presentation india infrastructure

Upload: sameer-singh

Post on 14-Apr-2018

232 views

Category:

Documents


3 download

TRANSCRIPT

  • 7/27/2019 Presentation India Infrastructure

    1/16

    Private Sector Participation inSewerage : Experiences in India

    Presentation at

    Second Annual Conference on Sewage Treatment

    Plants: Opportunities, Issues, Projects,

    Technologies,October, 17-18,2013

    R.V. SINGHVice President & Head - Engineering

    JITF WATER INFRASTRUCTURE LIMITED

  • 7/27/2019 Presentation India Infrastructure

    2/16

    STRUCTURE OF PRESENTATION

    Experience Of The Private Sector In Sewerage Management

    Risks And Challenges Faced By Private Players

    Expectations

    Way Forward

  • 7/27/2019 Presentation India Infrastructure

    3/16

    EXPERIENCE OF THE PRIVATE

    SECTOR IN SEWERAGEMANAGEMENT

  • 7/27/2019 Presentation India Infrastructure

    4/16

    SEWERAGE MANAGEMENT

    It consists of :

    Sewer Network

    Sewage Treatment Plant With Or Without Reuse & Sludge Management

    O &M

    PPP in complete Value chain of Sewerage Management, in India, is yet to happen.

  • 7/27/2019 Presentation India Infrastructure

    5/16

    PROCUREMENT STRUCTURE OF A

    SEWERAGE PROJECT

    There are mainly three elements in sewerage management:

    SEWERAGE NETWORKING: Private sector is involved in construction as contractor.

    contracts are awarded based on competitive bidding system and are of EPC

    Turnkey or Item Rate type. O&M responsibility of network is of ULB beyond the

    DLP or extended O&M period as per contract; Generally 1-7 years (vary contract to

    contract)

    O&M: Service Contract are not so common for sewerage networks & generally

    undertaken by ULBs after end of DLP of the contractor.(Management contract in line with water supply, are yet to happen)

    STP: Private sector is involved as EPC Contractor & Developer both.

  • 7/27/2019 Presentation India Infrastructure

    6/16

    SEWERAGE NETWORK

    EXPERIENCE CONSIDERING EPC/TURKEY CONTRACT:

    Delay in approval of network design

    House connection is responsibility of ULB which is done poorly byuntrained workers resulting into leakage of sewage

    Generally S/W & RCC pipes are prescribed in bid documents which are

    prone to breakage due to unequal settlement of soil below sewer owing to

    ingress of rain water or any other reason

    Least state level commitment or support

  • 7/27/2019 Presentation India Infrastructure

    7/16

    STP/ETP/CETP

    EXPERIENCES CONSIDERING BOT PROJECT:

    Inadequate considerations for financial viability and lack of project development ability

    Delay in appointment in independent engineer

    Delay in approval due to prescriptive rather than participative technical specifications as well

    ambiguity in specification & interpretation of codes

    Sludge disposal mechanism not defined in contract

    Reuse policy or facility not in place in time; often not in concession agreement

    Industries discharge effluent in nearby natural course and least bother to take membership of CETP.

    Projected revenue not realized as plant is ready but either sewer conveyance network is not readyor users not ready to connect with network/number of users substantially lower than projected atprocurement stage

    Least involvement of employer during implementation

  • 7/27/2019 Presentation India Infrastructure

    8/16

    CASE STUDY

    CETP, SIDCUL INDUSTRIAL PARK, SITARGANJ ON

    BOT

  • 7/27/2019 Presentation India Infrastructure

    9/16

    CASE STUDY

    Capacity of CETP in CA 8MLD with RO (for Reuse)

    Plant capacity reduced to 4MLD during development stage & RO system procuredbut not installed owing to zero demand in local market of treated effluent forreuse

    Plant is running under capacity as only 1.3MLD influent is available

    Even BEP sale is not realizing

    Though Tariff revision based on deviation in Base Effluent Parameters (pH, COD,

    TDS) is permissible yet deviation measuring mechanism not in place. HenceTariff revision is always a conflict

    Private developer is making loss

  • 7/27/2019 Presentation India Infrastructure

    10/16

    RISKS AND CHALLENGES

    FACED BY PRIVATEPLAYERS

  • 7/27/2019 Presentation India Infrastructure

    11/16

    RISK & CHALLANGES

    o The typical design & preparation process is still largely technically-

    oriented with limited appreciation of the overall financial and

    commercial risk issues involved.

    o Often information distortions in the market have led to large variations

    in the bids/offers received during the procurement process.o The procurement process is highly prescriptive, rather than

    participative.

    o The emphasis is on conforming to public sector requirements which

    may not offer value for money and doesn't not encourage innovative

    solutions

    o While public sector dictating the terms, it is quite often not willing to

    shoulder commitment risk and apportionment of risk, in some cases,

    quite inefficient.

  • 7/27/2019 Presentation India Infrastructure

    12/16

    EXPECTATIONS

  • 7/27/2019 Presentation India Infrastructure

    13/16

    PRIVATE SECTOR EXPECTATIONS

    o Incorporation Of State Asset Management Company Such As TNUIFSL (Tamil Nadu

    Urban Infrastructure Financial Services Limited) to take the lead in preparing &

    structuring the project and finance package in conjunction with multi-stake holder

    committee to ensure sound and bankable project.

    o There must be an agreement among the parties/stake holders for sharing

    responsibilities to avoid confusion and delay in implementation stage of theproject.

    o Transparent Lines Of Communication With BOT Operator/ Management

    Contractor.

    o PAYMENT ASSURANCE TO THE PRIVATE SECTOR PARTICIPANTS: ULB to provide

    BOT Contractor a minimum level of revenue through a form of TAKE OR PAY

    arrangement; ULB to guarantee to supply minimum level of raw sewage/effluent

    to the plant and pay through a unit rate agreement at pre-determined annual fee.

    Through this arrangement, ULB/ the city assume the risk of paying the fee if the

    predetermined level sewage was not met. in turn, the private partner assumes all

    responsibilities and risks for financing, constructing and operating the

    STP/ETP/CETP for whole concession period.

  • 7/27/2019 Presentation India Infrastructure

    14/16

    OUTLOOK GOING FORWARD

  • 7/27/2019 Presentation India Infrastructure

    15/16

    PROJECTS; ENSURE FINANCIAL VIABILITY

    AND DEVELOPERSS REPAYMENTS THROUGH

    TAKE OR PAY CLAUSE IN CA. FURTHER, AS

    LONG -TERM SUSTAINBILITY OF THEPROJECT IS THE ABILITY OF THE ULB TO

    ASSUME RESPONSIBILTY FOR OPERATION &

    MAINTENANCE OF THE PROJECT AFTER THE

    END OF CONCESSION PERIOD ..FOR THIS ULB TO HAVE LONG-TERM PLAN THAT

    SHOULD INCLUDE THE TRAINING AND STAFFING OF

    MUNICPAL EMPLOYEES.

    A VIABLE ALTERNATIVE TO THIS APPROACH

    WOULD BE FOR THE ULB TO AWRAD A NEW

    MANAGEMENT CONTRACT AND KEEP O&M

    WITHIN THE PRIVATE SECTOR.

  • 7/27/2019 Presentation India Infrastructure

    16/16

    THANKS

    REFERENCES: Case studies of bankable water & sewerage projectfor USAID by ARD

    Infrastructure In India: A Vast Land Of ConstructionOpportunities By PWC

    R V SinghVice President & Head-Engineering

    JITF WATER INFRASTRUCTURE LTD.

    Jindal ITF Centre, 28 Shivaji Marg

    New Delhi-110 015

    Mob: +91 9910772779

    email: [email protected]

    [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]