procedures for license application for hydropower ... · procedures for license application for...
TRANSCRIPT
Department of Electricity Development, HMG, Nepal,
in Collaboration with
United States Agency for International Development and
International Resources Group
June 2005
Procedures for LicenseApplication for Hydropower
Development in NepalA GUIDEBOOK
Table of Contents
Background
Acronyms
I. Application Process for Hydropower 1
Projects with Installed Capacity less
than 100 kW
II. Application Process for Hydropower 2
Projects with Installed Capacity from
100 kW up to 1000 kW
III. License Application Process for 5
Hydropower Projects with Installed
Capacity more than 1000 kW
TablesTable 1 License Application Fees 6
Table 2 Royalty Schedule 20
FiguresFigure 1 4
Application Process for Hydropower Projects with
Installed Capacity from 100 kW up to 1000 kW
Figure 2 9
Application Process for Production/Transmission/
Distribution Survey License
Figure 3 12
Process for Screening for IEE/EIA
Figure 4 13
Process for Conducting IEE
Figure 5 14
Process for Conducting EIA
Figure 6 19
Application Process for Production/Transmission/
Distribution License
BackgroundThis guidebook on Procedures for License Application for
Hydropower Development in Nepal is based on the Electricity Act
2049, Electricity Regulation 2050, Environment Protection Act
2053, Environment Protection Rules 2054, Water Resources
Act 2049 and Water Resources Regulation 2050. The purpose of
this guidebook is to present the license application processes in
a simplified and stepwise manner to assist hydropower developers.
For projects with installed capacity less than 1,000 kW, no
licenses are required. However, certain approvals/acceptance
of project details are necessary. For projects with installed
capacity greater than 1,000 kW, a survey license is required
to study the project. For such projects, separate licenses are
required for construction and operation of production,
transmission and distribution facilities.
Applications may be submitted in Nepali or English.
This guidebook presents a step-wise procedure of licensing
processes and includes the following:
� Application processes for hydropower projects with
installed capacities less than 100 kW, 100 kW to 1000
kW and greater than 1000 kW
� Process for screening for Initial Environmental Examination
(IEE)/Environmental Impact Assessment (EIA)
� Process for conducting IEE and EIA
While the guidebook has been prepared for hydropower
developers, we expect it to be useful to other stakeholders
in the hydropower sector as well.
If this guidebook contradicts the prevailing laws, the
provisions of the law shall prevail.
i ii
AcronymsAcronymsAcronymsAcronymsAcronymsDOED Department of Electricity Development
DWRC District Water Resources Committee
EIA Environmental Impact Assessment
HMG/N His Majesty's Government of Nepal
IEE Initial Environmental Examination
kV kilovolt
kW kiloWatt
kWh kiloWatt hour
MW MegaWatt
MOEST Ministry of Environment Science and
Technology
MOFSC Ministry of Forests and Soil Conservation
MOWR Ministry of Water Resources
PAN Permanent Account Number
PPA Power Purchase Agreement
TOR Terms of Reference
T/L Transmission Line
VDC Village Development Committee
iii
I. Application Process forHydropower Projects with InstalledCapacity less than 100 kW1.1.1.1.1. A project proponent (who may be a citizen or corporate
body) does not require a license for survey, construction,
and/or operation of production/transmission/distribution
of a hydropower project with installed capacity less than
100 kiloWatt (kW) (Section 3 of Electricity Act, 2049).
However, the proponent will have to obtain a permit from
the District Water Resources Committee (DWRC) prior to
the commencement of survey, construction and operation
of production/transmission/distribution facility (Water
Resources Act, 2049).
2. The proponent independently fixes the selling price of
electricity generated from the project in consultation with
the buyer(s).
1
1
Procedures for License Application for Hydropower Development in Nepal A Guidebook
I. Application Process forHydropower Projects with InstalledCapacity less than 100 kW1. A project proponent (who may be a citizen or corporate
body) does not require a license for survey, construction,
and/or operation of production/transmission/distribution
of a hydropower project with installed capacity less than
100 kiloWatt (kW) (Section 3 of Electricity Act, 2049).
However, the proponent will have to obtain a permit from
the District Water Resources Committee (DWRC) prior to
the commencement of survey, construction and operation
of production/transmission/distribution facility (Water
Resources Act, 2049).
2. The proponent independently fixes the selling price of
electricity generated from the project in consultation with
the buyer(s).
3
Procedures for License Application for Hydropower Development in Nepal A Guidebook
2
Procedures for License Application for Hydropower Development in Nepal A Guidebook
submit the following to the DOED in addition to the
information listed in (1) above:
a. Schedule for completion of Feasibility Study Report
b. Construction work schedule
c. Cost of development
d. Letter of intent regarding Power Purchase
Agreement (PPA) if sold in bulk to utility and/or a
letter of intent regarding Power Sales Arrangement
if sold to consumers isolated from the National Grid,
providing information on types and number of such
consumers.
e. Financial evidence to support construction of
the project.
Figure 1 summarizes the application process for hydropower
projects with installed capacity from 100 kW upto 1000 kW.
Steps to be taken by the proponent after obtaining
an approval letter from the DOED:
a. If the approval letter from the DOED is for survey only,
then the proponent starts surveying, and submits six
monthly progress report and Feasibility Study Report
(Rule 3 of Electricity Regulation, 2050) to DOED
b. If the approval letter from DOED is for survey, production,
transmission and distribution, the proponent:
� Completes survey, submits Feasibility Study to
DOED and starts construction
� Submits six monthly progress reports to the DOED
until construction is complete
II. Application Process forHydropower Projects with InstalledCapacity from 100 kW up to1000 kWA project proponent does not require a license for survey,
construction and operation of production/ transmission/
distribution of a hydropower project with installed capacity
from 100 kW up to 1000 kW (Section 3 of Electricity Act,
2049). However, the proponent shall submit the following
information before commencing the work of the project, in
the format as prescribed in Schedule 1 of Rule 3 of Electricity
Regulation, 2050. Submittal shall be made to the Secretary
of Ministry of Water Resources (MOWR) through the
Department of Electricity Development (DOED).
1. If the proponent's application is for survey of the project
only, the proponent shall submit the following
information to the DOED:
a. Desk study of the proposed project which includes
salient features (e.g., name of the water body),
scope of work and work schedule
b. Topographical map showing all the major
components of the project (in scale of 1:25000 or
1:50000)
c. Electricity distribution area and estimated number
of customers to benefit, if any
d. Information regarding other water uses in the area
e. Letter of recommendation addressed to DOED for
project development (survey, production,
transmission and distribution) from concerned
Village Development Committee (VDC)/Municipality
with a copy addressed to DWRC
f. Boundaries of the survey area with latitudes and
longitudes including VDC/Municipalities
2. If the proponent's application is for survey, production,
transmission and distribution, the proponent shall
5
Procedures for License Application for Hydropower Development in Nepal A Guidebook
4
Procedures for License Application for Hydropower Development in Nepal A Guidebook
III. License Application Process forHydropower Projects with InstalledCapacity more than 1,000 kWFour types of licenses may be required to develop a hydropower
project with installed capacity more than 1,000 kW:
A. Survey License (to study a project)
B. Production License (for construction and operation of
a production facility)
C. Transmission License (for construction and operation
of a transmission facility)
D. Distribution License (for construction and operation of
a distribution facility)
Licenses for construction and operation of the facilities
are only needed after the studies are completed under a
Survey License. A proponent requires a license for each
type of facility that is part of the proposed project.
A. Survey License
A survey license is required to conduct investigation at a
project site to assess its feasibility and preparation of an
IEE/EIA. A survey license provides the survey licensee
exclusive right to study the site for the term of the license
and provides a right-of-first-refusal to develop the project as
provided in the Electricity Act, 2049. Survey licenses are
needed to study production, transmission, and distribution
facilities and are termed Production Survey License,
Transmission Survey License, and Distribution Survey
License respectively. The maximum term of a Survey License
is 5 years.
The proponent shall submit three copies of application to
the Secretary of MOWR through the DOED in the format as
prescribed in Schedules 2,3,4 of Rules 4,5,6 of the
Electricity Regulation, 2050 respectively for Production
Survey License, Transmission Survey License, and
Distribution Survey License. The proponent shall also submit
an application fee of an amount equal to fifteen percent of
the license fee to the DOED as shown in Table 1 (Schedule
7
Procedures for License Application for Hydropower Development in Nepal A Guidebook
6
Procedures for License Application for Hydropower Development in Nepal A Guidebook
� Authorization letter appointing a contact person in
the company for DOED to correspond with regarding
the application.
� Contact address of applicant
� Details of other water uses in the requested survey
area like water supply, irrigation, water mill, etc or
details of licenses issued by DWRC regarding such
uses
� Details of in-house technical capability of applicant
to conduct survey or details of technical capability
of consultant in case consultant is to be hired.
2. Transmission Survey License
Proponent shall submit the following additional supporting
documents along with the application:
a. Preliminary route-map of electricity transmission line
(proposed main transmission line and alternative lines
in scale of 1:25000 or 1:50000)
b. Survey area including related VDCs/Municipalities
c. Need and purpose of the project
d. Total length of the transmission line
e. Transmission voltage and capacity
f. Maximum transmission load and types of consumers
g. Estimated cost of the project and cost break-down
of survey
h. Other requirements:
� In case of company - Certificate of registration,
Memorandum of Association, Memorandum of
Articles, PAN
� In case of individual - copy of applicant's
citizenship certificate
� Desk study report including detailed scope of work
� Work schedule
� Financial evidence to support survey activities
� Authorization letter appointing a contact person in
the company for DOED to correspond with regarding
the application.
� Contact address of applicant
11 of Rule 24 of the Electricity Regulation, 2050).
A Survey License is issued within 30 days of receiving
complete and adequate application package.
Figure 2 shows the application process for production/
transmission/distribution survey license.
1. Production Survey License
Proponent shall submit the following supporting documents
along with the application:
a. Topographical map showing all the major components
of the project (in scale of 1:25000 or 1:50000)
b. Survey area in longitude and latitude including
related VDCs
c. Estimated cost of the project and cost break-down
of the survey
d. Other requirements
� In case of a company - Certificate of registration,
Memorandum of Association, Memorandum of
Articles, Permanent Account Number (PAN)
� In case of an individual - copy of applicant's
citizenship certificate
� Desk study report including detailed scope of work
according to HMGN Guidelines for Study of
Hydropower Projects, 2003.
� Work schedule
� Financial evidence to support survey activities
Table 1: License Application Fees
Installed Capacity (kW) License Fees (Rs)
1,000 - 5,000 1,000
5,001 - 25,000 5,000
25,001 - 1,00,000 25,000
1,00,001 - 4,00,000 1,00,000
4,00,001 - 10,00,000 4,00,000
10,00,001 - above 10,00,000
Based on: Schedule 11 relating to Rule 24 of Electricity Regulation, 2050
9
Procedures for License Application for Hydropower Development in Nepal A Guidebook
8
Procedures for License Application for Hydropower Development in Nepal A Guidebook
� Details of in-house technical capability of applicant
to conduct survey or details of technical capability
of consultant in case consultant is to be hired.
3. Distribution Survey License
Proponent shall submit the following additional supporting
documents along with the application:
a. Map of the distribution area (geographical description,
present distribution system and preliminary sketch of
proposed distribution system in scale of 1:25000
or 1:50000).
b. Need and purpose of the project.
c. Estimated number and types of consumers to benefit
from the distribution system.
d. Location of purchase or acquired point.
e. Particulars relating to purchase and sale.
f. Estimated cost of the project and cost break-down
of survey
g. Other requirements:
� In case of a company - Certificate of registration,
Memorandum of Association, Memorandum of
Articles, PAN
� In case of an individual - copy of applicant's
citizenship certificate
� Desk study report including detailed scope of work
� Work schedule
� Financial evidence to support survey activities
� Boundaries of the survey area including
VDCs/Municipalities
� Information of concerned VDCs/Municipalities
within distribution line
� Authorization letter appointing a contact person in
the company for DOED to correspond with regarding
the application.
� Contact address of applicant
� Details of in-house technical capability of applicant
to conduct survey or details of technical capability
of consultant in case consultant is to be hired.
11
Procedures for License Application for Hydropower Development in Nepal A Guidebook
10
Procedures for License Application for Hydropower Development in Nepal A Guidebook
� Route Survey with alternative route
� Geotechnical Survey
� Design of Structure
� Project Optimization
� Financial and Economical Analysis
c. If found feasible, applies for Transmission License
3. Distribution Survey License
a. Submits quarterly progress reports to the DOED
(Environment Protection Rules, 2054)
b. Completes survey; submits Feasibility Study
Report including:
� IEE (If the distributing capacity of the project is
between 1-6 MVA or if the project falls under the
categories mentioned in Schedule 1 of Environment
Protection Rules, 2054)
� EIA (If the distributing capacity of the project is
greater than 6 MVA or if the project falls under the
categories mentioned in Schedule 2 of Environment
Protection Rules, 2054)
� Route Survey with alternate route
� Design of Structure
� Project Optimization
� Financial and Economical Analysis
c. If found feasible, applies for Distribution License
The screening process determining which power projects
(production, transmission, and distribution) require an
EIA or IEE study is shown in Figure 3, and processes for
conducting IEE and EIA are shown in f igures
4 and 5 respectively.
Steps to be taken by the proponent after obtaining
Survey License from the DOED:
1. Production Survey License
a. Starts actual physical work within three months.
b. Submits six monthly progress reports to the DOED [Rule
21(2) of Environment Protection Rules, 2054]
c. Completes survey; submits Feasibility Study Report
including:
� IEE (If the generating capacity of the project is
between 1-5 MegaWatt (MW) or if the project falls
under the categories mentioned in Schedule 1 of
Environment Protection Rules, 2054)
� EIA (If the generating capacity of the project is 5
MW or if the project falls under the categories
mentioned in Schedule 2 of Environment Protection
Rules, 2054)
� Topographical Survey
� Hydrological Survey
� Geotechnical Survey
� Design of Structure
� Project Optimization
� Financial and Economical Analysis
d. If found feasible, applies for Production License
2. Transmission Survey License
a. Submits six monthly progress report [Rule 21(2) of
Electricity Regulation, 2050]
b. Completes the survey; submits Feasibility Study Report
including:
� IEE (If transmission voltage level of the project is
between 33-66 kilovolt (kV) or if the project falls
under the categories mentioned in Schedule 1 of
Environment Protection Rules, 2054)
� EIA (If transmission voltage level of the project is
greater than 66 kV or if the project falls under the
categories mentioned in Schedule 2 of Environment
Protection Rules, 2054)
13
Procedures for License Application for Hydropower Development in Nepal A Guidebook
12
Procedures for License Application for Hydropower Development in Nepal A Guidebook
13
15
Procedures for License Application for Hydropower Development in Nepal A Guidebook
14
Procedures for License Application for Hydropower Development in Nepal A Guidebook
Survey License Renewal
Renewal of a survey license is possible if the original license
term was less than five years. The proponent may request
for renewal of a survey license prior to its expiry. The
proponent shall submit copies of all progress reports, a
complete description of the status of the remaining
activities, or a list of pending activities and a schedule for
completion of the activities. The proponent shall pay renewal
fee of an amount equal to ten percent of the license fee
prescribed in Schedule 11 of the Electricity Act, 2049.
B. Production License
A Production License is required to construct and operate
a production facility after completion of the survey. The
proponent shall submit three copies of the production
license applications to the Secretary of MOWR through the
DOED in the format as prescribed in Schedule 6 of Rule 12
of Electricity Regulation, 2050, and an application fee of
an amount equal to 33.33 percent of the license fee as
prescribed in Schedule 11 of Rule 24 of Electricity
Regulation, 2050 to the DOED. The maximum term of a
Production License is 50 years (Electricity Act, 2049).
The Production License is issued within 120 days of
receiving complete and adequate application package.
The proponent shall submit the following supporting
documents along with the application:
a. Feasibility Study Report including:
� Detailed description of the project
� Description of related transmission line to
evacuate power
� Approved IEE/EIA Report from concerned ministry
b. Names of partners in the project and type of their
association, full name and address of the person or
corporate body and its directors with whom the
ownership of the project shall be vested at last.
17
Procedures for License Application for Hydropower Development in Nepal A Guidebook
16
Procedures for License Application for Hydropower Development in Nepal A Guidebook
The proponent shall submit the following supporting
documents along with the application:
a. Feasibility Study Report including:
� Detailed description of the project
� Transmission voltage and capacity
� Approved IEE/EIA Report from concerned ministry
b. Names of partners in the project and type of their
association, full name and address of the person or
corporate body and its directors with whom the
ownership of the project shall be vested at last.
c. Mode of Finance (Detail Financing Plan)
� Estimated cost of the project
� Financial capability of the investors of the project
� Commitment of the financial institutions to be
involved directly in the project
� Percentage of liability of investor
� Equity and debt ratio
d. Agreement regarding sale and purchase of the power
(i.e., PPA)
e. Other requirements:
� Certificate of registration, Company's license,
Industrial Registration Certificate
� PAN
� Details of in-house technical capability of applicant
to implement construction works or the technical
capability of contractor/construction company in
case contractor/construction company is to be hired
for construction works.
Figure 6 shows the application process for the
transmission license.
D. Distribution License
A Distribution License is required to construct and
operate a distribution facility after completion of the
survey. The proponent shall submit three copies of the
distribution license applications to the Secretary of MOWR
c. Mode of Finance (Detail Financing Plan)
� Estimated cost of the project
� Financial capability of the investors of the project
� Commitment of the financial institutions to be
involved directly in the project
� Percentage of liability of investors
� Equity and debt ratio
d. Agreement regarding sale and purchase of the power
(i.e., PPA)
e. Other requirements:
� Certificate of registration, Memorandum of
Association, Memorandum of Articles, Industrial
Registration Certificate
� PAN
� Details of in-house technical capability of applicant
to implement construction works or the technical
capability of contractor/construction company in
case contractor/construction company is to be hired
for construction works.
Figure 6 shows the application process for the
production license.
C. Transmission License
A Transmission License is required to construct and operate a
transmission facility after completion of the survey. The
proponent shall submit three copies of the transmission
license applications to the Secretary of MOWR through the
DOED in the format as prescribed in Schedule 7 of Rule 13 of
Electricity Regulation, 2050, and an application fee of an
amount equal to 33.33 percent of the license fee to the DOED
along with the application as prescribed in Schedule 11 of
Rule 24 of Electricity Regulation, 2050. The maximum term
of a Transmission License is 50 years (Electricity Act, 2049).
The Transmission License is issued within 120 days of
receiving complete and adequate application package.
19
Procedures for License Application for Hydropower Development in Nepal A Guidebook
18
Procedures for License Application for Hydropower Development in Nepal A Guidebook
through the DOED in the format as prescribed in Schedule 8 of
Rule 14 of Electricity Regulation, 2050, and an application fee
of an amount equal to 33.33 percent of the license fee to the
DOED along with the application as prescribed in Schedule 11
of Rule 24 of Electricity Regulation, 2050. The maximum term
of a Distribution License is 50 years (Electricity Act, 2049).
The Distribution License is issued within 120 days of receiving
complete and adequate application package.
The proponent shall submit the following supporting documents
along with the application:
a. Feasibility Study Report including:
� Detailed description of the project
� Map of distribution area
� Distribution voltage and capacity
� Approved IEE/EIA Report from concerned ministry
b. Names of partners in the project and type of their
association, full name and address of the person or
corporate body and its directors with whom the
ownership of the project shall be vested at last.
c. Mode of Finance (Detail Financing Plan)
� Estimated cost of the project
� Financial capability of the investors of the project
� Commitment of the financial institutions to be involved
directly in the project
� Percentage of liability of investors
� Equity and debt ratio
d. Agreement regarding sale and purchase of the power (i.e.,
PPA)
e. Other requirements:
� Certificate of registration, Company's license,
Industrial Registration Certificate
� PAN
� Details of in-house technical capability of applicant to
implement construction works or the technical
capability of contractor/construction company in case
contractor/construction company is to be hired for
construction works.
Figure 6 shows the application process for the
distribution license.
19
21
Procedures for License Application for Hydropower Development in Nepal A Guidebook
20
Procedures for License Application for Hydropower Development in Nepal A Guidebook
Steps to be taken by the proponent after obtaining
Production/Transmission/Distribution License from
the DOED:
1. Production License
a. Starts construction work within 1 year
b. Completes financial closure within 1 year of license
issued date
c. Submits bi-annual progress report until construction
is completed
d. Testing and commissioning
e. Starts commercial operation
f. Pays Royalty
2. Transmission License
a. Starts construction work within 1 year
b. Completes financial closure within 1 year of license
issued date
c. Submits bi-annual progress report until construction
is completed
d. Testing and commissioning
e. Starts commercial transmission
3. Distribution License
a. Starts construction work within 1 year
b. Completes financial closure within 1 year of license
issued date
c. Submits bi-annual progress report until construction
is completed
d. Testing and commissioning
e. Starts commercial distribution
Table 2: Royalty Schedule
Royalty Up to 15 years After 15 years
Annual Capacity Rs. 100/kW Rs. 1000/kW
Royalty
Annual Energy 2 % of average 10 % of average
Royalty tariff/kWh tariff/kWh
generated generated
Based on: Schedule 11 relating to Electricity Act, 2049
22
Procedures for License Application for Hydropower Development in Nepal A Guidebook
For further details, please contact:
Department of Electricity Development
� Director General
� Deputy Director General (Privatization Division)
� Senior Divisional Engineer (Project Promotion Section)
� Senior Divisional Engineer (License Section)
Anamnagar, Thapagaon
Kathmandu, Nepal
Tel: +977 1 449-6800
Fax: +977 1 448-0257
Email: [email protected]
Website: www.doed.gov.np
Front Cover : BhoteKoshi Hydropower Project, Sindhupalchowk District, Nepal.
Back Cover : Kulekhani Hydropower Project, Makawanpur District, Nepal.
Photo Courtesy : BhoteKoshi Power Company Pvt. Ltd. and Department of Electricity Development.