procurement, installation and commissioning of
TRANSCRIPT
PROCUREMENT, INSTALLATION AND COMMISSIONING
OF
INSTRUMENTATION SYSTEM FOR BULK STORAGE
FACILITIES
ISRO PROPULSION COMPLEX
Indian Space Research Organization
Department of Space, Government of India
Mahendragiri 627 133
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
TABLE OF CONTENTS
SL:NO CHAPTER PAGE NO
ANNEXURE A SCOPE OF WORK & SERVICES
1 Introduction 1
2 Instrumentation system requirements for BSF 1
3 Scope of contract 11
ANNEXURE -1 Control room layout 45
ANNEXURE -2 Instrumentation System Configuration andschematic diagram
48
ANNEXURE -3 Instrumentation rack General Assembly drawing 60
ANNEXURE -4 Specification & Sub-vendor directory 65
ANNEXURE -5 Free Issue Items 173
ANNEXURE -6 T & E Sheet format 174
ANNEXURE-7 Process & Instrumentation Diagrams And Layout 178
ANNEXURE B PRICE FORMAT 181
ANNEXURE C TERMS AND CONDITIONS 202
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
1 | P a g e 2 2 2
1. INTRODUCTION
Bulk Storage Facilities (BSF) is planned to be established at IPRC,
Mahendragiri as a part of semi-cryo project. This facility caters to the
requirement of storing propellants which will be used for various activities.
The Instrumentation System for Bulk Storage Facilities is divided into two
work packages namely Field & Control room Instrumentation and Control
System.
This document defines the scope & basic requirements for realization of Field& control room Instrumentation for Bulk Storage Facility (BSF). BSF includes
Isrosene Storage Facility (ISF)LOX Storage Facility (LOX SF)LIN Storage Facility (LIN SF)GHe Storage Facility (GHe SF)
These storage facilities are distributed in various locations with separateindividual control rooms.The scope of this work package includes detailed engineering, equipments &materials supply, installation & wiring of field elements, wiring ofinstrumentation racks, erection of cable trays, laying of cables on cable trays,testing & evaluation of instrumentation system and documentation for BSFinstrumentation system.
2. INSTRUMENTATION SYSTEM REQUIREMENT FOR BSF
2.1. DEFINITION OF FIELD & CONTROL ROOM INSTRUMENTATIONThe Field & Control room Instrumentation system includes four subsystems namely Measurement System, Safety System, CommandSystem and Auxiliary System. Field refers to the location where thestorage tanks and its associated fluid systems are located. Fieldelements refer to pressure transmitter, guided wave level sensors,temperature probes, temperature transmitters, mass flow meters,junction boxes, Solenoid Valves (SOV), SOV cubicle, camera etc locatedin field. In control room, the signal conditioners, relays, powersupplies, instrumentation racks, consoles etc will be located.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
2 | P a g e 2 2 2
2.2. INSTRUMENTATION SYSTEM – CHANNEL WISEREQUIREMENTS
Sl. No System ISF LOX LIN GHE TotalA Facility Measurement System1 Absolute Pressure,
Differential Pressure(DP) & DP based Level
30 8 16 4 58
2 Guided wave radarbased level
8 8
3 Temperature 7 8 154 Flow 2 25 Current/ voltage 3 3
Sub Total-1 47 8 27 4 86B Safety System4 UV/IR Flame Detectors 12 125 Hydrocarbon Gas
Detection10 10
6 Oxygen gas detection 2 5 1 8Sub Total-2 22 2 5 1 30
C Command System7 E/P valve 59 598 Flow Switch 5 59 Pressure switch 9 9
10 Control valve 1 1Sub Total-3 65 9 74
D Auxiliary System11 CCTV 6 2 3 2 1312 Wired Inter Com Units 6 1 3 2 1213 Wireless
Communication Units6 2 3 2 13
Sub Total-4 18 5 9 6 38Total 152 15 50 11 228
The instrumentation system configuration diagram for each of theabove storage facilities is given in Fig. No 1 to 4 of Annexure 2.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
3 | P a g e 2 2 2
2.3. INSTRUMENTATION SYSTEM WISE REQUIREMENTS2.3.1. Measurement system
Pressure/DP Based Level measurement system
This measurement is used for monitoring the storage tank & fluid line
pressure/Level.
The SMART pressure transmitters (Absolute & Differential) with built
in electronics senses the pressure and converts the sensed pressure to a
corresponding 4 to 20mA electrical signal.
The 4 to 20mA output is wired to intrinsic safe Transformer Isolated
Barrier (TIB). TIBs are powered from 24V DC linear power supply.
The TIBs and 24V DC linear power supply are housed inside
instrumentation rack.
For ISF & LINSF, the output of TIB is given to Control system for
acquisition and monitoring. Selected channels are wired to Data logger
also. Schematic is shown in Annexure 2- Fig.No:5
For other storage facilities, the output of TIB is wired to Data logger
alone. Schematic is shown in Annexure 2- Fig.No:5A.
Guided wave radar based Level measurement system
This measurement is used for monitoring the storage tank level.
The guided wave radar based sensor with built in electronics senses
the level and converts to a corresponding 4 to 20mA electrical signal.
The 4 to 20mA output is wired to intrinsic safe Transformer Isolated
Barrier (TIB). TIBs are powered from 24V DC linear power supply.
The TIBs and 24V DC linear power supply are housed inside
instrumentation rack.
For ISF, the output of TIB is given to Control system for acquisition
and monitoring. Selected channels are wired to Data logger also.
Schematic is shown in Annexure 2- Fig.No:6
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
4 | P a g e 2 2 2
Temperature (RTD based) measurement system.
This measurement chain is used for monitoring the storage tank &
fluid line temperature.
4 wire RTDs are used as sensors. The sensors are interfaced to
temperature transmitters.
The 4 to 20mA output of temperature transmitters is wired to intrinsic
safe TIB. TIBs are powered from 24V DC linear power supply. The
TIBs and 24V DC linear power supply are housed inside
instrumentation rack.
For ISF & LINSF, the output of TIB is given to Control system for
acquisition and monitoring. Schematic is shown in Annexure 2-
Fig.No:7.
Facility flow measurement system
This measurement is used for measuring the flow rate in fluid lines.
The 4 to 20mA output of flow transmitters is wired to intrinsic safe
TIB. TIBs are powered from 24V DC linear power supply. The TIBs
and 24V DC linear power supply are housed inside instrumentation
rack.
For ISF, the output of TIB is given to Control system for acquisition
and monitoring. Schematic is shown in Annexure 2- Fig.No:8.
The scope involves procurement, installation & wiring of field
elements, impulse tubing, erection of cable trays, signal cable laying on
cable trays, wiring of instrumentation rack and interfacing between
racks.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
5 | P a g e 2 2 2
2.3.2. Safety Instrumentation systemOxygen detector system.
The Oxygen presence is continuously monitored by using oxygen
detectors.
Totally 8 numbers of monitors are planned for LIN SF, LOXSF & GHe
SF.
The sensors are mounted in field and the 4-20mA output is interfaced
to TIBs.
TIBs and the detectors are powered from 24V DC linear power supply.
The TIBs and 24V DC linear power supply are housed inside
instrumentation rack.
For LINSF, the output of TIB is given to Control system for acquisition
and monitoring. Selected channels are wired to Data logger also.
Schematic is shown in Annexure 2- Fig.No:9.
For LOXSF & GHe SF, The output of TIB is wired to Data logger.
Schematic is shown in Annexure 2- Fig.No:9A.
Hydrocarbon detector system.
The hydrocarbon presence is continuously monitored by using
hydrocarbon detectors.
Totally 10 numbers of monitors are planned.
The sensors are mounted in field and the 4-20mA output is interfaced
to TIBs.
TIBs and the detectors are powered from 24V DC linear power supply.
The TIBs and 24V DC linear power supply are housed inside
instrumentation rack.
In ISF, the output of TIB is given to control system for acquisition and
monitoring. All the channels are wired to Data logger also.
Schematic is shown in Annexure 2- Fig.No:10.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
6 | P a g e 2 2 2
UV/IR Flame detecting system.
The flame presence is continuously monitored by using flame
detectors.
Totally 12 numbers of monitors are planned.
The sensors are mounted in field and the 4-20mA output is interfaced
to TIBs.
TIBs and the detectors are powered from 24V DC linear power supply.
The TIBs and 24V DC linear power supply are housed inside
instrumentation rack. The same 24V DC linear power supply is used to
power detectors.
In ISF, the output of TIB is given to control system for acquisition and
monitoring. All the channels are wired to Data logger also.
Schematic is shown in Annexure 2- Fig.No:11.
The scope involves procurement, mounting & wiring of safety
detectors & field elements, cable tray laying, signal cable laying on
cable trays, the wiring of instrumentation rack and its interface
cabling.
2.3.3. Command systemE/P valve Command/ flow switch/ pressure switch
The command signals (Digital Output) from control system actuates
relays housed inside instrumentation rack.
The acknowledgement of this command signal from one relay contact
is patched to control system as Digital input.
The other contact of relay drives the SOlenoid Valve (SOV) housed
inside SOV cubicles in the field.
Separate 24VDC SMPS are used for actuating SOVs and
acknowledging command signal to control system.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
7 | P a g e 2 2 2
The status signal from proximity sensors of Electro Pneumatic (E/P)
valve located in field run to Transformer Isolated Barrier (TIB).
Similarly, the status output of flow and pressure switches are also
terminated in TIBs.
For ISF, the outgoing signals (ON/OFF status) from TIB are
terminated in Control system Rack as Digital input signal. For other
facilities, the output is wired to data logger.
Schematic diagram & wiring diagram of EP valve command system
are shown in Annexure 2-Fig.No:12&13 respectively. Schematic
diagram of Flow/pressure switch is shown in Annexure 2- Fig.No:14
&15.
Control Valve command
The analog command (4 to 20mA) for operating the control valve is
issued from control system.
The command output will be wired to control valve through TIBs.
The position feedback of control valve from positioner is terminated in
control system through TIBs.
The TIBs and 24VDC linear power supply are housed inside
instrumentation rack. The output of TIB is given to control system for
acquisition and monitoring. Schematic diagram is shown in Annexure
2-Fig.No:16.
The scope involves procurement, installation & wiring of fieldelements, Pneumatic tubing, erection of cable trays, signal cable layingon cable trays, wiring of instrumentation rack and interfacing betweenracks.
2.3.4. Auxiliary Instrumentation
Auxiliary system includes closed circuit television (CCTV) system,Communication equipments, and Timing system.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
8 | P a g e 2 2 2
CCTV System
CCTV is designed for remotely controlling, monitoring and recording
the videos of the storage facility for safety and surveillance monitoring
of the process during propellant storage and transfer from road tank to
storage tanks.
CCTV system consisting of Digital colour Cameras with motorised
zoom/focus lens housed inside Explosion proof Pan /tilt unit for ISF
and LOXSF. For LINSF and GHe SF Weather proof Pan /tilt unit is
used. The camera is 24V AC powered.
The video output from the camera is wired to 4 channel Fibre optic
transmitter and receiver system located in Cable terminal room (CTR)
using RG12 co axial cable.
These video signals are fed to Video Cross matrix switcher and
Controller unit. This controller has Joystick control or keyboard control
and built in RS 485 data multiplexer unit.
Through this data multiplexer unit, the
Pan/Tilt/Zoom/Focus/Left/Right/Auto commands are given to
pan/tilt unit of camera via 17 function telemetry receiver from
controller unit. Each camera requires one telemetry receiver.
The video output is fed to video distribution unit. The output of video
distribution unit is given to LED TV display units and video recorder.
Schematic diagram is shown in Annexure 2-Fig.No:17.
Inter communication system
Communication equipments are required for interpersonal
communication between the personnel working at storage facility and
control room and to make any announcements during transfer of
propellant.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
9 | P a g e 2 2 2
Wired intercom units and wireless communication equipments are
planned.
Wired Inter communication system includes
1. Flame proof Intercom station with flame proof page horn
speaker and microphone type handset for mounting in field for
ISF and LOXSF.
2. Weather proof Intercom station with outdoor page horn speaker
and microphone type handset for mounting in field for LINSF
and GHESF.
3. Rack mountable Intercom station with false ceiling mountable
speaker and microphone type handset for mounting in all
control rooms.
4. Surge protectors are to be used for power and Data lines were
ever applicable.
Wireless communication equipment includes one base station and
12numbers of handsets
Schematic diagram is shown in Annexure 2-Fig.No:18.
Timing System
Timing system are designed to Generate GPS/IRNSS based universal
time code signals with an accuracy of 1ms or better with output in
Analog IRIG-B format and TCP/IP packets.
UTC generator time code is connected to operator stations and PLC
control system for time tagged logging of data.
Timing system includes
o GPS/IRNSS based Universal Time Code Generator
o Network Time display units
o Ethernet switches & Ethernet cables
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
10 | P a g e 2 2 2
o System & Application Software including required drivers and
license
Schematic diagram is shown in Annexure 2-Fig.No:19.
The scope involves procurement, wiring and mounting of all auxiliaryequipments, interface cable laying and its wiring.
2.3.5. Fiber optic cable laying and splicing
The different storage facilities need to be linked in a common network.
This is to be done with fiber optic network.
The fiber optic cables shall be laid between
o ISF command room and LOX command room
o LOX command room and LIN command room
The fiber optic cable termination to be done.
2.3.6. Powering of Equipments For equipment powering, 230V, 50Hz power outlet is available in
control room at MCB panel.
This power has to be distributed to equipments, racks and consoles.
The power cable shall be laid in conduits and terminated in Terminal
blocks/ sockets on one side.
The other end termination shall be made in MCBs.
The scope of work involves conduit laying and laying of cable throughconduits with one end termination in MCB and the other endtermination in instrumentation rack, console or other equipments.
2.3.7. Grounding of Equipments
Separate instrumentation and power earth grounding strips are
available in the control room.
The instrumentation earth and power earth are separately maintained.
In each instrumentation rack, isolated instrumentation earth strip shall
be planned.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
11 | P a g e 2 2 2
The instrumentation cable shields shall be connected to earthing strip
in each rack and in turn to instrumentation earth strip running
through the building.
All the equipment body are to be connected to power earth.
The work involves laying of cable with one end termination in racks/rack equipments and the other end termination in grounding strip.
2.3.8. Console & Control room Table - Equipment mounting and wiring
8 segment console and 3 numbers of control room tables are planned
for Isrosene Storage Facility.
2 segment console and 1 control room table are planned for LINSF.
For GHe SF & LOX SF, 1 control room table for each facility is planned.
In these control room tables, Personal Computers (PC) will be placed
for data display/configuration/data processing.
The Personal Computers (PC), switches, keys, indicators, power
supply, keyboard for CCTV system controller and rack mountable
intercommunication equipments will be mounted in consoles.
The scope involves procurement, installation, equipment mountingand its wiring. Also powering of all equipments is to be carried out.
3. SCOPE OF CONTRACTThe scope of contractor includes
Detailed engineering
Equipments and Material supply as per list attached in
Annexure -4.
Erection and commissioning which includes
Installation and Mounting of equipments & field
elements.
Wiring of field elements & instrumentation rack
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
12 | P a g e 2 2 2
Erection of cable trays, laying of signal cables,
impulse tubes, pneumatic tubes on cable trays
Powering and grounding of equipments
Testing & evaluation of instrumentation system
Documentation
Detailed scope of above activities is given below.
3.1. DETAILED ENGINEERINGThe following input documents shall be referred during detailed
engineering
Annexure-1: Control room layouts showing the positioning of
racks, consoles and data processing nodes.
Annexure-2: Instrumentation system Configuration & schematic
diagram.
Annexure-3: Instrumentation rack General Assembly layout
Annexure-4: List of items to be supplied by contractor, its
quantity, specifications and recommended brands/vendors.
Annexure-5: Free issue materials
Annexure-6: Sample Testing and Evaluation sheets.
Annexure-7: P&I diagram
The following documents will be provided by Department during
Detailed Engineering
The sensor mounting procedure recommended by manufacturer
for safety sensors and temperature probes.
Detailed Measurement/Command Plan
The points explained in chapter 3.3 shall also be considered during
detailed engineering phase. The following documents shall be
prepared and submitted by the contractor for the approval from the
Department during detailed engineering.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
13 | P a g e 2 2 2
Specification document which includes the detailed specification
of all items & accessories supplied by contractor, its part number
and test plans.
Quantity Estimation of items including the accessories under
supply of contractor’s scope and its specifications.
Selection of all major equipments including Model matrix and
sizing sheets with supporting documents like latest catalogues.
Instrument/equipment erection diagram
Instrument/equipment mounting procedure
Cable & Cable tray routing layout diagram
Pneumatic / Impulse tubes routing diagram
Instrument rack General Assembly diagrams
Instrumentation rack signal flow and ferruling details
Equipment powering layout diagram
Conduit routing layout inside control room for power
distribution.
Equipment earthing scheme / layout inside control room
Field Instrument, Junction Box and control room cable
Termination and ferruling details
Testing and evaluation plan.
Quality assurance plan
3.2. EQUIPMENTS AND MATERIAL SUPPLYa. The list of field instruments & materials which are freely issued
by Department for the execution of this work package are givenbelow: Control System & its support for commissioning activities.
Heavy duty connectors
Switch mode power supplies
Contactor
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
14 | P a g e 2 2 2
Safety sensors for all facilities (Oxygen, Hydro carbon &
UV/IR Flame detectors)
Temperature Probes
Flow switches (4Nos) for ISF SF
Terminal block ( Single deck & for use in 230V AC power
wiring)
b. All other instruments & materials which are required to
complete the field and control room instrumentation detailed in
this contract shall be supplied by the contractor.
c. The list of items to be supplied by the contractor and its
specification along with recommended brands/vendors is given
in Annexure-4.
d. The contractor shall source the list of items only from the
recommended brands/vendors indicated here in Annexure-4.
e. In case the contractor proposes to source the items from any
other supplier/brand, necessary prior approval from the
department need to be obtained.
f. The required accessories (as mentioned in the document
Annexure 4) and its quantity shall be worked out by the vendor.
The quantity of accessories shall include 20% spare or 1 number
whichever is higher.
g. The accessories apart from which are mentioned in this
document and are required for the execution of work shall also
be quoted (unit rate) by the party.
h. The exact quantity and the list of items required for
commissioning the facility will be finalized during detailed
engineering and 10% quantity variation is permitted for supply
and erection as per contract.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
15 | P a g e 2 2 2
i. The consumables required for erection and commissioning apart
from those mentioned Annexure-4 shall be in contractor’s scope.
j. For few items, part number/model matrix is given as guidelines
for the supplier to select the product. However it is the
responsibility of the vendor to decide up on the finalized model
matrix complying to the specifications given with the latest
available catalogues.
k. Wherever mentioned, the material despatch shall be carried out
only after the test certificate/calibration certificate/ inspection
report approvals.
l. The vendor shall submit finalized Specification document which
includes the detailed specification of all items & accessories
supplied by contractor, its part number, test certificates,
approvals, calibration and guarantee certificates.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
16 | P a g e 2 2 2
3.3. ERECTION AND COMMISSIONING3.3.1. General Instructions
Tools for Erection & Commissioning1. The contractor shall bring necessary tools required for erection
& commissioning of the instruments & components and an
instrument work shop shall be made ready at the erection site.
2. Erection & commissioning works shall be carried out strictly
according to the specifications stipulated in the contract,
documents/drawings approved by department during detailed
engineering. Also it shall be carried out as per the supervision of
the department’s representative.
3. The Contractor shall provide and maintain a formal system for
documenting technical clarification from the Department.
4. Only correctly signed documents which are marked “Approved
for Construction” (AFC) shall be used for installation work.
5. Only the best trade practices and correct tools shall be used and
all works are expected to be completed in a neat and safe
manner.
6. Welding shall be done only by qualified personnel.
7. Electrical installation shall only be performed by appropriate
qualified trade persons.
8. Holes shall be drilled or punched and not burnt out by gas
torches or electric arcs.
9. Piping and tubing shall be formed with the appropriate pipe or
tube bending equipment.
10. Instrument/equipment shall be mounted using suitable
stands/brackets/clamps. As far as possible all field instruments
shall be mounted on instrument support stands. These shall be
installed on floors, RCC columns and walls using approved make
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
17 | P a g e 2 2 2
anchor fasteners / Hilti bolts and on steel structure by drilling
suitable holes and using chromium plated/galvanized bolts and
nuts or in exceptional cases by welding. After welding, the slag on
weld surface shall be removed and one coat each of Red-oxide
primer and paint shall be applied over the surface.
11. Equipment shall be installed in a neat, workman like manner so
that it is level, plumb, square and properly aligned and oriented.
12. Field Instruments should not be supported from impulse lines,
hand rails and vibrating structures.
13. Instruments shall be located such that it is easy to approach for
operation and maintenance. Cover can be removed without
obstruction and there should not be any problem in re-glanding the
cable later on.
14. All indicating instruments shall be located such that its scale is
conveniently visible to plant operator.
15. Canopy shall be provided for all the instruments, JBs and SOV
located outdoor.
16. All threaded opening of the instruments shall be protected by
suitable Aluminium/Chromium plated plugs.
17. During installation of the signal and control cables and prior to
connection up to the instruments, the cables shall be checked for the
insulation resistance, continuity and tagging.
18. If the insulation resistance is not found within the limits, these
cables shall not be used. The contractor should lay new cables,
meeting the continuity and insulation resistance requirements,
without any cost implication.
19. The signal and control cable wires shall be connected to respective
terminals, as per the wiring drawings.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
18 | P a g e 2 2 2
20. Field equipment shall be properly grouped at a convenient
location based on the equipment layout diagrams.
21. Allocation of grouping of channels based on signal levels in
junction boxes and racks shall be finalized during detailed
engineering.
22. Separate trays shall be used for routing pneumatic tubes and cables.
23. Field transmitters (pressure, temperature, flow) shall be mounted
on 2” pipe stands. The instrument stands shall have a suitable
height so that instrument shall be mounted at 1.4m from ground or
platform / catwalk. If the instrument to be mounted on a catwalk /
platform the preferred location shall be on the outside of the hand
railing.
24. Field instruments, which are exposed to open terrain, shall be
provided with weather canopy.
25. To protect temperature probes from mechanical damage /entry of
water, suitable individual enclosures shall be designed.
Handling & storage of Instruments26. The Contractor shall be responsible for the collection of “free-issue”
instrument items, transportation, storage and safe custody of the
equipments until completion of its installation and acceptance by
Department’s representative. This excludes the control system.
Contractor shall maintain a stock system to enable material tracking
throughout the installation & commissioning of the facility.
27. All instruments shall be visually examined by the Contractor on
receipt to ensure that they have not been damaged in transit.
Instruments shall then be replaced in their original packing and
housed in a separate secure, dry, cool storage area provided by the
department.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
19 | P a g e 2 2 2
28. If any item is damaged by the contractor, new item may be
procured and replaced by the contractor with their own cost or the
cost of the item will be deducted from the contractor’s bill.
29. When unpacking is necessary, care shall be taken to ensure that
accessories are not mislaid or mixed.
30. Instruments shall not be left lying around the construction area.
31. All covers and plugs on the instrument connections shall be left in
place until connections are used.
Installation Preparation32. Verify that instrument process connections ports before tapping.
33. Sensitive electronic instruments/components shall be protected
during welding, drilling & filing activities.
34. Metal Filing and metal or wood shaving shall be prevented from
falling on the components/ports/connectors.
35. Instrument stands and mounting brackets shall be fabricated
according to design drawings approved by the department.
36. Identification tags shall be attached to each field component bearing
its instrument number in accordance with P&ID drawings/
Instrument schedules.
37. Nameplate shall be attached to all junction boxes, SOV Cubicle and
racks. Nameplates shall be of stainless steel with black lettering
shall be provided for junction boxes and SOV Cubicle.
38. Nameplates shall be of plastic type for racks.
3.3.2. Erection and Commissioning Works3.3.2.1. Measurement and safety system
Absolute pressure/ DP based level measurement system
1. HART protocol based pressure Transmitters shall be planned for
facility absolute pressure measurements.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
20 | P a g e 2 2 2
2. HART protocol based Differential pressure Transmitters shall be
planned level & DP measurements.
3. The transmitters for Absolute pressure and level shall be installed in
the transmitter mounting post (2” pipe) as per drawing approved by
Department. Mounting shall be done as per 3.3.2.14.
4. A three way valve manifold for absolute pressure measurement and
five way valve manifold with block equalizing and drain valves for
differential pressure (level) measurement shall be installed with the
transmitter.
5. Impulse lines for pressure transmitters shall be of 12.7 mm (1/2”)
OD SS tube and thickness suitable for the process pressure.
6. Suitable double compression SS tube fittings shall be used to
connect process line, impulse tubes and instruments.
7. The length of impulse lines shall not exceed 5 meters and shall be
without any joint.
8. Impulse tubing shall be hydro tested to 1.5 times the rated pressure.
9. Impulse tubing shall be carried out as per procedure explained in
3.3.2.7.
10. Two core shielded PVC armoured cable shall be used between
facility transmitters (Pressure & Level) and field junction box.
Level measurement system
11. Guided wave level sensors shall be planned for tank level
measurements.
12. The sensor and transmitter shall be installed as per manufacturer
guide lines. The mounting procedure and drawing shall be
approved by Department before mounting.
13. Two core shielded PVC armoured cable shall be used between
level transmitters and field junction box.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
21 | P a g e 2 2 2
Temperature measurement system
14. RTD temperature sensors with HART protocol based Temperature
Transmitters shall be planned for facility temperature
measurements.
15. RTD temperature probes shall be installed as per
recommendations of manufacturer and drawing approved by
Department. The interface adaptors in SS material if required shall
be fabricated by the contractor with drawing approval by
Department. These adapters shall be inspected by the contractor
and certificates shall be approved by Department.
16. The temperature transmitters shall be installed in the transmitter
mounting post (2” pipe) as per drawing approved by Department.
Mounting shall be done as per 3.3.2.14.
17. Four core shielded PVC armoured cable shall be used between
temperature transmitter and RTD sensor.
18. Two core shielded PVC armoured cable shall be used between
Temperature transmitters and field junction box.
Flow measurement system
19. Mass flow meters shall be planned for facility flow measurements.
20. Flow meter shall be installed as per recommendations of
manufacturer and drawing approved by Department. Mounting
shall be done as per 3.3.2.14.
21. Four core shielded PVC armoured cable shall be used between
flow transmitter and field junction box.
Safety measurement system
22. Oxygen, Hydrocarbon sensor and UV/IR flame detectors shall be
used as safety detectors.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
22 | P a g e 2 2 2
23. Safety detectors shall be installed as per recommendations of
manufacturer and drawing approved by Department.
24. Four core shielded PVC armoured cable shall be used between
safety sensors and field junction box.
25. Multi core PVC cable shall be used between field junction box to
control room.
26. All multi core PVC cables shall be laid on cable trays.
27. All Cable laying & cable tray laying shall be done as per 3.3.2.9 &
3.3.2.13 respectively. Junction box mounting and wiring shall be
done as per 3.3.2.10 & 3.3.2.14.
28. The multi core PVC cables from the field entering in to control
room shall pass though a transit plate. Refer to chapter 3.3.2.12.
29. In control room multi core PVC cables from field junction boxes
shall be terminated in Heavy duty connectors mounted inside
facility measurement rack.
30. For ISF, facility measurement rack combines absolute pressure,
temperature, Differential Pressure (DP), DP based level and flow
measurements. Also TIBs for control valve command and feedback
shall also be mounted in this rack. This rack houses all TIBs and
24V DC linear power supply. The TIBs are of 24V DC powered and
shall be powered from single power supply. These TIBs provide
dual 2 to 10V output.
31. In Isrosene & LIN storage facility, one output of the TIB shall be
connected to control system rack through heavy duty connectors.
Female end termination at control system rack shall also be done.
32. Second output of required channels shall be connected to data
logger through heavy duty connectors. The data logger shall be
housed in separate rack.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
23 | P a g e 2 2 2
33. In ISF, safety measurements shall be clubbed to one rack along with
data logger. One output of TIB shall be wired to data logger and the
other output shall be wired to control system.
34. In LOX/ GHe storage facilities, all the measurements shall be
combined to single rack. Only one output of TIB shall be used and
shall be connected to data logger which shall be housed in a rack.
35. The rack wiring details are explained in 3.3.2.16.
36. PTFE cables shall be used for inter rack communication and these
cables shall be laid in trays inside control room. Cable laying and
cable tray laying procedures are explained in chapter 3.3.2.9
&3.3.2.13 respectively.
3.3.2.2. Command systemEP Valve Command system
37. The EP valve command chain is planned with single coil solenoid
valve.
38. Solenoid valves shall be mounted inside SOV cubicles.
39. The location of SOV cubicles shall be finalized during detailed
engineering.
40. The SOV cubicles shall be mounted as per mounting procedure
explained in chapter 3.3.2.10.
41. 5 Nos. of solenoid valves shall be mounted in one SOV cubicle, out
of which 1 No. of solenoid valve shall be kept as spare.
42. The length of command tubing from SOV cubicle to the
EP valve actuator shall be less than 10 meter, so that nearby
commands are grouped together.
43. Command tubing shall be carried out between Solenoid valve and
EP valve actuator using 8mm OD SS tube. 8mm bulkhead unions
shall be used for taking the 8mm SS tube out of SOV cubicle.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
24 | P a g e 2 2 2
Pneumatic tubing shall be carried out as per procedure explained in
3.3.2.8.
44. SS piping shall be carried out between common command headers
available in facility to each SOV header using 1” SS pipe.
45. The pneumatic tubing from SOV header to individual SOVs shall
also be done.
46. Pneumatic tubing shall be pneumatic tested at 1.1 times the rated
pressure.
47. 10 core 18AWG shielded armoured cable shall be used between
Junction box and each SOV cubicle for command.
48. Two status switches are to be provided to indicate open & close
status for each EP valve.
49. Four core shielded armoured cable shall be used between EP valve
status switch junction box and field junction box
50. Pressure and Flow switches shall be mounted as per the approved
mounting procedure.
51. Four core shielded armoured cable shall be used between pressure,
flow switches to field junction box
52. Multi core PVC cables shall be used between field junction boxes
and control room for command & status of EP valves, pressure and
flow switches.
53. All multi core PVC cables shall be laid on cable trays.
54. All Cable laying & cable tray laying shall be done as per 3.3.2.9 &
3.3.2.13 respectively. Junction box mounting and wiring shall be
done as per 3.3.2.10 & 3.3.2.14.
55. The multi core PVC cables from the field entering in to control
room shall pass though a transit plate. Refer to chapter 3.3.2.12.
56. In control room multi core PVC cables from field junction boxes
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
25 | P a g e 2 2 2
shall be terminated in Heavy duty connectors mounted inside
command system racks.
57. The EP valve command inputs from the control system shall be
terminated in EP valve command rack (ISF R2). The relays,
contactor and power supplies shall be accommodated in these
racks. Separate power supply shall be planned for Command
Acknowledgement and field actuation. The command
acknowledgement shall be connected to control system through
heavy duty connector. The field command shall be wired to field
junction box through heavy duty connector. These heavy duty
connectors shall be housed inside same rack.
58. The E/P valve status, pressure and flow switch status from the field
(digital input), shall be terminated in status rack ISF-R3. This rack
houses status TIBs powered from single power supply. The status
output of rack shall be connected to control system through heavy
duty connector.
59. The rack wiring details are explained in 3.3.2.16.
60. PTFE cables shall be used for inter rack communication and these
cables shall be laid in trays inside control room. Cable laying and
cable tray laying procedures are explained in chapter 3.3.2.9
&3.3.2.13 respectively.
61. Female end termination at control system rack shall also be done.
Control Valve Command system
62. Control valve shall have smart valve positioner with integrated
position transmitter.
63. Four core shielded armoured cable shall be used between JB and
control valve for command and position feedback.
64. Multi core PVC cables shall be used between control room and field
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
26 | P a g e 2 2 2
junction boxes.
65. All multi core PVC cables shall be laid on cable trays.
66. All Cable laying & cable tray laying shall be done as per 3.3.2.9 &
3.3.2.13 respectively. Junction box mounting and wiring shall be
done as per 3.3.2.10 & 3.3.2.14.
67. The multi core PVC cables from the field entering in to control
room shall pass though a transit plate. Refer to chapter 3.3.2.12.
68. In control room multi core PVC cables from field junction boxes
shall be terminated in Heavy duty connectors mounted inside
command system racks. The rack wiring details are explained in
3.3.2.16.
69. PTFE cables shall be used for inter rack communication and these
cables shall be laid in trays inside control room. Cable laying and
cable tray laying procedures are explained in chapter 3.3.2.9
&3.3.2.13 respectively.
70. Female end termination at control system rack shall also be done.
3.3.2.3. Auxiliary System
CCTV system
Field equipment mounting and wiring
71. The CCTV camera structures are to be fabricated and erected in the
field at location identified by the department suitable enough to
withstand the adverse wind condition at IPRC site. The fabrication
drawing to be prepared by Contractor and approved by
Department. Mounting shall be done as per 3.3.2.14.
72. The cameras are to be mounted on top of the erected camera
structure using appropriate fasteners.
73. 2 core armoured cable shall be laid for powering (24V AC) camera
from field junction box.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
27 | P a g e 2 2 2
74. 10 core Armoured PVC cable shall be laid from 17 function
telemetry receiver to pan/tilt unit of each camera.
75. Multi core PVC cable shall be planned from field junction box to
control room.
76. 17 function telemetry receiver of all cameras shall be mounted
inside field junction box.
77. RG12 Coaxial cable shall be laid from all cameras to control room.
78. The cables have to be routed from the cameras in the field using
flexible metal hoses or pipes. Suitable cable glands are to be used
for all the cables entering and exiting from the CCTV cameras.
79. Separate field junction box shall be planned for auxiliary system
in ISF. For other facilities, common junction box shall be planned.
80. Cable laying and cable tray laying procedures are explained in
chapter 3.3.2.9 &3.3.2.13 respectively.
81. Junction box mounting and wiring shall be done as per 3.3.2.10 &
3.3.2.14.
Control room Rack wiring
82. The video data (RG12) shall be wired to 4 channel Fibre optic
transmitter and receiver system. This system shall be interfaced to
Video Cross matrix switcher and Controller unit. This controller
has Joystick control or keyboard control which shall be mounted
in console and built in RS 485 data multiplexer unit.
83. The multi core PVC cable from field shall also terminated in
controller unit.
84. The 24V AC power transformer shall be also mounted in the rack.
85. The video output is fed to video distribution unit. The output of
video distribution unit is given to LED TV display units and video
recorder. Except LED TV all other equipments are mounted inside
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
28 | P a g e 2 2 2
instrumentation rack along with rack mountable timing and
intercom equipments.
86. For ISF and LIN SF separate racks are planned. For LOXSF and
GHeSF the equipments are combined with other racks.
87. General guidelines for rack wiring shall be followed.
88. The video recording must be programmable for selectable video
resolution, frame rate, encoding bit rate, bandwidth, audio
encoding, recording schedule, continuous, event based or motion
detection.
89. The required software shall be loaded and the system shall be
commissioned in total by the contractor.
Intercommunication system
90. Suitable structures are to be fabricated for mounting wired
intercom units and erected in the field at location identified by the
department suitable enough to withstand the adverse wind
condition at IPRC site. The fabrication drawing to be prepared by
Contractor and approved by Department. Mounting shall be done
as per 3.3.2.14.
91. In control room intercommunication equipments shall be located
at racks/consoles.
92. Multi core PVC cables are to be laid from intercom unit to field
junction box and to instrumentation rack at control room.
93. Align the Microphone output card, line cards and power amplifier
for optimum sound reception at field and at control room.
94. The speakers shall be mounted at suitable height in the field using
fabricated structure and on the ceiling at control room.
95. Terminate the speakers to the individual intercom units using two
core twisted pair cable.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
29 | P a g e 2 2 2
96. All Cable laying and cable tray laying procedures are explained in
chapter 3.3.2.9 &3.3.2.13 respectively.
Wireless System
97. Wireless units are to be programmed for the approved frequencies
after obtaining licensee from WPC.
Timing System98. GPS Antenna to be fixed on top of the building using proper
fasteners.
99. Antenna cables has to be routed from antenna to GPS/IRNSS
receiver
100. The GPS/IRNSS receiver has to be configured and the output
interfaced to all operator station and display unit.
101. The network display has to be mounted on the wall or on
structures at command room.
102. Necessary software modules has to provided for interfacing the
Time server with Command control PLC and other system
103. All Cable laying and cable tray laying procedures are explained inchapter 3.3.2.9 &3.3.2.13 respectively.
Fibre optic cable laying, mounting of patch panel and splicing worksCable Laying Through Excavated Earth
104. The earth has to be excavated to a depth of 750 mm and width of
400 mm along the road sides at a distance of 5 meters from the
road edge. The Trench excavated should be first filled with River
sand for a height of 10 mm, then the Fiber optic or PVC cables
have to be then laid inside the trench. Properly baked bricks are to
be positioned along the sides of the cables. River sand has to be
filled inside the bricks after laying the cables. Place one more brick
on top of the two bricks placed along the cables. The details are
given below .Then fill the excavated cable trench with earth sand.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
30 | P a g e 2 2 2
If required jungle clearance has to be done by the contractor before
excavation of the earth .
105. At road crossing the party has to use 2 “Hume pipe. The road has
to be cut to a depth of 750 meters and width 300 meters. After
laying the cable through the Hume pipe, the road crossing has to
be filled with earth and after the earth settles down, the trench cut
across the road has to be cemented with PCC or black topped
properly to protect the Hume pipes from damage by movement of
heavy vehicles. The road crossing should be properly leveled so
that there is smooth flow of vehicles.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
30 | P a g e 2 2 2
If required jungle clearance has to be done by the contractor before
excavation of the earth .
105. At road crossing the party has to use 2 “Hume pipe. The road has
to be cut to a depth of 750 meters and width 300 meters. After
laying the cable through the Hume pipe, the road crossing has to
be filled with earth and after the earth settles down, the trench cut
across the road has to be cemented with PCC or black topped
properly to protect the Hume pipes from damage by movement of
heavy vehicles. The road crossing should be properly leveled so
that there is smooth flow of vehicles.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
30 | P a g e 2 2 2
If required jungle clearance has to be done by the contractor before
excavation of the earth .
105. At road crossing the party has to use 2 “Hume pipe. The road has
to be cut to a depth of 750 meters and width 300 meters. After
laying the cable through the Hume pipe, the road crossing has to
be filled with earth and after the earth settles down, the trench cut
across the road has to be cemented with PCC or black topped
properly to protect the Hume pipes from damage by movement of
heavy vehicles. The road crossing should be properly leveled so
that there is smooth flow of vehicles.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
31 | P a g e 2 2 2
106. The Cable route marker has to be positioned adjacent to cable laid
at every 50 meters. The detail of cable marker is given in figure-1.
The cable marker has to be provided after digging the earth near
the
cables laid, by placing the cable marker using Concrete mixer
firmly to a depth of 300 mm underneath the earth. The Baked
bricks, River Sand, Hume pipes and cable route marker are the
scope of the contractor
107. The fibre optic cables shall be laid between
ISF command room and LOX command room
LOX command room and LIN command room
108. The fibre optic cable termination shall be done in patch panelsmounted in respective command rooms with qualified persons.
3.3.2.4. Console and Control room table wiring
109. There shall be 8segment console in ISF and 2 segment console in
LIN storage facility. There shall be 3 nos of Personal Computer
(PC) table in ISF. For other storage facilities, there shall one PC
table for each.
O F CDATAE & I
1000 mm
100 mm
300 mm
White over orangebackground
300 mm
PCC
300 mm
Cable route marker
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
32 | P a g e 2 2 2
Console segments:
110. The equipments like intercom units, keyboard for CCTV system
controller, switches, keys and indicators shall be mounted in
console segments.
111. The required 24V DC power supply for the switches shall be
mounted in console cabinets.
112. The 24” LED monitors and PCs shall be mounted in each segment.
The powering of all console equipments shall be done.
Control room tables:
113. The 24” LED monitors, PCs and printer shall be mounted in each
segment. The powering of the equipments shall be carried out.
3.3.2.5. Powering of control room equipments
114. For equipment powering, power distribution boards with MCBs is
available in the control room.
115. The 230V, 50Hz powering layout shall be made for all equipments
housed in instrumentation racks, consoles, LED TVs, intercom
equipments and timing display units.
116. The power cable shall be routed through conduits and near
console/rack/equipment flexible hoses shall be used.
117. The terminations on the equipment side shall be in terminal
blocks or in distribution board or in plugs based on the
equipment. The other end termination shall be made in MCBs.
118. Standard wiring procedure shall be followed with termination
using suitable lugs, ferrules, cable and cable conduit identification
tags.
3.3.2.6. Grounding of equipments
119. The cable shield shall be terminated in copper strips provided in
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
33 | P a g e 2 2 2
the instrumentation rack and isolated from power earth and
finally connected to instrumentation earth strips in the control
room. The chassis of equipments shall be connected to power
earth. The cable laying shall be done neatly and the cables shall be
harnessed properly.
120. The cables shall be tagged every 5m. Termination ends shall be
with suitable lugs and shall be ferruled.
3.3.2.7. Impulse Tubing
121. 12.7 mm OD S.S. tubes shall be used as impulse tubes. Instrument
tubing shall be laid as per standard on cable trays. The width of
cable trays shall be selected as per number of instrument tubing
laid.
122. The tube routing shall be carried out as per approved drawing.
123. Transmitters shall be mounted above the process pipe line and
continuous slope shall be provided in the impulse line between
transmitter and process line.
124. S.S. Tubes shall be cleaned with lint free cloth dipped in acetone
and pulled through the tube using nylon wire until all dirt/dust is
removed. As a check for thorough cleaning of tubes, last lint free
cloth shall be as clean as new. This is to be done in presence of the
department’s representative. Outside surface of tube shall also be
cleaned by rubbing manually with lint free cloth soaked in acetone.
Tubes shall be cleaned by blowing dust free GN2 before laying.
125. Tube bends shall be made with approved and appropriate sizes of
tube benders. Bends shall be of uniform curvature and smooth and
shall be free from wrinkles, flattening and kinks. Use of filler
material during bending is prohibited. Hot bending is also not
permitted.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
34 | P a g e 2 2 2
126. Tubes shall be clamped at intervals not exceeding 1 meter with the
help of special spacer and clamps.
127. Impulse lines and their supports should be kept away and free
from vibrating structures or equipment. Minimum bending radius
should be taken as 2.5 times the tube OD.
128. To avoid corrosion of SS Tubes, contacts of SS Tubes with CS/MS
surfaces should be avoided by installing brass shims/foil in
between SS Tubes and CS/MS Surface.
129. Wherever impulse lines run side by side, they should be neatly
bunched together with bolted straps and screwed clamps. Tubing
should be ganged vertically rather than horizontally to avoid
collection of dust, dirt and other corrosive conditions.
130. S.S. Tubes are terminated by using approved make of double
ferrule type fittings.
131. Fittings shall be installed by qualified fitters who have to undergo
qualification test to be conducted by the Quality Surveillance
Engineer of the department.
132. Tubes shall be identified at both ends by line number/instrument
number/equipment number to which it is terminated by Anodized
Aluminium tags of rectangular shape and shall be tied to the tube
securely by 16 gauge S. S. wire.
3.3.2.8. Pneumatic Tubing
133. The scope of work covers installation, routing as per approved
drawing, clamping, supporting and connection of 8mm OD SS tube
with fittings.
134. S.S. Tubes shall be cleaned with lint free cloth dipped in acetone
and pulled through the tube using nylon wire until all dirt/dust is
removed. As a check for thorough cleaning of tubes, last lint free
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
35 | P a g e 2 2 2
cloth shall be as clean as new. This is to be done in presence of the
department’s representative. Outside surface of tube shall also be
cleaned by rubbing manually with lint free cloth soaked in acetone.
Tubes shall also be cleaned by blowing dust free GN2 before laying.
135. Tube bends shall be made with approved and appropriate sizes of
tube benders. Bends shall be of uniform curvature and smooth and
shall be free from wrinkles, flattening and kinks. Use of filler
material during bending is prohibited. Hot bending is also not
permitted.
136. S.S. Tubes are terminated by using approved make of double
compression type ferrule fittings. At the place of termination/joint,
tubes shall be cut square and burrs if any shall be removed by fine
emery paper without reducing wall thickness of the tube. Tube
shall be cut with approved brand of tube cutter only.
137. Fittings shall be installed by qualified fitters who have to undergo
qualification test to be conducted by the Quality Surveillance
Engineer of the department.
138. Tubing shall be routed on the cable trays and shall be clamped at
the intervals not exceeding 1 m. The tubing shall be run in such a
manner to provide maximum protection against physical damage.
Tubing runs shall be neatly dressed and grouped together where
ever possible. Tubes shall be ganged vertically rather than
horizontally to avoid collection of dirt, dust and other corrosive
material.
139. Tubes which are to be terminated on the instruments, may be
subjected to vibrations during operation, a semi circular loop shall
be formed on the tube near the termination point to avoid damage
to the tubes during operation. All such instruments shall be
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
36 | P a g e 2 2 2
identified in consultation with the department Engineer, before
termination of the tubes.
140. Tubes shall be identified at both ends by line number/instrument
number/equipment number to which it is terminated by Anodized
Aluminium tags of rectangular shape and shall be tied to the tube
securely by 16 gauge S. S. wire.
141. Compression unions shall be used for joining the tubes. At the joint
an offset of around six inches (3 inches on each side of the joint)
shall be given on the tube run from the tray, so that the fitting will
be away from the surface of the tube support and have free access
for tightening and checking of leaks during test. Joints on adjacent
tubes in a bundle shall be staggered suitably to avoid interference.
142. All the air supply lines shall be pneumatically tested by the
contractor, using dry air at 8 bar. The joint should be bubble tight.
3.3.2.9. Laying of Cables
143. All cable routes shall be carefully measured and cut to the required
length, leaving sufficient amount for the final connections of the
cable to the terminals on either end.
144. The scope of work consists of laying and termination of multi core
cables at various Junction Boxes / Terminal blocks. Supply of cable
harnessing materials, end Terminals & Identification ferrules is in
the scope of contractor.
145. Cable shall be of single piece and joint is not allowed from one
termination to the other termination.
146. Cables shall be rigidly supported on cable trays, individually or in
groups as required using individually cast or malleable iron
galvanized clips. Distance between the two cable supports shall not
be more than 1 m.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
37 | P a g e 2 2 2
147. Physical protection shall be provided wherever required.
148. Cables are to be terminated on the junction box/instruments using
appropriate size of cable glands/lock nuts and rubber washer with
gland hoods. All Single seal cone grip compression gland shall be
used for armoured and un-armoured cable. All glands should be of
NPT at junction box and Instrument side.
149. Each of the cables shall be tagged with cable number punched
clearly in anodized aluminium tags and tied to the cable at both the
ends and at 15meter intervals.
150. Cables, wires shall be connected on the field instruments/terminal
blocks using lugs. Wire identification shall be provided by inserting
printed PVC sleeves with ferrule number.
151. Cable shall be laid and terminated as per approved cable
scheduling.
152. All wires shall be checked for proper identification, continuity and
insulation before taking up wiring connections.
153. Power Cables and control cables shall be laid in separate Cable
Trays as per IEEE 518-1982.
154. All cable screens/shields shall be earthed.
155. Care should be taken to avoid sharp bending and kinking of
conductor, damaging of insulation and stressing the cable beyond
the pulling force recommended by the manufacturer. Minimum
radius of bend of an insulated cable shall be 12 D for unarmoured
cable and 15 D for armoured cable.
156. While terminating the cable at the devices, a loop involving
around 0.5 mtr extra cable shall be provided.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
38 | P a g e 2 2 2
3.3.2.10. Junction Boxes/SOV cubicles
157. Junction boxes and SOV cubicle shall be mounted in suitable
support structure. The fabrication of support structure shall be
done by the party with approved drawing.
158. The cable entry to Junction boxes & SOV cubicle shall be through
cable glands with PVC hoods.
159. Cable Glands shall be of Single Compression NPT type made from
nickel coated brass with PVC Hoods.
160. All unused holes shall be plugged with Aluminium plug.
161. In general, all cable entries from field elements shall be through
sideways and all cables to control room shall be from bottom.
162. The JBs & SOV cubicle shall be tagged according to tagging
philosophy followed in respective units.
3.3.2.11. Canopy Requirement
163. All junction box and field instruments which are kept outside shall
be provided with pre-fabricated canopy for Rain and Sun
protection.
164. The canopy shall be fabricated by powder coated MS plates of 2
mm thick.
165. The fabrication drawings shall be prepared and shall be approved
by Department.
3.3.2.12. Multi Cable Transit Plate
166. Four numbers of Multi Cable Transit Plate shall be planned; one
for each control room.
167. The transit plate shall be mounted in control room / rack room
entry hole which is already available in the room.
168. The plate shall be drilled with suitable holes matching to cable
diameter.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
39 | P a g e 2 2 2
169. The multicore PVC cables shall pass though the holes and shall be
provided with cable glands at the holes.
170. Additional holes may be provided for future augmentation. Such
holes may be properly sealed with dummy glands to avoid the
entry of dust and insects.
3.3.2.13. Cable Trays
171. Instrument cabling shall be through trench/overhead.
Main Cable Way /Trench : Ladder Tray
Local Branch Cable Way : Perforated Tray
172. Ladder trays shall be used from control room to junction boxes.
These ladder trays run inside cable trench/ structural supports.
173. Perforated G.I. trays shall be used from junction boxes to
individual instruments and inside control room.
174. Suitable cable clamps shall be supplied for binding the
cables/tubes at every 2 m for horizontal and 0.5 m for vertical.
175. Structural supports for the cable/tubing trays shall be
fabricated as per approved drawings and shall be inspected
before erection.
3.3.2.14. Structural support
176. Structural support for the Instrument mounting post, camera post,
Junction box and SOV cubicle shall be fabricated using MS
structural materials and sharp corners shall be smoothened by
grinding.
177. The fabrication shall be carried out with drawing approved by
Department.
178. Structural materials shall be painted with one coat of Red-oxide
Primer and two coats of Grey enamel Paint.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
40 | P a g e 2 2 2
3.3.2.15. Cable Trays – Structural support fabrication
179. Perforated G.I. trays shall be used for cable and SS tube laying.
180. The structural supports for this shall be fabricated as per approved
drawings and shall be inspected before erection.
181. All the welding points shall be painted with one coat of red-oxide
primer and two coats of paint shall be applied.
182. The cable trays shall be welded to the support structures. The burrs
at welding points shall be removed and painted with silver colour
paint
3.3.2.16. Instrumentation Rack-Equipment Assembly & Wiring
183. The instrumentation racks shall be installed and commissioned at
different control room located at different locations.
184. The instrumentation racks are wired for full capacity as given in
Table-A of Annexure 3. The instrumentation rack layouts are given
in Annexure-3.
185. The instrumentation rack shall be 19” width and 42U height
effective spacing.
186. Design of rack shall be in such a way, to provide proper
operational and maintenance access and conceal interconnecting
wires and cables.
187. Wires shall be housed in PVC cable ducts of suitable dimensions to
accommodate system cables, signal cables and power cables.
188. PVC cable ducts shall be organized to run electric wires according
to their voltage level and function. Power supply wires and low
voltage signal wires shall not be grouped together in the same
cable duct.
189. Wiring for different voltage signals shall be terminated separately
on dedicated terminal strips.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
41 | P a g e 2 2 2
190. All the terminal blocks shall be DIN rail mountable.
191. Power supply shall be provided with fan tray for cooling.
192. The incoming cables from the field shall be terminated in 72/108
pin heavy duty connector which is supplied by department.
193. 96/64/32 core PTFE cable shall be used for interconnection
between instrumentation racks.
194. These cables shall be terminated in 72/108 pin heavy duty
connectors at the rack output and also at control system or Data
logger rack (Female end).
195. The cable trays and its structural support required for cable laying
shall be provided.
196. Cable entry in all instrumentation rack shall be from bottom
3.3.2.17. False floor planks cutout
197. In all control rooms, false floor is provided. The instrumentation
racks, consoles and control room tables are positioned over these
false floor planks.
198. The cut out to be taken in these planks so as to enable the cables to
be routed inside racks/consoles/tables.
199. The cut-out of suitable dimension shall be taken in planks. The
dimension shall be approved by department before taking cut-
outs.
3.3.3. TESTING AND EVALUATION3.3.3.1. Test Equipments
200. The contractor shall bring all the required test and measureinstruments required for testing and evaluation. The standardSource/Measure equipments with calibration validity traceable tonational standards shall be used by the contractor. The equipmentsof ±0.02% accuracy class of shall be used for sourcing andmeasuring.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
42 | P a g e 2 2 2
3.3.3.2. Testing and Evaluation
201. Only preliminary details regarding testing and evaluations are
given below. However the contractor shall prepare detailed
Testing and evaluation procedure and formats during detailed
engineering phase. As per the approved procedures, the contractor
shall carry out the testing and evaluation. The final results shall be
entered in relevant formats and finally to be approved by
Department.
202. Check all the instruments for proper mounting and sealing. Check
for proper routing & dressing of wiring. Ensure the availability of
terminal strip nos., Wire nos., tags and ferrules. Ensure proper
grounding of racks/equipments.
203. Check and log insulation resistance of all cables, continuity of
wiring of all instrument loops as per the relevant drawings.
204. Integrity test up to sensor shall be done.
205. Power supply load test: All the power supplies shall be load
tested up 110% of rated load. The stability and ripple test
shall also be carried out.
Measurement & safety system
206. A known input signal shall be fed from calibrated
source/communicator and the output shall be recorded in
the control system/Data logger. The results are to be entered
in a format. The sample format is given in Annexure-5. The
format will be finalised at the time of detailed engineering.
Command System
207. Manual command shall be issued from control system and
the voltage at the SOV coil end in the case of E/P valve shall
be measured.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
43 | P a g e 2 2 2
208. Also coil resistance shall be measured.
209. For control valve the percentage of control valve opening
shall be checked. For switches functioning shall be checked.
210. Also in simulation mode, command acknowledgements shall
be checked in control system.
211. The results are to be entered in a format. The sample format
is given in Annexure-6.
212. The format will be finalised at the time of detailed
engineering.
Auxiliary system
213. Each camera has to be checked for its operation like pant/tilt,
zoom /focus, recording & configuration from the control
room.
214. Functional verification of all auxiliary system equipment.
3.3.3.3. Inspection & Quality Surveillance
215. The contractor shall prepare detailed inspection & quality
surveillance plan for all the items and services provided by
the contractor.
216. All Instrumentation items supplied by the contractor
(Annexure 4) and services covered by this contract shall be
subjected to inspection and testing by department’s
representatives.
217. The inspection by the department’s representative and issue
of inspection certificate thereon shall in no way limit the
liabilities and responsibilities of the contractor in meeting the
specification and quality requirements specified.
218. The contractor shall supply the material test certificates /
calibration certificates (wherever mentioned) for the items
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
44 | P a g e 2 2 2
under the supply of contractor’s scope.
219. The contractor shall supply and maintain an independent
comprehensive database system containing inspection &
testing and performance records for each instrument.
3.4. DOCUMENTATION220. The contractor shall provide with 2 sets of hard copy and a
soft copy for the purpose of documentation. The lists ofdocuments are to be provided by the contractor at thedifferent phases specified thereupon are as follows:
221. The contractor shall submit the documents specified underdetailed engineering in chapter 3.1 – 1 set of hard copy & Softcopy.
222. Catalogues, Test certificate, warrantee/guarantee certificatesand inspection report for the materials /items which areunder the contractor scope of supply.
223. The software CDs, manual, installation guidelines and other
relevant documents for auxiliary systems.
224. The following documents shall be submitted by the
contractor during erection & commissioning phase
Operation & Maintenance manual including Technical& installation details.
Approved fabrication, mounting and layout drawings.
225. Test and evaluation reports.
226. Up on completion of commissioning activities, as-built
version of all documents approved during detailed
engineering.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
45 | P a g e 2 2 2
ANNEXURE –1
CONTROL ROOM LAYOUT
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
46 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
46 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
46 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
47 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
47 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
47 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
48 | P a g e 2 2 2
ANNEXURE – 2
INSTRUMENTATION SYSTEM CONFIGURATION &
SCHEMATIC DIAGRAM
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
49 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
49 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
49 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
50 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
50 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
50 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
51 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
51 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
51 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
52 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
52 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
52 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
53 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
53 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
53 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
54 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
54 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
54 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
55 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
55 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
55 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
56 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
56 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
56 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
57 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
57 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
57 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
58 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
58 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
58 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
59 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
59 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
59 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
60 | P a g e 2 2 2
ANNEXURE-3
INSTRUMENTATION RACK GENERAL ASSEMBLY LAYOUT
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
61 | P a g e 2 2 2
Instrumentation Rack Wiring RequirementsInstrumentation system Wiring
CapacityRack No Scope
ISFFacility measurementparameters & Control Valve
96 ISF-R1 Contractor
EP Valve command 96 ISF-R2 Contractor
EP Valve Status, Flow switch 96 ISF-R3 ContractorSafety system and Data logger 32 ISF-R4 Contractor
Auxiliary system 12 ISF-R5 ContractorControl System ISF-R6 & R7 DepartmentLIN Storage Facility -Monitoring system (CombinesMeasurement system, safetysystem, switches and Datalogger)
48 LIN-R8 Contractor
LIN Storage Facility -Auxiliary system
6 LIN-R9 Contractor
LIN Storage Facility –Control system
1 LIN-R10 Department
LOX Storage FacilityMonitoring system (CombinesMeasurement system, safetysystem, auxiliary system andData logger)
16 LOX-R11 Contractor
GHe Storage Facility(Combines Measurementsystem, auxiliary system andData logger)
16 HE-R12 Contractor
Total 12Department Scope 3
(Racks: ISF-R6, R7 &LINR10)
Contractor Scope 9Note: For some racks tentative GA drawing are provided for guidance
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
62 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
62 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
62 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
63 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
63 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
63 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
64 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
64 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
64 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
65 | P a g e 2 2 2
ANNEXURE -4
SPECIFICATIONS & SUB-VENDOR DIRECTORY
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
66 | P a g e 2 2 2
Table-B
S.No Items Unit Qty RecommendedVendors/Brands
1 Pressure Transmitters withmanifolds
Nos 70 Absolute Pressure: Rosemount :3051TA ; SMAR : LD400;YOKOGAWA : EJX610A;HONEYWELL: STA 800Differential Pressure:Rosemount : 3051CD ; SMAR :LD400; YOKOGAWA :EJX110A; HONEYWELL: STD800Manifold:Parker/Swagelok/Anderson/Hoke
2 Guided Wave level sensor Nos 10 Rosemount, Vega, Magnetrol3 Temperature transmitter Nos 18 Smar TT301
Rosemount 3144PHoneywell: STT 850
4 Mass Flow meters Nos 3 Micromotion, E+H5 HART communicator suitable for
communicating with all quotedpressure, temperature, GuidedWave level & flow transmitters
No 1
6 Flow switch Nos 2 Honeywell, Omega, ifm7 Pressure switch Nos 11 Honeywell, Omega, ifm8 Solenoid valve Nos 75 M/s Asco, Chennai
M/s HerionM/s Parker
9 SOV cubicle Nos 15 1. M/s Baliga LightingEquipments Ltd2. M/s FlameProof EquipmentsPvt. Ltd3. M/s CEAG FlameProofControl Gears (P) Ltd4. M/s. Stahl, Chennai5. M/s FCG Power IndustriesPvt. Ltd6. M/S. EX Protecta7. M/S. Pepperl+Fuchs Pvt Ltd.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
67 | P a g e 2 2 2
S.No Items Unit Qty RecommendedVendors/Brands
10 Junction boxes 1. M/s Baliga LightingEquipments Ltd2. M/s Flame Proof EquipmentsPvt. Ltd3. M/s. Stahl, Chennai4. M/s CEAG Flame ProofControl Gears (P) Ltd5. M/s FCG Power IndustriesPvt. Ltd6. M/S. EX Protecta7. M/S. Pepperl+Fuchs Pvt Ltd.Type I : 600x400x225 Nos 10
Type II : 300x300x165 Nos 411 Compression fittings & SS tubes SS Tubes
1. M/S. Swagelok India2. M/S. Sandvik3. M/s. Ratnamani4. M/s. Remi5. M/s. Parker
Compression Ferrule Fittings1. Swagelok2. Parker
12.7mm SS tube; Wallthickness:2.2mm
m 600
12.7mm SS tube; Wallthickness:7.47mm
m 100
8mm SS tube m 15001/2" NPT M to 12.7mm SS tube;
Operating pressure: 400barNos 150
1/2" NPT F to 12.7mm SS tube;Operating pressure: 400bar
Nos 100
12.7mm SS tube union; Operatingpressure: 400bar
Nos 120
12.7mm SS tube Tee; Operatingpressure: 400bar
Nos 60
1/2" NPT M to 12.7mm SS tube;Operating pressure: 650bar
Nos 50
1/2" NPT F to 12.7mm SS tube;Operating pressure: 650bar
Nos 50
12.7mm SS tube union; Operatingpressure: 650bar
Nos 15
12.7mm SS tube Tee; Operatingpressure: 650bar
Nos 10
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
68 | P a g e 2 2 2
S.No Items Unit Qty RecommendedVendors/Brands
1/4" NPTM to 8mm SS tube;Operating pressure: 400bar
Nos 150
1/4" NPTF to 8mm SS tube;Operating pressure: 400bar
Nos 150
8mm SS tube union; Operatingpressure: 400bar
Nos 125
8mm SS tube Tee; Operatingpressure: 400bar
Nos 75
Bulk head union for 8mm tube;Operating pressure: 400bar
Nos 25
½” NPT SS Plug; Operatingpressure: 400bar
Nos 100
¼” NPT SS Plug; Operatingpressure: 400bar
Nos 100
12 PVC cables 1. Delton Cables, New Delhi2. Paramount communicationLtd., New Delhi3. NICCO corporation limited,Kolkata4. Cable Corporation of India,New Delhi5. CMI LTD, New Delhi
2 core 20AWG armoured cable m 45004 core 20AWG armoured cable m 400010 core 18AWG armoured cable m 150064 Core 20AWG Un armouredCable
m 2500
96 Core 18AWG Un armouredCable
m 800
96 Core 20AWG Un armouredCable
m 2500
13 Cable trays 1. M/s Patny systems,Secundrabad2. M/s Elcon Instruments, Pune3. M/s Shruti Industries, Pune
Perforated Cable Trays- width:50mm; Height: 12mm; Thickness:1.6mm
m 700
Perforated Cable Trays- width:100mm; Height: 25mm; Thickness:2.0 mm
m 2500
Perforated Cable Trays- width:150mm; Height: 25mm; Thickness:2.0 mm
m 1500
Perforated Cable Trays- width:300mm; Height: 50mm; Thickness:2.0 mm
m 300
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
69 | P a g e 2 2 2
S.No Items Unit Qty RecommendedVendors/Brands
Ladder Cable Trays- width:300mm; Height: 75mm; Thickness:2.0 mm
m 1000
Accessories for above cable trays lot 114 Structural materials kg 1000015 Canopy sq m 1016 Racks & Accessories Nos 10 Make: President, Rittal.17 Console & Control Room Tables seg
ment10&6 Adarsha Control & Automation
Pvt Ltd, Chennai.Pyrotech workspace solutions,
Bangalore.Digilog Technologies Pvt Ltd,
Bangalore.Workspace solution, Bangalore.
18 Transformer Isolated Barrier (TIB)TIB for transmitters. Nos 216 Make: Pepperl + Fuchs &
MTLTIB for status Nos 112TIB for Control valve command Nos 8
19 Relays Nos 100 Make: Phoenix20 24V±20%,20ALinear power supply Nos 6 Make: Aplab
21 PTFE cables 1. M/s. Meerut PTFE ProductsPvt Ltd., Meerut2. T&F Insulation Pvt Ltd.,Bulandshahr3. Delton Cables Ltd., NewDelhi5. FLU-TEF Industries.,Ahmedabad6. Satellite Cables., Ahmedabad7. Techno Cables Pvt Ltd.,Secundrabad8. TCL Special cables., NewDelhi9. Advance Cables, Bangalore10. Tempsens Instruments PvtLtd, Udaipur.
20AWG 96 Core Cable m 50020AWG 64 Core Cable m 10020AWG 32 Core Cable m 10020AWG Single core wire m 1200018AWG Single core wire m 2000
22 Power cable m 1000 Finolex, Poly Cab, V Guard, RR
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
70 | P a g e 2 2 2
S.No Items Unit Qty RecommendedVendors/Brands
Kabel, Havells, Lapp, Kundan23 Earth cable m 500 Finolex, Poly Cab, V Guard, RR
Kabel, Havells, Lapp24 Terminal block 1. Wago
2. Phoenix3. ABB4. Weid muller
Terminal Blocks- No. of levels:2 ;No of terminals:4 with diode inseries
Nos 50
Terminal Blocks- No. of levels:2 ;No of terminals:4 with diode inparallel
Nos 50
25 Cable glands Make:1. Trinity2. Hummel3. Weid muller4. Lapp
Nickel coated Brass TypeCable Gland - 46mm Nos 50Cable Gland - 32mm Nos 50Polymide TypeCable Gland - 46mm Nos 50Cable Gland - 32mm Nos 50Cable Gland - 25mm Nos 50Cable Gland - 19mm Nos 50
26 Cable entry Plate Nos 427 Mounting Plate Nos 15
28 Metal conduits, Metal flexiblehoses suitable for conduit, 4/3/2way metal junction box suitablefor conduit bends, elbows, Teesand couplers of requiredquantities.
lot 1
29 Indicators , Switches &Keys 1.Tyco; 2.Amphenol;3.Honeywell
4.EntrelacIndicators 40 NosAuthorization keys 10 NosSwitches with Indicators 40 NosMushroom caped emergency stopswitches
10 Nos30
Data logger, its accessories &sparesNos 4 Data Taker, Yokogowa, UEI,
Dewesoft31 Operator chair Nos 25 Godrej, Featherlite, Merryfair32 SS Interface adaptor for
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
71 | P a g e 2 2 2
S.No Items Unit Qty RecommendedVendors/Brands
Temperature probes Nos 18CCTV system
33
Field Mountable cameraincluding Digital colour Cameraswith motorised zoom/focus lensand Explosion proof Pan /tilt unit
Nos 7 Videotec /SonyDvtel/Bosch/Pelco/Panasonic
Motorized zoom lens :Yamaano/optokina/tamro
34
Field Mountable cameraincluding Digital colour Cameraswith motorised zoom/focus lensand weather proof Pan /tilt unit
Nos 5 Videotec /SonyDvtel/Bosch/Pelco/Panasonic
Motorized zoom lens :Yamaano/optokina/tamro
35Telemetry receiver with 17functions.
Nos 12 Videotec/Pelco/Molynox
36
4 channel Fibre optic transmitterand receiver system for video,audio and data
Nos 5 OSD/Datacom/AMG
37
Video Cross matrix switcher andController unit with Joystickcontrol & . RS 485 datamultiplexer unit.
Nos 4 Videotec /SonyDvtel/Bosch/Pelco/Panasonic
388 channel Video distributionamplifier
Nos 4 Extron/Kramer
39 Video Recorder Nos 4 Bosch/Panasonic/Samsung/Sony
40Large LED Display monitors of42Inches
Nos 10 LG/ Panasonic/Samsung/Sony
41Large LED Display monitors of 32Inches
Nos 2 LG/ Panasonic/Samsung/Sony
42 RG 12 Co-axial cable m 4000 Techno cables/Advanced/Belden
43 Surge protectors for CCTV system Nos 25 OBO/MTL/Emerson/Sneider
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
72 | P a g e 2 2 2
S.No Items Unit Qty RecommendedVendors/Brands
44 24V AC Transformer Nos 12 Customised
Inter communication system
45 Flame proof Intercom station Nos 5 Phiaudiocom/Clearcom/Bosch
46 Weather proof Intercom stations Nos 3 Phiaudiocom/Clearcom/ Bosch
47 Rack mountable Intercom station Nos 5 Phiaudiocom/Clearcom/ Bosch
48Surge protectors for intercomstations
Nos 13 OBO/MTL/Emerson/Schneider
49 Wireless units Nos 13 Motorola/Kenwood
Timing system
50GPS/IRNSS based Universal TimeCode Generator
Nos 2 End run Technologies/T& F/ACCORD
51 Network Time display units Nos 4 End run Technologies/T& F/ACCORD
5224 core Fiber Optic Armouredcable
m 4000 Amp/Krone/HFCL/Sneider
53 RG 59 Co-axial cable m 500 Techno cables/Advanced/Belden
54 Ethernet cables m 1000 R & M/Molex/Amp/Krone/FCI/Sneider/D-link
55 3 core armoured power cable m 500 Finolex/ECI/Kundan/Anchor
56 Network switch Nos 6 Allied Telesis/Cisco/HP/3M
57 Audio Visual alarm units Nos 5 Baligha/P &F /Sneider /R &M
58 Fibre optic splicing patch panel Nos 4 R & M/Molex/Amp/Krone/HFCL/Sneider
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
73 | P a g e 2 2 2
1. PRESSURE TRANSMITTERS & MANIFOLDSSPECIFICATION FOR SMART ABSOLUTE PRESSURE TRANSMITTER
Sl.No Parameters Specification
1 Type SMART Absolute Pressure Transmitter≥300 bar Gauge pressure transmitter canalso be quoted.
2 Measurement Range As per Table 1
3 Service Medium As per Table 14 Maximum Turndown Ratio 100:15 Output Two wire 4–20 mA with superimposed
Digital communication with HARTprotocol.
6 Power Supply 12 to 30 V DC.7 Local Indication 4½ digits LCD – Local Alpha Numeric
Digital display in Engineering units.
8 Hazardous AreaCertification
Both Intrinsically safe and Explosion proofsuitable for use in Hydrogen atmosphere.(CENLEC / CSA / FM / ATEX or anyequivalent approval).
9 Safety Integrity LevelStandard (SIL)
Safety Instrumented System Certification asper IEC 61508 standard, SIL 2 or above.
10 Zero & Span Adjustments Zero and Span are to be adjusted from theHandheld HART Communicator andprovision for local adjustment to be setanywhere within the range limits.
11 Failure mode alarms High alarm ≥ 21.0 mALow Alarm ≤ 3.6 mA
12 Accuracy@ TD 8:1 for URL<300 Barand@ TD 2.5:1 for URL>300 Bar
≤± 0.085 % of Calibrated span(including the effect of Terminal - Based
linearity, hysteresis & repeatability)
13 Ambient Temperature Effectfor 28°C variation@ TD 8:1 for URL<300 Barand@ TD 2.5:1 for URL>300 Bar
≤ ± 0.4 % span
14 Stability ≤± 0.2 % of URL for 60 months
15 Power Supply Effect ≤± 0.005 % of Calibrated Span per Volt.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
74 | P a g e 2 2 2
16 Over Pressure limit Over pressure limit of selected transmittersshall be 1.25 times of URL
17 Nominal OperatingTemperature
0 – 80oC
18 Response time ≤ 150 millisecond19 Wetted Material As per Table 120 Fill Fluid As per Table 121 Transient Protection As per IEEE C62.41, category B : i) 4kV
crest , 1.2 micro sec rise time X 50 microsec delay time at half value, ii) peak surgecurrent : 4000A to housing , iii) peaktransient voltge : 100V DC, iv) loopimpedance : <25ohms,Applicable standards : IEC61000-4-4,IEC61000-4-5.
22 Drain vent port Not required.23 Electrical Connection ½ " – 14 NPT (F) with SS plug for dust
proof.24 Transmitter Process
connection½ " – 14 NPT (F) or suitable for the quotedmanifold
25 Housing Material Polyurethene covered aluminium with ½”-14 NPT conduit entry.
26 External Grounding screwassembly on transmitterbody
Required
27 Mounting Bracket Stainless Steel Bracket with SS fasteners,bolts, nuts, washers and U-clamps suitablefor 2 inch pipe mounting.
28 Calibration Calibration shall be carried out at roomtemperature in 5 steps ascending and 5steps descending. Calibration certificate isto be provided. Calibration shall betraceable to National Standards.
29 Ingress Protection IP66/6730 Manifold 2 Valve manifold. Manifold can be either
integral type or separate type. For separatetype, if any interface adaptor is required,the party has to supply the interfaceadaptor along with manifold and ensuretheir leak tightness.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
75 | P a g e 2 2 2
SPECIFICATION FOR SMART DIFFERENTIAL PRESSURE TRANSMITTER
Sl.No Parameters Specification
1 Type SMART Differential Pressure Transmitter
2 MeasurementRange
As per Table 1
3 Service medium As per Table 1
4 Turndown Ratio 100:1
5 Output Two wire 4–20 mA with superimposed Digitalcommunication HART protocol.
6 Power Supply 12 to 30 V DC.
7 Local Indication 4 ½ digit LCD- Local Alpha Numeric Digitaldisplay in Engineering unit.
8 Hazardous AreaCertification for allTransmitters
Both Intrinsically safe and Explosion proof suitablefor use in Hydrogen atmosphere.( CENELEC / CSA / FM / ATEX or any equivalentapproval).
9 Safety IntegrityLevel Standard (SIL)
Safety Instrumented System Certification as per IEC61508 standard, SIL 2 or above.
10 Zero & SpanAdjustments
Zero and Span are to be adjusted from theHandheld HART Communicator (HHC) andprovision for local adjustment to be set anywherewithin the range limits.
11 Failure modealarms
High alarm ≥ 21.0 mA
Low Alarm ≤ 3.6 mA
12 Reference Accuracy@ TD 5:1
≤ ±0.075%Span for URL above 100 mbar≤ ± 0.1% span for URL below100 mbar(including the effect of Terminal - based linearity,hysterisis & repeatability).
13 AmbientTemperature effectfor 280 C variation@ TD 5:1
≤±0.4%Span for URL above 100 mbar≤± 0.75% for URL below 100 mbar
14 Stability ≤±0.2%URL for 5 years , for URL above 100 mBar≤±0.2% URL for 1 year, for URL below 100 mar
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
76 | P a g e 2 2 2
15 Power Supply Effect ≤± 0.005 % of Calibrated Span per volt.
16 Mounting PositionEffect
Zero shifts can be calibrated out.
17 Static Pressure effect Span error: ≤ ± 0.2 % of span /70 bar for URL above100 mbar.Span error: ≤0.45 %span/70 bar for URL below 100mbar
18 Maximum Staticpressure
As per Table 1
19 Over pressure limit Over pressure limit of selected transmitters shouldbe 1.25 times of URL (Upper range Limit) .
20 Nominal OperatingTemperature
0 – 80oC
21 Response time ≤ 150 ms for URL above 100 mbar≤ 260 ms for URLbelow 100 mbar
22 Wetted Material As per Table 1
23 Fill Fluid As per Table 1
24 Transient Protection As per IEEE C62.41, category B : 4kV crest , 1.2micro sec rise time X 50 micro sec delay time at halfvalue, peak surge current : 4000A to housing, peaktransient voltge : 100V DC, loop impedance :<25ohms,Applicable standards : IEC61000-4-4, IEC61000-4-5.
25 Drain vent port Not required.
26 ElectricalConnection
½ " – 14 NPT (F) with SS plug for dust proof.
27 Transmitter ProcessConnection
½ " – 14 NPT (F) or suitable for the quoted manifold
28 Housing Material Polyurethane covered aluminum with 1/2-14NPTConduit entry.
29 External Groundingscrew assembly ontransmitter body
Required.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
77 | P a g e 2 2 2
30 Mounting Bracket Stainless Steel Bracket with SS fasteners, bolts, nuts,washers and U-clamps suitable for 2 inch pipemounting.
31 Calibration Calibration shall be carried out at roomtemperature in 5 steps ascending and 5 stepsdescending. Calibration certificate is to be provided.Calibration shall be traceable to National Standards.
32 Ingress Protection IP66/6733 Manifold 5 Valve manifold. Manifold can be either integral
type or separate type. For separate type, if anyinterface adaptor is required, the party has tosupply the interface adaptor along with manifoldand ensure their leak tightness.
Oxygen cleaning service is required for transmitters & manifold with LOXmedia.
TABLE 1
LIST OF PRESSURE TRANSMITTERSSl.No Tag No. Range
(bar )Medium Wetted Part
materialFill Fluid
ABSOLUTE PRESSURE TRANSMITTER1 PT 0 - 1.4 GHe SS316 Silicone oil2 KPI 5001 0-5 GN2/Kerosene SS316 Silicone oil3 KPI 5021 0-5 GN2/ Kerosene SS316 Silicone oil4 KPI 5041 0-5 GN2/ Kerosene SS316 Silicone oil5 KPI 5002 0-5 GN2/ Kerosene SS316 Silicone oil6 KPI 5022 0-5 GN2/ Kerosene SS316 Silicone oil7 KPI 5042 0-5 GN2/ Kerosene SS316 Silicone oil8 KPI 5061 0-5 GN2/ Kerosene SS316 Silicone oil9 KPI 2101 0-5 GN2/ Kerosene SS316 Silicone oil
10 KPI 5141 0-5 GN2/ Kerosene SS316 Silicone oil11 KPI 5161 0-5 GN2/ Kerosene SS316 Silicone oil12 KPI 5142 0-5 GN2/ Kerosene SS316 Silicone oil13 KPI 5162 0-5 GN2/ Kerosene SS316 Silicone oil14 KPI 5083A 0 - 6 GN2/ Kerosene SS316 Silicone oil15 KPI 5083B 0 - 6 GN2/ Kerosene SS316 Silicone oil16 KPI 5084A 0 - 6 GN2/ Kerosene SS316 Silicone oil17 KPI 5084B 0 - 6 GN2/ Kerosene SS316 Silicone oil18 KPI 7122 0-7 GN2 SS316 Silicone oil19 KPI 7123 0-10 GN2/ Kerosene SS316 Silicone oil
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
78 | P a g e 2 2 2
TABLE 1
LIST OF PRESSURE TRANSMITTERSSl.No Tag No. Range
(bar )Medium Wetted Part
materialFill Fluid
20 KPI 2102 0-10 GN2/ Kerosene SS316 Silicone oil21 KPI 2104 0-10 GN2/Kerosene SS316 Silicone oil22 H7911A-1 0-10 GN2 SS316 Silicone oil23 H7911A-2 0-10 GN2 SS316 Silicone oil24 HPT-701 0-10 GN2 SS316 Silicone oil25 HPT-702 0-10 GN2 SS316 Silicone oil26 HPT-703 0-10 GN2 SS316 Silicone oil27 HPT-704 0-10 GN2 SS316 Silicone oil28 HPI-6G01 0-10 GHe SS316 Silicone oil29 HPT-101 0-10 Liquid Oxygen /
VapoursSS316 Inert Fill
30 HPT-102 0-10 Liquid Oxygen /Vapours
SS316 Inert Fill
31 H7911A-1 0-10 Liquid Oxygen /Vapours
SS316 Inert Fill
32 H7911A-2 0-10 Liquid Oxygen /Vapours
SS316 Inert Fill
33 S1 0-20 Water SS316 Silicone oil34 S2 0-20 Water SS316 Silicone oil35 S3 0-20 Water SS316 Silicone oil36 S4 0-20 Water SS316 Silicone oil37 S5 0-20 Water SS316 Silicone oil38 HAL-6G19 0-250 GHe SS316 Silicone oil39 KPI 7101 0-300 GN2 SS316 Silicone oil40 KPI 7121 0-300 GN2 SS316 Silicone oil41 HPT-301 0-650 GN2 SS316 Silicone oil42 HPT-302 0-650 GN2 SS316 Silicone oil43 HPT-303 0-650 GN2 SS316 Silicone oil44 HPT-705 0-650 GN2 SS316 Silicone oil45 Spare -1 0 - 1.4 GHe SS316 Silicone oil46 Spare -2 0-10 GN2/Kerosene SS316 Silicone oil47 Spare -3 0-10 GHe SS316 Silicone oil48 Spare -4 0-10 LOX SS316 Inert Fill49 Spare -5 0-20 Water SS316 Silicone oil50 Spare -6 0-250 GHe SS316 Silicone oil51 Spare -7 0-300 GN2 SS316 Silicone oil
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
79 | P a g e 2 2 2
TABLE 1
LIST OF PRESSURE TRANSMITTERSSl.No Tag No. Range
(bar )Medium Wetted Part
materialFill Fluid
52 Spare -8 0-650 GN2 SS316 Silicone oilDIFFERENTIAL PRESSURE TRANSMITTER (Line Pressure: 10bar)
55 LLT 0-250mbar Liquid Helium SS316 Silicone oil53 KLI 2082B 0-500mbar Kerosene liquid SS316 Silicone oil54 KLI 2081B 0-500mbar Kerosene liquid SS316 Silicone oil56 H7911A-L1L 0-500mbar Liquid Nitrogen SS316 Silicone oil57 H7911A-L2L 0-500mbar Liquid Nitrogen SS316 Silicone oil58 H7911A-L1 0-500mbar LOX SS316 Inert Fill59 H7911A-L2 0-500mbar LOX SS316 Inert Fill60 HLT-301 0-1 Liquid Nitrogen SS316 Silicone oil61 HLT-302 0-1 Liquid Nitrogen SS316 Silicone oil62 HLT-303 0-1 Liquid Nitrogen SS316 Silicone oil63 HLT-304 0-1 Liquid Nitrogen SS316 Silicone oil64 HLT-101 0-1 LOX SS316 Inert Fill65 HLT-102 0-1 LOX SS316 Inert Fill66 KPDI2121 0-10 Kerosene liquid SS316 Silicone oil67 Spare -9 0-250mbar Liquid Helium SS316 Silicone oil68 Spare -10 0-1 LOX SS316 Inert Fill69 Spare -11 0-1 Liquid Nitrogen SS316 Silicone oil70 Spare -12 0-10 Kerosene liquid SS316 Silicone oil
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
80 | P a g e 2 2 2
PRESSURE TRANSMITTERS MODEL MATRIX SELECTION GUIDELINESSl.No Tag No. Range
(Bar)Medium Recommended
MakeGuide line Model Number Matrix
1 PT 0-1.4 GHe Smar LD400 A3 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Spare-1 Rosemount 3051 CA 1 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
3051 TA 1 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T06
2 KPI 5001 0-5 GN2/KEROSENEKPI 5021
KPI 5041KPI 5002 Smar LD400 A4 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4KPI 5022 Rosemount 3051 CA 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DOKPI 5042 3051 TA 2 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1KPI 5061 Honeywell STA84L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000KPI 2101 Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T06KPI 5141KPI 5161KPI 5142KPI 5162
3 KPI5083A
0 - 6 GN2/KEROSENE
Smar LD400 A4 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4
KPI5083B
Rosemount 3051 CA 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
KPI5084A
3051 TA 2 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T06Honeywell STA84L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000
4 KPI 7122 0-7 GN2 Smar LD400 A4 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Rosemount 3051 CA 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
3051 TA 2 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
81 | P a g e 2 2 2
PRESSURE TRANSMITTERS MODEL MATRIX SELECTION GUIDELINESSl.No Tag No. Range
(Bar)Medium Recommended
MakeGuide line Model Number Matrix
Honeywell STA84L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T06
5 KPI 7123 0-10 GN2/KEROSENE
Smar LD400 A4 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4KPI 2102 Rosemount 3051 CA 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
3051 TA 2 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1KPI 2104 Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T06HPT 701 Honeywell STA84L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000 OXHPT 702HPT 703HPT 704H7911A-1H7911A-2Spare-2
6 HPI-6G01 0-10 GHe Smar LD400 A4 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Spare-3 Rosemount 3051 CA 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
3051 TA 2 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T06Honeywell STA84L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000
7 HPT-101 0-10 LOX Smar LD400 A4 D 0 H 1 1 T 0 1 1 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Rosemount 3051 TA 2 A 2B 2 2 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1 P2
HPT-102 Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 K1 K3 C2 C3 M15 T06H7911A-1 Honeywell STA84L E 2 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000 OXH7911A-2
Spare-48 S1 0-20 Water Smar LD400 A4 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
82 | P a g e 2 2 2
PRESSURE TRANSMITTERS MODEL MATRIX SELECTION GUIDELINESSl.No Tag No. Range
(Bar)Medium Recommended
MakeGuide line Model Number Matrix
S2 Rosemount 3051 CA 3 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DOS3 3051 TA 3 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1S4 Yokogowa EJX610A E B S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T07S5 Honeywell STA84L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000Spare-5
9 HAL-6G19 0-250 GHe Smar LD400 A5 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Spare-6 Rosemount 3051 CA 4 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
3051 TA 4 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1Yokogowa EJX610A E D S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T15
10 KPI 7101 0-300 GN2 Smar LD400 A6 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4KPI 7121 Rosemount 3051 TA 5 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1
Yokogowa EJX610A E D S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T15Spare -7 Honeywell STG88L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000HPT301 0-650 GN2
HPT302 0-650 Rosemount 3051 TA 5 A 2B 2 1 A B4 K8 D4 Q4 Q8 QT M5 DO T1 P1HPT303 0-650 Yokogowa EJX610A E D S 4 N 0 1 7 D L KU21 A D3 N4 C2 C3 M15 T15HPT705 0-650 Honeywell STG89L E 1 G S00 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000Spare-8 0-650
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
83 | P a g e 2 2 2
PRESSURE TRANSMITTERS MODEL MATRIX SELECTION GUIDELINESSl.No Tag No. Range
(Bar)Medium Recommended
MakeGuide line Model Number Matrix
LIST OF DIFFERENTIAL PRESSURE TRANSMITTER11 LLT 0-250mbar GHe Smar LD400 D2 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4
Rosemount 3051 CD 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DOSPARE-9
Honeywell STD820 E 1 H S 1 A S 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000Yokogowa EJX110 A E M H 4 G 9 1 7 D J KU21 A D3 N4 T12
12 KLI2082B(DP)
0 -500mbar KEROSENELIQUID
Smar LD400 D2 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Rosemount 3051 CD 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
KLI2081B Honeywell STD820 E 1 H S 1 A S 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000
Yokogowa EJX110 A E M H 4 G 9 1 7 D J KU21 A D3 N4 T12
13 H7911A-L1L
0 -500mbar LIQUIDNITROGEN
Smar LD400 D2 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Rosemount 3051 CD 2 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DOHoneywell STD820 E 1 H S 1 A S 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000
H7911A-L2L
Yokogowa EJX110 A E M H 4 G 9 1 7 D J KU21 A D3 N4 T12
14 H7911A-L1 0-500 mbar LOX Smar LD400 D2 D 0 H 1 1 T 0 1 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4H7911A-L2 Rosemount 3051 CD 2 A 2 2 A 2 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 P2 D7 DO
Honeywell STD820 E 2 H S 1 A S 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000 OXYokogowa EJX110 A E M H 4 G 9 1 7 D J KU21 A K1 K3 D3 N4 T12
15 HLT-101(DP)
0-1 LOX Smar LD400 D3 D 0 H 1 1 T 0 1 1 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4Rosemount 3051 CD 3 A 2 2 A 2 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 P2 D7 DO
HLT-102(DP)
Honeywell STD820 E 2 H S 1 A S 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000 OX
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
84 | P a g e 2 2 2
PRESSURE TRANSMITTERS MODEL MATRIX SELECTION GUIDELINESSl.No Tag No. Range
(Bar)Medium Recommended
MakeGuide line Model Number Matrix
Spare-10(DP)
Yokogowa EJX110 A E M H 4 G 9 1 7 D J KU21 A K1 K3 D3 N4 T12
16 HLT301 0-1 LIN Smar LD400 D3 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4HLT302 Rosemount 3051 CD32 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DOHLT303 Honeywell STD820 E 1 H S 1 A S 1 C C H C 13C B 2 1 A6 FX F1 FE TP 0000HLT304 Yokogowa EJX110 A E M H 4 G 9 1 7 D J KU21 A D3 N4 T12SPARE-11
17 KPDI2121(DP)
0-10 KEROSENELIQUID Smar LD400 D4 1 0 H 1 1 T 0 1 0 I 2 1 0 I 2 A 9 H 1 0 Y2 Y1 Y0 M4
Spare-12(DP)
Rosemount 3051 CD 4 A 2 2 A 1 A S6 B4 K8 L4 M5 Q4 Q8 D4 QT D4 T1 P1 D7 DO
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
85 | P a g e 2 2 2
SPECIFICATION OF 2 VALVE MANIFOLD
SPECIFICATION OF 5 VALVE MANIFOLD
1 Type : 2 valve manifold2 Material : 316 SS3 Packing material : PTFE4 Seat type : Integral5 Instrument Connection : Suitable for quoted transmitter interface6 Process connection : ½ inch-14 NPTF7 Maximum Operating
Pressure: 400 bar (for transmitters up to 300bar
pressure range)650 bar (for transmitters above 300barpressure range)
8 OperatingTemperature
: 0 to 100 Deg C
9 Hydro Testing : To be carried out at 1.5 times themaximum operating pressure for all themanifolds and certificate to be provided
10 Material Test certificate : To be provided11 Mounting Bolts : To be supplied with SS material.12 Oxygen cleaning : Oxygen cleaning to be carried out for
transmitters operating in oxygenmedium.
1 Type : 5 valve manifold2 Material : 316 SS3 Packing material : PTFE4 Seat type : Integral5 Instrument Connection : Suitable for quoted transmitter interface6 Process connection : ½ inch-14 NPTF7 Maximum Operating
Pressure: 400 bar
8 Operating Temperature : 0 to 100 ° C9 Hydro Testing : To be carried out at 1.5 times the
maximum operating pressure for all themanifolds and certificate to be provided
10 Material Test certificate : To be provided11 Mounting Bolts : To be supplied with SS material.12 Oxygen cleaning : Oxygen cleaning to be carried out for
transmitters operating in oxygenmedium.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
86 | P a g e 2 2 2
Along with offer, the vendor shall supply the detailed catalogue and theselected model matrix for pressure transmitter and manifold. Thedimensional drawing for manifold shall also be provided.
2. GUIDED WAVE RADAR LEVEL SENSOR1. Type : Guided wave radar2. Measurement Principle : Time Domain reflectometry (TDR)3. Medium : Kerosene4. Measuring range : 1.3m-1No,1.8m-1No,2.2m-1No
3.6m -5NosSpare: 1.8m-1No,2.2m-1No(The exact length will be provided atthe time of detailed engineering.)
5. Process pressure : 10 bar6. Process Temperature : 300K7. Accuracy : 3mm or 0.03 % of measured distance
whichever is greater8. Repeatability : better than 1mm9. Ambient temperature effect : 0.2 mm/K10. Update interval : < 1 sec11. Reference condition : 298 K and ambient pressure in water12. Microwave output power : 0.3mW to 45 mW13. Display : Integral digital display to be provided
to display the level14. Output : 2 wire, 4 to 20 mA analog output and
HART signal superimposed on analogoutput
15. Power supply : 16-42 VDC16. Probe type : Coaxial/Flexible with centring disc17. Material : SS316L18. Process connection : 2” Flange, ANSI 2500# CL19. Housing material : Polyurethene covered aluminium20. Ingress protection : NEMA 4X and IP 6621. Vibration resistance : Housing : IEC 60770-1 Level 122. Electromagnetic compatibility : Emission and immunity :
EN61326-1:1997
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
87 | P a g e 2 2 2
Along with offer, the vendor shall supply the detailed catalogue and theselected model matrix.
3. TEMPERATURE TRANSMITTERInputs : a. 2/3/4 wire Pt 100 IEC
: b. 2/3/4 wire Pt 500 IEC: c. Thermocouples: B,E,J,K,N,R,S,T types: d. Ohms:0-2000Ω: e. millivolt : -10 to 100 mV
Output Signal : Two-wire, 4-20mA with superimposed digitalcommunication (HART protocol)
Power Supply : 12 to 42 VDCDigital Accuracy (Excludingsensor)
: Given in table.2
Minimum span : Given in table.24-20 mA D/A accuracy : ≤ ± 0.03% of spanCJC accuracy for T/C : ±0.25 degCAmbient Temp effect for 10 °Cvariation in temperature
: RTD (IEC: Pt50, Pt100): 0.04ohm Ohm (0...2000ohm) & RTD (IEC: Pt500):
0.3ohm mV (-10...100 mV) & TC (NBS: E, J, K, N):
15µV .Stability 0.05%URL for 5 yearsIndication : 4½ or 5 digit LCD indicatorZero and Span Adjustment : By Hand-Held Terminal or Local adjustment.
Temperature Limits : Operation: 15 to 500C: Storage : 15 to 600C
Sensor Failure : In case of sensor or circuit failure, the selfdiagnostics to drive the output to 3.9 or to21.0mA,user selectable.
Humidity Limits : 10 to 100% RH (non condensing)Turn-on Time : ≤ 10 secondsUpdate Time : ≤ 0.5 secondsDamping : 0 to 30 sec (adjustable)Power Supply Effect : ≤ ± 0.005% of calibrated span per volt.
EMI Effect : To be designed to comply with IEC standardsAlarm : As per NAMUR standards.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
88 | P a g e 2 2 2
Configuration : To be done by an Hand- Held terminal (HARTprotocol) or locally using switches.
Hazardous Location : Intrinsically safe certified ATEX II 2G Ex ia IICT6.
Electrical connection : ½-14 NPTMaterial of Construction : Painted copper aluminum housing, with Buna
N 0-rings on coverIngress Protection : IP66/67Accessories : Mounting bracket to be supplied to mount on
2” pipeTable 2
Range &Input
Accuracy
Type Range(°C) Min. Span(°C)
DigitalAccuracy 0C
RTD Pt 100 -200 to 850 10 ± 0.2Pt 500 -200 to 450 10 ± 0.2
T/C B 100 to 1800 50 ± 0.8E -50 to 1000 25 ± 0.2J -150 to 1200 30 ± 0.3K -180 to 1350 60 ± 0.6N -100 to 1300 50 ± 0.5R 0 to 1750 40 ± 0.6S 0 to 1750 40 ± 0.5T -200 to 400 25 ± 0.3
OHM Ohm 0 to 2000Ω 20 Ω ±0.35 ohmmV mV -10 to 100mV 3mV ± 0.02%
Guidelines for Model matrix selection:
Smar: TT301 1 2 1 0 ZZRosemount: 3144P D1 A 1 I1 B5 M5 G1 T1 A1 CN C4 QGHoneywell: STT 850 S 0 C C H C 4 S A 3 1 A6 F1
Along with offer, the vendor shall supply the detailed catalogue and theselected model matrix.
4. MASS FLOW METERFlow tube :
Type : Coriolis Mass flowTag No : As per Table-1
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
89 | P a g e 2 2 2
Fluid Medium : Kerosene
Maximum Operating pressure : 10bar(g)Operating Flow range : 10-45m3/hrLine size (NB) : 3”End Connection : RF Flanged ANSI B16.5, #150 class
flange ratingProcess temperature : 290 to 323 KMass flow accuracy (Including linearity ,Repeatability & zero stability)
@ Max. flow & Min. flow : ≤± 0.15% of ReadingPressure Drop
@ Max. flow & Min. flow : < 0.05MpaTemperature accuracy : ± 1°C ± 0.5% of rate in °CMaterials of constructionFlow Tube & Flange
Housing
: SS 304L/SS316L
SS 304/SS316TransmitterTransmitter Output : 1. One active 4-20 mA output to
represent Mass Flow withHART communication
2. One passive 4-20 mA outputto represent Mass /temperature / density3. One active pulse output formass flow rate
Power supply : 24 V DC ±10%Field mount housing : Epoxy painted cast Al housing
Housing protection : NEMA 4X (IP67)Flow Transmitter Mounting : Remote/Integral mount (For
remote mount: mounting kit to beprovided, interconnecting cable tobe supplied)
Local display : LCD display, Flow rate/ Total inEngineering unit.
Programming : Through Front Panel Key Pad &HART Communicator
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
90 | P a g e 2 2 2
The party shall provide the following along with the quote
Catalogue, Drawing & Specifications:
The party shall provide detailed catalogue showing part numbers andoptions selected in their quotation.
The party shall provide with dimensional drawing of quoted flowmeter.
The quote shall indicate the inaccuracy of flow meter including Non-linearity, Repeatability ,Long term stability & Zero stability for theminimum and maximum flow rates.
Flow meter Sizing Sheet
The party shall provide detailed sizing sheet with Pressure drop,Velocity & Accuracy for operating flow range.
During procurement and supply phase, the vendor shall provide with
Calibration Certificate
Calibration certificate of fully assembled flow meter from NationalAccredited Laboratory shall be provided.
Calibration shall be carried out at minimum 5 points of required flowrange, with water or equivalent medium, preferably water.
Accuracy of calibration rig to be provided.
The accuracy change due to calibration medium other than water shallbe provided.
The vendor shall dispatch the items, only after the approval ofcalibration certificates.
5. HART COMPATIBLE HAND HELD COMMUNICATOR FORPROGRAMMING THE TRANSMITTERS.HART communicator suitable for communicating with all quoted pressure,temperature, Guided Wave level & flow transmitters. The communicatorshould be able to communicate all device specific and generic commands.The required updated versions of DDs shall be loaded.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
91 | P a g e 2 2 2
6. FLOW SWITCHType : Flow switch with one DPST / DPDTInput:1. Should sense the presence of flow2. Max operating pressure : 10 bar gauge3. Flow range : 2 to 10 l/s4. Wetted Part : Stainless steel suitable for KeroseneOutput:1. Electrical output : Potential free contact2. Excitation : 10 VDC3. Switching electrical rating : 24 V/50 mA4. Switch operating mode : Normally open5. Set point accuracy : 2%6. Dead band : 1%Environmental:1. Construction : Hermetically sealed2. Operating Temperature : -55 deg C to +70 deg C3. Humidity : 100 % RH4. Mechanical shock : 50 g5. Enclosure : Explosion proofPhysical:1. Electrical connection : MIL standard bayonet locking type hermetic
connector with required number of pins orpigtailcable of length 500 metres
2. Process connection : ½” NPTM
The party shall provide the following along with the quoteCatalogue, Drawing & Specifications: The party shall provide detailed catalogue showing part numbers and
options selected in their quotation.
The party shall provide with dimensional drawing of quoted flowswitch.
7. PRESSURE SWITCHType: Pressure switch with one DPST / DPDTInput:1. Set Pressure : 8/50 bar absolute2. Max operating pressure : 10/60 bar absolute3. Over Pressure : 2 times Max. operating Pressure4. Burst Pressure : 3 times Max. operating Pressure
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
92 | P a g e 2 2 2
5. Wetted Part : Stainless steel suitable for GN2Output:1. Electrical output : Potential free contact2. Excitation : 24 VDC3. Switching electrical rating : 24 VDC/50 mA4. Switch operating mode : Normally open5. Set point accuracy : ≤ 2% of set pressure6. Dead band : ≤ 1% of set pressureEnvironmental:1. Construction : Hermetically sealed2. Operating Temperature : -55 deg C to +70 deg C3. Humidity : 100 % RH4. Mechanical shock : 50 g5. Enclosure : Explosion proofPhysical:1. Electrical connection : ½” NPTF2. Process connection : ½” NPTMThe party shall provide the following along with the quote
Catalogue, Drawing & Specifications:
The party shall provide detailed catalogue showing part numbers andoptions selected in their quotation.
The party shall provide with dimensional drawing of quoted pressureswitch.
8. SOLENOID VALVE1. Valve Body
Type: Three way, Normally closed
Body material : SS 316
Housing : Die cast Aluminium epoxy painted
Stem: SS 316/ SS304
Seat: Viton
End connection: Threaded female NPT conforming to ANSI-B1.20.1.1/4" NPT (F)
Mounting altitude: Any altitude without affecting their operation.
Orifice Size: <3 mm
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
93 | P a g e 2 2 2
2. Solenoid
Power supply : 24 VDC / 300 mA (max)
Solenoid coil: Suitable for continuous energization.
Enclosure: IP 65
Coil insulation: Class F as defined in IS: 1271.
Coil pick up voltage: Between 50 to 70% of normal supply voltage.
Coil drop up voltage: Between 30% to 50% of nominal supplyvoltage.
Coil temperature rise: Not to exceed 70°C.
Single coil
Response Time : Less than 100 ms.
Conduit connection: Enclosure shall have 1/2” NPT (F) connectionfor power Supply cable.
Mode of operation: Direct operated
Manual operation : Provision to open the valve using Lever
Freewheeling Diode : Two diode in series to be provided
3. Process condition
Fluid: GN2
Operating Pressure: Min. 2 bar, Max. 10 bar, Nominal: 7 bar
Service Life : 50,000 cycles
Operating Temperature: 30°C to 40°C
Relative humidity: up to 95%
The party shall provide the following along with the quote
Catalogue, Drawing & Specifications:
The party shall provide detailed catalogue showing part numbers andoptions selected in their quotation.
The party shall provide with dimensional drawing of quoted solenoid.
9. SOV CUBICLEEnclosure
1. Type : Suitable for mounting 4+1 no of SOVs
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
94 | P a g e 2 2 2
2. Enclosure protection : SOV cubicle : Weather proof to IP 65Junction Box : Flame proof
3. No of JB per SOV cubicle : One4. Material : SOV cubicle : CRCA 3.2 mm thick
Junction Box : Die cast Aluminium alloy(LM6)
5. Cover : Hinged for SOV cubicleBolted for Junction Box
6. Colour : Epoxy base, shade 631 IS : 5 (Light Grey)
7. Body grounding : Earthing screws of SS material with washer8. Size : Suitable for accommodating 5 SOVs and
header9. Mounting Interface Provision to mount the air header,
solenoids and outlet tube to EP valves to beprovided inside the SOV cubicle. The airheader shall be welded to 1 ” pipe andtaken outside the cubicle and the end shallbe provided with 1” 150# class RF Flange
10. Transit Arrangement : Lifting Hook to be provided
Terminals
1. No. of Terminals : 10 Terminals (Each suitable for 2.5mm2 )2. Style : Clip on type3. Mounting : On DIN rail with end stoppers
Cable Gland
1. No of cable entry : One per Junction Box2. Cable gland : SS Single compression type3. PVC hood for cable gland : Each cable gland to be supplied with
suitable size PVC hood4. Cable entry : Multipair cable entry at bottom of JB
General
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
95 | P a g e 2 2 2
1. Pneumatic connection : Suitable for fixing bulk head union for 8mm OD SS tubes. The vendor has tosupply this bulk head union for allcubicles. This excludes the supplymentioned in S.No:10 Compressionfittings. Inspection and clearanceprocedure shall follow same procedure forcompression fittings.
2. Interconnection : SOV cubicle and JB to be interconnected bysealed nipple
3. Tag Plate : Aluminium anodized nameplate indicatingthe equipment to be controlled shall beprovided on each local SOV cubicle. Theparticulars of the plate will be supplied tothe vendor. Nameplate shall be fixed byscrews and not pasted. Tag plate shall befixed firmly on the front face of the cubicleand JB cover
10. JUNCTION BOX1. Enclosure
All Junction Box shall be explosion proof.
The degree of ingress protection shall be IP66.
The equipment shall be suitable for operating in humid & corrosiveatmosphere
Junction box shall have housing of cast aluminum LM6 alloy
All Junction Box shall be provided with neoprene gaskets.
All accessories like nut, bolts, washers etc shall be made of stainlesssteel SS- 304.
Conduit and cable entry- Side & Bottom Entry
Door of JB- Hinged with proper locking arrangement to avoid entryof dust and moisture
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
96 | P a g e 2 2 2
Ambient temperature-50 deg C
Ambient humidity-0-100 % RH
Earthing : Two numbers of Earthing bolts for JB Earthing.
Junction box size shall be as per the following dimensions:
600 x 400 x 225 mm
300 x 300 x 165mm
2. Terminal blocks
Terminals shall be shrouded and shall be numbered as per thewiring diagram. Minimum rating of the terminal block shall be 5Amps.
For Individual shielded multipair cables a separate terminal shallbe provided for each shield drain wire.
Terminal Strip- screw-less cage clamp type capable of terminating 1sq.mm and 1.5 sq mm cables
3. Name plate
Aluminium anodized nameplate indicating the equipment to becontrolled shall be provided on each local Junction Box. Theparticulars of the plate will be supplied to the vendor. Nameplateshall be fixed by screws and not pasted.
The letter shall be engraved in black on white background.
Certificate numbering date and gas group classification must beindicated on the manufacturer’s nameplate on each junction box.
4. Mounting
Junction Box shall have 4 lugs for fixing on wall or fabricated steelsupport. The lugs shall be offset so that the rear of the unit stays awayfrom the surface by at least 5mm. Two of the holes shall be roundand the other two oblong to facilitate correct positioning. All screws,nuts and studs etc. shall be of electro galvanized or zinc passivatedtype.
5. Painting
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
97 | P a g e 2 2 2
The enclosure shall be treated & prepared for painting with two coatsof Dark admiralty grey shade 632 of IS-5 epoxy paint (Both insideand outside)
The party shall provide the following along with the quote
Catalogue, Drawing & Specifications:
The party shall provide detailed catalogue & dimensional drawing ofquoted junction box and SOV cubicle.
Dimensional drawing shall indicate pneumatic tubing entry, insideheader and cable entry provisions
During Detailed engineering, the exact number of cable entries shall bedecided and the final drawing shall be approved by Departmentbefore fabrication.
11. SS TUBES & COMPRESSION FERRULE FITTINGSSS Tube:
1. Type : Seamless SS tubes2. Outside Diameter : As given in Table 33. Wall Thickness : As given in Table 34. Material grade : As Given in Table35. Ends : Both the ends shall be plain with square cuts.
All the burrs at the ends of tubes shall beremoved.
6. The tubes shall be supplied in lengths of 6 meters.
7. Test and Inspection : The tubes shall be tested and inspected as perthe quality assurance plan given in Table 4
8. Cleanliness : All the tubes shall be suitably cleaned/ pickledand dried.
9. Documentation : Along with dispatch documents, thecertificates of test specified in the QAP (Table4), Pre-delivery Inspection certificate by thesupplier’s quality control (QC) inspector andguarantee certificate shall be provided.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
98 | P a g e 2 2 2
10. Marking and packing : The tubes shall be marked, packed andloaded for transportation as per ASTM A 700.Identification marks such as specification,material grade, heat and batch number, size,wall thickness and year of manufacturing shallbe stenciled on each tube.
11. Quantity variation : The variation in the quantity of tubes suppliedshall be permissible to the extent of 10 % ofthe quantity ordered.
Table 3:
Sl. No Outside Diameter Wall Thickness Material Grade
1. ½” 2.2 mm ASTM A 269 TP 316 L
2. ½” 7.47 mm ASTM A 269 TP 316 L
3. 8.0 mm 1.0 mm ASTM A 269 TP 316 L
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
99 | P a g e 2 2 2
Table 4: QUALITY PLAN
Sl.No
TestComponenttested
Characteristicssought for
Extendof test
TestProcedure
Acceptancecriterion
Formofrecord
Pre Delivery inspection
TestPerformedby
Testwitnessedby
Recordsreviewedby
1 VisualInspection
All tubes Surface Finish 100% VisualExamination
Workmenlike finish
InspectionCertificate
Supplier’squalitycontrolInspector
- Purchaser
2 ChemicalAnalysis
Specimenfromtubes
ChemicalComposition
1 perheat
ASTMA751
ASTM A269 Material TestCertificate
Supplier’sor GovtapprovedLaboratory
- Supplier’sQCInspector&Purchaser
3 Mechanicaltest(Tensile &hardnessTest)
SpecimenfromTubes
MechanicalProperties
1 perlot
ASTMA370
ASTM A269 Material TestCertificate
Supplier’sor GovtapprovedLaboratory
- Supplier’sQCInspector&Purchaser
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
100 | P a g e 2 2 2
Sl.No
TestComponenttested
Characteristicssought for
Extendof test
TestProcedure
Acceptancecriterion
Formofrecord
Pre Delivery inspection
TestPerformedby
Testwitnessedby
Recordsreviewedby
4 Hydro-staticPressuretest
Tubes StructuralIntegrity underpressure
100% ASTMA530
ASTM A530 Testcertificate
Supplier Supplier’sQCInspector
Purchaser
5 Flattening Specimenof 65mmlengthcut fromthe endsof thetubes
Ductility andsoundness
5% ASTMA530
ASTM A530 Testcertificate
Supplier Supplier’sQCInspector
Purchaser
6 Intergranularcorrosion(IGC) test
SpecimenFromtubes
Grain Structure 1 perlot
ASTMA262practiceA/E
ASTM A262practice A/E
Testcertificate
Supplier Supplier’sQCInspector
Purchaser
Procurement, Installation and Commissioning of Instrumentation System for BSF Annexure A: Scope of work and services
101 | P a g e 2 2 2
Sl.No
TestComponenttested
Characteristicssought for
Extendof test
TestProcedure
Acceptancecriterion
Formofrecord
Pre Delivery inspection
TestPerformedby
Testwitnessedby
Recordsreviewedby
7 EddycurrentTest
Tubes Internal FlawDetection
100% ASTME426
ASTM E426 Testcertificate
Supplier Supplier’sQCInspector
Purchaser
8 Cleaning Cleaning 100% CGAG-4.1(or) ASTMG-93
CGAG-4.1(or) ASTMG-93
certificate
Supplier Supplier’sQCInspector
Purchaser
9 Dimensionchecking
All tubes 100% Metrology Manufacturedrawing
Report Supplier Supplier’sQCInspector
Purchaser
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
102 | P a g e 2 2 2
SPECIFICATIONS OF SS TUBE FITTINGS1. Description of the item : SS Double compression Ferrule Fittings
2. Applicable standard : ASTM F 1387-99
3. Outer diameter of thetube
: As per Table 3
4. Type of fittings : Double compression Ferrule with Nut andbody
(Type : IV as per ASTM F 1387)
5. Material of the fittings : Grade B, SS 304 L/SS 316L
6. Operating pressure : 400 bar/650 bar
7. Shape of the Fitting : As per Table 5
8. Tests & Inspection :
Certification of Testing: The vendor shall provide a certificate that samplesof fittings of the same design, material and manufacturing process as thatof the fitting supplied have been subject to standard performance tests(such as examination of specimen, pneumatic proof test, hydrostatic prooftest, impulse test, flexure fatigue test, tensile test, burst test, repeat-assembly test and rotary flexure test) as per Table 3 of ASTM F 1387.
Certification of raw material: The vendor shall provide a certificate ofcompliance stating that all applicable requirements of raw material aremet. Besides, copies of the MIL certificates for the physical and chemicalproperties of the raw materials shall be supplied.
Leakage test: One sample from each type of fitting shall be subjected toleakage test with Helium Mass Spectrometer Leak Detector (MSLD) bytracer probe technique. The acceptance criterion shall have leakage finerthan 1 x 10-6 Std.cm3/sec.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
103 | P a g e 2 2 2
9. Marking : All fittings must be marked with followingdetails
a) Pressure rating
b) Raw Material and
c) Size of the end connection
Conditions:
All the fittings shall be neatly packed before delivery.
The test and inspection certificates as mentioned in Para (9) shall be suppliedbefore delivery of the items to the Department. After approval of thecertificates by Department, the party has to dispatch the items.
Table 5
Type OperatingPressure
(bar)
Qty Unit
1/2" NPT Male to 12.7mm SS tube 400 150 Nos1/2" NPT Female to 12.7mm SS tube 400 100 Nos12.7mm SS tube union 400 120 Nos12.7mm SS tube Tee 400 60 Nos1/2" NPT Male to 12.7mm SS tube 650 50 Nos1/2" NPT Female to 12.7mm SS tube 650 50 Nos12.7mm SS tube union 650 15 Nos12.7mm SS tube Tee 650 10 Nos1/4" NPT Male to 8mm SS tube 400 150 Nos1/4" NPT Female to 8mm SS tube 400 150 Nos8mm SS tube union 400 125 Nos8mm SS tube Tee 400 75 NosBulk head union for 8mm tube 400 25 Nos½” NPT SS Plug 400 100 Nos¼” NPT SS Plug 400 100 Nos
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
104 | P a g e 2 2 2
12. PVC CABLECONSTRUCTION:
96 Core (48x2 core) PVC Data Cable (Un-Armoured)- FRLS Type
20AWG (7/0.31) Annealed tinned high conductivity copper conductor,insulated with polyethylene, 2 cores of Red and Black twisted to form a pairmelinex taped, aluminum mylar tape shielded with 7/0.31mm Annealedtinned copper drain wire run continuously in contact with aluminum side ofthe tape, melinex tapped, PVC sheathed, such 48 such groups laid up,melinex tapped, overall sheathed with FRLS PVC and Blue in color.
96 Core (48x2 core) PVC Data Cable (Un-Armoured)- FRLS Type
18AWG (19/0.25mm) Annealed tinned high conductivity copperconductor, insulated with polyethylene, 2 cores of Red and Black twisted toform a pair melinex taped, aluminum mylar tape shielded with 7/0.31mmAnnealed tinned copper drain wire run continuously in contact withaluminum side of the tape, melinex tapped, PVC sheathed, such 48 suchgroups laid up, melinex tapped, overall sheathed with FRLS PVC and Blue incolor.
64 Core (16x 4 core) PVC Data Cable (Un-Armoured)- FRLS Type
Two pairs of 7/0.31mm (20AWG) Annealed tinned copper conductor,insulated with polyethylene, first pair coloured brown and grey, second paircoloured yellow and violet, the two pairs laid up to form a group, melinextaped, mylar backed aluminum taped with a drain wire of size 7/0.31mmAnnealed tinned copper, melinex tapped, PVC sheathed, such 16 groups laidup, melinex tapped, overall sheathed with FRLS PVC and Blue in color.
10 Core PVC Cable (Armoured)
5 pairs of 19/0.25mm (18 AWG) annealed tinned copper conductor,polyethylene insulated, cores colour coded, all the 5 pairs laid up to form agroup, melinex taped, mylar backed aluminum taped with a drain wire ofsize 7/0.31mm Annealed tinned copper, melinex tapped PVC sheathed, steelround GI wire armoured and overall sheathed with FRLS PVC and Blue incolor.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
105 | P a g e 2 2 2
4 Core PVC Cable (Armoured) – FRLS Type
2 pairs of 7/0.31mm (20 AWG) annealed tinned copper conductor,polyethylene insulated, cores colour coded, both pairs laid up to form agroup, melinex taped, mylar backed aluminum taped with a drain of size7/0.31mm Annealed tinned copper, melinex tapped, PVC sheathed, steelround GI wire armoured and overall sheathed with FRLS PVC and Blue incolor.
2 Core PVC Cable (Armoured) – FRLS Type
One pair of 7/0.31mm (20 AWG) annealed tinned copper conductor,polyethylene insulated, cores colour coded, melinex taped, mylar backedaluminum taped with a drain of size 7/0.31mm Annealed tinned copper,melinex tapped, PVC sheathed steel round GI wire armoured and overallsheathed with FRLS PVC and Blue in color.
DETAILED SPECIFICATIONS:
1. Voltage grade : 300 V
2. Operating temperature : 0 Deg.C to 60 Deg.C
3. Conductor :
a) Material : Annealed Tinned copper as per IS:8130
b) Size of the conductor : 20AWG (7/0.31mm)
18AWG (19/0.25mm)
4. Insulation :
a) Material : solid polyethylene type-03of BS6234
b) Thickness (Nom.) : 0.40 mm
c) Pair colors : 96 Core (48x2 core):
Pair : Red and black (Twisted)
64 Core (16x4 core):
First pair : Brown and Grey (Twisted)
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
106 | P a g e 2 2 2
Second pair : Yellow and Violet (Twisted)
10 Core:
1-st pair : White and Blue (Twisted)
2-nd pair : White and Orange (Twisted)
3-rd pair : White and Green (Twisted)
4-th pair : White and Brown (Twisted)
5-th pair : White and Grey (Twisted)
4 Core
First pair : Brown and Grey (Twisted)
Second pair : Yellow and Violet (Twisted)
2 Core
Red and Black (Twisted)
d) No. of twists/mtr : 30 (Min)
e) Dia. over insulation (Nom.) : 1.75 mm
5. Screening over group :
a) Tapping before and after : Thickness of melinex tape to be 0.025mm(100% screening Coverage, min-20%overlap)
b) Screening :
i) Material : Aluminum mylar tape
ii) Thickness : 0.044mm
iii) Coverage and overlap : 100% Coverage and 35% overlap
iv) Drain wire : 7/0.31mm Annealed tinned copper
6. Inner sheath :
a) Material : PVC type ST2 of IS:5831with FRLS
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
107 | P a g e 2 2 2
properties
b) Thickness (Nom.) : 0.65 mm
c) Color : Black
7. Outer sheath :
a) Material : PVC type ST2 of IS:5831with FRLSproperties
b) Thickness (Nom.) : 2.2 mm (96 & 64 Core)
2.0 mm (10,4 & 2 Core)
c) Color : Blue
8. a) Insulation elongation : 300%
b) Sheath elongation : 150%
c) Insulation T.S : 100 Kg/cm2
d) Sheath T.S : 125 Kg/cm2
9. a) Approx. overall diameter : 96 Core : 46.0 mm
64 Core : 46.0 mm
10 Core : 19.0 mm
4 Core : 16.0 mm
2 Core : 10.0 mm
b) Tolerance : ± 2mm
10. Electrical parameters :
a) Conductor resistance at 20deg.C
: 20 AWG: 40.0 Ohms/Km
18 AWG: ≤ 21.5 ohm/Km
b) Min. Insulation resistance offinished cable at RoomTemperature
: 5000 Mohms-Km
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
108 | P a g e 2 2 2
c) Max. Mutual capacitance : 75.00 pF/m at 0.8/1.0KHz
d) Max. capacitance core toscreen at 0.8/1.0KHz
: 400 pF/m
e) Max. drain wire resistance(with screen contact)
: 37 ohms/Km
f) Inductance : < 650 H/Km
g) L/R Ratio : 20 AWG: < 25 H/ohm
18 AWG: < 40 H/ohm
h) Static noise : better than 60dB
i) Characteristic impedance(typical)
: 20 AWG: 450 ohm ± 15%
18 AWG: 350 ohms ± 15%
HV test :
i) Conductor to conductor :1 KV for 1 minute
ii) Conductor to screen :
11. FRLS Tests :
1. Min Oxygen Indexwhen tested as perASTM D2863
: 29%
2. Min Temperature Indexwhen tested as perASTM D2863
: 250 Deg. C
3. Max Smoke Densityrating when tested asper ASTM D2843
: 60%
4. Max Acid gasgeneration when testedas per IEC 754 (I)
: 20%
5. Flammability test as perIEEE 383,IEC 332-III
: Shall meet the requirement
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
109 | P a g e 2 2 2
category-C and SS4241475 CLF3
12. General : Cable should be Anti-Rodent and Anti-termite type
13. Cable mark : a. The cable group number (1-16) shall beprinted on the cable at 0.5m interval.
b. The cable type shall be embossed /printed on the outer sheath at 1.0minterval.
14. Length marking : At every meter on outer sheath.
15. Drum lengths :
i) Standard Continuous length : 96 & 64 Core: 500 meters
10,4 & 2 Core: 1000 meters
ii) Tolerance : ±5%
Applicable only for Armoured Cables
16. Armouring
a) Material : Galvanized Steel round wire
b) Size : 1.4 mm dia
General Specifications:
1. Wherever PVC is specified virgin PVC should be used.
2. All cables should have ‘anti-rodant’ type outer sheath andshould be immune to termite attack. It is required to have theseprotections by addition of chemicals to outer sheath.
3. Cable testing as stipulated in section 1 shall be conducted andnecessary conformity certificate should be supplied by themanufacturer.
4. Thermal aging test certificate to be provided by manufacturerfor each type of cable.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
110 | P a g e 2 2 2
5. Cable should be manufactured relevant to the followingstandards.
a. Copper conductor : IS 8130 – 1984
b. Poly Ethylene (PE) insulation : BS 6234
c. PVC insulation : IS 5831.
d. FRLS properties : ASTM D2863, IEC754(I), IEC 332-III category-C and SS424 1475 CLF3
6. Proper packing material to be used during laying(manufacturing) in order that the finished sheathed cable crosssection is circular with a tolerance of ±5% of dia.
7. Cable should have proper laying to maintain circularity andtight packing with outer sheath shall be ensured.
8. Cable drum should withstand transportation and handling.
9. The drums shall be proofed against attack by white ant ortermite, conforming to IS:10418:1982
Cable Testing
The following tests as per applicable IS/BS standard shall beconducted in the presence of Department engineer and test certificate to beprovided.
a) Conductor resistance test
b) Cold bend test
c) Insulation resistance test
d) High voltage test
e) Mutual capacitance test
f) FRLS tests:
i. Min Oxygen Index test as per ASTM D2863
ii. Min Temperature Index test as per ASTM D2863
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
111 | P a g e 2 2 2
iii. Max Smoke Density rating test as per ASTM D2843
iv. Max Acid gas generation test as per IEC 754 (I)
v. Flammability test as per IEEE 383,IEC 332-III and SS4241475 CLF3
Note:
The vendor shall provide detailed catalogue along with offer
The vendor shall provide sample piece during detailed engineering from the
manufacturer.
The tests shall be carried out in the presence of Department Engineer.
The vendor shall provide test certificate before dispatch of items. The vendorshall dispatch the item only after clearance of test certificates by Department.
13. CABLE TRAYSPerforated Cable Tray:
Type : Perforated type cable trayMaterial : Mild Steel As per IS: 2062 / 1079Finish : Hot dip galvanized, Self-color.Galvanizing : As per IS: 2629 / 4759Length : Standard length of tray is 2500 / 3000mmLoading : As per NEMA standardSize : As per table 6
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
112 | P a g e 2 2 2
Table 6
WIDTH (mm) HEIGHT (mm) THICK (mm)
50 25 1.6
100 25 2.0
150 50 2.0
300 50 2.0
Note: Accessories like cross, Vertical bend, Reducer, Horizontal Tee, Couplerplates, necessary Bolts & Nuts to be quoted as 1 lot.
Ladder type Cable Tray:
Type : Ladder
Material : Mild Steel As per IS: 2062 / 1079
Finish : Hot dip galvanized, Self-color.
Galvanizing : As per IS: 2629 / 4759
Length : Standard length of tray is 2500 / 3000mm
Rung Spacing : 250 mm
Loading : As per NEMA standard
WIDTH (mm) HEIGHT (mm) THICK (mm)
300 100 2.5
Operating temperature : 60 °C maximumHumidity : Up to 95% RH
Note: The Accessories like cross, Vertical bend, Reducer, Horizontal Tee,
Coupler plates, necessary Bolts & Nuts shall be quoted.
The vendor shall provide detailed catalogue along with offer
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
113 | P a g e 2 2 2
14. STRUCTURAL STEEL MATERIALS1. Material : Structural steel includes steel sections, L
angles, Plates, steel pipes chequered &Plain plates
2. Material Governingstandard
: IS 2062 (GRADE-A)
3. Dimensions governingstandard
: IS 808 & IS 1161
4. Certificates : Test certificates showing heat number,physical and chemical properties of theitems in conformance to relevantstandard shall be sent along withdispatch documents.
15. CANOPY1. Material : CRCA steel with RAL7035 light gey
colour powder coating2. Thickness : 2mm
16. INSTRUMENTATION RACK1. Size : Height - 42U
Width - 600 mm
Depth - 800 mm
Standard : Conforms to DIN 41494 & EIA 310
2. Frame : Steel profiles
Vertical : 4 Nos -45 W x 70 D x 2000 H (mm)
Horizontal : Top 4 Nos & Bottom 4 Nos.
Front & Rear : 510W x 45H x 25D (mm)
Side : 25 W x 45H x 660 D (mm)
conforms to the specification of 7604 & 7588 IS -1285-1975
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
114 | P a g e 2 2 2
3. Steel frame along with side, top and bottom panels in steel.
4. Lockable front door made of toughened tinted glass of 5 mm Thick.
Steel frame of 18 Gauge CRCA sheet.
5. Rear steel door to be provided with a lock facility made of 18 Gauge
CRCA sheet and to comply the specifications of IS-513-CRCA.
6. Side panels with slam latches vented top cover made of 18 Gauge
CRCA sheet.
7. Cross support to be made up of 14 Gauge CRCA sheet comply the
specifications in IS-513- CRCA.
8. 100 mm Height Base Frame 600*800 mm for additional clearance for
cable entry.
9. Base frame to be made up of 13 Gauge CRCA sheet and to comply the
specifications in IS-513-CRCA.
10. 19” Mount for equipment mounting channels made of 14 Gauge
CRCA sheet and to comply the specifications in IS 513 – CRCA.
11. Equipment support angles to be made of 14 Gauge CRCA sheet as
specified in IS-513-CRCA.
12. Bottom panel with cable gland plate for cable entry.
13. Maximum Load rating of 500 kg.
14. Cross ventilation to be done with 4 fan tray made of 14 Gauge CRCA
sheet at bottom with 10 micron filters.
15. Two sets of fan trays (in a group of 4 fans per set) to be provided for
each rack.
16. Cooling fans to be provided at rear door top with ventilation holes.
17. Earthing continuity kit to be provided.
18. One No of AC mains distribution board with 5 Nos of 5A socket
(Horizontal mounting to be provided). One No per Rack to be
provided.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
115 | P a g e 2 2 2
19. Front and rear holed profiles (inter hole distance of 1U) for mounting
equipment supports to be provided. 2 Nos on the front side and 2Nos
on the rear side.
20. Vertical cable tray to be made up of polymide with black colour cover
to be provided.
21. Internal lighting to be provided with On/Off switch.
22. Rollers to be provided at the bottom for moving the racks. The rollers
should be lockable type for positioning the racks.
23. Side panels, Top & Bottom panels and doors to be powder coated
with Light grey EPOXY/Anti flame property specified in RAL 7035.
24. Frame to be made of Aluminium extrusions powder coated specified
in RAL 7037 Dark Grey.
2. Accessories1. Powder coated Support angles (14 Gauge
CRCA sheet)125
2. Powder coated filler plates3. - 1U 504. - 2U 505. - 3U 506. - 4U 507. - 5U 508. - 6U 509. Keyboard tray 510. 19” rack mountable polyamide cable manager
with cover(black color)50
11. Fasteners (Captive mounting hardware) 1500 (As 100No perpack/rack)
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
116 | P a g e 2 2 2
Tests to be done
Powder coating As per Standard OS -02
Phosphate conversion coating As per IS 3618
Chromate conversion coating As per IS 11232
Salt spray test ASTM B 117 creepage should be lessthan 1/16th after 100 hrs.
For corrosion protection Electroplating of zinc over steel plates tobe done as per IS 1573-1970
Corrosion Resistant Humidity test as per IS 101 R/T of 100%and temperature cycle of 42-48 °C.
Non-yellowing properties No yellowing to occur after 200 hrs ofexposure to ammonium carbonate
Adhesion As per ASTM D3359
No blistering after 1. 2% H2 SO4 for 8 hrs.2. 2% NaOH for 8 hrs.3. 5% detergent solutions for 8 hrs.4. In boiling water for 24 hrs.
Scratch test on rack To be done
Note: The cost of accessories as mentioned in the table shall be included in
the quoted cost.
The vendor shall provide detailed catalogue and dimensional drawingalong with offer
17. SPECIFICATION OF CONSOLES & CONTROL ROOMTABLESSPECIFICATION OF CONSOLES
There are 2 sets of consoles which includesSet1: 8 segment consoles (as 4+4 segments)
Set2: 2segment console.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
117 | P a g e 2 2 2
The console shall have work surface with a closed equipment cabinetbelow to accommodate equipments like CPU, Intercom Unit, powersupply and surface to accommodate other equipments of similar size.
The consoles shall be provided with aesthetically pleasing curved endpanels.
The layout of console shall have curved design. Console should be designed in accordance with the ergonomics
standards and accepted human factors guidelines of ISO 11064. Console shall be BIFMA X5.5 Compliant.
Work surface: The work surface includes a flat work area, PCmounting provision, a slanting surface for mounting switches andcommunication equipments on a removable panel. The work surface shall be premium acrylic solid surface material
with glossy finish (re-polishable) and should seamlesslyintegrate with the slanting portion housing the panel forswitches.
Both ends shall be thermoformed and create continuous waterfall edge to increase the aesthetics of console.
The thickness of acrylic solid surface shall be of 12mm min. Thissurface shall be mounted on Medium Density Fibre (MDF)board of minimum 25mm thick.
Surface to floor height shall be of 750 mm with 50mm heightadjustable floor leveling bolts.
Work surface depth shall be of 400mm. The width of eachconsole segment shall be of 800mm.
The work surface shall be a single unit, seamlessly integratedover the whole cluster of segments. Work surface shall becontinuous at joints of segments.
The acrylic work surface shall have Aluminum frameunderneath for support and must be rigidly fixed to the cabinetstructure to form an integral unit.
Work surface front edge shall be inbuilt ergonomic sloped withbull nose front edge. T-mould, PVC edge or vinyl edge trims arenot acceptable.
The bearable static load shall be of 50kg. Sliding keyboard tray under the work surface shall be with ball
bearing operation. Friction or roller type slides are notacceptable.
The work surface of console shall support articulated arms formounting the TFT/LCD flat monitors (diagonal size: 24 inches)with PAN (180°) & TILT (± 20°) adjustment mechanism.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
118 | P a g e 2 2 2
Slanting surface shall be provided with a removable panel formounting illumination switches and Authorization keys.
Slanting surface angle shall be of 60 degrees. The depth of thisslanting surface shall be of approximately 150mm.
The edges of the back removable panel shall be of good finishingso that it looks continuous.
Easy human access to remove and re-fix the removable panelshall be possible. Also holed profiles suitable for mounting 19”width 1U height and 225mm depth intercommunicationequipment shall be provided where necessary.
The rear view of the console shall be aesthetically pleasing andshall be provided with slat wall.
Cabinet: The console shall be provided with a rigid structured cabinet
below the work surface, heavy-duty pullout tray arrangement toaccommodate tower/desktop CPU configuration of computerworkstations, VGA Distributors, power supply units and othernecessary equipments.
Complete frame structure shall be of made of heavy dutyExtruded Vertical and Horizontal Aluminum profiles of 6036T6grade. The Extrusions shall be duly powder coated with min 40micron over all surfaces.
Except frame structure, rest of cabinet shall be made from ColdRolled Steel (CRS) Metal (14 Gauge) with powder coated finish.
The structure shall comply to BIFMA X5.5. The structure shallallow easy assembly of Gland Plate, Monitor arms etc inextremely rigid manner.
The front side of cabinet shall be fully closed. The accessibilityshall be provided from rear side alone.
It shall be possible to pull out the tray from rear side of theconsole. Pull out shall be possible to a maximum of 150mm fromthe face of the console cabinet.
Rear access doors shall provide accessibility for easy installation,operation& servicing of the equipments inside the console.
Pull out tray shall have load bearing capacity of approximately35 kg.
The console shall be designed to have adequate space foraccommodating the CPUs & accessories
The Console shall have earthing provision in structure. The cabinet shall be provided with holed profiles for mounting
19” width equipments where ever required. Console cabinet shall be provided with fan for Cooling.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
119 | P a g e 2 2 2
The console shall be provisioned with concealed electricaloutlets, information outlets (LAN) and RJ-11 Telephone jacks.
The provision for mounting of electrical outlets and telephonejacks shall be designed for flexible placement of monitors,telephones, intercommunication units and laptops on theconsole with zero cable clutter on the work surface.
Industrial grade metal powder coated finish Universal sockettype Power Distribution unit (5A, 5Nos and a master MCB) mustbe provided for power supply.
Cable entry holes shall be provided in Support legs of thecabinet for data and power cables entry in console cabinets.
PVC cable ducts with covers shall be provided for concealed andneat cable routing.
Grommets/Gasket shall be provided for cable entry holes toavoid damage of cables.
Sharp edges at the consoles base shall be avoided. End Panels:
The end panels shall be premium acrylic solid surface materialwith glossy finish (re-polishable) and should seamlesslyintegrate with the structure.
The leg cover element shall cover the structure and shouldincrease the aesthetic look of the console.
The end panels at the extreme end of consoles shall matchingcurved shapes designs.
SPECIFICATIONS OF CONTROL ROOM TABLES There are totally 6 nos of data processing tables. The data processing tables shall have work surface with a cabinet
below to accommodate CPU and a closed filing cabinet underneath thework surface.
The work surface includes a flat work area with 24” LED monitormounting provision.
The work surface shall be premium acrylic solid surface material withglossy finish (re-polishable).
Both ends shall be thermoformed and create continuous water falledge to increase the aesthetics of table.
The thickness of acrylic solid surface shall be of 12mm min. Thissurface shall be mounted on Medium Density Fibre (MDF) board ofminimum 25mm thick.
Surface to floor height shall be of 750 mm with 50mm height adjustablefloor leveling bolts.
Work surface depth shall be of 600mm. The length of table shall be of1000mm.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
120 | P a g e 2 2 2
The acrylic work surface shall have Aluminum frame underneath forsupport and must be rigidly fixed to the cabinet structure to form anintegral unit.
The bearable static load shall be of 50kg. Sliding keyboard tray under the work surface shall be with ball
bearing operation. Friction or roller type slides are not acceptable. The work surface of table shall support articulated arms for mounting
the TFT/LCD flat monitors (diagonal size: 24 inches) with PAN (180°)& TILT (± 20°) adjustment mechanism.
The rear view of the table shall be aesthetically pleasing and shall beprovided with slat wall.
The table shall be provided with a rigid structured cabinet below thework surface to accommodate tower/desktop CPU configuration ofcomputer workstations.
A closed filing cabinet shall be provided underneath work surface. The table shall aesthetically good looking. The table shall be provided with cable managers for routing cables.
The cable management shall be neat and provide zero cable clutter. One no of power distribution board with 5Nos of 5A socket and a
master MCB shall be conveniently located to power up theequipments.
The designs/layouts attached with the specifications are onlyindicative and are provided to clarify the requirements. Vendor shallprovide aesthetic designs meeting all the operational/functionalcriteria for the control room.
The vendor shall provide the following documents along with offer(for both consoles & Data Processing tables]
2D view of consoles & data processing tables indicating thedimensions
Cabinet interior layouts 3D equipment layout view of control rooms [Room-1 & Room-2]
with consoles & data processing tables in position. The catalogue and specifications of light fittings, lamps and
materials. Photographs of similar installations made
The above drawings shall be color printout by considering sitemeasurements, architectural, mechanical and electrical elementsfor each console type.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
121 | P a g e 2 2 2
Detailed Engineering phase
The party shall submit samples of solid acrylic material anddifferent variants of colors available.
Vendor/Manufacturer shall ensure that the design isergonomically sound and has excellent aesthetics.
Based on the designs and samples submitted by the supplier, thedepartment will evaluate and decide the color and dimensions.
During this evaluation, Department may suggest minormodifications and the vendor shall be willing to accommodatesuch modifications.
After the finalization of design, the party shall submitfabrication drawings.
Pre-fabrication review to include submission of drawings andcomplete components listing of selected finish materials.
Fabrication & Sample Inspection at factory site
After the approval of the fabrication drawings by theDepartment, the party shall fabricate one sample consolesegment and one data processing table.
After the inspection of sample by Department, final fabricationshall be carried out.
The offered product shall be manufactured using high qualitycomponents and shall processes to ensure consoles of highquality, good surface finish, durability and reliability.
The party shall provide with test certificates for powder coating.Same tests as mentioned for instrumentation racks shall becarried out.
Final Acceptance & Commissioning at site
Photographs of assembled consoles and data processing tableshall be furnished prior to dispatch and proper internationalstandard air worthy packing to be used to ensure undamagedand complete arrival at the destination.
Vendor shall take installation and commissioning of the consoleat Department site.
The vendor/manufacturer shall be a fully responsible for thecommissioning of product including all design services, metalwork, woodwork and millwork to ensure product consistencyand lead-time.
Fully detailed assembly instructions in the English languageshall be supplied with both written and pictorial descriptions foreach item/model numbered component with dimensions.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
122 | P a g e 2 2 2
18. SPECIFICATIONS OF TRANSFORMER ISOLATED BARRIERSTIB FOR PRESSURE AND TEMPERATURE MEASUREMENTS
Type: Transformer Isolated Barrier (Dual output)HART communication interface possible through both 4-20 mA outputs.1. Input (Intrinsically Safe)Input signal : 4 mA - 20 mAVoltage at 20 mA : 16V min2. Outputs (Not Intrinsically Safe)Output voltage : 2-10VNumber of outputs : 2Output resistance : 500Ripple : 25mV3. Power Supply:Supply voltage : 20V- 35V DCPower consumption : < 2.5 WConnection type : Power rail and terminal4. Details of certificate of conformity Group, Category, ignition protectionMethod:
: ATEX II 2 G EEx ia IIC T6Voltage (Uo) : 25.4 VDCCurrent (Io) : 86.8 mA5. Transfer CharacteristicsTransfer error :10mV including calibration,linearity
hysteresis, supply and load variationsTemperature drift : 20 ppm/KFrequency range (-3dB) :0Hz-7.5 KHz6. Galvanic Isolation Between
: Input & Output.: Input & Power supply: Output & Power supply.
7. GeneralOperating temperature : 15°C to 60°CPower supply feed provision : Through power rails/Back planeMounting :DIN rail (35 mm)II. TIB FOR CONTROL VALVE1. Input (not intrinsically safe)Connection type : TerminalsCurrent range : 4 - 20 mAMax. Current input : 40 mA2. Output (intrinsically safe)Connection type : TerminalsCurrent output : 4…20 mA
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
123 | P a g e 2 2 2
Output load : 850 ohm3. Power supplyConnection type : Power rail and terminalRated operational voltage : 20…35 VDC4. Details of certificate of conformity Group, Category, ignition protectionMethod
: ATEX II 2 G EEx ia IIC T6Voltage (Uo) : 25.2 VDCCurrent (Io) : 93 mA5. Transfer characteristicsError : 0.1 % incl. non-linearity and
hysteresisTemperature : 0.01%/KRise time : < 10second6. Galvanic Isolation Between
: Input & Output.: Input & Power supply: Output & Power supply.
7. GeneralOperating temperature : 15°C to 60°CPower supply feed provision : Through power rails/Back planeMounting : DIN rail (35mm)III. TIB FOR E/P VALVE STATUS1. InputType : Proximity/Relay.No. of channel : 2Reverse mode : To be providedLED indication : Relay output & power supplyConnections Type : TerminalsLead monitoring input current : 0.1 mA2. Output (not intrinsically safe)Connection type : TerminalsOutput I & II : signal; relayMinimum switching current : 2 mA/24V DCEnergized/De-energized delay : approx. 20 ms / approx. 20 msMechanical Life : 10^7 switching cycles3. Power supplyConnection type : Power rail and terminalsRated operational voltage : 20…30 VDC4. Details of certificate of conformity Group, Category, ignition protectionMethod
: ATEX II 2 G EEx ia IIC T6Voltage (Uo) : 10.5 V
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
124 | P a g e 2 2 2
Current (Io) : 13 mA5. Transfer characteristicsSwitching frequency : ≥10 Hz6. Galvanic Isolation Between
: Input & Output.: Input & Power supply: Output & Power supply.
7. GeneralOperating temperature : 15°C to 60°CPower supply feed provision : Through power rails/Back planeMounting : DIN rail (35mm)
ACCESSORIESThe party shall quote for all required accessories such as power rails, powerfeed modules, Din rail, mounting kit, Backplane etc.
Note:The party shall provide detailed catalogue along with offer. Along with thesupply of items, the party shall provide test certificates. The TIBs shallundergo functional test, linearity check etc at Department site after supply.After passing the test as per specification only, the TIBs shall be accepted byDepartment.
19. SPECIFICATION FOR ELECTROMECHANICAL RELAYTechnical data:
Coil side:
Nominal i/p voltage : 24 VDC
Nominal i/p current : 18 mA
Typical response time : 8 ms
Typical release time : 10 ms
Protective circuit : Reverse polarity diode and
freewheeling diode provision.
Contact side:
Contact type : 2-PDT
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
125 | P a g e 2 2 2
Contact material : AgNi
Maximum switching voltage : 250VAC/DC
Minimum switching voltage : 5VAC/DC (at 10 mA)
Minimum switching current :10 mA
Limiting continuous current : 6 A
Interrupting rating max : 140 W (at 24 VDC)
General data:
Test voltage relay winding/relay contact : 4 KVAC (50 Hz, 1min)
Test voltage PDT/PDT : 2.5 KVAC (50 Hz, 1min)
Operating temperature : -40º C to 60 º C
Mechanical life service : 3*107 cycles
Standards/Regulations : IEC 60664, EN 50178, IEC 62103
Connection data:
Connection method : Screw connection
Conductor cross section solid max : 2.5 mm2
Part No: PLC-RSC- 24 VDC/ 21-21-2967060
Note:The party shall provide detailed catalogue along with offer.Along with the supply of items, the party shall provide test certificates. Therelays shall undergo functional test at Department site after supply. Afterpassing the test as per specification only, the relays shall be accepted byDepartment.
20. SPECIFICATION OF REGULATED LINEAR POWER SUPPLIESItem Description : Dual Regulated Linear DC Power
Supplies. One unit should have twoisolated independent power suppliesassembled in a 19 inch Rack mountchassis. Output of the two powersupplies to be Diode ‘OR’ed to provide
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
126 | P a g e 2 2 2
redundancy. The output terminals ofboth power supplies shall be providedon the front panel and redundant modeis enabled by connecting external links.The high current ‘OR’ing diode andheat sink shall be fitted in the powersupply chassis.
Output : 24V DC ±20%, Current rating 20A.
Line Regulation : ±0.05% (for ± 10% change in supplyvoltage)
Load Regulation : ±0.05% from no load to full load
Ripple & Noise : 1mVrms
Output impedance : 0.05Ω
Over Voltage Protection : Crow-bar protection acting atapproximately 40V
Current Limit (Overload) : Constant current fold back type
protection having automatic crossovercharacteristics settable from 10% to110% max. of rated current by frontpanel controls.
Monitoring : Independent Digital panel meters forboth power supplies. Howevervoltage and current readings of eachpower supply can be combined in asingle display and selected by a switch.
Stability : 0.1% for eight hours
Remote Sense Provision : Required
Transient Recovery time : 100µsec
Operating Power : 230V AC ±10% 50 Hz
Operating Temperature : 0-500 C
Mounting : 19” Rack mountable
Note:The party shall provide detailed catalogue along with offer.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
127 | P a g e 2 2 2
Along with the supply of items, the party shall provide test certificates. Thepower supplies shall undergo load regulation test, ripple test, stability test,line regulation test at Department site after supply. After passing the test asper specification only, the power supplies shall be accepted by Department.
21. SPECIFICATION OF PTFE CABLES1. 18 AWG SINGLE CORE PTFE WIRES
Inner conductor : Multi Stranded silver plated copper wire ofsize AWG 18/19/0.25mm.
Standard : MIL-W-16878 (or) JSS 51034Core insulation : PTFE tape wrapped and fusedInsulation thickness : 0.25 0.05 mmConductor dia (Nominal) : 1.27 0.03 mmDiameter of core includinginsulation
: 1.87 0.1 mm
Color : Red, Black, Green, WhiteMax. Resistance of theconductor at 20 O C
: 18.99/Km
Roll : 100m 10%continuous per drum2. 20 AWG SINGLE CORE PTFE WIRES
Inner conductor : Multi Stranded silver plated copper wire ofsize AWG 20/19/0.2mm.
Standard : MIL-W-16878 (or) JSS 51034Core insulation : PTFE tape wrapped and fusedInsulation thickness : 0.25 0.05 mmConductor dia (Nominal) : 1.02 0.03 mmDiameter of core includinginsulation
: 1.57 0.1 mm
Color : Red, Black, Green, White, Violet, YellowMax. Resistance of theconductor at 20 O C
: 32.8/Km
Roll : 100m 10%continuous per drum
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
128 | P a g e 2 2 2
20AWG 64 CORE PTFE CABLE
Description : PTFE insulated silver plated copper wireSize: AWG 20/19/0.2mm, each coreinsulated and Pair twisted, each pair laid incircular construction, PTFE sheathed and 32such pairs laid in circular construction andoverall shielded and PTFE jacketed.
1. Inner conductor : Stranded silver plated copper wire of sizeAWG 20/19/0.2mm
2. Core Insulation : PTFE tape wrapped and fused
a) Insulation thickness : 0.25 0.05 mm
b) Core diameter : 1.57 0.1 mm
3. No. of cores : Two cores twisted into pair with a twistedlay of 25 mm.
4. No of twists per meter : 40
5. Colour coding : Pair : Red – Black. Each pair shall benumbered.
6. Max resistance of theconductor at 20O C
: 32.8 /Km
7. Max capacitance : ≤75 pF/m
8. Shield : Silver copper braid.
a) Shield Gauge dia : 0.12 mm
b) Coverage : > 90%
9. Overall & individual Sheath : PTFE tape wrapped and fused
a) Sheath thickness : 0.35 0.05 mm
b) Colour : Grey
10. Overall dia. of the cable : 19 5 mm
11.Packing Length : 250mts 10% continuous
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
129 | P a g e 2 2 2
20AWG 96 CORE PTFE CABLE
Description : PTFE insulated silver plated copper wireSize: AWG 20/19/0.2mm, each coreinsulated and Pair twisted, each pair laid incircular construction, PTFE sheathed and 48such pairs laid in circular construction andoverall shielded and PTFE jacketed.
1. Inner conductor : Stranded silver plated copper wire of sizeAWG 20/19/0.2mm
2. Core Insulation : PTFE tape wrapped and fused
a) Insulation thickness : 0.25 0.05 mm
b) Core diameter : 1.57 0.1 mm
3. No. of cores : Two cores twisted into pair with a twistedlay of 25 mm.
4. No of twists per meter : 40
5. Colour coding : Pair : Red – Black. Each pair shall benumbered.
6. Max resistance of theconductor at 20O C
: 32.8 /Km
7. Max capacitance : ≤75 pF/m
8. Shield : Silver copper braid.
a) Shield Gauge dia : 0.12 mm
b) Coverage : > 90%
9. Overall & individual Sheath : PTFE tape wrapped and fused
a) Sheath thickness : 0.35 0.05 mm
b) Colour : Grey
10. Overall dia. of the cable : 22 5 mm
11.Packing Length : 250mts 10% continuous
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
130 | P a g e 2 2 2
20AWG 32 CORE PTFE CABLE
Description : PTFE insulated silver plated copper wireSize: AWG 20/19/0.2mm, each coreinsulated and Pair twisted, each pair laid incircular construction, PTFE sheathed and 16such pairs laid in circular construction andoverall shielded and PTFE jacketed.
1. Inner conductor : Stranded silver plated copper wire of sizeAWG 20/19/0.2mm
2. Core Insulation : PTFE tape wrapped and fused
a) Insulation thickness : 0.25 0.05 mm
b) Core diameter : 1.57 0.1 mm
3. No. of cores : Two cores twisted into pair with a twistedlay of 25 mm.
4. No of twists per meter : 40
5. Colour coding : Pair : Red – Black. Each pair shall benumbered.
6. Max resistance of theconductor at 20O C
: 32.8 /Km
7. Max capacitance : ≤75 pF/m
8. Shield : Silver copper braid.
a) Shield Gauge dia : 0.12 mm
b) Coverage : > 90%
9. Overall & individual Sheath : PTFE tape wrapped and fused
a) Sheath thickness : 0.35 0.05 mm
b) Colour : Grey
10. Overall dia. of the cable : 19 5 mm
11.Packing Length : 250mts 10% continuous
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
131 | P a g e 2 2 2
TEST DETAILS ON EACH OF THE ABOVE MENTIONED CABLES ASPER JSS: 51034 STANDARDS
The following tests are required to be carried out at manufacturer’s site.NAME OF THE TEST EXPECTED REQUIREMENT
1. Dimensional check : As per standard
2. Concentricity of Insulation : Greater than 70%
3. Spark test : 3.4 KV for 1 sec
4. Conductor Resistance : As per standard
5. Dielectric withstanding voltage : 2.0KV for 1 minute
6. Insulation Resistance : 1500M/km.Min
7. Silver coating thicknessover conductor : 1 micron Min
8. Conductor Elongation : 10% Min
9. Insulation tensile strength : 21 106 N/m2 Min
10. Insulation Elongation : Greater than150% Min
11. Cold Bend : -65° C for 4 Hours
12. Heat resistance : 290C for 96 Hours
13. Wrap Back (307C for 2 Hours) : No cracks. No dielectric
breakdown.
14. Flammability :i) Wire shall cease to burnless than 10 sec.
ii) Total length burnt or
charred not exceed 75 mm
ON FINISHED CABLE
1. Shielded coverage : 90%
2. Dielectric withstanding voltage between core and shield
: 2 KV for 1 minute
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
132 | P a g e 2 2 2
Note:
1. The party shall provide detailed catalogue along with offer.2. The vendor shall provide sample piece during detailed engineering
from the manufacturer.
3. The tests shall be carried out in the presence of Department Engineer.
4. The vendor shall provide test certificate before dispatch of items. The
vendor shall dispatch the item only after clearance of test certificates
by Department.
22. SPECIFICATION OF POWER CABLE
Type : PVC Insulated and PVC sheathed, flexible threecore multi stranded copper cable
Voltage grade : 1.1kVSize of conductor : 2.5 mm2
Current rating : 16ANo of cores : Three (Red, Black and Green)Conforming standard : IS/IEC standards
23. SPECIFICATION OF EARTHING CABLES
Inner conductor : Multi Stranded copper wire of size 12 AWG
Insulation : PVC
Color : Green
24. SPECIFICATION OF TERMINAL BLOCKS
Type : Cage Clamp
Insulating material : Polyamide 6.6
Contact material : Tinned Copper
Size of the wire : 12-22 AWG
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
133 | P a g e 2 2 2
Colour : Grey
Cable entry : Front,Top
Current rating : 20A
Nominal Voltage : 600V
Rated Surge voltage : 8kV
Pollution Degree : 3
Voltage category :III
Flammability : UL94 V0
Compliance standard : IEC 60947-7-1
Mounting : Din rail: 35mm width
Accessories : End plate, Mounting rail, Marking ferrule.
Types I :
No: of terminals : 4
No of levels : 2 with Diode in series
Diode :1 N 4007
Qty :50Nos
Types II :
No: of terminals : 4
No of levels : 2 with Diode in parallel.
Diode :1 N 4007
Qty :50Nos
All Accessories like Separators, marking labels and end stoppers shall beincluded as one lot
Note:The party shall provide detailed catalogue along with offer.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
134 | P a g e 2 2 2
25. SPECIFICATION OF CABLE GLANDSMetal cable Gland:
Type : Metric Threaded cable glandMaterial : Nickel coated BrassCable Type : Unarmoured/armouredStandard : European EN 50262Operating Temperature : -30 °C to + 100 °CMax. Continuous temperature : +70 °CProtection : IP 67Accessories : Lock nut, Washer
Polyamide cable Gland:Type : Metric Threaded cable gland
Material : Polyamide 6
Cable Type : Unarmoured
Operating Temperature : -30 °C to + 100 °C
Application : Indoor
Compliance : RHoS, CE
Accessories : Lock nut, Washer
Note:The party shall provide detailed catalogue along with offer.
26. CABLE ENTRY PLATE1. Material : CRCA steel with RAL7035 light gey
colour powder coating
2. Dimensions : 500H x 500W x 4mm thickness
27. MOUNTING PLATE
1. Material : CRCA steel with RAL7035 light geycolour powder coating
2. Dimensions : 1600H x 480W x 2mm thickness
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
135 | P a g e 2 2 2
28. MS CONDUITS (FOR POWER CABLE LAYING)1. Material : MS conduits
2. Dimensions as pergoverning standard
: 20mm and 32mm
3. Colour : Painted black (Anti corrosive)
4. Thickness : 16 SWG
5. Joint by : Thread
6. Governing standard : IS 9537 Part-I 1980
29. INDICATORS, SWITCHES AND KEYSINDICATORS
1. Connection Method : Plugin
2. Type of Head : Square
3. Illumination colors : Red, Green, Yellow
4. Illumination type : LED
5. Contact type : Silver
6. Service category : 24VDC ; 1A
7. Approximate dimension : 24mmx18mm
8. Mounting depth : 45mm
9. Qty : 40Nos
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
136 | P a g e 2 2 2
SWITCHES WITH INDICATORS
1. Contacts : NO-3; NC-3
2. Switching Action : Maintained Action at two positions
3. Ingress Protection(IP) : IP40
4. Connection Method : Plug in
5. Type of Head : Square
6. Illumination colors : Red, Green, Yellow
7. Illumination type : LED
8. Contact type : Silver
9. Service Life : >2x106 cycles
11. Service category : 24VDC ; 1A
12. Approximate dimension : 24mmx18mm
13. Approximate Mountingdepth
: 45mm
14. Qty : 40Nos
MUSHROOM HEAD EMERGENCY STOP SWITCHES
1. Contacts : NO-3; NC-3
2. Switching Action : Maintained Action
3. Ingress Protection(IP) : IP40
4. Connection Method : Plug in
5. Type of Head : Mushroom head cap of polyimide
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
137 | P a g e 2 2 2
8. Contact type : Silver
9. Service Life : >2x106 cycles
11. Service category : 24VDC ; 1A
13. Approximate Mountingdepth
: 55mm
14. Qty : 10Nos
KEYS
1. Contacts : NO-3; NC-3
2. Switching Action : Maintained Action at two positions
3. Ingress Protection(IP) : IP40
4. Connection Method : Plug in
5. Type of Head : Square
6. Key removable position : Position1 alone
7. Contact type : Silver
8. Service Life : >5x104 cycles
9. Service category : 24VDC ; 1A
10. Approximate Mountingdepth
: 50mm
11. Qty : 10Nos
General:
Ambient temperature : -25 deg C to +55 deg C
Rated Insulation Voltage : 300V AC
Over voltage category : III
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
138 | P a g e 2 2 2
Degree of Pollution :3
Electrical specification compliance : IEC 512-2-11
Shock Resistance : IEC 512-4
Accessories:
Protective covers, Blind plugs, labels, spare keys shall be quoted.
Note:The party shall provide detailed catalogue along with offer.
30. DATA LOGGERA data logger with 32 numbers of analog input signal and 8
numbers of digital input and 8 numbers of digital output signal is to beconfigured for data acquisition, recording and on line viewing atremote location. Such four systems are required. Each system shallhave four client nodes licenses for remote online display. Software fordata acquisition, online data display, offline data viewing and datastorage shall be provided.
SYSTEM SPECIFICATION
Analog Input Module1. No: Of Inputs : 322. Sampling rate : 10Hz per channel3. Input configuration : Through PC interface4. Input Type : Single ended input5. Input range : 0 to10V6. Isolation between channels : Required7. Measurement Accuracy : ± 0.1%8. Input impedance : >1Mohm9. A/D resolution : 16 bit
Digtial Input ModuleNo: Of channels : 8
Digital Output ModuleNo: Of channels : 8
Data Acquisition & Recording Data to be acquired, recorded continuously at sampling rate of 100ms,
1/5 /10 seconds, 1 /5 /30 minutes, 1hour for 24 hours for all channels. The stored data shall be time stamped. Built – in real time clock shall be provided
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
139 | P a g e 2 2 2
Data Storage Data storage through local memory and possible to store 100ms, 48
channels data continuously for 5 days. The stored data shall be possible to transfer to a PC for centralized data
storage. This shall be made possible through file transfer protocol.
Communication Interfaces Ethernet Port
Interface: 10/100 BaseT Protocol: TCP/IP
Hardware configuration & Real Time Monitoring: Through webbrowser software
Web Server To Access current data and status from any web browser. To Customize display pages. To Download data in CSV format. To interface Command window.
FTP Client To Automatically upload logged data direct to an FTP server
FTP Server To Access logged data from any FTP client or web browser
Environmental & Mounting Operating temperature: 15 to 50°C Operating Humidity: 20-80 % RH Power Supply: 24V DC±10% (Necessary adaptors shall be provided) Mounting interfaces: 19” rack mountable
Software Package (Data Acquisition And Analysis)
1. Complete data acquisition, storage and analysis software package
Configuration Settings
2. The acquisition software shall be capable of scanning the selected user
required channels at user required sampling rate.
3. Also the per channel selection of legend, description, unit, alarm,
Engineering Unit (EU) conversion and other configurable parameters
shall be possible.
4. Logging of set configurations in notepad or in spreadsheet format.
5. This shall be made possible from a Personal Computer.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
140 | P a g e 2 2 2
6. The set configurations shall be retained in controller even after
power interruption.
Acquisition
7. The acquisition software shall be capable of being operated with
acquisition ON/OFF & recording ON/OFF features.
8. The acquisition sampling intervals shall be 100ms, 1/5 /10 seconds, 1
/5 /30 minutes, 1hour
9. Data to be stored in data storage media at the defined intervals.
10. The data shall be stored with reference to universal time.
11. This feature shall be made possible in all client nodes for the
administrator login.
12. Three level Security login levels shall be provided for the client nodes.
The viewer login shall view the parameter or graphical display.
13. Each client shall be possible to select different view pages.
Online Display and Analysis
14. The online display shall be possible at all client nodes.
15. The online display may be of graphical and numerical form.
16. The displayed data shall be in EU.
17. The graphical display shall have different scales for each parameter
and shall have four parameters per screen.
18. Multiple pages for parameter and graphical display shall be possible.
19. Maximum of 8 parameters per page and 4 parameter pages shall be
possible for numerical display in each client node.
20. Maximum of 2 graphical display pages per client shall be possible.
21. The channels for numerical and graphical display shall be selectable.
22. The alarm pop up shall be taken to the current display page.
23. The numerical and graphical display shall have the option for color
change when threshold limits are not met.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
141 | P a g e 2 2 2
24. On analysis tools such as zoom, pan etc shall be provided.
25. Alarm summary shall be provided.
Offline Processing
26. Off line viewing of recorded data for selected channels in EU withselectable intervals shall be possible. The file shall have optionalheader and stored in DAT/CSV format.
27. Offline plotting of selected channels in EU with optional headers shallbe possible.
Note: Along with offer, the party shall provide with the detailed catalogue
indicating model number and list of all accessories. The party shall include the spares for I/O modules and memory
modules if any. The spares shall be 20% of the total quantity for 4systems or 1No whichever is higher.
During detailed engineering phase, the party shall work out the SiteAcceptance procedure for the entire system.
The vendor shall take up the installation and commissioning of thesystem at site.
The vendor shall be capable of customizing the software as per userrequirement.
The vendor shall provide detailed training for 2 Department engineersfor a minimum of 2 days.
A copy of software, driver software, operating system, operation&maintenance manual and user manual shall be provided.
The network connection support will be provided by Department. The client PC will also be provided by Department. The system shall be accepted by Department, only after SAT and final
commissioning.
31. OPERATOR CHAIRS1. Overall Dimension : Total Height – 800 to 1200 mm
Overall Width – 700 to 750 mm
2. Backrest Height / width : Height ≥ 440 mm
3. Seat width/depth : Width ≥ 440 mm
4. Seat height adjustment : Pneumatic seat height adjustment shallbe provided for minimum of 90 mm.Seat height shall be adjusted by lever forthe required height and providecushioning effect for each time of sitting.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
142 | P a g e 2 2 2
5. Swivel Mechanism : Allows 360 degree lateral movement
6. Seat & Backrest : Cushioned
8. Base : 350 stiletto base stand for stability andbalance
9. Armrest : Fixed Loop armrest
10. Backbone : Die cast aluminium backbone in silverepoxy powder coating.
11. Castors : Not required.
12. Lumbar support : Integral lumber support 28-48 mmplaced in the lumber region of the back.which provides comfortable sittingposture .
13. Fabric colour : Shall be selectable by Department.fabrics during Detailed engineering.
The party shall provide with catalogue along with offer. The party shallquote for chair along with all items required for assembly.
Vendor shall provide different color sample during Detailed engineering.
The vendor shall take up assembly of chair at site.
CCTV SYSTEM
33 Field Mountable camera including Digital colour Cameras withmotorized zoom/focus lens and Explosion proof Pan /tilt unit
&
34 Field Mountable camera including Digital colour Cameras withmotorised zoom/focus lens and weather proof Pan /tilt unit
Electrical:
1. Input voltage : 24 V AC, 50 Hz2. Motor :Two phase induction motor3. Limit switch :Pan -15A, 10 million operations
Tilt-15 A, 10 million operations4. Conductor requirement :Pre-wired multi conductor cable of
length 7.5 meter
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
143 | P a g e 2 2 2
Mechanical:1. Pan range :0 to 360 deg2. Pan speed :6 deg /sec at no load condition3. Pan torque :2.5 Kgm4. Tilt range :+/- 90 deg5. Tilt speed :2.4 deg /sec at no load condition6. Tilt torque :6kgm7. Maximum load :50 Kg8. Gearing :Adjustable worm gear final drive
to prevent drift and minimizeBacklash
9. Bearing : Pan : Heavy duty ball bearingTilt : Oilite bronze bushing
10. Braking :Mechanical
11. Construction :Aluminum casting and plate withCorrosion protection for all internals
12. Internal usable area :100x100x280 mm13. Window :114 mm dia.12. Approvals : Explosion proof standard IECEX EX d
IICT6 & ATEX II 2GD EX d IIC T6standards (for explosion proof units:7Nos alone)
13. Environmental standard : Compliant with IIEC 529 dust proofWaterproof IP 66 international standard(for weather proof units: 5Nos alone)
Day/Night Digital Colour Cameras:Image sensor : 1/ 3 “super HAD CCD color image sensorDay /Night : Color, Mono, AutoDSP : 16 bit advanced DSPVideo standard : PALScanning system : 2:1 interlacePicture element : 752x 582 /625 lines, 50 HZDynamic range : 96 dBDynamic noise reduction : Auto, on/off selectableModes : 6 preset programmable modesSensitivity : 0.001 lux F1.2 AGC On @30IRE,
0 lux on IR illuminator, AGCResolution : > 700 TV lines horizontal,Scanning frequency : 15, 625, 50 HzVideo output : 1 V p-p 75 ohms
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
144 | P a g e 2 2 2
S/N ratio : >50 dB (AGC off, shutter off)White balance : ATW: 2500 –10000 KGain setting : Auto or 0/6/10/12/18/24/30 dBFlicker less : 1/50 sec to 1/10,000 sec or OFFSynchronization : Internal/line lock/Gen lock/HV-lockLens drive : Manual, Video IRIS & DC IRISVideo motion detection : One area, fully programmableControls : OSD with soft key operationCamera mount : C-mount type or CS mounts with C-mountadapterPrivacy masking : 4 independent area ,fully programmablePower : 24 V AC, 250 mAAccessories : C/CS mount conversion ring, 4 pin Lens
IRIS connectorTripod mount : bottom and top ¼ inch 20 UNCOperating temperature : -20 to 55 deg CHumidity : 20 to 93 % RHCertification & approvals : UL,FCC ,CE,CSA,EN55022 Class B ,
IEC600068-2-6,EN50130-4 ,EN 50121-4Safety : UL1950-1,CSA 22.2 no. 950-1,EN60950-1 ,
UL60950,CSA 60950
Motorized zoom /focus Lens with Auto DC IRIS:Lens Image format : 1/2 inchLens Mont type : C – MontLens focal length : 7.5 m-112.5mmZoom ratio : 15 xMaximum Aperture Ratio : 1: 1.6IRIS Range : F1.6 – 360Operation Method :
Focus : MotorizedZoom : MotorizedIRIS : Auto
Minimum Object Distance : 1.8mBack focal length : 11.0 mmFitter screw size : M62 mmAngle of field of view : wide TeleDiagonal 43 deg 2 degHorizontal 34 deg 1 degVertical 26 deg 1 degIRIS : DC IRISResponse time : 2 sec approx.Metering method : variable peak /average
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
145 | P a g e 2 2 2
Control voltage for Zoom : DC 6V –12 V max,Motor speed current : < /= 40 mA /motorFlange back length : 17.52 mm
35. Telemetry receiver with 17 functions.
General17 Functions : UP, Down, Left, Right, Auto, Washer, Wiper, Zoom Tele,
Zoom wide, Focus Near, Focus Far, IRIS open, IRISClose, Aux1, Aux2, Aux3, Aux4
Dip Switches : Selectable AddressInput : RS 232, RS 485, Current loopLens : Polarity Inversion Lens, Common wire lensLED : Power Supply
Active FunctionStorage option : EEPROM
16 bit micro controllerSelf Test
Lens Voltage : 3V to 12 VFunctions : PESET/ SCAN/ PATROLMemory : 40 PRESET functionsAlarm : 4
ElectricalPower Supply : 230 V, 50/60HzConsumption : 60 WMax. Switching Power : 100 WPower Supply to Positioning device: 230/ 24 V, 50Hz selectablePower Supply to the wiper : 230V, 50HzPower Supply to the washer :230V, 50HzPower Supply to the Camera : 230 V max 250mA (Cam ON)Power Supply to the lens : 3V to 12 V2 Dry contacts : 1 A 230V – 1A m24V (AUX3, AUX4)Fuses : F2 1 AF 250V, F5 2.5 AF 250VConsumption : 40 W
CommunicationsCommunication protocol : Videotec/ Molynx / PHELCO-DCommunication Speed : 38400/19200/9600/1200/300 BaudConfiguration : RS232, RS485Coaxial cable : RG 59 or DTCOAXTelemetry Data : D-type
RS485 on Matrix Series output max. Distance1200m
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
146 | P a g e 2 2 2
RS485 on Keyboard output max. Distance1200mRS232 on PC or Keyboard max. distance 15m
Environment : Indoor/OutdoorOperating temperature : 0 deg to 50 deg
36. 4 channel Fibre optic transmitter and receiver system for video, audioand data
Digital Audio Transmitter & Receivers (Bi-Directional) Electrical:
Number of audioChannels
4 Bi-directional
Nominal level 0 dBu (775 mv) nominal
Head Room 18dbInput Impedance 600Ω or 10KΩ
Output Impedance 200ΩFormat Balanced input and output
Signal to Noise Ratio >70db at nominal level
Total HarmonicDistortion
<0.05% at nominal level
Bandwidth (-3db) 10Hz to 20kHz
Indicator Red indicators for active transmit channels.
Green indicators for active receive channels.
Power supply 10-30 V DC
Optical:
Optical Wavelength 1310nm
Transmit Power > -15dBm in to single mode
Receiver Sensitivity < -39dBm
Receiver Saturation > -12dBm
Link status Indicator Green for healthy link, Red for sick link
Optical connectors ST connectors
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
147 | P a g e 2 2 2
Environmental:
Operating Temperature 0 to 55ºC
Relative Humidity 0 to 95% non-condensing
Digital video multiplexer:Channel availablity:
Number of Video channels 4 /8 one way
Electrical:
Input/Output Impedance 75Ω composite video
Input/output Level 1.0Vpp nominal
Bandwidth 5Hz to 10MHz +/-1dbWeighted Signal to NoiseRatio
>67db
Differential Gain <0.5%
Differential Phase <0.5˚Video connector BNC
Alarms Laser fail on TransmitterLow Received optical power on receiver
Alarm Connector Female 9 Pin D connectorPower supply 15-30 V DCOptical:
Transmitter Wavelength 1310nm
Transmitter Coupledpower
-7dBm
Receiver Sensitivity <-24dBm (PIN)
Receiver Saturation >0dBm (PIN)
Link Budget From 20dB to 39dB at 1310nm
Operating Distance Up to 10 km
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
148 | P a g e 2 2 2
Optical Connectors ST Standard
Optical Line Rate 1.35Gbps
Physical:
Operating Temperature 10 to 50ºC
Relative Humidity 0 to 95% non-condensing
37. Video Cross matrix switcher and Controller unit witha. Joystick control or keyboardsb. RS 485 data multiplexer unit.
General:No of Camera inputs : 16No of Monitor outputs : 4No of keyboards : 4 (max)On screen display with menu drivenDifferent Switching sequence for each monitor output videoText insertion for each outputDate & time managementRelay activation for each Alarm
Video:Video input impedance : 75 ohmsVideo bandwidth : > 6 MHzVideo level : 1 V p-p into 75 ohmsS/N : 50 dB @ 5.5 MHz
Electrical:Power supply : 230 V,50 HZ ACPower consumption : 15 WRelay contacts : 50 V, 0.3A
Communications:Protocol : Videotec & Pelco-DSpeed : 9600/2400/1200/300 baud
selectableTelemetry transmission : RS 485 for a max distance of
1200 metersKeyboard transmission : RS 485 for a max distance of
1200 meters
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
149 | P a g e 2 2 2
PC interface : RS232Connector:
Video : BNCRS-485 : RJ11Alarm : 25 pin D typeRS 232 : 9 pin D type
Mechanical:Cabinet Enclosure : MetalMount : 19” rack mountableHeight : 1 UOperating temperature : 0-45 deg C
Video matrix and Telemetry control keyboard
General feature:Joystick for Pan/tilt /Zoom control
LED display with adjustable contrastErgonomic keysMacro function keys 10 Max
Mechanical:ABS materialRubber keys3 axis proportional joystick with calibration and testDB9 connector for firmware update
Electrical:Power: 12 V DC, power adapter to be provided
Communications:No. of ports : 3 x RS 485 serial lineNo of ports for telemetry : 2 no’s.No of ports for Matrix & multiplexer : 1 no.No of RS232 ports : 1 no.
Compliance:CE : EN50081-1, EN50130-4, EN60950, EN55022 Class BFCC : part 15 class B
RS 485 DATA Multiplexer unitGeneral features :
No of input line : 1No of output lines : 8
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
150 | P a g e 2 2 2
Electrical:Power supply : 230, 50 HzPower consumption : 10 W (max)Protection : built in fuse
Communications:Telemetry transmission : RS 485 serial outputTransmission distance : 1200 metersControl : Telemetry receivers
Environment:Operating temperature : 0- 45 deg CHumidity : 10-90 % non condensing
Mechanical:
Mounting : Rack mountableCompliance:
CE : EN50081-1, EN50130-4, EN60065
37. VIDEO DISTRIBUTION AMPLIFIER
Nominal Video Level : 1V p-pInput / Output : four separate-one input, six outputcomposite videoLevel Range : 5 – 2 Volts p-pImpedance : 75 ohmBandwidth : 30MHz (Less than ±0.5dB)Differential Gain : 0.1Differential Phase : 0.1MTBF : 30,000 hoursConnectors : Female BNCCompatible with : NTSC, PAL or SECAMWeight : 4 – 5 Kg (Approx)Power Supply : 100 – 240V 50/60 Hz (Internal AutoSwitchable)Warranty : Two Years Parts & LabourInput & Output each use professional female BNC Connector for 75 ohmimpedance levelsMetal Enclosure and Rack MountableAccessories : BNC – RCA Adapter
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
151 | P a g e 2 2 2
38. HYBRID VIDEO RECORDER
Electrical
Power input 100 to 240 VAC; 50/60 HzPower consumption Max. 2.5 to 1.0 A (250 Watt)
835 BTU/hAble to withstand power dips up to 100MS,assuring continuous operation
VideoVideo standard PAL or NTSC auto-detectionResolution 704x576 PAL, 704x480 NTSCCompression H.264Inputs 8 or 16 composite video 0.5 to 2 Vpp, 75
ohmautomatic termination
Outputs 8 or 16 composite video 1 Vpp, 75 ohm,sync0.3 V ± 10%
AudioInputs 8 or 16 line in (DHR models only), mono
RCA,1 Vpp, 10 kohm
Output 2 line out, dual mono RCA, 1 Vpp, 10kohm
Compression MPEG-1 layer IISampling rate 24 kHz per channelMonitorsMON-A Live, playback, menus
VGA: analog RGB 1280x1024, 60/75 Hz(NTSC/PAL)CVBS: 1 Vpp, 75 ohm, BNCY/C
MON-B (Hybrid models only) LiveVGA: analog RGB 1024x768, 60/75 Hz(NTSC/PAL)CVBS: 1 Vpp, 75 ohm, BNCY/C
Display ModesMonitor A Full, full sequence, quad, multi-screen
(liveand playback), event call-up (live)
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
152 | P a g e 2 2 2
Monitor B(Hybrid models only) Full, full sequence, quad, multi-screen,eventcall-up (live)
Frame rate PAL/NTSC
25/30 IPS per channel (real time)
Multi-screen mode 8channels
1, 2x2, 3x3 (showing 8 channels)
Multi-screen mode16 channels
1, 2x2, 3x3, 4x4
Zoom 1.5x, 2x, 3x, 5xDisplay languages English, Chinese (Simplified), Czech,
Danish,Dutch, Finnish, French, German, Greek,Hungarian, Italian, Japanese, Norwegian,Polish, Portuguese, Russian, Spanish,Swedish, Turkish
Alarm HandlingInputs Screw terminal, 8 or 16 inputs,
configurableNO/NC,Max. input 40 VDC
Outputs Screw terminal 4 relay outputs,configurableNO/NC, max. rated 30 VAC, 40 VDC, 0.5A,continuous -10 VA
Remote notification Via Control Center softwareMalfunction relay Temperature related failures,
Voltage ratings, Disk failuresConnectionsEthernet 1 or 2 RJ45 modular jack, 8 pins shielded:
10/100/1000 Base-TBiphase Screw terminal connector (5 outputs)
Maximum 5 controllable cameras perBiphaseoutputImpedance 128 ohm, max. overvoltageprotection ±40 V, max. cable length 1.5km(0.9 miles)
PTZ control interface RS485Serial interface RS232 output signals according to EIA/
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
153 | P a g e 2 2 2
TIA-232 F, max. input voltage ±25 V2xDB-9 male connector
Intuikey keyboard(KBD Digital orKBD Universal)
Conforms to RS485, max. signal voltage±12 V, power supply to keyboard 11 to12.6 VDC at max. 400 mARJ11 modular jack 6 pins
USB Five USB 2.0 ports10/100/1000 Base-T network interfaces (max 2)
Connect with Bosch iSCSI Video StorageArrays
NetworkBandwidth control 0.1-100 Mbps limiterRemote users Maximum 7 simultaneously connected
Control Center usersProtocol support TCP/IP, DHCP, DNS, and SNTPIP cameras Up to 16 IP H.264 for DHR modelsSupported IP H.264devices
Dinion, FlexiDome, AutoDome Modular,EX series IP cameras, VIP X seriesencoders(running firmware 3.7 or later, andAutoDome Easy IP
StorageInternal HDD 2 TB per disk
Up to 4 hard disksRedundancy RAID-4 (4 hard disks plus optional
license required)ExportingDVD Built-in DVD+R/RW recorder (optional)USB Flash memory or external HDD (FAT32)Network Bosch Video Client or Control Center
SoftwareSecurityPassword protection Multi-levelImage authentication All recordings and archives in native file
formatRecord Frame RatePAL Up to 25 IPS per channel at 4CIF
IP Channels Up to 25/30 IPS per channel at 4CIF,720p60and 1080p30
RecordingOverwrite modes Continuous, overwrite after 1 to 99 days
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
154 | P a g e 2 2 2
Pre-alarm recording Up to 120 sPlaybackPlayback function Fast forward/reverse, frame
forward/reverse,freeze
Zoom 1.5x, 2x, 3x, 5xSearch mode Date/time, Event (motion, input), Text,
SmartSearch
[
39. & 40. Specification of LED TV display
FeaturesSmart energy savingMotion eco sensor2D to 3D source convert3D to 2 D source convert3D Depth & Image controlDual core CPUDLNA built inNetwork file browserInternal memory recordingExternal HDD recordingFull Web browser
Display
1. Display screen size : 42 & 32 Inches
2. Display type : Full HD 3D Smart LED LCD
3. Display design : Cinema screen design.
4. Display resolution : 1920 x 1080 Full HD
5. Back light module : Ultra slim LED
6. Pixel control : Micro lens array
7. Motion control index (Hz) : 800 (120 Hz)
Video8. Video system : PAL
9. Video processing : Triple Engine
10. Resolution upscale : Basic
11. Color enhancer : Dynamic
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
155 | P a g e 2 2 2
12. Aspect ratio : 16:9,just scan,original,4:3
13. Noise reduction : 3 D MPEG
Audio14. DTS decoder : Built In
15. Dolby Digital decoder : Built in
16. Speaker system : 2 way 3 speaker (2.1)
17. Audio output : > 20 watts
18. Sound optimization : Normal, Wall mount, Stand mount
19. Surround sound : Built in virtual surround plus
20. Sound sync : OpticalConnectivity
21. Wi-FI : Built in
22. Wi-Fi : Direct
23. Full Web Browser : Built in
24. DNLA : Built in
25. NFC tagging : Built in
26. USB : 3 no’s of USB 3.0/2.0
27. HDMI 1.4 : 4
28. RF In : 1
29. Video RCA composite : 1x RCA (F)
30. Component video : 3 x RCA(F)
31. Digital audio out : Optical
32. LAN connectivity : 1 RJ45
33. Head phone out : 3.5 mm stereo socket
Power34. Power supply : 100-240 V ac ,50-60 Hz
Accessories35. Mounting Kit : Wall mounting
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
156 | P a g e 2 2 2
41. SPECIFICATION OF ARMOURED RG-12 CO - AXIAL CABLE
Cable type : Video RG 12 /UInner conductor Gauge : 14 solid 0.064 inches BARE copperInner conductor DC Resistance : 2.5 Ohms/ mInsulation and Nominal core Dia. : polyethylene , 7.11mmNominal O.D of cable : 12 mmNumber of Shielded Material : Single bare copper 96% shield coverage,1.4 Ohms/mNominal Impedance : 75 OhmsNominal Velocity of Propagation : 78 %Nominal capacitance : 56 PF/mtNominal Attenuation at 200 MHz : 7 dB/100 mtNominal Outer PVC color : Grey or BlackMaximum Operating Voltage RMS : 300 VArmour : GI wires
42. Surge Protectors Device (SPD) for CCTV system
Surge Protectors Device (SPD)video lines
Input impedance : 75 OhmsInput bandwidth : 65 MHzInput connector : BNC-femaleOutput connector : BNC -femaleLimiting voltage : 27 VoltsWorking voltage : 7.5 volts maximumMaximum discharge current : 10 KA peak current (8/20 µsec wave form)Series resistance : 1 ohm (Inner and shield path)Insertion loss(dc) : <0.2 dBCrosstalk : < -60 dB @ 5 MHzAccessories : Mounting Kit for up to 5 devicesSurge Protector Device (SPD) for power line for 230 V AC line
Working voltage : 230 Volts AC, 50 HzMaximum continuousOperating voltage : 25 % above nominal voltage
Limiting voltage : < 800 VoltsMaximum continuousOperating current : 15 Amp
Nominal discharge current : 18 kA peak current (8/20 µsec waveform)Maximum attenuation : 55 dBMaximum leakage current : < 0.3 mA at working voltageLines protected : L,N,EMounting type : Din rail mountableTerminal : 2.5 Sqmm
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
157 | P a g e 2 2 2
Compliance : IEC 61000-4-5, level 4.Surge Protector Device (SPD) for Ethernet twisted pair linesInput connector : RJ45Output connector : RJ45Input signal type : Ethernet twisted pair 100 Base TNo. of Input wires : 8 wireMaximum bandwidth : >155 MHzInsertion loss : 0.1 dB @144 KhzLimiting voltage : 12 Volts (10/350 kA)Working voltage : 6 Volts DCMaximum discharge current : 5 kA peak current (8/20 µsec waveform)Mounting : Plug in typeEMC compliance : BS EN 61000-6-2:1999,BS EN60950:1992Surge Protectors Device (SPD) for power line to video camerasWorking voltage : 24 Volts AC,50 HzMaximum continuousOperating voltage : 34 Volts AC,50 Hz
Limiting voltage : < 800 VoltsMaximum continuousOperating current : 20 Amp
Nominal discharge current : 0.7 kA peak current (8/20 µsec waveform)Maximum attenuation : 70 dBImpulse energy absorption : 420 JoulesFuse rating : 10 AmpMaximum leakage current : < 0.3 mA at working voltageMounting type : Din rail mountableTerminal : 2.5 SqmmCompliance : IEC 61000-4-5, level 4.Surge Protector Device (SPD) for RS485 lineInput connector : Terminal screwOutput connector : Terminal screwInput signal type : RS 485Input wires : 2 wireMaximum bandwidth : 50 MHzLimiting voltage : 10 Volts (6kV/ 3kA)Working voltage : 5 Volts DCMaximum discharge current : 10 kA peak current (8/20 µsec waveform)Mounting : DIN railEMC compliance : BS EN 61000-6-2:1999,BS EN
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
158 | P a g e 2 2 2
43. Specification of 24V AC Transformer
1. Primary rating : 230 V AC, 1 Amp2. Secondary rating : 24 V AC, 6 Amp3. Efficiency : > 80 %4. Load regulation : 10 %5. Line regulation : 10 %6. Temperature raise while in : 10 degree C (max)
Operation7. Core type & insulation : Laminated & paper insulated8. Coil : Electrolytic Annealed copper9. Enclosure : The transformer should be enclosed in a
Metallic case.10. Terminals : Terminated on a terminal block outside the
Case with clear marking for primary &Secondary and screws for making theConnection 60950:1992
Inter Communication system:
44. Flame proof intercom station and page horn speaker for hazadrousenvironment (group IIB)
Flame Proof Intercom For Group II B (16 channel)
1.HAND SETa) Microphone Type : Dynamic, Noise canceling
Sensitivity : 1.5 mv @1 kHzImpedance at, 1KHz : 300 Ohms +/- 20%
b) Receiver Type : DynamicSensitivity : 24 +/- 4 dBImpedance at 1KHz : 300 Ohms +/- 20%Sound pressure level : 116 dB/v
2. LINE DRIVE AMPLIFIER SECTIONInput sensitivity : 1.5mV at 1 KHzInput impedance : 200 Ohms.Load impedance : 8 ohmsOutput power : 1 watt (Balanced)Output impedance : 600 ohms balancedT.H.D : < 1% @ 1KHzResidual Noise Level : - 60 dB.Frequency Response : 100 Hz to 10KHz +/- 3 dB
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
159 | P a g e 2 2 2
Protection : short circuit, open circuitreverse polarity
3. POWER AMPLIFIER SECTIONInput Impedance : 10 kilo ohmsOutput Power : 10 W. R.M.S 16 Ohms Load
Or 100 V lineFrequency Response : 100 Hz to 10 KHz +/- 3 dBT.H.D : < 1% at KHzResidual Noise Level : - 60 dBProtection : short circuit, reverse polarity
4. AUTOMATIC GAIN CONTROLInput Sensitivity : 350 mV P-P@ 1KHZInput Impedance : 10 K OHM Balanced.Output impedance : 600 ohms balancedT.H.D : Less than 1%Residual Noise : -60 dB.
5.MECHANICAL SPECIFICATIONSa) Enclosure Type : Flame Proof Groups :II C
As per is : 2148/1981b) Weather Proof : IP 67 As per I.S.2147 /1962c) Material : Cast Aluminum Alloy, LM 6.d) Finish : Light Grey Epoxy Power Coated Shad
No.631 of I.S:5e) Cable Entries : 3 Nos. 19 mm Entryf) Gasket : Endless Neoprene 'o' Ring Type
6. Power : 220±10% V AC, 50Hz7. Display : 2 line LCD display with key pad8. Cross talk
Page & Private : 100 dbAdjacent channel : 100 db
B.Flame Proof Page Horn Speaker With DriverInput Power Handling Capacity: 15 W RMSImpedance : 16 ohms or 110 V lineS.P.L. at 1 KHz : 108 dB at 1 W / 1 MeterFrequency Response : 100 to 12,000 HzMaterial : Aluminum, LM6Application : Flame Proof Groups I,
EExd II C T 5 AS PER I.S.2148/1981
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
160 | P a g e 2 2 2
Weatherproof Intercom Station and Page Horn Speaker1. HAND SETa) Microphone Type : Dynamic, Noise canceling
Sensitivity : 1.5 mv @1 kHzImpedance at, 1KHz : 300 Ohms +/- 20%
b) Receiver Type : DynamicSensitivity : 24 +/- 4 dBImpedance at 1KHz : 300 Ohms +/- 20%Sound pressure level : 116 dB/v
2. LINE DRIVE AMPLIFIER SECTIONInput sensitivity : 1.5mV at 1 KHzInput impedance : 200 Ohms.Load impedance : 8 ohmsOutput power : 1 watt (Balanced)Output impedance : 600 ohms balancedT.H.D : < 1% @ 1 KHzResidual Noise Level : - 60 dB.Frequency Response : 275 Hz to 10 KHz +/- 3 dBProtection : short circuit, open circuit reverse
polarity3. POWER AMPLIFIER SECTION
Input Impedance : 10 kilo ohmsOutput Power : 10 W. R.M.S 16 Ohms Load
Or 100 V lineFrequency Response : 100 Hz to 10 KHz +/- 3 dBT.H.D : < 1% at KHzResidual Noise Level : - 60 dBProtection : short circuit, reverse polarity
4. AUTOMATIC GAIN CONTROLInput Sensitivity : 350 mV P-P@ 1KHZInput Impedance : 10 K OHM Balanced.Output impedance : 600 ohms balancedT.H.D : Less than 1%Residual Noise : -60 dB.
5. Private channels : 15Page channel : 1
6. MECHANICAL SPECIFICATIONSa) Weather Proof : IP 67 as per I.S.2147 /1962b) Material : Cast Aluminum Alloy, LM 6.c) Finish : Light Grey Epoxy Power Coated
Shad No.631 of I.S:5d) Cable Entries : 3 Nos. 19 mm Entry
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
161 | P a g e 2 2 2
e) Gasket : Endless Neoprene 'o' Ring Type
7. Power : 220±10% V AC, 50Hz
8. Display : 2 line LCD display with key pad9. Cross talk
page & private : 100 dbAdjacent channel : 100 db
OUTDOOR PAGE HORN SPEAKER WITH DRIVER
Input Power Handling Capacity : 15 W RMSImpedance : 16 ohms or 110 V lineS.P.L. at 1 KHz : 108 dB at 1 W / 1 MeterFrequency Response : 100 to 10,000 HzMaterial : Aluminum, LM6
46. RACK MOUNT INTERCOM STATIONFUNCTIONS & FEATURES
1. 8 private and 1 page channel2. Input Facility to connect Hand Held Microphone for paging.3. Facility to connect 2Nos of Headset with Microphone simultaneously.4. Page mode select switch.5. Automatic gain control circuitry for page and private channels.6. Volume level control for external page amplifier.7. Volume level control for monitor amplifier.8. Built-in speaker to receive page and private9. Power ON/OFF.10. Recording output.11. Transmission through voice activated switch (VOX) built in
1. PRE AMPLIFIER AND LINE DRIVER AMPLIFIERInput Sensitivity control : 1.5 mV RMS @ 1KHz @ (Adjustable with
volume control)Output : 4 V RMS at 600 ohms resistive loadFrequency response : 100Hz to 10KHz + or -3 dB.T.H.D : Less than 1%Residual noise : -50 dB.
2. MONITOR AMPLIFIER (RECEIVE)Input sensitivity : 350 mV R.M.S @ 1KHz.Output : 4.0 VR.M.S @ 8 ohms Resistive Load.Output Power : 2 W R.M.S @ 8 ohms Resistive Load.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
162 | P a g e 2 2 2
Frequency Response : 100Hz to 12 KHz ±3 dB.T.H.D : Less than 1%Residual Noise :-50 dB.
3. EXTERNAL PAGE AMPLIFIER (RECEIVE).Input Sensitivity :4 v R.M.S @ 1 KHz.Output : 12 V R.M.S @ 16 ohms Resistive Load.
100 V into LMTOutput power : 10 Watts RMSFrequency Response : 100Hz to 10 KHz ± 3dB.T.H.D : Less than 1%Residual Noise : -60 dB.
4. AUTOMATIC GAIN CONTROL UNITInput Sensitivity : 350 mV to 4V P-P@ 1KHZInput Impedance : 10 K OHM Balanced.Output impedance : 600 ohms balancedConstant Output : 4V. (Adjustable with
internal threshold level preset)T.H.D : Less than 1%Residual Noise : -60 dB.
5. Built in Page & Private SpeakersOutput power : 2 Watts with level adjustmentImpedance : 8 ohmsSPL @ 1 KHz : 98 dbFrequency Response : 100 to 10,000 Hz
6. POWER : 230V AC, 50Hz with Fuse @ Rear andFront ON/OFF Switch
7. Display : 2 line LCD display8. Cross talk
Page & private : 100 dbAdjacent channel : 100 db
9. MECHANICAL :Dimension : 19' standard rack mounting type.
Height 2 UDepth 260 mm
47. Surge Protector Device (SPD) for wireless base station
Input connector : UHF –female/BNC – female orBNC Male /female
Output connector : BNC-femaleInput impedance : 50 OhmsInput bandwidth : 1000 MHzMaximum Transmit power : 45 WattsLimiting voltage : 600 Volts (6kV/ 3kA)
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
163 | P a g e 2 2 2
Working voltage : 90 voltsMaximum discharge current : 10 kA peak current (8/20 µsec waveform)Capacitance : < 1 pF (inner and shield path)Insertion loss : <0.1 dBVSWR : 1Accessories : Mounting Kit for 1 device
48. Specification for Handheld Wireless Transceiver
136 – 174MHz Frequency Range128 Programmable channels with channel-wise25 KHz programmable channel spacing1 W/5W RF PowerAuto ScanTransmission TimerSquelch settingBusy Channel lockoutSignalling systemLCD display (14 Character Alpha numeric display)Channel No. /aliasChannel Identity /aliasAddress Identity MessagesReceived signal Strength indication24 Hour ClockBattery LevelOther flags & iconsEmergency SirenCall alerts with Escalate TM. Tone tagging featuresX-PAND TM Digital audio ProcessingLong Range Digital Signalling with Error correction for transmittingand receiving selective individual /group callsTransmit and receive PTT identityInitiate and respond to Remote Radio check search16 Scan list with Dual Watch priority channelProgrammable function buttons for Monitor on/offRepeater / Talk aroundSquelch tight / normal
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
164 | P a g e 2 2 2
Should meet MIL STD 810 C, D, ERadio model Package includes:1450 mAH (Average capacity)(Rechargeable Batteries)
49. Specification for Wireless Base station
136 – 174MHz Frequency Range128 Programmable channels with channel-wise25 KHz programmable channel spacingDefinable low/high 25W RF PowerAuto ScanTransmission TimerSquelch settingBusy Channel lockoutSignalling systemExternal accessory port with programmable I/O for voice/data PTTinputsSOS/radio kill/channel select/preset call/scrambler on/off inputsCall alerts/External alarm outputsTx & Rx audio input/outputsRepetitive EMERGENCY/SOS signal transmission with queuingfacility acknowledgementFlexible signalling system allows radio user to
Transmit & Receive display PTT-ID Initiate one touch calls Initiate & receive selective individuals /group calls Initiate & Receive Emergency/ priority call Initiate and respond to remote to remote radio check
LCD display for Channel No. / named alias Caller Identity Other flags and icons
2 X 16 Channel scan lists with dual priority channel and normal/trunking scanProgrammable function buttons for monitor on/offOne touch call/multi call/memory channels /call forwardScan on/off
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
165 | P a g e 2 2 2
Repeater / talk aroundFront facing 4 watt internal speakerEMI/EMC Compatible (should meet MIL STD)
Radio model Package includes Operator handbook Compact microphone cable & hang up clips Non locking mounting bracket
TIMING SYSTEM50. Specification of GPS based network time server
GPS receiver:Band : L1 1575.42 MHzCode : C/ANo of channels : 8 channelTime base : TCXOTime to lock : < 5 minutesStratum level : level 1Antenna:Impedance : 50 OHMConnector : TNC jack on rear panelLNA & filter : Integrated +35 dB LNA and band pass filter for out ofbound
Interface rejectionENVIRONMENT : Rugged all weather housing capable ofoperation over -40 to +85 CCable length : 100 feet
Accuracy:GPS receiver : < 30 nanoseconds to GPS (< 100 ns to UTC)when
lockedHold over accuracy : 10 millisecond /dayNTP time stamping : < 10 microseconds while supporting 2,00,000 clients(typical)NTP client LAN Sync : 2 millisecond (typical)
Supported protocols: -SNTP, NTP v2, v3, v4, MD5 authentication andBroadcast/multicast mode and auto key.
- SSH server with secure copy utility, SCP.- SNMP v1, V2c, V3 with enterprise MIB.- HTTPS (web interface)- Time & Daytime server- TELNET client/server
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
166 | P a g e 2 2 2
- FTP & DHCP clients- IPv4 & IPv4/IPv6 hybrid- SYSLOG- PTP/IEEE-1588 (optional)
Software : Free NTP Client software
Network I/O:Rear panel : RJ-45 jackSpeed : 10/100 Base-T Ethernet
Serial port I/O : RS -232 on 9 pin jack on rear panelSystem status : Sync LED; Network LED; Alarm LED
Alphanumeric Display /keypads:Display : 16 x 280 dot matrixKeypad : Enter, Back, Edit, Left, Up, Down, Help
OutputsNTP time : 10/100 Base-T EthernetTime code output : 1 Vrms into 50 Ohms, 1 KHZ carrierFormat : User selectable format: IRIG-B120, IRIG-B12 andIRIG-B1231PPS output : TTL pulsePulse width : Selectable 20 microseconds, 1 milisec, 100 milisec, 500milisecAccuracy : < 30 nanoseconds to GPS (< 100 ns to UTC) whenlockedStability : TDEV < 20 nanosecond,
Firmware Upgrades : Field upgradable at free of charge
Power : 90-264 VAC, 47-63 Hz
Mechanical : 19 “rack mountable
Environmental:Temperature operating : 0 to 50 Deg C,Humidity : 0-95 %, non-condensingCompliance : CE, FCC
51. Network time displays
Display size : 4 inchesNumber of Display digits : 6NETWORK PROTOCOLS : NTP, SNTP, DHCP, TCP/IP, UDP
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
167 | P a g e 2 2 2
MODULE CONNECTION : 10/100 Base-T EthernetNetwork connector : RJ-45Synchronization input : NTPControl : Telnet for IP configuration, 12/24
hour format, statusReporting, SNTP server address,Daylightsavings time
Mount : Wall mountablePower : 90-264 VAC, 47-63 HzEnvironmental:Temperature operating : 0 to 50 Deg C,Humidity : 0-95 %, non-condensingCompliance : CE, FCC
52. 24core Fiber Optic Armoured cable
Fiber optic design : Glass fiber in multi tube loosefibers with jelly fill
Fiber type & size : Single mode, 9/125 micronsAttenuation @1310 nm : 0.4 dB/Km Max.Number of tubes : 6Number of fibers per tube : 4Loose tube material: PBTBLoose tube inner diameter : 2.0 mmLoose tube outer diameter : 3.0 mmArmouring : Corrugated steel tapeStrength member material : Steel wireNumber of strength material : 1Diameter of strength member : 2 mmMinimum bending radius : 220 mmOuter jacket material : Polyvinyl chlorideOuter jacket diameter/thickness : 12 mm/2 mmTensile strength : 4000 Newton’sCrush resistance : 4000 N/mm
53. specification of RG-59 /u co - axial cable
Cable type : Video RG 59/U
Inner conductor Gauge : 20 solid BARE copper
Inner conductor DC Resistance : 47 Ohms/ m
Insulation and Nominal core Dia : Polyethylene, 3.7mm
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
168 | P a g e 2 2 2
Nominal O.D of cable : 6.15 mm
Number of Shielded Material : Single bare copper braid 95% Shield
coverage 2.6 Ohms/m
Nominal Impedance : 75 Ohms
Nominal Velocity of Propagation : 78 %
Nominal capacitance : 56 PF /mt
Nominal Attenuation at 200 MHz : 15 dB /100 mt
Nominal Outer PVC colour : Grey or Black
Maximum Operating Voltage RMS : 300 V
54. Ethernet cable
CAT6 CLASS-E UTP cable (Roll of 305m)Frequency Range : 250 MHzAttenuation : 36 dB at 250 MHzNEXT : 33.1 dBPower sum NEXT : 30.2 dBACR : 2.9 dBPower sum ACR : 5.8 dBELFEXT : 15.3 dBPower Sum ELFEXT : 12.3 dBReturn Loss : 8 dBPropagation delay : 546 n SecDelay Slow : 50 n SecStandards : EIA/TIA 568 A
55. 3 core Armoured power cable
Core : 3 Core,Conductor : Multi strand copper
InsulationArmouring
: PVC Insulated PVC Overall FR sheathed: GI wires
Voltage grade : 1.1KVSize : 4 Sq mm
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
169 | P a g e 2 2 2
: IS-1554-I, IS-8130, IS-5831, IS-10810,IS-3961-II, IS-9938, IS-10418, IS-10462, iEC-754-I,ASTMD 2843, ASTMD 2863, IEC-332-I, SS 424 1475C1.F3 With IS certified and marking
Color coding : RYB
56. Network switchLayer 2with 1 G fiber uplink ports
Interface Port speed:
10/100TX : RJ-45
100FX : SFP support
10/100/1000T : RJ-45
1000SX, 1000LX : SFP slot
Console RS232 : RJ-45 connector
Performance
System System capacity : 128MB RAM, 16MB flash memory,
Up to 4,096 VLAN ID, 8000 MAC address, Packet buffer
memory 3Mbit
Throughput : up to50.6Mpps
Switching Capacity : 68 Gbps or higher
Switch fabric speed : 88Gbps or higher
Auto-negotiation, duplex, MDI/MDI-X
Physical & Environmental
Power input: 100 to 240 VAC, 50 to 60 Hz Internal Universal Power
Supply
Dimensions: 19” Rack Mount (Mount Hardware included ), Width: 1U
Height
EMI/EMC : FCC Class A, CE, C-Tick, VCCI Class A
Safety : UL, CE
Software FunctionsInterface Standards
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
170 | P a g e 2 2 2
IEEE 802.3 10T and 10FLIEEE 802.3u 100TXIEEE 802.3z 1000SXIEEE 802.3ab 1000TGeneral StandardsIEEE 802.1D BridgingIEEE 802.3x Backpressure/flow control
Multicast StandardsRFC 1112 IGMP snooping (ver. 1)RFC 2236 IGMP snooping (ver. 2)RFC 3376 IGMP snooping (ver. 3)RFC 3376 IGMP querierSupport for 256 multicastsUnregistered multicasts are dropped by defaultVLANIEEE 802.1Q VLAN taggingUp to 256 active VLANsPort-based VLANsMAC-based VLANsPrivate VLANsGARP VLAN Registration Protocol (GVRP)QoS (Quality of Service)IEEE 802.1p compliant Class of ServiceTraffic prioritization using IEEE 802.1p, ToS, DSCP fieldsMap IEEE 802.1p priorities to CoS queues to prioritize traffic at egressStrict scheduling and weighted round robinSecurityManagement security: username andPassword protectionSSHv2 for Telnet managementSSLv3 for Web managementRFC 1492 TACACS+RFC 2618 RADIUS authenticationIEEE 802.1x Dynamic VLANIEEE 802.1x RADIUS accountingIEEE 802.1x Multi-session modeIEEE 802.1x Action on violationIEEE 802.1x Single-host violationIEEE 802.1x Guest VLAN timeoutIEEE 802.1x Authentication not-requiredSecurity login bannerRFC 2865 IEEE 802.1x port-based
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
171 | P a g e 2 2 2
Network access controlMAC-based network access controlGuest VLANsACL – Access Control ListsManagement and MonitoringWEB, CLI, Telnet, SSH, serial console portRFC 1157 SNMPv1/v2cRFC 2570 SNMPv3RFC 1213 MIB-IIRFC 1573 Evolution of MIB-IIRFC 1215 TRAP MIBRFC 1493 Bridge MIBRFC 2863 Interfaces group MIBRFC 1643 Ethernet like MIBRFC 1757 RMON 4 groups:Stats, History, Alarms, EventsRFC 2674 IEEE 802.1Q MIBRFC 1866 HTMLRFC 2068 HTTPRFC 854 Telnet
57. Specification of Explosion proof Audio Visual Hooter
Electrical Data:
No of alarm tones : 4 tones selectable through switch settingOperating Voltage : 24 V DCMaximum current : 500 mA at 24 VSound Output : 112 dB (maximum) variable through preset
POTLamp type : LED clusterLED color : REDLED Cluster power : 1 Watt (24 V)Type of protection Flame Proof : Exd T6Gas group : GROUP IIBArea Classification : Zone 1 & 2Apparatus Standard : IS - 2148Approvals : CMRI Certified & CCE approvalEncapsulation : The electronics to be intrinsically safe
in a flame proof chamber.Mechanical Data:Material : Cast Aluminum LM 6IP Protection : IP 65 to IS 13947 / 93
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
172 | P a g e 2 2 2
Finish : Anti corrosive Epoxy - PowderCoated Red(RAL -3000)
Cable Entry : 2x½” NPTGasket : NeopreneHardware : Stainless SteelTerminals : Integrated chamber 4 x 2.5 sq. Mm(standard)
58. 48 core Fiber Optic Splicing Patch panel
Features:
Wall mounting
Compact and adequate space for fiber organizing
Provision for cable clamping and strain relief
Management for excess length of pigtail
Loaded with duplex couplers
Removable hinged door with lock & key arrangement
Powder coated
IP 65 category
Specifications
Material : Mild steelThickness : 1.6mmFinish : 50 Micron powder coatingSlack Management : up to 5 metersNo. of trays : 4No. of fibers : 12 per tray 4 No’s
Cable glands : 4 nos.
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
173 | P a g e 2 2 2
ANNEXURE-5
FREE ISSUE MATERIALS
The free issue materials supplied by Department are
1. Control System & its support for commissioning activities.2. Heavy duty connectors3. Switch mode power supplies4. Contactor5. Safety sensors for all facilities (Oxygen, Hydro carbon & UV/IR Flame
detectors)6. Temperature Probes7. Flow switches (4Nos) for ISF SF8. Terminal block ( Single deck & for use in 230V AC power wiring)
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
174 | P a g e 2 2 2
ANNEXURE-6
SAMPLE T&E SHEET
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
175 | P a g e 2 2 2
SECTION/DIVISION NAMEMEASUREMENT CHAIN TEST REPORT
Type ParameterLocation Legend
TRANSMITTER DETAILSTransmitter Make ConstantsTransmitter Model No A0Serial No A1Measurement Range Calibration Range
Calibration DateCALIBRATION EQUIPMENT
Calibration EquipmentFIELD WIRING DETAILS
JB No JB incoming cable tagJB outgoing cable tag
JB incoming ferrule tag JB outgoing ferrule tagINSTRUMENTATION RACK WIRING DETAILS
Rack tagField connector tag CS connectorTIB make TIB model noTIB ch.no TIB serial noTIB input pin details TIB output pin details
CONTROL SYSTEM WIRING DETAILSCS type Gain
OffsetIncoming connector no Connector pin noCS card/Slot no/Sl no
MEASUREMENT CHAIN CHECKINGInsulation resistance check
ELECTRICAL CHAIN CHECKINGSimulator Input Obtained Value Expected Value Error
mA (bar) (bar) % FSO48
10141620
Theoretically Estimated measurement chainaccuracy
Electrical chain accuracy
Chain Calibration Date
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
176 | P a g e 2 2 2
SECTION/DIVISION NAME
EP VALVE COMMAND CHAIN TEST REPORTTAGLOCATIONDESCRIPTIONVALVE DETAILS SOLENOID VALVE DETAILSMAKE SOV MAKEMODEL NO. MODEL NO.VALVE SIZE SL.NO.SUPPLY PRESSURE (bar)JB & CUBICLE DETAILS JB & CUBICLE DETAILSSOV CUBICLE & JB NO. SOV JB END FERRULEMARSHALLING JB NO. MARSHALLING JB FERRULESTATUS JB NO. STATUS JB FERRULERELAY DETAILS RELAY WIRING DETAILSMAKE RACK NO.MODEL NO. RELAY NO.SL.NO. FIELD END TB NO.STATUS TIB DETAILS STATUS TIB WIRING DETAILSMAKE & MODEL NO. RACK NO.SL.NO. TIB NO.PLC IO DETAILS PLC IO DETAILSIO CARD NO. SLOTSTATION CHANNEL
TEST DETAILSCOMMAND ISSUE OFF STATUSCMD ACK COIL RESISTANCE ()ON STATUS COIL VOLTAGE (DC VOLT)INSULATION RESISTANCE INSULATION RESISTANCESOV COIL RACK - STATUS JB CABLERACK - MJB CABLE STATUS JB - PROXIMITY SWITCH
CABLEMJB - SOV CABLEMIMIC DISPLAY VERIFICATION RESPONSE TIME (sec)COMMAND ISSUE ON TIMECMD ACK &STATUS OFF TIMESEALING & EARTHING CHECK OF FIELD OBSERVATIONSSOV CUBICLE SOV BACK EMF DIODE CHECKMARSHALLING & STATUS JBCHAIN CALIBRATED ON:TESTED BY VERIFIED BY CLEARED BY
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
177 | P a g e 2 2 2
SECTION/DIVISION NAMESECTION/DIVISION NAMECONTROL VAVE COMMAND CHAIN TEST REPORT
TYPE
TAG NO.PROCESS PARAMETERDESCRIPTIONVALVE DETAILSMAKE MODEL NO. SERIAL NO.FIELD JB NO.: CMD PIN NO. FB PIN NO.POSITIONER DETAILSMAKE MODEL NO. SERIAL NO.POSITIONER SETTINGSGAIN CL INT TIME CL SET TIME CLGAIN OP IN TIME OP SET TIME OPCONTROL GAPTIB DETAILS MAKE MODEL NO. FIELD TB NO. SL.NO.COMMANDFEEDBACK
PLC IO CARD DETAILS SLOT
STATION
SLOT
CHANNEL
COMMANDPOSITION FEEDBACK (M)TEST DETAILSCONTROLLERCONSTANTS
KP
TIME
KI KDINSULATIONRESISTANCE(G)
COMMANDLOOP
FEEDBACKLOOPRACK - FJB CABLE
FJB - CONTROL VALVECABLEOPENING COMMAND (%) CURRENT TO
POSITIONER(mA)
PHYSICAL OPENING(%)
CURRENT FROMPOSITIONER (mA)
POSITION
FEEDBACK(%)
MIMIC DISPLAY
VERIFIED
O.K
RESPONSE TIME (sec)ON TIME (0-100%)OFF TIME (100-0%)FIELD OBSERVATIONSSEALING CHECK OFFIELD JBEARTHING CHECK OFFIELD JBT& E DATE
TESTED BY VERIFIED BY CLEARED BY
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
178 | P a g e 2 2 2
ANNEXURE -7
PROCESS & INSTRUMENTATION DIAGRAMS
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
179 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation System for BSFAnnexure A: Scope of work and services
180 | P a g e 2 2 2
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
181 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
A. MATERIAL SUPPLY For materialsupply,
specificationsin Annexure4 & Chapter
3.2. ofAnnexure A
shall bereferred. Also
terms andcondition inannexure C
shall bereferred.
1 Pressure Transmitters withmanifolds (Absolute &Differential)
70 Nos Detailed catalogue and theselected model matrix forpressure transmitter andmanifold. The dimensionaldrawing for manifold shall alsobe provided.
2 Guided Wave level sensor 10 Nos Detailed catalogue and theselected model matrix.
3 Temperature transmitter 18 Nos Detailed catalogue and theselected model matrix.
4 Flow meters 3 Nos Detailed catalogue, sizingsheet, Dimensional drawing,accuracy calculations and theselected model matrix.
5 HART communicatorsuitable forcommunicating with allquoted pressure,temperature, Guided Wavelevel & flow transmitters
1 No Detailed catalogue
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
182 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
6 Flow switch 2 Nos Detailed catalogue,Dimensional drawing and theselected model matrix.
7 Pressure switch 11 Nos Detailed catalogue,Dimensional drawing and theselected model matrix.
8 Solenoid Valve 75 Nos Detailed catalogue,Dimensional drawing and theselected model matrix.
9 SOV cubicle 15 Nos Detailed catalogue andDimensional drawing showingthe pneumatic tubing entry,inside header and cable entryprovisions
10 Junction boxesType I : 600x400x225 10 NosType II : 300x300x165 4 Nos
11 Compression fittings & SStubes
Detailed catalogue
12.7mm SS tube; Wallthickness:2.2mm
600 m
12.7mm SS tube; Wallthickness:7.47mm
100 m
8mm SS tube 1500 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
183 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
Ferrule Fittings 1/2"NPTM to 12.7mm SS tubeOperating pressure :400bar
150 Nos
Ferrule Fittings 1/2" NPTFto 12.7mm SS tubeOperating pressure :400bar
100 Nos
12.7mm SS tube unionOperating pressure :400bar
120 Nos
12.7mm SS tube TeeOperating pressure :400bar
60 Nos
Ferrule Fittings 1/2"NPTM to 12.7mm SS tubeOperating pressure :650bar
50 Nos
Ferrule Fittings 1/2" NPTFto 12.7mm SS tubeOperating pressure :650bar
50 Nos
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
184 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
12.7mm SS tube unionOperating pressure :650bar
15 Nos
12.7mm SS tube TeeOperating pressure :650bar
10 Nos
1/4" NPTM to 8mm SStube; Operating pressure :400bar
150 Nos
1/4" NPTF to 8mm SStube; Operating pressure :400bar
150 Nos
8mm SS tube union;Operating pressure :400bar
125 Nos
8mm SS tube Tee;Operating pressure :400bar
75 Nos
Bulk head union for 8mmtube; Operating pressure :400bar
25 Nos
½” NPT SS Plug; 100 Nos
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
185 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
Operating pressure :400bar¼” NPT SS Plug;Operating pressure :400bar
100 Nos
12 PVC cables Detailed catalogue2 core 20 AWG armouredcable
4500 m
4 core 20 AWG armouredcable
4000 m
10 core 18AWG armouredcable
1500 m
64 Core 20 AWG unarmoured Cable
2500 m
96 Core 18 AWG unarmoured Cable
800 m
96 Core 20 AWG unarmoured Cable
2500 m
13 Cable trays Detailed cataloguePerforated Cable Trays-width: 50mm; Height:12mm; Thickness: 1.6mm
700 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
186 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
Perforated Cable Trays-width: 100mm; Height:25mm; Thickness: 2.0 mm
2500 m
Perforated Cable Trays-width: 150mm; Height:25mm; Thickness: 2.0 mm
1500 m
Perforated Cable Trays-width: 300mm; Height:50mm; Thickness: 2.0 mm
300 m
Ladder Cable Trays-width: 300mm; Height:75mm; Thickness: 2.0 mm
1000 m
13.a.Cable tray accessories 1 lot Details of accessories quoted
and unit cost for each shall bementioned.
14 Structural materials 10000 kg15 Canopy 10 sq m16 Racks 10 Nos Detailed catalogue and
dimensional drawing.16.a. Rack accessories 1 lot List of accessories are
mentioned along with
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
187 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
specification and unit cost foreach shall be mentioned.
17 Console & Control roomTables
16 segments * 2D view of consoles & dataprocessing tables indicating thedimensions* Cabinet interiorlayouts* 3D equipment layoutview of control rooms [Room-1& Room-2] with consoles &data processing tables inposition.* The catalogue andspecifications of light fittings,lamps and materials. *Photographs of similarinstallations madeThe abovedrawings shall be colorprintout by considering sitemeasurements, architectural,mechanical and electricalelements for each console type.
18 Transformer IsolatedBarriers (TIB)
Detailed catalogue
TIB for transmitters. 216 NosTIB for status 112 Nos
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
188 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
TIB for Control valvecommand
8 Nos
19 Relays 100 Nos Detailed catalogue20 Linear power supply :
24V±20A-Linear6 Nos Detailed catalogue
21 PTFE cables Detailed catalogue96 Core 20AWG Cable 500 m64 Core 20AWG Cable 100 m32 Core 20AWG Cable 100 m20AWG Single core wire 12000 m18AWG Single core wire 2000 m
22 Power cable 1000 m23 Earth cable 500 m24 Terminal block Detailed catalogue
Terminal Blocks- No. oflevels:2 ; No of terminals:4with diode in series
50 Nos
Terminal Blocks- No. oflevels:2 ; No of terminals:4with diode in parallel
50 Nos
25 Cable glands Detailed catalogue
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
189 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
Nickel coated Brass TypeCable Gland - 46mm 50 NosCable Gland - 32mm 50 NosPolyimide TypeCable Gland - 46mm 50 NosCable Gland - 32mm 50 NosCable Gland - 25mm 50 NosCable Gland - 19mm 50 Nos
26 Cable entry Plate:Dimension : 500H x 500Wx 4mm thicknessMaterial: CRCA steel withRAL7035 light grey colourpowder coating.
4 Nos
27 Mounting Plate:Dimension :1600H x 480Wx 2mm thickness ; Material: CRCA steel withRAL7035 light grey colourpowder coating.
15 Nos
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
190 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
28 Metal conduits, Metalflexible hoses suitable forconduit, 4/3/2 way metaljunction box suitable forconduit bends, elbows,Tees and couplers ofrequired quantities.
1 lot
29 Switches, Keys &indicators Detailed catalogueIndicators 40 NosAuthorization keys 10 NosSwitches with Indicators 40 NosMushroom capedemergency stop switches
10 Nos
29.a. Accessories for Switches,Keys &indicators
Details of accessories quotedand unit cost for each shall bementioned.
30 Data Logger 4 Nos Detailed catalogue indicatingmodel number and list of allaccessories.
30.a. Accessories for DataLogger
Details of accessories quotedand unit cost for each shall bementioned.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
191 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
30.b. Spares for data logger Details of spares quoted andunit cost for each shall bementioned.
31 Operator Chair 25 Nos Detailed catalogue32 Interface adaptor for
temperature probes18 Nos
33 Field Mountable cameraincluding Digital colourCameras with motorizedzoom/focus lens andExplosion proof Pan /tiltunit
7 Nos Detailed catalogue
34 Field Mountable cameraincluding Digital colourCameras with motorizedzoom/focus lens andweather proof Pan /tiltunit
5 Nos
35 Telemetry receiver with 17functions.
12 Nos
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
192 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
36 4 channel Fiber optictransmitter and receiversystem for video, audioand data
5 Nos
37 Video Cross matrixswitcher and Controllerunit witha. Joystick control orkeyboardsb. RS 485 data multiplexerunit.
4 Nos
38 8 channel Videodistribution amplifier
4 Nos
39 Video Recorder 4 Nos40 Large LED Display
monitors of 42Inches10 Nos
41 Large LED Displaymonitors of 32 Inches
2 Nos
42 RG 12 Co-axial cable 4000 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
193 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
43 Surge protectors for CCTVsystem
25 Nos
44 24V AC Transformer 12 Nos45 Flame proof Intercom
station5 Nos
46 Weather proof Intercomstations
3 Nos
47 Rack mountable Intercomstation
5 Nos
48 Surge protectors forintercom stations
13 Nos
49 Wireless units 13 Nos50 GPS/IRNSS based
Universal Time CodeGenerator
2 Nos
51 Network Time displayunits
4 Nos
52 24 core Fiber OpticArmored cable
4000 m
53 RG 59 Co-axial cable 500 m54 Ethernet cables 1000 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
194 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
55 3 core armored powercable
500 m
56 Network switch 6 Nos57 Explosion proof Audio
Visual Hooter5 Nos
58 Fiber optic splicing patchpanel
4 Nos
Sub Total -1
B. ERECTION WORKS Annexure A& C shall be
referred.1 Mounting of pressure
transmitter and its impulsetubing including hydrotesting
58 Nos
2 Mounting of guided wavelevel sensors and itstransmitter
8 Nos
3 Mounting of Temperaturesensor and its transmitter
15 Nos
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
195 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
4 Mounting of mass flowmeter and its transmitter
2 Nos
5 Mounting of flow switch 1 Nos6 Mounting of pressure
switch9 Nos
7 Mounting of 5 SOVs insideSOV cubicle, tubing fromheader to SOV cubicle inturn to individual SOVs.
75 Nos
8 Tubing from individualSOVs to EP valves(Approx. 10m length)including pneumatictesting
60 Nos
9 Mounting of Junction box 14 Nos10 2core 20AWG PVC Cable
laying and termination atboth ends in multi pinconnector/Terminal Block
4500 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
196 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
11 4core 20AWG PVC Cablelaying and termination atboth ends in multi pinconnector/Terminal Block
4000 m
12 10core 18AWG PVC Cablelaying and termination atboth ends in multi pinconnector/Terminal Block
1500 m
13 64core 20AWG PVC Cablelaying and termination atboth ends in multi pinconnector/Terminal Block
2500 m
14 96core 20AWG PVC Cablelaying and termination atboth ends in multi pinconnector/Terminal Block
800 m
15 96core 20AWG PVC Cablelaying and termination atboth ends in multi pinconnector/Terminal Block
2500 m
16 Leak Checking (Each no is10m in length)
150 Nos
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
197 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
17 Plain cement concretework
10 cu.m.
18 Structural fabricationworks
10000 kg
19 Laying of cable trays 6000 m20 Mounting and Wiring of
Instrumentation rack9 Nos
21 Multi core PTFE Cablelaying and termination atboth ends in multi pinconnector
700 m
22 Installation &Commissioning of consolesand control room tables.
16 segments
23 Installation,Commissioning of datalogger & Training
4 Nos
24 Erection andcommissioning of CCTVsystem - Field and controlroom equipmentsmounting, cable laying and
1 lot
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
198 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
Wiring. (except the workscovered underinstrumentation rackwiring and cable traylaying)
25 Erection andcommissioning of Intercomm system - Field andcontrol room equipmentsmounting, cable laying andWiring
1 lot
26 Erection andcommissioning of Timingsystem - Equipmentmounting, cable laying andWiring
1 lot
27 Mounting of fiber opticsplicing patch panel incontrol room and fiberoptic cable wiring
4 Nos
28 Underground Fiber opticcable laying which
3500 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
199 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
includes earth excavation,sand filling, brick workand placing marker. AnyPlain cement concretework, bricks, sandrequired shall also beincluded. (Refer3.3.2.3.104-106)
29 Fiber optic cable layinginside 2” hume pipe whichincludes supply of 2”hume pipe, couplers,fittings and layingconduits over MS supportstructures. Any Plaincement concrete work,bricks, sand required shallalso be included. (Refer3.3.2.3.104-106)
500 m
30 Powering of control roomequipments : Power cablelaying and termination
1000 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
200 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
31 Grounding of equipments :Laying of grounding cableand its termination.
500 m
32 Cable Entry Plate fixing 4 Nos33 False floor plank cutout 25 Nos34 Testing and Evaluation 250 Ch35 Detailed Engineering 1 lot36 Documentation 1 lot37 Miscellaneous works
37.a Equipments mounting 100 Nos37.b Cable laying
Cable laying - Ethernetcables
800 m
Cable laying - Co axialcables
300 m
Cable laying - Powercables
400 m
Cable laying - 96 core20AWG PTFE cable
600 m
Cable laying - 64 core20AWG PTFE cable
500 m
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure B: Price format
201 | P a g e 2 2 2
PRICE FORMATS.No Items Qty Unit Unit
Rate(Rs.)
TotalCost(Rs.)
Documents along with quotefor material supply
Reference
Cable laying - 32 core20AWG PTFE cable
300 m
37.c Termination works 10000 pointsSub Total -2TOTAL
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
202 | P a g e 2 2 2
TERMS & CONDITIONS1.1. ENTIRE AGREEMENT
1.1.1. The Contract to be entered into shall convey the final agreementbetween the Department and the Vendor on the terms andconditions.
1.1.2. In the event of conflicts between general conditions of Contract andthe specification furnished by the Department, the latter will takeprecedence.
1.2. MODIFICATIONS IN THE CONTRACT
This Contract may be amended or modified only in writing signed byboth the parties or their duly authorized agents or representatives bya change order issued by the Department and accepted by theVendor, pursuant to the terms stated therein.
1.3. CANCELLATION OF CONTRACT
1.3.1. The Department will have the right, at any time, to cancel theContract either wholly or in part by giving written notice. TheVendor shall undertake to observe the instructions of the Departmentas to the winding up of the Contract both on his own part and on thepart of his sub-vendors.
1.3.2. In the case of cancellation of the Contract by the Department withoutany fault of the Vendor, the Vendor shall forthwith take thenecessary steps to implement the Department’s instructions. Theperiod to be allowed to implement shall be fixed by the Departmentafter consultation with Vendor and, in general, shall not exceed 3months.
1.3.3. The Department will, in no circumstances, be liable to pay any sumwhich, when added to the other sums paid, due or becoming due tothe Vendor under the Contract and its amendments, if any, exceedsthe Contract payment for the work set forth in the Contract and itsamendments, if any.
1.3.4. The ownership of all materials, part and unfinished work paid for bythe Department under the provisions of this Section shall be vested inor transferred to the Department as soon as they have been paid for.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
203 | P a g e 2 2 2
1.4. VENDOR’S DEFAULT LIABILITY
1.4.1. The Department shall reserve the right to terminate the work in thecircumstances detailed hereunder:
a. If the Vendor fails to rectify or replace any defective system/sub-system/ equipment within a period of 60 days after theDepartment having given a notice to the Vendor to rectify orreplace the said defective system/ subsystem/ equipment or theVendor delays, suspends or is unable to complete the system/subsystem/ equipment by the date mutually agreed upon
b. If the vendor commits breach of any of the terms and conditionsof the Contract.
c. If the Government of India decides to terminate the Contract inpublic interest.
1.4.2. When the Vendor makes themselves liable for action under thecircumstances mentioned above, the Department will have power toforfeit the bank guarantee of Vendor and the Vendor shall have noclaim for damages whatsoever on such forfeiture.
1.4.3. The work remaining to be completed at the time of termination of theContract shall be got executed through any other Vendor, in whichcase the expenses, which may be incurred in excess of sums, whichwould have been paid to the original Vendor, had the whole workbeen executed by them, shall be borne by the original Vendor andshall be recovered from them.
1.5. CHANGES AND MODIFICATIONS TO SPECIFICATIONS ANDQUALITATIVE REQUIREMENTS
1.5.1. The Department shall reserve the right at any time to modify thequalitative requirements, specifications, patents or drawings relatedto the work covered by the Contract. The Vendor shall inform to theDepartment within 30 days, of any objections they have to themodifications required.
1.5.2. The Department may also accept the modification proposed by theVendor on his own initiative or on behalf of sub-vendors or as aresult of detailed engineering review.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
204 | P a g e 2 2 2
1.5.3. When a modification or other change is so authorized, the Vendorshall proceed with action in accordance with the Department’sdirection. They shall moreover, as soon as possible after the receipt ofsuch directions, submit to the Department a firm and detailedestimate showing any decrease or increase in the cost entailed by themodifications and any effect its introduction will have on thedelivery schedule.
Any amendment to the Contract which may be necessary in thisrespect will be established within a reasonable time in the form ofamendment to Contract, to be signed by both the parties. If theparties do not agree on the amendments to the Contract, in particularregarding prices, responsibility, delivery schedule etc, dispute shallbe submitted to arbitration.
1.6. SUB-CONTRACTING
The Vendor shall not assign or sub-contract the work or any part ofthe work without the written approval of the Department. In theevent of approval of sub-vendors, the detailed specifications anddrawings of sub-contracted items shall be approved by theDepartment. All the works carried-out by such sub-vendors shall alsobe scrutinized, inspected and approved by the Department. Howeverthe responsibility of such sub-contracted systems shall lie with theVendor. Any delay in carrying out the work by the sub-vendor whichaffects the overall schedule of the work does not absolve the Vendorfrom payment of compensation for the delays. All terms andconditions applicable to the Vendor shall also be applicable to sub-vendor.
1.7. COMPLIANCE WITH STANDARDS
All the materials supplied or used shall be of new and first qualityand manufactured and tested in accordance with the latest editions ofthe relevant Indian/ International standards. Wherever importedcomponents are used, they shall be manufactured in accordance withthe relevant standards published in the country of manufacture afterallowing for specific aspects under Indian conditions such as tropicalclimate, etc. Any material or work, where no specific standard is
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
205 | P a g e 2 2 2
applicable, shall be fabricated as per the instructions and directionsof the Department.
All the electrical equipments used shall conform to the latest IndianElectricity rules as regards safety, earthing and other essentialprovisions specified therein for installation and operation of electricalparts.
1.8. SECRECY
The technical information, drawings, specification and other relateddocuments forming part of enquiry or Contract are the property ofthe Department and shall not be used for any other purpose, exceptfor execution of the Contract. All rights, including the rights in theevent of grant of a patent and registration of designs are reserved.The technical information, drawings, specifications, records andother documents shall not be copied, transcribed, traced orreproduced in any other form or otherwise in whole and/ orduplicated, modified and/or disclosed to a third party and/or notmisused in any other form whatsoever without the Department’sconsent in writing except to the extent required for the execution ofthe work. This technical information, drawings, specifications,records and other documents shall be returned to the Departmentwith all approved copies and duplicates, if any, immediately afterthey have been used for the agreed purpose.
1.9. INSPECTION OF WORK
1.9.1. The Department or any person appointed by it shall have access andright to inspect the work, or any part thereof, at all times and placesduring the progress of the work. The inspection and supervision isfor the purposes of assuring the Department that the plans andspecifications are being properly executed and while the Departmentand its representative(s) will extend to the Vendor all desiredassistance in interpreting the plans and specifications, such assistanceshall not relieve the Vendor of any responsibility for the work. Anywork which is proved faulty shall be corrected by the Vendorwithout delay. The fact that faulty work or work which is not inaccordance with plan and specifications was not pointed out by the
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
206 | P a g e 2 2 2
Department will not relieve the Vendor from correcting such work asdirected by the Department without additional compensation.
1.9.2. The Department’s representatives shall at all reasonable times havefree access to the works and/ or to the workshops, factories or otherplaces where materials are being prepared or fabricated for the workand also to any place where the materials are lying or from wherethey are being obtained, and the Vendor shall give every facility tothe Department’s representatives for inspection and test of thematerials and workmanship even to the extent of discontinuingportions of the work temporarily or of uncovering or taking downportions of finished work.
1.9.3. The Department has no obligations to discover defects patents orotherwise and it shall be the sole responsibility of the Vendor. Theinspection and clearance for dispatch by Department’srepresentatives shall not absolve the Vendor’s obligations and dutiesunder terms and conditions herein.
1.10. CO-ORDINATION WITH OTHER VENDORS ANDINTERFACING OF THE WORKS
The Vendor shall extend all co-operation to other Vendors of theDepartment to perform their works at site simultaneously. TheVendor shall so arrange their activities so as to ensure smooth andtimely execution of the project, minimize interference with the worksof the other Vendors and allow the other Vendors to use the facilitiesengaged by them for erection activities. For this purpose, the Vendorshall plan such works and indicate such interfaces in an interfaceschedule. They shall not be entitled to any extra payment on thisaccount.
1.11. FORCE MAJEURE
If at any time during the execution of the Contract, the performancein whole or in part by either party of any obligation under the workis prevented or delayed by reasons of any war, hostility, acts of thepublic enemy/terrorist, civil commotion, sabotage, fire, flood, earthquake, epidemics, quarantine restrictions, strikes, lock-outs, or acts ofGod (hereinafter referred as Eventualities) and if notice is given byeither party to the other within 21 days from the date of occurrence
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
207 | P a g e 2 2 2
thereof, neither party shall for such eventuality be entitled toterminate the work nor shall any party have any claim for damagesagainst the other in respect of such non-performance or delay inperformance. The performance under the work shall be resumed assoon as practicable after such eventualities have come to an end andthe decision of the Department whether the performance has beenresumed or not shall be final and conclusive.
Provided further that if the performance in whole or in part of anyobligation under the work is prevented or delayed by sucheventuality for a period of exceeding 60 days, the Department may attheir option terminate the Contract provided also if the work isterminated under this clause, the Department will be at liberty totake over from the Vendor at a price fixed by the Department whichshall be final. All unused, un-damaged acceptable materials, bought-out components lying in stores in course of erection andcommissioning in the possession of the Vendor at the time of suchtermination of such portion thereof as the Department may deem fitexcepting such material, bought-out components lying in stores asthe Vendor may with the concurrence of the Department elect toretain.
1.12. INDEMNITY TO DEPARTMENT AGAINST INFRINGEMENTOF LABOUR LAWS
The Vendor shall indemnify the Department against any action,claim or proceedings relating to infringement of all or any of theprevailing labour laws of India like Workmen’s Compensation Act1923, Work Labour (Regulation and Abolition), Central Rules 1971,Employees Liability Act 1938, Industrial Disputes Act 1947,Employees Provident Funds and Miscellaneous Act 1952 as amendedfrom time to time during erection and commissioning atDepartment’s site.
1.13. PATENT RIGHTS
The Vendor shall fully indemnify the Department against any action,claim or proceedings relating to infringements or use of any patent orany design or any alleged patent or design rights and shall pay anyroyalty which may be payable in respect of any claims made under or
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
208 | P a g e 2 2 2
any action brought against the Department. In respect of suchmatters as aforesaid, the Vendor shall be set at liberty, at their ownexpense, to settle any dispute or to conduct any litigation that mayarise there-from. The Vendor shall not be liable to indemnify theDepartment on the infringement of the patent or design or anyalleged patent or design right which is the direct result of an orderpassed by the Department.
1.14. ARBITRATION
Except matters in respect of which the decision of the Department isfinal as specified in the Contract, any dispute, disagreement orquestion arising out of or relating to or in consequence of the work orfulfilment or the validity of the enforcement thereof which cannot besettled mutually, shall within 30 days from the date that either partyinforms the other in writing that such dispute or disagreement exists,be referred to arbitration. The Arbitrator shall be a serving Lawofficer of the rank of Joint Secretary to the Government of India andshall be nominated by Director, IPRC. The award of the Arbitrator soappointed shall be final and binding on the parties to this PurchaseOrder. The arbitration proceedings shall be in compliance with theArbitration and Conciliation Act 1996. The performance under thiswork shall continue during the arbitration proceedings and nopayment due or payable by the Department will be withheld unlessany such payment is or forms part of the subject matter of thearbitration proceedings. All expenditures towards arbitration will beequally shared by both the parties.
1.15. ASSIGNMENT
The work shall be binding upon the successors and the assignees ofthe parties hereto. It shall not be assigned in whole or in part byeither party without prior written consent of the other. If the Vendorbecomes insolvent or being a firm or a company whetherincorporated or not is dissolved or goes into bankruptcy or is causedto be wound up except for re-construction purposes or carried on itsbusiness under a receiver, the representatives in law of estate of theVendor or any such receiver, liquidator or any person in whom theagreement may be vested shall forthwith give notice thereof in
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
209 | P a g e 2 2 2
writing to the Department and shall remain liable for the successfulperformance of the Vendor or the successors of their obligationsunder this Contract under any circumstances.
1.16. JURISDICTION AND APPLICABLE LAW
The work shall be governed by the laws of India for the time being inthe force. The courts of the Tirunelveli, Tamil Nadu state only shallhave jurisdiction to deal with and decide any legal matters or disputewhatsoever arising out of the work.
1.17. EXECUTION OF WORK
The specifications of the work are intended to describe and providefor a complete finished system. It is to be understood and agreed bythe Vendor that the work described shall be complete in every detail,even though every item necessarily involved is not particularlymentioned. The Vendor shall be required to provide all labour,materials and equipments necessary for the completion of the workdescribed and shall not avail themselves of any manifestingunintentional error, omission or inconsistency that may exist. TheVendor shall carry out and complete the work in every respect inaccordance with the Contract and the directions and to thesatisfaction of the Department.
1.18. RIGHTS OF THE DEPARTMENT
1.18.1. RIGHT TO ILLUSTRATE AND EXPLAIN PLANS
a. The various parts of the Contract are intended to becomplementary to each other but if any discrepancies appear orany misunderstanding arises, the explanation of the Departmentwill be final and binding.
b. The corrections of any errors or omissions of specifications maybe made by the Department, when such correction is necessaryto bring out clearly the intention which is indicated by areasonable interpretation of the specifications as a whole.
c. Wherever in the specifications which are a part of the work orwhich may be furnished to the Vendor for directing the work,the terms and descriptions of various qualities of workmanship,
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
210 | P a g e 2 2 2
materials, structures, processes, plant or other features of thework are described in general terms, the meaning of fulfillmentof which must depend upon individual judgments, then in allsuch cases, the question shall be decided by the Department andsaid material shall be furnished, said work shall be done andsaid structure or feature shall be constructed, furnished orcarried out in full and in accordance with their interpretation ofthe same and to their full satisfaction and approval, providedsuch interpretation is not in direct conflict with the specificationsor generally accepted good practice.
1.18.2. RIGHT TO DIRECT WORK
a. The Department will have the right to direct the manner inwhich all work under this Contract shall be done, in so far as itmay be necessary to secure the safe and proper progress and thespecified quality of the work and all work shall be done and allmaterial shall be furnished to the satisfaction and approval ofthe Department.
b. Whenever, in the opinion of the Department, the Vendor hasmade marked departure from the schedule of completion laiddown in the Contract or when untoward circumstances forcedeparture from the said schedule, the Department in order toassure compliance with the schedule and the provisions of thework, shall direct the order, pace and method of doing the work,which shall be adhered to by the Vendor.
c. If, in the judgment of the Department, it becomes necessary atany time to accelerate the overall execution of the work, theVendor when ordered and directed by the Department willcease the work at any particular point and transfer their men tosuch other point or points and execute such portion of theirworks, as may be required, to enable others to hasten andproperly engage and carry on their work, as directed by theDepartment.
d. The work by the Vendor at the site beyond normal workinghours (08:45 to 17:15 hr) on working days and any time onholidays (including Saturdays and Sundays) shall be permitted
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
211 | P a g e 2 2 2
only with prior approval of the Department. The Departmentmay also direct the Vendor to operate extra shifts over andabove normal day shift to ensure completion of the work onschedule if, in the opinion of the Department, such work isrequired.
1.19. VENDOR’S FUNCTIONS
1.19.1 The Vendor shall provide everything necessary for properexecution of the work according to the intent and meaning of thespecifications whether the same may or may not be particularlyshown or described therein, provided that the same can reasonablybe inferred there-from and if the Vendor finds any discrepancythere-in, they shall immediately and in writing refer the same to theDepartment whose decision shall be final and binding on theVendor.
1.19.2 In the execution of the work, no person other than the Vendor, ortheir duly appointed representatives, their sub-vendors, and theirworkmen, shall be allowed to work at the site except by specialpermission, in writing by the Department.
1.19.3 The Vendor shall proceed with the work to be performed under thisContract and each and every part and detail thereof, in the best andmost workmen-like manner by engaging qualified, careful andefficient workers and to the several parts thereof at such time and insuch order as the Department directs and finish such work in strictconformance with the drawings and/or specifications and anychanges, modifications thereof made by the Department.
1.19.4 The Vendor’s personnel shall not be permitted to reside inside theDepartment’s premises after the work. The Vendor shall arrange fortransportation, accommodation, food, health care, communication,etc. for their personnel.
1.19.5 In respect of observance of local rules, administrative orders,working hours and the like, the Vendor and their personnel shall co-operate with the Department.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
212 | P a g e 2 2 2
1.20. SUPPLY OF TOOLS, AND OTHER MATERIALS
1.20.1. For full completion of the work, the party shall, at their own expense,furnish all erection tools, power tools, cables, wiring tools, testinstruments, and all associated protective equipments, appliances,materials required to accomplish the work under the contract unlessotherwise provided for. Adequacy of such tools shall be subject tofinal determination of the Department.
1.20.2. The party shall not dispose, transport or withdraw any tools,equipments and materials provided by them for the contract withouttaking prior written approval from the Department and theDepartment at all times shall have right to refuse permission fordisposal, transport or withdrawal of tools, equipment and material ifin their opinion, the same will adversely affect the efficientcompletion of the work.
1.20.3. The Vendor shall also furnish all necessary expendable devices likeanchors, grinding and abrasive wheels, plugs, hacksaw blades, taps,dies, drills, reamers, chisels, files, carborundum stones, wire brushes,necessary scaffolding, ladders, wooden planks, timbers, sleepers, andconsumable materials like oxygen, acetylene, argon, lubricating oils,greases, cleaning fluids, cylinder oil, graphite powder and flakes,fasteners, gaskets, temporary supports, stainless steel shims orvarious thicknesses as required, cotton waste, PTFE tapes and allother miscellaneous supplies of every kind required for carrying outthe work under the contract.
1.21. PROTECTION OF WORK
1.21.1. The Department will not be responsible or held liable for any damageto person or property consequent upon the use, misuse or failure ofany fabrication tools and equipment used by the Contractor or any oftheir sub-contractors.
1.21.2. The Contractor shall effectively protect all the works from action ofweather and from damages or defacement and shall cover finishedparts where required for their thorough protection.
1.21.3. The Contractor shall cover the work by a Contractor’s all-riskpolicyduring the currency of the contract.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
213 | P a g e 2 2 2
1.22. SITE PERSONNEL
The party shall identify a Site Supervisor and he/ she shall bepersonally present to supervise the work under the contract. The SiteSupervisor shall have full technical capability and completeadministrative and financial powers to expeditiously and efficientlyexecute the work under the contract. Any written orders orinstructions which the Department may give to the party’s SiteSupervisor shall be deemed to have been given to the party.
1.23. FIRST AID
The Vendor may have access to the Departments’ qualified first aidpersonnel and ambulance in case of accidents, subject to theavailability of the same. However, the Vendor shall make his ownmedical and transport arrangements to take care of his employees incase of accident. The Vendor shall provide a first aid kit at the worksite to meet the requirements of minor injuries.
1.24. REPORTING
The Vendor must report the following information to theDepartment by the end of every week during the work atDepartment’s site.
a) Progress achievedb) Expected dates for completion of individual worksc) Any actual or likely delay in the execution of work
1.25. WORKING AND SAFETY REGULATIONS
The Vendor shall observe all statutory and legal requirementsenforced by Central and State Government applicable to the work aswell as any local regulations applying to the site issued byDepartment or any other authority. Particular attention is drawn tothe following;
a) In case of accident, the Department shall be informed in writingforthwith. The Vendor shall strictly follow the regulations laiddown by the Factory Inspector, Central and State Governmentauthorities in this regard.
b) Compliance with all electricity regulations.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
214 | P a g e 2 2 2
1.26. ELECTRICAL SAFETY REGULATIONS
In no circumstances will the Vendor interfere with fuses andelectrical equipment belonging to the Department or other Vendors.Before the Vendor connects any electrical appliance to any plug orsocket belonging to other Vendor or Department, he will
a) Satisfy Department that the appliances are in good workingcondition
b) Inform the Department of the maximum current rating, voltageand phase of the appliance
c) Obtain permission of the Department detailing the sockets, towhich the appliance may be connected
1.27. POWER
Electricity will be supplied at free of cost. Contractor must providepower supply distributor with isolator for taking power for hisequipments. Contractor should obtain Electrical safety clearancefrom CMG/IPRC and safety clearance from safety division beforestarting the work.
1.28. WATER
Free supply of water will be made available by the Department.
1.29. CLEAN-UP OF WORK SITE
The party shall not store or place the equipment, materials or erectionequipment on the drive ways and streets and shall take care that theirwork in no way restricts or impedes traffic or passage of men andmaterial. All waste materials are to be disposed off safely to thelocation specified by the department
1.30. SAFETY AND RELIABILITY
1.31. Since the systems are highly complex in nature, the philosophy andcriteria to be adopted shall be highly safety-and-reliability-oriented fortheir systematic and proper functioning. The designs of the sub-systems, components, equipments to be carried out by the Contractorshall specifically address essential safety provisions both in-built andexternal. Reliability is a prime factor, which has to be embedded in theprocess of realization of the systems. To ensure that the sub-system
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
215 | P a g e 2 2 2
design, development, selection of equipment, components, material,etc are in compliance with the standard engineering practices, it isnecessary to follow established design codes and standards.
1.32. SECURITY DEPOSIT
The Supplier shall deposit an interest free amount equivalent to the10% (TEN PERCENT) of the total order value towards Security Depositfor the due performance of the Purchase Order within 30 days from thedate of Purchase Order. The Security Deposit can be submitted eitherin the form of (a) Cash to the Accounts Officer, IPRC against properReceipt, (b) Demand Draft drawn in favour of Accounts Officer, IPRC,(c) Bank Guarantee in Rs.100/- Non-judicial Stamp Paper obtainedfrom any Nationalized/Scheduled Bank and (d) Term Deposit Receiptsduly endorsed by the respective Banks in favour of IPRC. Thissecurity deposit shall be returned to the Supplier only upon successfulcompletion of all the contractual obligations or shall be adjusted /forfeited against non-fulfillment of any of the contractual obligations.
1.33. QUALITY ASSURANCE
The reliability of Instrumentation is a combination of specification ofthe equipments/ components, serviceability and maintenance of thesame, which are meant to serve and provide effective and timelyoperation, which includes trouble-free performance of systems andsub-systems to the intended specifications.
The Contractor must look for the quality factors individuallyattributed to engineering developments, selection of equipments andcomponents, test and acceptance procedures followed, repetitiveperformance achieved, risk analysis carried out, etc. each and everymodule must be manufactured and tested to international QualityControl standards. The test certificates shall be provided toDepartment.
The quality assurance is an unified approach that attempts to controlthe quality right from design stage to commissioning stage, whichincludes the checking of the adequacy of the equipments/components for materials, fabrication, installation, testing. It is thecombined responsibility of the Contractor and the Department toensure that all possible failure modes are exercised and validatedduring FAT.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
216 | P a g e 2 2 2
1.34. PURCHASE OF MATERIALS
The selection of equipments, components, materials, etc. withappropriate and suitable specifications shall be the responsibility ofthe Vendor, as overall performance of the system rests with theVendor. Accordingly, the selection and purchase tasks shall behandled by the Vendor immediately after the approval of DetailedEngineering documents by the Department.
The criteria for selection of particular product and the reasoninginvolved therein shall be submitted to the Department for necessaryapproval. However Department’s decision will be final.
For the goods of foreign origin, if any, the Supplier/their Suppliershall arrange Export License.
The Department will provide necessary end-use certificate forobtaining the required license for import of items if requested by theContactor.
In keeping with the terms of the Contract, the Vendor shallundertake the responsibility for handling, packaging andtransportation involved to the accepted level of any sub-systems/equipment covered by the work in the Contract.
1.35. EMPLOYMENT OF LABOURS
The vendor shall deploy Indian National only for execution of thework.
Only skilled employees with experience of this particular work shallbe employed.
No person below the age of 18 years shall be employed.
The Supplier shall pay to each person, wages not less than thosespecified by Minimum Wages Act.
The employees / labour, for carrying out all the site works shall beidentified well in advance by the vendor and necessary approvalshall be obtained from the Department for entry permit to the worksite.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
217 | P a g e 2 2 2
1.36. GATE PASS
For Vendor’s equipment, tools, materials, etc. which are to be takenout from IPRC, Mahendragiri campus after completion of work,proper entry shall be made at the main gate duly endorsed by CISF.The Department shall issue necessary gate passes for taking out theVendor’s materials, as and when required and after completion ofwork.
2 INSTRUCTIONS TO BIDDERS
The proposals are invited as sealed quotations on behalf of thePresident of India by the Head, Purchase & Stores, IPRC,Mahendragiri, from reputed Vendors of high competence for thefollowing work for IPRC, Mahendragiri, Tirunelveli District, TamilNadu State, India.
2.1 SCOPE OF WORK
The scope of the work includes Detailed Engineering, Procurement,erection & commissioning , test & Evaluation and documentation forBulk storage Facilities as per the specification given in this document.The bidder is required to submit quotation for the entire worksmentioned herein. The incomplete quotations shall be summarilyrejected. The deviation, if any, in the bidder’s proposal with respectto this document shall be explicitly mentioned in the schedule ofdeviations to be provided in the quotation. If the bidder does notmention any deviation, it shall be construed by the Department thatthe bidder agrees to comply with each and every aspect of thisdocument.
2.2 EXECUTION PERIOD
The proposed work contract is to cater to the requirements ofprocurement, installation and commissioning of instrumentationsystem for bulk storage facilities at IPRC, Mahendragiri. The contractshall be valid for a period of 12 months from the date of award ofcontract. The execution schedule shall be as given below.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
218 | P a g e 2 2 2
Sl. No Scope of work Period Responsibility
1 Detailed engineering andacceptance by Department 2 months Vendor
2 Equipment and materialsupply
3 months Vendor
3 Erection and commissioning 4 months Vendor
4 Test and Evaluation 2 months Vendor
5 Documentation 1 month Vendor
2.3 COMPENSATITION FOR DELAY
If the contractor fails to complete execution of the contract or fails tomeet delivery specified in the contract or any extension thereof, theDepartment will recover from the Contractor as Liquidated Damages(LD) a sum of 0.5% of the total contract price for each calendar weekof delay or part thereof. The total liquidated damages shall notexceed 10% of the contract price.
2.4 DELIVERY TERM
All equipments/materials to be supplied by contractor shall bedelivered at IPRC, Mahendragiri. The party shall be responsible forfurther transportation of items to erection site. Further responsibilityof handling and storage of all items lies with the vendor.
2.5 LANGUAGES AND MEASURES
All documents pertaining to the Contract including specifications,schedules, notices, correspondence, operating and maintenanceinstructions, drawings or any other writings shall be written inENGLISH Language only.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
219 | P a g e 2 2 2
2.6 DOCUMENTS
All operating, maintenance and technical manuals, drawings anddiagrams in English Language relevant to the systems/componentsshall be supplied by the Contractor.
2.7 GUARANTEE
a) The “Defect Liability Period” shall be 12 months from the date ofsuccessful completion of commissioning of instrumentation system.The work shall not be considered as completed until theDepartment has certified in writing that they have been actuallyaccepted and the Defect liability period shall commence from thedate of such certificate.
b) The equipments & material supplied by the vendor shall carry aguarantee for a period of 12 months from the date ofcommissioning, against any material defect, design defect,manufacturing defect and/or failure of equipment to perform, asstipulated.
c) In case any defect in the work due to bad materials, and/ or badworkmanship develop in the work before the expiry of the period,the Contractor, on notification by the Department, shall rectify orremedy the defects at their own cost and shall make their ownarrangements to provide materials, labour, equipment and anyother appliances required in this regard.
d) The equipments, or components repaired or replaced by theContractor shall be guaranteed for a period of 12 months from thedate of repairs or replacement.
e) The Contractor shall furnish performance guarantee in the form ofan unconditional irrevocable bank guarantee to the extent of 10 %of the total contract value valid during the defect liability period. Ifany defect is noticed by the Department during the defect liabilityperiod and Contractor fails to rectify or remedy the defects, theDepartment will have the right to get this done by other agenciesand recover the cost incurred, as determined by the Department,which shall be final and binding, by recovery from the amounts dueto the Contractor and/ or by enforcing bank guarantee.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
220 | P a g e 2 2 2
2.8INSURANCE
The contractor should take all necessary steps including thenecessary insurance cover till the system are dispatched & deliveredat purchaser’s site.
2.9PACKING
The contractor shall pack all the equipments, materials and itsaccessories and make the identification names at the top of each pack.Proper packing shall be done so as to ensure that the items are notdamaged during transportation.
2.10 FORM OF QUOTATION
The quotation shall be submitted separately fora. Technical and commercialb. Price
The first shall contain the technical and commercial aspectsshall be opened first. The price quotation and the revision in pricesthereof if any submitted subsequently based on authorization fromthe Department, shall be opened only after the evaluation of thetechnical and commercial quotation.
All documents (including the drawings) issued in this tenderenquiry shall be returned along with the quotation. The bidder notquoting for this enquiry shall return the tender documents (includingthe drawings) to the Head Purchase & Stores, IPRC, Mahendragiriwithin 15 days from due date of opening.
All corrections shall be attested by initials of the bidder with date.The Department reserves the right to reject any or all quotations inwhole or part without assigning reasons thereof.
2.11 PRICES
The bidder shall quote firm and fixed prices valid during theexecution of the Contract till commissioning and final acceptance ofthe systems to the satisfaction of the Department. The prices shallinclude all taxes, levies like octroi, duties, taxes, royalties, permitscharges, etc. levied by any central, state, local or other Governmentalauthority, which the Vendor is required to pay in any country as well
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
221 | P a g e 2 2 2
as in India with reference to fabrication, purchase, transportation upto the delivery point stated in this document.
The bidder shall provide the individual item wise break-upprices as given in Annexure-B price format.
2.12 PAYMENT
Milestone payments: Milestone payment will be considered asfollows:
1. 20% of price upon completion of configuration approval ofdetailed engineering review against bank guarantee valid up tofinal completion.
2. Further 30% of price shall be released after receipt andacceptance of all items at Department site.
3. Further 20% of price shall be released after completion ofcommissioning of entire system (including Testing &Evaluation).
4. 20 % of price after final documentation.5. Further 10% of price shall be released upon satisfactory
completion of commissioning all activities against performancebank guarantee.
2.13 VALIDITY
The quoted price should be valid for a period of 6 months from thedate of opening of the technical and commercial quotation.
2.14 QUANTITY VARIATION OF ITEM
The exact quantity and the list of items required for commissioningthe facility will be finalized during detailed engineering and 10%quantity variation shall be permitted for supply and erection part ofcontract.
2.15 PRE-BID MEETING
Within 2 weeks from date of floating of tender, it is proposed to briefall interested bidders on the requirements of this document at IPRC,Mahendragiri and the exact date will be intimated after tendering.
Procurement, Installation and Commissioning of Instrumentation system for BSFAnnexure C: Terms and conditions
222 | P a g e 2 2 2
Bidders interested to participate in the pre-bid meeting shallcommunicate their willingness in writing to Head, Purchase &Stores immediately on receipt of this document.
2.16 BIDDER’S PROFILE
The bidder shall elaborately bring out in their technocommercial offer, their company profile, which shall becommensurate with the level demanded for the execution of thework specified in this document. Department has right to reject theproposals which are in-complete or found unsuitable based on thedetails requested below.
The details shall include the following:
a. Infra-structural facilities such as factory area, machineries,equipments, material handling devices, instruments, tools,tackles, etc
b. Human resource inventory under the categories such asexecutives, managers, engineers, supervisors, foremen,technicians, unskilled laborers, clerical staff, auxiliary staff,etc. The educational qualification, expertise and experience ofthe key staff shall also be submitted.
c. Financial soundness, specifying the annual turn-over, annualincome tax paid, name of the banker, etc.
d. Previous experience in the execution of projects of the natureand quantum on par with those specified in this document.
e. Experience of having successfully completed similar works asmentioned below during last 7 years ending 30th September2016 shall be submitted.One project costing more than Rs. 100.00 lakhs
(or)Two projects costing more than Rs. 50.00 lakhs each
(or)Three projects costing more than Rs. 25.00 lakhs each.
f. Clientele, specifying the clients to whom they have executedworks of nature similar to that specified in this document.The address, telephone, fax, E-mail and contact person of theclients shall also be specified.