presentation on policy issues and 12th plan proposals by js, mnre

Upload: jhothi-rajadurai

Post on 03-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    1/27

    Wind Power Programme in

    India

    Ministry of New & Renewable Energy

    1st August 2012, New Delhi

    1

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    2/27

    Renewable Power Sector in INDIA

    70%4%

    13%

    13%

    Share of Installed Renewable CapacityShare of Installed Renewable CapacityShare of Installed Renewable CapacityShare of Installed Renewable Capacity

    Wind

    SolarHydro

    Biomass

    Total installed Capacity: 25,410 MW

    2

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    3/27

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    4/27

    Wind PowerWind PowerWind PowerWind Power ---- ProgressProgressProgressProgress

    Potential (at 50 m) : 49,130 MW

    Achievement so far : 17,644 MWAchievement in 10th Plan : 5427 MW

    11th Plan Target : 9,000 MW

    Achievement during 11th

    Plan : 10,250 MWAchievement during 2011-12 : 3,196 MW

    Target for 12th Plan : 15,000 MW

    Target for 2012-13 : 3,000 MW

    4

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    5/27

    Wind PowerWind PowerWind PowerWind Power Progress (Contd.)Progress (Contd.)Progress (Contd.)Progress (Contd.)

    Wind Cumulative Installed Capacity (MW)5

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    6/27

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    7/27

    Wind Power Policies

    Income Tax Holiday under section 80 1A

    Excise Duty reliefConcessional Customs Import Duty on specifiedparts and components

    IREDA provides loan for commercial wind powerprojects

    Preferential Tariff by State regulators

    Accelerated Depreciation (80%) in first year(withdrawn w.e.f. 01.04.2012). Now anAccelerated Depreciation of 35% for the first year

    Generation Based Incentive

    7

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    8/27

    Generation Based IncentiveGeneration Based IncentiveGeneration Based IncentiveGeneration Based Incentive

    To Encourage higher generation/improve CUF

    Transition from investment based incentive to outcomebased incentive

    Scheme for 4,000 MW in 11th PlanGBI- 50 paise/kWh subject to max. Rs. 62 lakh /MW

    Duration : > 4 years, and < 10 years

    Total of 1900 MW projects installed

    Evaluation carried out by CRISIL

    To increase from 50 p to 81 p

    To continue during 12th Plan without any ceiling

    GBI proposed to be continued in 12th Plan

    8

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    9/27

    Recent DevelopmentsGuidelines for installation of prototype windturbines issued on 22.05.2012 - to facilitate

    indigenizationCondition of min. 200 W/m2 of wind powerdensity withdrawn in September, 2011

    Benefit of AD withdrawn w.e.f. 1stApril, 2012

    Import of parts/sub-parts of rotor blades nowcovered under Concessional Customs DutyBenefit (Notification No. 12/2012-Customs, 17.03.2012, of Min. of Finance, for2012-13).

    Proposal to continue GBI

    9

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    10/27

    Renewable Regulatory Fund (RRF)

    MechanismAs per Grid Code, complementary commercial

    mechanism was to be implemented from 01.01.2011

    On request of IWTMA, implementation of RRFMechanism postponed to 01.01.2012

    CERC directed MNRE to convene a meeting among

    stakeholders to resolve RRF related issues

    Task Force constituted to resolve the RRF issues

    formed under the chairmanship of Shri S.K.

    Soonee, CEO, POSOCO

    After several rounds of discussions among thestakeholders and experts, Task Force submitted its

    report recently which is under consideration

    10

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    11/27

    Wind Resource AssessmentWind Resource AssessmentWind Resource AssessmentWind Resource Assessment IssuesIssuesIssuesIssuesWind Resource ReWind Resource ReWind Resource ReWind Resource Re----assessment at 100 m heightassessment at 100 m heightassessment at 100 m heightassessment at 100 m height

    Wind resource re-assessment at 100 m height to be

    done at 75 sites across seven states.StateStateStateState NoNoNoNo.... ofofofof sitessitessitessites NOCsNOCsNOCsNOCs awaitedawaitedawaitedawaited

    Andhra Pradesh 10 -

    Karnataka 13 1

    Rajasthan 12 12

    Tamil Nadu 12 6

    Maharashtra 8 -

    Gujarat 12 11Madhya Pradesh 8 -

    States requested to send remaining NOCs

    11

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    12/27

    General Wind Resource AssessmentGeneral Wind Resource AssessmentGeneral Wind Resource AssessmentGeneral Wind Resource Assessment

    Programme of CProgramme of CProgramme of CProgramme of C----WETWETWETWET

    WRA for 54 sites sanctioned in 2010-11

    27 stations already commissioned (APall 15; Karnataka-10;Kerala-2)

    No response from Tamilnadu(3), Puducherry(2), Rajasthan(2)

    States are requested to commission the remaining sites

    10 sites finalised under WRA Programme 2010-11 for

    NE States. NOCs for all 10 sites received .

    Year 2011-12

    Odisha - 7 sites finalised, masts being set-up

    12

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    13/27

    Offshore Wind Power in India

    India has a coast line of about 7600 km.

    Preliminary assessment at 54 locations on the coast

    in the states of Tamil

    Nadu, Gujarat, Odisha, Maharashtra, AndhraPradesh, Karnataka, Kerala, West

    Bengal, Puducherry and Goa.

    13

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    14/27

    Offshore Wind Power in India

    A Steering Committee formed by the Ministry

    A subcommittee of the Steering committee assignedthe task of preparing draft policy for offshore wind

    power development.

    Preliminary assessment done by Scottish Agency

    shows a potential of around 1000 (Rameshwaram)

    and another 1000 MW (Kaniyakumari). This needs

    validation.

    14

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    15/27

    Re-powering of Old Sites

    About 4000 MW with unit size below 500 kW

    For better potential harnessing replace old and

    smaller generators by larger capacity & new

    generation wind turbines.

    Issues -

    Land ownership,

    land costing and decommissioning costStates reluctant to go for new PPA

    Realistic assessment of re-powering potential

    Creation of an appropriate policy framework forre-powering including- Revision of PPA for

    repowered projects, transmission of power to other

    states

    15

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    16/27

    C-WETS ROLE

    Established at Chennai as an autonomous institution of

    MNRE

    Objectives and Functions:Objectives and Functions:Objectives and Functions:Objectives and Functions:

    Technical focal point for wind power development

    Wind Resource AssessmentStandardization and certification

    Testing facilities as per international standards

    Type approval for wind turbinesInformation, Training & Commercial Services

    Research and Development

    16

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    17/27

    Organization of C-WET

    Divisions in C-WET:

    The Centre for Wind Energy Technology is working

    with the following structure

    Research & Development unit

    Wind Resource Assessment Unit

    Wind Turbine Testing Unit

    Standards and Certification Unit

    Information, Training & Commercial Service Unit

    Solar Radiation Resource Assessment

    17

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    18/27

    Issues in Wind Power Development

    Forest land clearance, mainly in Karnataka

    Creation of infrastructure for power evacuation and

    transmission facilitiesAvailability of land

    Potential land mostly acquired by manufacturers/

    developersStates to revise Tariff as per CERC guidelines

    Development of scheduling and forecasting system

    Industry and LDCs not yet fully prepared

    Withdrawal of Accelerated Depreciation

    Continuation of GBI Scheme

    18

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    19/27

    State Specific Issues ANDHRAPRADESH

    Target for 2012-13 is 500 MW.

    Inadequate Tariff at low PLF sites.

    For Captive Generation, Banking and Wheeling not

    permitted

    Entire cost of evacuation infrastructure has to be borne

    by the developer

    No time limit on private wind monitoring due to which a

    few developers are holding potential land for long time

    150 MW installed but not commissioned (as on31.05.2012)

    19

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    20/27

    State Specific Issues - GUJARAT

    Target for 2012-13 is 300 MW and for 12th Plan 2100

    MWTariff control period and wind policy ending in current

    year

    Identification and purchase of land for compensatoryafforestation is costly and long drawn process

    Direct purchase of private land is not allowed

    Construction of evacuation lines has to be done by

    developer without any assistance from GETCO/GUVNL

    20

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    21/27

    State Specific Issues - KARNATAKA

    Target for 2012-13 is 604 MW.

    Difficulty in getting forest land clearances on Western

    Ghats retarding the growth.Formulation of policy for private wind resource

    assessment in consultation with C-WET.

    Purchase of private land by developer not allowedProcedure for conversion to Non-Agricultural use-

    Alienation Procedure is time consuming

    Actual potential of the state not clear - required to

    have long-term plan for development of the sector.

    To take up repowering of the old sites in the state.

    21

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    22/27

    State Specific Issues - KERALA

    In potential sites, availability of land a major concern

    since most of them fall in tea or coffee estates.

    Grid network in estate areas very weak, investments

    required from state government to strengthen the

    connectivity

    State has to take pro-active approach to attractprivate investors

    Delays in power evacuation clearances from KSEB

    22

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    23/27

    State Specific Issues - MADHYA PRADESH

    Target for 2012-13 is 250 MW and for 2013-14 its 590

    MW.

    Proposal for licensing of tribal land at the value of landfor a fixed period.

    Has prepared detailed guidelines for implementation of

    projects giving time lines

    Time taken for various clearances long

    To carry out survey for re-powering of old sites

    Working on a model of repowering where the owner of

    the old machines may be given share as per the average

    generation of the old machines for the remaining period

    of the otherwise replaced project.

    23

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    24/27

    State Specific Issues - MAHARASHTRA

    Target for 12th Plan is 1800 MW

    Only slight addition to the potential when revised from

    50 m to 80 m mast height.Difficulty in getting forest clearance in the buffer area

    at Tiger Reserves.

    Different rates of Gram Panchayat Tax and Right of Way

    charges (for erection of poles) across the state which

    should be uniform.

    Sharing of Capital Subsidy from State Government,

    between MSEDCL and developer.Issue of Mining Royalty levied on Wind Power

    developers.

    24

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    25/27

    State Specific Issues - RAJASTHANWith most of the high wind potential areas utilized by

    developers, fresh studies are required to be carried at

    new sites on higher altitudeGrid needs to be strengthened in Jaisalmer region to

    support the development of more wind power projects

    A few instances of delay in payments have been

    reported, which needs to be improved

    25

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    26/27

    State Specific Issues - TAMIL NADUTarget for 2012-13 is 1000 MW and for 12th Plan it is

    5000 MW

    Target for Repowering is 80 MW

    During peak windy season, many wind power projects

    were disconnected from grid, which caused a lot of

    wastage of powerA few instances of delay in payments have been

    reported, which needs to be addressed.

    TNEB has constraints in providing power evacuation

    facilities to the new developers

    26

  • 7/28/2019 Presentation on Policy Issues and 12th Plan Proposals by JS, MNRE

    27/27

    Thank You!

    27