programmes of work for core unit 2002
TRANSCRIPT
Programmes of WorkProgrammes of workProgrammes of work show the actual sequence of any work activities on a construction project. Part of the work programme plan is to show target times.
They are usually shown in the form of a bar or Gantt chart (a special kind of bar chart), as can be seen in Fig 2.8. on the following slide
Example of House Building Programme of Work
In this figure: * On the left hand side all of the tasks are listed – note this is in logical Order
* On the right the blocks show the target start and end date for each of the individual tasks
* The timescale can be days, weeks or months.
Gantt Chart
Far more complex forms of work programmes can also be created. The Gantt chart shown below (Fig 2.9) shows the construction of a house.
This is a more complex example of a bar chart: There are two lines – they show the target dates and actual dates.
The actual dates are shaded, showing when the work actually began and how long it actually took.
If this bar chart is kept up to date an accurate picture of progress andestimated completion time can be seen.
(Fig 2.9)Gantt Chart