problems of bridge bearings

Upload: jenniferballp

Post on 04-Apr-2018

236 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/31/2019 Problems of Bridge Bearings

    1/29

    1

    PROBLEMS OF BRIDGE BEARINGS ON SLOPING SPANS & AT ABUTMENTS

    By Dr. C V KAND

    SYNOPSIS

    PTFE bearings are extensively provided on flyovers which havegenerally some spans in gradient of 1 in 25 or flatter. If the movement of bearings is not stopped during construction, the deck is likely to slidedown gradient; similarly Roller rocker bearings and Elastomericbearings are provided extensively on the bridges. In case of high Abutments these are likely to deflect due to earth pressure. This will affect not only the bearings on abutments but also on the adjoining pier. These movements can also cause cracks in the deck besidesdamaging the bearings. Some case studies highlighting these effectsand rectification measures carried out are discussed in this paper.Following five case studies are brought out in this paper:-

    1. Narmada Bridge at Hoshangabad 2. Bairma Bridge3. Chambal Bridge4. Pipe Bridge at Wanchhoo Point near Indore with gradient 1/45. Flyover, gradient 1/25

    Case 4 is reported in IRC paper published in IRC Journal in 1997. It isreproduced since similar phenomenon is repeated on sloping spans.

    1. NARMADA BRIDGE AT HOSHANGABAD: -

    The bridge consists of 30 spans of 24.4m and two end spans of 12m. The

    bridge was opened to traffic in 1967. The piers are two circular piers connected by

    diaphragm, cast steel roller rocker bearing are provided for a superstructure

    consisting of prestressed girders with a cast in situ deck slab on it. The prestressed

    girders were cast in the yard and launched on the piers by a steel truss launching

    girder. The centering for the slab was fixed to the girder and removal of the

    centering was done by a specially made structural frame (see figures 1, 2 & 3). The 2

    end spans of 12 m have also girder section similar to prestressed girder but these are

    RCC girders, precast & launched in position. The girders are provided with cut steel

    circular roller bearing at one end and rocker bearing at the other end

    Foundations were open type foundations on rock; the abutment is located on

    higher bed level. On the abutment there are roller bearings, the abutment is of RCC

    A shaped two frames one below each girder and of spill through type.

  • 7/31/2019 Problems of Bridge Bearings

    2/29

    2

    The roller bearings at abutment were observed to have tilted since 1971 that

    is 4 years after completion. By 1980 the expansion gap at abutment closed

    completely. In 1981 the end RCC spans showed cracks.

    Investigations showed that A Frame of the abutment gradually tilted since

    this is founded on rock there is no possibility of any settlement. On closing of the

    expansion gap the deck started moving towards the pier and the expansion gap on

    the pier was also closed. Thus the deck started acting as a fixed beam and cracks

    were developed in the girder as shown in the sketch and photograph. The expansion

    joints consist of 2 angles and the mild steel plate above which can slide.

    Fig.1.1. Cracks in the girder

    1.1 Rehabilitation

    The expansion joint at abutment was removed. The span was lifted by 50mm.

    The roller bearings were removed and replaced by elastomeric bearings on the

    pedestal, the girders were lowered. The inner faces of the dirt walls behind the

    girders were chipped of to create an expansion gap of 50mm. the cracks in the

    girders were injected by epoxy resins. At abutment a curtain wall upto bed level and

    a apron were provided to prevent further tilting of the abutment. This work was

    done about 40 years ago and it is behaving well.

  • 7/31/2019 Problems of Bridge Bearings

    3/29

    3

    1.2 The lessons

    In respect of high abutments, it is advisable to calculate the deflection due to

    earth pressure and based on that provide adequate expansion gap. In the railway

    bridge on Mumbai- Delhi railway line the height of abutment for Betwa Bridge is

    about 18m, the expansion joint provided is more than 300mm that is why the

    deflection of abutment due to earth pressure did not affect the bearings and the

    adjoining spans. Cast in steel roller bearings are provided for this abutment. A sketch

    of this abutment is also given.

  • 7/31/2019 Problems of Bridge Bearings

    4/29

    4

    2. BAIRMA BRIDGE

    2.1 Structural Details:

    The bridge consist of continues span units of 20-25-20 m. The end span is

    15m simply supported with 3m cantilever on one side and a suspended span of 1.5m

    over abutment and tip of cantilever. The deck is a 4 girder system RCC deck on mild

    steel roller & rocker bearings. The piers are of mass concrete 1:3:6 with top width of

    1.2m. The abutment was of RCC frame of 4 twin columns each 225 X 375mm as a

    fully buried abutment, not designed for earth pressure and founded on soil at a level

    6.5m above the foundation of pier P10 which is provided with rocker bearings. At P2

    roller bearings were provided for span 1 and 2. The rocker bearing has only one

    rocker pin in centre.The sketch shows the extent of excavation pit for pier P1. The abutment

    frame was founded on filled up soil. With a view to allow traffic on the bridge, the

    earth work around abutment and end pier was completed before monsoon.

    Protection work of earthen bank could not be done before monsoon.

    2.2 Deformations:

    Several deformations were observed in this work:

    i. The abutment frame settled by 127mm during monsoon (observed in

    November). By next January the settlement was 165mm. Floating span (1.5m)

    was lifted to maintain road level.

    ii. Expansion gap on pier P2 closed and the same at articulation increased.

    iii. Earth work on river side of P1 was washed off during floods. On the other

    side (bank) it was 6m higher.

    iv. Top and bottom plate of rocker bearings on pier P1 displaced, maximum

    displacement was 51mm. displacements of four bearings were not uniform.

  • 7/31/2019 Problems of Bridge Bearings

    5/29

    5

    Fig.2.1. Tilting of end pier due to Earth Pressure

    Detailed study of the bridge and these deformations were carried out. Firstly

    the abutment frame on filled up soil settled. The pier P1 being subjected to

    differential earth pressure of 6m height and surcharge due to slope, deflected

    towards P2. Expansion gap on pier P2 was closed. On account of thermal movement

    of the span and continued deflection of pier, and since there was no space for

    further movement of span towards P2, this movement was reflected at P1 by

    shearing of rocker pin and displacement of its top plate from the bottom one.

    Simultaneously span 2 was also undergone thermal movement which pushed span 1

    towards bank, rocker pin having been sheared, no resistance was offered at P1.

  • 7/31/2019 Problems of Bridge Bearings

    6/29

    6

    Pic#2.1. Deflection of pier due to settlement of abutment frame

    Pic#2.2. Displacement of bottom plate from top and shearing of

    pin rocker bearing

  • 7/31/2019 Problems of Bridge Bearings

    7/29

    7

    2.3 Rectifications:

    Since pier P1 deflected on account of differential earth pressure, reverse

    conditions were created by digging a deep trench on bank side adjoining the pier

    and the earth was placed on the river side. When the trench was 7.5m deep, the pier

    re-deflected by 20mm. This trench was maintained for 2 months. Expansion gap at

    P2 was opened up to 43mm. however, there was no rectification of top and bottom

    plate of rocker bearing, indicating that the pin was sheared off and it acted as a

    sliding bearing. The earth work around the pier was made in proper slopes, pitched

    and toe wall were provided.

    It was also observed that the RCC abutment frame buckled and damaged.

    Crib type abutment and retaining block with RCC cribs frames filled by boulders wasprovided. This was expected if settled additional layer of crib will be added and the

    road formation level will be maintained. This work was done in 1968. During

    seventeen years, the crib wall was observed to have settled by 150mm & thereafter

    it is reported to be stable. The rocker bearings are rectified as shown in the sketch.

    2.4 Indications:

    This case study has brought out following important points:

    2.4.1 Slopes of earth work around abutment and its protection work must be designed

    as carefully as the design of main structure and completed before opening the

    bridge to traffic.

    2.4.2 Abutment structure, even if it is buried, must be designed for earth pressure

    from bank side since the earth on river side is vulnerable for being washed during

    floods. In important bridges, abutments are designed for all around scour

    conditions. Latest IRC-78 stipulates this provision.

    2.4.3 The foundation of non-load bearing abutment may be kept at level higher than

    the foundation level of pier but the level should be such that the founding soil of

    abutment is not disturbed due to excavation for pier foundations.

    2.4.4 Based on these observations two design criteria have been evolved:

  • 7/31/2019 Problems of Bridge Bearings

    8/29

    8

    a.) If the piers are provided on well foundations, the foundations level of non-

    load bearing abutment shall not be higher than the level of the bottom of

    well cap of adjoining pier. Open excavation for wells shall be limited to the

    bottom of well cap.

    b.) In open foundations, the difference of foundations level of the abutment and

    the adjoining pier shall not be more than

    h = 1 L for every hard soil like murrum.

    = L / 1.5 for Medium type of soils.

    = L / 2 for soft soil.

    Where, h = difference of level between the foundation levels of abutmentand adjoining pier.

    L = clear horizontal distance between the footing of pier &

    abutment.

    2.4.5 Wider expansion gap should be provided on abutments which are likely to settle

    and deflect due to earth pressure. 50mm or larger gap in place of usual 25mm

    gap is recommended. It is also advisable to provide earthwork behind abutment

    to a length of 30m before casting end span supported on abutment. This

    stipulation is also given in tender conditions. With this provision, a large part of

    deflection of abutment will take place before laying the span.

    2.4.6 It is desirable to provide roller bearings at abutment or end pier.

    2.4.7 Each rocker bearing must be provided with minimum 2 pins.

    2.4.8 Before opening a bridge to traffic, it must be observed that all expansion gaps

    are free and the bearings are free to slide or permit angular movement of deck.

    3. CHAMBAL BRIDGE:

    3.1 Details of the Bridge and Accident:

    The bridge is provided with continues RCC trough slab with span arrangement

    15 18.75 15 m. Depth of slab is 1.1m. RCC roller bearings are provided on end

    piers and one intermediate pier and RCC rocker at one pier in the unit.

  • 7/31/2019 Problems of Bridge Bearings

    9/29

    9

    Concreting of the deck was being done in layers continuously. First layer of

    45cm was laid in entire length of 48.75m in 24 hrs. Second layer of 45cm was done in

    one end span and 1.5m length of central span. At this stage the carpenters attending

    to centering heard a cracking sound and they jumped out from the location.

    Suddenly a loud cracking sound was heard and the whole unfinished structure came

    down. The end span which was concreted to 90cm depth, collapsed and the green

    concrete was reduced to pieces. Other end spans was pulled out from the abutment

    support and it came down. The middle span sagged down, the forms were broken

    and the green concrete collapsed. The reinforcement cage of central span was

    hanging in the catanary shape between P1-P2 over crushed timber centering; which

    however, did not collapse fully.

    3.2 Details of construction:

    The figure giving details of centering will show that the bed level in the centre

    of river is nearly 12m below the bed level at abutment. These levels were disturbed

    during open foundation for piers and the abutment. The bed levels were made up by

    providing embankment in steps between piers and centering was erected on filled

    up soil between spans 1, 2 & 3 respectively. The width of bank along river was 10m

    and side slopes of 1.5 to 1. It was reported to have been properly consolidated. The

    centering was of cut timber sections 10 X 15cm and these were laid on wooden

    sleepers.

    3.3 Causes of Failures :

    Investigations showed that the earthen embankment, supporting staging

    settled. The pier which was subjected to differential earth pressure with surcharge

    of centering load appears to have tilted. Normally bearings are clamped during

    concreting of deck. These bearings were not clamped at abutment & piers.

    Due to settlement of props in span 3, the shuttering with steel cages and

    concrete in side slipped off from the unclamped roller bearings over P3 and it came

  • 7/31/2019 Problems of Bridge Bearings

    10/29

    10

    down forcibly due to heavy load of 90cm deep green concrete. The centering of span

    3 damaged almost completely, and the reinforcement cage hung along the face of

    Fig.3.1. Failure of centering by not clamping bearings during concreting.

    P2 and was pulled in towards span 2 over the unclamped roller bearing of P2.

    The collapse of span 3 induced horizontal forces on continuous decking. Span 2 tried

    to move towards P1. Since rocker bearing is provided on P1, span 2 sagged down.

    Upper stage of centering in span 2 crumbled. The sag is nearly 3m. The pull damaged

    rocker bearing on P1. The anchor bars in the bearing were pulled out from RCC pier

    cap. Span 1 was pulled towards P1. The end of span 1 at abutment slipped and came

    down, forcibly, damaging the centering and the shuttering.

    3.4 Indications :

    This case study has brought out the following points:-

    a.) Earthen banks should not be allowed for erection of staging of bridges. If the river

    bed is slopping, it should be cut in steps and props erected on cut portion. It is

  • 7/31/2019 Problems of Bridge Bearings

    11/29

    11

    advisable that wooden piles are provided below props, if the bed contains soil or

    sand.

    b.) Piers of bridges should not be subjected to one side earth pressure if these are not

    designed for such a condition.

    c.) Bearings must be clamped before concreting of deck.

    d.) Centering of continuous deck must be absolutely free from settlement.

    Pic#3.1. Failure of centering.

    4. REHABILITATION OF PIPE BRIDGE:

    4.1 Details of the Bridge:

    Narmada water supply scheme for Indore town was taken up in 1972. The

    pipe line passes through Vindhyan Mountain ranges. Water of Narmada River is

    lifted by about 242m. Five pumping stations are established to lift water by 242m.

    Thereafter water is supplied by gravity to Indore and Mhow town. The pipe is

    1200mm dia. steel pipe 8mm thick. A pipe bridge is provided in a valley with 3 spans

    of 22m c/c and 2 spans of 20m c/c, two RCC girders, each span having 5 saddles on

  • 7/31/2019 Problems of Bridge Bearings

    12/29

  • 7/31/2019 Problems of Bridge Bearings

    13/29

    13

    Fig.4.2. Wanchoo point bridge with pedestals

    Fig.4.3. Wanchoo point bridge

  • 7/31/2019 Problems of Bridge Bearings

    14/29

    14

    Fig.4.4. Wanchoo point bridge

    b.) Span no. 2 with one end resting on pier P1 settled by 150mm and RCC bracket at

    end of span crushed. The deck also slid by 200mm towards hill side. Drawing of

    rocker bearing does not show any central pin. Thus at rocker end on P1, the

    girders were free to slid. The bearings were distorted. The triangular concrete

    brackets at inclined beams above bearings have cracked in all spans.

    Investigations showed that there is no reinforcement in bracket. Thus due tocrushing of bracket at pier 1 the girders settled and in that gradual process deck

    slid towards hill side. The pier P1 also tilted on that account. Since the pipe line is

    continuous on all spans, uneven supports on saddles caused due to horizontal

    and vertical moment of deck of span 2 appear to have caused some lateral sag in

    pipe line and the bridge deck also.

  • 7/31/2019 Problems of Bridge Bearings

    15/29

    15

    c.) Pier number one has tilted by 5mm towards hill side and this caused lateral

    deflection of deck in gradient. The pipe line is also likely to have developed

    similar effects.

    d.) At saddles in span 2, large gaps developed between the socket and the pipe at

    the one end. Thus pipe is partially supported on socket in span 2.

    4.3 Rectification:

    Following procedure and sequence has been adopted for rectification of defects.

    a. Repair of concrete: The honeycombs in girders were rectified by grouting mixture

    of cement mortar and 15% polymer.

    b. Strengthening of piers and replacement of bearings: Piers were strengthened by

    encasing these in RCC column. A pier cap with steel structural grillagereinforcement was laid as shown in sketch at a level where about 400mm

    minimum vertical space is available to place hydraulic jacks. It was designed to

    take point loads of jacks. The girders of span 3, 4, 5 were supported on jacks and

    raised by 3mm. The existing bearings and part of old pier projecting above was

    dismantled. Then steel plate pedestals were filled in concrete and elastomeric

    bearing of size 250 X 250 X 52mm was placed on it. The soffit of existing girder

    where brackets were provided was dismantled and new steel connectors were

    welded with main steel in girders. Thus the triangular bracket was adequately

    reinforced. A flat steel plate was fixed to bracket and it was concreted and

    grouted. The pedestal with bearings was laid in position so that it touched the

    steel plate of bracket. The jacks were lowered by 3mm and full contact was

    established between bracket and bearings. Two 100 Ton capacity jacks were

    used to lift deck.

    c. Pier No. 1: At pier No.1 both vertical jack 100 Ton capacity and horizontal jack (10

    Ton capacity) with transverse were provided. The arrangement is seen in

    photographs. Lifting was done in five stages. Vertically 30mm and horizontally

    40mm in each stage. This lifting presented lot of difficulties and obstructions.

    These had to be removed. The pressure developed at vertical jack was 25 tons

    before lifting and horizontal jack was 5 tons before sliding. When pressure was

  • 7/31/2019 Problems of Bridge Bearings

    16/29

    16

    increased, it was noticed that this can happen due to some obstructions. When

    obstructions were removed movement was smooth.

    4.4 Further Problems:

    It was expected that the large un-uniform gap between the pipeline and saddle will

    be fully closed on restoring span and at pier 1 end. But this has not happened at two

    sockets in span 2, three sockets in span 3, one socket in span 4 and two in span 5

    (there are 5 sockets in each span). Thus out of 5 X 5 = 25 sockets, support at 8

    sockets are not even. The gap is from 8mm to 30mm. Contact surface on circular

    saddle is 1800mm. Out of this at present contact is only in half of length at abovepoints where uneven gap exists. The gaps are on downhill side in span 2, 3 & 4 and

    uphill side in span 5. This could happen if the centre line of pipe and the same of

    saddle i.e. the bridge are not in one vertical plane. It appears that in span 2, 3 & 4

    the pipe line has sagged towards hill side in lateral plane upto expansion joint and

    the span 5 i.e. beyond expansion joint the lateral sag is towards downhill side.

    Movement due to thermal variations must be allowed in pipe line. Therefore, it is

    proposed to provide Neoprene pads in the annular gap (one or two pads) and

    provide Polysulphide in the remaining gap, so that proper contact of pipe line and

    saddle is established in a circular contact line of 1.8m.

    Pipe Bridge is not a road bridge. It is a pipe plus foot bridge. Yet the types of distress

    which have occurred in this bridge have also occurred in many road bridges and

    therefore this case is brought out in the paper. The thickness of pipe is 8mm and

    design calculations show that it can safely stand a span upto 30m. Therefore, the

    uneven partial support at saddles had not damaged the pipe line. Uneven supports

    may develop strains in the pipe and therefore, restoration is necessary.

  • 7/31/2019 Problems of Bridge Bearings

    17/29

    17

    5. SOLID SPAN OF A FLYOVER WITH SPAN IN GRADIENT :

    5.1 Structural Details

    Length 190 m

    Width 10m

    Span Arrangement: - 5 spans of 25m and 2 spans of 20 m.

    Foundations: - Open foundations approximately 4.0m below ground level and laid in

    rock.

    Piers: - single circular RCC piers 2.5m dia. with cantilevered pier cap.

    Deck Structures prestressed concrete box with cantilever deck slab on both sides.

    7.5m wide 2 lane road way and 1.5m footpath on one side. The box is single cell with

    inclined ribs. Deck is continuous over three spans or two spans. Central 2 spans of

    20m has voided RCC slab over the existing road and is level. 25m spans are in

    gradient of 1/25.

    Bearings POT PTFE bearings.

    Fig.1 gives General Arrangement Drawing and the cross section of the deck.

    Fig.2 gives the layout of the bearings.

    5.2 Mishap

    PSC box girder between P3-P4 slid down in traffic direction. The bearing pins of the

    top plate sheared off. There is no displacement of the box girder in transverse

    direction. No cracks were observed in the box structure.

    5.3 Causes of Distress

    It appears that the deck would slide if the pins provided at the 4 corners of PTFE

    bearing to prevent displacement of the top plate from the bottom plate during

  • 7/31/2019 Problems of Bridge Bearings

    18/29

    18

    Fig.5.1 Bridge with sloping deck. Continuous spans

    Fig.5.2. Bearing arrangement of a bridge in gradient.

    construction are broken. It is customary to provide such pins to avoid movement of

    deck during construction. In this case the movement could be along slope. The box

    structure was designed as a simply supported structure with the deck slab. The

  • 7/31/2019 Problems of Bridge Bearings

    19/29

    19

    continuity was to be given in the deck slab; however, on completing the box

    structure continuity of the slab was not provided at P2 & P3 and that is why the deck

    could slide. Sliding was 454mm in span P3-P4 towards P3

    5.4 Rehabilitation

    The centering of the spans P1 to P4 was not removed. A detailed procedure for

    carrying out the rehabilitation consisted of the following operations:

    5.4.1 To provide wooden blocks at the supports on P3 & P4 so that the span does not

    slide further and ensure that the existing centering is strong enough.

    5.4.2 To provide continuity of deck slab on P2 so that during the operation of re-sliding

    the jack force will be on spans P1-P2 & P2-P3. This was done, however, the gap

    on P3 is reduced by 454mm therefore it was not possible to complete this gap

    slab.

    5.4.3 To lift the deck at P4 & P3 by about 150mm by vertical jacks and retain it in that

    position by timber blocks. The weight of the deck is about 450 Tons. Therefore, 4

    jacks of 150Tons capacity are required to lift the deck.

    5.4.4 To slide back the deck on P3 & P4 by horizontal jacks. 2 such jacks with a capacityof 40 Tons operated by a combined manifold were used. It took nearly half a day

    in making preparations, actual pushing took about half an hour. For sliding back

    long steel plate was specially manufactured and was kept on jack position below

    the deck.

    5.4.5 Before the pushing the top plate of PTFE bearing at both ends were removed.

    Then the bottom plate was also removed. The bolts of the plate were unscrewed

    from the pedestal. Holes of the bolt were filled up by epoxy mortar.

    5.4.6 It was earlier proposed to provide PTFE bearing of earlier design at this location

    but this would involve manufacturing of the bearing and fixing the top plate to

    the deck and bottom plate to the pedestal. The manufacturers informed that

    manufacturing of similar four bearing would require 8 weeks time. Considering

    the risk in keeping the disturbed deck for a long time is likely to create more

    disturbances such as slipping of temporary wooden blocks, disturbances of

  • 7/31/2019 Problems of Bridge Bearings

    20/29

    20

    centering etc. therefore investigations were carried out to ascertain whether

    Neoprene bearings can be provided, these investigations showed that if

    Neoprene bearings are provided, the section of foundations may not be safe and

    therefore it was decided to strengthen the section of footing by providing

    additional concrete block of 1.2m over the existing footing so that reaction of

    the foundation is reduced and the reinforcement provided in the foundation is

    also safe. The reinforcement in the pier was also checked and found to be safe. A

    sketch giving strengthening of footing is shown in Fig.5.7. Neoprene Bearings

    manufacturer assured that he can manufacture & supply the bearings within one

    week.

    5.4.7

    The designs of neoprene bearings were also checked. It was noticed that thebearings are not safe for minimum load condition. It was also noticed if

    continuity of deck slab is to be given on pier P3 it will have effect on elastomeric

    bearings on P3 and P4. This will induce movement of 20mm at P4 and 10mm at

    P3. If movement of 20mm is considered the elastomeric bearings cannot be

    designed for minimum load conditions. Therefore elastomeric bearings on P3 &

    P4 have been designed by considering free support at P3 & p4. It is therefore not

    possible to give continuity at P3, therefore expansion joint will be provided on

    pier P3. Thus change of PTFE bearing to elastomeric bearing has caused 2

    modifications a.) Strengthening of footing b.) No continuity at P3.

    5.4.8 The bottom of the deck structure over the location of bearing has to be leveled.

    If it is not level steel plate with different thicknesses at the ends have to be

    provided so that the top will match with the bottom of sloping deck and the

    bottom of the plate will be level on the bearing. It was observed that the top of

    the pedestal is level. A sketch showing these plates is also enclosed.

    5.4.9 The deck was slid and brought correctly over the locations of pedestals by

    horizontal jacks. It was checked and rechecked to ascertain the correct location

    longitudinally and laterally.

    5.4.10 The entire deck was supported on jacks at both ends and the temporary timber

    blocks were removed. The elastomeric bearings were placed at correct position

  • 7/31/2019 Problems of Bridge Bearings

    21/29

    21

    with the bottom fix to the pedestal by epoxy. The end of the deck on P3 was

    lowered down and centrally spaced over the bearings by placing the top steel

    plate with different thicknesses at both ends and make the bottom of the plate

    on elastomeric bearing level.

    5.4.11 The same operation was carried out on P4. Top plate was extended on gap side

    (on pier) to check the level and ensure that it is perfectly horizontal. On

    completing this operation of lowering and placing the deck on the bearings and

    ensuring that it is level, several checks were carried out to ensure the level. An

    insignificant difference of 1mm was noticed.

    5.4.12 A question was raised whether it is correct to provide different type of bearings

    in the same bridge. This has been done in Hasdeo Bridge at Chappa which wasrehabilitated in 1970 since the foundations of the bridge gave way during floods.

    In the rehabilitation work 5 different types of bearings were provided and the

    case in reported in Paper No. 395 (1989). During last 40 years the structure is

    behaving well. Therefore there is nothing wrong in adopting different types of

    the bearings in the same bridge. Photo graphs and sketches of various operations

    are enclosed. P3

    Fig.5.3. Rehabilitation of sloping bridge Stage-1

  • 7/31/2019 Problems of Bridge Bearings

    22/29

    22

    Fig.5.4. Rehabilitation of sloping bridge Stage-2

    5.5 Following Equipments was employed at site to accomplish the rehabilitation:

    a. Hydraulic Jacks to lift the deck 4 X 150 T = 600 Tb. Hydraulic Jacks to slide the deck 2 X 40 T = 80 Tc. Long sliding steel plate to slide deck.d. Two steel plates at each bearing with varying thickness to make contact level

    on bearings.e. Manifold for operating two jacks together.

    5.6 The entire work was started on 9 th April 2012 and completed on 12 th April 2012.

    Fig.5.5. Rehabilitation of sloping bridge Stage-3

  • 7/31/2019 Problems of Bridge Bearings

    23/29

    23

    Fig.5.6. Rehabilitation of sloping bridge Stage-4

    Fig.5.7. Additional concrete block over the footing.

  • 7/31/2019 Problems of Bridge Bearings

    24/29

    24

    Fig.5.8. A steel plate with varying thickness fixed to the deck at bearings to make levelsupport.

    Pic#5.1 Dislodged Span

  • 7/31/2019 Problems of Bridge Bearings

    25/29

    25

    Pic#5.2. Lifting Jack

    Pic#5.3. Pushing Jack

  • 7/31/2019 Problems of Bridge Bearings

    26/29

    26

    Pic#5.4. Placement of sliding assembly

    Pic#5.5. Horizontal movement of deck

  • 7/31/2019 Problems of Bridge Bearings

    27/29

    27

    Pic#5.6. Neoprene bearing with steel plate at top, at the bearing location

    Pic#5.7. Steel plate and Neoprene bearing fixed with Epoxy Mortar.

  • 7/31/2019 Problems of Bridge Bearings

    28/29

    28

    6. Lessons from the Mishaps

    Lessons learned from case 1 to 4 above are reported in last Para of each case. The

    provisions made in the specifications for roads and bridges of ministry of road

    transport and highways contained in Para 2002. Similarly provisions made in the

    standard specifications in the code of practice in section 9 of IRC-83 are seen. These

    contain the following:-

    6.2.1 The bottom of girder to be received on the bearings is plain at the location of

    these bearings.

    6.2.2 During concreting of girders the bearings shall be held in position securely by

    providing temporary connection between the top and the bottom plates and

    clamps at roller and plate bearings.6.2.3 For bridges in gradient the bearing plate shall be placed in horizontal plane.

    6.2.4 On completing of the work clamps at bearings must be removed. If this is not

    done the structure cracks. We have observed that in one Yamuna bridge the

    clamps provided at the bearings during construction were not removed for more

    than 10 years, causing several cracks in the cross girder. A case of not providing

    clamps during concreting collapsed the structure during construction. This was

    observed in Chambal Bridge (case-3) & Ambika Bridge in 1953.

    6.2.5 The design of bearing is done by the manufacturer of bearings. He should record

    important instructions as mentioned above in the drawing (about placing and

    removal of clamps).

    6.2.6 In case of sloping spans the pin between top and bottom plates should be strong

    enough to prevent the movement of plates during construction. If the structure

    is designed as continues only in slab the continuity must be established

    immediately on completing the deck of individual span.

    6.2.7 Inadequate clamping arrangements of the sliding bearings during construction is

    the main cause of this mishap mentioned in Para 5.

  • 7/31/2019 Problems of Bridge Bearings

    29/29

    29

    7. Conclusions

    7.1 We have brought out actual field problems of mishaps of bearings laid on

    deflectable abutments and laid on sloping spans. There appears to be need to

    incorporate the findings in Para 6 in the specifications of bridges.

    7.2 It is absolutely necessary ascertain the causes of distresses before taking up the job

    of restoration.

    7.3 In bridge works expansion joints are proprietary products which have some amount

    of vulnerability since these are directly hit by the moving traffic. Expansion joint is

    therefore called the pulse of the bridge and any trouble in foundations,

    substructure, bearings and superstructure is reflected in the expansion joint.

    Similarly bearings are also important units and any trouble in the units can causemishap as had happened in many bridges. It is advisable that bearings and expansion

    joints are fixed by the manufacturers of these products.

    7.4 The technology has advanced so much that structural distresses can be restored.

    Such restorations have been done successfully by the author in several bridges,

    building and water towers.

    7.5 The rehabilitation project cannot be successful unless there is active involvement

    and cooperation between the owner/client, the contractor and Rehabilitation

    consultant

    7.6 Although one case (No.4) is reported in IRC paper, it is repeated again since such

    mishaps of bearings on sloping spans or mishaps in bearings at deflectable

    abutments have occurred at many places, although not reported in lifetime. There is

    need to modify the specifications for design and construction of bearings and also

    insist upon the calculation deflection of abutment and make suitable provisions in

    abutment cap size.