Question:
Plan ProcurementsProcess Group
Answer:
Planning
Question:Plan Procurements
Knowledge Area
Answer:
Project Procurement Management
Question:Plan ProcurementsInputs
Answer:
Scope baseline Requirements documentation Teaming agreements Risk register Risk related contract decisions Activity resource requirements Project schedule Activity cost estimates Cost performance baseline EEF OPA
Question:Plan ProcurementsTools & Techniques
Answer:
Make or buy analysis Expert judgement Contract types
Question:Plan ProcurementsOutputs
Answer:
Procurement management plan Procurement statements of work(SOW) Make or buy decisions Procurement documents Source selection criteria Change requests
Question:Conduct ProcurementsProcess Group
Answer:
Executing
Question:Conduct ProcurementsKnowledge Area
Answer:
Project Procurement Management
Question:Conduct ProcurementsInputs
Answer:
PMP, Project Management Plan
Procurement documents Source selection criteria Qualified seller list Seller proposals Project documents Make or buy decisions Teaming agreements OPA
Question: Answer:
-
7/29/2019 Procurement Flashcards (1).pdf
2/3
Conduct ProcurementsTools & Techniques Bidder conferences
Proposal evaluation techniques Independent estimates Expert judgement Advertising Internet search
Procurement negotiations
Question:Conduct ProcurementsOutputs
Answer:
Selected sellers Procurement contract award Resource calendars Change requests PMP updates Project document updates
Question:Administer ProcurementsProcess Group
Answer:
Monitoring & controlling
Question:Administer ProcurementsKnowledge Area
Answer:
Project Procurement Management
Question:Administer ProcurementsInputs
Answer:
Procurement documents PMP, Project Management Plan Contract Performance reports Approved change requests Work performance information
Question:Administer ProcurementsTools & Techniques
Answer:
Contract change control system Procurement performance reviews Inspections & audits Performance reporting Payment systems Claims administration Records management system
Question:Administer ProcurementsOutputs
Answer:
Procurement documentation OPA updates Change requests
PMP updates
Question:Close ProcurementsProcess Group
Answer:
Closing
Question:Close ProcurementsKnowledge Area
Answer:
Project Procurement Management
-
7/29/2019 Procurement Flashcards (1).pdf
3/3
Question:Close ProcurementsInputs
Answer:
PMP, Project Management Plan Procurement documentation
Question:Close ProcurementsTools & Techniques
Answer:
Procurement audits Negotiated settlements Records management system
Question:Close ProcurementsOutputs
Answer:
Closed procurements OPA updates
How many processes in "ProjectProcurement Management" ?
4 Plan Procurement Conduct Procurement Administer Procurement Close Procurement