project: construction of standard type b/c motiong …€¦ · 30. installation of 1 1/2"dia....

42
PROJECT: CONSTRUCTION OF STANDARD TYPE "B/C" MOTIONG MPS BUILDING LOCATION: MOTIONG, SAMAR 1. Mobilization and installation of temporary facilities; 2. Soil poisoning, staking and laying out; 3. Excavation, backfilling and compaction; 4. Fabrication and installation of reinforcing steel bars; 5. Fabrication and Installation of forms and scaffoldings; 6. Pouring of concrete at column and wall footings, tie beams and beams, columns, slabs and stairs; 7. Laying of CHB at exterior walls and interior wall and partitions in plain finish; 8. Laying of CHB at septic vault wall and partitions; 9. Installation of electrical and communication roughing-ins: and /waterlines systems; 10. Application of waterproofing membrane at roofdeck, canopy and toilets and baths; 11. Installation of steel roof frames, c-purlins and 12mm ficem board fascia board; 12. Installation of 10 mm thk double sided insulator; 13. Installation of pre-painted .50mm thk long span roofing, ridge rolls and gutter; 14. Installation of door jambs and window steel frames including finishing of window openings; 15. Installation of metal furring joists and 4.5mm thk ficem board ceiling at first floor, second floor & third floor; 16. Laying and installation of 0.60mx0.60m glazed and unglazed ceramic tiles at porch, first floor, second floor, 18. Installtion of plumbing fixtures and accessories at comfort rooms to include two urinals; 19. Installation of 15KVA transformer, electrical wires, conduits, circuit breakers, panel boards, entrance cap 21. Fabrication and installation of aluminum powder coated (blue) swing doors, gray panel doors, PVC doors with louver, steel doors, steel grills doors and see trough steel accordion door (entrance & exit), 22. Installation of glass for steel casement and awning windows; 23. Fabrication and installation of stainless handrails and 16mm square bar railings at stairs and porch areas; 24. Installation of wooden cabinets at COP room, quarters and information desk; 25. Fabrication of steel evidence cabinets with accordion doors at intel/inves rooms; 26. Installation of granite tiles at top of quality service desk; 27. Painting of exterior and interior walls of the building, ceiling, doors, windows, roof frames and cabinets; 28. Installation of one-meter pathwalk and plant box within the building perimeter; 29. Provision of 500 gal/2,000 lit overhead stainless water tank w/ stand and float valve w/ I HP water pump; 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex building signage with backlights and directory board; 32. Installation of 8"x11" x 3/16" thk building brass marker; 33. Electricity & water interconnection with the provider; 34. Functionality testing of electrical, communication fixtures and plumbing system; and dual band gigabit/LTE CPE broadband router; and steel security grills (entrance and exit); 20. Installation of internet outlet, data cabinet, wi-fi router, fixtures, accessories, configuration and commissioning of Republic of the Philippines National Police Commission PHILIPPINE NATIONAL POLICE POLICE REGIONAL OFFICE 8 Camp Kangleon, Brgy Campetic, Palo, Leyte ( Two (2) Storey with Roofing) SCOPE OF WORKS third floor, landing and stairs; 17. Laying and installation of 0.30mx0.30m glazed ceramics tiles and 0.30mx0.30m unglazed ceramic tiles at T&B walls and flooring respectively; and electrical fixtures;

Upload: others

Post on 18-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

PROJECT: CONSTRUCTION OF STANDARD TYPE "B/C" MOTIONG MPS BUILDING

LOCATION: MOTIONG, SAMAR

1. Mobilization and installation of temporary facilities;

2. Soil poisoning, staking and laying out;

3. Excavation, backfilling and compaction; 4. Fabrication and installation of reinforcing steel bars;

5. Fabrication and Installation of forms and scaffoldings;

6. Pouring of concrete at column and wall footings, tie beams and beams, columns, slabs and stairs;

7. Laying of CHB at exterior walls and interior wall and partitions in plain finish;

8. Laying of CHB at septic vault wall and partitions;

9. Installation of electrical and communication roughing-ins: and /waterlines systems;

10. Application of waterproofing membrane at roofdeck, canopy and toilets and baths;

11. Installation of steel roof frames, c-purlins and 12mm ficem board fascia board;

12. Installation of 10 mm thk double sided insulator;

13. Installation of pre-painted .50mm thk long span roofing, ridge rolls and gutter;

14. Installation of door jambs and window steel frames including finishing of window openings;

15. Installation of metal furring joists and 4.5mm thk ficem board ceiling at first floor, second floor & third floor;

16. Laying and installation of 0.60mx0.60m glazed and unglazed ceramic tiles at porch, first floor, second floor,

18. Installtion of plumbing fixtures and accessories at comfort rooms to include two urinals;

19. Installation of 15KVA transformer, electrical wires, conduits, circuit breakers, panel boards, entrance cap

21. Fabrication and installation of aluminum powder coated (blue) swing doors, gray panel doors,

PVC doors with louver, steel doors, steel grills doors and see trough steel accordion door (entrance & exit),

22. Installation of glass for steel casement and awning windows;

23. Fabrication and installation of stainless handrails and 16mm square bar railings at stairs and porch areas;

24. Installation of wooden cabinets at COP room, quarters and information desk;

25. Fabrication of steel evidence cabinets with accordion doors at intel/inves rooms;

26. Installation of granite tiles at top of quality service desk;

27. Painting of exterior and interior walls of the building, ceiling, doors, windows, roof frames and cabinets;

28. Installation of one-meter pathwalk and plant box within the building perimeter;

29. Provision of 500 gal/2,000 lit overhead stainless water tank w/ stand and float valve w/ I HP water pump;

30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy;

31. Installation of 3'x8' panaflex building signage with backlights and directory board;

32. Installation of 8"x11" x 3/16" thk building brass marker;

33. Electricity & water interconnection with the provider;

34. Functionality testing of electrical, communication fixtures and plumbing system; and

dual band gigabit/LTE CPE broadband router;

and steel security grills (entrance and exit);

20. Installation of internet outlet, data cabinet, wi-fi router, fixtures, accessories, configuration and commissioning of

Republic of the Philippines

National Police Commission

PHILIPPINE NATIONAL POLICE

POLICE REGIONAL OFFICE 8

Camp Kangleon, Brgy Campetic, Palo, Leyte

( Two (2) Storey with Roofing)

SCOPE OF WORKS

third floor, landing and stairs;

17. Laying and installation of 0.30mx0.30m glazed ceramics tiles and 0.30mx0.30m unglazed ceramic tiles at T&B

walls and flooring respectively;

and electrical fixtures;

Page 2: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

36. Cleaning and clearing.

35. Application for building permit;

Page 3: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Unit DAY QTYUnit Rate

(Php/Unit)TOTAL COST

I GENERAL REQUIREMENTS

a. sqm 96.00

Estimated Direct Cost(EDC)

Materials

2'x2'x12' of Cocolumber bdft 300

2'x3'x12' of Cocolumber bdft 470

1/4"thk Ordinary Plywood pcs 20

Portland Cement bags 7

Washed Sand cum 1

Washed gravel cum 1

Blue Sheets rolls 2

Temporary Electrical SupplyPower lot 1

Temporary Water Supply lot 1

Soi Poisoning/Termite Control Treatment lot 1

Ga 26 Corrugated GI Sheet, 12' pcs 10

Toilet bowl (Pail type) pcs 2

Assorted CW Nails kgs 8

Sub-total

Labor

Foreman m-d

Carpenter m-d

Mason m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

II

a.

1 Wall Footing cum 7.44

Estimated Direct Cost(EDC)

Labor

Foreman m-d

Cleaning, Grubbing, Soil Poisoning & Temfacil

EARTH WORKS

Excavation

DETAILED COST ESTIMATES

Item

NumberACTIVITY

Page 4: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

2 Column Footing and Footing Tie Beam cum 32.74

Estimated Direct Cost(EDC)

Labor

Foreman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

3 Septic Vault and Catch Basins cum 9.64

Estimated Direct Cost(EDC)

Labor

Foreman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

4 Filling and Grading cum 67.80

Estimated Direct Cost(EDC)

Materials

Earthfill cum 67.80

Sub-total

Labor

Foreman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Page 5: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Page 6: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Total Cost

UNIT COST

III

a. sqm 545.00

Estimated Direct Cost(EDC)

Materials

4" thk CHB pcs 6,540

Sub-total

Labor

Foreman m-d

Mason m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

b. sqm 317.22

Estimated Direct Cost(EDC)

Materials

6" thk CHB pcs 3,807

Sub-total

Labor

Foreman m-d

Mason m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

c. Plastering and Mortar Filling sqm 1,482.00

Estimated Direct Cost(EDC)

Materials

Portland cement (40kg) pcs 650

Washed Sand cum 73

Sub-total

Labor

Foreman m-d

Mason m-d

Laborer m-d

Sub-total

6" Wall CHB laying

MASONRY WORKS

4" Wall CHB laying

Page 7: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

Page 8: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

VAT

Total Indirect Cost

Total Cost

UNIT COST

IV

a. Concreting

1 Column and Column Footing cum 16.67

Estimated Direct Cost(EDC)

Materials

Portland Cement bags 150

Washed Sand cum 8

Washed gravel cum 15

Sub-total

Labor

Foreman m-d

Mason m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

2 Wall Footing cum 2.00

Estimated Direct Cost(EDC)

Materials

Portland Cement bags 18

Washed Sand cum 1

Washed gravel cum 2

Sub-total

Labor

Foreman m-d

Mason m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

3 Beams and Footing Tie Beam cum 15.60

Estimated Direct Cost(EDC)

Materials

Portland Cement bags 140

CONCRETE WORKS

Page 9: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Washed Sand cum 8

Washed gravel cum 16.00

Sub-total

Labor

Foreman m-d

Mason m-d

Page 10: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

4 Slab cum 30.00

Estimated Direct Cost(EDC)

Materials

Portland Cement bags 242

Washed Sand cum 15

Washed gravel cum 30

Sub-total

Labor

Foreman m-d

Mason m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

5 Stairs cum 3.80

Estimated Direct Cost(EDC)

Materials

Portland Cement bags 36

Washed Sand cum 2

Washed gravel cum 4

Sub-total

Labor

Foreman m-d

Mason m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Page 11: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Total Cost

UNIT COST

V

a. Structural Reinforcement Bar

1 Column kgs 3,797.72

STEEL WORKS

Page 12: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Estimated Direct Cost(EDC)

Materials

16mmф x 6m Steel bar pcs 276

10mmф x 6m Steel bar pcs 320

Tie Wire # 16 kgs 18

Sub-total

Labor

Foreman m-d

Steelman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

2 Column Footing kgs 426.15

Estimated Direct Cost(EDC)

Materials

16mmф x 6m Steel bar pcs 45

Tie Wire # 16 kgs 10

Sub-total

Labor

Foreman m-d

Steelman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

3 Second Floor and Roofdeck Beams kgs 2,560.08

Estimated Direct Cost(EDC)

Materials

16mmф x 6m Steel bar pcs 184

10mmф x 6m Steel bar pcs 221

Tie Wire # 16 kgs 30

Sub-total

Labor

Foreman m-d

Steelman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Page 13: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Page 14: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Total Cost

UNIT COST

4 Slab/Stairs kgs 3,835.33

Estimated Direct Cost(EDC)

Materials

12mmф x 6m Steel bar pcs 621

10mmф x 6m Steel bar pcs 142

Tie Wire # 16 kgs 40

Sub-total

Labor

Foreman m-d

Steelman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

5 Masonry Wall Steel Reinforcement kgs 2,062.70

Estimated Direct Cost(EDC)

Materials

10mmф x 6m Steel bar pcs 537

Tie Wire # 16 kgs 30

Sub-total

Labor

Foreman m-d

Steelman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

VI

a. sqm 96.00

Estimated Direct Cost(EDC)

Materials

2 X 2 X 1/4 X 6 m angle bar pcs 75

2 X 2 X 3/16 X 6 m angle bar pcs 16

2 X 2 X 1/8 X 6 m angle bar pcs 25

Steel Plate 4' x 8' x 12mm pcs 1

METAL WORKS

Steel Truss

Page 15: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

1 x 1/8 x 6m flat bar pcs 5

1 x 1 x 1/8 x 6m angle bar pcs 9

Anchor Bolt 20mm dia x 300mm pcs 32

Welding Rod kgs 50

Sub-total

Labor

Foreman m-d

Page 16: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Steelman/Welder m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

b. sqm 96.00

Estimated Direct Cost(EDC)

Materials

Channel Purlin 2 x 4 pcs 50

12mm dia Plain Steel Bar (sagrod) pcs 16

10mm dia Plain Steel Bar (sagrod) pcs 13

1/2" x 8" Turn Buckle pcs 14

Welding Rod kgs 15

Sub-total

Labor

Foreman m-d

Steelman/Welder m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

c. lnm 200.00

Estimated Direct Cost(EDC)

Materials

0.5mm thk. Long span roofing (pre-painted) lnm 183.00

Pre-fabricated colored ridge roll, 0.50mm x

0.457mm x 2.44mpcs 16

Pre-fabricated colored gutter, 0.50mm x

0.610mm x 2.44mpcs 22

10mm thick double sided aluminum foil

insulatorlnm 183.00

12mm x 300mm x 2440mm cement board pcs 21

1"x1" Plastic Screen lin m 182

Texscrew pcs 1,183

Blind rivets pcs 1,016

Silicon sealant ctdgs 6

Touch-up paint can 2

Aluminum duct tape rolls 9

Steel Purlins

Roofing

Page 17: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Ga. 16 G.I. Tie wire kgs 20

Sub-total

Labor

Foreman m-d

Steelman/Tinsmith m-d

Laborer m-d

Page 18: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

d. lnm 234.00

Estimated Direct Cost(EDC)

Materials

2 inches diameter Stainless Pipe, sch40 pcs 10

25mm x 6m Plain Round Bar pcs 32

16mm x 6m Square Bar pcs 17

25mm x 6m x 6mm thk Flat Bar pcs 6

Ordinary Welding Rod kls 10

S/S Welding Rod kls 6

Sub-total

Labor

Foreman m-d

Steelman/Welder m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

e. lot 1.00

Estimated Direct Cost(EDC)

Materials

4-layered Steel Shelving with Steel Frames

and bracessets 2

Steel Accordion Door: Closed Type with

Heavy Duty Padlocksets 2

Steel Sliding Door (Double) with Upper &

Lower Steel Track & Roller/Hangersets 2

Expansion Bolts pcs 12See trough Steel Accordion Door: Closed

type with heavy duty padlock (3.5m x 2.6m)

entance door

set 1

See trough Steel Accordion Door: Closed

type with heavy duty padlock (1.4m x 2.6m)

exit door

set 1

Steel Security Grills (entrance & exit) lot 1

Steel Grills Handrail & Railings

Steel Cabinet with Accordion Door and Steel

Security Grills (entrance & exit)

Page 19: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Sub-total

Labor

Foreman m-d

Steelman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

VII

a. units 19.00

Estimated Direct Cost(EDC)

Materials

D-1 ;Alum swing door, powder coated (blue):

Tinted glass; 3.50m x 2.45mpcs 1

D-2 ; Panel door with slight carvings; 2" x 5"

door lamb; 0.90m x 2.10m; with door closerpcs 6

D-3 ; Panel door with slight carvings; 2" x 5"

door jamb; 0.80m x 2.10m; with door closerpcs 2

D-4 ; PVC Flush door with louver; 2" x 5"

door jamb with door closer; 0.70m x 2.10mpcs 3

D-5 ;Alum swing door, powder coated (blue):

Tinted glass; 0.90m x 2.45mpcs 1

D-6 ; Steel door with steel jamb & glass;

0.80m x 2.10mpcs 1

D-7 ;Steel grill door with 25mm dia plain

round bar; 0.80m x 2.10mpcs 2

D8.1 ;Steel grill door with 25mm dia plain

round bar;double lock & with receiving

counter 0.80m x 2.10m

pcs 1

D8.2 ;Steel door with steel door jamb &

louver; 0.80m x 2.10mpcs 2

Sub-total

Labor

Foreman m-d

Carpenter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

DOORS AND WINDOWS

Doors

Page 20: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Total Cost

UNIT COST

b. sets 91.00

Estimated Direct Cost(EDC)

Materials

W-1 ; Steel casement window, 2.10m x

1.55msets 6

W-2 ; Steel casement window, 1.40m x

1.55msets 7

W-3 ; Steel awning window, 0.50m x 0.35m sets 3

W-4 ; Steel grills window, 1.20m x 0.35m sets 2

W-5 ; Steel awning window, 1.40m x 0.50m set 1

W-6 ; Glass Blocks, 0.20m x 0.20m pcs 72

Sub-total

Labor

Foreman m-d

Installer m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

VIII

a. Forming

1 Column cum 21.00

Estimated Direct Cost(EDC)

Materials

2''x2''x12' Cocolumber bdft 1,166

1/4"thk marine plywood pcs 40

CWN, assorted kgs 30

Sub-total

Labor

Foreman m-d

Carpenter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

CARPENTRY WORKS

Windows

Page 21: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

2 Footing Tie Beam cum 6.00

Estimated Direct Cost(EDC)

Materials

2''x2''x12' Cocolumber bdft 470

1/4"thk marine plywood pcs 15

CWN, assorted kgs 12

Sub-total

Labor

Foreman m-d

Carpenter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Page 22: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Total Indirect Cost

Total Cost

UNIT COST

3 Beam cum 16.00

Estimated Direct Cost(EDC)

Materials

2''x2''x12' Cocolumber bdft 880

2''x3''x12' Cocolumber bdft 750

1/4"thk marine plywood pcs 46

CWN, assorted kgs 25

Sub-total

Labor

Foreman m-d

Carpenter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

4 Slab sqm 192.00

Estimated Direct Cost(EDC)

Materials

2''x2''x12' Cocolumber bdft 960

2''x3''x12' Cocolumber bdft 1,200

1/2"thk marine plywood pcs 51

CWN, assorted kgs 28

Sub-total

Labor

Foreman m-d

Carpenter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

b. Sqm 332.00

Estimated Direct Cost(EDC)

Materials

4.5mm thk. Cement board pcs 109

Double furring, 50mm x 5m pcs 225

Ceiling Installation (1st, 2nd & 3rd floor)

Page 23: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Carrying Channel, 40mm x 5m pcs 86

Wall Angle, 25mm x 25mm x 3m pcs 129

W-Clip pcs 346

Rivets, 1/8" x 1/2" box 5

Black Screw, 1" pcs 2602

Drill Bit, 9/64 (metal) pcs 13

Page 24: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Drill Bit, 1/8 (masonry) pcs 13

Screw Bit, single pcs 13

Metal Ceiling, spandrel sqm 11

Sub-total

Labor

Foreman m-d

Carpenter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

c. Cabinetry Works & Information Counter Desk sq.m 2.00

Estimated Direct Cost(EDC)

Materials

3/4" thick Marine Plywood pcs 12

2" x 2" x 12' Good Lumber pcs 6

Termite Control/Wood Preservative gals 1

1/2" x 1" x 8' S4S KD Wood Edging pcs 10

Assorted CW Nail kls 1

1" Finishing Nail kls 1

3" Concrete Nail kls 1

Sliding door tracks and rollers sets 2

Wood Glue lit 4

Drill Bit, 1/8 (masonry) pcs 4

Sub-total

Labor

Foreman m-d

Carpenter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

IX

a. Waterproofing sqm 9.00

Estimated Direct Cost(EDC)

Materials

Cementitious Waterproofing gals 3

Paint brush pcs 2

TILE WORKS

Page 25: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Sub-total

Labor

Foreman m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Page 26: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

b. sqm 420.00

Estimated Direct Cost(EDC)

Materials

Floor Tiles, 60cm x 60cm, (Glazed) pcs 1195

Granite Tiles 40cm x 40cm pcs 6

Tile adhesive bags 162

Tile grout kgs 30

Stair brass nosing lnm 20

Rubberized stair nosing pcs 45

Sub-total

Labor

Foreman m-d

Mason/tile setter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

c. Comfort Room sqm 60.57

Estimated Direct Cost(EDC)

Materials

Floor Tiles, 30cm x 30cm, unglazed pcs 150

Wall Tiles, 30cm x 30cm, glazed pcs 381

Tile adhesive bags 15

Tile grout kgs 8

Tile trim pcs 12

Sub-total

Labor

Foreman m-d

Mason/tile setter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

Floors (1st, 2nd & 3rd), Stairs, landing, Porch

and Quality Service Countertop

Page 27: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

VAT

Total Indirect Cost

Total Cost

UNIT COST

X

a. lot 1.00

Estimated Direct Cost(EDC)

Materials

20mm dia. PVC Pipe Sch 40 pcs 190

20mm dia. Elbow pcs 120

25mm dia. PVC Pipe Sch 40 pcs 50

25mm dia. Elbow pcs 30

50mm dia. Elbow pcs 21

40mm dia RSC Pipe pcs 2

40mm dia RSC Elbow pcs 1

50mm dia RSC Pipe pcs 2

63mm dia RSC Pipe pcs 3

63mm dia RSC Pipe pcs 6

63mm dia RSC Coupling pcs 2

63mm dia RSC Elbow pcs 3

63 mm dia RSC Adapter pcs 1

Junction box pcs 121

Utility box pcs 110

Copper clad steel rod 16mm dia 2400mm pcs 1

Electrical tape (big) rolls 41

G.I. wire ga. #18 kgs 11

Sub-total

Labor

Foreman m-d

Electrician m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

b. lot 1.00

Estimated Direct Cost(EDC)

Materials

2.0 mm² THHN/THWN copper wire box 6

3.5 mm² THHN/THWN copper wire box 12

5.5 mm² THHN/THWN copper wire box 3

14 mm² THHN/THWN copper wire lnm 10

22 mm² THHHN/THWN copper wire lnm 30

38 mm² THHN/THWN copper wire lnm 10

60 mm² THHN/THWN copper wire lnm 15

100 mm² THHN/THWN copper wire lnm 60

ELECTRICAL WORKS

Electrical Roughing-ins

Electrical Accessories & Wirings

Page 28: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Sub-total

Labor

Foreman m-d

Electrician m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

Page 29: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

UNIT COST

c. sets 156.00

Estimated Direct Cost(EDC)

Materials

1x18W LED Tube in box type casing sets 12

2x18W LED Tube in 1'x4' casing w/ diffuser sets 13

LED covelight/downlight 4" sets 22

CFL w/ Lamp Holder 4" sets 5

LED Emergency Light sets 6

Wall lamp set 1

Lamp Post sets 7

ACU Outlet with ground sets 9

Single convenience outlet w/ ground sets 6

Duplex convenience outlet w/ ground sets 28

Duplex weatherproof convenience outlet w/

groundsets 8

Single pole switch sets 10

2-single pole switch in 1-gang sets 6

3-single pole switch in 1-gang sets 8

3-way switch, i-controlled fixture sets 8

Pull box 10"x10"x4" sets 4

Secondary rack 3-spool set 1

Manual transfer switch, breaker type, 250 AF with 200 AT CB, 2-pole, 240V, 60Hz with grounding lugsset 1Panel Board 12B, 100AF with 100 AT Main

CB, 3-15 AT 3-20AT, 4-30AT Bolt on, Center

Main, 2-pole, 240V, 60 Hz with grounding

lugs.

set 1

Panel Board 14B, 200AF with 125 AT Main

CB, 3-15 AT 7-20AT, 4-30AT Bolt on, Center

Main, 2-pole, 240V, 60 Hz with grounding

lugs.

set 1

Sub-total

Labor

Foreman m-d

Electrician m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

d. lot 1.00

Estimated Direct Cost(EDC)

Materials

63 mm dia Entrance Cap sets 2

25 mm dia Entrace Cap w/ adapter sets 2

Concrete Electrical Post sets 1

Transformer 15kVA unit 1

Electrical Fixtures

Electrical Power Service

Page 30: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Installation fee unit 1

Transformer bracket units 2

Cut-out and arrester assembly set 1

Cut-out bracket unit 1

Service & inspection fee unit 1

Electric meter class 200 unit 1

Meter base class 200 unit 1

Metering accessories unit 1

Grounding rod pc 1

Sealing lead pcs 2

Security deposit unit 1

Membership fee unit 1

Sub-total

Labor

Foreman m-d

Electrician m-d

Laborer m-d

Page 31: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

XI

a lot 1

Estimated Direct Cost(EDC)

Materials

1ft wall mount data cabinet unit 1

Horizontal wire manager unit 1

Dual band gigabit router/ LTE CPE

broadband routerunit 1

24-port fast ethernet network switch

(rackmountable)unit 1

300 Mbps wireless N router unit 2

CAT6 unshielded twisted pair cable

(4 pairs)rolls 2

CAT6 patch cord (2 meters) pcs 24

CAT6e I/O modular jack with faceplate sets 24

CAT6 rubber boot pcs 120

CAT6 RJ45 connector pcs 120

CAT3 unshielded twisted pair cable

(4 pairs)mtrs 160

CAT3 I/O modular jack with faceplate sets 8

CATV F-nut modular jack with faceplate sets 8

RG6 coaxial cable mtrs 150

BNC F-nut connector pcs 30

3-way CATV splitter pcs 4

2" PVC pipe pcs 2

2" Tee connector pcs 4

2" Elbow connector pcs 4

1 & 1/2" PVC pipe pcs 3

1 & 1/2" Tee connector pcs 4

1" PVC pipe pcs 8

1" Tee connector pcs 6

3/4" PVC Pipe pcs 12

3/4 Tee connector pcs 4

3/4 Elbow connector pcs 7

1/2" PVC pipe pcs 16

1/2" Elbow connector pcs 25

2" x 1" PVC reducer pcs 4

2" x 1 & 1/2" PVC reducer pcs 6

1 & 1/2" x 1" PVC reducer pcs 6

1" x 3/4" PVC reducer pcs 8

1" x 1/2" PVC reducer pcs 4

3/4" x 1/2" PVC reducer pcs 12

8" x 8" pull box pcs 4

Utility box pcs 14

INTERNET/COMMUNICATION LINE

Data, Voice and CaTV Peripherals and Active

Page 32: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

G.I wire ga. #18 kgs 6

Expansion shield with expansion bolt and

washersets 4

Sub-total

Labor

IT technician m-d

Helper m-d

Sub-total

Total Estimated Direct Cost

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-Total

VAT

Total Indirect Cost

Total Cost

UNIT COST

XII.

a.

1 Water Supply Lines lnm 24.00

Estimated Direct Cost(EDC)

Materials

12mmX4m PPR pipe pcs 12

20mmX4m PPR pipe pcs 8

12mm Plain Tee pcs 30

20mm Plain Tee pcs 8

12mm Plain Tee Reducer pcs 5

20mm Plain Tee Reducer pcs 5

12mm PPR Couplings pcs 20

20mm PPR Couplings pcs 7

12mm elbow w/ Thread Control Valve pcs 7

20mm elbow w/ Thread Control Valve pcs 8

12mm plain Elbow pcs 12

20mm plain Elbow pcs 13

12mm Tee with thread for faucet pcs 3

20mm Tee with thread pcs 5

12mm elbow with thread for Shower pcs 5

20mm elbow with thread pcs 12

PPR Connecting Machine pc 1

Teflon tape roll 5

Sub-total

Labor

Foreman m-d

Plumber m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Water Supply

PLUMBING WORKS

Page 33: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Total Indirect Cost

Total Cost

UNIT COST

2 Water Supply Fixtures sets 36.00

Estimated Direct Cost(EDC)

Materials

12 mm faucets pcs 6

12 mm control valve pcs 4

20 mm control valve pcs 2

12 mm Flexible supply hose pcs. 18

Soap Holder pcs 3

Towel bar pcs 3

Page 34: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Sub-total

Labor

Foreman m-d

Plumber m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

3 Water Supply Equipments unit 1.00

Estimated Direct Cost(EDC)

Materials

500 gals Overhead water tank, s/s with

stand and float valve w/ 1HP motor pump unit 1

Sub-total

Labor

Foreman m-d

Plumber m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

4 Sewer Lines lnm 40.00

Estimated Direct Cost(EDC)

Materials

100 mmф x 3 m PVC pipe pcs 11

75 mmф x 3 m PVC pipe pcs 35

50 mmф x 3 m PVC pipe pcs 14

100mmф PVC Clean Out pcs 13

75mmф PVC Clean Out pcs 10

100mmф PVC Elbow, 1/4 bend pcs 8

75mmф PVC Elbow, 1/4 bend pcs 36

50mmф PVC Elbow, 1/4 bend pcs 19

100mmф PVC Elbow, 1/8 bend pcs 14

75mmф PVC Tee pcs 5

50mmф PVC Tee pcs 10

100x50mmф PVC Tee pcs 8

100mmф PVC Y pcs 19

100x75mmф PVC Y pcs 8

Page 35: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

100x50mmф PVC Y pcs 4

75mmф PVC P-Trap pcs 5

50mmф PVC P-Trap pcs 5

Solvent Cement pcs 10

Sub-total

Labor

Page 36: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Foreman m-d

Plumber m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

5 Sanitary Fixtures units 36.00

Estimated Direct Cost(EDC)

Materials

Water closet (White) pcs 3

Lavatory,Wall Mounted (White) pcs 3

Toilet bowl (Pail type) pcs 2

Urinal pcs 2

Shower Head pcs 3

Shower Faucet pcs 3

Shower Valve pcs 3

Faucet, ordinary pcs 2

Faucet, hose bibb pcs 2

Floor drain,4" x 4", brass pcs 13

Shower curtain pcs 3

20mm dia Curtain Rod, stainless mtrs 3

Sub-total

Labor

Foreman m-d

Plumber m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

6 Drainage Lines lnm 40.00

Estimated Direct Cost(EDC)

Materials

150mmф x 3 m PVC pipe pcs 19

150mmф PVC cleanout pc 1

150mmф PVC wye pc 1

150mm PVC elbow pcs 2

Sub-total

Labor

Page 37: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Foreman m-d

Plumber m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Page 38: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

XIII.

a. sqm 544.00

Estimated Direct Cost(EDC)

Materials

Masonry

Neutalizer gals 8

Flat Latex Paint gals 25

Semi Gloss latex gals 20

PNP Blue gals 10

Roller Brush w/ Pan pcs 10

Paint Brush (Assorted) pcs 10

Skim Coat bags 49

Sand Paper doz 16

Sub-total

Labor

Foreman m-d

Painter m-d

Helper m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

b sqm 332.00

Estimated Direct Cost(EDC)

Materials

Flat Latex paint gals 34

Gloss latex gals 38

Roller Brush w/ Pan, #7 pcs 12

Paint Brush (3'') pcs 10

Sand Paper doz 30

Sub-total

Labor

Foreman m-d

Painter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

PAINTING WORK

Masonry wall & Roofdeck Slab

Ceiling

Page 39: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

c lot 1.00

Estimated Direct Cost(EDC)

Materials

Red Oxide Primer gals 4

Quick drying enamel gals 4

Paint Thinner gal 1

Paint Brush 4'' pcs 4

Paint Brush 3'' pcs 4

Sand Paper doz 12

Sub-total

Labor

Foreman m-d

Painter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

d lot 1.00

Estimated Direct Cost(EDC)

Materials

QDE tin 1

Flatwall Enamel tin 1

Paint Thinner gals 6

Tinting Color qrt 2

Paint Brush, assorted pcs 4

Stopa Rug kgs 3

Sand Paper doz 8

Sub-total

Labor

Foreman m-d

Painter m-d

Laborer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

Metal

Wood

Page 40: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

UNIT COST

XIV. lot 6.00

Estimated Direct Cost(EDC)

MaterialsPanaflex Building Signboard with backlight lot 1Directory Board with stand lot 1

1 1/2" x 3m dia GI Pipe (Sch 40) Flagpole to

include flaglot 1

8"x11"x3/16"thk Comm Brass Marker lot 1

DELIVERABLES

Page 41: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex

PVC Foldable Partition Wall lot 2

Sub-total

Labor

Foreman m-d

Installer m-d

Sub-total

Estimated Direct Cost (EDC)

Indirect Cost(IDC)

Overhead, Contingency, & Miscellaneous

Contractor's Profit

Sub-total

VAT

Total Indirect Cost

Total Cost

UNIT COST

TOTAL COSTTOTAL BID AMOUNT: ₱_____________________________________________

TOTAL BID AMOUNT (IN WORDS): ______________________________________________

_________________________________________________________________

Submitted by:

___________________Contractor

Page 42: PROJECT: CONSTRUCTION OF STANDARD TYPE B/C MOTIONG …€¦ · 30. Installation of 1 1/2"dia. G.I. pipe (Sch 40) flagpole and flag on top of canopy; 31. Installation of 3'x8' panaflex