 01.02.02
WBS 01.02.01
200k 200k 200k 200k 225k 225k 125k 125k 50k 50k WBS 01.02 2012 Project
Project Code
Project Code
London 2012 Project View
![Page 10: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/10.jpg)
London 2012 06/11/2012
100k 100k 50k 50k 50k 50k
50k 50k 75k 75k
50k 50k 50k 50k
100k 100k 100k 100k
50k 50k 75k 75k
50k 50k 50k 50k
Structures – Contractor Schedule Summary (WBS)
Activity
Activity
850k
400k
250k
200k Activity
100k 100k 150k 150k 100k 100k 75k 75k
Activity
Activity
889k
439k
250k
200k Activity
100k 100k 100k 100k 125k 125k 50k 50k 50k 50k Contractor WBS
Contractor WBS
200k 200k 200k 200k 225k 225k 125k 125k 50k 50k London 2012 WBS
![Page 11: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/11.jpg)
Copyright @ 2011. All rights reserved
2 – Objec0ve Measures of Progress
• Milestones • Percentage Complete
ü Agreed steps ü Evaluated ü Once at 100%
• Quan@@es • Appor@oned Level of Effort • Level of Effort
![Page 12: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/12.jpg)
Copyright @ 2011. All rights reserved
2 – Original Budget Summary
![Page 13: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/13.jpg)
Copyright @ 2011. All rights reserved
3 – Actual Costs
• Essen@al that Actual Costs (cost accounts) are mapped to WBS • Ensure that cost collec@on systems and contractor invoices are
broken down into at least the level of the WBS elements • Understand the material accoun@ng system and ensure plan
aligns with when material costs will be recorded (either invoiced or accrued)
• Keep the mapping up to date at each update (normally monthly)
![Page 14: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/14.jpg)
London 2012 06/11/2012
100k 100k 100k 100k
50k 50k 75k 75k
50k 50k 50k 50k
BAC
Status - Performance To Date Mar 08 Apr 08 May 08 Jun 08 Jul 08 Aug 08 Sep 08 Oct 08 Nov 08 Dec 08
200k
850k
400k
250k
200k
100k 100k 150k 150k 100k 100k 75k 75k
Performance Measurement BASELINE
BV
Time Now
CLM Accepted Programme CURRENT
- - 150k 50k 50k 50k
50k 50k 75k 75k
50k 50k 50k 50k
120k 119k
100k
989k
300k
250k
200k
239k
120k 119k 100k 100k 125k 125k 50k 50k 50k 50k EV
EAC
AC
Compare Cumulative To Date At Completion
BV EV AC SV CV BAC EAC VAC
200k 100k 239k -100k -139k 850k 989k -139k
![Page 15: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/15.jpg)
Copyright @ 2011. All rights reserved
4 – Analysis and Repor0ng
• Collect progress data and record % complete of each ac@vity (using the rules established at planning phase)
• Compare Baseline Plan with Progress and Actual Costs establishing Schedule Variance (SV) and Cost Variance (CV)
• Forecast Dura%ons to complete • Forecast Costs to complete • Review Milestone comple@on forecasts against Plan • Review An@cipated Final Cost to Budget • Project Team determine project issues/mi@ga@ons/plan
adjustments • Project Team Report the outcome of analysis and plans to
complete
![Page 16: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/16.jpg)
Copyright @ 2011. All rights reserved
4 – Quan00es
![Page 17: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/17.jpg)
Copyright @ 2011. All rights reserved
4 – Progress
![Page 18: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/18.jpg)
Copyright @ 2011. All rights reserved
4 – Performance
![Page 19: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/19.jpg)
Copyright @ 2011. All rights reserved
4 – Analysis
![Page 20: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/20.jpg)
Copyright @ 2011. All rights reserved
4 – Forecas0ng
![Page 21: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/21.jpg)
Copyright @ 2011. All rights reserved
4 – Project Manager Summary
![Page 22: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/22.jpg)
Copyright @ 2011. All rights reserved
5 – Change Management
Once the Baseline is agreed, published and fixed • The Original Budget should be FROZEN • Change Control should start and formal monthly change reviews
should be held and recorded • Approved Changes should be incorporated into the Current
Baseline (ONLY APPROVED CHANGES – need strong Governance) • Retrospec@ve Changes should be strongly discouraged • Con@ngency and Risk Management essen@al processes • Current Baseline should reflect realis0cally achievable targets
When status and forecasts show significant variance to Baseline
raise a change for Management approval.
![Page 23: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/23.jpg)
Copyright @ 2011. All rights reserved
5 – Change Process within Monthly Cycle
![Page 24: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/24.jpg)
Copyright @ 2011. All rights reserved
Crea0ng a Control Culture
• Do not under es@mate the effort required to set up an effec@ve control system
• Once set up the team and contractors need to understand how it will work
• Training is essen@al (team, contractor and execu@ve) • Establishing a culture will take @me, start early..... • The 0me and effort will be worth it
![Page 25: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/25.jpg)
2006 2007 2008 2009 2010 2011 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Controls Building Blocks in Place
Baseline developed & Yellow Book Published
Culture & Trust Established
Systems Maturing
Change Control implemented
Monthly & Quarterly Reviews
Trending Process
AFC process
Monthly Trend Reviews
Monthly Trend & AFC Reviews
Simplify Baseline
Schedule Integration maturing
Support & Training
Assurance, Support & Intervention (where necessary)
Align Reporting
London 2012 - Maturity Timeline
Big Build; Completion Big Build; Structures Big Build; Foundations Design, Dig, Demolish
Controls mature and
fully functional
![Page 26: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/26.jpg)
Copyright @ 2011. All rights reserved
Integrated Project Controls
The Plan & Physical Progress
Design, Procurement and
Construction
Commercial Position Budget,
Commitments & Outturn Costs
Financial Position
Invoiced and Accrued Liabilities
In summary
With Earned Value at it’s heart
![Page 27: Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch](https://reader030.vdocuments.site/reader030/viewer/2022020307/55a58c0e1a28ab51528b4581/html5/thumbnails/27.jpg)
Copyright @ 2011. All rights reserved