04. Procurement of Goods, Works, Services Islamic Development Bank Module 4 Project Start-up Workshop 04. Procurement of Goods, Works, Services Project Procurement Division, OPSDTRANSCRIPT
Procurement in Projects Financed by Islamic Development BankCountry Procurement WorkshopSeptember 2015, Jakarta, Republic of Indonesia
Project Procurement (PPR) DivisionOperations Policy And Services Department (OPSD)
04. Procurement of Goods, Works, Services
Project Start-up Workshop
04.1 PrequalificationProject Start-up Workshop
Prequalification Process
4Republic of Indonesia, September 2015
Qualification and Experience
Requirement
Draft Prequalification Document sent to
IsDB
IsDB NOL Advertisement – SPN for Prequalification
Preparation and Submission of
Application Document
Prequalification Report sent to IsDB IsDB NOL
2 No Objection Letters (NOLs) required± 4months after advertisement
Project Procurement Division, OPSD
5Republic of Indonesia, September 2015
Prequalification
• Large or complex contracts, supply contracts of specialized equipment and machinery or turnkey contracts
Application
• To ensure that the bids are submitted by the firms who have relevant expertise and adequate resources
Purpose
• Eligibility• Experience and past performance (overall & on similar scope)• Capabilities• Current commitment of works in progress• Financial position during the past 3 to 5 years
Evaluation Criteria
Project Procurement Division, OPSD
6Republic of Indonesia, September 2015
Prequalification
• Saves cost of tendering for unqualified bidders• Improves participation by qualified firms• Identifies possible conflict of interest• Encourages joint ventures and pooling of resources
Advantages
• Increases procurement lead time • Requires reviewing all prequalification applications vs to only
one or two at post-qualification• Collusion/Price rigging easier with limited number of identified
tenderers
Possible disadvantages
Project Procurement Division, OPSD
7Republic of Indonesia, September 2015
Prequalification
• Description of Works, Size (Cost), Quantities• Type of Contract• Implementation Schedule• Prequalification requirements• Criteria for evaluation of applicants
Information Provided to Applicants
• Eligibility (Applicants’ Legal status, Form of JV) • Historical Non-Performance (litigations if any)• Financial Capability • Relevant experience
Information Requested from Applicants
Project Procurement Division, OPSD
8Republic of Indonesia, September 2015
Prequalification
• Use IDB Standard Pre-Q Documents/Forms• The time allowed for preparation and submission of PQ
applications — preferably eight weeks, • Public Opening is not necessary • Late submission (within reasonable time) not automatically
rejected• Evaluation is based on pre-set Pass/Fail standards; no scoring
system! • All firms who meet the criteria prequalified (No maximum or
limitation)
Submission and Evaluation of Applications
Project Procurement Division, OPSD
9Republic of Indonesia, September 2015
Notification and Advertisement in Prequalification
Specific Procurement Notice (SPN)• Advertised in the same manner as GPN, including in
terms of type of media and distribution channel• Choice of media in all working languages of IsDB (Arabic,
English & French)• At least in one local newspaper as well, twice on two
nonconsecutive days within a span of ten (10) days
Project Procurement Division, OPSD
10Republic of Indonesia, September 2015
Prequalification Document
PART 1 – Prequalification Procedures• Section I. Instructions to Applicants• Section II. Prequalification Data Sheet• Section III. Qualification Criteria and Requirements• Section IV. Application Forms• Section V. Eligible Countries• Section VI. Bank Policy - Corrupt and Fraudulent PracticesPART 2 – Works Requirements• Section VII. Scope of Works
Section I, V, VI shall not be changed or revised,
Sections II, III, IV VII shall be customized as per the
assignment,
Project Procurement Division, OPSD
11Republic of Indonesia, September 2015
Evaluation
Administrative & Legal Information
Legal status, registration, principal place of business,
ownership
Power of attorney of signatory of the
application/bid
Litigation record in the past # years
Criteria
Bidder shall be eligible to participate
Authorized person signs the bid
No consistent history of litigation or arbitration
Project Procurement Division, OPSD
12Republic of Indonesia, September 2015
Evaluation
TechnicalInformation
Works of “similar” nature & size (last # years or ongoing)
Major construction equipment proposed
Key site management & technical personnel
Proposals for subcontracting (≥ # percent)
Criteria
≥ # similar works.
Acquisition plan (own, lease, hire, etc.)
Contract Manager ≥ # years, Managers ≥ # years
As per requirement in the future bidding
Project Procurement Division, OPSD
13Republic of Indonesia, September 2015
Evaluation
Financial Information
Audited financial standings (past n years)
Value of construction works in each of last n years
Net liquid assets or credit facilities
Bank’s reference
Criteria
Valid financial information
≥ # x annual average of contract value
≥ # months of average contract cash-flow
Availability of working capital confirmed
Project Procurement Division, OPSD
14Republic of Indonesia, September 2015
Evaluation
Joint Venture Association
All information provided for each partner
Signed and legally binding on all partners
All partners are eligible (excludes MC requirement)
All partners are jointly and severally liable
One partner in charge & fully meets MC requirement
Partner in charge meets 40% technical and financial requirement
Other partners meets 25% technical and financial requirement
Combined JV meets 100% technical and financial requirement
Project Procurement Division, OPSD
15Republic of Indonesia, September 2015
Issues with Prequalification• Discouraging otherwise prospective firms to participate– Extra application forms which ask for excessively detail information– Requirement relevant only to local firms
• Discarding otherwise fully qualified firms– Ignoring permissible clarifications due to incomplete application– Over-emphasize on administrative aspects– Scoring instead of pass/fail with assessment on responsiveness
• Inclusion of otherwise non-qualified firms– Claiming experience of joint-venture partner(s) or parent company’s– Claiming incomplete/ongoing works– Low qualification threshold
• Reducing overall competition– Excessively high requirement
Project Procurement Division, OPSD
16Republic of Indonesia, September 2015
Key Success Factors in Prequalification
Wider advertisement.
Well-defined & sufficient evaluation criteria and its consistent application
Thorough and consistent evaluation
Rectify non-material deficiencies, avoid premature ‘disqualification’
Project Procurement Division, OPSD
04.2 BiddingProject Start-up Workshop
ICB or ICB/MC Single-Stage One-Envelope with Prequalification
18Republic of Indonesia, September 2015
Draft BiddingDocument
IDB NOL
Bid document sent to prequalified
firms
Bid Preparation (≥60-90 days) &Bid Submission
Bid Opening
Bid Evaluation
Bid Evaluation Report &
Recommendation
IDB NOLContract
negotiation, draft negotiated
contract
IDB NOL
Contract Award
3 No Objection Letters (NOLs) required± 5 months bid documents issuance
Project Procurement Division, OPSD
19Republic of Indonesia, September 2015
Bidding Process
• Tender submission, evaluation and contract award recommendation in one-stage
• Administrative, technical and financial bids are all submitted at one time and opened simultaneously for evaluation
• All opened bids are evaluated
Single-Stage One-Envelope Bidding
Project Procurement Division, OPSD
20Republic of Indonesia, September 2015
Documents Comprising a Bid
Bidder shall submit:
The Bid, following the format given in the bid document
Bid Security
Priced Bill of Quantity (BOQ)
Updated qualification Information forms and documents
Alternative offers (if allowed)
Project Procurement Division, OPSD
21Republic of Indonesia, September 2015
Bidding DocumentSpecifications and Standards• Shall be based on relevant characteristics, performance, capability, and quality, and
shall not prescribe brand names, catalogue numbers, or products of a specific manufacturer. If there is a need to quote then the words “or equivalent” shall be added after such reference. As far as possible, internationally accepted standards shall be specified.
Bid Validity Period (BVP)• Normally from 60 to 120 days and may be up to 180 days for large and complex bids. Bid Security • In the form and amount specified in the Bidding documents, generally 2% is considered
fair and reasonable. Shall remain valid for a period of 4 weeks beyond the BVP, and will be returned to unsuccessful bidders within 10 days after notification of contract award.
Alternative bids• Shall clearly be stated in the Bidding documents. The bidder shall first quote the price
for the method and specifications indicated in the bidding documents and secondly indicate the price for deviation or alternative solution. Only the alternative bid submitted by the substantially responsive lowest evaluated bid shall be considered.
Project Procurement Division, OPSD
22Republic of Indonesia, September 2015
Bids Submission & Opening
• Bids preparation shall not be less than 60 days for ICB or ICB/MC, and 90 days for large and complex contract.
• Invitation specifies date, time and place for bids submission & opening.
Bid Submission
• Time for bid opening shall be the same as for the deadline for bid submission.
• Bids received after deadline are returned unopened• Bids opened publicly and bidders’ attendance is encouraged and should
be facilitated.
Bids Opening
• Name of the bidder, total bid price, price of alternative bids - if any, any unconditional discounts
• Bid security amount and validity• Minutes of the meeting shall be recorded and kept, and a copy of this
record shall promptly be sent to all bidders and to IDB.
Read out Information
Project Procurement Division, OPSD
23Republic of Indonesia, September 2015
Bids Examination & Evaluation
• To verify substantially responsive bids: whether the bidding document has been signed, valid bid security provided, prices for all items have been quoted, if required, eligibility criteria is met. If the bids is not substantially responsive to the bidding document it shall be rejected and not be considered further.
• Complete basic data sheet Prepare record of bid opening Prepare table of bid price Examine bids for responsiveness
Preliminary
• Used to determine the cost of each responsive bid in a manner that permits a comparison on the basis of their evaluated cost in order to select the technically acceptable lowest evaluated bid price.
• Identify bids for detailed evaluation Evaluate bids in detail Apply corrections and errors Apply other adjustments (discount)
Evaluation
Project Procurement Division, OPSD
24Republic of Indonesia, September 2015
• Use single currency specified in the bidding documents
• The Rates to be used are the selling rates quoted by and official source (Central bank, Commercial bank or internationally circulated newspaper)
• The date shall not be earlier thank 4 weeks prior to deadline for bid-submission and not later than the original expiry date of the bids.
Exchange Rate
Project Procurement Division, OPSD
25Republic of Indonesia, September 2015
Bids Evaluation – Works
Review of BoQ & Correction of arithmetical Errors
• Correction of errors• Correction of Provisional Sum• Modification and Discount• Evaluation of Currency• Additions and Adjustment
Alternatives time
• Alternative times for completion can be permitted when the Employer sees potential net benefits in different times for completion.
• If permitted under ITB 13.2 of the Bidding documents, the method for evaluating the differences offered by bidders should be specified as a specific amount for each week of delay from a specified “standard” or minimum completion date related to the loss of benefits to the Employer.
Project Procurement Division, OPSD
26Republic of Indonesia, September 2015
1.Preliminary Examination• Verification• Eligibility• Bid Security• Completeness of Bid• Substantial Responsiveness
2. Detailed Examination• Correction of Errors• Correction of Provisional sum• Modifications & Discounts• Evaluation Currency• Additions• Adjustments• Priced Deviations
3. Determination of Award• Qualification (Post)• Alternative Bids• Proposed Award
Evaluation of the Bids – Evaluation Steps
Project Procurement Division, OPSD
27Republic of Indonesia, September 2015
Bids Evaluation – Goods
• delivery schedule;• the projected operating and maintenance costs during the life of the
equipment;• the cost of components, mandatory spare parts, and service;• the performance and productivity of the goods/equipment offered; • the availability in the Purchaser’s country of spare parts and after-sales
services; and/or• other specific criteria indicated in the Bidding Documents and/or in the
Technical Specifications.
Factors
Project Procurement Division, OPSD
28Republic of Indonesia, September 2015
Bids Evaluation – “Plants”
• Example approach: Life-cycle Cost Evaluation (LCC)
“Total Cost of Ownership”
• Evaluate and compare alternative products/equipment• Assess economic viability of projects or products/equipment
LCC Benefits
• Acquisition (design, investment, installation & commissioning), operation, maintenance
LCC Elements
• Determine time-frame for each element and guaranteed value of each element• NPV of total of all elements to be considered for recommending the winner
LCC Steps
• The evaluation period, guaranteed parameter within evaluation period but post defect liabilities period
Issues with LCC
Project Procurement Division, OPSD
29Republic of Indonesia, September 2015
Update of Qualification• The Bidder shall continue to meet the
criteria used at the time of prequalification.
• Updating and reassessment of the qualification information which was previously considered during prequalification will be required:– Eligibility, pending litigation, financial
situation– Specialized subcontractors– Financial resources– Personnel– Equipment
Project Procurement Division, OPSD
30Republic of Indonesia, September 2015
• The award of contract is subject to IDB’s prior approval.
• Upon receipt of IDB’s “no-objection”, the Beneficiary shall promptly inform the successful bidder.
• The Beneficiary shall furnish to IDB a copy of signed contract, together with first request for disbursement and the performance guarantee.
• Contracts awarded under ICB, ICB/MC and NCB must be published in an appropriate newspaper.
• A Contract which is awarded without IDB’s “no-objection” shall not be eligible for IDB financing.
Contract Award
Project Procurement Division, OPSD
31Republic of Indonesia, September 2015
Review by IDB of Procurement Decisions• Prior Review is carried out for all contracts
unless a specific threshold amount is indicated in the Financing Agreement
• Before bids are invited, the Beneficiary shall furnish to IDB for its comments:– Advertising procedure;– Draft bidding documents, including the invitation to
bid;– Instructions to bidders, including the basis of bid
evaluation and contract award; – Conditions of contract and specifications for supply
of goods, or installation of equipment, or the civil works.
• After bids have been received and evaluated, the Beneficiary shall, before a final decision on the award is made, furnish to IDB in sufficient time for its review, a detailed report on evaluation and comparison of the bids.
Project Procurement Division, OPSD
32Republic of Indonesia, September 2015
Review by IDB of Procurement Decisions• Post Review (for contracts below a
monetary threshold if specified in the Financing Agreement)
• The Beneficiary shall furnish to IDB, promptly after its preparation, the bid evaluation report and recommendation for contract award, for IDB’s comments and “no-objection”.
• IDB shall, if it determines that the award of a contract or the contract itself is not in consistent with the Financing Agreement, promptly inform the Beneficiary that paragraph 1.12 of the Guidelines on Misprocurement shall apply and state the reasons for such determination.
Project Procurement Division, OPSD
33Republic of Indonesia, September 2015
• National (small works or goods) or International (goods)• Comparing written price quotations• obtained from several suppliers (off-the-shelf goods or standard specification
commodities) • or from several domestic contractors (small works)
National Shopping
Project Procurement Division, OPSD
34Republic of Indonesia, September 2015
• Reputable suppliers or contractors: provide the intended goods or construction works as part of its core business activities
• A minimum of three fully qualified quotations are compared, for international shopping of goods – at least from 2 MCs
• Reasonable time to submit quotation (10-30 days).• Goods: description, technical specifications, quantity and cost of the goods,
including the cost of inland transportation and insurance if applicable, estimated delivery time if not immediately available.
• Works: necessary drawings, estimated quantities, and completion time.• Shall be given in writing and may be submitted by electronic transmission
(e.g. telex or facsimile).• Opened at the same time, read out in public before the solicited suppliers or
contractors or their representatives, evaluated and compared at the same time.
• Brief report prepared• Post-review applicable below agreed threshold
National Shopping - Requirement
Project Procurement Division, OPSD
35Republic of Indonesia, September 2015
Key Success Factors in Tender for Goods and Works
Wider advertisement.
Well-defined & sufficient evaluation criteria and its consistent application
Thorough and consistent evaluation
Rectify non-material deficiencies, avoid premature ‘disqualification’
Project Procurement Division, OPSD
36Republic of Indonesia, September 2015
Question and Answer
Project Procurement Division, OPSD
Republic of Indonesia, September 2015
Thank YouProject Procurement Division
Operation Policy and Services Departmentwww.isdb.org, [email protected]
prepared by Amirmehdi AsghariSenior Project Procurement Specialist
أفضل مستقبالً نبني معاً Together we build a better future
Ensemble nous construisons un avenir meilleur
10Project Procurement Division, OPSD