prestressed concrete iit-m.pdf

Upload: sandeepgolu19

Post on 02-Apr-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 prestressed concrete IIT-M.pdf

    1/489

    1.1 Introduction

    This section covers the following topics.

    Basic Concept

    Early Attempts of Prestressing

    Brief History

    Development of Building Materials

    1.1.1 Basic Concept

    A prestressed concrete structure is different from a conventional reinforced concrete

    structure due to the application of an initial load on the structure prior to its use.

    The initial load or prestress is applied to enable the structure to counteract the stresses

    arising during its service period.

    The prestressing of a structure is not the only instance of prestressing. The concept of

    prestressing existed before the applications in concrete. Two examples of prestressing

    before the development of prestressed concrete are provided.

    Force-fitting of metal bands on wooden barrels

    The metal bands induce a state of initial hoop compression, to counteract the hoop

    tension caused by filling of liquid in the barrels.

    Metal bandsMetal bands

    Figure 1-1.1 Force-fitting of metal bands on wooden barrels

    Pre-tensioning the spokes in a bicycle wheel

    The pre-tension of a spoke in a bicycle wheel is applied to such an extent that there will

    always be a residual tension in the spoke.

    http://basic%20concepts/http://early%20attempts%20of%20prestressing/http://brief%20history/http://development%20of%20building%20materials/http://development%20of%20building%20materials/http://brief%20history/http://early%20attempts%20of%20prestressing/http://basic%20concepts/
  • 7/27/2019 prestressed concrete IIT-M.pdf

    2/489

    SpokesSpokes

    Figure 1-1.2 Pre-tensioning the spokes in a bicycle wheel

    For concrete, internal stresses are induced (usually, by means of tensioned steel) for

    the following reasons.

    The tensile strength of concrete is only about 8% to 14% of its compressive

    strength.

    Cracks tend to develop at early stages of loading in flexural members such as

    beams and slabs.

    To prevent such cracks, compressive force can be suitably applied in the

    perpendicular direction.

    Prestressing enhances the bending, shear and torsional capacities of the flexural

    members.

    In pipes and liquid storage tanks, the hoop tensile stresses can be effectively

    counteracted by circular prestressing.

    1.1.2 Early Attempts of Prestressing

    Prestressing of structures was introduced in late nineteenth century. The following

    sketch explains the application of prestress.

    Place and stretch mild steel rods, prior to concreting

    Release the tension and cut the rods after concreting

    Place and stretch mild steel rods, prior to concreting

    Release the tension and cut the rods after concreting

    Figure 1-1.3 Prestressing of concrete beams by mild steel rods

  • 7/27/2019 prestressed concrete IIT-M.pdf

    3/489

    Mild steel rods are stretched and concrete is poured around them. After hardening of

    concrete, the tension in the rods is released. The rods will try to regain their original

    length, but this is prevented by the surrounding concrete to which the steel is bonded.

    Thus, the concrete is now effectively in a state of pre-compression. It is capable of

    counteracting tensile stress, such as arising from the load shown in the following sketch.

    Figure 1-1.4 A prestressed beam under an external load

    But, the early attempts of prestressing were not completely successful. It was observed

    that the effect of prestress reduced with time. The load resisting capacities of the

    members were limited. Under sustained loads, the members were found to fail. This

    was due to the following reason.

    Concrete shrinks with time. Moreover under sustained load, the strain in concrete

    increases with increase in time. This is known as creep strain. The reduction in length

    due to creep and shrinkage is also applicable to the embedded steel, resulting in

    significant loss in the tensile strain.

    In the early applications, the strength of the mild steel and the strain during prestressing

    were less. The residual strain and hence, the residual prestress was only about 10% of

    the initial value. The following sketches explain the phenomena.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    4/489

    Original length of steel rod (L1)

    Original length of concrete beam (L2

    )

    Original length of steel rod (L1)

    Original length of concrete beam (L2

    )

    a) Beam before applying prestress

    Reduced length of concrete beam (L3)Reduced length of concrete beam (L3)

    b) Beam at transfer of prestress

    Final length of prestressed beam (L4)Final length of prestressed beam (L4)

    c) Beam after long-term losses of prestress

    Figure 1-1.5 Variation of length in a prestressed beam

    The residual strain in steel = original tensile strain in steel compressive strainscorresponding to short-term and long-term losses.

    Original tensile strain in steel = (L2 L1)/L1

    Compressive strain due to elastic shortening of beam = (L2 L3)/L1

    (short-term loss in prestress)

    Compressive strain due to creep and shrinkage = (L3 L4)/L1

    (long-term losses in prestress)

    Therefore, residual strain in steel = (L4 L1)/L1

    The maximum original tensile strain in mild steel = Allowable stress / elastic

    modulus

    = 140 MPa / 2105 MPa

    = 0.0007

  • 7/27/2019 prestressed concrete IIT-M.pdf

    5/489

    The total loss in strain due to elastic shortening, creep and shrinkage was also close to

    0.0007. Thus, the residual strain was negligible.

    The solution to increase the residual strain and the effective prestress are as follows.

    Adopt high st rength steel with much higher original strain. This leads to the

    scope of high prestressing force. Adopt high strength concrete to withstand the high prestressing force.

    1.1.3 Brief History

    Before the development of prestressed concrete, two significant developments of

    reinforced concrete are the invention of Portland cement and introduction of steel in

    concrete. These are also mentioned as the part of the history. The key developments

    are mentioned next to the corresponding year.

    1824 Aspdin, J ., (England)

    Obtained a patent for the manufacture of Portland cement.

    1857 Monier, J ., (France)

    Introduced steel wires in concrete to make flower pots, pipes, arches and slabs.

    The following events were significant in the development of prestressed concrete.

    1886 J ackson, P. H., (USA)

    Introduced the concept of tightening steel tie rods in artificial stone and concrete

    arches.

    Figure 1-1.6 Steel tie rods in arches

    1888 Doehring, C. E. W., (Germany)

    Manufactured concrete slabs and small beams with embedded tensioned steel.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    6/489

    1908 Stainer, C. R., (USA)

    Recognised losses due to shrinkage and creep, and suggested retightening the

    rods to recover lost prestress.

    1923 Emperger, F., (Austria)

    Developed a method of winding and pre- tensioning high tensile steel wiresaround concrete pipes.

    1924 Hewett, W. H., (USA)

    Introduced hoop-stressed horizontal reinforcement around walls of concrete

    tanks through the use of turnbuckles.

    Thousands of liquid storage tanks and concrete pipes were built in the two decades to

    follow.

    1925 Dill, R. H., (USA)

    Used high strength unbonded steel rods. The rods were tensioned and anchored

    after hardening of the concrete.

    Figure 1-1.7 Portrait of Eugene Freyssinet

    (Reference: Collins, M. P. and Mitchell, D.,Prestressed Concrete Structures)

    1926 Eugene Freyssinet (France)

    Used high tensile steel wires, with ultimate strength as high as 1725 MPa and

    yield stress over 1240 MPa. In 1939, he developed conical wedges for end

    anchorages for post-tensioning and developed double-acting jacks. He is often

    referred to as the Father of Prestressed concrete.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    7/489

    1938 Hoyer, E., (Germany)

    Developed long line pre-tensioning method.

    1940 Magnel, G., (Belgium)

    Developed an anchoring system for post-tensioning, using flat wedges.

    During the Second World War, applications of prestressed and precast concrete

    increased rapidly. The names of a few persons involved in developing prestressed

    concrete are mentioned. Guyon, Y., (France) built numerous prestressed concrete

    bridges in western and central Europe. Abeles, P. W., (England) introduced the

    concept of partial prestressing. Leonhardt, F., (Germany), Mikhailor, V., (Russia) and

    Lin, T. Y., (USA) are famous in the field of prestressed concrete.

    The International Federation for Prestressing (FIP), a professional organisation in

    Europe was established in 1952. The Precast/Prestressed Concrete Institute (PCI) was

    established in USA in 1954.

    Prestressed concrete was started to be used in building frames, parking structures,

    stadiums, railway sleepers, transmission line poles and other types of structures and

    elements.

    In India, the applications of prestressed concrete diversified over the years. The first

    prestressed concrete bridge was built in 1948 under the Assam Rail Link Project.

    Among bridges, the Pamban Road Bridge at Rameshwaram, Tamilnadu, remains a

    classic example of the use of prestressed concrete girders.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    8/489

    Figure 1-1.8 Pamban Road Bridge at Rameshwaram, Tamilnadu

    (Reference: http://www.ramnad.tn.nic.in)

    1.1.4 Development of Building Materials

    The development of prestressed concrete can be studied in the perspective of

    traditional building materials. In the ancient period, stones and bricks were extensively

    used. These materials are strong in compression, but weak in tension. For tension,

    bamboos and coir ropes were used in bridges. Subsequently iron and steel bars were

    used to resist tension. These members tend to buckle under compression. Wood and

    structural steel members were effective both in tension and compression.

    In reinforced concrete, concrete and steel are combined such that concrete resists

    compression and steel resists tension. This is a passive combination of the two

    materials. In prestressed concrete high strength concrete and high strength steel are

    combined such that the full section is effective in resisting tension and compression.

    This is an active combination of the two materials. The following sketch shows the use

    of the different materials with the progress of time.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    9/489

    Compression (C) Tension (T) C and T

    Stones, Bricks Bamboo, Ropes Timber

    Structural steelSteel bars, wires

    Reinforced

    Concrete

    Prestressed

    Concrete

    Passive combination

    High StrengthSteel

    High StrengthConcrete

    Active combination

    Concrete

    Compression (C) Tension (T) C and T

    Stones, Bricks Bamboo, Ropes Timber

    Structural steelSteel bars, wires

    Reinforced

    Concrete

    Prestressed

    Concrete

    Passive combination

    High StrengthSteel

    High StrengthConcrete

    Active combination

    Concrete

    Figure 1-1.9 Development of building materials

    (Reference: Lin, T. Y. and Burns, N. H.,

    Design of Prestressed Concrete Structures)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    10/489

    1.2 Advantages and Types of Prestressing

    This section covers the following topics.

    Definitions

    Advantages of Prestressing

    Limitations of Prestressing

    Types of Prestressing

    1.2.1 Definitions

    The terms commonly used in prestressed concrete are explained. The terms are placed

    in groups as per usage.

    Forms of Prestressing Steel

    Wires

    Prestressing wire is a single unit made of steel.

    Strands

    Two, three or seven wires are wound to form a prestressing strand.

    Tendon

    A group of strands or wires are wound to form a prestressing tendon.

    Cable

    A group of tendons form a prestressing cable.

    Bars

    A tendon can be made up of a single steel bar. The diameter of a bar is much

    larger than that of a wire.

    The different types of prestressing steel are further explained in Section 1.7,

    Prestressing Steel.

    Nature of Concrete-Steel Interface

    Bonded tendon

    When there is adequate bond between the prestressing tendon and concrete, it is called

    a bonded tendon. Pre-tensioned and grouted post-tensioned tendons are bonded

    tendons.

    http://definitions/http://advantages%20of%20prestressing/http://types%20of%20prestressing/http://types%20of%20prestressing/http://advantages%20of%20prestressing/http://definitions/
  • 7/27/2019 prestressed concrete IIT-M.pdf

    11/489

    Unbonded tendon

    When there is no bond between the prestressing tendon and concrete, it is called

    unbonded tendon. When grout is not applied after post-tensioning, the tendon is an

    unbonded tendon.

    Stages of LoadingThe analysis of prestressed members can be different for the different stages of loading.

    The stages of loading are as follows.

    1) Initial : It can be subdivided into two stages.

    a) During tensioning of steel

    b) At transfer of prestress to concrete.

    2) Intermediate : This includes the loads during transportation of the

    prestressed members.

    3) Final : It can be subdivided into two stages.

    a) At service, during operation.

    b) At ultimate, during extreme events.

    1.2.2 Advantages of Prestressing

    The prestressing of concrete has several advantages as compared to traditional

    reinforced concrete (RC) without prestressing. A fully prestressed concrete member is

    usually subjected to compression during service life. This rectifies several deficiencies

    of concrete.

    The following text broadly mentions the advantages of a prestressed concrete member

    with an equivalent RC member. For each effect, the benefits are listed.

    1) Section remains uncracked under service loads

    Reduction of steel corrosion

    Increase in durability.

    Full section is utilised Higher moment of inertia (higher stiffness)

    Less deformations (improved serviceability).

  • 7/27/2019 prestressed concrete IIT-M.pdf

    12/489

    Increase in shear capacity.

    Suitable for use in pressure vessels, liquid retaining structures.

    Improved performance (resilience) under dynamic and fatigue loading.

    2) High span-to-depth ratios

    Larger spans possible with prestressing (bridges, buildings with large column-free

    spaces)Typical values of span-to-depth ratios in slabs are given below.

    Non-prestressed slab 28:1

    Prestressed slab 45:1

    For the same span, less depth compared to RC member.

    Reduction in self weight

    More aesthetic appeal due to slender sections

    More economical sections.

    3) Suitable for precast construction

    The advantages of precast construction are as follows.

    Rapid construction

    Better quality control

    Reduced maintenance

    Suitable for repetitive construction

    Multiple use of formwork

    Reduction of formwork

    Availability of standard shapes.

    The following figure shows the common types of precast sections.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    13/489

    Double T-sectionT-section

    Hollow core Piles

    Double T-sectionDouble T-sectionT-sectionT-section

    Hollow core Piles

    L-section Inverted T-section I-girdersL-section Inverted T-section I-girders

    Figure 1-2.1 Typical precast members

    1.2.3 Limi tations of Prestressing

    Although prestressing has advantages, some aspects need to be carefully addressed.

    Prestressing needs skilled technology. Hence, it is not as common as reinforced

    concrete.

    The use of high strength materials is costly. There is additional cost in auxiliary equipments.

    There is need for quality control and inspection.

    1.2.4 Types of Prestressing

    Prestressing of concrete can be classified in several ways. The following classifications

    are discussed.

    Source of prestressing force

    This classification is based on the method by which the prestressing force is generated.

    There are four sources of prestressing force: Mechanical, hydraulic, electrical and

    chemical.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    14/489

    External or internal prestressing

    This classification is based on the location of the prestressing tendon with respect to the

    concrete section.

    Pre-tensioning or post-tensioning

    This is the most important classification and is based on the sequence of casting theconcrete and applying tension to the tendons.

    Linear or circular prestressing

    This classification is based on the shape of the member prestressed.

    Full, limited or partial prestressing

    Based on the amount of prestressing force, three types of prestressing are defined.

    Uniaxial, biaxial or multi-axial prestressing

    As the names suggest, the classification is based on the directions of prestressing a

    member.

    The individual types of prestressing are explained next.

    Source of Prestressing Force

    Hydraulic Prestressing

    This is the simplest type of prestressing, producing large prestressing forces. The

    hydraulic jack used for the tensioning of tendons, comprises of calibrated pressure

    gauges which directly indicate the magnitude of force developed during the tensioning.

    Mechanical Prestressing

    In this type of prestressing, the devices includes weights with or without lever

    transmission, geared transmission in conjunction with pulley blocks, screw jacks with or

    without gear drives and wire-winding machines. This type of prestressing is adopted for

    mass scale production.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    15/489

  • 7/27/2019 prestressed concrete IIT-M.pdf

    16/489

    Figure 1-2.3 Internal prestressing of a box girder

    (Courtesy: Cochin Port Trust, Kerala)

    Pre-tensioning or Post-tensioning

    Pre-tensioning

    The tension is applied to the tendons before casting of the concrete. The pre-

    compression is transmitted from steel to concrete through bond over the transmission

    length near the ends. The following figure shows manufactured pre-tensioned electric

    poles.

    Figure 1-2.4 Pre-tensioned electric poles

    (Courtesy: The Concrete Products and Construction Company, COPCO, Chennai)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    17/489

    Post-tensioning

    The tension is applied to the tendons (located in a duct) after hardening of the concrete.

    The pre-compression is transmitted from steel to concrete by the anchorage device (at

    the end blocks). The following figure shows a post-tensioned box girder of a bridge.

    Figure 1-2.5 Post-tensioning of a box girder

    (Courtesy: Cochin Port Trust, Kerala)

    The details of pre-tensioning and post-tensioning are covered under Section 1.3, Pre-

    tensioning Systems and Devices, and Section 1.4, Post-tensioning Systems and

    Devices, respectively.

    Linear or Circular Prestressing

    Linear Prestressing

    When the prestressed members are straight or flat, in the direction of prestressing, the

    prestressing is called linear prestressing. For example, prestressing of beams, piles,

    poles and slabs. The profile of the prestressing tendon may be curved. The following

    figure shows linearly prestressed railway sleepers.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    18/489

    Figure 1-2.6 Linearly prestressed railway sleepers

    (Courtesy: The Concrete Products and Construction Company, COPCO, Chennai)

    Circular Prestressing

    When the prestressed members are curved, in the direction of prestressing, the

    prestressing is called circular prestressing. For example, circumferential prestressing of

    tanks, silos, pipes and similar structures. The following figure shows the containment

    structure for a nuclear reactor which is circularly prestressed.

    Figure 1-2.7 Circularly prestressed containment structure, Kaiga Atomic PowerStation, Karnataka

    (Reference: Larsen & Toubro Ltd, ECC Division, 60 Landmark Years)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    19/489

    Full, Limited or Partial Prestressing

    Full Prestressing

    When the level of prestressing is such that no tensile stress is allowed in concrete under

    service loads, it is called Full Prestressing (Type 1, as per IS:1343 - 1980).

    Limited PrestressingWhen the level of prestressing is such that the tensile stress under service loads is

    within the cracking stress of concrete, it is called Limited Prestressing (Type 2).

    Partial Prestressing

    When the level of prestressing is such that under tensile stresses due to service loads,

    the crack width is within the allowable limit, it is called Partial Prestressing (Type 3).

    Uniaxial, Biaxial or Multiaxial Prestressing

    Uniaxial Prestressing

    When the prestressing tendons are parallel to one axis, it is called Uniaxial Prestressing.

    For example, longitudinal prestressing of beams.

    Biaxial Prestressing

    When there are prestressing tendons parallel to two axes, it is called Biaxial

    Prestressing. The following figure shows the biaxial prestressing of slabs.

    Duct forprestressingtendon

    Non-prestressed reinforcement

    Duct forprestressingtendon

    Non-prestressed reinforcement

    Figure 1-2.8 Biaxial prestressing of a slab

    (Courtesy: VSL India Pvt. Ltd., Chennai)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    20/489

    Multiaxial Prestressing

    When the prestressing tendons are parallel to more than two axes, it is called Multiaxial

    Prestressing. For example, prestressing of domes.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    21/489

    1.3 Pre-tensioning Systems and Devices

    This section covers the following topics.

    Introduction

    Stages of Pre-tensioning

    Advantages of Pre-tensioning

    Disadvantages of Pre-tensioning

    Devices

    Manufacturing of Pre-tensioned Railway Sleepers

    1.3.1 Introduct ion

    Prestressing systems have developed over the years and various companies have

    patented their products. Detailed information of the systems is given in the product

    catalogues and brochures published by companies. There are general guidelines of

    prestressing in Section 12 ofIS:1343 - 1980. The information given in this section is

    introductory in nature, with emphasis on the basic concepts of the systems.

    The prestressing systems and devices are described for the two types of prestressing,

    pre-tensioning and post-tensioning, separately. This section covers pre-tensioning.

    Section 1.4, Post-tensioning Systems and Devices, covers post-tensioning. In pre-

    tensioning, the tension is applied to the tendons before casting of the concrete. The

    stages of pre-tensioning are described next.

    1.3.2 Stages of Pre-tensioning

    In pre-tensioning system, the high-strength steel tendons are pulled between two end

    abutments (also called bulkheads) prior to the casting of concrete. The abutments are

    fixed at the ends of a prestressing bed.

    Once the concrete attains the desired strength for prestressing, the tendons are cut

    loose from the abutments.

    http://prestressing%20systems%20and%20devices/http://prestressing%20systems%20and%20devices/
  • 7/27/2019 prestressed concrete IIT-M.pdf

    22/489

    The prestress is transferred to the concrete from the tendons, due to the bond between

    them. During the transfer of prestress, the member undergoes elastic shortening. If the

    tendons are located eccentrically, the member is likely to bend and deflect (camber).

    The various stages of the pre-tensioning operation are summarised as follows.

    1) Anchoring of tendons against the end abutments

    2) Placing of jacks3) Applying tension to the tendons

    4) Casting of concrete

    5) Cutting of the tendons.

    During the cutting of the tendons, the prestress is transferred to the concrete with elastic

    shortening and camber of the member.

    The stages are shown schematically in the following figures.

    Prestressing bed

    Steel tendon

    Endabutment

    Jack

    Prestressing bed

    Steel tendon

    Endabutment

    Jack

    (a) Applying tension to tendons

    (b) Casting of concrete

    Cutting of tendonCutting of tendon

    (c) Transferring of prestress

    Figure1-3.1 Stages of pre-tensioning

    1.3.3 Advantages of Pre-tensioning

    The relative advantages of pre-tensioning as compared to post-tensioning are as

    follows.

    Pre-tensioning is suitable for precast members produced in bulk.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    23/489

    In pre-tensioning large anchorage device is not present.

    1.3.4Disadvantages of Pre-tensioning

    The relative disadvantages are as follows.

    A prestressing bed is required for the pre-tensioning operation. There is a waiting period in the prestressing bed, before the concrete attains

    sufficient strength.

    There should be good bond between concrete and steel over the transmission

    length.

    1.3.5 Devices

    The essential devices for pre-tensioning are as follows.

    Prestressing bed

    End abutments

    Shuttering / mould

    J ack

    Anchoring device

    Harping device (optional)

    Prestressing Bed, End Abutments and Mould

    The following figure shows the devices.

    Prestressing bed

    Mould

    Endabutment

    Jack

    Anchoringdevice

    Prestressing bed

    Mould

    Endabutment

    Jack

    Anchoringdevice

    Prestressing bed

    Mould

    Endabutment

    Jack

    Anchoringdevice

    Figure1-3.2 Prestressing bed, end abutment and mould

    An extension of the previous system is the Hoyer system. This system is generally

    used for mass production. The end abutments are kept sufficient distance apart, and

    several members are cast in a single line. The shuttering is provided at the sides and

  • 7/27/2019 prestressed concrete IIT-M.pdf

    24/489

    between the members. This system is also called the Long Line Method. The

    following figure is a schematic representation of the Hoyer system

    Prestressing bed

    A series of moulds

    Prestressing bed

    A series of moulds

    Figure 1-3.3 Schematic representation of Hoyer system

    The end abutments have to be sufficiently stiff and have good foundations. This is

    usually an expensive proposition, particularly when large prestressing forces are

    required. The necessity of stiff and strong foundation can be bypassed by a simpler

    solution which can also be a cheaper option. It is possible to avoid transmitting the

    heavy loads to foundations, by adopting self-equilibrating systems. This is a common

    solution in load-testing. Typically, this is done by means of a tension frame. The

    following figure shows the basic components of a tension frame. The jack and the

    specimen tend to push the end members. But the end members are kept in place by

    members under tension such as high strength steel rods.

    P

    Free bodiesPlan or Elevation

    TestspecimenHigh

    strengthsteel rods

    Loading

    jack

    P

    Free bodies

    P

    Free bodiesPlan or Elevation

    TestspecimenHigh

    strengthsteel rods

    Loading

    jack

    Plan or Elevation

    TestspecimenHigh

    strengthsteel rods

    Loading

    jack

    Figure 1-3.4 A tension frame

    The frame that is generally adopted in a pre-tensioning system is called a stress bench.

    The concrete mould is placed within the frame and the tendons are stretched and

    anchored on the booms of the frame. The following figures show the components of astress bench.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    25/489

    Jack

    Threaded rodElevation

    Plan

    Mould Strands

    Jack

    Threaded rodElevation

    Jack

    Threaded rodElevation

    Plan

    Mould Strands

    Plan

    Mould Strands

    Figure 1-3.5 Stress bench Self straining frame

    The following figure shows the free body diagram by replacing the jacks with the applied

    forces.

    Plan

    Load by jack

    Tension instrands

    Plan

    Load by jack

    Tension instrands

    Figure 1-3.6 Free body diagram of stress bench

    The following figure shows the stress bench after casting of the concrete.

    Elevation

    Plan

    Elevation

    Plan

    Figure 1-3.7 The stress bench after casting concrete

  • 7/27/2019 prestressed concrete IIT-M.pdf

    26/489

    Jacks

    The jacks are used to apply tension to the tendons. Hydraulic jacks are commonly used.

    These jacks work on oil pressure generated by a pump. The principle behind the design

    of jacks is Pascals law. The load applied by a jack is measured by the pressure

    reading from a gauge attached to the oil inflow or by a separate load cell. The following

    figure shows a double acting hydraulic jack with a load cell.

    Figure 1-3.8 A double acting hydraulic jack with a load cell

    Anchor ing Devices

    Anchoring devices are often made on the wedge and friction principle. In pre-tensioned

    members, the tendons are to be held in tension during the casting and hardening of

    concrete. Here simple and cheap quick-release grips are generally adopted. The

    following figure provides some examples of anchoring devices.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    27/489

    Figure 1-3.9 Chuck assembly for anchoring tendons

    (Reference: Lin, T. Y. and Burns, N. H.,

    Design of Prestressed Concrete Structures)

    Harping Devices

    The tendons are frequently bent, except in cases of slabs-on-grade, poles, piles etc.

    The tendons are bent (harped) in between the supports with a shallow sag as shown

    below.

    Harping point Hold up device

    a) Before casting of concrete

    Harping point Hold up device

    a) Before casting of concretea) Before casting of concrete

    b) After casting of concreteb) After casting of concrete

    Figure 1-3.10 Harping of tendons

    The tendons are harped using special hold-down devices as shown in the following

    figure.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    28/489

    Figure 1-3.11 Hold-down anchor for harping of tendons

    (Reference: Nawy, E. G., Prestressed Concrete: A Fundamental Approach)

    1.3.6 Manufacturing of Pre-tensioned Railway Sleepers

    The following photos show the sequence of manufacturing of pre-tensioned railway

    sleepers (Courtesy: The Concrete Products and Construction Company, COPCO,

    Chennai). The steel strands are stretched in a stress bench that can be moved on

    rollers. The stress bench can hold four moulds in a line. The anchoring device holds

    the strands at one end of the stress bench. In the other end, two hydraulic jacks push a

    plate where the strands are anchored. The movement of the rams of the jacks and the

    oil pressure are monitored by a scale and gauges, respectively. Note that after the

    extension of the rams, the gap between the end plate and the adjacent mould has

    increased. This shows the stretching of the strands.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    29/489

    Meanwhile the coarse and fine aggregates are batched, mixed with cement, water and

    additives in a concrete mixer. The stress bench is moved beneath the concrete mixer.

    The concrete is poured through a hopper and the moulds are vibrated. After the

    finishing of the surface, the stress bench is placed in a steam curing chamber for a few

    hours till the concrete attains a minimum strength.

    The stress bench is taken out from the chamber and the strands are cut. The sleepers

    are removed from the moulds and stacked for curing in water. After the complete curing,

    the sleepers are ready for dispatching.

    (a) Travelling pre-tensioning stress bench

  • 7/27/2019 prestressed concrete IIT-M.pdf

    30/489

    Wedge andcylinderassembly atthe dead end

    Wedge andcylinderassembly atthe dead end

    (b) Anchoring of strands

    Hydraulic jack atstretching end

    Initial gap

    Endplate

    Hydraulic jack atstretching end

    Initial gap

    Endplate

    (c) Stretching of strands

  • 7/27/2019 prestressed concrete IIT-M.pdf

    31/489

  • 7/27/2019 prestressed concrete IIT-M.pdf

    32/489

    Automatedbatchingby weight

    Automatedbatchingby weight

    (f) Batching of materials

    Hopper belowconcrete mixerHopper belowconcrete mixer

    (g) Pouring of concrete

  • 7/27/2019 prestressed concrete IIT-M.pdf

    33/489

    (h) Concrete after vibration of mould

    (i) Steam curing chamber

  • 7/27/2019 prestressed concrete IIT-M.pdf

    34/489

    (j) Cutting of strands

    (k) Demoulding of sleeper

  • 7/27/2019 prestressed concrete IIT-M.pdf

    35/489

    (l) Stacking of sleeper

    (m) Water curing

  • 7/27/2019 prestressed concrete IIT-M.pdf

    36/489

    (n) Storage and dispatching of sleepers

    Figure 1-3.12 Manufacturing of pre-tensioned railway sleepers

  • 7/27/2019 prestressed concrete IIT-M.pdf

    37/489

    1.4 Post-tensioning Systems and Devices

    This section covers the following topics

    Introduction

    Stages of Post-tensioning

    Advantages of Post-tensioning

    Disadvantages of Post-tensioning

    Devices

    Manufacturing of a Post-tensioned Bridge Girder

    1.4.1 Introduction

    Prestressing systems have developed over the years and various companies have

    patented their products. Detailed information of the systems is given in the product

    catalogues and brochures published by companies. There are general guidelines of

    prestressing in Section 12 ofIS 1343: 1980. The information given in this section is

    introductory in nature, with emphasis on the basic concepts of the systems.

    The prestressing systems and devices are described for the two types of prestressing,

    pre-tensioning and post-tensioning, separately. This section covers post-tensioning.

    Section 1.3, Pre-tensioning Systems and Devices, covers pre-tensioning. In post-

    tensioning, the tension is applied to the tendons after hardening of the concrete. The

    stages of post-tensioning are described next.

    1.4.2 Stages of Post-tensioning

    In post-tensioning systems, the ducts for the tendons (or strands) are placed along with

    the reinforcement before the casting of concrete. The tendons are placed in the ducts

    after the casting of concrete. The duct prevents contact between concrete and the

    tendons during the tensioning operation.

    Unlike pre-tensioning, the tendons are pulled with the reaction acting against the

    hardened concrete.

    http://post-tensioning/http://post-tensioning/
  • 7/27/2019 prestressed concrete IIT-M.pdf

    38/489

    If the ducts are filled with grout, then it is known as bonded post-tensioning. The grout

    is a neat cement paste or a sand-cement mortar containing suitable admixture. The

    grouting operation is discussed later in the section. The properties of grout are

    discussed in Section 1.6, Concrete (Part-II).

    In unbonded post-tensioning, as the name suggests, the ducts are never grouted andthe tendon is held in tension solely by the end anchorages. The following sketch shows

    a schematic representation of a grouted post-tensioned member. The profile of the duct

    depends on the support conditions. For a simply supported member, the duct has a

    sagging profile between the ends. For a continuous member, the duct sags in the span

    and hogs over the support.

    Figure 1-4.1 Post-tensioning (Reference: VSL International Ltd.)

    Among the following figures, the first photograph shows the placement of ducts in a box

    girder of a simply supported bridge. The second photograph shows the end of the box

    girder after the post-tensioning of some tendons.

    Figure 1-4.2 Post-tensioning ducts in a box girder

    (Courtesy: Cochin Port Trust, Kerala)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    39/489

    Figure 1-4.3 Post-tensioning of a box girder

    (Courtesy: Cochin Port Trust, Kerala)

    The various stages of the post-tensioning operation are summarised as follows.

    1) Casting of concrete.

    2) Placement of the tendons.

    3) Placement of the anchorage block and jack.

    4) Applying tension to the tendons.

    5) Seating of the wedges.

    6) Cutting of the tendons.

    The stages are shown schematically in the following figures. After anchoring a tendon

    at one end, the tension is applied at the other end by a jack. The tensioning of tendons

    and pre-compression of concrete occur simultaneously. A system of self-equilibrating

    forces develops after the stretching of the tendons.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    40/489

    Casting bed

    Duct

    Side viewCasting bed

    Duct

    Side view

    (a) Casting of concrete

    JackJack

    (b) Tensioning of tendons

    AnchorAnchor

    (c)Anchoring the tendon at the stretching end

    Figure 1-4.4 Stages of post-tensioning (shown in elevation)

    1.4.3 Advantages of Post-tensioning

    The relative advantages of post-tensioning as compared to pre-tensioning are as

    follows.

    Post-tensioning is suitable for heavy cast-in-place members.

    The waiting period in the casting bed is less.

    The transfer of prestress is independent of transmission length.

    1.4.4 Disadvantage of Post-tensioning

    The relative disadvantage of post-tensioning as compared to pre-tensioning is the

    requirement of anchorage device and grouting equipment.

    1.4.5 Devices

    The essential devices for post-tensioning are as follows.

    1) Casting bed

    2) Mould/Shuttering

    3) Ducts

  • 7/27/2019 prestressed concrete IIT-M.pdf

    41/489

    4) Anchoring devices

    5) J acks

    6) Couplers (optional)

    7) Grouting equipment (optional).

    Casting Bed, Mould and DuctsThe following figure shows the devices.

    Casting bed

    Mould

    Duct

    Casting bed

    Mould

    Duct

    Figure 1-4.5 Casting bed, mould and duct

    Anchor ing Devices

    In post-tensioned members the anchoring devices transfer the prestress to the concrete.

    The devices are based on the following principles of anchoring the tendons.

    1) Wedge action

    2) Direct bearing

    3) Looping the wires

    Wedge action

    The anchoring device based on wedge action consists of an anchorage block and

    wedges. The strands are held by frictional grip of the wedges in the anchorage block.

    Some examples of systems based on the wedge-action are Freyssinet, Gifford-Udall,

    Anderson and Magnel-Blaton anchorages. The following figures show some patented

    anchoring devices.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    42/489

    Figure 1-4.6 Freyssinet T system anchorage cones

    (Reference: Lin, T. Y. and Burns, N. H., Design of Prestressed Concrete Structures)

    Figure 1-4.7 Anchoring devices

    (Reference: Collins, M. P. and Mitchell, D., Prestressed Concrete Structures)

    Figure 1-4.8 Anchoring devices (Reference: VSL International Ltd)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    43/489

    Direct bearing

    The rivet or bolt heads or button heads formed at the end of the wires directly bear

    against a block. The B.B.R.V post-tensioning system and the Prescon system are

    based on this principle. The following figure shows the anchoring by direct bearing.

    Figure 1-4.9 Anchoring with button heads

    (Reference: Collins, M. P. and Mitchell, D., Prestressed Concrete Structures)

    Looping the wires

    The Baur-Leonhardt system, Leoba system and also the Dwidag single-bar anchorage

    system, work on this principle where the wires are looped around the concrete. The

    wires are looped to make a bulb. The following photo shows the anchorage by looping

    of the wires in a post-tensioned slab.

    Figure 1-4.10 Anchorage by looping the wires in a slab

    (Courtesy : VSL India Pvt. Ltd.)

    The anchoring devices are tested to calculate their strength. The following photo shows

    the testing of an anchorage block.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    44/489

    Figure 1-4.11 Testing of an anchorage device

    Sequence of Anchoring

    The following figures show the sequence of stressing and anchoring the strands. The

    photo of an anchoring device is also provided.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    45/489

    Figure 1-4.12 Sequence of anchoring

    (Reference: VSL International Ltd.)

    Figure 1-4.13 Final form of an anchoring device

    (Reference: VSL International Ltd)

    JacksThe working of a jack and measuring the load were discussed in Section 1.3, Pre-

    tensioning Systems and Devices. The following figure shows an extruded sketch of the

    anchoring devices.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    46/489

    Figure 1-4.14 J acking and anchoring with wedges

    (Reference: Collins, M. P. and Mitchell, D., Prestressed Concrete Structures)

    Couplers

    The couplers are used to connect strands or bars. They are located at the junction of

    the members, for example at or near columns in post-tensioned slabs, on piers in post-

    tensioned bridge decks.

    The couplers are tested to transmit the full capacity of the strands or bars. A few types

    of couplers are shown.

    Figure 1-4.15 Coupler for strands

    (Reference: VSL International Ltd)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    47/489

    Figure 1-4.16 Couplers for strands

    (Reference: Dywidag Systems International)

    Figure 1-4.17 Couplers for strands

    (Reference: Dywidag Systems International)

  • 7/27/2019 prestressed concrete IIT-M.pdf

    48/489

    GroutingGrouting can be defined as the filling of duct, with a material that provides an anti-

    corrosive alkaline environment to the prestressing steel and also a strong bond between

    the tendon and the surrounding grout.

    The major part of grout comprises of water and cement, with a water-to-cement ratio ofabout 0.5, together with some water-reducing admixtures, expansion agent and

    pozzolans. The properties of grout are discussed in Section 1.6, Concrete (Part-II).

    The following figure shows a grouting equipment, where the ingredients are mixed and

    the grout is pumped.

    Figure 1-4.18 Grouting equipment

    (Reference: Williams Form Engineering Corp.)

    1.4.6 Manufacturing of Post-tensioned Bridge Girders

    The following photographs show some steps in the manufacturing of a post-tensioned I-

    girder for a bridge (Courtesy: Larsen & Toubro). The first photo shows the fabricated

    steel reinforcement with the ducts for the tendons placed inside. Note the parabolic

    profiles of the duct for the simply supported girder. After the concrete is cast and cured

    to gain sufficient strength, the tendons are passed through the ducts, as shown in the

    second photo. The tendons are anchored at one end and stretched at the other end by

    a hydraulic jack. This can be observed from the third photo.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    49/489

    (a) Fabrication of reinforcement

    (b) Placement of tendons

  • 7/27/2019 prestressed concrete IIT-M.pdf

    50/489

    (c) Stretching and anchoring of tendons

    Figure 1-4.19 Manufacturing of a post-tensioned bridge I-girder

    The following photos show the construction of post-tensioned box girders for a bridge

    (Courtesy: Cochin Port Trust). The first photo shows the fabricated steel reinforcement

    with the ducts for the tendons placed inside. The top flange will be constructed later.

    The second photo shows the formwork in the pre-casting yard. The formwork for the

    inner sides of the webs and the flanges is yet to be placed. In the third photo a girder is

    being post-tensioned after adequate curing. The next photo shows a crane on a barge

    that transports a girder to the bridge site. The completed bridge can be seen in the last

    photo.

    (a) Reinforcement cage for box girder

  • 7/27/2019 prestressed concrete IIT-M.pdf

    51/489

    (b) Formwork for box girder

    (c) Post-tensioning of box girder

  • 7/27/2019 prestressed concrete IIT-M.pdf

    52/489

    (d) Transporting of box girder

    (e) Completed bridge

    Figure 1-4.20 Manufacturing of post-tensioned bridge box girders

  • 7/27/2019 prestressed concrete IIT-M.pdf

    53/489

    1.5 Concrete (Part I)

    This section covers the following topics.

    Constituents of Concrete

    Properties ofHardened Concrete (Part I)

    1.5.1 Const ituents of Concrete

    Introduction

    Concrete is a composite material composed of gravels or crushed stones (coarse

    aggregate), sand (fine aggregate) and hydrated cement (binder). It is expected that the

    student of this course is familiar with the basics of concrete technology. Only the

    information pertinent to prestressed concrete design is presented here.

    The following figure shows a petrographic section of concrete. Note the scattered

    coarse aggregates and the matrix surrounding them. The matrix consists of sand,

    hydrated cement and tiny voids.

    Figure 1-5.1 Petrographic section of hardened concrete

    (Reference: Portland Cement Association, Design and Control of Concrete Mixtures)

    Aggregate

    The coarse aggregate are granular materials obtained from rocks and crushed stones.

    They may be also obtained from synthetic material like slag, shale, fly ash and clay for

    use in light-weight concrete.

    http://constituents%20of%20concrete/http://hardened%20concrete/http://hardened%20concrete/http://constituents%20of%20concrete/
  • 7/27/2019 prestressed concrete IIT-M.pdf

    54/489

    The sand obtained from river beds or quarries is used as fine aggregate. The fine

    aggregate along with the hydrated cement paste fill the space between the coarse

    aggregate.

    The important properties of aggregate are as follows.

    1) Shape and texture2) Size gradation

    3) Moisture content

    4) Specific gravity

    5) Unit weight

    6) Durability and absence of deleterious materials.

    The requirements of aggregate is covered in Section 4.2 of IS:1343 - 1980.

    The nominal maximum coarse aggregate size is limited by the lowest of the following

    quantities.

    1) 1/4 times the minimum thickness of the member

    2) Spacing between the tendons/strands minus 5 mm

    3) 40 mm.

    The deleterious substances that should be limited in aggregate are clay lumps, wood,coal, chert, silt, rock dust (material finer than 75 microns), organic material, unsound

    and friable particles.

    Cement

    In present day concrete, cement is a mixture of lime stone and clay heated in a kiln to

    1400 - 1600C. The types of cement permitted by IS:1343 - 1980 (Clause 4.1) for

    prestressed applications are the following. The information is revised as per IS:456 -

    2000, Plain and Reinforced Concrete Code of Practice.

    1) Ordinary Portland cement confirming to IS:269 - 1989, Ordinary Portland Cement,

    33 Grade Specification.

    2) Portland slag cement confirming to IS:455 - 1989, Portland Slag Cement

    Specification, but with not more than 50% slag content.

    3) Rapid-hardening Portland cement confirming to IS:8041 - 1990, Rapid Hardening

    Portland Cement Specification.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    55/489

    WaterThe water should satisfy the requirements ofSection 5.4 ofIS:456 - 2000.

    Water used for mixing and curing shall be clean and free from injurious amounts of oils,

    acids, alkalis, salts, sugar, organic materials or other substances that may be

    deleterious to concrete and steel.

    Admixtures

    IS:1343 - 1980 allows to use admixtures that conform to IS:9103 - 1999, Concrete

    Admixtures Specification. The admixtures can be broadly divided into two types:

    chemical admixtures and mineral admixtures. The common chemical admixtures are as

    follows.

    1) Air-entraining admixtures

    2) Water reducing admixtures

    3) Set retarding admixtures

    4) Set accelerating admixtures

    5) Water reducing and set retarding admixtures

    6) Water reducing and set accelerating admixtures.

    The common mineral admixtures are as follows.

    1) Fly ash2) Ground granulated blast-furnace slag

    3) Silica fumes

    4) Rice husk ash

    5) Metakoline

    These are cementitious and pozzolanic materials.

    1.5.2 Propert ies of Hardened Concrete (Part I)

    The concrete in prestressed applications has to be of good quality. It requires the

    following attributes.

    1) High strength with low water-to-cement ratio

    2) Durability with low permeability, minimum cement content and proper mixing,

    compaction and curing

  • 7/27/2019 prestressed concrete IIT-M.pdf

    56/489

    3) Minimum shrinkage and creep by limiting the cement content.

    The following topics are discussed.

    1) Strength of concrete

    2) Stiffness of concrete

    3) Durability of concrete

    4) High performance concrete5) Allowable stresses in concrete.

    Strength of Concrete

    The following sections describe the properties with reference to IS:1343 - 1980. The

    strength of concrete is required to calculate the strength of the members. For

    prestressed concrete applications, high strength concrete is required for the following

    reasons.

    1) To sustain the high stresses at anchorage regions.

    2) To have higher resistance in compression, tension, shear and bond.

    3) To have higher stiffness for reduced deflection.

    4) To have reduced shrinkage cracks.

    Compressive Strength

    The compressive strength of concrete is given in terms of the characteristic

    compressive strength of 150 mm size cubes tested at 28 days (fck). The characteristic

    strength is defined as the strength of the concrete below which not more than 5% of thetest results are expected to fall. This concept assumes a normal distribution of the

    strengths of the samples of concrete.

    The following sketch shows an idealised distribution of the values of compressive

    strength for a sizeable number of test cubes. The horizontal axis represents the values

    of compressive strength. The vertical axis represents the number of test samples for a

    particular compressive strength. This is also termed as frequency. The average of the

    values of compressive strength (mean strength) is represented as fcm. The characteristic

    strength (fck) is the value in the x-axis below which 5% of the total area under the curve

    falls. The value offck is lower than fcm by 1.65, where is the standard deviation of the

    normal distribution.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    57/489

    fck fcm

    1.65

    Frequency

    28 day cube compressive strength

    5% area fck fcm

    1.65

    Frequency

    28 day cube compressive strength

    5% area

    Figure 1-5.2 Idealised normal distribution of concrete strength

    (Reference: Pillai, S. U., and Menon, D., Reinforced Concrete Design)

    The sampling and strength test of concrete are as per Section 15 of IS:1343 - 1980.The grades of concrete are explained in Table 1 of the Code.

    The minimum grades of concrete for prestressed applications are as follows.

    30 MPa for post-tensioned members

    40 MPa for pre-tensioned members.

    The maximum grade of concrete is 60 MPa.

    Since at the time of publication of IS:1343 in 1980, the properties of higher strength

    concrete were not adequately documented, a limit was imposed on the maximum

    strength. It is expected that higher strength concrete may be used after proper testing.

    The increase in strength with age as given in IS:1343 - 1980, is not observed in present

    day concrete that gains substantial strength in 28 days. Hence, the age factor given in

    Clause 5.2.1 should not be used. It has been removed from IS:456 - 2000.

    Tensile Strength

    The tensile strength of concrete can be expressed as follows.

    1) Flexural tensile strength: It is measured by testing beams under 2 point loading

    (also called 4 point loading including the reactions).

    2) Splitting tensile strength: It is measured by testing cylinders under diametral

    compression.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    58/489

    3) Direct tensile strength: It is measured by testing rectangular specimens under

    direct tension.

    In absence of test results, the Code recommends to use an estimate of the flexural

    tensile strength from the compressive strength by the following equation.

    cr ck f = f0.7 (1-5.1)

    Here,

    fcr = flexural tensile strength in N/mm2

    fck = characteristic compressive strength of cubes in N/mm2.

    Stiffness of Concrete

    The stiffness of concrete is required to estimate the deflection of members. The

    stiffness is given by the modulus of elasticity. For a non-linear stress (fc) versus strain

    (c) behaviour of concrete the modulus can be initial, tangential or secant modulus.

    IS:1343 - 1980 recommends a secant modulus at a stress level of about 0.3fck. The

    modulus is expressed in terms of the characteristic compressive strength and not the

    design compressive strength. The following figure shows the secant modulus in the

    compressive stress-strain curve for concrete.

    c

    fc

    fck

    Ec

    fc

    c

    fc

    fck

    Ecc

    fc

    fck

    Ec

    fcfc

    Figure 1-5.3 a) Concrete cube under compression, b) Compressive stress-strain

    curve for concrete

    The modulus of elasticity for short term loading (neglecting the effect of creep) is given

    by the following equation.

    c cE = f5000 k (1-5.2)

    Here,

    Ec = short-term static modulus of elasticity in N/mm2

    fck = characteristic compressive strength of cubes in N/mm2.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    59/489

  • 7/27/2019 prestressed concrete IIT-M.pdf

    60/489

    Table 10 provides the values for the above quantities for concrete exposed to sulphate

    attack.

    To limit the creep and shrinkage, IS:1343 - 1980 specifies a maximum cement content

    of 530 kg per m3 of concrete (Clause 8.1.1).

    High Performance Concrete

    With the advancement of concrete technology, high performance concrete is getting

    popular in prestressed applications. The attributes of high performance concrete are as

    follows.

    1) High strength

    2) Minimum shrinkage and creep

    3) High durability

    4) Easy to cast

    5) Cost effective.

    Traditionally high performance concrete implied high strength concrete with higher

    cement content and low water-to-cement ratio. But higher cement content leads to

    autogenous and plastic shrinkage cracking and thermal cracking. At present durability

    is also given importance along with strength.

    Some special types of high performance concrete are as follows.1) High strength concrete

    2) High workability concrete

    3) Self-compacting concrete

    4) Reactive powder concrete

    5) High volume fly ash concrete

    6) Fibre reinforced concrete

    In a post-tensioned member, the concrete next to the anchorage blocks (referred to as

    end block) is subjected to high stress concentration. The type of concrete at the end

    blocks may be different from that at the rest of the member. Fibre reinforced concrete is

    used to check the cracking due to the bursting forces.

    The following photo shows that the end blocks were cast separately with high strength

    concrete.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    61/489

    Figure 1-5.4 End-blocks in a bridge deck

    (Courtesy: Cochin Port Trust, Kerala)

    Al lowable Stresses in Concrete

    The allowable stresses are used to analyse and design members under service loads.

    IS:1343 - 1980 specifies the maximum allowable compressive stresses for different

    grades of concrete under different loading conditions in Section 22.8.

    Allowable Compressive Stresses under Flexure

    The following sketch shows the variation of allowable compressive stresses for different

    grades of concrete at transfer. The cube strength at transfer is denoted as fci.

    M30 M60 M40 M60

    0.51fci0.44fci

    0.54fci0.37fci

    Post-tension Pre-tension

    M30 M60 M40 M60

    0.51fci0.44fci

    0.54fci0.37fci

    Post-tension Pre-tension

    Figure 1-5.5 Variation of allowable compressive stresses at transfer

    The following sketch shows the variation of allowable compressive stresses for different

    grades of concrete at service loads.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    62/489

    0.34fck

    0.41fck

    0.27fck

    0.35fck

    M 30 M 60

    Zone I

    Zone II

    Figure 1-5.6 Variation of allowable compressive stresses at service loads

    Here, Zone I represents the locations where the compressive stresses are not likely to

    increase. Zone II represents the locations where the compressive stresses are likely to

    increase, such as due to transient loads from vehicles in bridge decks.

    Allowable Compressive Stresses under Direct Compression

    For direct compression, except in the parts immediately behind the anchorage, the

    maximum stress is equal to 0.8 times the maximum compressive stress under flexure.

    Allowable Tensile Stresses under Flexure

    The prestressed members are classified into three different types based on the

    allowable tensile stresses. The amount of prestressing varies in the three types. The

    allowable tensile stresses for the three types of members are specified in Section 22.7.

    The values are reproduced below.

    Table 1-5.2 Allowable tensile stresses (IS:1343 - 1980)

    Type 1 No tensile stress

    Type 23 N/mm2.

    This value can be increased to 4.5 N/mm2 for temporary loads.

    Type 3 Table 8 provides hypothetical values of allowable tensile stresses.

    The purpose of providing hypothetical values is to use the elastic analysis method for

    Type 3 members even after cracking of concrete.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    63/489

    1.6 Concrete (Part II)

    This section covers the following topics.

    Properties ofHardened Concrete (Part II)

    Properties of Grout

    Codal Provisions of Concrete

    1.6.1 Propert ies of Hardened Concrete (Part II)

    The properties that are discussed are as follows.

    1) Stress-strain curves for concrete

    2) Creep of concrete

    3) Shrinkage of concrete

    Stress-strain Curves for Concrete

    Curve under uniaxial compression

    The stress versus strain behaviour of concrete under uniaxial compression is initially

    linear (stress is proportional to strain) and elastic (strain is recovered at unloading). With

    the generation of micro-cracks, the behaviour becomes nonlinear and inelastic. After the

    specimen reaches the peak stress, the resisting stress decreases with increase in strain.

    IS:1343 - 1980 recommends a parabolic characteristic stress-strain curve, proposed by

    Hognestad, for concrete under uniaxial compression (Figure 3 in the Code).

    c0 cu

    fc

    fck

    fc

    c0 cu

    fc

    fck

    c0 cu

    fc

    fck

    fcfc

    Figure 1-6.1 a) Concrete cube under compression, b) Design stress-strain curve for

    concrete under compression due to flexure

    http://hardened%20concrete/http://properties%20of%20grout/http://properties%20of%20grout/http://hardened%20concrete/
  • 7/27/2019 prestressed concrete IIT-M.pdf

    64/489

    The equation for the design curve under compression due to flexure is as follows.

    Forc0

    c cck ck

    f = f -

    2

    0 0

    2 (1-6.1)

    Forc< ccu

    fc= fck (1-6.2)Here,

    fc = compressive stress

    fck = characteristic compressive strength of cubes

    c = compressive strain

    0 = strain corresponding to fck= 0.002

    cu = ultimate compressive strain = 0.0035

    For concrete under compression due to axial load, the ultimate strain is restricted to

    0.002. From the characteristic curve, the design curve is defined by multiplying the

    stress with a size factor of 0.67 and dividing the stress by a material safety factor of m =

    1.5. The design curve is used in the calculation of ultimate strength. The following

    sketch shows the two curves.

    0 cu c

    fc

    fck

    0.447 fck

    Characteristic curve

    Design curve

    0 cu c

    fc

    fck

    0.447 fck

    Characteristic curve

    Design curve

    Figure 1-6.2 Stress-strain curves for concrete under compression due to flexure

    In the calculation of deflection at service loads, a linear stress-strain curve is assumed

    up to the allowable stress. This curve is given by the following equation.

    fc= Ecc (1-6.3)

    Note that, the size factor and the material safety factor are not used in the elastic

    modulus Ec.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    65/489

    For high strength concrete (say M100 grade of concrete and above) under uniaxial

    compression, the ascending and descending branches are steep.

    0 c

    fcfck

    Es

    Eci

    0 c

    fcfck

    Es

    Eci

    Figure 1-6.3 Stress-strain curves for high strength concrete under compression

    The equation proposed by Thorenfeldt, Tomaxzewicz and Jensen is appropriate for high

    strength concrete.

    c

    c ck nk

    c

    n

    f = f

    n - +

    0

    0

    1

    (1-6.4)

    The variables in the previous equation are as follows.

    fc = compressive stress

    fck = characteristic compressive strength of cubes in N/mm2

    c = compressive strain

    0 = strain corresponding to fck

    k = 1 forc0

    = 0.67 + (fck / 77.5) forc>0. The value ofkshould be greater than 1.

    n = Eci / (Eci Es)

    Eci = initial modulus

    Es = secant modulus at fck= fck /0.

    The previous equation is applicable for both the ascending and descending branches of

    the curve. Also, the parameter k models the slope of the descending branch, which

    increases with the characteristic strength fck. To be precise, the value of 0 can be

    considered to vary with the compressive strength of concrete.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    66/489

    Curve under uniaxial tension

    The stress versus strain behaviour of concrete under uniaxial tension is linear elastic

    initially. Close to cracking nonlinear behaviour is observed.

    fc

    c

    fcfc

    c

    fc

    c

    fcfc

    (a) (b)

    Figure 1-6.4 a) Concrete panel under tension, b) Stress-strain curve for concrete

    under tension

    In calculation of deflections of flexural members at service loads, the nonlinearity is

    neglected and a linear elastic behaviourfc= Ecc is assumed. In the analysis of ultimate

    strength, the tensile strength of concrete is usually neglected.

    Creep of Concrete

    Creep of concrete is defined as the increase in deformation with time under constant

    load. Due to the creep of concrete, the prestress in the tendon is reduced with time.

    Hence, the study of creep is important in prestressed concrete to calculate the loss in

    prestress.

    The creep occurs due to two causes.

    1. Rearrangement of hydrated cement paste (especially the layered products)

    2. Expulsion of water from voids under load

    If a concrete specimen is subjected to slow compressive loading, the stress versus

    strain curve is elongated along the strain axis as compared to the curve for fast loading.

    This can be explained in terms of creep. If the load is sustained at a level, the increase

    in strain due to creep will lead to a shift from the fast loading curve to the slow loading

    curve (Figure 1-6.5).

  • 7/27/2019 prestressed concrete IIT-M.pdf

    67/489

    c

    fcFast loading

    Slow loading

    Effect of creep

    c

    fcFast loading

    Slow loading

    Effect of creep

    Figure 1-6.5 Stress-strain curves for concrete under compression

    Creep is quantified in terms of the strain that occurs in addition to the elastic strain due

    to the applied loads. If the applied loads are close to the service loads, the creep strain

    increases at a decreasing rate with time. The ultimate creep strain is found to be

    proportional to the elastic strain. The ratio of the ultimate creep strain to the elastic

    strain is called the creep coefficient.

    For stress in concrete less than about one-third of the characteristic strength, the

    ultimate creep strain is given as follows.

    cr,ult el = (1-6.5)

    The variation of strain with time, under constant axial compressive stress, is

    represented in the following figure.

    strain

    Time (linear scale)

    cr, ult= ultimate creep strain

    el= elastic strainstrain

    Time (linear scale)

    cr, ult= ultimate creep strain

    el= elastic strain

    Figure 1-6.6 Variation of strain with time for concrete under compression

    If the load is removed, the elastic strain is immediately recovered. However the

    recovered elastic strain is less than the initial elastic strain, as the elastic modulus

    increases with age.

    There is reduction of strain due to creep recovery which is less than the creep strain.

    There is some residual strain which cannot be recovered (Figure 1-6.7).

  • 7/27/2019 prestressed concrete IIT-M.pdf

    68/489

    strain

    Time (linear scale)

    Residual strain

    Creep recovery

    Elastic recovery

    Unloadingstrain

    Time (linear scale)

    Residual strain

    Creep recovery

    Elastic recovery

    Unloading

    Figure 1-6.7 Variation of strain with time showing the effect of unloading

    The creep strain depends on several factors. It increases with the increase in the

    following variables.

    1) Cement content (cement paste to aggregate ratio)

    2) Water-to-cement ratio

    3) Air entrainment4) Ambient temperature.

    The creep strain decreases with the increase in the following variables.

    1) Age of concrete at the time of loading.

    2) Relative humidity

    3) Volume to surface area ratio.

    The creep strain also depends on the type of aggregate.

    IS:1343 - 1980 gives guidelines to estimate the ultimate creep strain in Section 5.2.5. It

    is a simplified estimate where only one factor has been considered. The factor is age of

    loading of the prestressed concrete structure. The creep coefficient is provided for

    three values of age of loading.

    Table 1-6.1 Creep coefficient for three values of age of loading

    Age of Loading Creep Coefficient

    7 days 2.2

    28 days 1.6

    1 year 1.1

  • 7/27/2019 prestressed concrete IIT-M.pdf

    69/489

    It can be observed that if the structure is loaded at 7 days, the creep coefficient is 2.2.

    This means that the creep strain is 2.2 times the elastic strain. Thus, the total strain is

    more than thrice the elastic strain. Hence, it is necessary to study the effect of creep in

    the loss of prestress and deflection of prestressed flexural members. Even if the

    structure is loaded at 28 days, the creep strain is substantial. This implies higher loss of

    prestress and higher deflection.

    Curing the concrete adequately and delaying the application of load provide long term

    benefits with regards to durability, loss of prestress and deflection.

    In special situations detailed calculations may be necessary to monitor creep strain with

    time. Specialised literature or international codes can provide guidelines for such

    calculations.

    Shrinkage of Concrete

    Shrinkage of concrete is defined as the contraction due to loss of moisture. The study of

    shrinkage is also important in prestressed concrete to calculate the loss in prestress.

    The shrinkage occurs due to two causes.

    1. Loss of water from voids

    2. Reduction of volume during carbonation

    The following figure shows the variation of shrinkage strain with time. Here, t0 is the time

    at commencement of drying. The shrinkage strain increases at a decreasing rate with

    time. The ultimate shrinkage strain (sh) is estimated to calculate the loss in prestress.

    Shrinkage

    strain

    t0 Time (linear scale)

    sh

    Shrinkage

    strain

    t0 Time (linear scale)

    sh

    Figure 1-6.8 Variation of shrinkage strain with time

  • 7/27/2019 prestressed concrete IIT-M.pdf

    70/489

    Like creep, shrinkage also depends on several factors. The shrinkage strain increases

    with the increase in the following variables.

    1) Ambient temperature

    2) Temperature gradient in the members

    3) Water-to-cement ratio

    4) Cement content.

    The shrinkage strain decreases with the increase in the following variables.

    1) Age of concrete at commencement of drying

    2) Relative humidity

    3) Volume to surface area ratio.

    The shrinkage strain also depends on the type of aggregate.

    IS:1343 - 1980 gives guidelines to estimate the shrinkage strain in Section 5.2.4. It is a

    simplified estimate of the ultimate shrinkage strain (sh).

    For pre-tension

    sh = 0.0003 (1-6.6)

    For post-tension

    (1-6.7)

    ( )sh =

    log t +10

    0.0002

    2

    Here, tis the age at transfer in days. Note that for post-tension, tis the age at transfer

    in days which approximates the curing time.

    It can be observed that with increasing age at transfer, the shrinkage strain reduces. As

    mentioned before, curing the concrete adequately and delaying the application of load

    provide long term benefits with regards to durability and loss of prestress.

    In special situations detailed calculations may be necessary to monitor shrinkage strain

    with time. Specialised literature or international codes can provide guidelines for such

    calculations.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    71/489

    1.6.2 Properties of Grout

    Grout is a mixture of water, cement and optional materials like sand, water-reducing

    admixtures, expansion agent and pozzolans. The water-to-cement ratio is around 0.5.

    Fine sand is used to avoid segregation.

    The desirable properties of grout are as follows.

    1) Fluidity

    2) Minimum bleeding and segregation

    3) Low shrinkage

    4) Adequate strength after hardening

    5) No detrimental compounds

    6) Durable.

    IS:1343 - 1980 specifies the properties of grout in Sections 12.3.1 and Section 12.3.2.

    The following specifications are important.

    1) The sand should pass 150 m Indian Standard sieve.

    2) The compressive strength of 100 mm cubes of the grout shall not be less than 17

    N/mm2 at 7 days.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    72/489

    1.6.5 Codal Provisions of Concrete

    The following topics are covered in IS:1343 - 1980 under the respective sections. These

    provisions are not duplicated here.

    Table 1-6.2 Topics and sections

    Workability of concrete Section 6

    Concrete mix proportioning Section 8

    Production and control of concrete Section 9

    Formwork Section 10

    Transporting, placing, compacting Section 13

    Concrete under special conditions Section 14

    Sampling and strength test of concrete Section 15

    Acceptance criteria Section 16

    Inspection and testing of structures Section 17

  • 7/27/2019 prestressed concrete IIT-M.pdf

    73/489

    2.1 Losses in Prestress (Part I)

    This section covers the following topics.

    Introduction

    Elastic Shortening

    The relevant notations are explained first.

    Notations

    Geometric Properties

    The commonly used geometric properties of a prestressed member are defined as

    follows.

    Ac = Area of concrete section

    = Net cross-sectional area of concrete excluding the area of

    prestressing steel.Ap = Area of prestressing steel

    = Total cross-sectional area of the tendons.

    A = Area of prestressed member

    = Gross cross-sectional area of prestressed member.

    =Ac+Ap

    At = Transformed area of prestressed member

    = Area of the member when steel is substituted by an equivalent

    area of concrete.

    =Ac+ mAp

    =A + (m 1)Ap

    Here,

    m = the modular ratio = Ep/Ec

    Ec = short-term elastic modulus of concrete

    Ep = elastic modulus of steel.

    The following figure shows the commonly used areas of the prestressed members.

    http://elastic%20shortening/http://elastic%20shortening/
  • 7/27/2019 prestressed concrete IIT-M.pdf

    74/489

    = +

    A Ac Ap At

    = +

    A Ac Ap At

    Figure 2-1.1 Areas for prestressed members

    CGC = Centroid of concrete

    = Centroid of the gross section. The CGC may lie outside the

    concrete (Figure 2-1.2).

    CGS = Centroid of prestressing steel

    = Centroid of the tendons. The CGS may lie outside the tendons or

    the concrete (Figure 2-1.2).

    I = Moment of inertia of prestressed member

    = Second moment of area of the gross section about the CGC.

    It = Moment of inertia of transformed section

    = Second moment of area of the transformed section about the

    centroid of the transformed section.

    e = Eccentricity of CGS with respect to CGC

    = Vertical distance between CGC and CGS. If CGS lies below CGC,

    e will be considered positive and vice versa (Figure 2-1.2).

    CGSCGCe

    CGS

    CGCe

    CGSCGCeCGSCGCCGSCGCe

    CGS

    CGCe

    CGS

    CGC

    CGS

    CGC

    CGS

    CGCe

    Figure 2-1.2 CGC, CGS and eccentricity of typical prestressed members

    Load Variables

    Pi = Initial prestressing force

    = The force which is applied to the tendons by the jack.

  • 7/27/2019 prestressed concrete IIT-M.pdf

    75/489

    P0 = Prestressing force after immediate losses

    = The reduced value of prestressing force after elastic shortening,

    anchorage slip and loss due to friction.

    Pe = Effective prestressing force after time-dependent losses

    = The final value of prestressing force after the occurrence of creep,

    shrinkage and relaxation.

    2.1.1 Introduction

    In prestressed concrete applications, the most important variable is the prestressing

    force. In the early days, it was observed that the prestressing force does not stay

    constant, but reduces with time. Even during prestressing of the tendons and the

    transfer of prestress to the concrete member, there is a drop of the prestressing force

    from the recorded value in the jack gauge. The various reductions of the prestressing

    force are termed as the losses in prestress.

    The losses are broadly classified into two groups, immediate and time-dependent. The

    immediate losses occur during prestressing of the tendons and the transfer of prestress

    to the concrete member. The time-dependent losses occur during the service life of the

    prestressed member. The losses due to elastic shortening of the member, friction at the

    tendon-concrete interface and slip of the anchorage are the immediate losses. The

    losses due to the shrinkage and creep of the concrete and relaxation of the steel are the

    time-dependent losses. The causes of the various losses in prestress are shown in the

    following chart.

    Losses

    Immediate Time dependent

    Elasticshortening

    Friction Anchorageslip

    Creep Shrinkage Relaxation

    Figure 2-1.3 Causes of the various losses in prestress

  • 7/27/2019 prestressed concrete IIT-M.pdf

    76/489

    2.1.2 Elastic Shortening

    Pre-tensioned Members

    When the tendons are cut and the prestressing force is transferred to the member, the

    concrete undergoes immediate shortening due to the prestress. The tendon also

    shortens by the same amount, which leads to the loss of prestress.

    Post-tensioned Members

    If there is only one tendon, there is no loss because the applied prestress is recorded

    after the elastic shortening of the member. For more than one tendon, if the tendons

    are stretched sequentially, there is loss in a tendon during subsequent stretching of the

    other tendons.

    The elastic shortening loss is quantified by the drop in prestress (fp) in a tendon due to

    the change in strain in the tendon (p). It is assumed that the change in strain in the

    tendon is equal to the strain in concrete (c) at the level of the tendon due to the

    prestressing force. This assumption is called strain compatibility between concrete

    and steel. The strain in concrete at the level of the tendon is calculated from the stress

    in concrete (fc) at the same level due to the prestressing force. A linear elastic

    relationship is used to calculate the strain from the stress.

    The quantification of the losses is explained below.

    p p p

    p c

    cp

    c

    p c

    f = E

    = E

    f= E

    E

    f = mf (2-1.1)

    For simplicity, the loss in all the tendons can be calculated based on the stress inconcrete at the level of CGS. This simplification cannot be used when tendons are

    stretched sequentially in a post-tensioned member. The calculation is illustrated for the

    following types of members separately.

    Pre-tensioned Axial Members

    Pre-tensioned Bending Members

    Post-tensioned Axial Members

  • 7/27/2019 prestressed concrete IIT-M.pdf

    77/489

    Post-tensioned Bending Members

    Pre-tensioned Axial Members

    The following figure shows the changes in length and the prestressing force due to

    elastic shortening of a pre-tensioned axial member.

    Original length of member at transfer of prestress

    Length after elastic shortening

    Pi

    P0

    Original length of member at transfer of prestress

    Length after elastic shortening

    Pi

    P0

    Figure 2-1.4 Elastic shortening of a pre-tensioned axial member

    The loss can be calculated as per Eqn. (2-1.1) by expressing the stress in concrete in

    terms of the prestressing force and area of the section as follows.

    (2-1.2)

    p c

    c

    i ip

    t

    f = mf

    P= m

    AP P

    f = m mA A

    0

    Note that the stress in concrete due to the prestressing force after immediate losses

    (P0/Ac) can be equated to the stress in the transformed section due to the initial

    prestress (Pi /At). This is derived below. Further, the transformed area At of the

    prestressed member can be approximated to the gross areaA.

    The following figure shows that the strain in concrete due to elastic shortening ( c) is the

    difference between the initial strain in steel (pi) and the residual strain in steel (p0).

  • 7/27/2019 prestressed concrete IIT-M.pdf

    78/489

    Pi

    P0

    Length of tendon before stretchingpi

    p0

    c

    Pi

    P0

    Length of tendon before stretchingpi

    p0

    c

    Figure 2-1.5 Strain variables in elastic shortening

    The following equation relates the strain variables.

    c=pi- p0 (2-1.3)

    The strains can be expressed in terms of the prestressing forces as follows.

    c

    c c

    P =

    A E0

    (2-1.4)

    ipi

    p p

    P =

    A E

    (2-1.5)

    p

    p p

    P =

    A E0

    0

    (2-1.6)

    Substituting the expressions of the strains in Eqn. (2-1.3)

    i

    c c p p p p

    i

    c c p p p p

    i

    c p p

    i

    c p c

    P PP= -

    A E A E A E

    P, P + =

    A E A E A E

    Pm 1P + =

    A A A

    P P=

    A mA + A

    0 0

    0

    0

    0

    1 1or

    or,

    or,

    0or i

    c t

    P P=

    A A

    (2-1.7)

    Thus, the stress in concrete due to the prestressing force after immediate losses (P0/Ac)

    can be equated to the stress in the transformed section due to the initial prestress (Pi

    /At).

  • 7/27/2019 prestressed concrete IIT-M.pdf

    79/489

    The following problem illustrates the calculation of loss due to elastic shortening in an

    idealised pre-tensioned railway sleeper.

    Example 2-1.1

    A prest ressed concrete sleeper produced by pre-tension ing method has a

    rectangular cross-section of 300mm 250 mm (b h). It is prestressed with 9

    numbers of straight 7mm diameter wires at 0.8 times the ultimate strength of 1570

    N/mm2. Estimate the percentage loss of stress due to elastic shor tening of

    concrete. Considerm = 6.

    250

    40

    300

    40

    Solution

    a) Approximate solution considering gross section

    The sectional properties are calculated as follows.

    Area of a single wire, Aw = /4 72

    = 38.48 mm2

    Area of total prestressing steel, Ap = 9 38.48

    = 346.32 mm2

    Area of concrete section, A = 300 250

    = 75 103 mm2

    Moment of inertia of section, I = 300 2503/12

    = 3.91 108 mm4

    Distance of centroid of steel area (CGS) from the soffit,

  • 7/27/2019 prestressed concrete IIT-M.pdf

    80/489

    ( )438.48 250- 40 +538.4840y =

    938.48

    =115.5 mm

    Prestressing force, Pi = 0.8 1570 346.32 N

    = 435 kN

    Eccentricity of prestressing force,

    e = (250/2) 115.5

    = 9.5 mm

    The stress diagrams due to Piare shown.

    Since the wires are distributed above and below the CGC, the losses are calculated for

    the top and bottom wires separately.

    Stress at level of top wires (y= yt= 125 40)

    115.5

    e

    =+

    iP-A

    i iP P .e- yA I

    iP .e yI

    ( )

    ( )3 3

    3 8

    2

    435 10 435 10 9.5= - + 125 - 40

    7510 3.9110

    = -5.8+0.9

    = -4.9 N/mm

    i i

    c tt

    P P .e

    f = - + y A I

  • 7/27/2019 prestressed concrete IIT-M.pdf

    81/489

    Stress at level of bottom wires (y= yb = 125 40),

    ( )

    ( )3 3

    3 8

    2

    43510 43510 9.5= - - 125 - 40

    7510 3.9110

    = -5.8- 0.9

    = -6.7 N/mm

    i ic bb

    P P .ef = - - y

    A I

    Loss of prestress in top wires = mfcAp

    (in terms of force) = 6 4.9 (4 38.48)

    = 4525.25 N

    Loss of prestress in bottom wires = 6 6.7 (5 38.48)

    = 7734.48 N

    Total loss of prestress = 4525 + 7735

    = 12259.73 N

    12.3 kN

    Percentage loss = (12.3 / 435) 100%

    = 2.83%

    b) Accurate solution considering transformed section.

    Transformed area of top steel,

    A1 = (6 1) 4 38.48

    = 769.6 mm2

    Transformed area of bottom steel,

    A2 = (6 1) 5 38.48

    = 962.0 mm2

    Total area of transformed section,

    AT = A + A1 +A2

    = 75000.0 + 769.6 + 962.0

    = 76731.6 mm2

  • 7/27/2019 prestressed concrete IIT-M.pdf

    82/489

    Centroid of the section (CGC)

    A + A + A y =

    A1 2125 (250 - 40) 40

    = 124.8 mm from soffit of beam

    Moment of inertia of transformed section,IT = Ig+A(0.2)

    2 +A1(210 124.8)2 +A2(124.8 40)

    2

    = 4.02 108mm4

    Eccentricity of prestressing force,

    e = 124.8 115.5

    = 9.3 mm

    Stress at the level of bottom wires,3 3

    3 8

    2

    43510 (43510 9.3)84.8= - -

    76.7310 4.0210

    = -5.67 - 0.85

    = -6.52 N/mm

    c b(f )

    Stress at the level of top wires,

    3 3

    3 8

    2

    43510 (43510 9.3)85.2= - +

    76.7310 4.0210= -5.67+0.86

    = -4.81 N/mm

    c t(f )

    Loss of prestress in top wires = 6 4.81 (4 38.48)

    = 4442 N

    Loss of prestress in bottom wires = 6 6.52 (5 38.48)

    = 7527 N

    Total loss = 4442 + 7527

    = 11969 N

    12 kN

    Percentage loss = (12 / 435) 100%

    = 2.75 %

  • 7/27/2019 prestressed concrete IIT-M.pdf

    83/489

    It can be observed that the accurate and approximate solutions are close. Hence, the

    simpler calculations based onA and Iis acceptable.

    Pre-tensioned Bending Members

    The following figure shows the changes in length and the prestressing force due to

    elastic shortening of a pre-tensioned bending member.Pi

    wsw (self-weight)

    Pi

    wsw (self-weight)

    Figure 2-1.6 Elastic shortening of a pre-tensioned bending member

    Due to the effect of self-weight, the stress in concrete varies along length (Figure 2-1.6).

    The loss can be calculated by Eqn. (2-1.1) with a suitable evaluation of the stress in

    concrete. To have a conservative estimate of the loss, the maximum stress at the level

    of CGS at the mid-span is considered.

    (2-1.8)swi ic

    M eP Pe.ef = - - +

    A I I

    Here, Msw is the moment at mid-span due to self-weight. Precise result usingAtand It in

    place of A and I, respectively, is not computationally warranted. In the above

    expression, the eccentricity of the CGS (e) was assumed to be constant.

    For a large member, the calculation of the loss can be refined by evaluating the strain in

    concrete at the level of the CGS accurately from the definition of strain. This is

    demonstrated later for post-tensioned bending members.

    Post-tensioned Axial Members

    For more than one tendon, if the tendons are stretched sequentially, there is loss in a

    tendon during subsequent stretching of the other tendons. The loss in each tendon can

  • 7/27/2019 prestressed concrete IIT-M.pdf

    84/489

    be calculated in progressive sequence. Else, an approximation can be used to

    calculate the losses.

    The loss in the first tendon is evaluated precisely and half of that value is used as an

    average loss for all the tendons.

    (2-1.9)

    p p

    c

    ni,j

    j=

    f = f

    mf

    P= m

    A

    1

    1

    2

    1

    21

    =2

    1

    2

    Here,

    Pi,j = initial prestressing force in tendonj

    n = number of tendons

    The eccentricity of individual tendon is neglected.

    Post-tensioned Bending Members

    The calculation of loss for tendons