process operation
TRANSCRIPT
-
8/11/2019 Process Operation
1/171
Process Operation
Ahmed RagabProcess Engineer
EPROM
-
8/11/2019 Process Operation
2/171
AGENDA
1. Equipment Startup, shutdown &troubleshooting
2. Commissioning, startup & shutdownconsideration.
3. Maintenance Strategies & Policies4. Isolation Philosophy.5. Safety principles and basic HAZOP.6. Basic Math and physics required.
7. Interpersonal Skills
-
8/11/2019 Process Operation
3/171
Equipment Startup & shutdown
Pumps. Compressors.
Heat exchangers. Fired heaters. Valves.
-
8/11/2019 Process Operation
4/171
Pumps
Priming: no centrifugal pump should ever be started
until it is fully filled with the liquid pumpedand all the air contained in the pump hasbeen allowed to escape
-
8/11/2019 Process Operation
5/171
Starting procedures:1.Prime the pump, opening the suction
valve, closing the drains, and so on, toprepare the pump for operation.
2.Open the valve in the cooling supply to thebearings, where applicable.
-
8/11/2019 Process Operation
6/171
3.Open the valve in the cooling supply if theseal chambers are liquid-cooled.4.Open the valve in the sealing liquid supplyif the pump is so fitted.5.Open the warm-up valve of a pumphandling hot liquids if the pump is notnormally kept at operating temperature.When the pump is warmed up, close thevalve.
-
8/11/2019 Process Operation
7/171
6.Open the valve in the recirculating line ifthe pump should not be operated againstdead shutoff.7.Start the motor.8.Open the discharge valve slowly.
9.For pumps equipped with mechanicalseals, check for seal leakage: there shouldbe none.
-
8/11/2019 Process Operation
8/171
10.For pump with shelf packing, observe theleakage from the stuffing boxes and adjustthe sealing liquid valve for proper flow toensure the lubrication of the packing. If thepacking is new, do not tighten up on thegland immediately, but let the packing run in
before reducing the leakage through thestuffing boxes.
-
8/11/2019 Process Operation
9/171
11.Check the general mechanical operationof the pump and motor.
12.Close the valve in the recirculating linewhen there is sufficient flow through thepump to prevent overheating.
-
8/11/2019 Process Operation
10/171
Shutting down procedures:1. Open the valve in the recirculating line.
2. Close the gate valve.3. Stop the motor.4. Open the warm-up valve if the pump is to
be kept at operating temperature.5. Close the valve in the cooling supply tothe bearings and seal chambers.
-
8/11/2019 Process Operation
11/171
6. If the sealing liquid supply is not requiredwhile the pump is idle, close the valve in thissupply line.
7. Close the suction valve, open the drainvalves, and so on, as required by theparticular installation or if the pump is to beopened up for inspection.
-
8/11/2019 Process Operation
12/171
Troubleshooting
-
8/11/2019 Process Operation
13/171
-
8/11/2019 Process Operation
14/171
-
8/11/2019 Process Operation
15/171
-
8/11/2019 Process Operation
16/171
-
8/11/2019 Process Operation
17/171
-
8/11/2019 Process Operation
18/171
-
8/11/2019 Process Operation
19/171
-
8/11/2019 Process Operation
20/171
Compressors
TROUBLESHOOTING
GUIDE FORCOMPRESSOR
PROBLEMS
-
8/11/2019 Process Operation
21/171
Motor will not run1. Improper line voltage - Check line voltage,change lines as required.2. Poor contact on motor terminals or starterconnections Ensure good contact onmotor terminals and starter connections.3. Improper starter heaters - Install properstarter heaters.
-
8/11/2019 Process Operation
22/171
Oil in discharge gas1. Clogged or dirty inlet and/or dischargefilter - replace filter element.2. Oil viscosity too low - Drain existinglubricant from frame. Refill with properlubricant.3. Oil level too high - Drain lubricant fromframe to proper level.
-
8/11/2019 Process Operation
23/171
4. Detergent type lubricant being used -Drain existing lubricant from frame. Refillwith specified lubricant.5. Piston rings damaged or worn (broken,rough, scratched, excessive end gap or side{clearance) - Replace piston rings.
-
8/11/2019 Process Operation
24/171
6. Piston rings not seated, stuck in grooves,or end gaps not staggered.Clean and adjust piston rings. Replace asrequired.
-
8/11/2019 Process Operation
25/171
Oil in discharge gas7. Cylinder scratched, worn or scored. -Replace or repair as required.8. Piston scratched, worn or scored. - Repairor replace as required.
-
8/11/2019 Process Operation
26/171
Gas delivery has dropped off1. Clogged or dirty inlet and/or discharge filter -replace filter element.2. Gas leaks in piping (on compressor orexternal piping/system). -Check tubing andconnections. Repair or replace as required.3. Valves leaking, broken, carbonized or loose. -Check valves. Clean and replace as required.
-
8/11/2019 Process Operation
27/171
4. Automatic condensate drain valve defective -Inspect drain valve. Repair or replace asrequired.
5. Piston rings damaged or worn (broken, rough,scratched, excessive end gap or side clearance) -Replace piston rings.
6. Piston rings not seated, stuck in grooves, orend gaps not staggered. Clean and adjust pistonrings. Replace as required.
-
8/11/2019 Process Operation
28/171
Gas delivery has dropped off7. Cylinder scratched, worn or scored. -Replace or repair as required.8. Piston scratched, worn or scored. - Repairor replace as required.
-
8/11/2019 Process Operation
29/171
Relief valve vents pressure1. Clogged or dirty inlet and/or dischargefilter - replace filter element.2. Valves leaking, broken, carbonized orloose. - Check valves. Clean and replace asrequired.3. Automatic condensate drain valvedefective. - Repair or replace as required.
-
8/11/2019 Process Operation
30/171
Compressor runs excessively hot1. Inadequate ventilation around belt wheel -Relocate compressor or add ventilation.2. V-belt pulled too tight - Adjust belttension.3. Wrong belt wheel direction of rotation. -Check motor wiring for proper connections.
-
8/11/2019 Process Operation
31/171
4. Valves leaking, broken, carbonized orloose. - Check valves. Clean and replaceas required.
-
8/11/2019 Process Operation
32/171
Gas and/or oil leaking from shaft seal 1. Shaft seal leaking, broken or improperly
seated - Repair or replace as required.
-
8/11/2019 Process Operation
33/171
Excessive lubricant consumption1. Piston rings damaged or worn (broken,rough, scratched, excessive end gap or sideclearance).2. Piston rings not seated, stuck in grooves,or end gaps not staggered- Clean and adjustpiston rings. Replace as required.
-
8/11/2019 Process Operation
34/171
3. Cylinder scratched, worn or scored -Repair or replace as required.
4. Piston scratched, worn or scored - Repairor replace as required.
-
8/11/2019 Process Operation
35/171
Heat exchangers
Procedure to Take a Heat Exchangerout of Service :-
1. The hot fluid must be shut off before thecold fluid.
2. After the hot fluid has been shut off, thecold fluid can be shut off on both inletand outlet valves.
3. Both shell and tube side should now bepumped out to slop or drained down.
-
8/11/2019 Process Operation
36/171
4.Both inlet and outlet lines should beblanked off for safety.
5.the exchanger should be water washedbefore opening to the atmosphere (sour oilservice case)
-
8/11/2019 Process Operation
37/171
Procedure to Place Heat exchanger inService:-
1-Cheek the exchanger carefully toensure that all plugs have beenreplaced and that all pipe work isready for the exchanger to be placedin service .
2-All valves should be in the shutposition.
3-Purging and testing
-
8/11/2019 Process Operation
38/171
4-Line up the system.5-Open hot and cold fluid vent valves 6-cold fluid inlet valve &vent all air when
liquid full, then Close cold fluid ventvalve.7-open hot fluid outlet valve and vent allthe air, then close hot fluid vent valve.
-
8/11/2019 Process Operation
39/171
8-At this stage, the exchanger is liquidfull of both hot and cold flowingfluids - open cold fluid inlet and hotfluid outlet valves fully.
9-The cold fluid valve outlet may beopened slowly until the cold fluid ispassing through the exchanger.
-
8/11/2019 Process Operation
40/171
10-Start opening the hot fluid inlet valveslowly.
11-Both valves, the cold fluid outlet valveand the hot fluid inlet should be openslowly until fully open.
-
8/11/2019 Process Operation
41/171
TROUBLESHOOTING CHECKLIST
1-Plugged Tubes Back flushing
Air bumping Acid cleaning vs. piping corrosion Upsetting cooling tower pH due to
acid cleaning
-
8/11/2019 Process Operation
42/171
2- Hydrocarbon Leaks Watch for hydrocarbon haze Rapid biological growth on cooling tower
cell decks Check for gas with test meter on cell decks Vibrating cooling water lines Check vent on exchanger channel head for
leaks
-
8/11/2019 Process Operation
43/171
3-Cooling Tower Deficiency Check wet bulb temperature Inspect Interior for damaged fill Eliminate large holes in distribution
decks Redistribute water to individual cells Unplug distribution holes Increase chlorination rate
-
8/11/2019 Process Operation
44/171
4-High Exchanger Water OutletTemperature
Cooling water pump deficiency Plugged cooling tower screen
Plugged exchanger tubes Plugged floating head
-
8/11/2019 Process Operation
45/171
5-Water-Side Fouling Hardness deposits Poor pH control Biological deposits Insufficient chlorine addition
Routine tabulation of heat transfercoefficient
-
8/11/2019 Process Operation
46/171
Review vendor's treatment program Cycles of concentration
-
8/11/2019 Process Operation
47/171
Fired Heaters
Fired HeatersTroubleshooting
-
8/11/2019 Process Operation
48/171
Heater Tube Failures
The design pressure of the tube is not theinlet operating pressure of the heater.
The design tube temperature is theanticipated or calculated maximum tubeskin temperature (at end-of-runconditions).
-
8/11/2019 Process Operation
49/171
The calculated tube skin temperature is
mainly a function of the fouling resistanceassumed inside the tube.
A typical process heater tube diameter is 4to 10 in. Tube thickness is usuallybetween 0.25 and 0.50 in.
-
8/11/2019 Process Operation
50/171
Heater tubes are often constructed out ofchrome steel, the chrome content increasesthe heat resistance of the tube.
For added corrosion and temperatureresistance, the nickel content of tubes andsometimes the Moly (molybdenum) content as
well are increased.
-
8/11/2019 Process Operation
51/171
-
8/11/2019 Process Operation
52/171
If we just block in the leaking process tubesand fuel-gas supply, the flue-gas compositionenters the explosive region. The firebox will
now explode. The correct way to prevent this sort of firebox
explosion is to use firebox snuffing steam.
A typical heater firebox might have a halfdozen purge steam connections.
-
8/11/2019 Process Operation
53/171
Hot Spots Hot Spot Causes Flame impingement. Poor radiant-heat distribution. Interior tube deposits.
Dry-point deposits.
-
8/11/2019 Process Operation
54/171
Valves
Valvesoperation &
troubleshooting
-
8/11/2019 Process Operation
55/171
Operate the valve
NOTE
Nearly all valves follow the convention ofopening counterclockwise and closingclockwise, but it is always necessary to check
that the valve you are operating follows thisconvention. The following operatingguidelines are based on this convention.
-
8/11/2019 Process Operation
56/171
Operate a gate valve
To open:Turn the handwheelcounterclockwise allthe way.
Turn the valve one-quarter turn clockwiseto prevent the valvefrom freezing open.
To close: Turn the handwheel
clockwise all the way.
CAUTIONTurn the handwheel slowly to prevent waterhammer, so as to avoid damaging pipes andequipment.
-
8/11/2019 Process Operation
57/171
Operate a globe valve.
To open:Turn the handwheelcounterclockwise.
To throttle:Open the valve slightly past thedesired position, then throttleback to the desired position.
To close:Turn the handwheel clockwise.
-
8/11/2019 Process Operation
58/171
StartUp1. Valves should e started in a manner thatallow for controlled pressuringof the valve and the system.a. The valve should be pressured andvented.i. Bleed air off of the main valve coverii. Bleed air off of the controls1. Trapped air will give a false
-
8/11/2019 Process Operation
59/171
b. Bring pilots into service with pressure settinglower than the required.i. Adjust to higher pressures as system andvalve stabilizes.
-
8/11/2019 Process Operation
60/171
c. Pilot Adjustmentsi. Make all adjustments slowly, allowing forthe control, valve andsystem to read the change.ii. Clockwise adjustments always increasethe pressure setting.
-
8/11/2019 Process Operation
61/171
1. Turning the reducing control IN willINCREASE outlet pressure.2. Turning the relief/sustaining control IN willINCREASE the inletor relief set-point.
-
8/11/2019 Process Operation
62/171
iii. Counterclockwise adjustments alwaysLOWER/DECREASE thepressure setting.1. Turning the reducing control OUT willLOWER outlet pressure.2. Turning the relief/sustaining control OUTwill LOWER the inletor relief set-point.
-
8/11/2019 Process Operation
63/171
Troubleshooting
-
8/11/2019 Process Operation
64/171
-
8/11/2019 Process Operation
65/171
Commissioning,startup & shutdown
consideration.
-
8/11/2019 Process Operation
66/171
Mechanical Completion,Pre Commissioning &
Commissioning
-
8/11/2019 Process Operation
67/171
Mechanical Completion
All design and engineering has beencompleted
All installation work for that system including
all equipment has been completed in accordance with Approved for
Construction drawings,
specifications, applicable codes andregulations and good engineering practices.
All instruments have been installed.
-
8/11/2019 Process Operation
68/171
All tie-in connections have been made. All factory acceptance tests and all other
testing and inspection activities have been completed. Contractor has obtained approvals, which
are the responsibility of the Contractor to obtain.
-
8/11/2019 Process Operation
69/171
Safety Studies have been completed andsatisfaction of all the Safety Studies requirements have been met and all
documentation put in place. All required documentation and certificationdocuments required by the Contract havebeen supplied.
-
8/11/2019 Process Operation
70/171
All operating procedures and maintenanceprocedures have been forwarded to theCompany well in advance for review.
All items for which Contractor is responsiblefor obtaining third party,
regulatory or Company approval have beenobtained and confirmation documentation hasbeen provided to Company.
-
8/11/2019 Process Operation
71/171
Pre-Commissioning
Performance of all remaining works otherthan commissioning and PerformanceTests.
Making operational and commissioning allsystems that can be made operationalbefore well fluids are introduced.
-
8/11/2019 Process Operation
72/171
The completion and testing of the plantequipment & systems
Testing of all parts and systems of theWorks including the communicationssystems (if required).
-
8/11/2019 Process Operation
73/171
Provision of initial fill of packing,chemicals, inhibitors, lubricants, glycol,water and other stocks have been made.
Checking, site modifications. Internal inspection of the vessels. Flushing/cleaning of vessels & piping. Calibration of PSVs .
-
8/11/2019 Process Operation
74/171
Calibration of all the instruments Loop checking. Complete checking of the safety system Checks on electrical system and other
vendor packages including DCS etc. The delivery, storage and cataloguing of
all spares
-
8/11/2019 Process Operation
75/171
Items for which a defect Notice are issuedto be rectified and all defect
Notices shall have been closed out. The Completion Documents along with all
Design Documents to As-Built The preparation of the commissioning plan
and submission to Company for review.
-
8/11/2019 Process Operation
76/171
The hydro testing and pneumatic testing ofvessels.
Training and briefing of the Companysand Contractors personnel involved incommissioning.
Removal of all debris and constructionequipment from Site.
C i i i
-
8/11/2019 Process Operation
77/171
Commissioning
Ready for Commissioning means the point atwhich the Company issues a certificate to theContractor saying that the system is ready
for commissioning. At this point all systems and equipment shall
be at a stage where hydrocarbons/ injection
water can be safely introduced and allequipment can be safely operated with allcontrols and safety devices in service.
PERFORMANCE TESTS FOR
-
8/11/2019 Process Operation
78/171
WORKS
The Contractor shall carry outPerformance Tests. The Contractor shalldevelop a detailed procedure for the
performance tests in accordance with therequirements of the Contract and submitthem to Company for Approval.
DOCUMENTS TO BE SUBMITTED
-
8/11/2019 Process Operation
79/171
DOCUMENTS TO BE SUBMITTED
Operating ManualThe following information shall be included: Design basis Description of facilities Pre-commissioning checks
Start-up, normal operation & shut downprocedures for each equipment.
-
8/11/2019 Process Operation
80/171
Plant start-up procedure. Plant normal operation procedure Plant shut down procedure
(normal/emergency) Vendor instructions for all equipment for
normal operation and troubleshooting.
-
8/11/2019 Process Operation
81/171
Emergency procedures. Operating parameters and set points of
different alarms and trip devices Summary of chemical consumption
including list of recommended Indianequivalent.
Summary of utilities consumption for eachequipment.
P h Li i M h d S
-
8/11/2019 Process Operation
82/171
Punch-Listing Method Statement
A system will be developed to identify,record and correct damaged, incompleteand incorrect installation and/or
fabrication. Items which are inaccessibleor unsafe will be incorporated into thissystem.
-
8/11/2019 Process Operation
83/171
The system will be able to allowcategorization of punch-list items asfollows:
Category A Items that must be clearedprior to start of Pre-commissioning
Category B Items that can be clearedduring pre-commissioning
Category C Commissioning Items
St t & Sh td
-
8/11/2019 Process Operation
84/171
Startup & Shutdown
Start-up Procedures will be prepared foreach Process Unit, a detailed OperatingManual.
Note:Start-up and shut-down procedure will includedetailed
equipment procedure. Systems will be dividedinto main equipment , such as turbines, specialmotors, etc., and common equipment .
START UP PROCEDURE
-
8/11/2019 Process Operation
85/171
START UP PROCEDURE
All necessary blinds are removed All relief valves installed and tested. Flare header purged and in service. Sewers in service Heaters steamed out
Fuel gas and fuel oil lines in service Pilot lit in all heaters.
-
8/11/2019 Process Operation
86/171
All instruments ready for service All drains and vents closed in operation
section.
Control valves and bypassed blocked in All compressors blocked in Flanges taped in an operation section. Nitrogen supply available and connected Steam jet ejectors connected.
-
8/11/2019 Process Operation
87/171
Evacuation and purging to remove air fromreactor circuits.
Steam out of vessels The loading shall be started at a level
lower than the design standard and shallbe gradually increased while observingpresence of problems in machinery andequipments
-
8/11/2019 Process Operation
88/171
At the time at which all the productsreached the desired specifications acomparison should be made between the
actual figures and the design figures In case of running a modern refinery plant
the remedial action taken to solve the
problem should be recorded.
-
8/11/2019 Process Operation
89/171
Maintenance
Strategies &Policies
Maintenance Strategy
-
8/11/2019 Process Operation
90/171
Maintenance Strategy
Maintenance Strategy Maintenance Approach Signification
BreakdownMaintenance Fix-it when broke
Large maintenancebudget
PreventiveMaintenance
ScheduledMaintenance
Periodic componentreplacement
PredictiveMaintenance
Condition-basedMonitoring
Maintenance decisionbased on equipmentcondition
ProactiveMaintenance
Detection of Sourcesof Failures
Monitoring andcorrecting failing rootcauses
Maintenance Policies
-
8/11/2019 Process Operation
91/171
Maintenance Policies
The policy is a certain rule-based for longterm according to the working conditions.
-
8/11/2019 Process Operation
92/171
-
8/11/2019 Process Operation
93/171
(2) Time-Based Preventive (PM): - Calendar:
Weekly
Monthly :: - Running:
1000 R.H. 1000 K.M. ::
-
8/11/2019 Process Operation
94/171
(3) Condition-Based Predictive (PdM): Oil analysis Vibration analysis
Temperature analysis
Pressure analysis
Wear analysis
Efficiency analysis ::
-
8/11/2019 Process Operation
95/171
(4) Risk-Based Proactive (PaM): - RCFA (The Root Cause Failure Analysis )
- FMEA (Failure mode & effet analysis) FMECA (Failure mode & cause and effet analysis)
- HAZOP
- RCM (Reliability centered maintenance)
- RBI (Risk Based Inspection )
-
8/11/2019 Process Operation
96/171
5) Total-Based Global (GM): - OSM
- TPM ::
-
8/11/2019 Process Operation
97/171
Policy Approach Goals
Reactive Run to failure (fix-it whenbroke). Minimize maintenance costsfor non-critical equipment.
Preventive Use-based maintenance
program.
Minimize equipment
breakdown.
Predictive Maintenance decisionbased on equipmentcondition.
Discover hidden failuresand improve reliability forcritical equipment.
Proactive Detection of sources offailures. Minimize the risk of failuresfor critical systems.
Global Integrated approach. Maximize the systemproductivity.
-
8/11/2019 Process Operation
98/171
Policy Approach Goals
RCFA Identification of root causesof failures. Eliminate failures.
FMECA Identification of criticality offailures. Improve equipmentavailability.
HAZOP Identification of hazards andproblems associated withoperations.
Improve HSE effect.
RCM Determination of bestmaintenance requirements forcritical systems.
Preserve system function &
improve reliability.
RBI Determination of an optimuminspection plan for criticalsystems.
Improve system HSE andavailability.
-
8/11/2019 Process Operation
99/171
Policy
Approach
Goals
OSM Optimization approach for the
global maintenance system.
Maximize reliabilitymeasures and minimizemaintenance cost rates.
TPM Comprehensive productive-maintenance system. Maximize planteffectiveness and resourceproductivity.
-
8/11/2019 Process Operation
100/171
IsolationPhilosophy
-
8/11/2019 Process Operation
101/171
cover common isolation applicationsrelated to
the project. The philosophy coversprocess and utility piping and equipment
along with instrumentation isolationrequirements. It also addresses the
-
8/11/2019 Process Operation
102/171
positive isolation requirements for vesselentry etc.
Requirements for ducting systems andpiping systems containing air or flue
gases under low pressure are excludedfrom this philosophy
Responsibilities.
-
8/11/2019 Process Operation
103/171
Safetyprinciples
-
8/11/2019 Process Operation
104/171
Occupational accidents and diseases not onlycause great pain, suffering and death tovictims
Occupational accidents and diseases also resultin: loss of skilled and unskilled but experienced
labour; material loss, i.e. damage to machinery and
equipment well as spoiled products.
-
8/11/2019 Process Operation
105/171
high operational costs through medicalcare, payment of compensation, andrepairing or replacing damaged machinery
and equipment.
Engineering control and housekeeping
-
8/11/2019 Process Operation
106/171
Engineering control and housekeeping
Engineering control involves controllingthe hazard at the source. The competentauthority should ensure that exposure to
hazardous substances is prevented orcontrolled by prescribing engineeringcontrols and work practices which afford
maximum protection to workers
Work practices and organizationalh d
-
8/11/2019 Process Operation
107/171
methods
reduce the source of the hazard, so thatrisks are confined to certain areas whereengineering control measures can be
applied effectively; adopt adequate work practices and
working-time arrangements so that
workers exposure to hazards is effectivelycontrolled; and
-
8/11/2019 Process Operation
108/171
minimize the magnitude of exposure, thenumber of workers exposed and theduration of exposure, e.g. carry out noisy
operations at night or during the weekend,when fewer workers are exposed.
Personal protective equipment
-
8/11/2019 Process Operation
109/171
Personal protective equipment
When none of the above approaches isfeasible, or when the degree of safetyachieved by them is considered
inadequate, the only solution is to provideexposed persons with suitable personalprotective equipment and protective
clothing.
-
8/11/2019 Process Operation
110/171
Employers should consult workers or theirrepresentatives on suitable personalprotective equipment and clothing, having
regard to the type of work and the typeand level of risks.
Technological change
-
8/11/2019 Process Operation
111/171
Technological change
Technological progress can play animportant role in improving workingconditions and job content, but it can also
introduce new hazards. The hazards associated with technologies
(equipment, substances and processes)
used at the work site must be identifiedand effective measures taken to eliminateor control them
-
8/11/2019 Process Operation
112/171
The introduction of new technology shouldbe accompanied by adequate informationand training. Furthermore, potentially
dangerous machinery, equipment orsubstances should not be exported withoutadequate safeguards being put in place,
including information on safe use in thelanguage of the importing country.
HAZOP
-
8/11/2019 Process Operation
113/171
HAZOP There are many techniques to highlighthow hazards can occur in the processindustries.
They also provide a clearer understanding ofhazards nature and possible consequences,thereby improving the decision making
process. These techniques assures more safe andoperable design.
-
8/11/2019 Process Operation
114/171
What is a HAZOP study HAZOP is a systematically structuredtechnique for identifying hazards, failuresand operability problems resulting frompotential malfunctions in the process(process deviation).
-
8/11/2019 Process Operation
115/171
Why do a HAZOP study HAZOP study generates a list of identified
process and operability problems.
In addition to suggestions for improvement of thesystem under study.
Alert operators from possible processdeviations and what to do in such cases. HAZOP review is very cost effective, as it
appears from the following example.
-
8/11/2019 Process Operation
116/171
Case study
-
8/11/2019 Process Operation
117/171
Feed supply system to a process reactor. A light study is to identify offsite hazards. HC reagent is pumped from a Nitrogen
blanketed buffer tank (T-1), which suppliesthe process reactor.
A Piping and Instrument Diagram (P&ID)is used for the HAZOP study.
-
8/11/2019 Process Operation
118/171
The instruments include: Pressure indicator. (PI) Pressure indicator controller. (PIC) Flow indicator controller. (FIC) No alarms were included at this stage.
Starting with (T-1), and applying guidewords as shown in the following table.
-
8/11/2019 Process Operation
119/171
-
8/11/2019 Process Operation
120/171
-
8/11/2019 Process Operation
121/171
-
8/11/2019 Process Operation
122/171
-
8/11/2019 Process Operation
123/171
Basic Math and
physics
required.
Fluid Dynamics
-
8/11/2019 Process Operation
124/171
y
Velocity is a measure of speed anddirection of an object.
-
8/11/2019 Process Operation
125/171
Laminar flow of a liquid occurs when itsaverage velocity is comparatively low andthe fluid particles tend to move smoothly in
layers.
-
8/11/2019 Process Operation
126/171
Turbulent flow occurs when the flowvelocity is high and the particles no longerflow smoothly in layers and turbulence or a
rolling effect occurs.
-
8/11/2019 Process Operation
127/171
The Reynolds number R is a derivedrelationship combining the density andviscosity of a liquid with its velocity of flow
and the cross-sectional dimensions of theflow and takes the formR = VD /
-
8/11/2019 Process Operation
128/171
Flow rate is the volume of fluid passing agiven point in a given amount of time
Q = VA
-
8/11/2019 Process Operation
129/171
Bernoulli equationThe Bernoulli equation gives the relation
between pressure, fluid velocity, andelevation in a flow system.
Pressure
-
8/11/2019 Process Operation
130/171
pressure the force exerted by gases and liquids due to theirweightDynamic pressure
is the pressure exerted by a fluid or gas when itimpacts on a surface or an object due to its motion orflow.
Impact pressure (total pressure)the sum of the static and dynamic pressures on a
surface or object.
-
8/11/2019 Process Operation
131/171
Total vacuumzero pressure or lack of pressure, as would be experienced in
outer space.
Vacuum
pressure measurement made between total vacuum and normalatmospheric pressure (14.7 psi).
Atmospheric pressurethe pressure on the earths surface due to the weight of the
gases in the earths atmosphere and is normally expressed atsea level as 14.7 psi or 101.36 kPa. It is however, dependanton atmospheric conditions.
-
8/11/2019 Process Operation
132/171
Absolute pressurethe pressure measured with respect to a vacuum
Gauge pressure
the pressure measured with respect to atmosphericpressure.
Differential pressurethe pressure measured with respect to anotherpressure
-
8/11/2019 Process Operation
133/171
PUMP HORSEPOWER The handiest pump horsepower formula is
where HP = pump horsepower GPM = gallons per minute
AP = delivered pressure (discharge minus suction), psi Eft. = pump efficiency
Thermodynamics
-
8/11/2019 Process Operation
134/171
Temperature definitions
Temperature is a measure of the thermal energy in abody, which is the relative hotness or coldness of amedium and is normally measured in degrees usingone of the following scales; Fahrenheit (F), Celsiusor Centigrade (C), Rankine (R), or Kelvin (K).
Absolute zero is the temperature at which allmolecular motion ceases or the energy of themolecule is zero.
-
8/11/2019 Process Operation
135/171
Fahrenheit scale was the first temperature scale togain acceptance. It was proposed in the early 1700sby Fahrenheit (Dutch). The two points of referencechosen for 0 and 100 were the freezing point of a
concentrated salt solution (at sea level) and theinternal temperature of oxen .This eventually led to theacceptance of 32 and 212 (180 range) as thefreezing and boiling point, respectively of pure water at
1 atm (14.7 psi or 101.36 kPa) for the Fahrenheitscale. The temperature of the freezing point andboiling point of water changes with pressure.
-
8/11/2019 Process Operation
136/171
Celsius or centigrade scale (C) was proposed in mid1700s by Celsius (Sweden), who proposed thetemperature readings of 0 and 100 (giving a 100 scale) for the freezing and boiling points of pure waterat 1 atm.
Rankine scale (R) was proposed in the mid 1800s byRankine. It is a temperature scale referenced toabsolute zero that was based on the Fahrenheit scale,
i.e., a change of 1 F = a change of 1 R. The freezingand boiling point of pure water are 491.6 R and671.6 R, respectively at 1 atm, see Fig. 8.1.
-
8/11/2019 Process Operation
137/171
Kelvin scale (K) named after Lord Kelvin wasproposed in the late 1800s. It is referenced to absolutezero but based on the Celsius scale, i.e., a change of1C = a change of 1 K. The freezing and boiling point
of pure water are 273.15 K and 373.15 K, respectively,at 1 atm, see Fig. 8.1. The degree symbol can bedropped when using the Kelvin scale.
-
8/11/2019 Process Operation
138/171
-
8/11/2019 Process Operation
139/171
-
8/11/2019 Process Operation
140/171
Heatis a form of energy; as energy is
supplied to a system the vibration amplitudeof its molecules and its temperatureincreases. The temperature increase isdirectly proportional to the heat energy inthe system.
-
8/11/2019 Process Operation
141/171
A British Thermal Unit (BTU or Btu) isdefined as the amount of energyrequired to raise the temperature of 1
lb of pure water by 1F at 68
F and atatmospheric pressure. It is the most
widely used unit for the measurement
of heat energy.
-
8/11/2019 Process Operation
142/171
Heat Transfer Basics
Radiation
Convection
Conduction
-
8/11/2019 Process Operation
143/171
Radiation Transfer of heat by direct waves Direct from heat source or reradiated from reflecting
source Driving force is difference in absolute temperature to
4thpower
e: Emissivity : Stephan-Boltzmann (5.6697 x 10-8 W/m2.K4) A: area
-
8/11/2019 Process Operation
144/171
Convection
Heat transfer by flow of liquid or vapor Contact required Driving force is temperature difference Depends on fluid properties and geometry
-
8/11/2019 Process Operation
145/171
Conduction
Heat transfer within a substance Depends on thermal conductivity of
material Driving force is temperature difference
-
8/11/2019 Process Operation
146/171
InterpersonalSkills
-
8/11/2019 Process Operation
147/171
Communication Skills
Conflict resolution
Creative Thinking
C.V writing
Cover letter writing
Interview Skills (C.V Discussion) Team Working (Cooperation)
COMMUNICATION SKILL
-
8/11/2019 Process Operation
148/171
WHAT IS COMMUNICATION?
The word communicate comes
from the Latin word communicare meaning to share, or to make
common.
-
8/11/2019 Process Operation
149/171
7 communication Barriers1. Physical2. Perspective
3. Emotional4. Cultural Educational5. Language
6. Gender7. Interpersonal skills
-
8/11/2019 Process Operation
150/171
What Makes People Listen? Self-interest.
Who's telling it.
How it's told.
-
8/11/2019 Process Operation
151/171
Positive Speaking StylesWarm
Exciting
KnowledgeableCreativeInspiring
Honest
AuthenticFriendly
InterestingOrganizedConfident
Open
-
8/11/2019 Process Operation
152/171
Negative Speaking Styles
ARROGANTComplex
Unsure
IrrelevantMonotonous { dull}
Nervous
UnenergizedBelittling
Formal
StuffyClosed
Conflict resolution
-
8/11/2019 Process Operation
153/171
What is Conflict? Perception of mutual interference
A process that begins when goals of one partyare frustrated by another
Requires interdependence/interaction
-
8/11/2019 Process Operation
154/171
Sources of Conflict Conflict arises from resource scarcity Goals of parties are incompatible Other structural factors (size, routinization,
specialization, reward systems) Conflicting perceptions, ideas, or beliefs Differences between people Conflicting thoughts/needs within an individual Lack of communication (maybe)
-
8/11/2019 Process Operation
155/171
Goal of Conflict Resolution
Confront problems, communicate openly and
respectfully with someone of opposing opinion toprovide optimal patient care.
Strategies for ConflictResolution
-
8/11/2019 Process Operation
156/171
1. Withdrawal little or no significance to eitherparty (lose-lose)2. Forcing force outcome regardless of the
desire of one party (win-lose)
3. Conciliation giving in to preserve relationshipwith other party (lose-win)
4. Compromise concerned with both outcomeand relationship (?-?)
5. CONFRONTATION meet the problem headon (win-win)
-
8/11/2019 Process Operation
157/171
LEEN--A Model for Conflict Resolution
L- Listen E- Empathize E- Explain
N- Negotiate
-
8/11/2019 Process Operation
158/171
Confrontation is an Assertive means ofConflict Resolution
Respectful negotiation Effective Conflict resolution is what is right
not who is right. Never Aggressive. Use to explain
perspectives. If handled appropriately maybe an opportunity to educate the otherparty involved.
Creative Thinking
-
8/11/2019 Process Operation
159/171
Creative thinking barriers One line tram thinking
One and only one right answer Fear thoughts Conservative thinking (Lack of
imagination)
-
8/11/2019 Process Operation
160/171
Creative Thinking Techniques Brain storming
Mind mapping Lateral thinking( Edward de
Bono )
C.V writing
http://www.google.com.eg/url?sa=t&rct=j&q=Lateral%20thinking&source=web&cd=9&cad=rja&ved=0CF8QFjAI&url=http://edwdebono.com/debono/worklt.htm&ei=CGhkUZvJLum70QWOuoD4CA&usg=AFQjCNEcv4DxJ7iZ2bAMVsya6wOGi2LI-ghttp://www.google.com.eg/url?sa=t&rct=j&q=Lateral%20thinking&source=web&cd=9&cad=rja&ved=0CF8QFjAI&url=http://edwdebono.com/debono/worklt.htm&ei=CGhkUZvJLum70QWOuoD4CA&usg=AFQjCNEcv4DxJ7iZ2bAMVsya6wOGi2LI-ghttp://www.google.com.eg/url?sa=t&rct=j&q=Lateral%20thinking&source=web&cd=9&cad=rja&ved=0CF8QFjAI&url=http://edwdebono.com/debono/worklt.htm&ei=CGhkUZvJLum70QWOuoD4CA&usg=AFQjCNEcv4DxJ7iZ2bAMVsya6wOGi2LI-ghttp://www.google.com.eg/url?sa=t&rct=j&q=Lateral%20thinking&source=web&cd=9&cad=rja&ved=0CF8QFjAI&url=http://edwdebono.com/debono/worklt.htm&ei=CGhkUZvJLum70QWOuoD4CA&usg=AFQjCNEcv4DxJ7iZ2bAMVsya6wOGi2LI-g -
8/11/2019 Process Operation
161/171
It is targeted on the specific job It is carefully and clearly laid out It is informative but concise It is accurate in content, spelling and
grammar
Be honest
-
8/11/2019 Process Operation
162/171
Job Skills You Should List on YourResume Communication Interpersonal Skills Research and Planning
Organizational Skills Management Skills
Cover letter writing
-
8/11/2019 Process Operation
163/171
What is a cover letter?
A cover letter is a formal letter that
accompanies your rsum. Use it tointroduce yourself to potential employers,and to convince them that youre the right
person for the job.
-
8/11/2019 Process Operation
164/171
What information to include in your coverletter
Your cover letter should give an employer anidea of who you are, and explain what skillsyou could bring to the job.
-
8/11/2019 Process Operation
165/171
Content Paragraph 1: a positive, formal introduction
outlining how you heard about the opportunity,listing the documents you have enclosed (such
as your CV). Paragraph 2: outline why you are interested in
the role and the organization, demonstrating indepth research and mature reflection on howthe opportunity fits into your career plans.
http://www.prospects.ac.uk/example_cvs.htmhttp://www.prospects.ac.uk/example_cvs.htm -
8/11/2019 Process Operation
166/171
Paragraph 3: highlight your key skills andexperiences.
Paragraph 4: end positively outliningwhen you will be available for interview
Interview Skills (C.VDiscussion)
-
8/11/2019 Process Operation
167/171
Dress for the Job or Company Listen Don't Talk Too Much Don't Be Too Familiar Use Appropriate Language Don't Be Cocky Take Care to Answer the Questions
Ask Questions Don't Appear Desperate
Team Working (Cooperation)
-
8/11/2019 Process Operation
168/171
Team working Ethics:
Share information Emotional intelligence Minimum social hypocrisy Avoid Overlapping personal relationships
with labor relations
-
8/11/2019 Process Operation
169/171
Team working skills1. Listening2. Questioning
3. Persuading4. Respecting5. Helping
6. Sharing7. Participating
-
8/11/2019 Process Operation
170/171
Q & A
-
8/11/2019 Process Operation
171/171
Thanks