Progress report June 2017
BLOCK – E
BLOCK – E UPDATES• External Block work completed till 14th Floor
• Internal Block work in 11th, 12th,13th & 14th floor work is in progress.
• Lintel work in progress for 10th Floor.
• Door Frame installation work in progress.
• Plumbing work in progress.
• Internal plastering work completed till 3rd Floor.
• 4th Floor Plastering work is in progress.
• Electrical conducting work in progress.
• Ceiling plastering and Bathroom Rough Plastering work is in
progress at 7th Floor.
• Block work for Electrical panel room in stilt floor completed and
plastering work is in progress.
• Meter panel inspection completed for D & E Block , delivery of the
panels are expected shortly.
BLOCK – E UPDATES
Lintel works is in progress
BLOCK – E UPDATES
Internal Block works is in progress
BLOCK – E UPDATES
Bathroom rough plastering & Electrical room plastering work is in progress