prince street, orange, nsw civil engineering works · 2018-09-16 · adco construction pty ltd...

8
Date Scale Title Project Drawing number Drawn Checked Revision Designed Approved This drawing and design remains the property of Henry & Hymas and may not be copied in whole or in part without the prior written approval of Henry & Hymas. Architect Client REVISION AMENDMENT DATE REVISION AMENDMENT DATE DESIGNED DRAWN DESIGNED DRAWN Level 5, 79 Victoria Avenue Chatswood NSW 2067 +61 2 9417 8400 +61 2 9417 8337 [email protected] www.henryandhymas.com.au Global-Mark.com.au® 03 DIO-CV-0000 PRINCE STREET, ORANGE NSW COVER SHEET, DRAWING SCHEDULE, NOTES AND LOCALITY SKETCH J.Knight J.Sun T.Rozehnal A.Francis AUG 2018 NTS ADCO CONSTRUCTION PTY LTD GROUP GSA PTY LTD PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS LOCALITY SKETCH SCALE: NTS GENERAL NOTES: 1. ALL WORK TO BE CARRIED OUT IN ACCORDANCE WITH ORANGE CITY COUNCIL'S SPECIFICATION. CONTRACTOR TO OBTAIN AND RETAIN A COPY ON SITE DURING THE COURSE OF THE WORKS. 2. ALL NEW WORKS ARE TO MAKE A SMOOTH JUNCTION WITH EXISTING CONDITIONS AND MARRY IN A 'WORKMANLIKE' MANNER. 3. THE CONTRACTOR IS TO VERIFY THE LOCATION OF ALL SERVICES WITH EACH RELEVANT AUTHORITY. ANY DAMAGE TO SERVICES SHALL BE RECTIFIED BY THE CONTRACTOR OR THE RELEVANT AUTHORITY AT THE CONTRACTOR'S EXPENSE. SERVICES SHOWN ON THESE PLANS ARE ONLY THOSE EVIDENT AT THE TIME OF SURVEY OR AS DETERMINED FROM SERVICE DIAGRAMS. H & H CONSULTING ENGINEERS PTY. LTD CANNOT GUARANTEE THE INFORMATION SHOWN NOR ACCEPT ANY RESPONSIBILITY FOR INACCURACIES OR INCOMPLETE DATA. 4. SERVICES & ACCESSES TO THE EXISTING PROPERTIES ARE TO BE MAINTAINED IN WORKING ORDER AT ALL TIMES DURING CONSTRUCTION. 5. ADJUST EXISTING SERVICE COVERS TO SUIT NEW FINISHED LEVELS TO RELEVANT AUTHORITY REQUIREMENTS WHERE NECESSARY. 6. REINSTATE AND STABILISE ALL DISTURBED LANDSCAPED AREAS. 7. MINIMUM GRADE OF SUBSOIL SHALL BE 0.5% (1:200) FALL TO OUTLETS. 8. ALL TEMPORARY SEDIMENT AND EROSION CONTROL DEVICES ARE TO BE CONSTRUCTED, PLACED AND MAINTAINED IN ACCORDANCE WITH THE TECHNICAL SPECIFICATIONS, EROSION AND SEDIMENTATION CONTROL PLAN AND ORANGE CITY COUNCIL'S REQUIREMENTS WHERE APPLICABLE. 9. CONTRACTOR TO CHECK AND CONFIRM SITE DRAINAGE CONNECTIONS ACROSS THE VERGE PRIOR TO COMMENCEMENT OF SITE DRAINAGE WORKS. 10. PROPERTIES AFFECTED BY THE WORKS ARE TO BE NOTIFIED IN ADVANCE WHERE DISRUPTION TO EXISTING ACCESS IS LIKELY. DRAWING SCHEDULE DIO-CV-0000 COVER SHEET, DRAWING SCHEDULE, NOTES AND LOCALITY SKETCH DIO-CV-0100 GENERAL ARRANGEMENT PLAN DIO-CV-0200 STORMWATER MISCELLANEOUS DETAILS AND PIT LID SCHEDULE DIO-CV-0201 OSD TANK PLAN, SECTION AND DETAILS DIO-CV-0250 STORMWATER CATCHMENT PLAN DIO-CV-SE01 SEDIMENT AND EROSION CONTROL PLAN DIO-CV-SE02 SEDIMENT AND EROSION CONTROL SECTIONS AND DETAILS DIO-CV-SE03 SEMI PERMANENT SEDIMENT AND EROSION CONTROL PLAN - FUTURE LOT EXISTING SERVICES & FEATURES THE CONTRACTOR SHALL ALLOW FOR THE CAPPING OFF, EXCAVATION AND REMOVAL (IF REQUIRED) OF ALL EXISTING SERVICES IN AREAS AFFECTED BY WORKS WITHIN THE CONTRACT AREA OR AS SHOWN ON THE DRAWINGS UNLESS DIRECTED OTHERWISE BY THE SUPERINTENDENT. THE CONTRACTOR SHALL ENSURE THAT AT ALL TIMES SERVICES TO ALL BUILDINGS NOT AFFECTED BY THE WORKS ARE NOT DISRUPTED. PRIOR TO COMMENCEMENT OF ANY WORKS THE CONTRACTOR SHALL GAIN APPROVAL OF HIS PROGRAM FOR THE RELOCATION/ CONSTRUCTION OF TEMPORARY SERVICES. CONTRACTOR SHALL CONSTRUCT TEMPORARY SERVICES TO MAINTAIN SUPPLY TO EXISTING BUILDING REMAINING IN OPERATION DURING WORKS TO THE SATISFACTION AND APPROVAL OF THE SUPERINTENDENT. ONCE DIVERSION IS COMPLETE AND COMMISSIONED, THE CONTRACTOR SHALL REMOVE ALL SUCH TEMPORARY SERVICES AND MAKE GOOD TO THE SATISFACTION OF THE SUPERINTENDENT. INTERRUPTION TO SUPPLY OF EXISTING SERVICES SHALL BE DONE SO AS NOT TO CAUSE ANY INCONVENIENCE TO THE PRINCIPAL. CONTRACTOR TO GAIN APPROVAL FROM THE SUPERINTENDENT FOR TIME OF INTERRUPTION. EXISTING SERVICES, BUILDINGS, EXTERNAL STRUCTURES AND TREES SHOWN ON THESE DRAWINGS ARE EXISTING FEATURES PRIOR TO ANY DEMOLITION WORKS. EXISTING SERVICES UNLESS SHOWN ON SURVEY PLAN HAVE BEEN PLOTTED FROM SERVICES SEARCH PLANS AND AS SUCH THEIR ACCURACY CANNOT BE GUARANTEED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO COMPLETE A 'DIAL BEFORE YOU DIG' SEARCH AND TO ESTABLISH THE LOCATION AND LEVEL OF ALL EXISTING SERVICES PRIOR TO THE COMMENCEMENT OF ANY WORK. ANY DISCREPANCIES SHALL BE REPORTED TO THE SUPERINTENDENT. CLEARANCES SHALL BE OBTAINED FROM THE RELEVANT SERVICE AUTHORITY. ALL BRANCH GAS AND WATER SERVICES UNDER DRIVEWAYS AND BRICK PAVING SHALL BE LOCATED IN Ø80 uPVC SEWER GRADE CONDUITS EXTENDING A MINIMUM OF 500mm BEYOND EDGE OF PAVING. SITEWORKS NOTES DATUM : A.H.D. ORIGIN OF LEVELS : REFER TO BENCH OR STATE SURVEY MARKS WHERE SHOWN ON PLAN. CONTRACTOR MUST VERIFY ALL DIMENSIONS AND EXISTING LEVELS ON SITE PRIOR TO THE COMMENCEMENT OF WORK. ALL WORKS TO BE UNDERTAKEN IN ACCORDANCE WITH THE DETAILS SHOWN ON THE DRAWINGS & THE DIRECTIONS OF THE SUPERINTENDENT. EXISTING SERVICES UNLESS SHOWN ON THE SURVEY PLAN HAVE BEEN PLOTTED FROM SERVICES SEARCH PLANS AND AS SUCH THEIR ACCURACY CANNOT BE GUARANTEED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO ESTABLISH THE LOCATION AND LEVEL OF ALL EXISTING SERVICES PRIOR TO THE COMMENCEMENT OF ANY WORK. ANY DISCREPANCIES SHALL BE REPORTED TO THE SUPERINTENDENT. CLEARANCES SHALL BE OBTAINED FROM THE RELEVANT SERVICE AUTHORITY. WHERE NEW WORKS ABUT EXISTING THE CONTRACTOR SHALL ENSURE THAT A SMOOTH EVEN PROFILE, FREE FROM ABRUPT CHANGES IS ACHIEVED. THE CONTRACTOR SHALL ARRANGE ALL SURVEY SETOUT TO BE CARRIED OUT BY A REGISTERED SURVEYOR. CARE IS TO BE TAKEN WHEN EXCAVATING NEAR EXISTING SERVICES. NO MECHANICAL EXCAVATION IS TO BE UNDERTAKEN OVER TELSTRA OR ELECTRICAL SERVICES. HAND EXCAVATE IN THESE AREAS. CONTRACTOR TO OBTAIN AUTHORITY APPROVALS WHERE APPLICABLE. MAKE SMOOTH TRANSITION TO EXISTING SURFACES AND MAKE GOOD. THESE PLANS SHALL BE READ IN CONJUNCTION WITH APPROVED LANDSCAPE, ARCHITECTURAL, STRUCTURAL, HYDRAULIC AND MECHANICAL DRAWINGS AND SPECIFICATIONS OR WRITTEN INSTRUCTIONS THAT MAY BE ISSUED RELATING TO DEVELOPMENT AT THE SITE. TRENCHES THROUGH EXISTING ROAD AND CONCRETE PAVEMENTS SHALL BE SAWCUT TO FULL DEPTH OF CONCRETE AND A MINIMUM OF 50mm IN BITUMINOUS PAVING. ALL BRANCH GAS AND WATER SERVICES UNDER DRIVEWAYS AND BRICK PAVING SHALL BE LOCATED IN Ø80 uPVC SEWER GRADE CONDUITS EXTENDING A MINIMUM OF 500mm BEYOND EDGE OF PAVING. GRADES TO PAVEMENTS TO BE AS IMPLIED BY RL'S ON PLAN . GRADE EVENLY BETWEEN NOMINATED RL'S. AREAS EXHIBITING PONDING GREATER THAN 5mm DEPTH WILL NOT BE ACCEPTED UNLESS IN A DESIGNATED SAG POINT. ALL COVERS AND GRATES ETC TO EXISTING SERVICE UTILITIES ARE TO BE ADJUSTED TO SUIT NEW FINISHED SURFACE LEVELS WHERE APPLICABLE. #18757 PROPOSED SITE SURVEY INFORMATION SURVEYED BY CRAIG JAQUES & ASSOC. PTY LTD 01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018 02 ISSUED FOR DA ONLY IK JS 31.08.2018 SURVEY NOTES THE EXISTING SITE CONDITIONS SHOWN ON THE FOLLOWING DRAWINGS HAVE BEEN INVESTIGATED BY THE SURVEYOR SPECIFIED IN THE TITLE BLOCK. THE INFORMATION IS SHOWN TO PROVIDE A BASIS FOR DESIGN. HENRY AND HYMAS PTY. LTD. DOES NOT GUARANTEE THE ACCURACY OR COMPLETENESS OF THE SURVEY BASE OR ITS SUITABILITY AS A BASIS FOR CONSTRUCTION DRAWINGS. SHOULD DISCREPANCIES BE ENCOUNTERED DURING CONSTRUCTION BETWEEN THE SURVEY DATA AND ACTUAL FIELD DATA, CONTACT HENRY AND HYMAS PTY. LTD. THE FOLLOWING NOTES HAVE BEEN TAKEN DIRECTLY FROM ORIGINAL SURVEY DOCUMENTS. ORIGIN OF LEVELS .PM 9086; RL 873.445 DATUM AHD CONTOUR INTERVAL 0.2m MINOR 1.0m MAJOR. 03 ISSUED FOR DA ONLY MC JS 03.09.2018

Upload: others

Post on 25-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 03DIO-CV-0000

PRINCE STREET, ORANGE NSW

COVER SHEET, DRAWING SCHEDULE,

NOTES AND LOCALITY SKETCH

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

NTS

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

PRINCE STREET,

ORANGE, NSW

CIVIL ENGINEERING WORKS

LOCALITY SKETCHSCALE: NTS

GENERAL NOTES:

1. ALL WORK TO BE CARRIED OUT IN ACCORDANCE WITH ORANGE CITY COUNCIL'S

SPECIFICATION. CONTRACTOR TO OBTAIN AND RETAIN A COPY ON SITE DURING THE

COURSE OF THE WORKS.

2. ALL NEW WORKS ARE TO MAKE A SMOOTH JUNCTION WITH EXISTING CONDITIONS AND

MARRY IN A 'WORKMANLIKE' MANNER.

3. THE CONTRACTOR IS TO VERIFY THE LOCATION OF ALL SERVICES WITH EACH RELEVANT

AUTHORITY. ANY DAMAGE TO SERVICES SHALL BE RECTIFIED BY THE CONTRACTOR OR

THE RELEVANT AUTHORITY AT THE CONTRACTOR'S EXPENSE. SERVICES SHOWN ON

THESE PLANS ARE ONLY THOSE EVIDENT AT THE TIME OF SURVEY OR AS DETERMINED

FROM SERVICE DIAGRAMS. H & H CONSULTING ENGINEERS PTY. LTD CANNOT

GUARANTEE THE INFORMATION SHOWN NOR ACCEPT ANY RESPONSIBILITY FOR

INACCURACIES OR INCOMPLETE DATA.

4. SERVICES & ACCESSES TO THE EXISTING PROPERTIES ARE TO BE MAINTAINED IN

WORKING ORDER AT ALL TIMES DURING CONSTRUCTION.

5. ADJUST EXISTING SERVICE COVERS TO SUIT NEW FINISHED LEVELS TO RELEVANT

AUTHORITY REQUIREMENTS WHERE NECESSARY.

6. REINSTATE AND STABILISE ALL DISTURBED LANDSCAPED AREAS.

7. MINIMUM GRADE OF SUBSOIL SHALL BE 0.5% (1:200) FALL TO OUTLETS.

8. ALL TEMPORARY SEDIMENT AND EROSION CONTROL DEVICES ARE TO BE CONSTRUCTED,

PLACED AND MAINTAINED IN ACCORDANCE WITH THE TECHNICAL SPECIFICATIONS,

EROSION AND SEDIMENTATION CONTROL PLAN AND ORANGE CITY COUNCIL'S

REQUIREMENTS WHERE APPLICABLE.

9. CONTRACTOR TO CHECK AND CONFIRM SITE DRAINAGE CONNECTIONS ACROSS THE

VERGE PRIOR TO COMMENCEMENT OF SITE DRAINAGE WORKS.

10. PROPERTIES AFFECTED BY THE WORKS ARE TO BE NOTIFIED IN ADVANCE WHERE

DISRUPTION TO EXISTING ACCESS IS LIKELY.

DRAWING SCHEDULEDIO-CV-0000 COVER SHEET, DRAWING SCHEDULE, NOTES AND LOCALITY SKETCH

DIO-CV-0100 GENERAL ARRANGEMENT PLAN

DIO-CV-0200 STORMWATER MISCELLANEOUS DETAILS AND PIT LID SCHEDULE

DIO-CV-0201 OSD TANK PLAN, SECTION AND DETAILS

DIO-CV-0250 STORMWATER CATCHMENT PLAN

DIO-CV-SE01 SEDIMENT AND EROSION CONTROL PLAN

DIO-CV-SE02 SEDIMENT AND EROSION CONTROL SECTIONS AND DETAILS

DIO-CV-SE03 SEMI PERMANENT SEDIMENT AND EROSION CONTROL PLAN - FUTURE LOT

EXISTING SERVICES & FEATURES

• THE CONTRACTOR SHALL ALLOW FOR THE CAPPING OFF, EXCAVATION AND REMOVAL (IF

REQUIRED) OF ALL EXISTING SERVICES IN AREAS AFFECTED BY WORKS WITHIN THE

CONTRACT AREA OR AS SHOWN ON THE DRAWINGS UNLESS DIRECTED OTHERWISE BY

THE SUPERINTENDENT.

• THE CONTRACTOR SHALL ENSURE THAT AT ALL TIMES SERVICES TO ALL BUILDINGS NOT

AFFECTED BY THE WORKS ARE NOT DISRUPTED.

• PRIOR TO COMMENCEMENT OF ANY WORKS THE CONTRACTOR SHALL GAIN APPROVAL OF

HIS PROGRAM FOR THE RELOCATION/ CONSTRUCTION OF TEMPORARY SERVICES.

• CONTRACTOR SHALL CONSTRUCT TEMPORARY SERVICES TO MAINTAIN SUPPLY TO

EXISTING BUILDING REMAINING IN OPERATION DURING WORKS TO THE SATISFACTION AND

APPROVAL OF THE SUPERINTENDENT. ONCE DIVERSION IS COMPLETE AND

COMMISSIONED, THE CONTRACTOR SHALL REMOVE ALL SUCH TEMPORARY SERVICES AND

MAKE GOOD TO THE SATISFACTION OF THE SUPERINTENDENT.

• INTERRUPTION TO SUPPLY OF EXISTING SERVICES SHALL BE DONE SO AS NOT TO CAUSE

ANY INCONVENIENCE TO THE PRINCIPAL. CONTRACTOR TO GAIN APPROVAL FROM THE

SUPERINTENDENT FOR TIME OF INTERRUPTION.

• EXISTING SERVICES, BUILDINGS, EXTERNAL STRUCTURES AND TREES SHOWN ON THESE

DRAWINGS ARE EXISTING FEATURES PRIOR TO ANY DEMOLITION WORKS.

• EXISTING SERVICES UNLESS SHOWN ON SURVEY PLAN HAVE BEEN PLOTTED FROM

SERVICES SEARCH PLANS AND AS SUCH THEIR ACCURACY CANNOT BE GUARANTEED. IT IS

THE RESPONSIBILITY OF THE CONTRACTOR TO COMPLETE A 'DIAL BEFORE YOU DIG'

SEARCH AND TO ESTABLISH THE LOCATION AND LEVEL OF ALL EXISTING SERVICES PRIOR

TO THE COMMENCEMENT OF ANY WORK. ANY DISCREPANCIES SHALL BE REPORTED TO

THE SUPERINTENDENT. CLEARANCES SHALL BE OBTAINED FROM THE RELEVANT SERVICE

AUTHORITY.

• ALL BRANCH GAS AND WATER SERVICES UNDER DRIVEWAYS AND BRICK PAVING SHALL BE

LOCATED IN Ø80 uPVC SEWER GRADE CONDUITS EXTENDING A MINIMUM OF 500mm

BEYOND EDGE OF PAVING.

SITEWORKS NOTES

• DATUM : A.H.D.

• ORIGIN OF LEVELS : REFER TO BENCH OR STATE SURVEY MARKS WHERE

SHOWN ON PLAN.

• CONTRACTOR MUST VERIFY ALL DIMENSIONS AND EXISTING LEVELS ON SITE

PRIOR TO THE COMMENCEMENT OF WORK.

• ALL WORKS TO BE UNDERTAKEN IN ACCORDANCE WITH THE DETAILS SHOWN

ON THE DRAWINGS & THE DIRECTIONS OF THE SUPERINTENDENT.

• EXISTING SERVICES UNLESS SHOWN ON THE SURVEY PLAN HAVE BEEN

PLOTTED FROM SERVICES SEARCH PLANS AND AS SUCH THEIR ACCURACY

CANNOT BE GUARANTEED. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO

ESTABLISH THE LOCATION AND LEVEL OF ALL EXISTING SERVICES PRIOR TO

THE COMMENCEMENT OF ANY WORK. ANY DISCREPANCIES SHALL BE

REPORTED TO THE SUPERINTENDENT. CLEARANCES SHALL BE OBTAINED

FROM THE RELEVANT SERVICE AUTHORITY.

• WHERE NEW WORKS ABUT EXISTING THE CONTRACTOR SHALL ENSURE THAT A

SMOOTH EVEN PROFILE, FREE FROM ABRUPT CHANGES IS ACHIEVED.

• THE CONTRACTOR SHALL ARRANGE ALL SURVEY SETOUT TO BE CARRIED OUT

BY A REGISTERED SURVEYOR.

• CARE IS TO BE TAKEN WHEN EXCAVATING NEAR EXISTING SERVICES. NO

MECHANICAL EXCAVATION IS TO BE UNDERTAKEN OVER TELSTRA OR

ELECTRICAL SERVICES. HAND EXCAVATE IN THESE AREAS.

• CONTRACTOR TO OBTAIN AUTHORITY APPROVALS WHERE APPLICABLE.

• MAKE SMOOTH TRANSITION TO EXISTING SURFACES AND MAKE GOOD.

• THESE PLANS SHALL BE READ IN CONJUNCTION WITH APPROVED LANDSCAPE,

ARCHITECTURAL, STRUCTURAL, HYDRAULIC AND MECHANICAL DRAWINGS AND

SPECIFICATIONS

OR WRITTEN INSTRUCTIONS THAT MAY BE ISSUED RELATING

TO DEVELOPMENT AT THE SITE.

• TRENCHES THROUGH EXISTING ROAD AND CONCRETE PAVEMENTS SHALL BE

SAWCUT TO FULL DEPTH OF CONCRETE AND A MINIMUM OF 50mm IN

BITUMINOUS PAVING.

• ALL BRANCH GAS AND WATER SERVICES UNDER DRIVEWAYS AND BRICK

PAVING SHALL BE LOCATED IN Ø80 uPVC SEWER GRADE CONDUITS EXTENDING

A MINIMUM OF 500mm BEYOND EDGE OF PAVING.

• GRADES TO PAVEMENTS TO BE AS IMPLIED BY RL'S ON PLAN . GRADE EVENLY

BETWEEN NOMINATED RL'S. AREAS EXHIBITING PONDING GREATER THAN 5mm

DEPTH WILL NOT BE ACCEPTED UNLESS IN A DESIGNATED SAG POINT.

• ALL COVERS AND GRATES ETC TO EXISTING SERVICE UTILITIES ARE TO BE

ADJUSTED TO SUIT NEW FINISHED SURFACE LEVELS WHERE APPLICABLE.

#18757

PROPOSED SITE

SURVEY

INFORMATIONSURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018

02 ISSUED FOR DA ONLY IK JS 31.08.2018

SURVEY NOTES

THE EXISTING SITE CONDITIONS SHOWN ON THE FOLLOWING DRAWINGS

HAVE BEEN INVESTIGATED BY THE SURVEYOR SPECIFIED IN THE TITLE

BLOCK.

THE INFORMATION IS SHOWN TO PROVIDE A BASIS FOR DESIGN. HENRY

AND HYMAS PTY. LTD. DOES NOT GUARANTEE THE ACCURACY OR

COMPLETENESS OF THE SURVEY BASE OR ITS SUITABILITY AS A BASIS FOR

CONSTRUCTION DRAWINGS.

SHOULD DISCREPANCIES BE ENCOUNTERED DURING CONSTRUCTION

BETWEEN THE SURVEY DATA AND ACTUAL FIELD DATA, CONTACT HENRY

AND HYMAS PTY. LTD. THE FOLLOWING NOTES HAVE BEEN TAKEN DIRECTLY

FROM ORIGINAL SURVEY DOCUMENTS.

ORIGIN OF LEVELS .PM 9086; RL 873.445

DATUM AHD

CONTOUR INTERVAL 0.2m MINOR 1.0m MAJOR.

03 ISSUED FOR DA ONLY MC JS 03.09.2018

Page 2: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

DN

PRINCE STREET

ANSON STREET

DALTON STREET

RL869.75

RL869.60

RL869.60

EX870.21

869.50 869

.50

RL868.71

RL868.40

RL869.85

869.00

869.00

868.50

868.50

RL868.55

RL868.45

RL868.45

RL868.80

RL868.40 RL868.40

868.50

868.50

RL868.60

RL869.60

RL868.30

2.5%

2.5%

3%

3%

RL868.45 RL868.45RL868.50

RL868.50

RL868.50

RL870.70

RL870.70

RL870.70

RL870.70

RL870.76

RL870.74

RL869.70

RL868.50 RL868.50

RL868.50

RL868.50

RL868.50

RL868.35

RL868.47

RL868.41

RL868.47

RL868.41

RL867.70

RL870.80 RL870.80

RL868.21A 1

A 6A 5

A 2

A 3

A 4

A 7

A 8

A 9

B 1

B 2

B 3

IL868.464Ø37516.2m1.9%IL868.151

IL868.428Ø37516.2m1.9%IL868.115

IL868.115Ø37516.2m1.9%IL867.802

IL868.151Ø37516.2m1.9%IL867.838

IL867.838Ø37521.8m1.5%IL867.502

IL867.429Ø3755.8m0.5%IL867.400

IL866.919Ø37519.6m0.5%IL866.821

IL867.802Ø37521.9m1.7%IL867.429

IL867.890Ø15013.4m1.1%IL867.740

IL867.000Ø3758m1%IL866.919

IL868.100Ø15014.1m1.3%IL867.920

IL869.508Ø1508m7%IL868.950

IL869.790Ø1508.5m0.9%IL869.700

IL869.870Ø1509.4m0.9%IL868.790

IL869.952Ø1509.5m0.9%869.870

IL867.650Ø22511.8m1.3%IL867.500

D 1D 2

D 3

E 2

E 1

GD 3

GD 1

GD 2

C 1

C 2C 4

C 5

C 3PROPOSED JUNCTION PIT OVER

STREET STORMWATER PIPE

DRAINAGE OUTLET TO CONNECT

TO PUMP-OUT PIT IN BASEMENT

F 1

WATER TREATMENT CHAMBER

PROPOSED JUNCTION PIT

OVER EXISTING COUNCIL

STORMWATER SYSTEM

CATCHMENT TO CONNECT TO

PUMP-OUT IN BASEMENT

RL868.85

RL868.85

RL869.30

RL869.30

RL869.65

RL869.57

RL870.70

RL870.70

RL870.54

IL867.502Ø37514.4m0.5%IL867.429

IL869.020Ø1504m1.75%IL868.950

PROPOSED SPEED HUMP

AT THE ENTRANCE

PROVIDE FLUSH

KERB FOR

OVERFLOW

DRAINAGE LINE UNDER GROUND

SLAB SOFFIT MIN. FALL 1%

MULTI STOREY CAR PARK

DRAINAGE BY HYDRAULIC

ENGINEERS, DRAINAGE TO

CONNECT TO PITS B-2 AND B-3

RAMP TO CAR PARK 1

CAR PARK 3

FFL871.80

CAR PARK 2

FFL870.30

LOADING AND WASTE

AREA ON LOWER LEVEL

OVERFLOW FROM

RAINWATER TANK

PROPOSED OSD REFER

TO DRAWING DIO-CV-0201

FOR DETAILS.

RL868.55

G 1

G 2

G 3

G 5

G 4

RL869.56

RL869.70

RL869.30RL869.56

RL869.35

RL869.30

RL869.10

RL868.80

RL869.30 RL869.30RL869.30

RL868.85

RL868.90

RL868.85 RL868.85

RL868.45

RL868.70

RL868.80

RL868.60

RL870.80 RL870.80

RL870.75

RL870.75

RL870.75

RL870.40

GROUND

FFL 870.80

2.3%

0.8%

0.8%

2.5%

1.5%

1.5%

6.25%

2% 1%

0.7% 0.9%

RL867.65

RL867.65

2.2%

VEHICULAR CROSSING

TO BE REMOVED

RL868.40

1.2%

VEHICULAR CROSSING

TO BE REMOVED

VEHICULAR CROSSING

LOCATION TO BE

CONFIRMED

VEHICULAR CROSSING

TO BE REMOVED

PROPOSED VEHICULAR

CROSSING TO ORANGE

COUNCIL'S SPECIFICATIONS

PROPOSED VEHICULAR

CROSSING TO ORANGE

COUNCIL'S SPECIFICATIONS

RECONSTRUCT FOOTPATH IF DAMAGED

OR REQUIRED IN ACCORDANCE WITH

ORANGE COUNCIL'S REQUIREMENTS

RECONSTRUCT FOOTPATH IF

DAMAGED OR REQUIRED IN

ACCORDANCE WITH ORANGE

COUNCIL'S REQUIREMENTS

RECONSTRUCT FOOTPATH IF

DAMAGED OR REQUIRED IN

ACCORDANCE WITH ORANGE

COUNCIL'S REQUIREMENTS

RAINWATER TANK PROPOSED

LOCATION TO HYDRAULIC

ENGINEERS DETAILS

PROPOSED PIPE TO BE

STRAPPED TO OSD WALL

RL870.70

SURVEY

INFORMATIONSURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD

25m

SCALE 1:250

2015105

12345

0

01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 03DIO-CV-0100

PRINCE STREET, ORANGE NSW

GENERAL ARRANGEMENT PLAN

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

1:250 @ A1

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

GENERAL ARRANGEMENT PLANSCALE: 1:250

#18757

LEGEND

OVERLAND FLOW PATHO/F

EXISTING BOUNDARY

PROPOSED RIDGE LINE

PROPOSED VALLEY LINE

PROPOSED JUNCTION PITS

PROPOSED SURFACE INLET PITS

PROPOSED PIT TAG-A 1LINE LETTER

PIT NUMBER

STORMWATER UPSTREAM INVERT RL.STORMWATER PIPE DIAMETER & CLASSSTORMWATER PIPE LENGTHSTORMWATER PIPE GRADESTORMWATER DOWNSTREAM INVERT RL.

40.125Ø425RCP20.450m1.5%39.818

PROPOSED GRATED DRAIN

PROPOSED STORMWATER PIPE

PROPOSED CONTOURS868.50

PROPOSED SPOT LEVELRL869.60

EXISTING SPOT LEVEL870.40

VEHICULAR CROSSING TO BE REMOVED

AND REPLACED WITH KERB & GUTTER

TO ORANGE COUNCIL'S SPECIFICATION

EXISTING STORMWATER PIPE

02 ISSUED FOR DA ONLY IK JS 31.08.2018

PROPOSED STRAPPED STORMWATER PIPE

PROPOSED FLUSHING POINT (FP)

PROPOSED INTERMEDIATE RISER (IR)

FP

IR

03 ISSUED FOR DA ONLY MC JS 03.09.2018

Page 3: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

CL

(H1 & H2 SUPPORT)SCALE 1:20

O.D.

TRENCH WIDTH = O.D.+600

300

100

DESIGN PAVEMENT

SUBGRADE LEVEL

COMPACTED TO 98% SMDD

IN 150mm (MAX.) LAYERS

HAUNCH ZONE

BED ZONE

COMPACTED NON

COHESIVE BACKFILL =1/3 O.D.

COMPACTED TO 100% SMDD

IN 2x150mm(MAX.) LAYERS

COMPACTED TO 95% SMDD

IN 250mm (MAX.) LAYERS

ORDINARY FILL FREE FROM

CLAY LUMPS EXCEEDING 75mm,

STONES EXCEEDING 25mm AND

CONTAMINATE MATERIALS

CL

O.D.

TRENCH WIDTH = O.D.+600

300

100

100mm MIN. THICK TOP SOIL

COMPACTED TO 98% SMDD

IN 150mm(MAX.) LAYERS

HAUNCH ZONE

BED ZONE

COMPACTED NON

COHESIVE BACKFILL =1/3 O.D.

COMPACTED TO 100% SMDD

IN 2x150mm(MAX.) LAYERS

COMPACTED TO 95% SMDD

IN 250mm(MAX.) LAYERS

ORDINARY FILL FREE FROM

CLAY LUMPS EXCEEDING 75mm,

STONES EXCEEDING 25mm AND

CONTAMINATE MATERIALS

(H1 & H2 SUPPORT)SCALE 1:20

PIPE TRENCH INSTALLATION

IN LANDSCAPE AREAS

PIPE TRENCH INSTALLATION

BENEATH PAVEMENT

100Ø A.G. PIPE 3m IN LENGTH

DRAINING IN DIRECTION OF FALL

OF PIPE TO DOWNSTREAM PIT.

PIPE TO BE WRAPPED IN GEOFABRIC

300 MIN.

TOP LAYER

700

IF APPLICABLE

700

IF APPLICABLE

300 MIN.

TOP LAYER

TYPICAL STEP IRON DETAILSCALE 1:10

ELEVATION

300

350

100

220 45

R20 GALV. STEEL M.S.

@ 300 CTRS

PLAN SECTIONELEVATION

300 300

NOTE: SLOTTED RIGID PVC PIPE AND

FITTINGS MAY BE USED

600 MIN. UNO

LIGHT DUTY IN LANDSCAPED AND PEDESTRIAN

AREAS HEAVY DUTY IN VEHICULAR PAVEMENTS.

AIR TIGHT CAST IRON OR BRASS SCREW OR BOLT

DOWN CAP.

300x300x150

CONCRETE SURROUND

HEAVY DUTY uPVC TO BE CONNECTED

TO THE SUB SOIL DRAINAGE LINE

100 DIA RIGID PVC

45° BEND

FLUSHING POINT (FP)SCALE 1:10

600 MIN UNO

NOTE: SLOTTED RIGID PVC PIPE AND

FITTINGS MAY BE USED

LIGHT DUTY IN LANDSCAPED AND PEDESTRIAN AREAS

HEAVY DUTY IN VEHICULAR PAVEMENTS. AIR TIGHT CAST

IRON OR BRASS SCREW OR BOLT DOWN CAP

300 x 300 x 150 CONCRETE

SURROUND

45°BEND

45°BEND Y PIECE

FLOW 1% MIN

300 x 300 x 150

CONCRETE SURROUND

100Ø RIGID PVC

HEAVY DUTY uPVC

TO BE CONNECTED

TO THE SUB SOIL

DRAINAGE LINE

100 SUBSOIL DRAINAGE LINE

REFER SUBSOIL BEDDING DETAILS

INTERMEDIATE RISER (IR)SCALE 1:10

200

2-N16

N16@ 200 CENTRES

'T'

500 max.

'T'

600 lap

450 lap

1000 max.

N16 @ 200 CENTRES

EACH WAY EACH FACE

PIT REINFORCEMENT

SHOWN DASHED

HAUNCH DETAIL -TYPICALSCALE 1:10

2000mm1200 16004000

200400

800

SCALE 1:20

A = 900

H

A

H

A

B

PIPE DIA. + 150

A = 600 FOR PIPES UP TO 375 DIA.

PIT CHAMBER DIMENSIONS

FOR PIPES UP TO 600 DIA.

PIT CHAMBER FOR PIPES

GREATER THAN 600 DIA.

H = 0-900mm - AxB = 600x600mm

H = 900-1200mm - AxB = 900x600mm

H = >1200mm - AxB = 900x900mm

FOR B = 600mm - MAX. SIDE ENTRY PIPE AT 45° SKEW = 225mm

FOR B = 900mm - MAX. SIDE ENTRY PIPE AT 45° SKEW = 375mm

FOR B = 1200mm - MAX. SIDE ENTRY PIPE AT 45° SKEW = 600mm

FOR B = 1500mm - MAX. SIDE ENTRY PIPE AT 45° SKEW = 825mm

FOR B = 1900mm - MAX. SIDE ENTRY PIPE AT 45° SKEW = 1050mm

FLOW FLOW

FLOW

PIT CHAMBER FOR

SIDE ENTRY ON SKEW

TYPICAL PIT CHAMBER SIZESIT IS THE CONTRACTORS RESPONSIBILITY TO SELECT PIT CHAMBER SIZE WITH REGARDS TO PIPE SIZE, DEPTH TO

INVERT AND SKEW ANGLE. REFER SKETCHES BELOW.SELECT PIT CHAMBER USING THE STEPS BELOW:

SELECT PIT CHAMBER SIZE DEPENDING ON THE PIPE DIAMETERS.

CHECK PIT CHAMBER SIZE TO SATISFY DEPTH TO INVERT REQUIREMENTS.

CHECK PIT CHAMBER DIMENSIONS TO SATISFY THE SKEW ANGLE IN THE TABLE.

SECTIONSECTION

PLAN

PIT SIZE & DEPTH

REQUIREMENTS

1

2

3

1 1

2

3

FOR REINFORCEMENT TO WALLS

AND FLOOR OF PITS (WHERE

REQUIRED) REFER TO NOTES 10

AND 21.

FOR REINFORCEMENT TO HAUNCH SEE BELOW

NTSNTS

NTS

1000mm800600400

SCALE 1:10

0

200 100

200

PIT LID SCHEDULE

PIT/STRUCTURE NUMBER DESCRIPTION

-A 1

-A 2

DRAINAGE NOTES:1. ALL STORMWATER WORK TO COMPLY WITH AS 3500 PART 3.

2. CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING THE MINIMUM COVER OF 600mm ON ALL PIPES.

3. PROTECTION OF PIPES DUE TO LOADS EXCEEDING W7 WHEEL LOAD SHALL BE THE CONTRACTOR'S

RESPONSIBILITY.

4. BEDDING TYPE SHALL BE TYPE H2 FOR RCP. WHERE NECESSARY THE OVERLAY ZONE SHALL BE REDUCED TO

ACCOMMODATE PAVEMENT REQUIREMENTS. REFER TO THIS DRAWING FOR DETAILS.

5. MINIMUM COVER OVER EXISTING PIPES FOR PROTECTION DURING CONSTRUCTION SHALL BE 800mm.

6. NO CONSTRUCTION LOADS SHALL BE APPLIED TO PLASTIC PIPES.

7. FINISHED SURFACE LEVELS SHOWN ON LAYOUT PLAN DRGS TAKE PRECEDENCE OVER DESIGN DRAINAGE

SURFACE LEVELS.

8. ALL PIPES UP TO AND INCLUDING 300 DIA. SHALL BE SOLVENT OR RUBBER RING JOINTED PVC CLASS SH PIPE TO

AS1260. ALL OTHER PIPES TO BE RCP USING CLASS 2 RUBBER RING JOINTED PIPE. HARDIES FRC PIPE MAY BE USED

IN LIEU OF RCP IF DESIRED IN GROUND. ALL AERIAL PIPES TO BE PVC CLASS SH.

9. ALL PITS IN NON TRAFFICABLE AREAS TO BE PREFABRICATED POLYESTER CONCRETE "POLYCRETE" WITH "LIGHT

DUTY" CLASS B GALV. MILD STEEL GRATING AND FRAME.

ALL PITS IN TRAFFICABLE AREAS (CLASS "D" LOADING MAX) TO HAVE 150mm THICK CONCRETE WALLS AND BASE

CAST IN-SITU f'c=32 MPa, REINFORCED WITH N12-200 BOTH LOADING WAYS CENTRALLY PLACE .U.N.O. ON SEPARATE

DESIGN DRAWINGS IN THIS SET. GALV.MILD STEEL GRATING AND FRAME TO SUIT DESIGN LOADING. PRECAST PITS,

RECTANGULAR OR CIRCULAR IN SHAPE, MAY BE USED IN LIEU AND SHALL COMPLY WITH RELEVANT AUSTRALIAN

STANDARDS.

10. ALL PITS, GRATINGS AND FRAMES SHALL BE INSTALLED IN ACCORDANCE WITH THE MANUFACTURERS

SPECIFICATION AND TO BE IN ACCORDANCE WITH AS3500.3 AND AS3996.

11. PIT CHAMBER DIMENSIONS ARE TO BE SELECTED TO SATISFY THE FOLLOWING:

- PIPE SIZE

- DEPTH TO INVERT

- SKEW ANGLE

REFER TYPICAL PIT CHAMBER DETAILS BELOW

IF PIT LID SIZE IS SMALLER THAN THE PIT CHAMBER SIZE THEN THE PIT LID IS TO BE CONSTRUCTED ON THE CORNER

OF THE PIT CHAMBER WITH THE STEP IRONS DIRECTLY BELOW. ALTERNATIVELY THE PIT LID TO BE USED, IS TO BE

THE SAME SIZE AS THE PIT CHAMBER.

12. FOR PIPE SIZES GREATER THAN Ø300mm, PIT FLOOR IS TO BE BENCHED TO FACILITATE FLOW.

13. GALVANISED STEP IRONS SHALL BE PROVIDED AT 300 CTS FOR PITS HAVING A DEPTH EXCEEDING 1200mm.

SUBSOIL DRAINAGE PIPE SHALL BE PROVIDED IN PIPE TRENCHES ADJACENT TO INLET PIPES. (MINIMUM LENGTH 3m).

14. ALL SUBSOIL PIPES SHALL BE 100mm SLOTTED PVC IN A FILTER SOCK, UNO, WITH 3m INSTALLED UPSTREAM OF

ALL PITS.

15. ALL PIPEWORK SHALL HAVE MINIMUM DIAMETER 100.

16. MINIMUM GRADE FOR ROOFWATER DRAINAGE LINES SHALL BE 1%.

17. ALL PIPE JUNCTIONS AND TAPER UP TO AND INCLUDING 300 DIA. SHALL BE VIA PURPOSE MADE FITTINGS.

18. ALL ROOF DRAINAGE TO BE INSTALLED IN ACCORDANCE WITH AS3500, PART 3. TESTING TO BE UNDERTAKEN

AND REPORTS PROVIDED TO THE SUPERINTENDENT.

19. LOCATION OF THE DIRECT DOWN PIPE CONNECTIONS MAY VARY ON SITE TO SUIT SITE CONDITIONS, WHERE

CONNECTION SHOWN ON LONG SECTIONS CHAINAGES ARE INDICATIVE ONLY.

20. PITS IN EXCESS OF 1.5 m DEEP TO HAVE WALL AND FLOOR THICKNESS INCREASED TO 200mm. REINFORCED WITH

N12@200 CTS CENTRALLY PLACED BOTH WAYS THROUGHOUT U.N.O.ON SEPARATE DESIGN DRAWINGS IN THIS SET.

IF DEPTH EXCEEDS 5m CONTACT ENGINEER.

21. SUBSOIL DRAINAGE LINES FOR LANDSCAPE AREA NOT SHOWN ON THESE DRAWINGS. REFER TO LANDSCAPING

PLANS FOR DETAILS.

22. ALL STORMWATER PITS TO HAVE Ø100 uPVC SLOTTED SUBSOIL PIPES CONNECTED TO THEM. THESE SUBSOILS

TO EXTEND 3m UPSTREAM OF THE PIT AT A MINIMUM GRADE.

-A 5 -A 6

-A 3 -A 4

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 03DIO-CV-0200

PRINCE STREET, ORANGE NSW

STORMWATER MISCELLANEOUS DETAILS

AND PIT LID SCHEDULE

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

AS NOTED @ A1

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

PROPOSED SURFACE INLET PIT WITH 900x900 HINGED

MEDIUM DUTY GRATED LID CLASS "C" TO BE FITTED

WITH "ENVIROPOD" PIT BASKET IN ACCORDANCE

WITH LOCAL COUNCIL REQUIREMENTS.

-F 1PROPOSED JUNCTION PIT WITH 900x900 HEAVY DUTY

SEALED LID CLASS "D" IN ACCORDANCE WITH LOCAL

COUNCIL REQUIREMENTS.

-A 7 -A 8 -A 9 -B 1 -B 2 -B 3

PROPOSED 900x900 GRATED ACCESS LID HEAVY DUTY

CLASS "D" WITHIN OSD TANK IN ACCORDANCE WITH

LOCAL COUNCIL REQUIREMENTS.

PROPOSED 300x300 DRAINAGE OUTLETS IN ACCORDANCE

WITH LOCAL COUNCIL REQUIREMENTS.-C 3 -C 4 -C 5 -D 1 -D 2 -D 3

-GD 2200mm WIDE LIGHT DUTY GRATED DRAIN AND LIGHT

DUTY FRAME CLASS "B" IN ACCORDANCE WITH LOCAL

COUNCIL REQUIREMENTS.

-1GD

300mm WIDE HEAVY DUTY GRATED DRAIN AND HEAVY

DUTY FRAME CLASS "D" IN ACCORDANCE WITH LOCAL

COUNCIL REQUIREMENTS.

-3GD

-E 1PROPOSED SURFACE INLET PIT WITH 900x900 HINGED

HEAVY DUTY GRATED LID CLASS "D" IN ACCORDANCE

WITH LOCAL COUNCIL REQUIREMENTS.

-E 2

-G 1 -G 2 -G 3 -G 4 -G 5

SURVEY

INFORMATIONSURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018

-C 2

02 ISSUED FOR DA ONLY IK JS 31.08.2018

#18757

-C 1

03 ISSUED FOR DA ONLY MC JS 03.09.2018

Page 4: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

PROPOSED OSD TANKAREA PROVIDED = 150m²

VOLUME REQUIRED = 130m³

(OSD FOOTINGS, WALL AND COLUMNS TO

STRUCTURAL ENGINEERS DETAILS)

G 3G 2

G 1

G 5 A 3A 4IL867.25IL867.25 IL867.10

STORMFILTER CHAMBER26 x 460mmPSORB

STORMFILTER

IL867.17

IL867.23

IL867.25 IL867.25

1%

1%

Ø375 INLET PIPE

Ø375 OUTLET PIPE

A-

4000

5000

9600

2400

8900

9100

7200

18000

G 4

OVERFLOW FROM

RAINWATER TANK

PIPE TO BE STRAPPED TO

OSD WALL. REFER TO DETAIL

Ø300

500

50 TYP.FIX TO TANK WALL USING 4M10

MASONARY ANCHORS NON

REMOVABLE.

5mm STAINLESS STEEL PLATE

500

ORIFICE PLATE DETAILSCALE 1:10

DEBRIS SCREEN DETAILNOT TO SCALE

ALL STEEL TO BE HOT DIPPED GALVANISED

LIFTING HANDLES

DEBRIS SCREEN WELDLOK A40/203

(HOT DIPPED GALVANISED)

1.0m² AREA OF THE SCREEN

(20xORIFICE)

60 x 5mm LOCK DOWN PLATE

WITH PENETRATION. REFER DETAIL

100 x 16 MOUNTING BAR WITH

BRACKETS, SCREEN TO BE ATTACHED

(GENERALLY ON A SLIDING MECHANISM)

TO THE WALL, BUT SHOULD BE

REMOVABLE (WITHOUT THE USE OF

TOOLS) TO PERMIT CLEANSING AND

EASY INSPECTION OF THE OUTLET

CONTROL. ALL STEEL TO BE HOT

DIPPED GALVANISED.

SCREEN TYPE WELDLOK A40/203 IS

RECOMENDED FOR ORIFICES LARGER

THAN 150mm AND SCREEN AREA 20 x

THE ORIFICE AREA FOR THAT TYPE OF

SCREEN - REFER UPRCT SECTION 4-13

MAXIMESH RH3030 IS RECOMMENDED

FOR ORIFICES LESS THAN 150mm IN

DIAMETER AND SCREEN AREA 50xTHE

ORIFICE AREA REFER BURWOOD

COUNCIL AND UPPER PARRAMATTA

RIVER CATCHMENT TRUST HANDBOOK.

TWL 868.25 (100ARI)

RL867.94

RL868.10

RL868.45RL868.55

PROPOSED 900x900 HEAVY

DUTY ACCESS LID CLASS 'D'900

RL867.10

4xØ90 RELIEF DRAIN WITH 10mm AGGREGATE

SURROUND WRAPPED IN GEOTEXTILE FABRIC

IL867.00

26x460mm PSORB STORMFILTER CARTRIDGES

A-1:25

PROPOSED Ø375mm OUTLET

PIPE TO COUNCIL'S SYSTEM

INSTALL GALVANISED STEP

IRONS @ 300 CTS, TYPICAL.

REFER DETAIL ON DRAWING

DIO-CV-0200PROPOSED OSD TANKAREA PROVIDED = 150m²

VOLUME REQUIRED = 130m³

(OSD FOOTINGS, WALL AND COLUMNS TO

STRUCTURAL ENGINEERS DETAILS)

�867.15

PROPOSED DEBRIS SCREEN

REFER TYPICAL DETAIL

STAGED DISCHARGE WEIR

Ø300 ORIFICE PLATE

REFER TO DETAIL

150mm FALSE FLOOR

PROVIDE MASS CONCRETE

TO INVERT OF OUTLET PIPE

PROPOSED 900x900 HEAVY

DUTY ACCESS LID CLASS 'D'

RL866.90

Ø375 INLET PIPE

900

PROPOSED 900x900 HEAVY

DUTY ACCESS LID CLASS 'D'

900

PROPOSED 900x900 HEAVY

DUTY ACCESS LID CLASS 'D'900

UNDERDRAIN OUTLET

RL868.45

RL867.25

RL867.40

G 1G 5 A 3

A 4

PIPE STRAP DETAILSCALE: N.T.S.

8mm x 50 GALVANISED HOLD

DOWN STRAP AT 2000 CENTRES

1-M16'L'BOLT CAST INTO SLAB.

100 COG AT BOTTOM

1-N12 x 600 LONG

80 x 50 x 16mm GALVANISED

PLATE WELDED TO STRAP

OSD TANK WALL

2500mm1500 20005000

100300500

1000

SCALE 1:25

OSD TANK PLANSCALE: 1:50

1000mm800600400

SCALE 1:10

0

200 100

200

5000mm3000 400010000

2006001000

2000

SCALE 1:50

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE

Surveyor

DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 03DIO-CV-0201

PRINCE STREET, ORANGE NSW

OSD TANK PLAN, SECTION AND DETAILS

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

AS NOTED @ A1

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

#18757

FLOW L/s 20YR 100YR

PRE-DEVELOPMENT 247 394

POST-DEVELOPMENT 199 312

SURVEY

INFORMATIONSURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018

02 ISSUED FOR DA ONLY IK JS 31.08.2018

03 ISSUED FOR DA ONLY MC JS 03.09.2018

Page 5: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

DN

PRINCE STREET

ANSON

STREET

DALTON STREET

AREA = 2746m²

AREA = 2417m²

AREA = 3349.9m²

AREA = 186m²

AREA = 1345m²

25m

SCALE 1:250

2015105

12345

0

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 03DIO-CV-0250

PRINCE STREET, ORANGE NSW

STORMWATER CATCHMENT PLAN

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

1:250 @ A1

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

STORMWATER CATCHMENT PLANSCALE: 1:250

#18757

TOTLA SITE AREA: 9951m²

CATCHMENT TO OSD TANK

VIA PIT & PIPE SYSTEMAREA: 3349.95m²

CATCHMENTS CONNECT TO

OSD FROM RAINWATER TANKS

AREA: 5163m²

CATCHMENTS BYPASS OSD

AREA: 186m²

SURVEY

INFORMATION

SURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD

01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018

02 ISSUED FOR DA ONLY IK JS 31.08.2018

03 ISSUED FOR DA ONLY MC JS 03.09.2018

Page 6: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

DN

PRINCE STREET

ANSON STREET

DALTON STREET

FALL

PROPOSED STOCKPILE LOCATION

PROPOSED STABILISED SITE

ACCESS AND SHAKER GRID

PROPOSED SEDIMENT

BASIN VOLUME = 163.8m³

FALL

FALL

FALL

FALL

PROPOSED SEDIMENTATION FENCE

DIVERSION CATCH DRAIN

PROPOSED HAYBALE FILTER

PROPOSED HAYBALE FILTER

25m

SCALE 1:250

2015105

12345

0

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 03DIO-CV-SE01

PRINCE STREET, ORANGE NSW

SEDIMENT AND EROSION CONTROL PLAN

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

1:250 @ A1

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

SEDIMENT AND EROSION CONTROL PLANSCALE: 1:250

LEGEND

CATCH DIVERSION DRAIN

TRAFFIC MANOEUVRING

OVERLAND FLOW PATHO/F

PROPOSED SEDIMENTATION FENCE

PROPOSED VEHICLE SHAKER GRID

PROPOSED STABILISED SITE ACCESS

PROPOSED STOCKPILE LOCATION

PROPOSED HAYBALE FILTER

SEDIMENT & EROSION CONTROL NOTES

• ALL SEDIMENT CONTROL DEVICES ARE TO BE CONSTRUCTED, PLACED AND

MAINTAINED IN ACCORDANCE WITH RESPECTIVE COUNCIL SPECIFICATIONS

AND LANDCOM'S "SOIL AND CONSTRUCTION" MANUAL.

• ALL PERIMETER & SILTATION CONTROL MEASURES ARE TO BE PLACED PRIOR

TO, OR AS THE FIRST STEP IN EARTH WORKS AND/OR CLEARING.

• THE SEDIMENT & EROSION CONTROL PLAN MAY REQUIRE FUTURE

ADJUSTMENT TO REFLECT CONSTRUCTION STAGING. IT IS ALSO THE

CONTRACTORS RESPONSIBILTY TO PREPARE THEIR OWN SEDIMENT AND

EROSION CONTROL PLAN WHICH SUITS THE DESIGNED CONSTRUCTION

STAGING.

• FILTRATION BUFFER ZONES ARE TO BE FENCED OFF AND ACCESS PROHIBITED

TO ALL PLANT AND MACHINERY.

• ALL TEMPORARY EARTH BERMS, DIVERSIONS & SILT DAM EMBANKMENTS ARE

TO BE MACHINE COMPACTED, SEEDED & MULCHED FOR TEMPORARY

VEGETATION COVER AS SOON AS THEY HAVE BEEN FORMED.

• ALL SEDIMENT TRAPPING STRUCTURES AND DEVICES ARE TO BE INSPECTED

AFTER STORMS FOR STRUCTURAL DAMAGE OR CLOGGING. TRAPPED MATERIAL

IS TO BE REMOVED TO A SAFE LOCATION.

• ALL TOPSOIL IS TO BE STOCKPILED ON SITE FOR REUSE (AWAY FROM TREES

AND DRAINAGE LINES). MEASURES SHALL BE APPLIED TO PREVENT EROSION

OF THE STOCKPILES.

• ALL EARTHWORK AREAS SHALL BE ROLLED EACH EVENING TO SEAL THE

EARTHWORKS.

• ALL FILLS ARE TO BE LEFT WITH A LIP AT THE TOP OF THE SLOPE AT THE END.

ALL CUT AND FILL SLOPES ARE TO BE SEEDED AND STRAW MULCHED WITHIN

14 DAYS OF COMPLETION OF FORMATION U.N.O. BY LANDSCAPE ARCHITECTS.

• UPON COMPLETION OF ALL EARTHWORKS OR AS DIRECTED BY COUNCIL SOIL

CONSERVATION TREATMENTS SHALL BE APPLIED SO AS TO RENDER AREAS

THAT HAVE BEEN DISTURBED, EROSION PROOF WITHIN 14 DAYS.

• EROSION AND SILT PROTECTION MEASURES ARE TO BE MAINTAINED AT ALL

TIMES.

SURVEY

INFORMATIONSURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018

02 ISSUED FOR DA ONLY IK JS 31.08.2018

#18757

03 ISSUED FOR DA ONLY MC JS 03.09.2018

Page 7: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 03DIO-CV-SE02

PRINCE STREET, ORANGE NSW

SEDIMENT AND EROSION CONTROL

SECTIONS AND DETAILS

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

NTS @ A1

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

CATCH DRAINS SD 5-8SCALE N.T.S.

CATCH DRAIN CONSTRUCTION NOTES:1. CONSTRUCT ALONG GRADIENT AS SPECIFIED.

2. MAXIMUM SPACING BETWEEN BANKS SHALL BE 80 METRES.

3. DRAINS TO BE OF PARABOLIC OR TRAPEZOIDAL CROSS SECTION NOT V-SHAPED.

4. EARTH BANKS TO BE ADEQUATELY COMPACTED IN ORDER TO PREVENT FAILURE.

5. CONSTRUCTION IS OF A TEMPRORARY NATURE AND SHALL BE COMPACTED AT THE END A DAYS WORK OR

IMMEDIATELY PRIOR RAIN.

6. ALL OUTLETS FROM DISTURBED LANDS ARE TO FEED INTO SEDIMENT BASIN OR SIMILAR.

7. DISCHARGE RUNOFF COLLECTED FROM UNDISTURBED LANDS ONTO EITHER A STABILISED OR AN UNDISTURBED

DISPOSAL AISTE WITHIN THE SAME SUBCATCHMENT AREA FROM WHICH THE WATER ORIGINATED.

8. COMPACT WITH A SUITABLE IMPLEMENT IN SITUATIONS WHERE THEY ARE REQUIRED TO FUNCTION FOR MORE

THAN FIVE DAYS.

9. EARTH BANKS TO BE FREE OF PROJECTIONS OR OTHER IRREGULARITIES THAT WILL IMPEDE NORMAL FLOW.

NOTE: ONLY TO BE USED AS TEMPORARY BANK WHERE

MAC.UPSLOPE LENGTH IS 80 METERS.

80 METRE MAX.UPSLOPE

DIRECTION OF FLOW

CHANNE

L GRADIE

NT 1-5%

ALL BA

TTER G

RADES

1(V) : 2

(H) MA

X.

200 mm MIN.

150 mm MIN.

2 METRES MIN.

SECTION DETAIL

1.5m STAR PICKETS@ MAX. 2.5m CENTRES

SELF-SUPPORTINGGEOTEXTILE

DIRECTION OF FLOW

ON SOIL, 150mm x 100mmTRENCH WITH COMPACTEDBACKFILL AND ON ROCK, SETINTO SURFACE CONCRETE

DISTURBED AREA DIRECTION OFFLOW

1.5m STAR PICKETS@ MAX. 2.5m CENTRES

UNDISTURBED AREAS

PLAN

FLOWSTAR PICKETS @ MAX.2.5m SPACINGS TYPICAL

SEDIMENT FENCESCALE N.T.S.

MIN. 1.5m

20m MAX.

600m

m MIN.

500 - 600m

m

SEDIMENT FENCE CONSTRUCTION NOTES:1. CONSTRUCT SEDIMENT FENCES AS CLOSE AS POSSIBLE TO BEING PARALLEL TO THE CONTOURS OF THE

SITE, BUT WITH SMALL RETURNS AS SHOWN IN THE DRAWING TO LIMIT THE CATCHMENT AREA OF ANY ONE

SECTION. THE CATCHMENT AREA SHOULD BE SMALL ENOUGH TO LIMIT WATER FLOW IF CONCENTRATED

AT ONE POINT TO 50 LITRES PER SECOND IN THE DESIGN STORM EVENT, USUALLY THE 10-YEAR EVENT.

2. CUT A 150mm DEEP TRENCH ALONG THE UPSLOPE LINE OF THE FENCE FOR THE BOTTOM OF THE FABRIC

TO BE ENTRENCHED.

3. 3. DRIVE 1.5m LONG STAR PICKETS INTO GROUND @ 2.5m INTERVALS (MAX.) AT THE DOWNSLOPE EDGE OF

THE TRENCH. ENSURE ANY STAR PICKETS ARE FITTED WITH SAFETY CAPS.

4. 4. FIX SELF-SUPPORTING GEOTEXTILE TO THE UPSLOPE SIDE OF THE POSTS ENSURING IT GOES TO THE

BASE OF THE TRENCH. FIX THE GEOTEXTILE WITH WIRE TIES OR AS RECOMMENDED BY THE

MANUFACTURER. ONLY USE GEOTEXTILE SPECIFICALLY PRODUCED FOR SEDIMENT FENCING. THE USE OF

SHADE CLOTH FOR THIS PURPOSE IS NOT SATISFACTORY.

5. 5. JOIN SECTIONS OF FABRIC AT A SUPPORT POST WITH A 150mm OVERLAP. 6. BACKFILL THE TRENCH

OVER THE BASE OF THE FABRIC AND COMPACT IT THOROUGHLY OVER THE GEOTEXTILE.

BUFFER ZONE

GRASSED AREA

ANGLE FIRST STAKE

TOWARDS PREVIOUSLY

LAID BALE

100mm

DEEP

DIRECTION

OF FLOW

DISTURBED AREA

BLUE METAL

STAKES DRIVEN 500-700mm

INTO THE GROUND

N.T.S.

HAYBALE BARRIERS

EARTH BANK

FLOW

STABILISE STOCKPILE SURFACE

2:1 SL

OPE (M

AX.) 2:1 SLOPE (MAX.)

SEDIMENT FENCE

STOCKPILE CONSTRUCTION NOTES:PLACE STOCKPILES MORE THAN 2 (PREFERABLY 5) METRES FROM EXISTING VEGETATION,CONCENTRATED WATER FLOW, ROADS AND HAZARD AREAS.CONSTRUCT ON THE CONTOUR AS LOW, FLAT, ELONGATED MOUNDS.WHERE THERE IS SUFFICIENT AREA, TOPSOIL STOCKPILES SHALL BE LESS THAN 2 METRES IN HEIGHT.WHERE THEY ARE TO BE PLACED FOR MORE THAN 10 DAYS, STABILISE FOLLOWING THE APPROVEDE.S.C.P. OR S.W.M.P. TO REDUCE THE C-FACTOR TO LESS THAN 0.10.CONSTRUCT EARTH BANKS ON THE UPSLOPE SIDE TO DIVERT WATER AROUND STOCKPILES ANDSEDIMENT FENCES 1 TO 2 METRES DOWNSLOPE.

1.

2.3.4.

5.

STOCKPILESSCALE N.T.S.

RUNOFF DIRECTED TO

SEDIMENT TRAP/ FENCE

GEOTEXTILE FABRIC DESIGNED TO PREVENT

INTERMIXING OF SUB GRADE AND BASE

MATERIALS AND TO MAINTAIN GOOD

PROPERTIES OF THE SUB-BASE LAYERS. GEOTEXTILE MAY BE A WOVEN OR NEEDLE

PUNCHED PRODUCT WITH A MINIMUM CBR

BURST STRENGTH (AS3706.4-90) OF 2500 N

DGB 20 ROAD BASE OR

30mm AGGREGATE. 150mm

THICK MIN TO BE PLACED

OVER GEOTEXTILE FABRIC

N.T.S.

MIN LENGTH 15 METERS

PROPERTY BO

UNDARY

EXISTING ROADWAY

300mm MIN

MIN WIDTH 3

METERS

STABILISED SITE ACCESS WITH SHAKER RAMP

CONSTRUCTION SITE

NOTES:

1. THIS DEVICE IS TO BE LOCATED AT ALL EXITS FROM

CONSTRUCTION SITE.

2. THIS DEVICE IS TO BE REGULARLY CLEANED OF DEPOSITED

MATERIAL SO AS TO MAINTAIN A 50mm DEEP SPACE BETWEEN

PLANKS.

3. ANY UNSEALED ROAD BETWEEN THIS DEVICE AND NEAREST

ROADWAY IS TO BE TOPPED WITH 100mm THICK 40-70mm SIZE

AGGREGATE.

4. ALTERNATIVELY, THREE(3) PRECAST CONCRETE CATTLE GRIDS

(AS MANUFACTURED BY "HUMES CONCRETE MAY BE USED. 1, 2

& 3 ABOVE ALSO APPLY.

PLAN

STABILISED SITE ACCESS WITH SHAKER RAMPN.T.S.

PROPERTY BOUNDARY

EXISTING ROADWAY

min 15 m

150mm THICK 40-70mm

AGGREGATE

SHAKER RAMP

OF TIMBER OR

STEEL SLATS

200m

m M

IN

SEDIMENT SETTLING ZONEOVERFLOW SPILLWAY

TYPE 'D' & 'F' SEDIMENTATION BASIN

1500

INFLOW

12

600

SEDIMENT STORAGE ZONE

TYPICAL SECTION

N.T.S.

SPILLWAYCREST

21

SEDIMENTATION BASIN CALCULATIONS:

(FOR TYPE D & F SOILS) - PER 1 ha

OVERFLOW

SPILLWAY

PERSPECTIVE VIEW

B1

B

INFLOW

BASIN CAPACITY = SETTLING ZONE + SEDIMENT STORAGE ZONE

Settling Zone = 10 x Cv x A x R(y %ile , 5 day)

= 10 x 0.5 x 1.06 x 20.6

= 109.18 m³

and

Sediment Storage Zone = 50 % Settling Zone

= 0.5 x 109.18 m³

= 54.59 m³

therefore

BASIN CAPACITY = 109.18 + 54.59 = 163.8 m³

The basin is to be a slow settling basin with a slow discharge to the level of

required storage capacity. This will mean that sediment will settle over a period

of approximatly 5 days.

SURVEY

INFORMATIONSURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD01 ISSUED FOR INFORMATION ONLY IK JS 24.08.2018

02 ISSUED FOR DA ONLY IK JS 31.08.2018

#18757

03 ISSUED FOR DA ONLY MC JS 03.09.2018

Page 8: PRINCE STREET, ORANGE, NSW CIVIL ENGINEERING WORKS · 2018-09-16 · adco construction pty ltd group gsa pty ltd prince street, orange, nsw civil engineering works locality sketch

PRINCE STREET

DALTON STREET

PROPOSED SEDIMENT

BASIN VOLUME = 159m³

PROPOSED HAYBALE FILTER

PROPOSED HAYBALE FILTER

DIVERSION CATCH DRAIN

DIVERSION CATCH DRAIN

PROVIDE RAISED STORMWATER

PIT FOR EMERGENCY OVERFLOW

TO EXISTING Ø300 STUB

FUTURE LOT

PROPOSED

DEVELOPMENT

LOT

PIT RL TO BE CONSTRUCTED AT 300mm

BELOW TOP OF BASIN. REQUIRED VOLUME

TO BE PROVIDED BELOW TOP OF PIT RL

CONNECT PIT TO

EXISTING STUB

SALE

STREET

25m

SCALE 1:250

2015105

12345

0

Date

Scale

Title

Project

Drawing number

Drawn

Checked

Revision

Designed

Approved

This drawing and design remains the property of Henry & Hymas and may not becopied in whole or in part without the prior written approval of Henry & Hymas.

Architect

Client

REVISION AMENDMENT DATEREVISION AMENDMENT DATE DESIGNEDDRAWNDESIGNEDDRAWN

Level 5,

79 Victoria Avenue

Chatswood NSW 2067

+61 2 9417 8400

+61 2 9417 8337

[email protected]

www.henryandhymas.com.auGlobal-Mark.com.au® 02DIO-CV-SE03

PRINCE STREET, ORANGE NSW

SEMI PERMANENT SEDIMENT AND

EROSION CONTROL PLAN - FUTURE LOT

J.Knight J.Sun

T.Rozehnal A.Francis

AUG 2018

1:250 @ A1

ADCO CONSTRUCTION PTY LTD

GROUP GSA PTY LTD

SEMI PERMANENT SEDIMENT AND EROSION CONTROL PLANSCALE: 1:250

LEGEND

CATCH DIVERSION DRAIN

PROPOSED SEDIMENTATION FENCE

PROPOSED HAYBALE FILTER

SEDIMENT & EROSION CONTROL NOTES

• ALL SEDIMENT CONTROL DEVICES ARE TO BE CONSTRUCTED, PLACED AND

MAINTAINED IN ACCORDANCE WITH RESPECTIVE COUNCIL SPECIFICATIONS

AND LANDCOM'S "SOIL AND CONSTRUCTION" MANUAL.

• ALL PERIMETER & SILTATION CONTROL MEASURES ARE TO BE PLACED PRIOR

TO, OR AS THE FIRST STEP IN EARTH WORKS AND/OR CLEARING.

• THE SEDIMENT & EROSION CONTROL PLAN MAY REQUIRE FUTURE

ADJUSTMENT TO REFLECT CONSTRUCTION STAGING. IT IS ALSO THE

CONTRACTORS RESPONSIBILTY TO PREPARE THEIR OWN SEDIMENT AND

EROSION CONTROL PLAN WHICH SUITS THE DESIGNED CONSTRUCTION

STAGING.

• FILTRATION BUFFER ZONES ARE TO BE FENCED OFF AND ACCESS PROHIBITED

TO ALL PLANT AND MACHINERY.

• ALL TEMPORARY EARTH BERMS, DIVERSIONS & SILT DAM EMBANKMENTS ARE

TO BE MACHINE COMPACTED, SEEDED & MULCHED FOR TEMPORARY

VEGETATION COVER AS SOON AS THEY HAVE BEEN FORMED.

• ALL SEDIMENT TRAPPING STRUCTURES AND DEVICES ARE TO BE INSPECTED

AFTER STORMS FOR STRUCTURAL DAMAGE OR CLOGGING. TRAPPED MATERIAL

IS TO BE REMOVED TO A SAFE LOCATION.

• ALL TOPSOIL IS TO BE STOCKPILED ON SITE FOR REUSE (AWAY FROM TREES

AND DRAINAGE LINES). MEASURES SHALL BE APPLIED TO PREVENT EROSION

OF THE STOCKPILES.

• ALL EARTHWORK AREAS SHALL BE ROLLED EACH EVENING TO SEAL THE

EARTHWORKS.

• ALL FILLS ARE TO BE LEFT WITH A LIP AT THE TOP OF THE SLOPE AT THE END.

ALL CUT AND FILL SLOPES ARE TO BE SEEDED AND STRAW MULCHED WITHIN

14 DAYS OF COMPLETION OF FORMATION U.N.O. BY LANDSCAPE ARCHITECTS.

• UPON COMPLETION OF ALL EARTHWORKS OR AS DIRECTED BY COUNCIL SOIL

CONSERVATION TREATMENTS SHALL BE APPLIED SO AS TO RENDER AREAS

THAT HAVE BEEN DISTURBED, EROSION PROOF WITHIN 14 DAYS.

• EROSION AND SILT PROTECTION MEASURES ARE TO BE MAINTAINED AT ALL

TIMES.

SURVEY

INFORMATIONSURVEYED BY CRAIG

JAQUES & ASSOC. PTY LTD01 ISSUED FOR DA ONLY IK JS 31.08.2018

#18757

02 ISSUED FOR DA ONLY MC JS 03.09.2018