Comprehensive and detailed article on the working of WAPDA and rivers & barrages in Pakistan.TRANSCRIPT
PRESENTATION TOPRESENTATION TO
PAKISTAN DEVELOPMENT FORUMPAKISTAN DEVELOPMENT FORUM
PAKISTAN WATER & POWER DEVELOPMENT AUTHORITY
April 27, 2007
2
� UNIFIED DEVELOPMENT OF WATER & POWER
RESOURCES
� RESERVOIR OF COMPETENT, PROFESSIONAL &
TECHNICALLY QUALIFIED WORK FORCE
� ADMINISTRATIVE AND FINANCIAL AUTONOMY
UNDERLYING PRINCIPLES FORCREATION OF WAPDA
3
� GENERATION, TRANSMISSION AND DISTRIBUTION OF
POWER
� IRRIGATION, WATER SUPPLY AND DRAINAGE
� PREVENTION OF WATERLOGGING AND RECLAMATION OF
WATERLOGGED AND SALINE LAND
� FLOOD MITIGATION
CHARTER OF DUTIES
4
RESTRUCTURING & REFORM PROGRAMME
5
Restructuring & Reform Objectives
To establish in phases a competitive
and efficient Electric Power System
covering generation, transmission and
distribution according to a carefully
designed strategy and plan of action.
PAKISTAN POWER SECTOR
6
Reform Initiatives
Government of Pakistan has approved a Strategic Plan for
Restructuring of the Vertical-Monolithic Power Sector to form
distinct autonomous entities for Generation, Transmission and
Distribution. The salient futures of the programme are:
• Restructuring of Unified Power Wing of WAPDA into public
limited companies under the corporate law, separating
Generation, Transmission and Distribution functions.
Today 8 DISCOs + 4 GENCOs + 1 Transmission companies
are operating
• Promote competition to eventually offer affordable
electricity to customers
• Enhance privatization initiatives
RESTRUCTURING & REFORM PROGRAMME
7
POWER WING
N T D C500/220 kV
DISCOs
. . . TRANSFORMING THESE ORGANIZATIONAL COMPONENTSINTO INDEPENDENT CORPORATE ENTITIES
POWER SECTOR REFORMSUNBUNDLING & RESTRUCTURING OF WAPDA
Finance &Common Services
WATER WING
GENERATION
TRANSMISSION
WAPDA
CUSTOMERS
DISTRIBUTION
GENCOs( Thermal )
WAPDA( Hydro )
8
OVERVIEW OF PERFORMANCE
12.2 12.7 13.314.1 14.9
15.9
Target
16.8
175186.5 200
220 231270.8 Target
292Revenues (Rs. Billion)
199.5
Jul 06 –Mar 07
1595 1699 2246
71939467
12764 Target
15000
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07
No. of Consumers (Millions)
Villages Electrified
16.7
Jul 06 –Mar 07
10374
Jul 06 –Mar 07
9
Planning/Development/
Generation and Operation
of Hydro Power
WAPDA (POST-RESTRUCTURING SCENARIO)
FINANCE WINGWATER WING POWER WING
AUTHORITY
Restructured WAPDA
Planning/Development
of Water Resources
Management of Finance/
Common Services
VISION 2025
11
BACKGROUND
• Agriculture based economy, about 24% of GDP
• Over 70% exports rely upon agricultural based
products
• 90% of food and fiber requirement meets from
Irrigated Agriculture
• 1/3 of agricultural potential remains untapped
• Semi Arid to Arid Climate
12
CHALLENGES
13
AFGHANISTAN
GILGIT R
GILGIT
HUNZA
ABOTTABADA
ISLAMABADRAWALPINDI
MUZAFFAR ABAD
BALLOKI H/W
SAHIWAL
OKARA
I N D I AIN
DU
S R
.
D.G
KH
AN
SUTLEJ
MIRANI DAM
BOLAN DAM
SIBI
TURBAT
BALOCHISTAN
I R A N
GWADAR
NIHING R.
DASH
T R
.MIRANI DAM
A R A B I A N S E ARANN OF KUTCH
N.W.C
SUKKUR
S I N D H
RO
HRI C
.
PO
RALI
R.
HUB R
.
NAL R
.
ORMARA
KECH R
.
HIN
GO
L
HINGOL DAM
R
.
KARACHI
HUB DAM
KALR
SEHWAN
KOTRI BARRAGE
R.
MASH
KAI
P.F
STAGE-II
GAJ R
.
LARKANA
DA
DU
C.
MASTUNG
NA
RI
R.
HYDERABAD
BADINMITHI
NA
RA
C.
TH
AR
/R
AIN
EE
MIRPUR KHAS
CHOLI
STAN
DESE
RT
KHAIRPUR
SUKKUR BARRAGE
GUDDU BARRAGE
DAJA
L
BRANCH
EXT.
KACHHI
CANAL
BAHAWALPURPANJNAD H/W
BALOCHISTAN PROJECTS
RIV
ER
SW
AT
INDUS R
.
N. W. F. P
RIV
ER
A F G
H A
N I
S T A
N
GOMAL
QUETTA
PISHIN
GOMAL ZAM DAM
KURRAM TANGI DAM
Jalalpur
RIV
ER
CHASHMA BARRAGE
GOMAL ZAM DAM
TAUNSA BARRAGE
MUZAFFARGARH
C.R
.B.C
D.G KHAN
C.
ZH
OB R
. C.R
.B.C
D.I. KHAN
(1st
. LIF
T)
GR
EA
TER
TRIMMU BARRAGE
SDHNAI BARRAGE
KHANEWAL
RAVI
MULTAN
MAILSI SYPHON
RIVER
ISLAM
H/W.
JHANG
CHANAB
TH
AL C
.
TH
AL
CAN
AL
FAISALABAD
PESHAWAR
KOHAT
KALABAGH DAM
TOCHI
KURRAM
TANGI DAM
BANNU
KURRAM
RIVER
R.
WARSAK DAM
NOWSHERA
JHELUM
SOAN R.
JINNAH BARRAGE R
.
RASUL BARRAGE
C.
SAIDU SHARIF
SWABI
MUNDA DAM
TARBELA DAM
KALABAGH DAM PROJECT
MUNDA DAM PROJECT
NWFP PROJECTS
BASHA DAM
Existing Reservoir
NAIGAJ DAM
RAINEE CANALS
SIND PROJECTS
Capital City
City
Town
Barrage/Headworks
Flood Area
Riverian Area
Proposed Command Area
N
SHYOK
GREATER THAL CANAL
AKHORI DAM PROJECT
PUNJAB PROJECTSQADIRABAD BARRAGE
SULEIMANKI
H/W
RIV
ER
LAHORE
SHEIKHUPURA
JAMMU & KASHMIR (DISPUTED TERRITORY)
MARALA BARRAGE
KHANKI
H/W
MANGLA DAM
RIVERINDUS R.
SKARDU
INDUS R
HUNZA
SKARDU
RIVER
International Boundary
Province Boundary
River
Distributry
Existing Dam
Proposed Dam
Canal
LEGEND
ATTOCK
AKHORI DAM
DAMS AND CANAL (VISION-2025) - UNDER CONSTRUCTION
SABAKZAI DAM
KACHHI CANAL
MANGLA RAISING
ABANDONED CHANNELS OF SVP
P U N J A
B
14
• INDIA CLOSED SUPPLIES FROM EASTERN RIVERS
RAVI, BEAS & SUTLEJ IN APRIL 1948
• INDUS BASIN TREATY ON 19 SEPT. 1960
• DIVERTED WATER FROM WESTERN RIVERS INDUS,
JHELUM & CHENAB
DAMS - 2
Mangla Dam
Tarbela Dam
BARRAGES - 5
LINK CANALS - 8
Challenge No.1
15
WATER LOGGING & SALINITY
• WAPDA Completed 46 SCARP Projects
• Open Drains 12,700 Km
• Tile Drains 9600 Km
• Public Tube Wells 14800
• Private Tube Wells 700,000
Challenge No.2
16
Gomal River
Kurram River
Kabul River
Terbela
Reservoir
Chashma
Reservoir
Indus River
Jhelum River
Chenab River
Ra
vi R
ive
r
Su
tle
j R
ive
rArabian Sea
Ne
ela
m
Riv
er
India
Kashmir
Pakistan
Pakistan
Schematic DiagramIndus Basin Irrigation System
(IBIS)
Soan Rive
r
Kunhar River
Haro R
iver
Kala Bagh Reservoir
(proposed)
Mangla
Reservoir
Che
nab
Sutlej
PunjnadRiver
Sehwan Reservoir
(Proposed)
Th
al C
an
al
Thal
reservoir
(proposed)
Chashma-Jhelum Link
Jinnah
Barrage
Rasul
Barrge
U. Jheluam Link
U. Jh
elu
m
Inte
rnalRasul-Qadirabad Link
L. Jh
elu
m
L.ChenabL.C.C.
L.C
.C.
Fee
der
L.C
.C.
We
st
(Jh
an
g)
L.C
.C.
Ea
st
(Gu
ge
ra)
Qadirabad-BallokiLink
Marala-Ravi Link
U. C
henab LinkB.R.B.D. Link
U.C
he
na
bIn
tern
al
BR
BD
Inte
rna
l C.B
.D.C
U. D
ep
alp
ur
B.S.Link 1
B.S.Link2L
. De
pa
lpu
r
L.B
.D.C
U.
Pa
kp
atta
n
Fo
rdw
ah
Ea
ste
rn
Sa
diq
ia
Qaim
U. Bahawal
Sidhnai-M
ailsi-Bahaw
al link
Mailsi
Sidhnai
Trimm
u-Sidhnai Link
Haveli Link
Haveli Internal
De
ra G
ha
zi K
ha
n
Mu
za
ffarg
arh
Punjnad
Abassia
Ghotki fe
eder
Pat Feeder
Des
ert F
eede
rB
eghari F
eeder
North W
est
Ric
e
Dadu
Khairp
ur W
est
Rohri
Khairpur East
Nara
Kalri
Pin
yari
Lined Channel
Fuleli
Kotri
Barrage
Sukkur
Barrage
Guddu
Barrage
Taunsa
Barrage
Trimmu
Barrage
Sidhnai
Barrage
Balloki
Barrag
e
Marala
Barrage
Khanki
Barrag
e
Qadirab
ad
Barrage
Sulemanki
Barrage
Islam
Barrag
e
Ravi
Ch
en
ab
Chenab
Jh
elu
m
Taunsa-Panjnad Link
Warsak
Dam
L. Bahawal
Ras
ul P
ower
Cha
nnel
North
Ra
ng
pu
r C
an
al
L.
Pakpattan
C.R
.B.C
Tarbela Dam
Mangla Dam
Warsak Dam
HEAD WORKS 15
LINK CANALS 11
TOTAL CANALS 55
17
IRRIGATION SYSTEM
• Large Dams 2
• Barrages 23
• Inter River Canals 12
• Perennial and
non Perennial Canals 48
• Irrigation Canals Length 60,000 Km
• Water Courses Length 100,000 Km
18
REHABILITATION OF IRRIGATION SYSTEM
• Remodeling of Barrages
• De-silting of canals
• Canal lining
Challenge No.3
19
Challenge No.4
• INCREASING POPULATION
• DECREASING STORAGE CAPACITY
• SUSTAINABILITY OF RESERVOIR
(SEDIMENT MANAGEMENT)
20
WATER AVAILABILITY Vs POPULATION GROWTH
3888
2751
2129
1555
1282
1066915
858
34
46
65
84
115
139.5
195.5
167.72
208.4
0
1000
2000
3000
4000
5000
6000
1951 1961 1971 1981 1991 2002 2010 2020 2025
YEAR
PER CAPITA AVAILABILITY (M) 3
30
50
70
90
110
130
150
170
190
210
230
PER CAPITA
AVAILIBILITY
POPULATION
GROWTH
WATER AVAILABILITY (MAF)
POPULATION (Million)158.4 Million
(2006)
1100 m3
2006
5260
21
PROJECTED DEMAND FOR WATER
100
135
10.5
4.2
5
3.6
0
20
40
60
80
100
120
140
160
2003 2025
MAF
Industry
Muncipal and Rural Water Supply
Agriculture at the Farmgate
22
PROBLEM DUE TO WATER SHORTAGE
• Water demand increasing due to population
growth, rapid urbanization and Industrialization
• Rising Imbalance between supply and demand
leading to inter provincial tension
• Misuse of Water leads to Environmental
Degradation.
23
7.87 (43%)
0.50 (57%)
1.97 (34%)
5.40 (46%)
YEAR 2025YEAR 2012YEAR 2006YEAR 2006
ORIGINAL
13.22 (72%)
0.46(53%)
4.52(77%)
8.24(71%)
6.22 (34%)
0.48 (55%)
1.72 (29%)
4.02(35%)
5.15 (28%)
18.37TOTAL
0.41(47%)
0.87 (1971)
CHASHMA
1.36 (23%)
5.88 (1967)
MANGLA
3.38 (29%)
11.62 (1974)
TARBELA
GROSS STORAGE LOSSGROSS STORAGE
CAPACITYRESERVOIR
RESERVOIR SEDIMENTATION (MAF)
24
SEDIMENTATION AND STORAGE CAPACITY
0
5
10
15
20
25
1975 1985 1995 2005 2015 2025
15.6 MAF from TarbelaMangla and Chashma
2.9 MAF from Manglaraising
12.8 MAF of current capacity
6 MAF from Kalabagh or Basha
15.6 MAF
10.4 MAF
18 MAF
0 5 10 15 20 25 30 35 40 45 50
10 20 25 30 35 40 45 50 55 60 65 671100
115011601190
1225
1250
1350
1450
1550
(T3,T4)(T5)
(T1,T2)
EL
EV
AT
ION
IN
FE
ET
DISTANCE IN MILES FROM DAM
D.S.L 1369.0
MAX. WATER LEVEL
PIVOT POINT EL. 1356.46.59 MILES(10.6 Km)
SEP/OCT.1979
SEP. 2005
ORIGINAL BED LEVEL
TARBELA DAM RESERVOIR
DELTA PROFILE
SEP 2006
26
STORAGE LOSS %
27
0
8 5 05 0 0 0 1 5 0 0 0 2 5 0 0 0 3 5 0 0 0 4 5 0 0 0 5 5 0 0 0 6 5 0 0 0
9 0 0
9 0 0
1 0 5 0
1 1 0 0
1 1 5 0
1 2 0 0
1 2 5 0
1 0 0 0
S P IL L W A Y C R E S T L E V E L 1 0 8 6 .0
D .S .L 1 0 4 0 .0
D IS T A N C E IN F E E T .
O R IG IN A L B E D L E V E L
P O W E R T U N N E L S L E V E L . 9 5 3 .0
ELE
VA
TIO
N I
N F
EE
T.
M A X . R .L . 1 2 0 2 .0
M A X . R .L . 1 2 4 2 .0 (R A IS E D M A N G L A )
P IV O T P O IN T (E L . 1 0 5 5 )(7 .9 K m )
1 9 9 7
2 0 0 2
2 0 0 5
M A N G L A D A M R E S E R V O IR
D E L T A P R O F IL E
28
Project Life
Existing 145 Years
Raising +80 years
Total 225 Years
STORAGE LOSS %
29
PROBLEMS DUE TO RESERVOIR SEDIMENTATION
• Loss of live storage, reduction in water availability
• Reduction in the energy produced
• Physical Effects of Sedimentation:
� Erosion of Turbine Blades
� Risk of Clogging of Low Level Outlets
� Erosion of Concrete out let structures
� Exorbitant maintenance costs
30
FLOODS
DROUGHT
BUILD RESERVOIRS
Challenge No.5
31
ESCAPAGE BELOW KOTRIHYDROLOGICAL YEAR FROM APRIL TO MARCH
Source: WRMD WAPDA based on data supplied by Govt. of Sindh
30.39 29.81
9.68
45.91
29.5526.90
17.53
52.86
17.22
42.34
53.29
81.49
29.11
91.83
62.76
45.40
0.771.93
24.4021.8020.18
0.29
69.08
33.79 35.15
2.37
8.83
20.79
80.59
20.10
10.98
0
20
40
60
80
100
1976-77
1977-78
1978-79
1979-80
1980-81
1981-82
1982-83
1983-84
1984-85
1985-86
1986-87
1987-88
1988-89
1989-90
1990-91
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
1997-98
1998-99
1999-2000
2000-01
2001-02
2002-03
2003-04
2004-05
2005-06
2006-07
YEARSYEARSYEARSYEARS
ANNUAL DISCHARGE (MAF)
ANNUAL DISCHARGE (MAF)
ANNUAL DISCHARGE (MAF)
ANNUAL DISCHARGE (MAF)
AVG. (35.2)
Upto31.03.07
AVG. 32.761976-2006
32
GROWTH OF TUBERWELLS
0
100000
200000
300000
400000
500000
600000
700000
800000
Tubewells
196019651970197519801985199019952000200320052006
Years
714,800
33
DEGRADATION OF GROUND WATER
Laws Regulating Ground Water Extraction
Small dams to capture seasonal runoff
Challenge No.6
34
MEASURES REQUIRED
• Develop available water resources
• Develop Hydropower Potential
• Conserve Water
• Adopt modern Irrigation Techniques
35
STORAGE PER CAPITA IN DIFFERENT SEMI-ARID COUNTRIES
0
1000
2000
3000
4000
5000
6000
USA Australia China Spain Morocco India Pakistan Ethiopia
Cubic meter per capita
150
36
� WATER-SHORT LAND-RICH COUNTRY
� RAPIDLY INCREASING POPULATION
� DEPLETING ON-LINE STORAGES
� LARGE ESCAPAGES OF UNCONTROLLED FLOOD
FLOWS INTO SEA.
� EFFECTIVE RIVER REGULATION AND INTEGRATED
WATER RESOURCE MANAGEMENT
NEED FOR ADDITIONAL RESERVOIRS
37
CONSENSUS BUILDING
PROVINCES & STAKEHOLDERS AGREEMENT
Challenge No.7
38
IMPLEMENTATION OF MEGA DAMS
INSTITUTION BUILDING
i. Capacity building in Consultancy
ii. Capacity building in construction
iii. Strengthening of Execution &
Monitoring of projects
iv. O&M of Projects
Challenge No.8
39
OPPORTUNITIES
40
ARABIAN SEA
Chenab Rive
r
DISPUTED
TERRITORY
INDUS
RIV
ERKABUL RIVER
Ravi Rive
r
Jhelu
m R
iver
Sutlej River
LEGEND
MOUNTAINS
DESERTS
AREA UNDERIRRIGATION
AREA THATCAN BE BROUGHTUNDER IRRIGATION
SOURCE: AGRICULTURAL STATISTICS OF PAKISTAN 1998-99
22.5ADDITIONAL AREA THAT CAN BE BROUGHT UNDER IRRIGATED AGRICULTURE
44.4AREA UNDER IRRIGATION(BY ALL SOURCES)
54.5CULTIVATED AREA(IRRIGATED + BARANI)
77.1AREA SUITABLE FOR AGRICULTURE
196.0GEOGRAPHICAL AREA
AREA (MA)CATEGORY
LAND USE IN PAKISTAN
Indus R
iver
Sindh 3.6 MA
Punjab 4.3 MA
NWFP 3.0 MA
Baloch. 11.6 MA
TOTAL 22.5 MA
41
PAKISTAN SURFACE WATER RESOURCES
15.00SYSTEM LOSSES3.
1/: Post Tarbela Average
34.88AVAILABLE FOR FURTHER USES4.
105.00PRESENT CANAL DIVERSIONS2.
154.88Total Surface Water Available
4.94• Eastern River Inflows
3.53• Eastern River run-off Generated within Pakistan
5.65• NWFP diversions above Rim Stations
26.99• Chenab At Marala
23.06• Jhelum At Mangla
90.71• Indus At Kalabagh
SURFACE WATER AVAILABILITY1.
INFLOW1/
(MAF)ITEM
SR.
NO.
42
DAMS PROPOSED FOR CONSTRUCTION
• THE PRESEIDENT OF PAKISTAN ON
JANUARY 17, 2006 ANNOUNCED TO
COMPLETE THE CONSTRUCTION OF THE
FOLLOWING DAMS IN PAKISTAN BY 2016
- Diamer-Basha Dam
- Munda Dam
- Kalabagh Dam
- Akhori Dam
- Kurram Tangi Dam
43
PROPOSED DAMS
AKHORI DAMAKHORI DAM
MUNDA DAMMUNDA DAM
DIAMER BASHA DAM
KURRAM TANGIKURRAM TANGI
44
DIAMER BASHA DAM PROJECT
45
DIAMER BASHA DAM PROJECTSALIENT FEATURES
MAIN DAM:
Maximum Height 270 m
Type Roller Compacted Concrete (RCC)
RESERVOIR EL 1160
Gross capacity 7.3 MAF
Live capacity 6.4 MAF
Min. operation level El. 1060 m
POWER HOUSE(S): 2
Total installed capacity 4500 MW
No. of units 12, each of 375 MW
Average generation 16,500 Gwh/year
ESTIMATED COST (Year 2005) US$ 6.5 Billion
46
ProposedMUNDA RESERVOIR
ProposedMUNDA DAM
Location MapMunda Multipurpose Dam Project
Kalam
Swat River
47
*MUNDA DAM PROJECTSALIENT FEATURES
US $ 1.023 Billion(Year 2006 Feasibility)COST
62 Ft- Lift Pump Head
3 Miles long- Pressure Tunnel 7.2 ft dia
78 Cs- Discharge
13 Miles- Length (main & distributaries)
5040 Acres- CCA
RIGHT BANK CANAL
155 Cs- Discharge
23 Miles- Length (main & distributaries)
10057 Acres- CCA
LEFT BANK CANAL660 MW (2669 GWh)Hydropower Generation5930 Acres- Reservoir Area (Acres)
0.67 MAF- Live Storage
1.30 MAF- Gross Storage
RESERVOIR2500 Ft- Length
650 Ft- Height
Concrete face rockfill dam- Type
DAM
*Awarded to Private Sector Company (M/s AMZO) in March 2004
48
KALABAGH DAM PROJECT LAYOUT
49
KALABAGH DAM PROJECT SALIENT FEATURES
RESERVOIRGROSS STORAGE 7.9 MAFLIVE STORAGE 6.1 MAFRETENTION LEVEL 915 FT
MAIN DAMCREST ELEVATION 940 FT.MAXIMUM HEIGHT 260 FT.LENGTH 11,000 FT.
SPILLWAYSOVERFLOW SPILLWAY 1,070,000 Cusecs ORIFICE 980,000 Cusecs
POWERSTATIONNUMBER OF UNITS 8/12 Nos.Initial/Ultimate
INSTALLED CAPACITY 2,400/3,600 MW
(11,400 GWh per year)
ESTIMATED COST (SEPTEMBER 2005) US $ 6.1 Billion
50
51
AKHORI DAM PROJECTSALIENT FEATURES
DAM • Type of Dam Earth Core & Rock fill Dam• Length 5.16 Km (3.23 Miles)• Maximum Height 122 meters (400 Ft)SADDLE DAM• Type of Dam Earth & Rock fill Dam• Height 65 meters (213 Ft)• Length 7.65 Km (4.78 Miles)CONVEYANCE CHANNEL• Discharge 1700 m3/s (60,000 Cusecs)• Length 37 KmsSTORAGE• Gross 7.0 MAF• Live 6.0 MAFPOWER 600 MW (2155 GWh)ENVIRONMENTAL IMPACTS• Area Submerged 65,976 Acres• Population Displaced 49,600ESTIMATED COST US$ 4.4 Billion
52
KURRAM TANGI DAM SITE
SADDLE DYKE
P.H - 1
TUNNEL -1P.H -2
ZARWAM
RIVERS------------EXISTING CANALS ------PROPOSED CANALS ----
PROPOSED POWER TUNNEL/POWER HOUSE---
PROPOSED RESERVOIR-------
MIR ALI
PROPOSED WEIR SITE
A G E N C Y
PROPOSED ACCESS ROAD
ZANGARI
KA
ITU
R
IVE
R
SH
ER
ATALA C
AN
AL
MIR
ALI T
HAL R
OAD
PR
OPO
SED
SHAH A
LGAD
TOCHI RIVER
CA
NA
LPROPOSED THAL CANAL
MAR
WAT
GARANG
ALG
AD
KU
RR
AM
R
IVER
KANDE ALGAD
ALGADKAITU
RIV
ER
15'
10'
33°
5'
0'
32°
55'
70°
15'
20'
25'
30'
35'
40'
70°
70°
70°
70°
33°
33°
33°
70°
TUNNEL -2
P.H -3
DATTAKHEL
CANAL
PROPO
SED S
PAIR
A
SPAIRA RAGHA PLAIN
KURRAM GARHI HEADWORKS
B A N N U
D I S T T: B A N N U RIG
HT B
AN
K
F . R
BARAN DAM
BANNU PLAIN
BANNU
W A
Z I
R I
S I
T A
NN
O
R
T
H
SPINWAM
PROPOSED FEEDER
TUNNEL/CANAL
SHER ATALA
PLAIN
EXISTING RESERVOIR---
COMMAND AREA UNDER CIVIL CANALS------ UNDER MARWAT CANALS-- NEW COMMAND AREA------ PROVINCES BOUNDARY----- ROADS ------------
LEGEND
SCALE (1 Inch = 4 Miles)
1
0
1
2
3 MILE
CENTRAL WAZIRISTAN ROAD
KURRAM TANGI DAM PROJECT
PROPOSED DAM ---------
EXISTING DAM ---------
P.H-4
P.H-5
PROJECT LAYOUT PLAN
RAGHA
Kurram Tangi Dam Site
53
KURRAM TANGI DAM PROJECTSALIENT FEATURES
2. TOTAL COMMAND AREA = 362,380 Acres
68,000 Acres- THAL CANAL(Bannu)
4,080 Acres- SPAIRA RAGHA CANAL(North Waziristan Agency)
107,500 Acres
170,500 Acre
- Civil Canal(Bannu)
- Marwat Canal(Bannu)
12,300 Acres- SHERATALA CANAL(North Waziristan Agency)
278,000 AcresREMODELLING OF EXISTING COMMAND AREAS
84,380 AcresNEW COMMAND AREAS
0.914 MAF- Gross Storage
83 MW (331 GWh)- Power
0.614 MAF- Live Storage
295 Ft- Height
DAM
54
Say 17 Billion
16955
890
1981
1929
2947
3061
2347
1654
1150
547
408
41
TOTAL KALABAGH, DIAMER-BASHA &
AKHORITotalForeignLocal
4399
-
881
879
1099
881
527
88
44
-
-
-
1406
-
282
281
351
282
168
28
14
-
-
-
2993645828443614609825453553
-890435455---2017
5991100555545---2016
5981050530520---2015
7489154254909334165172014
59991044546512705667042013
35962024038012005506502012
6041016025011564866702011
30269542158373574802010
-147-1474001502502009
-147-147261112502008
----419322007
TotalForeignLocalTotalForeignLocal
AKHORI DAMDIAMER-BASHA DAMKALABAGH DAMYEARS
TOTAL FINANCIAL OUTLAY FOR KALABAGH, DIAMER-BASHA & AKHORI DAM (Including IDC)
US $ Millions
*Kalabagh Dam starts immediately & Akhori Dam completes by 2016
55
• Golen Gol
• Phandar
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
• Dasu ?
• Keyal Khwar
• Spat Gah
• Palas Valley
• Lawi
• Bunji
• Kohala
• Basho
Projects
NEW HYDROPOWER PROJECTS -CONSTRUCTION PERIODS
56