primavera 5 or 6 - 25 12 10
DESCRIPTION
PrimaveraTRANSCRIPT
-
PM 5.0
Computerized Project ManagementPrimavera 5.0, 6.0, 6.1, or 6.2
C
E
A B
D
Primavera Project Plannerwww.primavera.com
1993 1994 1995AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
Plot Date 18MAR95Data Date 2AUG93Project Start 2AUG93Project Finish *******
(c) Primavera Systems, Inc.
Activity Bar/Early DatesCritical ActivityProgress BarActivity Late DatesMilestone/Flag Activity
D:\P3WIN\P3OUT\~VIE023B.HGL
Date ApprovedCheckedRevision
Housing Authority of City of Los AngelesJordan Downs Porj. 1314 - Compressed
As-Built AnaylsisBACK Sheet 1 of 1
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
Building 38
Building 36
Building 37
Building 35
Building 39
Building 40
Compressed First Pilot Building
Compressed 2nd Pilot Building
1 2 3
4
1. Contract 1314-Compressed Starts 1/3/942. Worked Stopped on Bldg. 383. 1314-Compressed Executed 4/11/94
4. Building 36 Successful as 2nd Pilot
Dr. Attia GomaaHead of Industrial Engineering Department - Benah University
&Industrial Engineering Professor & Consultant
Engineering and Science Services - American University in Cairo2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Content: Computerized Project Management Overview How to install Primavera 5.0? Main Screens Data Gathering Data Entering Project Planning (Schedule, Bar chart & PERT) Layouts & Reporting Case Study (Real Project) Updating Advanced options
Primavera 5.0 - Overview
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Computerized Project Management
Primavera P5.0, P6.0, P6.1, P6.2
Enterprise Management = Multi-Project Standard Information
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Microsoft Projecthttp://www.microsoft.com/office/
project/prodinfo/default.mspxPrimavera Project Planner
www.primavera.com
Open Planwww.welcom.com
SuperProjectwww.cai.com/products/
superproject.htm
Plan Viewwww.planview.comKnowledge Plan
www.artemispm.com
Project Management Software
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Primavera Project Planner - P3- 1996
Primavera P5.0 2005 XP windows Primavera P6.0 2006 Vista window Primavera P6.1 - 2007 Primavera P6.2 - 2008 Primavera P7.0 - 2010
Microsoft Project MSP Time Line6 - TL6 Microsoft Excel
Single project
Single project
Multi-ProjectEnterprise ManagementIntegration Management
Standard Information
Project Planning Packages:
Project Information Systems:
Undo
10 %6 %
50 %
10 %
15 %
Project Management Software
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
ALL TOOLS HAVE
Network
GANTT Chart
Resource Allocation
Resource Profiles
Budgeting
Reports
DIFFERENCES
Standard Information
Integration Management
Multi-project resources
Performance analysis
Interface with other software
Flexibility & Ease of Use
Primavera P5.0, P6.0, P6.1, P6.2
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Resources: Labor Equipment & Tools Material Subcontractors
Critical Resources Parameters: Limited (Available < Required) Safety effect Cost effect
P 5.0Labor Time unitNon-Labor Time unitMaterial Physical unit
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
A
B
C
D
F
E
G
H
Breakdown StructureOBS: Organization Breakdown StructureEPS: Project Breakdown StructureRBS: Resource Breakdown StructureWBS: Work Breakdown Structure
L
E
T
M
E
RBSLabor
C
H
IT
HW
SW
X
Y
EPS
MI
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Project Level:
Top
Middle
Operational
Master Planfor WBS
Action Plan for each WP (design, resource, cost,..)
Detailed Plans
Systematic Approach
Main Activities
Detailed Activities
Resource Allocation
WBS (main items)
Planning Analysis
Project Overview
Target Plans
Baseline Schedule
WBS:1. Survey2. Design3. Procurement4. Construction5. Testing6. Handover
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
I- Project PlanningWBS: Work breakdown StructureActivity ListCalendar
NetworkGantt Chart
RBS: Resource Breakdown StructureResource ListResource Allocation
Resource Profiles (Histogram)Critical Resources (Limited)Resource Analysis (Smoothing & Leveling)CrushingCost Curves
Baseline (Target) Plan(Planned performance)
II- Project ControlUpdate (actual performance)
Performance Analysis VariancePerformance Evaluation KPI ReportForecasting
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Project Planning Module:Scope of work & BOQ
Planned Performance
Constraints a) Limited Res. b) Limited Time c) Limited Budget
NormalPlan
TargetPlan
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Project Planning Module:Scope of work = 30,000 m3 Execution
Planned Performance
10 dayEq. Perf. 30 m3/hr10 hr/day10 + 20% = 12 Eq.
Eq. rate 1000 LE/day10*12*1000 = 120,000 LE
Constraints a) 8 Eq. b) 8 day c) 100,000 LE
NormalPlan
TargetPlan
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Project Planning:Scope of work:
Activity: Execution BOQ = 30,000 m3
Constraints:a) 8 Eq. b) 8 day c) 100,000 LE
Target PlanActivity: Excavation BOQ= 30,000 Duration: 10 day Overtime: 3 hoursNo. of Eq.: 8 ExcavatorTotal Cost: 100,000 LE
Time Schedule:Duration: 10 day
Resource Schedule:Equipment Perf. 30 m3/hr Working condition: 10 hr/dayNumber of Equipment = 10 + 20% = 12 Eq
Cost Schedule:Equipment cost rate 1000 LE/day
Total Cost = 10*12*1000 = 120,000 LE
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Project Planning:Scope of work:
Activity: Execution BOQ = 30,000 m3
Constraints:a) 8 Eq. b) 8 day c) 100,000 LE
Target PlanActivity: Excavation BOQ= 30,000 Duration: 8 day Overtime: 5 hoursNo. of Eq.: 8 ExcavatorTotal Cost: 100,000 LE
Time Schedule:Duration: 10 day
Resource Schedule:Equipment Perf. 30 m3/hr Working condition: 10 hr/dayNumber of Equipment = 10 + 20% = 12 Eq
Cost Schedule:Equipment cost rate 1000 LE/day
Total Cost = 10*12*1000 = 120,000 LE
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Multi-Project Planning:Scope of work: Design for 3 Projects (A, B & C)
A 500 man-hour B 600 man-hour C 800 man-hour
Constraints:Available No. of Engineers = 10 Outsourcing = ??
Target Plan
Time Schedule:A 3 month Start: 1/5/2010 Finish: 30/7/2010A 2 month Start: 1/6/2010 Finish: 30/7/2010A 3 month Start: 1/6/2010 Finish: 30/8/2010
Resource Schedule:Design Engineer 180 man-hour/monthResource profile ???
Cost Schedule:Labor cost rate = $10/man-hour for in-source & 15 for out-sourceLabor Cost profile ???
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Project Planning:Scope of work:
Constraints:
Target Plan
Time Schedule:
Resource Schedule:
Cost Schedule:
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Time
C
E
A B
D
1) Network & Time Clacultion Logic diagram Flow chart Sequence chart - PERT
2) Bar ChartTime Chart
GANTT Chart(Basic plan)
A
B
C
D
1 2 3 4 5 6 7
Activity
Time
E
3) Resource Profiles - Histogram (Material, Equipment, Labor, Subcontractors)
6) Reports Baseline Planned Performance Updating Control
Project Planning Main Outputs:
5) Cost Analysis (Budget, Cash In/out, S-Curve, Payments, ...)
D
ES, EFLS, LF
TF
4) Resource Analysis Limited Res. (Smoothing, Leveling, Crushing)
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Network & Time Clacultion
Bar Chart
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Resource / Budget Profiles
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Project Control Module:
Scope of work Control
Time Control
Resource Control
CostControl
KPI Report for each level
(Actual / Planned) Analysis
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
WBS (Main Item) List
PhaseWork
PackageDescription Responsibility
(Key person)I- Design A110000
Refer to,
ProjectOrganization
Structure
A210000A310000
II- Procurement A120000A220000A320000
III- Construction A130000A230000A330000
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Master Plan Master Planned PerformancePhase
Work Package
Duration (week)
Budget ($1000)
Totals
I- Design A110000 4 20 Time = 12 W Cost = $ 60,000 A210000 5 25
A310000 3 15II- Procurement A120000 2 200 Time = 7 W
Cost = 650,000A220000 3 300A320000 2 150
III- Construction A130000 12 24 Time = 38 WCost = $ 78,000 A230000 15 32
A330000 11 22
Total Project A00000 24 20 Time = 24 WCost = 800,000Bonus rate = $1500 /week
For example
I
II
III
1 -- -- -- -- -- 20
Phase
Week24
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Actual PerformancePhase
Work Package
Duration (week)
Actual ($1000)
Totals
I- Design A110000 3 25 Time = 11 W Cost = $ 62,000 A210000 4 25
A310000 4 12II- Procurement A120000 3 220 Time = 8 W
Cost = 640,000 A220000 3 260A320000 2 160
III- Construction A130000 11 25 Time = 35 W Cost = $ 77,000 A230000 13 30
A330000 11 22
Total Project A00000 22 779+3 = 781
Bonus = 1500*2= $ 3000
For example
I
II
III
1 -- -- -- -- -- 20
Phase
Week24
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
KPI ReportPhase
Planned Performance
Actual Performance
Total time variance(week)
Total cost Variance($1000)Time Cost Time Cost
I- Design 12 60 11 62 -1 Good + 2 Bad
II- Procurement 7 650 8 640 +1 Bad -10 Good
III- Construction 38 78 35 77 -3 Good -1 Good
Total Project 24 788 22 779+3=781
- 2 Good - 9 Good
For example
Conclusion :Strength points 1-
2-
Weakness points 1-2-
Recommendations 1-2-
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Cost Analysis
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Updating A100
A100-01
A100-02
A100-03
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
How to install Primavera 5.0 to 6.2?
Primavera Package 70 MB
Microsoft SQL Server (Primavera) 70 MBFree Space > 0.5 GB
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
How to install Primavera 5.0?
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Desktop Short Cut
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
1. Start Primavera by clicking the Primavera icon on the desktop or clicking Start, Programs, Primavera, Project Management.
2. Type a Login Name and a Password , and then click OK.
Log in
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
1) Title bar2) Menu bar
3) Directory bar
4) Navigation bar
5) Status bar
Main Screen Overview
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Primavera 5.0 Overview
Relationship between Primavera components.
Oracle Database
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Data Gathering
Enterprise Project
Admin User
Defaults
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Primavera P5.0, P6.0, P6.1, P6.2Enterprise Management = Multi-Project Standard Information
Information Enterprise Level:1) Organizational Breakdown Structure (OBS) Managers
2) Enterprise Project Structure (EPS) Project Classification
)(3) Coding System Standard IDs4) Calendars Working / Non-working days/hours5) Resource List Material, Labor, Non-labor6) Cost Accounts Cost centers
Information Project Level:1) Reference Data EPS, Manager, Coding, Calendars, etc.2) Project name & Project ID 3) Work Breakdown Structure (WBS) Main Items4) Activity List (main activities to Details activities)5) Resource Allocation6) Planning Analysis Smoothing, leveling, crushing
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Main Information:
I- Enterprise Data: Long term
Organizational Breakdown Structure (OBS) Enterprise Breakdown Structure (EBS) Calendar List (Working & Non-working days) Activity Codes Cost Accounts (Cost Centers) Resource roles Resource List (Labor, Non-labor, Materials)
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
1) Organizational Breakdown Structure (OBS)
Cairo Manager:- IT Manager- MIS Manager- Network Manager
Alex Manager:- IT Manager- MIS Manager
XYZ Manager (Top Manager)Top
Middle
Operational
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
2) Enterprise Project Structure (EPS)ID Name Responsible ManagerITP IT Projects IT Manager
- Hard Ware Projects- Soft Ware Projects- Installation Projects- Maintenance Projects
MIS MIS Projects IT Manager
NWP Network Projects IT Manager
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
3) Calendars (Working & Nonworking)
Global: Company wide Standard 5 days
Add Holidays10 Jan 2009
Resource: --Supplier, Vendor, Consultant, third party
Project: ---Customer calendar
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
4) Activity Codes:
Code Value DescriptionHW Hard Ware ActivitiesSW Soft Ware ActivitiesSR Server ActivitiesGA General Activates
Global:
EPS:-----
Project:-----
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
5) Cost Accounts (Cost Centers)Budget work break structure
ID NameIT IT Cost Account
ITD IT DesignITH IT H/wITS IT S/w
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
6) Resource Role: Policy
Role ID: ITC Role Name: IT Crew
Description: Engineer Technician Helper Tool Box
Rate type: Price / unit Price / unit $ 100 /hour Price / unit 2 $ 120 /hour Price / unit 3Price / unit 4Price / unit 5
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
7) Resource List
Resource ID
Resource name
Resource type
Unit/day Maximum units/day
Role
HWE H/w Eng. Labor 8 Hour 8 ITC
SWE S/w Eng. Labor 8 Hour 8 ITC
MAT Total Materials
Material $1000 - -
Resource type: Labor Non-Labor Material
Project:
----
Global:
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Enterprise Information
Milestones
Main Activities
Main Steps
WBS (main items)
Details
Project
Top
Middle
Operational
Master Plan for WBS(Target plan)
(Monthly to Annual)
Action Plan for each WP(design, resource, cost,..)
(Weekly to Monthly)
Detailed Plans(Daily to Weekly)
Systematic Approach
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Main Information:
II- Project Data:1. Project name & description
2. Work Breakdown Structure (WBS)
3. Activity list (ID, description, duration)
4. Activity relations (Predecessor, SS, SF, FS, FF)
5. Resource Assignments (allocation)
6. Resource Availability (Maximum limits)
7. Work Products & Documents
8. Notebook
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
1) Project name & description
- EPS: IT Projects- Project ID: AUCIT- Project Name: AUC IT Center- Planned Start: 01 / 01 / 09- Must finish by: ---- (Max. 2 Month)- Responsible Manager (OBS): IT Manager- Rate type: Price / unit- Project Architect: No
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
ID Name- SR Server room
- L1 Lab #1
- L2 Lab #2
- L3 Lab #3
- GA General Activities
2) Work Breakdown Structure (WBS)
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
- SR Server room- SRHW Server H/w activities 2 - SRSW Server S/w activities 2
- L1 Lab #1- L1HW Lab #1 H/w activities 10 - L1SW Lab #1 S/w activities 6
- L2 Lab #2- L2HW Lab #2 H/w activities 10 - L2SW Lab #2 S/w activities 6
- L3 Lab #3- L3HW Lab #3 H/w activities 10- L3SW Lab #3 S/w activities 6
- GA General Activities- GASR Survey activities 2- GADS Design activities 5- GAMB Mob.& Preparation 1 - GAST Setup & testing activities 2
3) Activity List Original duration(Day)
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
- SR Server room- SRHW Server H/w activities 2 GAMB FS=0- SRSW Server S/w activities 2 SRHW FS=0
- L1 Lab #1- L1HW Lab #1 H/w activities 10 SRSW SS1-FF1- L1SW Lab #1 S/w activities 6 L1HW SS3-FF2
- L2 Lab #2- L2HW Lab #2 H/w activities 10 SRSW SS1-FF1- L2SW Lab #2 S/w activities 6 L2HW SS3-FF2
- L3 Lab #3- L3HW Lab #3 H/w activities 10 SRSW SS1-FF1- L3SW Lab #3 S/w activities 6 L3HW SS3-FF2
- GA General Activities- GASR Survey activities 2 - -- GADS Design activities 5 GASR FS=0- GAMB Mob.& Preparation 1 GADS FS=0- GAST Setup & testing activities 2 L1SW,2SW,3SW FS=0
4) Activity Relations Original duration(Day)
Predecessors
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
- SR Server room- SRHW Server H/w activities 2 -- SRSW Server S/w activities - 2
- L1 Lab #1- L1HW Lab #1 H/w activities 3 -- L1SW Lab #1 S/w activities - 4
- L2 Lab #2- L2HW Lab #2 H/w activities 3 -- L2SW Lab #2 S/w activities - 4
- L3 Lab #3- L3HW Lab #3 H/w activities 3 -- L3SW Lab #3 S/w activities - 4
- GA General Activities- GASR Survey activities 1 1 - GADS Design activities 2 2- GAMB Mob.& Preparation 1 1- GAST Setup & testing activities 1 1
HWE /day SWE /day 5) Resource allocation Mat
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
6) Resource Availability
Resource ID
Resource name
Resource type
Unit/day Maximum units/day
Requiredunits/day
HWE H/w Eng. Labor 8 Hour 8*4=32 ?
SWE S/w Eng. Labor 8 Hour 8*4=32 ?
Duration (day) ? ?
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
7) Work Products & Documents
GADS Design activities:
Drawings Approved Detailed Design Specification In Progress
GAMB Mob.& Preparation
General Documents In Progress
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
8) Notebook
GAMB Mob.& Preparation
Contractor will send the equipment & tools specification for review and approval before it is shipped.
.
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
ID Orig. Dur. Actual Start Actual Finish Remaining Dur.
Lab #1
L1HW 10 18-Jan-09 30-Jan-09 0
L1SW 6 26-Jan-09 5
General Activities: GASR 2 03-Jan-09 04-Jan-09 0
GADS 5 05-Jan-09 10-Jan-09 0
GAMB 1 12-Jan-09 12-Jan-09 0
Server Room:
SRHW 2 15-Jan-09 17-Jan-09 0
SRSW 2 16-Jan-09 18-Jan-09 0
Updating
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Main Screens & Data Entering
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Gantt Chart Show in Bottom Layout
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Resource/Cost Usage Profile /
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Resource/Cost Usage Spreadsheet /
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Activity Usage Profile /
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Activity Usage Spreadsheet
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Resource leveling
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
setaD etaL dna ylraE deludehcS evreserP
gnileveL
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
1) Organizational Breakdown Structure (OBS)
Cairo Manager:- IT Manager- MIS Manager- Network Manager
Alex Manager:- IT Manager- MIS Manager
XYZ Manager (Top Manager)Top
Middle
Operational
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
2) Enterprise Project Structure (EPS)IT Projects
- Hard Ware Projects- Soft Ware Projects- Installation Projects- Maintenance Projects
MIS Manager-
-
Network Manager
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
3) Calendars (Working & Nonworking)
Global: Company wide Standard 5 days
Resource: --Supplier, Vendor, Consultant, third party
Project: ---Customer calendar
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Cost Accounts (Cost Centers)
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
4) Activity Codes:
Code Value DescriptionHW Hard Ware ActivitiesSW Soft Ware ActivitiesSR Server ActivitiesGA General Activates
1 2 3 4WBS Main Activities
Global:
EPS:-----
Project:-----
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Resources (Labor, Non-labor, Materials)
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
5) Cost Accounts (Cost Centers)Budget work break structure
IT IT Cost AccountITD IT DesignITH IT H/wITS IT S/w
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
6) Resource Role: Policy
Role ID: ITC Role Name: IT Crew
Description: Engineer Technician Helper Tool Box
Rate type: Price / unit Price / unit $ 100 /hour Price / unit 2 $ 120 /hour Price / unit 3Price / unit 4Price / unit 5
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
7) Resource List
Resource ID
Resource name
Resource type
Unit/day Maximum units/day
Role
HWE H/w Eng. Labor 8 Hour 8 ITC
SWE S/w Eng. Labor 8 Hour 8 ITC
Resource type: Labor Non-Labor Material
Project:
----
Global:
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Enterprise Information
Milestones
Main Steps
Main Activities
WBS (main items)
Detailed Activities
Project
Top
Middle
Operational
Master Plan for WBS(Target plan)
(Monthly to Annual)
Action Plan for each WP(design, resource, cost,..)
(Weekly to Monthly)
Detailed Plans(Daily to Weekly)
Systematic Approach
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Main Information:
II- Project Data:
1. Project name & description
2. Work Breakdown Structure (WBS)
3. Activity list (ID, description, duration)
4. Activity relations (Predecessor, SS, SF, FS, FF)
5. Resource Assignments (allocation)
6. Work Products & Documents
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
1) Project name & description
- EPS: IT Projects- Project ID: AUCIT- Project Name: AUC IT Center- Planned Start: 01 / 01 / 09- Must finish by: ---- (Max. 2 Month)- Responsible Manager (OBS): IT Manager- Rate type: Price / unit- Project Architect: No
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
- SR Server room
- L1 Lab #1
- L2 Lab #2
- L3 Lab #3
- GA General Activities
2) Work Breakdown Structure (WBS)
1 2 3 4WBS Work type
Activity Codes:
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
- SR Server room- SRHW Server H/w activities 2 - SRSW Server S/w activities 2
- L1 Lab #1- L1HW Lab #1 H/w activities 10 - L1SW Lab #1 S/w activities 6
- L2 Lab #2- L2HW Lab #2 H/w activities 10 - L2SW Lab #2 S/w activities 6
- L3 Lab #3- L3HW Lab #3 H/w activities 10- L3SW Lab #3 S/w activities 6
- GA General Activities- GASR Survey activities 2- GADS Design activities 5- GAMB Mob.& Preparation 1 - GAST Setup & testing activities 2
3) Activity List Original duration(Day)
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
- SR Server room- SRHW Server H/w activities 2 GAMB FS=0- SRSW Server S/w activities 2 SRHW FS=0
- L1 Lab #1- L1HW Lab #1 H/w activities 10 SRSW SS1-FF1- L1SW Lab #1 S/w activities 6 L1HW SS3-FF2
- L2 Lab #2- L2HW Lab #2 H/w activities 10 SRSW SS1-FF1- L2SW Lab #2 S/w activities 6 L2HW SS3-FF2
- L3 Lab #3- L3HW Lab #3 H/w activities 10 SRSW SS1-FF1- L3SW Lab #3 S/w activities 6 L3HW SS3-FF2
- GA General Activities- GASR Survey activities 2 - -- GADS Design activities 5 GASR FS=0- GAMB Mob.& Preparation 1 GADS FS=0- GAST Setup & testing activities 2 L1SW,2SW,3SW FS=0
4) Activity Relations Original duration(Day)
Predecessors
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Trace Logic
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
- SR Server room- SRHW Server H/w activities 2 -- SRSW Server S/w activities - 2
- L1 Lab #1- L1HW Lab #1 H/w activities 3 -- L1SW Lab #1 S/w activities - 4
- L2 Lab #2- L2HW Lab #2 H/w activities 3 -- L2SW Lab #2 S/w activities - 4
- L3 Lab #3- L3HW Lab #3 H/w activities 3 -- L3SW Lab #3 S/w activities - 4
- GA General Activities- GASR Survey activities 1 1 - GADS Design activities 2 2- GAMB Mob.& Preparation 1 1- GAST Setup & testing activities 1 1
HWE /day SWE /day 5) Resource allocation
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Resource Analysis
Resource ID
Resource name
Resource type
Unit/day Maximum units/day
Requiredunits/day
HWE H/w Eng. Labor 8 Hour 8*4=32 72 = 8*9
SWE S/w Eng. Labor 8 Hour 8*4=32 96 = 8*12
Duration (day) 45 25
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
7) Work Products & Documents
GADS Design activities:
Drawings Approved Detailed Design Specification In Progress
GAMB Mob.& Preparation
General Documents In Progress
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
8) Notebook
GAMB Mob.& Preparation
Contractor will send the equipment & tools specification for review and approval before it is shipped.
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
gnitadpU senilesaB
senilesaB
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
etaD ataD .
001x }noitaruD lanigirO/)noitaruD gniniameR noitaruD lanigirO({ = % noitaruD
:noitaruD
noitaruD gniniameR
:tinU
001 x )stinU noitelpmoC tA / stinU lautcA( = % tinU
:lacisyhP
.
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Status
Actual started date
Remaining duration
Duration % = {(Original Duration Remaining Duration)/Original Duration} x100
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
ID Orig. Dur. Actual Start Actual Finish Remaining Dur.
Lab #1
L1HW 10 18-Jan-09 30-Jan-09 0
L1SW 6 26-Jan-09 5
General Activities: GASR 2 03-Jan-09 04-Jan-09 0
GADS 5 05-Jan-09 10-Jan-09 0
GAMB 1 12-Jan-09 12-Jan-09 0
Server Room:
SRHW 2 15-Jan-09 17-Jan-09 0
SRSW 2 16-Jan-09 18-Jan-09 0
Updating
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Advanced options
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Create a New File
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
reganaM ygolodohteM
eliF weN a etaerC
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Advanced Activity Options
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Group
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Filters
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Activity Types
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
tnednepeD ksaT
.
tnednepeD ecruoseR
.
troffE fO leveL
.
troffE fO leveL
sepyT ytivitcA
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
enotseliM
enotseliM eliM enotS
.
enotseliM .
enotseliM %
enotseliM enotseliM tratS enotseliM hsiniF
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Duration Types
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
emiT/tinU dexiF
.
emit / tinu dna noitaruD dexiF
.
tinU dexiF
mus pmuL .
stinU dna noitaruD dexiF.
sepyT noitaruD
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Customize activity details
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
spetS
: % % %
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Complete
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Work Products and Documents
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Constraints
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
retfa ro no tratS
erofeb ro no tratS
nO tratSretfa ro no hsiniF. .
erofeb ro no hsiniF
no hsiniF.
trats yrotadnaM
. hsinif yrotadnaM
elbissop sa etal sA.
taolF eerF
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
sesnepxE
...
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
esnepxE epyT laurccA
.
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Customize project details
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
File
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
File
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
File
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
File
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
File
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Import & ExportOptions
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
File
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Edit
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Edit
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Edit
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Advance ProjectOptions
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Access Mode
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
evisulcxE
derahS
ylnO daeR
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Edit
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Edit
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Edit
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Tools
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin Options
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Admin
-
0102 - 0.5 arevamirP - tnemeganaM tcejorP deziretupmoC 0.5 MP
smreT yeK )SBO( erutcurtS nwodkaerB lanoitazinagrO )SPE( erutcurtS tcejorP esirpretnE )SBW( erutcurtS nwodkaerB kroW sedoC ytivitcA ( ) stnemucoD dna stcudorP kroW sedoC tcejorP gnikcarT tcejorP
tnuoccA tsoC erutcurtS nwodkaerB tsoC stniartsnoC noitacolla ecruoseR smetI koobetoN gnitadpU senilesaB tuoyaL
sesnepxE eulaV denraE segnahC labolG tnemeganaM ksiR tropxE tropmI
-
PM 5.0 Computerized Project Management - Primavera 5.0 - 2010
Discussion
Suggestions
Questions
Comments
Thank you for your attention!
Dr. Attia Hussien GomaaIndustrial Engineering Professor & Consultant
[email protected] or [email protected]: 0122738497
Copyrights & More Information:
Were here to help you!
Useful Science For the Sake of Allah