problems and countermeasures of the quality of …
TRANSCRIPT
![Page 1: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/1.jpg)
PROBLEMS AND COUNTERMEASURES OF THE
QUALITY OF FABRICATED STEELWORK IN
THAILAND BUILDING PROJECTS
BY
WATCHARAPHON SAEGOW
A THESIS SUBMITTED IN PARTIAL FULFILLMENT OF THE
REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE
(ENGINEERING AND TECHNOLOGY)
SIRINDHORN INTERNATIONAL INSTITUTE OF TECHNOLOGY
THAMMASAT UNIVERSITY
ACADEMIC YEAR 2018
Ref. code: 25615922040299ZBX
![Page 2: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/2.jpg)
PROBLEMS AND COUNTERMEASURES OF THE
QUALITY OF FABRICATED STEELWORK IN
THAILAND BUILDING PROJECTS
BY
WATCHARAPHON SAEGOW
A THESIS SUBMITTED IN PARTIAL FULFILLMENT OF THE
REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE
(ENGINEERING AND TECHNOLOGY)
SIRINDHORN INTERNATIONAL INSTITUTE OF TECHNOLOGY
THAMMASAT UNIVERSITY
ACADEMIC YEAR 2018
Ref. code: 25615922040299ZBX
![Page 3: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/3.jpg)
![Page 4: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/4.jpg)
ii
Abstract
PROBLEMS AND COUNTERMEASURES OF THE
QUALITY OF FABRICATED STEELWORK IN THAILAND
BUILDING PROJECTS
by
WATCHARAPHON SAEGOW
Bachelor of Engineering (Civil Engineering),
Sirindhorn International Institute of technology, Thammasat University, 2015.
Master of Science (Engineering and Technology),
Sirindhorn International Institute of Technology, Thammasat University, 2018.
Nowadays, pre-engineered steel buildings (PEB), which are imported from foreign
countries, become popular for the construction of factories and warehouses in Thailand.
In most of the PEB projects in Thailand, the fabricated parts imported from foreign
countries, have not been properly examined by the concerned Thai authorities or the
third party. This study collects information about imported PEB steel structures. The
method consists of site visiting and interviews of personnel in charge of design and
construction of the imported PEB. In order to perform a comparative study on the
quality of fabricated structures, international inspection standards for fabrication are
adopted in this study. From the inspection results at five imported PEB construction
sites, some defects in the steel structures are found as follows: 1) welding defects such
as undercut, overlap and porosity, 2) defects in anchor bolt such as remaining screw
length less than position of nut, 3) defects in the fabricated part, due to error of
fabrication process such as distortion of area surrounding the holes and insufficient of
coating thickness. The proposed countermeasures for quality control of fabricated steel
structures were divided into two schemes as follows: (a) fabricator accreditation to
classify the fabricator according to their capabilities. (b) checklist for inspection the
quality of fabricated steel structures.
Keywords: Pre-Engineered Steel Buildings (PEB), Steel Structures, Inspection and
Defects
Ref. code: 25615922040299ZBX
![Page 5: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/5.jpg)
iii
Acknowledgement
First of all, I would like to express my gratitude to my upmost appreciation and
sincere gratitude to Assoc. Prof. Dr. Taweep Chaisomphob, my research supervisor,
for his guidance, and valuable suggestions for my research study.
Besides my mentor, I would like to acknowledge the rest of my thesis
committee: Asst. Prof. Dr. Pakawat Sancharoen and Col. Asst. Prof. Dr. Nuthaporn
Nuttayasakul, for their knowledge, encouragements, and comments which motivated
me to widen my knowledge to improve thesis.
Finally, I would like to thank all of my senior students, friends, and companies
(PEB, ATAD, Kirby and BMB) for their assistance, time, strength, and encouragement
which always support me during the tough time. And special thanks go to my parents
for their supports and encouragements in moving forward and completing the thesis.
Ref. code: 25615922040299ZBX
![Page 6: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/6.jpg)
iv
Table of Contents
Chapter Title Page
Signature Page i
Abstract ii
Acknowledgements iii
Table of Contents iv
List of Tables vii
List of Figures viii
1 Introduction 1
1.1 General 1
1.2 Statement of Problems 1
1.3 Objectives of study 2
1.4 Scopes of study 2
2 Literature Review 3
2.1 Steel Structures Damage and Defect 3
2.1.1 Corrosion Damage 3
2.1.2 Welding Defect 3
2.2 Inspection and Evaluation Standard 4
2.2.1 Welding Inspection 4
2.2.2 Bolt Inspection 8
2.2.3 Coating Inspection 9
3 Methodology 10
3.1 Maintenance Personnel Interview 10
3.2 Inspection and Evaluation on Steel Structure 10
3.2.1 Welding Inspection Criteria 11
3.2.1.1 Welding Inspection Equipment 11
Ref. code: 25615922040299ZBX
![Page 7: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/7.jpg)
v
3.2.2 Bolting Inspection Criteria 11
3.2.3 Steel Coating Inspection Criteria 12
3.2.3.1 Steel Coating Inspection Equipment 15
4 Results and Discussion 16
4.1 New Steel Structures (PEB) 16
4.1.1 Data Collection 16
4.1.2 Fabrication Process 16
4.1.3 Material Specification 17
4.1.3.1 Visiting Construction Sites of Pre-Engineered
Buildings (PEB) 17
4.1.3.1.1 Site No.1 18
4.1.3.1.2 Site No.2 20
4.1.3.1.3 Site No.3 22
4.1.3.1.4 Site No.4 24
4.1.3.1.5 Site No.5 28
4.1.3.2 Inspection Result 30
4.1.3.2.1 Welding Defects 30
4.1.3.2.2 Defects of Anchor Bolt 30
4.1.3.2.3 Comparison Result of Steel Thickness 31
4.1.3.2.4 Comparison Result of Coating Thickness 33
4.2 Existing Steel Structures 34
4.2.1 Power Plant A1 34
4.2.1.1 Steel Structure Inspection and Evaluation Results 34
4.2.2 Power Plant A2 39
4.2.1.1 Steel Structure Inspection and Evaluation Results 40
4.2.3 Steel Billboard A 42
4.2.3.1 Steel Structure Inspection and Evaluation Results 43
4.3 Survey Fabricator Companies 47
4.3.1 Fabricator in Foreign Country 47
4.3.1.1 PEB Steel Company 47
4.3.2 Fabricator in Thailand 50
Ref. code: 25615922040299ZBX
![Page 8: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/8.jpg)
vi
4.3.2.1 BlueScope Building Company 50
4.3.2.2 M.C.S. Steel Public Company Limited 52
4.3.2.3 T-rex Steel Company Limited 53
4.3.2.4 ST. Frame & Truss Company Limited 55
4.3.2.5 Mano Steel Company limited 56
4.4 Proposed Countermeasure 56
4.4.1 Structural Steel Fabrication Accreditation 56
4.4.2 Checklist for fabricated steelwork 58
4.4.2.1 Material Selection 59
4.4.2.2 Fabrication 59
4.4.2.3 Welding 59
4.4.2.4 Welding Inspection 59
4.4.2.5 Coating 60
4.4.2.6 Erection 60
5 Conclusion 66
5.1 Conclusion 66
5.2 Suggestion of Solutions 66
5.2.1 Fabricators Accreditation 66
5.2.2 Checklist for Inspection Fabricated Steel Structure 67
References 68
Appendices 70
Appendix A 71
Ref. code: 25615922040299ZBX
![Page 9: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/9.jpg)
vii
List of Tables
Tables Page
2.1 Welding Visual Inspection Acceptance Criteria (DPT 1561-51) 5
3.1 Rating scheme for designating the quantity of defects (ISO 4628-1) 12
3.2 Rating scheme for designating the size of defects (ISO 4628-1) 12
3.3 Rating scheme for designating the intensity of changes (ISO 4628-1) 13
3.4 Degree of rusting and rested area (ISO 4628-3) 13
3.5 Rating scheme for designating the quantity of cracks (ISO 4628-4) 13
3.6 Rating scheme for designating the size of cracks (ISO 4628-4) 14
3.7 Rating scheme for designating the quantity of flaking (ISO 4628-5) 14
3.8 Rating scheme for designating the size of areas exposed by flaking
(ISO 4628-5) 14
4.1 Comparisons of material specifications 17
4.2 Description of visited sites 18
4.3 Result of steel thickness 32
4.4 Result of coating thickness 33
4.5 Inspection of coating defect of power plant building 35
4.6 Inspection of welding defect of power plant building 37
4.7 Inspection of bolt defect of power plant building 38
4.8 Inspection of coating defect of power plant building 40
4.9 Inspection of welding defect of power plant building 41
4.10 Inspection of bolt defect of power plant building 41
4.11 Inspection of coating defect of billboard 43
4.12 Inspection of welding defect of billboard 45
4.13 Inspection of bolt defect of billboard 46
4.14 Guidelines of Classification of Thai steel constructors 57
4.15 Equipment of Guidelines of Classification of Thai steel constructors 58
4.16 Checklist for inspection fabricated steel structure 61
Ref. code: 25615922040299ZBX
![Page 10: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/10.jpg)
viii
List of Figures
Figures Page
2.1 Undercut, Porosity and Overlap welds 4
3.1 Taper Gauge 11
3.2 Tape measurement 11
3.3 Welding Gauge 11
3.4 DFT Gauging 15
3.5 Thickness Gauging (UT) 15
4.1 Flow chart of fabrication process 17
4.2 Frame cross section 18
4.3 Overview of site no.1 19
4.4 Part of steel structure in site no.1 20
4.5 Overview of site no.2 20
4.6 Steel structure in site no.2 21
4.7 Defect of steel structure in site no.2 22
4.8 Overview of site no.3 22
4.9 Steel structure in site no.3 24
4.10 Overview of site no.4 24
4.11 Steel structure in site no.4 25
4.12 Weld connection of the steel structure in site no.4 26
4.13 Defect of steel section from factory at site no.4 27
4.14 Scratch of anti-corrosive paint at site no.4 27
4.15 Flaking of anti-corrosive paint at site no.4 27
4.16 Overview of site no.5 28
4.17 Steel structure in site no.5 29
4.18 Weld connection of the steel structure in site no.5 29
4.19 Welding defects found on column and rafter 30
4.20 Defects of anchor bolt 31
4.21 Components of built-up steel section 32
4.22 Overview of Power Plant A1 34
4.23 Overview of Power Plant A2 39
Ref. code: 25615922040299ZBX
![Page 11: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/11.jpg)
ix
4.24 Overview of Billboard A 42
4.25 Fabrication process of PEB Company 49
4.26 Fabrication process of BlueScope Building Company 52
4.27 Fabrication process of MCS 52
4.28 Fabrication process of T-Rex Steel Company 54
4.29 Fabrication process of ST. Frame & Truss Company 55
A-1 Blistering of size 2 63
A-2 Blisters of size 3 64
A-3 Blisters of size 4 65
A-4 Blisters of size 5 66
A-5 Degree of rusting Ri 1 67
A-6 Degree of rusting Ri 2 67
A-7 Degree of rusting Ri 3 68
A-8 Degree of rusting Ri 4 68
A-9 Degree of rusting Ri 5 69
A-10 Cracking without preferential direction 70
A-11 Cracking with preferential direction 79
A-12 Flaking without preferential direction 80
A-13 Flaking with preferential direction 81
Ref. code: 25615922040299ZBX
![Page 12: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/12.jpg)
1
Chapter 1
Introduction
1.1 General
Steel structures had been used widely in Thailand, espectually Pre-engineered
steel buildings (PEB) is a metal building designed and fabricated in the factory
premises; all components are shipped to site and are assembled and erected at site with
nuts, bolts and anchor bolts. The advantages of PEB are high durability, fast erection,
and cost saving. Particularly PEB as the latest trend in building construction are
increasingly confirmed their outstanding advantages in industrial and commercial
projects such as factory, warehouse, cold storage, showroom, office, supermarket,
school, stadium.
Durability of steel structure constructed is an important issue to be consider by
an engineer who desired long-lasting service life of the structures. So, good
maintenance system is highly essential to maintain durability of a structure.
It’s important to keep monitoring a steel structure to prevent the structural
failure, either by damage from deterioration during service life, or damage from defect
before or after construction process, or both type of damage.
.
1.2 Statement of Problem
We have not to control over the quality of fabrication and erection. In this
research, we have determined the problems of steel structure and solutions as follows;
1. Steel imported from foreign countries do not good quality.
2. Steel structures are imported from foreign countries that are not standard and
quality control has been erection in Thailand.
3. Steel constructors do not have the expertise and capability to manufacture of
large scale or poor workmanship such as welder and erector.
1.3 Objective of Study
The objective of this research is:
1. Establishment of construction guidelines for new steel structure
1.1 Inspection new structures imported from foreign country
2. Establishment of inspection guidelines for existing steel structure
2.1 Inspection steel structures in Thailand
Ref. code: 25615922040299ZBX
![Page 13: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/13.jpg)
2
1.4 Scope of Study
The scope of this research is:
1. visited some factories to inspected from foreign country and propose guideline
to inspect.
2. Inspection new structures imported from foreign country
3. Inspection existing steel structures in Thailand
Ref. code: 25615922040299ZBX
![Page 14: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/14.jpg)
3
Chapter 2
Literature Review
2.1 Steel Structures Damage and Defect
2.1.1 Corrosion Damage
Mars G. Fontana (1987) revealed that corrosion is the deterioration of a material
occur on the reaction with an environment which can be classified into “Wet corrosion”
and “Dry corrosion”. Wet corrosion occurs like the corrosion of steel by water. Dry
corrosion like the attack on steel by furnace gases. Small amounts of moisture can
highly affect the severity of the corrosion, like when moist chlorine or chlorine
dissolved in water is extremely corrosive comparing to dry chlorine which is
noncorrosive to steel.
corrosion damage is decreasing of steel section thickness. The corrosion
damage can affect the cost of the structure and the material to more resistance to its
condition can save the total cost, also many steel structures are stopped corrosion
failure. Inspection helps to protect the corrosion failure in structure.
2.1.2 Welding Defects
Baughurst et al. (2009) revealed that welding could be inefficient for its
purpose. which involve with the welding, such as overlap (Fig 2.1b) is caused by poor
welding techniques.
But there are more severe types of defects which can highly affect the capacity
of the weld such as cracking, undercutting (Fig 2.1a) which is an unfilled groove weld,
and Porosity (Fig 2.1c) which cause of problem for Cracking.
a) Undercut
Ref. code: 25615922040299ZBX
![Page 15: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/15.jpg)
4
b) Overlap
c) Porosity
Fig 2.1 Undercut, Porosity and Overlap welds
2.2 Inspection and Evaluation Standards
2.2.1 Welding Inspection
“Structural Steel welding inspection standard using Non-destructive testing” is
the standard to inspect the welding connection of steel connection is called DPT 1561-
51: using Visual inspection and equivalent to American Welding Society (AWS
D1.1/D1.1M).
DPT 1561-51 is criteria for VT to check the welding defect according to the
type of defect such as crack, porosity, and undercut, etc.
All welds should be visually inspected 100 percent based on DPT 1561-51
shown in Table 2.1.
Ref. code: 25615922040299ZBX
![Page 16: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/16.jpg)
5
Table 2.1 Welding visual inspection acceptance criteria (DPT 1561-51)
Ref. code: 25615922040299ZBX
![Page 17: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/17.jpg)
6
Table 2.1 Welding visual inspection acceptance criteria (DPT 1561-51) (Continue)
Ref. code: 25615922040299ZBX
![Page 18: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/18.jpg)
7
Table 2.1 Welding visual inspection acceptance criteria (DPT 1561-51) (Continue)
Ref. code: 25615922040299ZBX
![Page 19: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/19.jpg)
8
Table 2.1 Welding visual inspection acceptance criteria (DPT 1561-51) (Continue)
2.2.2 Bolt Inspection
JASS 6 state that, for bolt, after tightening process the bolt connection should
be inspected, to check the quality, size, and tightness level of the bolt. The tightening
check can be simply done by using torque wrench. Over-tightened bolt shall be
replaced, and loose bolt shall be tightened correctly.
JIS B 1186 state that, for high strength hexagon bolt, nut, and washers shall be inspected
to ensure the properties of the bolt connection such as, Shape and dimension using
direct measurement, appearance of the bolt such as the surface defect test using liquid
penetrant testing or magnetic particle testing to indicate the crack. Also, the mechanical
properties of the bolt shall be tested using bolt test pieces as a sample of bolt, nut, and
washer.
Finally, the joint shall be visually verified the faying surface of slip-critical joint
whether it meets the specification or not.
2.2.3 Coating Inspection
ISO 4628 state the general designation system for paint and varnishes
evaluation of degradation of coating based on quantity and size of defects and the
intensity of change by means of ratings on a numerical scale ranging from 0 to 5, while
“0” means “No defects”, and “5” means “Very severe”. The rest of the rating (1, 2, 3,
4) corresponds the severity range from low to high severity. Coating shall be inspection
visually to indicate the defects and its severity level. ISO 4628 specified the assessment
of degree of blistering, rusting, cracking, flaking of paint accordingly, Photographic
Ref. code: 25615922040299ZBX
![Page 20: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/20.jpg)
9
reference is given for each defect type based on quantity and size of defect, as shown
in Appendix A.
Ref. code: 25615922040299ZBX
![Page 21: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/21.jpg)
10
Chapter 3
Methodology
To indicating the damage and defect that occurred to steel structure, and to
identify the cause of the damage, Real site inspection and interview of maintenance
personnel are necessary to obtain enough information that leads to the countermeasure
to solve and prevent the damage. The target structures were steel billboards and steel
buildings.
3.1 Maintenance Personnel Interview
Information about the construction site, problem, and maintenance of the
damaged steel structures is to interview the maintenance personnel. This information
helps on identify indirect and root cause of the defect for steel structure in Thailand.
There are no specific questions that were asked in the interview, the interview was
carried out as a a topic or issues about the maintenance work, damage occurred on the
steel structures, and the opinion on a topic such as Thailand standards and guideline of
construction system in Thailand. These questions were asked to inspect steel structure.
And to obtain some knowledge about how to improve the steel structure maintenance,
standards and guideline of steel structure construction system in Thailand.
3.2 Inspection and Evaluation on Steel Structures
Visiting the real construction site is the best way to acknowledge the damage or
defect that occurred to steel structures. Site inspections were mostly carryout by using
visual inspection, coating thickness and steel thickness, since this method does not
affect property, appearance, or function of the structures. Visual inspection routine used
in this research, the visual inspection and evaluation was divided in to two target areas
which are steel connection inspection and steel surface inspection. The steel connection
inspection was focused on both of weld and bolt connection based on DPT 1561-51 and
JASS 6 accordingly. Steel surface inspection was focused on coating thickness and
corrosion on the steel surface based on ISO 4628.
Ref. code: 25615922040299ZBX
![Page 22: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/22.jpg)
11
3.2.1 Welding Inspection Criteria
In this research, visual inspection method was used to inspect the steel structure
with welded connections, which was considered to be the most severe welding defects.
The welding inspection criteria are according to the criteria in DPT 1561-51.
3.2.1.1 Welding Inspection Equipment
The equipment for welding inspection was listed below:
1. Taper Gauge (Shown in Fig 3.1)
2. Tape measurement (Shown in Fig 3.2)
3. Welding Gauge (Shown in Fig 3.3)
Fig 3.1 Taper Gauge Fig 3.2 Tape measurement Fig 3.3 Welding Gauge
3.2.2 Bolting Inspection Criteria
According to JASS 6 that bolt inspection for every bolt after tightening is
necessary and need to all of bolt that tightening. But this research is targeted Pre-
engineered steel building (PEB) and existing steel structure makes difficulty on getting
those certain structure design data or drawing, so it impossible to follow the criteria
about JASS 6 directly. Bolting inspection criteria was to check the appearance of the
bolt connection. The criteria were to VT check the damage on the bolt connection such
as bolt connection surface damage, bolt connection deformation, the length of bolt
beyond nuts is too short, and bolt connection failure.
3.2.3 Steel Coating Inspection Criteria
The inspection criteria for steel coating are used in this research was followed
the international standard ISO 4628. The inspection carried out by using visual
inspection and photographic reference (shown in Appendix A), and then recorded the
Ref. code: 25615922040299ZBX
![Page 23: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/23.jpg)
12
inspection data in the charge of photograph and table. The data was evaluated based on
the quantity, size, and intensity of change of each defect according to ISO 4628. The
coating damage was evaluated by using the table and photograph as shown in Table 3.1
until Table 3.8 and comparing with reference in Appendix A.
Table 3.1 Rating scheme for designating the quantity of defects (ISO 4628-1)
Table 3.2 Rating scheme for designating the size of defects (ISO 4628-1)
Ref. code: 25615922040299ZBX
![Page 24: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/24.jpg)
13
Table 3.3 Rating scheme for designating the intensity of changes (ISO 4628-1)
Table 3.4 Degree of rusting and rested area (ISO 4628-3)
Table 3.5 Rating scheme for designating the quantity of cracks (ISO 4628-4)
Ref. code: 25615922040299ZBX
![Page 25: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/25.jpg)
14
Table 3.6 Rating scheme for designating the size of cracks (ISO 4628-4)
Table 3.7 Rating scheme for designating the quantity of flaking (ISO 4628-5)
Table 3.8 Rating scheme for designating the size of areas exposed by flaking (ISO
4628-5)
Ref. code: 25615922040299ZBX
![Page 26: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/26.jpg)
15
3.2.3.1 Steel Coating Inspection Equipment
The equipment used in steel coating inspection was listed as follow:
1. Tape measurement (Shown in Fig 3.2)
2. Camera
3. Reference photo (from ISO 4628)
4. Dry Film Thickness (DFT) Gauging (Shown in Fig 3.4)
5. Thickness Gauging (UT) (Shown in Fig 3.5)
Fig 3.4 DFT Gauging Fig 3.5 Thickness Gauging (UT)
3.3 Survey Fabricator Companies
The Fabricator is the primary responsibility for ensuring the structural steelwork
is manufactured to the requirements of the contract documents. They must operate some
form of production control system, which will include:
• Fabricator production control system
• Traceability and component marking
• Weld quality management
• Acceptance of material (Structural steels, weld consumables, bolts)
• Fabrication processes (milling, drilling, cutting and coating)
• Inspection and testing method (VT, UT, RT for heavy industry and PT)
Ref. code: 25615922040299ZBX
![Page 27: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/27.jpg)
16
Chapter 4
Results and Discussion
4.1 New Steel Structures (PEB)
4.1.1 Data Collection
We have visited four companies to collect data on PEB such as design,
fabrication, erection and also interviewed engineers who are responsible for design and
construction. These four companies are the international companies in which their
fabrication factories are located outside Thailand, they are named as company A, B, C
and D. We went to visit the headquarter (Company A) of one company in the foreign
country and the branch of other three companies (Company B, C, D) in Thailand.
For the design method, most of the companies use the Allowable Strength
Design (ASD) and loading conditions as follows:
1. Dead load consists of the weight of all material of construction incorporated
into the building.
2. Roof Live Loads, for built-up frames minimum uniformly distributed live load
on roof is 0.57kN/m2 according to MBMA.
3. Collateral loads are included in roof live loads that arise due to sprinklers, ducts,
lighting fixtures and ceilings.
4. Wind loads are governed by wind speed, roof slope, eave height and open wall
conditions of the building. PEB are designed for a minimum wind speed of a 110 km/hr.
more than DPT 1511 (Department of Public Works and Town & Country Planning,
Thailand).
4.1.2 Fabrication Process
The fabrication process of the components of PEB companies are shown in
Fig.4.1. The first step begins with preparation of raw material. Second step is
cutting/drilling and punching by plasma and flame method. Third step is tacking web
and flange built up into H-Beam, after that auto welding by a submerged arc welding
process (SAW). Fourth step is fitting and final welding by a gas metal arc welding
process (GMAW) or Flux core arc welding process (FCAW). The last step is blasting
two surface profiles including SA2.0 and SA2.5 according to ISO 8501-1, and coating
with a quick drying primer.
Ref. code: 25615922040299ZBX
![Page 28: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/28.jpg)
17
Fig.4.1 Flow chart of fabrication process
4.1.3 Material Specification
From the results of collecting data at 4 companies, it was found that the
international standards such as USA and Japan are used for material selection of the
frame structure as shown in Table 4.1.
Table 4.1 Comparisons of material specifications
Material Company A Company B Company C Company D
1.Built-up member ASTM A572
Gr 50
ASTM A572
Gr 50 Q 345 (GB)
Q 345 (GB) or
ASTM A 572
Gr.50
2.X-Bracing rod ASTM A 36 JIS G3101/
SS400 ASTM A36
JIS SS 400 or
ASTM A36
3.Anchor bolt ASTM A 36
(Gr. 4.6)
TCVN 1916-
1995
ASTM A36
(Gr. 4.6)
ASTM A36
(Gr. 4.6)
4.High strength bolt ASTM A 325
(Gr 8.8)
ASTM A490
(Gr 10.9)
ASTM A325
(Gr8.8)
ASTM A325
(Gr8.8)
4.1.3.1 Visiting Construction Sites of Pre-Engineered Buildings (PEB)
Generally, PEB will be constructing by using a built-up member and it is a metal
building designed and was welded from fabrication in the factory premises; all
components are shipped to site and are assembled and erected at site using bolt
connection (nuts, bolts and anchor bolts).
Five construction sites were visited: two construction sites in a foreign country
(site no.1, 2) and three construction sites in Thailand (site no. 3, 4, 5). The dimension
and some description of the visited sites are illustrated is Fig.4.2 and Table 4.2
Ref. code: 25615922040299ZBX
![Page 29: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/29.jpg)
18
Fig.4.2 Frame cross section
Table 4.2. Description of visited sites
Site No. Type Description of Site Dimension of PEB
X (m) Y (m)
1 Garment
Factory
Fabricated by company A
Erected in the foreign country
60 10
2 Furniture
storage
Fabricated by company A
Erected in the foreign country
60 6
3 Coal
storage
Fabricated by company B
Erected in Thailand
60 14.4
4 Warehouse Fabricated by company C
Erected in Thailand
48 8
5 Warehouse Fabricated by company D
Erected in Thailand
30 9.8
4.1.3.1.1 Site No.1
Site no.1 is a Garment Factory located in Vung Tau province, Vietnam. The
structural steel was fabricated from the factory in Vietnam, and then erected at the site
in Vietnam.
Fig. 4.3 shows the overall of construction site no.1, Fig 4.4 a) shows the anchor
bolt using double nut and 1 washer according to MBMA, and Fig.4.4 b) and c) shows
some part of the steel structure consist of column and rafter.
Ref. code: 25615922040299ZBX
![Page 30: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/30.jpg)
19
Fig 4.3 Overview of site no.1
a) Anchor bolt using double nut and 1 washer
b) Rafter component
Ref. code: 25615922040299ZBX
![Page 31: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/31.jpg)
20
c) Column component
Fig 4.4 Part of steel structure in site no.1
4.1.3.1.2 Site No.2
Site no.2 is a furniture storage warehouse that located in Dong Nai province,
Vietnam. The structural steel was fabricated from the factory in Vietnam, and then
erected at the site in Vietnam.
Fig 4.5 shows the overview of the steel structures in site no.2, Fig 4.6 a) shows
the anchor bolt using double nut and 1 washer according to MBMA, Fig.4.6 b) shows
rafter and column connected by bolt. Component of column in site no.2 was thoroughly
inspected base on visual inspection is shown in Fig.4.7 shows defect of anchor bolt are
unacceptable (see 4.2.1).
Fig 4.5 Overview of site no.2
Ref. code: 25615922040299ZBX
![Page 32: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/32.jpg)
21
a) Anchor bolt using double nut and 1 washer
b) Rafter and column connected by bolt
Fig 4.6 Steel structure in site no.2
a) Defect of anchor bolts
Ref. code: 25615922040299ZBX
![Page 33: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/33.jpg)
22
b) Defect of anchor bolts (single nut)
Fig 4.7 Defect of steel structure in site no.2
4.1.3.1.3 Site No.3
Site no.3 is a coal storage located in Ayutthaya province, Thailand. The
structural steel was fabricated from the factory in Vietnam, and then erected at the site
in Thailand, Fig.4.8 shows overall of construction site no.3.
Fig 4.8 Overview of site no.3
Fig 4.8 shows the overview of the steel structures in site no.3, Fig 4.9 a) shows
the anchor bolt using double nut and 1 washer according to MBMA, Fig.4.9 b) shows
rafter and purlin erection and Fig.4.9 c) shows installation rafter using bolt tightening
by Torque wrench.
Ref. code: 25615922040299ZBX
![Page 34: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/34.jpg)
23
a) Anchor bolt using double nut and 1 washer
b) Erection rafter and purlin
Ref. code: 25615922040299ZBX
![Page 35: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/35.jpg)
24
c) Bolt installation by torque wrench
Fig 4.9 Steel structure in site no.3
4.1.3.1.4 Site No.4
Site no.4 is a warehouse located in Chonburi province, Thailand. The structural
steel was fabricated from the factory in Vietnam, and then erected at the site in
Thailand.
Fig 4.10 shows the overview of the steel structures in site no.4, Fig 4.11 a)
shows the Component of rafter, purlin and roof after installation, Fig.4.11 b) shows
rafter and column connected by bolt.
Fig 4.10 Overview of site no.4
Ref. code: 25615922040299ZBX
![Page 36: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/36.jpg)
25
a) Component of rafter, purlin and roof after installation
b) Rafter and column connected by bolt
Fig 4.11 Steel structure in site no.4
Component of rafter and column in site no.4 was thoroughly inspected base on
visual inspection. The inspection results show many serious weld defects especially
porosities, undercuts and spatters at the welding, as in the figure shows the location of
defect (see Fig 4.12).
Ref. code: 25615922040299ZBX
![Page 37: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/37.jpg)
26
a) Porosity defect
b) Spatter defect
c) Undercut defect
Fig.4.12 Weld connection of the steel structure in site no.4
Ref. code: 25615922040299ZBX
![Page 38: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/38.jpg)
27
The visual inspection show that the steel structure has minor deterioration such
as flaking, intensive change in appearance (color), scratch and defect from factory,
shown in Fig.4.12 to Fig.4.15.
Fig.4.13 Defect of steel section from factory at site no.4
Fig.4.14 Scratch of anti-corrosive paint at site no.4
Ref. code: 25615922040299ZBX
![Page 39: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/39.jpg)
28
Fig.4.15 Flaking of anti-corrosive paint at site no.4
4.1.3.1.5 Site No.5
Site no.5 is a warehouse located in Samutprakarn province, Thailand. The
structural steel was fabricated from the factory in Vietnam, and then erected at the site
in Thailand, Fig.4.16 shows overall of construction site no.5.
Fig 4.16 Overview of site no.5
Fig 4.17 a) shows the anchor bolt using double nut and 1 washer according to
MBMA, Fig.4.17 b) shows rafter and column connected by bolt
Ref. code: 25615922040299ZBX
![Page 40: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/40.jpg)
29
a) Anchor bolt using double nut and 1 washer
b) Rafter and column connected by bolt
Fig 4.17 Steel structure in site no.5
The inspection shows the damage from the welding process during the
construction in factory, the arc of the weld was melted the steel section out and
penetrated the steel section as shown in Fig.4.18.
a) Undercut defect
Ref. code: 25615922040299ZBX
![Page 41: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/41.jpg)
30
b) Imperfect welding
Fig.4.18 Weld connection of the steel structure in site no.5
4.1.3.2 Inspection Result
4.1.3.2.1 Welding Defects
From the inspection results, it was found that some steel structures have defects
of welding on the steel surface, especially incomplete fusion, spatter, porosity, and
undercut, which exceed the standard limit in DPT 1561 (Department of Public Works
and Town & Country Planning, Thailand), which is equivalent to AWS D1.1/D1.1M.
The evaluation of the weld defects was classified as unacceptable. Examples of the
welds that were unacceptable for some sites are shown in Fig.4.19.
a) Welding defects on rafter at site no. 4
b) Welding defects on column at site no. 5
Fig.4.19 Welding defects found on column and rafter
porosit
y
spatte
r incomplete fusion
undercut
imperfect
welding undercut
Ref. code: 25615922040299ZBX
![Page 42: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/42.jpg)
31
4.1.3.2.2 Defects of Anchor Bolt
From the inspection results, it was found that there are the defects of anchor bolt
at site no.2. It was evaluated that the bolt was unacceptable because the length of bolt
beyond nuts is too short, i.e. less than 3 threads, according to JASS 6 as shown in
Fig.4.20 a). In addition, single nut is used as shown in Fig.4.20 b), but according to
MBMA, double nut must be adopted.
a) Defect of anchor bolts
b) Defect of anchor bolt (single nut)
Fig.4.20 Defects of anchor bolt
4.1.3.2.3 Comparison Result of Steel Thickness
In this study, we measured steel thickness of a steel parts (column, rafter) as
shown in Fig.4.21. The inspection of steel thickness was done by using ultrasonic pulse-
echo testing (UT) in Fig.3.4 according to ASTM E797, the results of steel thickness
measurement are compared with the thickness specified in the as-built drawing (Table
4.3), From Table 4.3, it can be seen that the measured steel thickness is more than the
thickness specified in the drawing, and the results are acceptable.
single nut
remaining screw length less than
position of nut.
Ref. code: 25615922040299ZBX
![Page 43: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/43.jpg)
32
Fig.4.21 Components of built-up steel section
Table 4.3 Result of steel thickness
Inspected part
Thick.
Specified
in the
drawing
(mm)
Measured Value (mm)
Average
(mm)
S.D.
(mm)
Difference
(%) Evaluation
x1 x2 x3 x4 x5
Site no.1
Column Web 6 5.98 5.9 6.5 6.2 6.7 6.7 0.13 1% OK
Flange 8 8.07 8.2 8.6 7.9 8.5 8.2 0.29 3% OK
Site no.2
Column Web 6 6 5.5 6 6.2 6.1 6.2 0.26 0% OK
Flange 8 8.6 8.2 8.7 8.9 8.2 8.5 0.32 7% OK
Site no.3
Column Web 10 11.7 11.6 11.4 11.2 12.6 11.6 0.34 16% OK
Flange 10 11.5 10.6 11.1 11.9 10.7 11.2 0.54 12% OK
Site no.4
Column Web 8 8.7 8.7 8.9 8.9 8.7 8.8 0.1 10% OK
Flange 10 10.8 10.5 10.5 10.6 11.5 10.8 0.4 8% OK
Rafter Web 8 9.8 9.1 9.3 9.4 9.2 9.2 0.16 15% OK
Flange 10 10.9 10.8 10.7 10.9 10.6 10.8 0.12 8% OK
Site no.5
Column Web 5 5.3 5.7 5.9 5.3 5.6 5.6 0.24 11% OK
Flange 10 10.3 11.7 10.9 10.4 10.9 10.8 0.57 8% OK
Rafter Web 5 5.7 5.7 5.9 5.5 6 5.7 0.27 14% OK
Flange 10 10.8 10.5 10.3 10.6 10.6 10.7 0.18 6% OK
Flange
Web
Ref. code: 25615922040299ZBX
![Page 44: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/44.jpg)
33
4.1.3.2.4 Comparison Result of Coating Thickness
We measured coating thickness of a steel parts (column, rafter) as shown in
Fig.4.21. The inspection of coating thickness was made by using NDFT by coating
thickness gauge in Fig.3.5 according to ISO 19840. The results of coating thickness
measurement results are compared with the required thickness (Table 4.4). From Table
4.4, it was found that the coating thickness at some sites is less than the required
thickness. Therefore, the quality control on coating process must be seriously
performed at the fabrication factory.
Table 4.4 Result of coating thickness
Inspected part
Thick.
specied in
the drawing
(µm)
Measured Value (µm) Avera
ge
(µm)
S.D.
(µm)
Difference
(%)
Evalua
tion x1 x2 x3 x4 x5
Site no.1
Column Web
80 87 88.4 90.2 85.7 100 90.3 5.7 13% OK
Flange 80.5 82 94.5 81.7 92.4 86.2 6.7 8% OK
Site no.2
Column Web
80 100.4 107.2 102.8 83 82 95.1 11.8 19% OK
Flange 102 89.2 102.2 91.4 95.4 96 6 20% OK
Site no.3
Column Web
660 935 883 1052 1224 979 1014.6 132 54% OK
Flange 510 666 636 640 603 611 60.7 -7% NG
Site no.4
Column Web
660
256.3 249.8 258.8 253.1 215.5 246.7 17.8 -63% NG
Flange 179.9 222.1 209.1 193.8 188.2 198.6 16.9 -70% NG
Rafter Web 263.4 236.6 230.3 239.3 218.5 237.6 16.5 -64% NG
Flange 202.4 185 230.8 218.8 210.7 209.5 17.3 -68% NG
Site no.5
Column Web
80
105 115.6 102.4 110 111.2 108.8 5.2 36% OK
Flange 91.1 101.1 100 95.4 96.3 96.8 4 21% OK
Rafter Web 80.2 85.4 90.5 90 88.5 86.9 4.3 9% OK
Flange 98.4 95.2 94.6 96.3 98.2 96.5 1.8 21% OK
Ref. code: 25615922040299ZBX
![Page 45: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/45.jpg)
34
4.2 Existing Steel Structures
4.2.1 Power Plant A
The steel structure in Power Plant A1 was a constructed by hot-rolled steel as
the main structure connected by bolt connection, so the main damage for the structure
in Power Plant A1. Shown in Fig 4.22 is the steel structure in Power Plant A1.
Fig 4.22 Overview of Power Plant A
4.2.1.1 Steel Structure Inspection and Evaluation Results
The results show that the steel structures had severe damage on the steel
building and bolt connections. The corrosion covers large area on the steel surface and
steel section and some of area has no coating on the steel surface, because of the
corrosion on steel surfaces is severe rust.
The damage could occur from poor workmanship during erection and coating
works, because some area of steel could be unprotected, because of the paint may not
cover the area of the steel, especially at the connection area, so the moisture is cause of
severe corrosion. Table 4.5 shown inspection data based on ISO 4628 standard.
Ref. code: 25615922040299ZBX
![Page 46: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/46.jpg)
35
Table 4.5 Inspection of coating defect of power plant building
Defect Location of defect Useful
Life
(yr)
Criteria Detail of
inspection
Rust Point A
10 Ri 0
Ri 1
Ri 2
Ri 3
Ri 4
Ri 5
Checking steel
thickness and
coating
thickness
Blistering
Column A
10 0 S 0
1 S 1
2 S 2
3 S 3
4 S 4
5 S 5
Checking steel
thickness and
coating
thickness
Ref. code: 25615922040299ZBX
![Page 47: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/47.jpg)
36
Table 4.5 Inspection of coating defect of Power Plant Building (Continue)
Defect Location of defect Useful Life
(yr)
Criteria Detail of
inspection
Flaking
Column A
10 0 S 0
1 S 1
2 S 2
3 S 3
4 S 4
5 S 5
Checking steel
thickness and
coating
thickness
Ref. code: 25615922040299ZBX
![Page 48: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/48.jpg)
37
The steel structure in Power Plant A1 was welded, bolted, and painted at the
site. This explain steel structure in Power Plant A1 have a lot of defect. However, weld
and bolt connection were unacceptable (shown in Table 4.6 and Table 4.7), but poor
paint workmanship could cause a lot of problem to the steel structure.
Table 4.6 Inspection of welding defect of power plant building
Defect Location of defect Useful Life
(yr)
Cause Detail of inspection
Cracking - - - -
Underfill
10 Poor welder -
Undercut
10 Poor welder -
Ref. code: 25615922040299ZBX
![Page 49: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/49.jpg)
38
Table 4.7 Inspection of bolt defect of power plant building
Defect Location of defect Useful
Life
(yr)
Cause Detail of
inspection
Is the bolt
loosening?
10 Bolt are not
tightening
Checking bolt
tightening by
using hammer
method from
EXACT manual
Is the bolt
quality and
size correct?
10 Material low
quality
-
Checking
bolt nut or
rivet
10 Poor
workmanship
-
Rust
10 Ri 0
Ri 1
Ri 2
Ri 3
Ri 4
Ri 5
-
Ref. code: 25615922040299ZBX
![Page 50: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/50.jpg)
39
4.2.2 Power Plant A
The steel structure in Power Plant A was a constructed by hot-rolled steel as
connected by bolt connection, the structure was located near the water river, so the main
damage for the structure in Power Plant A2. Shown in 4.23 is the steel structure in
Power Plant A.
(a) Steel Structure in Power Plant A2
(b) Steel Structure in Power Plant A2
Fig 4.23 Steel Structure in Power Plant A2
Ref. code: 25615922040299ZBX
![Page 51: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/51.jpg)
40
4.2.1.1 Steel Structure Inspection and Evaluation Results
The visual inspection results are shown that the steel structure have minor
deterioration of anti-corrosive paint, welded and bolted, such as blistering (from high
moisture), flaking, and cracking, causing damage shown in Table 4.8 to Table 4.10
Table 4.8 Inspection of coating defect of power plant building
Defect Location of defect Useful
Life
(yr)
Criteria Detail of
inspection
Rust
10 Ri 0
Ri 1
Ri 2
Ri 3
Ri 4
Ri 5
Checking steel
thickness and
coating
thickness
Flaking
10 0 S 0
1 S 1
2 S 2
3 S 3
4 S 4
5 S 5
Checking steel
thickness and
coating
thickness
Ref. code: 25615922040299ZBX
![Page 52: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/52.jpg)
41
Table 4.9 Inspection of welding defect of power plant building
Defect Location of defect Useful Life
(yr)
Cause Detail of
inspection
Cracking - - - -
Underfill
10 Poor welder -
Table 4.10 Inspection of bolt defect of power plant building
Defect Location of defect Useful Life
(yr)
Cause Detail of
inspection
Rust
10 Ri 0
Ri 1
Ri 2
Ri 3
Ri 4
Ri 5
-
Rust
10 Ri 0
Ri 1
Ri 2
Ri 3
Ri 4
Ri 5
-
Ref. code: 25615922040299ZBX
![Page 53: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/53.jpg)
42
4.2.3 Steel Billboard A
In this research, steel billboard which located in Samutprakarn area was visually
inspected, the billboard owner in negative ways, the billboard will be named as
“Billboard A”. The inspection criteria were carried out by using the acceptation criteria
in Thai standard for welding visual inspection, and ISO 4628 for steel coating
inspection. Fig 4.24 shows the overview to the structure of Billboard A.
Fig 4.24 Structure overview of Billboard A
Ref. code: 25615922040299ZBX
![Page 54: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/54.jpg)
43
4.2.3.1 Steel Structure Inspection and Evaluation Results
The inspection results show defects such as flaking, blistering, undercut,
porosity and rusting, as well as the inspection and evaluation results were recorded in
as shown in Table 4.11 to Table 4.13.
Table 4.11 Inspection of coating defect of power plant building
Defect Location of defect Useful
Life
(yr)
Criteria Detail of
inspection
Rust
2 Ri 0
Ri 1
Ri 2
Ri 3
Ri 4
Ri 5
Checking steel
thickness and
coating
thickness
Blistering
2 0 S 0
1 S 1
2 S 2
3 S 3
4 S 4
5 S 5
Checking steel
thickness and
coating
thickness
Ref. code: 25615922040299ZBX
![Page 55: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/55.jpg)
44
Table 4.11 Inspection of coating defect of power plant building (Continue)
Defect Location of defect Useful
Life
(yr)
Criteria Detail of
inspection
Flaking
2 0 S 0
1 S 1
2 S 2
3 S 3
4 S 4
5 S 5
Checking
steel
thickness
and
coating
thickness
Ref. code: 25615922040299ZBX
![Page 56: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/56.jpg)
45
Table 4.12 Inspection of welding defect of power plant building
Defect Location of defect Useful Life
(yr)
Cause Detail of inspection
Cracking - - - -
Underfill
10 Poor welder -
Undercut
10 Poor welder -
Ref. code: 25615922040299ZBX
![Page 57: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/57.jpg)
46
Table 4.13 Inspection of bolt defect of power plant building
Defect Location of defect Useful Life
(yr)
Cause Detail of
inspection
Checking
bolt, nut
or rivet
10 Poor
workmanship
Rust
10 Ri 0
Ri 1
Ri 2
Ri 3
Ri 4
Ri 5
-
Ref. code: 25615922040299ZBX
![Page 58: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/58.jpg)
47
4.3 Survey Fabricator Companies
In this visiting five fabricator in Thailand and one fabricator in foreign country
which fabricated steel structures, we have interviewed the personnel who respond for
fabrication process and inspect the quality of steel structures.
4.3.1 Fabricator in Foreign Country
4.3.1.1 PEB Steel Company
PEB Steel Company is the leading PEB Company in Thailand. Established in
1994, PEB Steel Company specializes in the Design, Fabrication, and Erection of Pre-
Engineered Steel Buildings (PEB), steel structures for factories, warehouses. PEB
Company are designed in compliance with the design and building codes (IBC 2015,
AWS 2015, AISC 2016, MBMA 2012, AISI 2013) and PEB Company have
management system such as ISO 9001:2015 and OHSAS19001:2007
The fabrication process of the components of PEB companies are shown in
Fig.4.25. The first step begins with preparation of raw material (ASTM A572 Gr.50) as
shown in Fig.4.25 (a). Second step is cutting/drilling and punching by plasma and flame
method as shown in Fig.4.25 (b and c). Third step is tacking web and flange built up
into H-Beam, after that auto welding by a submerged arc welding process (SAW) as
shown in Fig.4.25 (d). Fourth step is fitting and final welding by a gas metal arc welding
process (GMAW) or Flux core arc welding process (FCAW) as shown in Fig.4.25 (e
and f). The last step is blasting two surface profiles including SA2.0 and SA2.5
according to ISO 8501-1, and coating with a quick drying primer (Single Coat 40
microns for alkyd and 80 microns for epoxy) as shown in Fig.4.25 (g and h).
a) Raw Material
Ref. code: 25615922040299ZBX
![Page 59: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/59.jpg)
48
b) Cutting Steel Plate
c) Drilling and Punching
d) Auto Welding Line
e) Fitting Section
Ref. code: 25615922040299ZBX
![Page 60: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/60.jpg)
49
f) Final Welding and Finishing
g) Shot Blasting Machine ( to clean Steel Member )
h) Painting Area
Fig.4.25 Fabrication process of PEB Company
Ref. code: 25615922040299ZBX
![Page 61: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/61.jpg)
50
4.3.2 Fabricator in Thailand
4.3.2.1 BlueScope Building Company
BlueScope Building Company is one of the PEB Company in Thailand.
BlueScope Building Company specializes in the Design, Fabrication, and Erection of
Pre-Engineered Steel Buildings (P.E.B) in Rayong province Thailand, BlueScope
Building Company are designed in compliance with the design and building codes (IBC
2015, AWS 2015, AISC 2016, MBMA 2012, and AISI 2013) and BlueScope Building
Company have management system such as ISO 9001:2015, SSSS Class S1 and
OHSAS19001:2007.
The fabrication process of the components of BlueScope Building Companyare
shown in Fig.4.26. The first step is stock inventory raw material (steel plate SM520B)
and supply to cutting in CNC plasma line and Flame cutting. Second step is
cutting/drilling and punching by Plasma machine cutting. Third step is assembly of
built-up component into H-Beam, after that auto welding by a submerged arc welding
process (SAW). Fourth step is fitting and final welding by a gas metal arc welding
process (GMAW). The last step is blasting two surface profiles including SA2.0 and
SA2.5 according to ISO 8501-1, and coating with a quick drying primer (Single Coat
50 microns, Multi coat 80 microns and Fire proofing 500 microns).
a) Raw Material
Ref. code: 25615922040299ZBX
![Page 62: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/62.jpg)
51
b) CNC Plasma Machine
c) Flame Planner Machine
d) Tack Station Line
e) Auto Welding
Ref. code: 25615922040299ZBX
![Page 63: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/63.jpg)
52
Cutting Drilling Built-up Welding Blasting Coating
f) Fitting-up and Final Welding
g) Shot Blasting
h) Painting Booth
Fig.4.26 Fabrication process of BlueScope Building Company
4.3.2.2 M.C.S. Steel Public Company Limited
M.C.S. Steel Public Company Limited is the leading steel fabricating Company
in Thailand and the company in Ayutthaya. Established in 1992, M.C.S. has more than
20 years of successful experiences in fabrication of high-rise steel structure building,
power plant, bridge & general steel works. With the most advanced manufacturing
equipment, high standards & punctuality, we are now able to provide & export steel
structure works for various projects worldwide, mainly in Japan with 50,000 tons per
annual. The fabrication process of this company as show in Fig 4.27
Fig 4.27 Fabrication process of MCS
Ref. code: 25615922040299ZBX
![Page 64: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/64.jpg)
53
4.3.2.3 T-rex Steel Company Limited
T-Rex Steel is one of Thailand's leading manufacturer of steel and grating
products. T-Rex Steel are a leader in the design and improvements of steel and grating
products. T-Rex Steel are designed and manufactured to exacting standards,
incorporating the latest technique in high tensile structure design and fabrication. With
over twenty year of experience in manufacturing multi – products, T-Rex Steel offer
internations class for Building Structure, Machine part Structure, Automotive Structure
and Grating. Automotive Structure have management system such as ISO 9001:2015,
and SSSS Class S2.
Fabrication process, T-Rex Steel imported the steel from Hong Kong but steel
plate and steel section such as H and I Section they have bought from LPN plate mill
public company limited and Siam Yamato Steel Company. They focus on the welding
process as much as they can because of this process is the critical point of the
fabrication, they have 3 machines for cutting steel plates and pipes such as CNC cutting
machine, plasma cutting machine, and saw cutting machine as show in Fig 27, they will
cut steel plate, dimension depends on the shop drawing, before fabrication process.
Next, the inspection process, they use UT and PT to inspect the structural product.
Blasting, they will be blasting before coating and painting. Coating and painting
process, they are coating a primer color around 35-50 microns then painting epoxy
around 60-65 microns and the last one is painting color around 30 microns (it depends
on the specification of customer).
a) Raw Material (from SYS and LPN)
Ref. code: 25615922040299ZBX
![Page 65: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/65.jpg)
54
b) Cutting
c) Punching and Drilling
d) Welding Process
e) Steel Grit Blasting (steel grid) and Painting
Fig 4.28 Fabrication process of T-Rex Steel Company
Ref. code: 25615922040299ZBX
![Page 66: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/66.jpg)
55
4.3.2.4 ST. Frame & Truss Company Limited
ST. Frame & Truss was established in 1992.The company specializes in the fabrication
and election of the steel structures for factories, warehouse, commercial/trade center, etc.
During, more than decades of the operation in the field of steel structures industry, we are very
confident that the management is well qualified to prove the best service at the mentioned.
Fabrication process as show in below.
Fig 4.29 Fabrication process of ST. Frame & Truss Company
Ref. code: 25615922040299ZBX
![Page 67: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/67.jpg)
56
4.3.2.5 Mano Steel Company limited
Mano Steel was founded in 2003, we are a specialist in steel structure and
construction and obtained and ISO 9001 certificate, Mostly, we have been working with
Japanese companies such as Thai Shimizu, Thai Obayashi, and Kajima.
4.4 Proposed Countermeasure
The proposed countermeasures were divided into two phases consist of; 1)
Structural Steel Fabrication Accreditation, 2) Checklist for Fabricated Steelwork
4.4.1 Structural Steel Fabrication Accreditation
Structural steel fabrication accreditation scheme by Singapore Structural Steel
Society state the accreditation for the fabricator, which will ensure that the structural
steelwork construction is carried out by suitably qualified fabricators. Quality control
of the steel work is possibly another issue in Thailand, as show in the research that the
welding work was done poorly in many steel structures. The countermeasure against
this issue is to establish the accreditation of fabricators and welders to control the
quality of the steel work. Additionally, the accreditation shall divide into several levels
or types, to indicate the work that a certain fabricator could do. For example, the
structural steel fabricators accreditation of Singapore was divided into three categories,
as Category S1 to Category S3 based on their capabilities, track records, financial
status, technical capability and the standard of the fabrication plants. infrastructure,
resources and capabilities to fabricate and erect structural steel structures of that
companies. For example, the fabricator that has building of over 30 m in height, or large
span bridges of over 30 m will be classified as Category S1, or up to 30 m will be
classified as Category S2, and finally up to 10 m will be classified as Category S3.
Ref. code: 25615922040299ZBX
![Page 68: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/68.jpg)
57
Table 4.14 Guidelines of Classification of Thai steel constructors.
Ref. code: 25615922040299ZBX
![Page 69: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/69.jpg)
58
Table 4.15 Equipment of guidelines of classification of Thai steel constructors.
4.4.2 Checklist for Fabricated Steelwork
A checklist given in the Table 4.14 can be used as a guide to assess compliance
of the fabricated steelwork. The checklist provides references to the international
standards and defines documentation required to claim compliance. Depending on the
outcome of the assessment, the fabricated steelwork may be subject to additional NDT
and (destructive) testing. There are additional considerations if steel is supplied to a
non-Thailand material supply standard. Inspector have a task of verifying compliance
of the steel work that fabricated from foreign countries. It is the responsibility to make
sure that the fabricator complies with applicable international standards and rules.
Therefore, evaluation of compliance of fabricated steelwork poses some significant
risks. In order to achieve compliance, it may be necessarily to provide a full third-party
supervision and inspection to the overseas fabricator. The quantity of NDT and
inspection may need to be significantly higher than that recommended in standard to
verify compliance. An important aspect for the safety of welded connections is the
acceptance level of external and internal weld imperfections defined in standard.
Therefore, welding procedures and welder qualification tests performed to overseas
standards usually need to be re-qualified due to the difference in the acceptance levels
for weld imperfections.
Ref. code: 25615922040299ZBX
![Page 70: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/70.jpg)
59
4.4.2.1 Material Selection
This study sets out of minimum requirements for the selection of materials of the
construction of steel structures. All structural steel coming within the scope of these clauses
shall, before fabrication, comply with the requirements such as Thai Industrial Standards,
Australian or Joint Australian/New Zealand Standards, British Standards, Japanese Standards
and American Standards.
4.4.2.2 Fabrication
A manufacturer’s certificate of compliance with the specified material in 4.3.2.1 can
requested, but the request is usually contained in the contract documents rather than
introduced during fabrication as follows;
• Identification The steel grade shall be identifiable at all stages of fabrication and any
marking of steelwork shall be such as to not damage the material.
• Fabrication procedures such as Straightening, curving and cambering, cutting, drilling,
Precamber, Holing, Tolerances, and etc.
4.4.2.3 Welding
Welded connections may be made by butt, fillet, plug or slot welds by welded joints
are to be welded in accordance with AWS. The welding procedure, weld preparation, the
welding consumables and the welding parameters, shall be qualified before welding of either
the structure or the component commences. The fabricator shall be welding procedure and list
the applicable parameters in the welding procedure qualification record (also known as PQR),
which welding procedure specification (WPS) is sample of welding before welded, which is
the formal written document provides direction to the welder or welding operators for making
quality production welds. WPS is supported by PQR.
4.4.2.4 Welding Inspection
The inspector shall conduct a VT in accordance with the requirements of DPT 1561.
Inspection and measuring shall be sufficient to enable the inspector to detect imperfections
that could occur on welds or test pieces. Prior to and during or after welding, the inspector
shall inspect the set-up of the work and ensure that
1. Welds are in accordance with the drawings.
2. The welding is carried out on the specified material with suitable equipment.
3. Correct procedures are maintained and the work is performed in accordance with
requirements standard.
Ref. code: 25615922040299ZBX
![Page 71: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/71.jpg)
60
All welds shall receive a full VT in accordance with criteria of welding defect. Welds
shall be inspected in accordance to DPT 1561 to 1565 and, where appropriate, DPT 1561 to
1565. Inspection for the relevant types of imperfections shown in Table 2.1 shall be carried
out in accordance with relevant standard, as appropriate. Repaired welds shall be respected to
the same level as that original specified or inspection and testing plan (ITP). Reporting is too
necessary in welding inspection, test reports for non-destructive examination (NDT) shall
comply with the suitable standard and shall include the following information by identity of
testing personnel and statement on whether the weld complies with the requirement of this
section. If the weld does not comply, the location and extent of the defect are given and should
have results of re-tests.
4.4.2.5 Coating
Before coating shall be surface preparation and application of coating systems shall
be in according to ISO 8501 (SA2.0 and SA2.5). coating inspection recommendations are
covered in detail in ISO 4628 for corrosion defect and ISO 19804 for coating thickness.
Standards of workmanship for each step in the system, surface preparation, suitability of
equipment, drying and curing time intervals between coats and handling, coating thickness,
and reporting.
4.4.2.6 Erection
During the erection of a structure, steelwork shall be made safe against erection
loading including loading by erection equipment or its operation, and wind. And erection
procedures, the requirements specified in fabrication procedure shall also be observed during
the erection of the steel frame and during any modifications to the steelwork in the course of
erection such as Full contact splices, Welding, Holing, and Bolting. Delivery, storage, and
handling also important because all work shall be protected from damage in transit. And
adequately protect all surfaces prepared for full contact splices, all bolts, nuts, washers,
screws, plates and articles generally shall be suitably packed and identified.
Assembly and alignment, all matching holes shall align with each other so that so that a gauge
or drift, equal in diameter to that of the bolts, shall pass freely through the assembled contact
faces at right angles to them. For bolt, the length of a bolt shall be including all bolts, at least
one clear thread shall show above the nut after tightening. And welding shall not have all type
of defect such as porosity, undercut and cracking.
Ref. code: 25615922040299ZBX
![Page 72: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/72.jpg)
61
Table 4.16 Checklist for inspection fabricated steel structure
No. Detail Note Document
1. Materials
1.1 Do all construction materials
comply with standard specified and
records available? And is there
evidence of conformity with the
material supply standard?
Material test
certificates
1.2 Has a metallurgist or a materials
engineer confirmed that the
material supplied to an alternate
internationally recognized standard
is equivalent to a material standard
referenced from TISI?
Material test
certificates
1.3 Has a metallurgist or a materials
engineer confirmed that the
material supplied to an alternate
internationally recognized standard
is equivalent to a material standard
referred to TISI?
Record of approval by
the design engineer
1.4 If the material to be replaced is
certified as equivalent to the
standard. Are the tolerances and
uniformity of the mechanical
properties (COV ≤ 10%) of the
materials supplied are in
accordance with the TISI standard?
Record of approval by
the design engineer
1.5 Has the material been supplied with
test reports or test certificates
prepared by a laboratory accredited
by signatories to the International
Laboratory Accreditation
Cooperation (ILAC) Mutual
Recognition Agreement (MRA) on
behalf of the manufacturer?
Test certificates
1.6 Are construction materials traceable
through the entire fabrication and
construction process?
As-built fabrication
drawings, traceability
record
Ref. code: 25615922040299ZBX
![Page 73: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/73.jpg)
62
Table 4.16 Checklist for inspection fabricated steel structure (Continue)
No. Detail Note Document
2. Fabrication Practice
2.1 Does the fabricator have
procedures/records to ensure that
the following operations
complies with client’s
specification and/or requirements
of customer
2.1A Tolerances Production Quality Plan
2.1B Transition of thickness and width
for seismic members
Production Quality Plan
2.1C Holing Production Quality Plan
2.1D Straightening, curving and
cambering
Production Quality Plan
2.1E Tolerances Production Quality Plan
2.2 Have all stages of construction
(including welding) been
adequately reviewed by a person
who is competent to undertake
the review?
Record of review by
construction reviewer
2.3 Does the fabricator maintain
procedures to ensure work is
within fabrication tolerances?
Does the fabricator maintain
dimensional check lists and
reports as identified in the
Quality Plan?
Dimensional inspection
checklist reports
Ref. code: 25615922040299ZBX
![Page 74: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/74.jpg)
63
Table 4.16 Checklist for inspection fabricated steel structure (Continue)
No. Detail Note Document
3. Welding
3.1 Has welding been specified in
accordance with standard as
applicable?
Project documentation
3.2 Have matters for resolution been
resolved/addressed prior to
welding and evidence exist?
Technical review
checklist
3.3 Has fabricator qualified welding
procedures prior to welding?
Approval records
required or third-party
inspection reports
3.4 Have welders been suitably
qualified to carry out tasks
according to welding procedure?
Welder/welding operator
qualification certificate
3.5 Do all construction materials to
be welded comply with the
materials listed in the standard
and evidence exist?
Material test certificates
Record design engineer’s
approval
3.6 If the answer to the above is
“not”, has the weldability of
alternative steel grade been
established and evidence exist?
PQR/WPS Qualification
test reports
3.7 Have welding consumables been
selected in accordance with the
(seismic requirements of)
standard?
Welding consumables
test certificates
3.8 Have welding consumables been
used within the welding
parameter ranges specified by
the manufacturer and the
standard?
Welding inspection
reports confirming the
suitability of WPS or
records of review
3.9 Have welding procedures been
approved prior to welding by the
design Engineer and evidence
exist?
Records or review and
approval prior to
welding.
Ref. code: 25615922040299ZBX
![Page 75: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/75.jpg)
64
Table 4.16 Checklist for inspection fabricated steel structure (Continue)
No. Detail Note Document
3. Welding
3.1 Is there evidence (e.g. inspection
reports) that welding complied
with all the appropriate
requirements of standard such as
workmanship, quality of welds
and dimensional tolerances?
Welding coordination
personnel qualification
records
3.11 Is there evidence that fabricator
complied with a quality
management system such as ISO
9001?
Certified ISO 9001
4. Welding Inspection
4.1 Has the extent of non-
destructive examination been
nominated/approved by the
design engineer?
Project documentation
4.2 Has inspection been carried out
in accordance with the standard?
Inspection reports
4.3 Has welding inspection
personnel been properly
qualified and evidence exist?
Welding inspection
personnel qualification
records
4.4 Has non-destructive
examination personnel been
properly qualified and evidence
exist?
NDT personnel
qualification records
4.5 Do final inspection reports exist
stating that inspected welds
comply with the permissible
level of imperfections of weld as
applicable?
Final inspection report
Ref. code: 25615922040299ZBX
![Page 76: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/76.jpg)
65
Table 4.16 Checklist for inspection fabricated steel structure (Continue)
No. Detail Note Document
5. Coating
5.1 Has steel surfaces been prepared
in accordance with the
requirements of standard for
coating system?
Project documentation
5.2 Has the coating system been
applied in accordance with the
requirements of standard for
coating system?
Project documentation
5.3 Has inspection of protective
coatings been carried out in
accordance with the
recommendations?
Inspection reports
5.4 Has structural steel members been
adequately protected from coating
damage during handling and
transport?
Project documentation
5.5 Has the coating system damage
by welding, erection or other
causes been adequately repaired?
Project documentation
Ref. code: 25615922040299ZBX
![Page 77: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/77.jpg)
66
Chapter 5
Conclusion
5.1 Conclusion
In this study, the defect or damage on the fabricated steelwork in Thailand. It
was found that, most of fabrication defects are found in welded. They are undercut,
overlap and porosity. Distortions due to fabrication process are also observed.
Thickness of coating is insufficient. Assembly defects are found such as improper bolts
installation, caused from poor workmanship in the construction process. These defects
can be fixed directly by redoing the construction process, such as re-weld, re-coat, and
re-install. The defect from poorly coated steel could cause a severe damage to the
structure, corrosion damage on the steel surface. In order to guarantee the safety and
serviceability of steel structures in Thailand, the Thai authorities or the third party
should strictly check the quality of steel structures.
Finally, the implementation of a fabricator accreditation in conjunction with
checklist for inspection the quality of fabricated steel structures. These two
countermeasures are essential to ensure high quality and establish standard for steel
construction in Thailand. Internationally there has been various structural steel quality
initiatives to reduce the compliance risk to all parties associated with fabrication of
structural steel. In addition, this paper aim of empowering Construction Reviewers to
more competent and fulfill their role in controlling quality, for projects featuring
structural steel.
5.2 Suggestion of Solutions
5.2.1 Fabricators Accreditation
The structural steel fabricators accreditation scheme is also important. The
Structural Steel Fabricators Accreditation Scheme will grade steel fabricators for
consist of track records, financial status, Skilled technical, human resource and the
standard of the fabrication plants. There will be three categories of fabricators
accreditation by Table 4.14 to 4.16 are Guidelines of Classification of Thai steel
constructors.as follows:
1. Category S1: Large Company
2. Category S2: Medium Company
3. Category S3: Small Company
Ref. code: 25615922040299ZBX
![Page 78: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/78.jpg)
67
5.2.2 Checklist for Inspection the Quality of Fabricated Steel Structures
Thailand needs to have a system in place to ensure quality of steel structures for
inspect the steel structure practically by using this system. So, we should have proposed
guideline to provides official with a tool to ensure quality and public safety involved
steel structures.
The checklist will include six main items as follows:
1. Material selection
2. Fabrication
3. Welding
4. Welding Inspection
5. Coating
6. Erection
Ref. code: 25615922040299ZBX
![Page 79: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/79.jpg)
68
References
AWS D1.1/D1.1M. Structural Welding Code – Steel. American Welding Society,
Miami, FL 33126, 2010.
Baughurst, L., Voznaks, G. (2009). Welding defects, causes and corrosion. Australian
Bulk Handling Review: July/August 2009, 26-28.
DPT 1561 – 51. Structural Steel welding inspection standard. Department of Public
Works and Town & Country Palnning, Thailand, 2008.
ISO 4628 – 1. Paints and Varnishes – Evaluation of degree of coatings –designation of
quantity and size of defect, and of intensity of uniform changes in appearance –
Part 1: General introduction and designation system. International Standard
Organization, Switzerland, 2003.
ISO 4628 – 2. Paints and Varnishes – Evaluation of degree of coatings –designation of
quantity and size of defect, and of intensity of uniform changes in appearance –
Part 2: Assessment of degree of blistering. International Standard Organization,
Switzerland, 2003.
ISO 4628 – 3. Paints and Varnishes – Evaluation of degree of coatings –designation of
quantity and size of defect, and of intensity of uniform changes in appearance –
Part 3: Assessment of degree of rusting. International Standard Organization,
Switzerland, 2003.
ISO 4628 – 4. Paints and Varnishes – Evaluation of degree of coatings –designation of
quantity and size of defect, and of intensity of uniform changes in appearance –
Part 4: Assessment of degree of cracking. International Standard Organization,
Switzerland, 2003.
ISO 4628 – 5. Paints and Varnishes – Evaluation of degree of coatings –designation of
quantity and size of defect, and of intensity of uniform changes in appearance –
Part 5: Assessment of degree of flaking. International Standard Organization,
Switzerland, 2003.
JASS 6. Japanese Architectural Standard Specification JASS 6 (1993) Structural
Steelwork Specification for Building Construction. Architectural Institute of
Japan, Japan, 1993.
Ref. code: 25615922040299ZBX
![Page 80: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/80.jpg)
69
JIS B 1186. Set of high strength hexagon bolt, hexagon nut and plain washers for
friction grip joints. Japanese Industrial Standard, Japan, 1995.
RCSC. Specification for Structural Joints Using High – Strength Bolts. Research
Council in Structural Connections, Chicago, Illinois, 2009.
Structural Steel Fabricators Accreditation Scheme. Singapore Structural Steel Society
(SSSS), Singapore, 13 Mar, 2016.
ISO 19840 Paints and varnishes -- Corrosion protection of steel structures by protective
paint systems -- Measurement of, and acceptance criteria for, the thickness of
dry films on rough surfaces, 2012.
International Standard Organization. ISO 8501-1 – Rust grades and preparation of
uncoated steel substrates and steel substrates after overall removal of previous
coatings, 2007.
MBMA: Metal Building Manufacturers Association, Metal Building Systems Manual,
2016.
ASTM E797 Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse
Echo Contact Method, 2015.
Fussell, A., Cowie, K., Hicks S., Karpenko, M.,. Ensuring Compliance of Structural
Steelwork - Regardless of Origin. Steel Advisor QLT1001, Steel Construction
New Zealand, 2016.
Fontana, M. (Ed). (1986). Corrosion Engineering. New York: McGraw-Hill.
Ref. code: 25615922040299ZBX
![Page 81: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/81.jpg)
70
Appendices
Ref. code: 25615922040299ZBX
![Page 82: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/82.jpg)
71
Appendix A
Reference Photo for Paint Inspection
Fig. A-1 Blistering of size no.2
(Reference: ISO 4628-2:2003, Page 3. Figure 1)
Ref. code: 25615922040299ZBX
![Page 83: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/83.jpg)
72
Fig. A-2 Blisters of size no. 3
(Reference: ISO 4628-2:2003, Page 4. Figure 2)
Ref. code: 25615922040299ZBX
![Page 84: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/84.jpg)
73
Fig. A-3 Blisters of size no. 4
(Reference: ISO 4628-2:2003, Page 5. Figure 3)
Ref. code: 25615922040299ZBX
![Page 85: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/85.jpg)
74
Fig. A-4 Blisters of size no.5
(Reference: ISO 4628-2:2003, Page 6. Figure 4)
Ref. code: 25615922040299ZBX
![Page 86: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/86.jpg)
75
Fig. A-5 Degree of rusting Ri 1
(Reference: ISO 4628-3:2003, Page 4, Figure 1)
Fig. A-6 Degree of rusting Ri grade 2
(Reference: ISO 4628-3:2003, Page 5, Figure 2)
Ref. code: 25615922040299ZBX
![Page 87: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/87.jpg)
76
Fig. A-7 Degree of rusting Ri grade 3
(Reference: ISO 4628-3:2003, Page 6, Figure 3)
Fig. A-8 Degree of rusting Ri grade 4
(Reference: ISO 4628-3:2003, Page 6, Figure 4)
Ref. code: 25615922040299ZBX
![Page 88: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/88.jpg)
77
Fig. A-9 Degree of rusting Ri grade 5
(Reference: ISO 4628-3:2003, Page 7, Figure 5)
Ref. code: 25615922040299ZBX
![Page 89: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/89.jpg)
78
Fig. A-10 Cracking without preferential direction
(Reference: ISO 4628-4:2003, Page 4, Figure 1)
Ref. code: 25615922040299ZBX
![Page 90: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/90.jpg)
79
Fig. A-11 Cracking with preferential direction
(Reference: ISO 4628-4:2003, Page 5, Figure 2)
Ref. code: 25615922040299ZBX
![Page 91: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/91.jpg)
80
Fig. A-12 Flaking without preferential direction
(Reference: ISO 4628-5:2003, Page 4. Figure 1)
Ref. code: 25615922040299ZBX
![Page 92: PROBLEMS AND COUNTERMEASURES OF THE QUALITY OF …](https://reader033.vdocuments.site/reader033/viewer/2022042811/6268cef103ed603e80178c74/html5/thumbnails/92.jpg)
81
Fig. A-13 Flaking with preferential direction
(Reference: ISO 4628-5:2003, Page 5. Figure 2)
Ref. code: 25615922040299ZBX