progress report june 2017 -...

6
Progress report June 2017

Upload: others

Post on 09-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of

Progress report June 2017

Page 2: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of

BLOCK – E

Page 3: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of

BLOCK – E UPDATES• External Block work completed till 14th Floor

• Internal Block work in 11th, 12th,13th & 14th floor work is in progress.

• Lintel work in progress for 10th Floor.

• Door Frame installation work in progress.

• Plumbing work in progress.

• Internal plastering work completed till 3rd Floor.

• 4th Floor Plastering work is in progress.

• Electrical conducting work in progress.

• Ceiling plastering and Bathroom Rough Plastering work is in

progress at 7th Floor.

• Block work for Electrical panel room in stilt floor completed and

plastering work is in progress.

• Meter panel inspection completed for D & E Block , delivery of the

panels are expected shortly.

Page 4: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of

BLOCK – E UPDATES

Lintel works is in progress

Page 5: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of

BLOCK – E UPDATES

Internal Block works is in progress

Page 6: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of

BLOCK – E UPDATES

Bathroom rough plastering & Electrical room plastering work is in progress