Página 1 ESTRUCTURA DE CONTENCION PARA LLENOS DEL EDIFICIO - OBRA NUEVA PRESUPUESTO DE OBRA NUEVAS ACTIVIDADES Descripción Vr/Un. Cant. Vr/Total CONCRETO ADICION CIMENTACION NUEVO ADICION CONCRETO CAISSON EJE 8A , 9A M3 311,219.00 4.11 1,279,155.00 NUEVO M3 386,766.00 2.91 1,127,036.00 NUEVO PEDESTALES ADICIONALES A10-B10-C10 M3 485,730.00 1.46 710,380.00 NUEVO ACERO DE REFUERZO KG 2,789.00 713.54 1,990,063.00 SUBTOTAL 5,106,634.00 MURO CONTENCION LLENOS EDIFICIO NUEVO GLOBAL 829,777.00 1.00 829,777.00 NUEVO GLOBAL 296,349.00 1.00 296,349.00 NUEVO MAMPOSTERIA PROTECCION TANQUES M2 25,444.00 13.51 343,850.00 SUBTOTAL 1,469,976.00 6,576,610.00 VIGAS TRANSVERSALES APOYO CONCRETO RAMPA PRESUPUESTO DE OBRA NUEVAS ACTIVIDADES CANTIDADES CONCRETO RAMPA NUEVO CONCRETO VIGAS TRANSVERSAL APOYO RAMPA M3 494,650.00 5.83 2,882,573.00 NUEVO ACERO DE REFUERZO KG 2,789.00 1,042.71 - SUBTOTAL 2,882,573.00 OBRAS NUEVAS ASCENSOR PRESUPUESTO DE OBRA NUEVAS ACTIVIDADES Descripción Vr/Un. Cant. Vr/Total CANTIDADES ASCENSOR NUEVO M3 485,730.00 5.16 2,506,367.00 NUEVO CONCRETO VIGAS AEREAS F´C 3000 PSI M3 494,650.00 10.95 5,416,418.00 NUEVO CONCRETO MURO Y PLACA ASCENSOR F´C´= 3000 PSI M3 445,653.00 9.21 4,104,464.00 NUEVO ML 23,513.00 - - NUEVO ML 27,519.00 19.09 525,342.00 NUEVO MURO EN BLOQUE DE ARCILLA No 4 (10*20*30) M2 25,444.00 109.72 2,791,716.00 NUEVO ACERO DE REFUERZO KG 2,789.00 768.78 - NUEVO CITIFONO PARA ASCENSOR UN 75,534.00 1.00 75,534.00 18,5,1 NUEVO RED ACOMETIDA CABLE CITOFONO ML 3,070.00 60.00 184,200.00 18,1,19 NUEVO UN 191,730.00 2.00 383,460.00 18,1,18 NUEVO UN 94,846.00 2.00 189,692.00 12.1 NUEVO UN 250,240.00 1.00 250,240.00 EMPRESA SOCIAL DEL ESTADO HOSPITAL ISMAEL ROLDAN VALENCIA QUIBDÓ - CHOCÓ Un. de pago 3,2 ITEM BAHIRV 3,4 ITEM BAHIRV ADICION CONCRETO VIGAS DE CIMENTACION EJE 10 DE A A C Y EJE A ENTRE 9 Y 10 3,6 ITEM BAHIRV 3,18 ITEM BAHIRV MURO DE CONTENCION EN MAMPOSTERIA Y COLUMNETAS EJE 10 ENTRE B Y C 4,2x1,45m MURO DE CONTENCION EN MAMPOSTERIA Y COLUMNETAS EJE 10 ENTRE C Y D de 1,5x1,45m 3,8 ITEM BAHIRV 3,18 ITEM BAHIRV Un. de pago 3,6 ITEM BAHIRV CONCRETO COLUMNAS ADICIONALES 6C, 6D, 7C, 7D ASCENSOR 3,8 ITEM BAHIRV 3,11 ITEM BAHIRV 3,13 ITEM BAHIRV CONCRETO COLUMNETAS DE CONFINAMIENTO F´C´= 3000 PSI 3,14 ITEM BAHIRV CONCRETO VIGAS DE AMARRE SOBRE MUROS F´C´= 3000 PSI 4,1 ITEM BAHIRV 3,18 ITEM BAHIRV 18,1,15 ITEM BAHIRV TOMA TRIFASICO CUARTO MAQUINA Y CUARTO GASES MEDICINALES TOMA MONOFASICO CUARTO MAQUINAS Y CUARTO GASES MEDICINALES Puerta en madera entamborada en triplex Okume e= 4 mm de 0.80 m x 2.10 m

Upload: milena-hoyos

Post on 01-Dec-2015

33 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Presupuesto Obra Adicionales

Página 1

ESTRUCTURA DE CONTENCION PARA LLENOS DEL EDIFICIO - OBRA NUEVA

PRESUPUESTO DE OBRANUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalCONCRETO ADICION CIMENTACION

NUEVOADICION CONCRETO CAISSON EJE 8A , 9A

M3 311,219.00 4.11 1,279,155.00

NUEVO M3 386,766.00 2.91 1,127,036.00

NUEVOPEDESTALES ADICIONALES A10-B10-C10

M3 485,730.00 1.46 710,380.00

NUEVOACERO DE REFUERZO

KG 2,789.00 713.54 1,990,063.00 SUBTOTAL 5,106,634.00 MURO CONTENCION LLENOS EDIFICIO

NUEVO GLOBAL 829,777.00 1.00 829,777.00

NUEVO GLOBAL 296,349.00 1.00 296,349.00 NUEVO MAMPOSTERIA PROTECCION TANQUES M2 25,444.00 13.51 343,850.00

SUBTOTAL 1,469,976.00 6,576,610.00

VIGAS TRANSVERSALES APOYO CONCRETO RAMPA

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADESCANTIDADES CONCRETO RAMPA

NUEVOCONCRETO VIGAS TRANSVERSAL APOYO RAMPA

M3 494,650.00 5.83 2,882,573.00

NUEVOACERO DE REFUERZO

KG 2,789.00 1,042.71 -

SUBTOTAL 2,882,573.00

OBRAS NUEVAS ASCENSOR

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalCANTIDADES ASCENSOR

NUEVO M3 485,730.00 5.16 2,506,367.00

NUEVO CONCRETO VIGAS AEREAS F´C 3000 PSIM3 494,650.00 10.95 5,416,418.00

NUEVO M3 445,653.00 9.21 4,104,464.00

NUEVO ML 23,513.00 - -

NUEVO ML 27,519.00 19.09 525,342.00

NUEVO MURO EN BLOQUE DE ARCILLA No 4 (10*20*30)M2 25,444.00 109.72 2,791,716.00

NUEVO ACERO DE REFUERZOKG 2,789.00 768.78 -

NUEVO CITIFONO PARA ASCENSOR

UN 75,534.00 1.00 75,534.00 18,5,1 NUEVO RED ACOMETIDA CABLE CITOFONO ML 3,070.00 60.00 184,200.00

18,1,19 NUEVO UN 191,730.00 2.00 383,460.00

18,1,18 NUEVO UN 94,846.00 2.00 189,692.00

12.1 NUEVO UN 250,240.00 1.00 250,240.00

EMPRESA SOCIAL DEL ESTADO HOSPITAL ISMAEL ROLDAN VALENCIAQUIBDÓ - CHOCÓ

Un. de pago

3,2 ITEM BAHIRV

3,4 ITEM BAHIRV

ADICION CONCRETO VIGAS DE CIMENTACION EJE 10 DE A A C Y EJE A ENTRE 9 Y 10

3,6 ITEM BAHIRV

3,18 ITEM BAHIRV

MURO DE CONTENCION EN MAMPOSTERIA Y COLUMNETAS EJE 10 ENTRE B Y C 4,2x1,45m

MURO DE CONTENCION EN MAMPOSTERIA Y COLUMNETAS EJE 10 ENTRE C Y D de 1,5x1,45m

3,8 ITEM BAHIRV

3,18 ITEM BAHIRV

Un. de pago

3,6 ITEM BAHIRV

CONCRETO COLUMNAS ADICIONALES 6C, 6D, 7C, 7D ASCENSOR

3,8 ITEM BAHIRV

3,11 ITEM BAHIRV

CONCRETO MURO Y PLACA ASCENSOR F´C´= 3000 PSI

3,13 ITEM BAHIRV

CONCRETO COLUMNETAS DE CONFINAMIENTO F´C´= 3000 PSI

3,14 ITEM BAHIRV

CONCRETO VIGAS DE AMARRE SOBRE MUROS F´C´= 3000 PSI

4,1 ITEM BAHIRV

3,18 ITEM BAHIRV

18,1,15 ITEM

BAHIRV

TOMA TRIFASICO CUARTO MAQUINA Y CUARTO GASES MEDICINALES

TOMA MONOFASICO CUARTO MAQUINAS Y CUARTO GASES MEDICINALES

Puerta en madera entamborada en triplex Okume e= 4 mm de 0.80 m x 2.10 m

Page 2: Presupuesto Obra Adicionales

Página 2

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

12.2 NUEVO UN 115,216.00 1.00 115,216.00

12.17 NUEVO ML 123,270.00 5.00 616,350.00 12.19 NUEVO Canal en lamina Cal 18 ml 6.00 71,374.00 428,244.00 13.1 NUEVO Cerradura Interior marcha shlage linea ball platinum Un 44,120.00 1.00 44,120.00

14.3 NUEVO Pintura esmalte domestico de pintuco puerta en madera M2 13,803.00 3.20 44,170.00

14.4 NUEVO UN 25,974.00 1.00 25,974.00 Fanche en lamina galvanizada cal 22 Un 14.70

SUBTOTAL 15,344,307.00

TUBERIA DESAGUE ACUIFERO MURO CONTENCION H5

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalTUBERIA DESAGUE ACUIFERO MT1

NUEVO ML 33,080.00 12.00 396,960.00

NUEVO ML 63,251.00 12.00 759,012.00

SUBTOTAL 1,155,972.00

FOSO DESECHOS HOSPITALARIOS - OBRA NUEVA

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalFOSO DE DESECHOS HOSPITALARIOS

NUEVO NUEVO DEMOLICION Y DESMONTE DE TAPAS UNIDAD 15,000.00 4.00 60,000.00 NUEVO NUEVO VERTIMIENTO DE CAL VIVA KG 5,907.00 17.28 102,073.00

NUEVOCONCRETO TAPAS DE 3000 PSI

M3 485,730.00 0.15 72,860.00

NUEVO M2 31,724.00 3.00 95,172.00

NUEVO M2 13,997.00 9.00 125,973.00

NUEVOTUBERIA PVC LIVIANA DE 2"

ML 13,870.00 24.00 332,880.00

SUBTOTAL 788,958.00

PRESUPUESTO DE OBRA

NUEVAS CANTIDADES

Descripción Vr/Un. Cant. Vr/TotalOBRA EXTERIOR PLACA AMBULANCIA

NUEVO M2 84,858.00 55.20 4,684,162.00

NUEVO M3 60,222.00 27.60 1,662,127.00

NUEVO M3 21,297.00 27.60 587,797.00

SUBTOTAL -

IMPERMEABILIZACION EN MANTO PARA TERRAZAS NORTE Y SUR Y VIGA CANAL

PRESUPUESTO DE OBRA

Marco metálico en Lámina Galvanizada de 0.88 m x 2.16 m Cal 20 con patas de anclaje para puertas de madera

Escalera tipo gato en hierro liso 3/4" para tanques y cajas de aforo

Wash Primer y esmalte blanco domestico pintuco para marco metálico en Lámina Galvanizada de 0.88 m x 2.16 m

Un. de pago

TUBERIA NOVAFOR 4" DRENAJE ACUIFEROS - CANGREJERAS MURO DE CONTENCION TIPO 1

TUBERIA NOVAFOR 6" DRENAJE ACUIFEROS - CANGREJERAS MURO DE CONTENCION TIPO 1

Un. de pago

3,6 ITEM BAHIRV

5,1 ITEM BAHIRV

LAMINA SUPERBOARD 8MM MAS ESTRUCTURA CAL 26 PISO 1

14,1 ITEM BAHIRV

ESTUCO Y PINTURA PARED INTERIOR EN VINILO VINILTEX PINTUCO X 3 MANOS 2 CAPAS TIPO 2 Y 1 CAPA ACABADO TIPO 1

17,7,1 ITEM BAHIRV

PLACA AMBULANCIA

Un. de pago

21,1 ITEM BAHIRV

PLACA EN CONCRETO HIDRAULICO DE 3500 PSI ESPESOR e=0.18MTS INCLUYE ACELERANTE DE FRAGUADO Y SELLADO ASFALTICO

2,2 ITEM BAHIRV

RELLENO EN RECEBO COMPACTADO AL 95% PROCTOR MODIFICADO

2,3 ITEM BAHIRV

EXCAVACION MISCELANEAS (PARA RELLENO OBRAS EXTERIOR PLACA CONCRETO)

Page 3: Presupuesto Obra Adicionales

Página 3

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/Total

NUEVO m2 50,930.00 59.23 3,016,711.00

NUEVO m2 57,840.00 362.90 20,990,078.00 SUBTOTAL -

IMPERMEABILIZACION EN MANTO PARA TERRAZAS NORTE Y SUR Y VIGA CANALPRESUPUESTO DE OBRA NUEVO

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/Total

NUEVO m2 50,930.00 59.23 3,016,711.00

NUEVO m2 50,930.00 175.50 8,938,215.00

m2 29,500.90 187.40 5,528,468.66

SUBTOTAL 17,483,394.66

m2 40,715.00 175.49 7,145,075.35

ACOMETIDA DOMICILIARIA ALCANTARILLADO 8" X 6" HOSPITAL CAJA PRINCIPAL

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/Total

NUEVO Empalme Acometida de Caja a Anden UNIDAD 1,395,782.36 1.00 1,395,782.00

SUBTOTAL 1,395,782.00

OBRAS NUEVAS APANTALLAMIENTO

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalCANTIDADES APANTALLAMIENTO

NUEVO Cable de aluminio desnudo ACSR Nº 2 Mts 1,885.00 132.00 248,820.00

NUEVO Ud 15,600.00 14.00 218,400.00

Un. de pago

IMPERMEABILIZACION VIGA CANAL Y TERRAZAS NORTE Y SUR

Mortero Impermeabilizado 5cm + Capa de Manto Edil 3mm en terraza sur

Mortero Impermeabilizado 5cm + Capa de Manto Edil 3mm + Acabado Final en pintura bituminosa alumol terraza norte y viga canal

Un. de pago

IMPERMEABILIZACION VIGA CANAL Y TERRAZAS NORTE Y SUR

Mortero Impermeabilizado 5cm + Capa de Manto Edil 3mm en terraza sur

Mortero Impermeabilizado 5cm + Capa de Manto Edil 3mm Terraza norte

viga canal Mortero impermeabilizado subiendo a cada lado 30 cms

Tablón de gres 33x33 para terrazas y patios interiores en la terrraza norte

Un. de pago

ACOMETIDA DOMICILIARIA ALCANTARILLADO 8" X 6"

Un. de pago

Soportes en platina de 1/4"x1.1/2" con 3 perforaciones para tornillo de 1/2"

Page 4: Presupuesto Obra Adicionales

Página 4

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

NUEVO Grapas prensahilos de tres tornillos Ud 11,050.00 14.00 154,700.00 NUEVO Anclas de 1/2" x 2" Ud 4,550.00 28.00 127,400.00 NUEVO Pararrayos tipo Franklin Ud 214,500.00 3.00 643,500.00

Page 5: Presupuesto Obra Adicionales

Página 5

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

NUEVO Tubo galvanizado de 1" Ud 39,000.00 3.00 117,000.00 NUEVO Reducciòn galvanizada de 1" a 3/4" Ud 5,850.00 3.00 17,550.00 NUEVO Abrazaderas en u para tubo de 1" Ud 8,450.00 6.00 50,700.00 NUEVO Tubos EMT de 1" Ud 24,050.00 16.00 384,800.00 NUEVO Curvas EMT de 1" Ud 5,460.00 4.00 21,840.00 NUEVO Uniones EMT de 1" Ud 2,990.00 12.00 35,880.00 NUEVO Riel unistruc de 2 mts Ud 58,500.00 2.00 117,000.00 NUEVO Abrazadera unistruc de 1" ud 3,640.00 32.00 116,480.00 NUEVO Anclas de 1/4" x 2" Ud 3,250.00 64.00 208,000.00 NUEVO Conectores bimetalicos de ponchar DBH 8 Ud 9,750.00 4.00 39,000.00 NUEVO Varillas cooperwell de 5/8" x 2.40 mts de cobre Ud 162,500.00 4.00 650,000.00 NUEVO Soldaduras exotermicas con soldadura cadwell Ud 65,000.00 9.00 585,000.00

NUEVO UD 248,372.00 4.00 993,488.00

NUEVO Mts 22,750.00 322.13 7,328,412.00

NUEVO Ud 2,527,500.00 1.00 2,527,500.00 NUEVO Mano de obra apantallamiento. Ud 3,450,000.00 1.00 3,450,000.00

SUBTOTAL 18,035,470.00

PRESPUESTO CERRAMIENTO PERIMETRAL

PRESUPUESTO DE OBRACANTIDADES NUEVAS

Descripción Vr/Un. Cant. Vr/TotalNUEVO CARPINTERIA METALICA

Cerramiento en hierro cuadrado 1'' calibr M2 182,046.00 73.46 13,372,735.00

M2 259,861.00 21.00 5,457,081.00

SUBTOTAL 18,829,816.00

PRESPUESTO CERRAMIENTO LATERAL EN MAMPOSTERIA, COLUMNETA Y VIGA DE AMARRE

PRESUPUESTO DE OBRACANTIDADES NUEVAS

Descripción Vr/Un. Cant. Vr/TotalNUEVO CERRAMIENTO EN MAMPOSTERIA

2.3 NUEVO Excavacion Miscelaneas m3 21,297.00 3.18 67,622.23

3.1 NUEVO Concreto Pobre Solado e=0,05 m2 18,488.00 10.58 195,676.99

3.4 NUEVO Concreto viga cimentacion m3 386,766.00 3.18 1,228,059.40

3.13 NUEVO Concreto columnetas de confinamiento ml 23,513.00 37.50 881,737.50

3.14 NUEVO Concreto Vigas de Amarre sobre muros ml 27,519.00 35.28 970,870.32

3.15 NUEVO Concreto Impermeabilizado para alfajia ml 28,558.00 35.28 1,007,526.24

3.18 NUEVO Acero de Refuerzo kg 2,789.00 594.46 1,657,937.78

4.1 NUEVO Muro en Bloque de Arcilla N°4 10x20x30 m2 25,444.00 82.58 2,101,038.30

6.3 NUEVO Pañete Liso impermeabilizado exterior m2 17,914.00 190.51 3,412,831.97

14.10 NUEVO Pintura fachada koraza pintuco 10 años m2 13,528.00 190.51 2,577,246.34

SUBTOTAL 14,100,547.08

OBRAS NUEVAS CASETA DESECHOS HOSPITAL

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Camaras de inspeccion de 40x40x30 cmts,con tapa en concreto ,base y recibidor en angulo de 1/4x 1.1/2"

Cable de cobre desnudo 1/0 para anillo inferior enterradoa 50 cmts y bajantes

Malla de puesta a tierra con tres varillas cooperwell de cobre de 5/8x2.40 mts,4 soldaduras exotermicas,25 mts de cable de cobre desnudo 1/0 y 3 camaras de inspeccuion de 40x40x30 cmts.Profundidad malla 1.0 mts

Un. de pago

Puerts corredizas y de acceso Cerramiento en hierro cuadrado 1'' calibre 18

EMPRESA SOCIAL DEL ESTADO HOSPITAL ISMAEL ROLDAN VALENCIAQUIBDÓ - CHOCÓ

Un. de pago

Page 6: Presupuesto Obra Adicionales

Página 6

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

Descripción Vr/Un. Cant. Vr/TotalPRELIMINARESLocalizacion y Replanteo m2 35.62 2,043.00 72,780.00

EXCAVACIONExcavaciones cimentacion m3 19.03 53,840.00 1,024,683.00

ESTRUCTURAS

Concreto solado pobre de limpieza 10Mpa e= m2 19.03 18,488.00 351,864.00

Concreto Zapatas f'C = 3000PSI m3 3.81 324,337.00 1,234,556.00

m31.27 386,766.00 490,729.00

m230.35 40,034.00 1,214,852.00

Concreto columnas f'C = 3000PSI ml 28.00 23,513.00 658,364.00

ml37.22 27,519.00 1,024,257.00

Malla electrosoldada 6mm- 15cmx 15cm m2 30.35 7,415.00 225,012.00

Acero de refuerzo fy = 60000PSI Kg 563.39 2,789.00 1,571,298.00

Estructura de cubierta perfiles PAG kg 617.64 2,789.00 1,722,585.00

MAMPOSTERIA

Muro en bloque de arcilla No 4 (10*20*40) m2 77.88 25,444.00 1,981,553.00

Dinteles en bloque N° 4 e = 15cm ml 19.61 27,262.00 534,608.00

PAÑETES

Pañete Liso 1:4 m2 155.76 14,021.00 2,183,883.00

PISOS

m2 30.35 38,732.00

ml 33.11 19,760.00

M2 30.35 27,918.52 847,327.00

CUBIERTA

Teja Termoacustica de Ajover Ref. Marina m2 57.10 51,172.00 2,922,126.00

Caballete de Ajover Ref. Marina ml 8.30 40,714.00 337,926.00

ENCHAPES

m2 32.08 41,874.00 1,343,527.00

CARPINTERÍA METÁLICA

Un5.00 447,533.00 2,237,665.00

m2 12.30 170,240.00 2,093,952.00

PINTURAS Y REVESTIMIENTOS

Un 5.00 25,974.00 129,870.00

pintura esmalte domestico de pintuco m2 20.16 13,803.00 278,268.00

Pintura Epoxica Interior m2 33.49 18,068.00 605,170.00

Pintura fachada Koraza pintuco 10 años m2 52.82 13,528.00 714,535.00

INSTALACIONES HIDROSANITARIAS

Tuberia PVC-P RED 26 DE 3/4 ml 30.00 6,772.00 203,160.00

Registro de 3/4" Un 2.00 60,508.00 121,016.00

Caja de inspeccion de 0.70x0.70 Un 1.00 427,562.00 427,562.00

ml 12.00 33,080.00 396,960.00

Tuberia PVC-S 4" ml 24.00 33,080.00 793,920.00

PUNTO HIDRAULICO

Lavaplatos Un 1.00 26,995.00 26,995.00

Poseta de aseo Un 1.00 26,995.00 26,995.00

Llave de manguera, incluye caja y tapa Un 1.00 44,819.00 44,819.00

Un. de pago

Concreto Vigas de cimentacion f'C = 3000PSI

Concreto placa de contrapiso e= .10mts. F'C =3000PSI

Concreto vigas de amarre cubierta f'C = 3000PSI

Gravilla lavada para caseta desechos incluye dilataciones en bronce

Media caña en gravilla lavada, incluye dilataciones en bronce

PISO EN MORTERO AFINADO CON MEDIA CAÑA

Ceramica para pared blanco 22500771 0,203x0,305

Puerta metálica cal 18 de acceso, 1,0 X 2.10 mts

Ventana corrediza 2 hojas en aluminio anodisado crudo en sistema 5020 con vidrio de 5 mm

Wash Primer y esmalte blanco domestico pintuco para marco metálico en Lámina Galvanizada de 1.08 m x 2.16 m

Bajantes de aguas lluvias tuberia de 4" pulgada

Page 7: Presupuesto Obra Adicionales

Página 7

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

SALIDA SANITARIO

Lavaplatos Un 1.00 44,704.00 44,704.00

Poseta de aseo Un 1.00 44,704.00 44,704.00

Sifon de piso 2" Un 4.00 44,704.00 178,816.00

MONTAJE DE APARATOS

Lavaplatos Un 1.00 28,194.00 28,194.00

Aparatos Sanitarios

ml 0.70 340,140.00

INSTALACIONES ELECTRICAS

Un 5.00 75,534.00 377,670.00

Un 5.00 155,294.00 776,470.00

ASEO

Aseo general final m2 35.62 1,065.00 37,940.00

TOTAL COSTOS DIRECTOS 29,331,315.00

PRESPUESTO PUNTOS AIRE ACONDICIONADO SIN MINI SPLIT

PRESUPUESTO DE OBRACANTIDADES NUEVAS

Descripción Vr/Un. Cant. Vr/TotalNUEVO PUNTOS AIRE ACONDICIONADO

17,2,6 NUEVO Tuberia PVC presion de 1/2" ml 5,464.00 144.00 786,816.00

17,3,1 NUEVO Punto desague inicial aire acondicionado Un 35,479.00 24.00 851,496.00

17,3,3 NUEVO Punto desague final aire acondicionado Un 44,704.00 24.00 1,072,896.00

20.1 NUEVO ml 50,000.00 240.00 12,000,000.00

NUEVO Tubo conduit de 1/2 ml 8,500.00 240.00 2,040,000.00

SUBTOTAL 16,751,208.00

OBRA NUEVA CONSTRUCCION RED ALCANTARILLADO

PRESUPUESTO DE OBRACANTIDADES NUEVAS

ESP. EPM Descripción Vr/Un. Cant. Vr/Total100 PRELIMINARES ML 3,844.00 75.00 288,300.00

104Localización, trazado y replanteo con equipo.

-

-

801, 803 ML 84,380.37 75.00

6,328,528.00

Ø 8" (NOVAFORT) ML -

Ø 46" ML -

Ø 36" ML -

Ø 36" -

-

300 CONCRETOS M3 47,530.00 0.00 -

301 Corte y retiro de pavimento M3 386,109.50 0.00 -

300 -

-

201,204,205,206 EXCAVACIONES Y LLENOS 29,850.00 150.00 4,477,500.00

Meson en Acero Inoxidable Cal 18 G Hosp. 304 incluye, posuelo, canastilla, griferia.

Toma doble con polo a tierra 120v-15a levinton cable cobre tipo THWN en 2n°12+1N°14t-tubo EMT 1/2"

Salida para lampara fluorescente incrustar t8 encendido electronico de 2x32w, velas marca philis o silvania, incluye lampara

Un. de pago

tuberia flexible de cobre de 1/2" y 1/4 con pvc y poliuretano

Un. de pago

SUMINISTRO INSTALACION Y TRANSPORTE DE TUBERIAS PARA ALCANTARILLADO NOVAFORT, INCLUYE BOMBEO Y ENTIBADO

M3

Page 8: Presupuesto Obra Adicionales

Página 8

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

201,204,205,208 15,770.00 112.50

1,774,125.00

201,204,205,208 Retiro de material sobrante de excavación M3 58,940.00 7.50 442,050.00

404.704M3 19,726.00 37.50

739,725.00

201,204,205,208 Relleno en material de excavación M3 58,940.00 105.00 6,188,700.00

201,204,205,208 Relleno en material seleccionado -

Excavaciones en material comùn h= de 0 a 2mts

M3

Lleno en material seleccionado para cimentación de tuberias

Page 9: Presupuesto Obra Adicionales

Página 9

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

-

806.0 un 68,520.3 -

-

un 213,411.7 - -

Kit Silla Yee 12" x 6" (Completa) un 197,893.3 - -

Kit Silla Yee 10" x 6" (Completa) UND 846,418.0 10.0 8,464,180.00

Ø 8" x 6" un 27,814.7 - -

Codo de 6 x 45 ml 30,453.8 - -

Tubo Ø 6" Un 97,654.5 - -

Instalación conexión domiciliaria -

ML 1,243,878.0 3.00 3,731,634.00

807, 808 -

-

REPARACION DE CANALES DE AGUAS LLUVIAS ML 730,047.50 10.00 7,300,475.00

Reparación de canales de aguas lluvias -

1000, 1003 REPARACION DE DUCTOS TELEFONICO ML 14,001.00 20.00 280,020.00

Reparación de ducto telefonico -

REPARACION DE TUBERIAS DE ACUEDUCTO ML 45,005.12 10.00 450,051.00

Reparación de tuberia de acueducto -

SUBTOTAL 40,465,288.00

AIU DE 25% 10,116,322.00

TOTAL COSTOS DIRECTOS -

OBRAS NUEVAS GASES MEDICINALES

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalGASES MEDICINALES

NUEVO

un

218,561.00

48.00

NUEVO un 218,561.00

1.00

NUEVO un 8,490,364.00

1.00

5,208,925.17

NUEVO un 4,990,364.00

1.00

4,990,364.00

SUMINISTRO TRANSPORTE E INSTALACION DE CONEXIONES DOMICILIARIAS DE ALCANTARILLADO INCLUYE EXCAVACIÒN Y LLENOS EN MATERIAL GRANULAR, CORTE DEMOLICION Y REPOSICION DE PAVIMENTO, CAJA DOMICILIARIA EN CONCRETO VACIADA DE 2500PSI CON CAÑUELA, KIT SILLA YEE

Derivación para domiciliaria para tuberias de 36" hasta 18", Ø 6"

ROTURA Y REPOSICIÒN DE CAMARAS DE INSPECCION

Un. de pago

Tomas para Gases Medicinales con doblecheque de pared Qc de Vacio Tipo Chemetron

Tomas para Gases Medicinales con doblecheque cielíticas DISS de Aire Medicinal TipoChemetron

Alarma Combinada 2 gases y 10 puntos - Sonoray Visual para monitoreo constante de Gases,programable, con sensores de estado solido

Alarma de Área de 2 Gases - Sonora y Visualpara monitoreo constante de Gases,programable, con sensores de estado solido

Page 10: Presupuesto Obra Adicionales

Página 10

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

NUEVO un 8,133,606.00

1.00

NUEVO un 66,887,250.00

1.00

NUEVO un 17,394,250.00

1.00

SUBTOTAL

10,199,289.17

ESTUCO AREA ASEPCIA

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalESTUCO AREA ASEPCIA

NUEVO ESTUCO AREA ASEPCIA M2 4,996.17 869.40 4,343,667.00

SUBTOTAL 4,343,667.00

DESAGUES TERRAZAS NORTE Y SUR

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalDESAGUES TERRAZA NORTE Y SUR

NUEVO UN 60,254.00 6.00 361,524.00

NUEVO ML 33,080.00 50.50 1,670,540.00

SUBTOTAL -

OBRAS NUEVAS INSTALACIONES ELECTRICAS

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalOBRAS ELECTRICAS NUEVAS

NUEVO TABLERO LAVADORA 3 X 100A UN 524,966.00 1.00 524,966.00

NUEVO TABLERO RX 3 X 150A UN 888,907.00 1.00 888,907.00

NUEVO TABLERO ASCENSOR 3 X 60A UN 524,966.00 1.00 524,966.00

NUEVO TABLERO AUTOCLAVE 3 X 80A UN 524,966.00 1.00 524,966.00

NUEVO ML 184,892.00 98.45 -

SUBTOTAL 2,463,805.00

OBRAS NUEVAS CARPINTERIA METALICA PUERTAS

Manifold Simplex para Thermo de Oxigeno 2 x 1para la distribución de Gases Medicinales

Compresor de Aire libre de aceite, de 3HP conuna capacidad de producción de 15 scfm@50PSI

Secador de Aire ciclado con sistema de válvulasy reguladores

Un. de pago

Un. de pago

17,5,2 ITEM BAHIRV

DESAGUES DE 6" TERRAZAS NORTE Y SUR...EN EL PLANO HIDROSANITARIO NO INCLUIA DESAGUES

17,9,2 ITEM BAHIRV

BAJANTE SALIDA DESAGUES TERREZAS NORTE Y SUR...NO ESTABAN PRESUPUESTADOS

Un. de pago

18,2,4 ITEM BAHIRV

18,3,4 ITEM BAHIRV

18,2,4 ITEM BAHIRV

18,2,4 ITEM BAHIRV

18,6,4 ITEM BAHIRV

Acometida principal en cable tipo AAAC de 15 KV en 3N° 1/0 con bajante en tuberia conduit galv. De 4" PVC 2" de 4"

Page 11: Presupuesto Obra Adicionales

Página 11

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

Page 12: Presupuesto Obra Adicionales

Página 12

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

NUEVO UN 250,240.00 - -

NUEVO UN 115,216.00 - -

NUEVOPuerta metálica cal 18 de acceso, 0.80 X 2.10 mts

UN 447,553.00 1.00 447,553.00 13.1 NUEVO Cerradura Interior marcha shlage linea ball platinum Un 44,120.00 1.00 44,120.00

NUEVOPintura esmalte domestico de pintuco puerta en madera

M2 13,803.00 2.11 29,095.00

NUEVO UN 25,974.00 - -

SUBTOTAL 520,768.00

OBRAS NUEVAS MACHONES APOYO ACERO INOXIDABLE

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalOBRAS APOYO MACHONES

NUEVOMuro en bloque de arcilla No 4 (10*20*40)

UN 25,444.00 28.08 714,468.00

NUEVOPañete Liso 1:4

UN 14,021.00 56.16 787,419.00

NUEVO UN 13,997.00 56.16 786,072.00

SUBTOTAL -

OBRAS NUEVAS ESCALERA ACCESO CASETA TRANSFORMADOR Y DESECHOS

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalOBRAS APOYO MACHONES

NUEVOConcreto escalereas f´c = 3000 PSI

M3 483,894.00 2.53 1,226,033.00

NUEVOACERO DE REFUERZO

KG 2,789.00 213.50 595,452.00

SUBTOTAL -

OBRAS NUEVAS POTABILIZACION EQUIPO

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalOBRAS DE POTABILIZACION

NUEVO UN 27,850,000.00 1.00 27,850,000.00

M2 84,858.00 2.00 169,716.00

M3 60,222.00 1.00 60,222.00

M3 53,840.00 1.00 53,840.00 TOMAS ELECTRICOS UN 75,534.00 2.00 151,068.00 PUNTOS HIDRAULICOS UN 26,995.00 2.00 53,990.00 SALIDAS SANITARIAS UN 60,254.00 2.00 120,508.00

OBRAS CARPINTERIA METALICA PUERTAS RACK Y CUARTO MAQUINA Y ACCESO CUARTO GASES MEDICINAL

12.1 ITEM BAHIRV

Puerta en madera entamborada en triplex Okume e= 4 mm de 0.80 m x 2.10 m

12.2 ITEM BAHIRV

Marco metálico en Lámina Galvanizada de 0.88 m x 2.16 m Cal 20 con patas de anclaje para puertas de madera

12.16 ITEM BAHIRV

14.3 ITEM BAHIRV

14.4 ITEM BAHIRV

Wash Primer y esmalte blanco domestico pintuco para marco metálico en Lámina Galvanizada de 0.88 m x 2.16 m

Un. de pago

4.1 ITEM BAHIRV

6.1 ITEM BAHIRV

14.1 ITEM BAHIRV

Estuco y pintura pared interior en vinilo viniltex pintuco 3 manos (2 capas tipo 2 y acabado tipo 1)

Un. de pago

3,10 ITEM BAHIRV

3,18 ITEM BAHIRV

Un. de pago

CONSTRUCCION Y PUESTA EN MARCHA PLANTA DE FUNCIONAMIENTO OBRAS DE POTABILIZACION

PLACA EN CONCRETO HIDRAULICO DE 3500 PSI ESPESOR e=0.18MTS INCLUYE ACELERANTE DE FRAGUADO Y SELLADO ASFALTICO

RELLENO EN RECEBO COMPACTADO AL 95% PROCTOR MODIFICADO

EXCAVACION MISCELANEAS (PARA RELLENO OBRAS EXTERIOR PLACA CONCRETO)

Page 13: Presupuesto Obra Adicionales

Página 13

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

Malla electrosoldada 6mm- 15cmx 15cm M2 7,415.00 2.00 14,830.00

SUBTOTAL 28,474,174.00

Page 14: Presupuesto Obra Adicionales

Página 14

Descripción Vr/Un. Cant. Vr/TotalUn. de pago

OBRAS NUEVAS POZO PROFUNDO PARA CAPTACION DE AGUA

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalOBRAS POZO PROFUNDO

NUEVO UN 44,025,826.00 1.00 44,025,826.00

SUBTOTAL 44,025,826.00

OBRAS MURO DE CONTENCION

PRESUPUESTO DE OBRA

NUEVAS ACTIVIDADES

Descripción Vr/Un. Cant. Vr/TotalMUROS DE CONTENCION

MURO H = 5,00m (L = 10,00m) UN 8,033,709.00 1.00 8,033,709.00

ALETA MURO ADICIONAL H = 5,00m (L = 7,00m)UN 24,758,606.00 1.00 24,758,606.00

MURO H = 4,00m /L = 44,00m) UN 8,469,254.00 1.00 8,469,254.00 MURO H = 3,00m (L = 6,00m) UN 11,313,129.00 1.00 11,313,129.00 MURO H = 1,80m (L = 4,00m) UN 4,437,055.00 1.00 4,437,055.00 MURO H = 1,25m (L = 3,00m) UN 2,245,780.00 1.00 2,245,780.00

UN 13,118,173.33 1.00 13,118,173.00 MURO H = 3,00m (L = 25,00m) UN 55,630,171.00 (1.00) (55,630,171.00)SUBTOTAL 16,745,535.00

COSTO DIRECTO TOTAL 256,594,092.00

Administración 13.00% 33,357,232.00

Imprevisto 3.00% 7,697,823.00

Utilidad 4.00% 10,263,764.00 Iva (16% sobre Utilidad)

COSTO TOTAL 307,912,911.00

Ing. Wladimir Ledesma Ing. Milena Hoyos Palacios Arq. Henry Valdez Lara

Realizo Realizo VoBo

Un. de pago

ESTUDIO, DISEÑO Y CONTRUCCION POZO PROFUNDO

Un. de pago

RELLENO SELECCIONADO TERMINACION MUROS DE CONTENCION H5 Y H4

NOTA: SON LOS VALORES PARA TERMINAR DE REALIZAR LA CONSTRUCCION Y LLENO DEL MURO TIPO 3 DE 3M DE ALTURA Y LOS LLENO AL 100% DE LOS MURO TIPO 1 DE 5M Y TIPO 2 DE 4M