prince2 wallchart v1.03

1
Project Mandate Initiation notification Project authorization notification Project Board request for advice Corporate advice and decisions Closure notification PRINCE2 ® Process model version 1.03 (Based upon the manual Managing Successful Projects with PRINCE2, 2009 edition) PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries. Based upon OGC (PRINCE2®) material. Reproduced under licence from OGC Request to initiate a project Authority to initiate a project 8,9 Request to deliver a project 11, 13, Lessons Log Request to approve next Stage Plan Request to approve Exception Plan 1,3,8,10,11,12 1,8,10,11,12,13 DP Directing a Project Authorize initiation Authorize a Stage or Exception Plan Stage authorization Exception Plan approved Request for advice Exception raised 12 13 Project Board advice Premature close 14 Exception Plan request Closure recommendation Authority to deliver a Work Package Completed Work Package 8 1 Stage boundary approaching Project end approaching Premature close New issue SU Starting up a Project Products: 1. Daily Log (CU) 2. Lessons Log (C) 3. PM team role descriptions* (C) 4. PM team structure* (C) 5. (Outline) Business Case (C) 6. Project Product Description (C) 7. Project approach* (C) 8. Project Brief (C) 9. (Initiation) Stage Plan (C) Appoint the Executive & Project Manager Capture previous lessons Design and appoint the project management team Prepare the outline Business Case Select the project approach & assemble the Project Brief Plan the initiation stage Premature close IP Initiating a Project Products: 1. Risk Management Strategy (C) 2. Risk Register (CU) 3. Configuration Management Strategy (C) 4. Configuration Item Records (CU) 5. Issue Register (CU) 6. Quality Management Strategy (C) 7. Quality Register (C) 8. Communication Management Strategy (C) 9. Project controls* (C) 10. Project Plan (C) 11. Benefits Review Plan (C) 12. (Detailed) Business Case (C) 13. Project Initiation Documentation (C) 14. PM team role descriptions* (U) 15. PM team structure* (U) Prepare the Configuration Management Strategy Prepare the Communication Management Strategy Create the Project Plan Products 1. Project Plan (U) 2. Product Status Account (C) 3. Issue Register (U) 4. Additional work estimates* (C) 5. Follow on action recommendations* (C) 6. Configuration Item Records (U) 7. Benefits Review Plan (U) 8. Acceptance records* (obtain) 9. End Project Report (C) 10. Lessons Report (C) 11. Draft project closure notification* (prepare) 12. Risk Register (Close) 13. Quality Register (close) 14. Issue Register (close) 15. Daily Log (close) 16. Lessons Log (close) CP Closing a Project SB Managing a Stage Boundary Products: 1. Project Initiation Documentation (U) 2. Configuration Item Records (CU) 3. (Next) Stage Plan (C) 4. Risk Register (U) 5. Issue Register (U) 6. Quality Register (U) 7. Project Plan (U) 8. Benefits Review Plan (U) 9. Business Case (U) 10. End Stage Report (C) 11. Lessons Report (C) 12. Follow-on action recommendations* (C) 13. Exception Plan (C) Plan the next stage Update the Project Plan Report stage end PRINCE2 training specialists For more copies of this wall chart, or for information about PRINCE2 training, contact Knowledge Train at: 2nd Floor 14 Charterhouse Square London EC1M 6AX United Kingdom +44(0)20-7148-5985 | info@ knowledgetrain.co.uk www.knowledgetrain.co.uk KEY Trigger 8,9 This is a PRINCE2 process. Products which are not PRINCE2 management products are denoted by an asterisk*. The products used in the process are specified as followed: (A) - Approved (C) - Created (R) - Reviewed (U) - Updated This is an activity. Each process comprises a number of activities. This is an event or decision that triggers another process or is used to notify corporate or programme management. The arrow shows which process is triggered by the event. These show the products output from one process to another. CS Controlling a Stage Products: 1. Work Package (C) 2. Configuration Item Records (CU) 3. Issue Register (U) 4. Quality Register (U) 5. Risk Register (U) 6. Team Plan (AR) 7. Stage Plan (U) 8. Checkpoint Report (R) 9. Lessons Log (U) 10. Highlight Report (C) 11. Daily Log (U) 12. Issue Report (C) 13. Exception Report (C) 14. Risk* (raise) 15. Issue* (raise) Escalate issues and risks Report highlights MP Managing Product Delivery Products: 1. Team Plan (CU) 2. Quality Register (U) 3. Work Package (AU) 4. Risk* (raise) 5. Issue* (raise) 6. Specialist products* (C) 7. Configuration Item Records (U) 8. Checkpoint Report (C) 9. Approval records* (obtain) 7, 9, 11 Business Case 10 Authorize the project Give ad hoc direction Products: 1. Project Brief (A) 2. Initiation Stage Plan (A) 3. Lessons Log (R) 4. Project Initiation Documentation (A) 5. Benefits Review Plan (A) 6. Specialist Products* (confirm approval) 7. End Stage Report (A) 8. Lessons Report (distribute) 9. Follow on action recommendations* (distribute) 10. Stage Plan (A) 11. Exception Plan (A) 12. Highlight Report (R) 13. Exception Report (R) 14. Issue* (raise) 15. End Project Report (A) Stage boundary approaching

Upload: elena2005rai360

Post on 08-Feb-2016

87 views

Category:

Documents


0 download

DESCRIPTION

PRINCE2 Wallchart v1.03

TRANSCRIPT

Page 1: PRINCE2 Wallchart v1.03

Project Mandate

Initiation notificationProject authorization

notificationProject Board

request for advice

Corporate adviceand decisions

Closure notification

PRINCE2® Process model version 1.03

(Based upon the manual Managing Successful Projects with PRINCE2, 2009 edition)

PRINCE2® is a Registered Trade Mark of the Office of GovernmentCommerce in the United Kingdom and other countries. Based upon

OGC (PRINCE2®) material. Reproduced under licence from OGC

Request toinitiate a project

Authority toinitiate a project

8,9

Request todeliver a project

11, 13, Lessons LogRequest to approvenext Stage Plan

Request to approveException Plan

1,3,8,10,11,12

1,8,10,11,12,13

DPDirecting a Project

Authorize

initiation

Authorize a

Stage or

Exception Plan

Stage authorizationException Plan

approved

Request for advice

Exception raised

12

13

Project Board advice Premature close14 Exception Plan

request

Closurerecommendation

Authority to deliver aWork Package

CompletedWork Package

8

1

Stage boundaryapproaching

Project endapproaching

Premature close

New issue

SUStarting up a Project

Products:

1. Daily Log (CU)

2. Lessons Log (C)

3. PM team role descriptions* (C)

4. PM team structure* (C)

5. (Outline) Business Case (C)

6. Project Product Description (C)

7. Project approach* (C)

8. Project Brief (C)

9. (Initiation) Stage Plan (C)

Appoint the

Executive &

Project Manager

Capture

previous

lessons

Design and

appoint the project

management team

Prepare the

outline

Business Case

Select the

project approach

& assemble the

Project Brief

Plan the

initiation stage

Premature close

IPInitiating a Project

Products:

1. Risk Management Strategy (C)

2. Risk Register (CU)

3. Configuration Management Strategy (C)

4. Configuration Item Records (CU)

5. Issue Register (CU)

6. Quality Management Strategy (C)

7. Quality Register (C)

8. Communication Management Strategy (C)

9. Project controls* (C)

10. Project Plan (C)

11. Benefits Review Plan (C)

12. (Detailed) Business Case (C)

13. Project Initiation Documentation (C)

14. PM team role descriptions* (U)

15. PM team structure* (U)

Prepare the

Configuration

Management

Strategy

Prepare the

Communication

Management

Strategy

Create the

Project Plan

Products

1. Project Plan (U)

2. Product Status Account (C)

3. Issue Register (U)

4. Additional work estimates* (C)

5. Follow on action

recommendations* (C)

6. Configuration Item Records (U)

7. Benefits Review Plan (U)

8. Acceptance records* (obtain)

9. End Project Report (C)

10. Lessons Report (C)

11. Draft project closure notification*

(prepare)

12. Risk Register (Close)

13. Quality Register (close)

14. Issue Register (close)

15. Daily Log (close)

16. Lessons Log (close)

CP Closing a ProjectSBManaging a Stage Boundary

Products:

1. Project Initiation Documentation (U)

2. Configuration Item Records (CU)

3. (Next) Stage Plan (C)

4. Risk Register (U)

5. Issue Register (U)

6. Quality Register (U)

7. Project Plan (U)

8. Benefits Review Plan (U)

9. Business Case (U)

10. End Stage Report (C)

11. Lessons Report (C)

12. Follow-on action recommendations* (C)

13. Exception Plan (C)

Plan the

next stage

Update the

Project Plan

Report

stage end

PRINCE2training

specialists

For more copies of this wall chart, or for information about

PRINCE2 training, contact Knowledge Train at:

2nd Floor

14 Charterhouse Square

London EC1M 6AX

United Kingdom

+44(0)20-7148-5985 | info@ knowledgetrain.co.uk

www.knowledgetrain.co.uk

KEY

Trigger

8,9

This is a PRINCE2 process. Products which are not PRINCE2management products are denoted by an asterisk*. The productsused in the process are specified as followed:

(A) - Approved(C) - Created(R) - Reviewed(U) - Updated

This is an activity. Each process comprises a numberof activities.

This is an event or decision that triggers another process oris used to notify corporate or programme management.

The arrow shows which process is triggered by the event.

These show the products output from one process to another.

CSControlling a Stage

Products:

1. Work Package (C)

2. Configuration Item Records (CU)

3. Issue Register (U)

4. Quality Register (U)

5. Risk Register (U)

6. Team Plan (AR)

7. Stage Plan (U)

8. Checkpoint Report (R)

9. Lessons Log (U)

10. Highlight Report (C)

11. Daily Log (U)

12. Issue Report (C)

13. Exception Report (C)

14. Risk* (raise)

15. Issue* (raise)

Escalate

issues and risksReport highlights

MP

Managing Product Delivery

Products:

1. Team Plan (CU)

2. Quality Register (U)

3. Work Package (AU)

4. Risk* (raise)

5. Issue* (raise)

6. Specialist products* (C)

7. Configuration Item Records (U)

8. Checkpoint Report (C)

9. Approval records* (obtain)

7, 9, 11Business Case

10

Authorize

the project

Give ad hoc direction

Products:

1. Project Brief (A)

2. Initiation Stage Plan (A)

3. Lessons Log (R)

4. Project Initiation Documentation (A)

5. Benefits Review Plan (A)

6. Specialist Products* (confirm approval)

7. End Stage Report (A)

8. Lessons Report (distribute)

9. Follow on action recommendations* (distribute)

10. Stage Plan (A)

11. Exception Plan (A)

12. Highlight Report (R)

13. Exception Report (R)

14. Issue* (raise)

15. End Project Report (A)

Stage boundaryapproaching