A secure network platform that collects, analyses and presents your local content and jobs data, providing a
solution to the challenges in supply chain monitoring and reporting, to meet project requirements
Contact us:
[email protected] | 03 9864 6700 | www.icnvic.org.au
Process Guidehttps://gateway.icn.org.au/mrs
This document has been designed to provide our ICN Analytics users with marketing
material, process flows, workflows and a high level user guide with notes throughout.
Please contact the ICN Analytics helpdesk for more information:
[email protected] | 03 9864 6700 | www.icnvic.org.au
• Local spend data and employment hours directly from suppliers
• Complex project structures are easily set up and effortlessly scalable
Collect
• Validates data• Performs local content
and employment calculations
• Maps forecasts• Highlights variances
Analyse
• Real-time monitoring• User specific visibility• Supply chain
variances are colour coded
• Dashboard and downloadable reports
Present
Workflows• Build the project• Decide permission levels of each package • Add new package(s)
• Details• Reporting• Commitment Targets• State Commitment Targets
• Add/edit Line Item Commitments • Item Description• Contract Value• ANZ Content• State Content• Total Hours• ANZ Hours• State Hours• Total New Hours• ANZ New Hours• State New Hours• WDP Training Hours• State WDP Training Hours• WDP Disadvantaged Hours• State WDP Disadvantaged Hours
Prime Contractor • Reporting
• LIDP Summary by:• Package• Report Date• Revision Date
• Local Content Forecast• Local Content Commitment• Spend To Date• Estimate To Complete
Workflows• Add/edit Package Estimate To Complete
• Select Date• For Each Item:
• Contract Value• ANZ Content• State Content• Total Hours• ANZ Hours• State Hours• Total New Hours• ANZ New Hours• State New Hours• WDP Training Hours• State WDP Training Hours• WDP Disadvantaged Hours• State WDP Disadvantaged Hours
• Add/edit Package Spend To Date• Report Date• For Each Item:
• Contract Value• ANZ Content• State Content• Total Hours• ANZ Hours• State Hours• Total New Hours• ANZ New Hours• State New Hours• WDP Training Hours• State WDP Training Hours• WDP Disadvantaged Hours• State WDP Disadvantaged Hours
Subcontractor
Straight out of the box, ICN Analytics will be prepopulated with your top-level Project package, identified during the ICN facilitated workshop.
The following steps will help you build the project structure and add/edit contents.
tier 1 Project and lower level
packages
ProcessHow to Log-in and Use the Menu
• Right click on any package and you will see the menu options available based on data entered and permission levels
• ‘Package Details’ must be completed before new packages can be added
• Line Item Commitments must be entered before Spend to Date (STD) and Estimate to Complete (ETC) can be submitted
• Reports cannot be downloaded until STD and ETC data is submitted
log-in from the top left of the homepage
https://gateway.icn.org.au/mrs
• Edit Package Content & Permissions• Add New Packages• Line Item Commitments
Step 1 Collect: Building Your Project
• Add/Edit Spend To Date• Add/Edit Estimate To Complete
Step 2 Analyse: Populating Your Project Data
• LIDP Summary by:• Package• Report Date• Revision Date
Step 3 Present: Reporting• Local Content Forecast• Local Content Commitment• Spend To Date• Estimate To Complete
How To...User Guide
this is a Package but you’ll probably
hear it called ‘box’• Edit Package Content & Permissions
• Add New Packages• Line Item
Commitments
Step 1 Collect: Building Your Project
Right click on any package and you will see the menu options available
for your permission levels
Create Package & Add PermissionsRight click on the Package Edit Package Details
The content populated here informs the reporting, commitments, targets and subcontractor requirements for the Project
• Package Details• Project Reporting Details
including :• AEE Baseline Hours• Reporting Period, Start and
End date• Package Commitment Targets• State Commitment Targets
this process is repeated
for each new Package
at least one State is
required, can add more
Edit Package Content & PermissionsRight click on the Package Edit Package Permissions
This process is repeated for all Packages.
Manage:• Edit package permissions
• Edit Package details
• Add/Edit Line Item Item
Commitments
• Add New Package
• Add/Edit Package Spend
To Date
• Add/Edit Package
Estimate To Complete
• View LIDP onscreen
• Download reports
Save:• Add/Edit Package Spend
To Date
• Add/Edit Package
Estimate To Complete
• View LIDP onscreen
• Download reports
Read:• Download reports
email password notifications are
sent to each new userEach level of
permission will effect the user’s
view
Add New Packages & CommitmentsRight click on the Package Add New Package
This process is repeated for all new Packages
• Package Details• Project Reporting Details• Package Commitment Targets• State Commitment Targets
‘Package Details’ must be
completed before new packages can be added
Add State Commitment TargetsRight click on the Package Add New Package State Commitment Targets
At least one State must be added to each Project
this process is repeated
for each new Package
• Content Value• Hours• New Hours• WDP Training Hours• WDP Disadvantaged Hours• Add More States
Edit Line Item CommitmentsRight click on the Package Add/Edit Line Item Commitments
• Item Description• Contract Value• ANZ & State Content• Total Hours• ANZ & State Hours• Total New Hours• ANZ & State New Hours• WDP Training Hours• State WDP Training Hours• WDP Disadvantaged Hours• State WDP Disadvantaged Hours
this process is repeated
for each new Package
here you’ll see any child
packagesANZ Hours must be less
than Total Hours
Populate the fields by scrolling left to right, green indicates work is on target whilst red is a miss against the Project Commitments
• Add/Edit Spend To Date• Add/Edit Estimate To Complete
Step 2 Analyse: Populating Your Project DataSubcontractors
to complete
an error has been identified, please check
Subbies will only see their
packages
Add/Edit Spend To DateRight click on the Package Add/Edit Package Spend To Date
• Item Descriptions will be prepopulated from the Commitments
• Effective date is when the data is accurate (ideally submission date however it is understood that is not always possible)
• You can use “Save for Later” to check your numbers before submitting
only submit when absolutely sure,
there is no turning back
Populate the fields with your STD data by scrolling left to right A Red highlight indicates a form validation error, please check data
Line Item Commitments must be entered before STD and ETC can
be submitted
Add/Edit Estimate To CompleteRight click on the Package Add/Edit Package Estimate To Complete
• Item descriptions will be prepopulated from the Commitments
• STD date aligns with Spend To Date submissions
• You can use “Save for Later” to check your numbers before submitting
only submit when absolutely sure,
there is no turning back
always choose
latest date
Populate the fields with your ETC data by scrolling left to right A Red highlight indicates a form validation error, please check data
• LIDP Summary by:• Package• Report Date• Revision Date
• Local Content Forecast• Local Content Commitment• Spend To Date• Estimate To Complete
Step 3 Present: Reporting
all users can view reports
aligned to their permission levels
STD and ETC data must be submitted to
generate reports
Available ReportsRight click on the Package Show LIDP Summary
Right click on the Package Download Local Content Forecast
Right click on the Package Download Local Content Commitment
Right click on the Package Download Spend To Date
Right click on the Package Download Estimate To Complete
All downloadable reports display the latest submitted data.
Each spreadsheet is fully editable and contains notes to explain red cell discrepencies
ensure you have enabled
editing on Excel spreadsheet
Displays the latest submitted data prior to the selected LIDP Summary revision date
Reports cannot be downloaded until STD and ETC data is submitted
Right click on the Package Download LIDP Summary PDF
For all technical enquiries please contact: ICN Analytics [email protected] 9864 6700