European Strategic Technologies (SET) Plan Conference Dublin

7th-8th May 2013‘A European Regional Success

Story – The ISLES Project’

rpsgroup.com

Presentation by PJ RuddenGroup Director Energy & EnvironmentRPS Group

ISLES Development Zone is extensive

Circa 16GW ‘potential’ resource

Regional approach has better economics of scale and creates more interconnection between countries

rpsgroup.com

Potential ISLES Development Zone

To provide an exemplar regional study as to how integrated offshore networks can be developed in a cross jurisdictional environment for ISLES.Generate a coherent study which identifies the necessary Development Pathways and informs government bodies of the necessary changes to regulation and legislation that may be needed to enable an effective integrated solution.The study was built on a firm technical, engineering and costing base to provide confidence in feasibility and viability assessments Contribute significantly to the broader North Seas and European Grid studies. Results will provide a blueprint for future integrated developments based on specific development plans for offshore resources. This could potentially be the further phases of ISLES supported by European funding. Study needs to reflect on and evaluate near term opportunity and identify longer term potential having regard to EU SET Plan objectives.

rpsgroup.com

Underpinning Objectives of the ISLES Project

rpsgroup.com

ISLES – Study Road Map

rpsgroup.com

Ireland’s Tidal Energy Resource

Shannon Velocity Map

Viable Resource

Practical Resource

rpsgroup.com

For the first time, tidal–generated electricity is fed directly into the UK national grid.

RPS designed a twin-pile structure, installed at EMEC in Orkney off Scotland, which is now operating as a test-bed for Openhydro’sdevelopment programme.

rpsgroup.com

Northern ISLES Concept Southern ISLES Concept

rpsgroup.com

Key ISLES Technology Areas Strategic Energy Technologies (SET)

Identification of requirements;Development of a technology road map to identify where any potential restrictions may exist either on the supply chain or technical capability

Offshore TransmissionOffshore SubstationsSubsea CablingOnshore Connection

‐ Cable manufacture ‐ Specialised vessels for installation/repair

‐ Long lays and jointing operations in energetic seas

‐ Offshore renewables generators (wind, wave, tidal)

‐ Subsea substations‐Wet mate connectors

Offshore Collector

Onshore Converter StationOffshore Collector

‐Multi‐terminal operation‐ System voltage standardisation

‐ Offshore HVDC substation‐ Platform installation

Onshore Converter Station

‐ HVDC converter‐ Substation footprint‐ Landfall to substation‐ Directional drilling

‐ upgrade/develop new transmission corridors 

‐ 1GW per circuit (SQSS)‐ FACTS technology‐ System balancing

Onshore Transmission Network

Consumer Demand

Consumer DemandConsumer Demand

rpsgroup.com

Summary Conclusions

There are no significant adverse technical or environmental constraints to routing, positioning and construction although the landfall points will present challenges

Co-ordination of construction of an integrated network has the potential to reduce overall environmental impacts

Due to the cross border nature of ISLES, there are particular challenges in navigating both complex and evolving onshore / offshore planning and licensing regimes across three jurisdictions

Environmental benefits in the order of 100 million metric tonnes of C02 emissions savings could result from Northern and Southern ISLES implementation

Planning & Environment

rpsgroup.com

Key policy / regulatory areas to be addressed to allow ISLES become a reality:

Create some form of anticipatory investment model for co-ordinated offshore build to allow phased build and commitment to future phases to support generation investment

Develop regulatory model which redefines the fundamental distinction between interconnection and connection for offshore generation

Recommend an approach to subsidies where they are paid for by the consumer state rather than the state generating the energy

A transmission pricing regime which is seen to be equitable and affordable for generators while ensuring offshore network owners earn sufficient return

Developing an approach acceptable to EU for cross border contributions to meeting targets

Regulatory

Summary Conclusions

rpsgroup.com

ISLES Capital Cost is order of £5.6 billion (€7 b) for combined Northern and Southern ISLES equating to circa £1 million (€1.2 m) / MW of offshore network capacity

Level of subsidy required for generation connected to ISLES to be bankable is in region £79 – 85 (€98 – 106) / MWh equivalent to 1.8 – 1.9 ROCs

ISLES combines interconnection and generation and thus a case can be made for synergistic benefits by increasing the utilisation of the network – thus saving approx £170 million (€212 m) per annum for Southern ISLES. This reduces subsidy to £74.5 (€93) / MWh

Economics & Business Case (1)

Summary Conclusions

rpsgroup.com

Level of renewable subsidy is sensitive to variations in wind turbine load factors – for instance, wind resource supporting ISLES will have improved load factor over projects on East coast of England

Lower planning risk considerations than stand alone projects

ISLES is a transparent mechanism for trading of renewable subsidies between Member States

Environmental benefits in the order of 100 million metric tonnes of CO2 emissions result from implementation of Northern & Southern ISLES (42 million tonnes for Northern ISLES and 58 million tonnes for Southern ISLES)

Economics & Business Case (2)

Summary Conclusions

rpsgroup.com

We have established a credible marine resource that could be developed post 2020 comparable with technology maturity and market expectations for scale and timing.We have developed realistic credible concepts for an ISLES transmission network in the context of the EU SET Plan having regard to future offshore and onshore transmission capacity, environmental considerations, available technology cost and potential supply chain limitations.We have tested the technical and economic feasibility of ISLES in relation to energy policy, planning and licensing/consenting regimes, regulatory and infrastructure scenarios and identify key sensitivities.We have informed government and industry thinking on policy and market changes required to facilitate and streamline the development of such a network in a techno-efficient manner.In fact, the ISLES Report has set the agenda for bulk energy export from Ireland and there are now many projects which are following this established concept and innovative regulatory approach. We must now build on this regional concept to optimise low carbon infrastructure as recommended in the SET Plan approach.

What success has ISLES achieved?

rpsgroup.com

The Full ISLES Report – 12 Volumes

ISLES Project

Thank YouEmail: [email protected]