project advisory committee meeting - pg&e3 introductions • project advisory committee members...

22
Hunters Point Site Project Advisory Committee Meeting October 27, 2015 1

Upload: others

Post on 14-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Hunters Point Site Project Advisory Committee Meeting

October 27, 2015

1

Page 2: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

2

Agenda

• Welcome and Introductions

• Safety Moment

• Project Status

• Upcoming/Current Work

• NOW Hunters Point/Interim Uses

• Local Hiring

• Continued Communications

• Q&A

2

Page 3: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

3

Introductions

• Project Advisory Committee Members

• PG&E

‐ Rob Saur, Remediation Project Manager

‐ Andrea Gooden, Manager, Stakeholder Engagement

‐ Susana Razo, Communications Lead

• Contractors

‐ JBR Partners – James Bryant (Community Outreach)

‐ ERM – John Cavanaugh (Remediation Contractor)

‐ ERM – Rob Dyer (Remediation Contractor)

‐ envelope a+d – Nathan John (Architect)

‐ envelope a+d – Allegra Madsen (Program Designer)

3

Page 4: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

4

Committed to Safety

4

• Room Safety

• Site Safety

• Public Safety

Temporary walkway provides pedestrian safety during Area J work

Page 5: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Hunters Point Site

5

Page 6: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

6

Project Status

6

• Groundwater cleanup work: Completed. Monitoring and polishing work ongoing

• Area J Retaining Wall Area: Cleanup underway. Complete early 2016.

• Shoreline Area: Awaiting final permits

• Interim use events: Ongoing

Page 7: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Groundwater Treatment Program

7

• Treatment of the off-site area (White Cap and Jennings) completed at the end of 2014

• Polishing work ongoing • Periodic monitoring and sampling to

confirm treatments are effective

•DTSC oversight and confirmation

Groundwater Monitoring Area

Off-Site Groundwater Remediation Area

Page 8: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

8

Area J – Retaining Wall Area Cleanup

8

• Majority of Area J soil cleanup completed in 2011

• Excavating soil near the retaining

wall and installing a durable cover

• Air monitoring and dust control during soil disturbing work

• Anticipated completion: early 2016

Page 9: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

9

Area J Cleanup Pedestrian/Auto Safety

9

Page 10: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

10

Air Monitoring and Dust Control

• Air monitoring and dust control during soil disturbing work

- Perimeter misters - Manual misters - Air monitors - Covered stockpiles and trucks

• Targeted mindful use of water;

misters with specialized nozzles • Air monitoring results reported to

BAAQMD, uploaded to www.pge.com/hunterspoint

10

Page 11: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Area J – Streetscape Improvements

•New pedestrian plaza at the corner of Evans Ave. and Jennings St.

•Neighborhood public space

•New plaza will serve as overlook to Site and Bay

11

Page 12: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

12

Area J – Streetscape Improvements

Page 13: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

13

Shoreline Area Cleanup

13

• Cleanup to address impacted soils in

parts of the Shoreline Area • Restoration to follow Cleanup • Performed over two construction

seasons (September 1 - January 31) • Permitting with USACE, Regional

Board, BCDC, and other agencies

• DTSC Work Notice to be distributed before work begins

Page 14: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Shoreline Area Cleanup: Soil Removal

• Planning to begin soil removal in November, pending receipt of permits

• Removal of top two feet of accessible soil (in six

areas)

• Off-site soil disposal, covered trucks using established truck routes

• Clean soil or rock placed where impacted soil is removed

• Air monitoring, dust control and soil management

14

Page 15: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Shoreline Area Cleanup: Restoration

• Begin in Fall 2016 • Enhanced public path and

other features

15

Page 16: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Interim Uses: NOW Hunters Point

16

• Launched in 2013

• Local youth + labor (APRI / JBR)

• 29 events to date

• First evening events, job

training, health activities

• Over 4,000 participants Learn more: www.nowhunterspoint.org

16

Page 17: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

17

Page 18: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Local Hiring

• Local Hiring Goal: 30 percent • Use of local contractors when

possible • Coordinate local hires with SF

CityBuild program (415-701-4889)

• PG&E worker requirements:

www.pge.com/hunterspoint - Go to Local Jobs tab

18

Page 19: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Ongoing Communications

• Email updates

• PAC Meetings + Follow-Up

• Newsletters • PGE.com/hunterspoint • Project Hotline/Email

June 2015 PAC Meeting

19

Page 20: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

For More Information (Cleanup):

• Environmental Remediation Response Line: 1-866-247-0581

• Project Email: [email protected]

• Project Website: www.pge.com/hunterspoint

Interim Use Team:

• NOW Hunters Point: (415) 644-5883; [email protected]

• Website: www.nowhunterspoint.org

California Department of Toxic Substances Control Contacts:

• Robert (Bob) Boggs: (510) 540-3751; [email protected]

• Wayne Hagen: (510) 540-3911; [email protected]

Contacts

20

Page 21: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

• Customer Service: 1-800-743-5000 (1-800-PGE-5000)

• Electric Outage Information: 1-800-743-5002

• IF YOU SMELL NATURAL GAS, see downed power lines, or suspect another emergency situation, leave the area immediately and then call 9-1-1 and PG&E at 1-800-743-5000.

PG&E Contacts

21

Page 22: Project Advisory Committee Meeting - PG&E3 Introductions • Project Advisory Committee Members • PG&E ‐ Rob Saur, Remediation Project Manager ‐ Andrea Gooden, Manager, Stakeholder

Thank You!