3/21/2015 PrimaveraP6PercentCompleteTypes|TenSixConsulting
http://tensix.com/2013/07/primaverap6percentcompletetypes/ 1/4
Searchthesite
07/23/13
byTheP6Pro
WhenaddingactivitiestoaPrimaveraP6EPPMorProfessionalschedule,youhavethreepossiblepercentcompletetypestochoosefrom:Duration,PhysicalandUnits.Whichoneyouchoosedependsonyourdesiredoutcome.ThisarticleexplainseachofthePrimaveraP6activitypercentcompetechoices,whenyoushoulduseaparticularpercentcompletetypeandhowtheyaffectyourprocessforenteringstatustoyourprojectsschedule.
TheActivity%CompleteField
Beforewegetintothespecificsofthepercentcompletetypes,weneedtotakeaquicklookattheActivity%Completefield.Thisfieldsexistencecanbealittleconfusingbecauseitsoundslikeanotherpercentcompletetype.Howeveritis,infact,afield(column)intowhichavaluecanbeplacedtoupdatethevalueintheactivitysselectedpercentcompletetypefield.Inotherwordsyoudontneedtoaddacolumnforallthreepercentcompletetypesthatyoumightbeusingwithinaschedule,ratheryoujustaddtheActivity%Completefield,andenteryourvaluesthere.
AnyoptionthatreducesthenumberofcolumnsyouneedtohavedisplayedinyourP6tableareaisagoodthing.
Duration%Complete
Thisoptionisusedtocalculateprogressfromtheplannedandremainingdurationvalues.Forexample,ifyouenter6daysofremainingdurationfora10daydurationactivity,PrimaveraP6willcalculate40%complete.Transversely,ifyouenter40%intheActivity%Completefield,P6willcalculatearemainingdurationof6days.
OriginalorPlannedDurationRemainingDuration=PercentComplete
Usage:
EnterapercentcompletevalueintheActivity%CompletecolumnordirectlyintotheDuration%Completecolumn.PrimaveraP6willautomaticallycalculatetheRemainingDurationfortheactivity.OrenteraRemainingDurationvalueandletP6calculatethepercentage.
CATEGORIESDeltekCobraEarnedValueMgmtMicrosoftProjectNewsPrimaveraP6ProjectManagementTraining
ARCHIVES[+]2015[+]2014[+]2013[+]2012[+]2011
Joinourmailinglist.
CONTACTUS
(703)9102600
Name
Email
Comment
Typethecharactersabove
SUBMIT
Consul tingServices
SoftwareServices
Tra in ing
Blog
Cl ients
ContactUs
AboutTenSix
PRIMAVERA P6 PERCENT COMPLETETYPES
-
3/21/2015 PrimaveraP6PercentCompleteTypes|TenSixConsulting
http://tensix.com/2013/07/primaverap6percentcompletetypes/ 2/4
Thispercentcompletetypeisbestusedformorelevelofefforttypeactivitieswheremeasurabledeliverablesarenotexpectedandthepercentcompleterepresentselapsedtimemorethandeliverablescompleted.
Physical%Complete
Thepercentcompletevalueswillbeenteredbytheusermanually.EnteringavalueintheActivity%CompletefieldwillupdatethePhysical%Completevalue.ThePhysical%CompletetypeisrequiredifyouwishtouseStepstodriveprogress.
Caution:WhenPhysical%Completeisused,youmustadjusttheRemainingDurationasthisisnotcalculatedbyPrimaveraP6.YoumustenteraRemainingDurationmanually,orsetanExpectedFinishdateontheactivity.
IfyoudontadjusttheRemainingDuration,P6willaddtheActualDurationtotheRemainingDuration.Thiswillcauseunnecessaryvarianceintheprojectandwilllikelyalteryourcriticalpath.Asyoucanseeinthefollowingfigure,theRemainingDurationremainedat10days,theActualDurationwasaddedtoit,givinganAtCompletionDurationof14days,andpushingallsuccessoractivitiesoutbutthatamount.
YoucanusetheExpectedFinishdateoptiontohelpcontroltheremainingdurationofPhysical%Completeactivities.AddingadateintheExpectedFinishdatefieldlocksdowntheenddateoftheactivityandforcesP6tocalculatetheRemainingDuration.
IntheaboveimageyoucanseethatanExpectedFinishdateof27Jan15haspulledtheenddatebacktoitsoriginaldateandcausedP6tocalculatea6dayremainingduration.
Physical%CompleteandSteps
AnadditionaladvantagewhenusingthePhysical%Completetechniqueistheabilitytoprogresstheactivityusingweightedsteps.WeightedStepsaresimplyachecklistofthingsthatmustbecompletedbeforetheactivitycanbeconsideredfinished.
ContinuingwithourMobilizeactivityexample,weightedstepshavebeenaddedfromaStepTemplate.
-
3/21/2015 PrimaveraP6PercentCompleteTypes|TenSixConsulting
http://tensix.com/2013/07/primaverap6percentcompletetypes/ 3/4
TheweightsvaluesenteredwillbecalculatedtoapercentagevaluebyPrimaveraP6andwilldrivethePhysical%Completevalueoftheactivity.TheweightvaluescanbeanydecimalnumberandthussparetheuserfrommanuallycalculatingthePercentCompletevaluestheyjustentersomearbitraryvaluebasedonwhateverfactortheychoosenumberofhours,relativedegreeofdifficulty,whatever.
AsStepsarecheckedoffasCompleted,sotheywilldrivethePercentCompletefortheactivity.Theuserwillstillneedtomanuallyupdatetheremainingdurationorexpectedfinishdatevaluesaspreviouslydescribed.
Note:theCalculateActivity%CompletefromtheactivitystepsmustbesetintheCalculationstaboftheSetProjectPreferencesdialogmustbesetinorderforthisfeaturetowork.
Usage:
ThePhysical%Completeprogresstypeshouldbeusedwhendealingwithdiscreteworkthatequatestooneormoremeasurabledeliveryitems.
Units%Complete
TheUnits%Completetypeisusedwhenresourcesareassignedtoanactivityandactualunitsworkedwillbetracked.ActualUnitsmaybeenteredmanuallyorviatheApplyActualsfeaturethatloadsactualunitsfromatimesheetmodulesuchasPrimaveraProgressReporter.
AswithPhysical%Complete,Units%Completedoesntcalculatetheremainingdurationforactivities,soyouwillneedtouseeithertheRemainingDurationfieldoranExpectedFinishdatetomanuallycontrolthecalculatedenddateforyouractivity.
Usage:
UseUnits%Completewhenresourcesareassignedtotheactivityandactualunitswillbetracked.Theonlydrawbackofthismethodisthathoursexpendeddoesntnecessarilyequatetoprogressachieved,
-
3/21/2015 PrimaveraP6PercentCompleteTypes|TenSixConsulting
http://tensix.com/2013/07/primaverap6percentcompletetypes/ 4/4
20102015TenSixConsulting,LLC|(703)9102600
InterviewWithAuthorStephenD.Kelly
sothismethodisnotverydiscrete.
Summary
IhopethisarticlehelpsgiveyouabetterunderstandingofeachofthePrimaveraP6activitypercentcompletechoices,whentheyshouldbeappliedandwhattheoutcomewillbewhenstatusingyourproject.