preparedness planning campus utility system rma webinar feb 28, 2013

51
Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

Upload: josephine-parkman

Post on 29-Mar-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

Preparedness Planning

Campus Utility System

RMA WebinarFeb 28, 2013

Page 2: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

Presenters:

Henry Johnstone PE Director Mechanical Engineering

Ted Moeller PEDirector Electrical Engineering

John McGann PEDirector Civil Engineering

Page 3: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

Our ExperienceCampus Utility Systems

TroubleshootingPlanning Design Commissioning

Higher EducationUA, NAU, ASU, UNM, NMSU, UW, UAF…..Utility Development PlansPlant and Distribution DesignSystem Commissioning

Health CareDepartment of Veterans AffairsFacility Condition AssessmentHurricane Preparedness EvaluationPhysical Security Design ManualCritical Operations Electrical Analyses

Page 4: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

Campus Utility System Preparedness Planning

•Review characteristics of campus systems and interfaces with external utilities

•Consider vulnerabilities that could lead to major unplanned campus utility outages

•Review campus utility system reliability metrics

•Discuss campus utility system reliability enhancements

•Learning Objectives

• Gain an understanding of campus utility system reliability from an engineering perspective

• Gain insight and tools that can be applied to your specific campus situation

Page 5: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

5

Utility Gas Distribution

CityGate B

 

LPG

HPG

CampusSubstation

13.8kV46kV

4160V

480V

Power Generation

Gas Turbine Generator SteamGeneration

GAS

CityGate A

Utility Substation A

Utility Substation B

50,000lb/ hr 50,000lb/ hr 50,000lb/ hr 50,000lb/ hr

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

7300 Tonhr

2000T 2000T2500 T

2000T2500 T

850 T

Public Utilities Plant Campus Utilities

Cooling Towers

Legend

Water

Electric Power

Steam

Chilled Water

Well

Storage Tank

Gas TurbineGenerator

Ice Storage

Pump

Boiler

Cooling Tower

Chiller

Switchgear

Transformer

Sewer

To WWTP

Campus Utility Systems Preparedness Planning

Page 6: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

6

Utility Gas Distribution

CityGate B

 

LPG

HPG

CampusSubstation

13.8kV46kV

4160V

480V

Power Generation

Gas Turbine Generator SteamGeneration

GAS

CityGate A

Utility Substation A

Utility Substation B

50,000lb/ hr 50,000lb/ hr 50,000lb/ hr 50,000lb/ hr

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

7300 Tonhr

2000T 2000T2500 T

2000T2500 T

850 T

Public Utilities Plant Campus Utilities

Cooling Towers

Legend

Water

Electric Power

Steam

Chilled Water

Well

Storage Tank

Gas TurbineGenerator

Ice Storage

Pump

Boiler

Cooling Tower

Chiller

Switchgear

Transformer

Sewer

To WWTP

Campus Utility Systems Preparedness Planning

Page 7: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

7

Campus Utilities Mission

Subject to capital and operating cost constraints (enterprise mentality)

• Establish & maintain plant, infrastructure and services for a safe, healthy, and productive campus environment• Maintain services to on-campus residence community• Support special requirements of funded research• Meet medical and patient care environmental standards

Page 8: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

8

Page 9: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

9

Page 10: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

10

Page 11: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

11

Preparedness• A set of contingency plans or

processes that enable ongoing operation of utilities through unplanned system disruption

• Internal• External• Forces of Nature

Page 12: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

12

Page 13: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

13

Internal Disruptions

• Distribution Pipe Breaks

• Electrical Breaker Trips

• Prime Equipment Failures

• Unexpected Consequences: Cascading, Compounding Failures

Page 14: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

14

Page 15: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

External Disruptions

• Utility Outages

•Water Line Break• Electrical Substation Failure•Natural Gas Outage

15

Page 17: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

17

Page 18: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

18

Page 19: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

19

Acts of Nature

• Fire• Flood• Earthquake• Extreme Temperature

geographically remote causes

Page 20: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

20

Page 21: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

21

Page 22: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

22

Grid Reliability

Source: IEEE

Page 23: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

23

Other External Vulnerabilities

• Water System Contamination• Electric Grid Instability• Vandalism• Cyber Attack – web access

Geographically Remote Causes

Page 25: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

25

Page 26: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

26

Murphy’s Law

Everything that can fail, shall fail

• What could go wrong with the system or process?

• How badly might it go wrong?

• What needs to be done to prevent (or accommodate) failures

Page 27: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

27

Failure Mode and Effects Analysis

• FMEA : a systematic analysis of the system to whatever level of detail required to demonstrate that no single failure will cause an undesired event

Page 28: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

28

Failure Mode and Effect Analysis Simple Approach

• Risk Priority Number• Severity x Occurrence x Detection =

RPN– Severity

• Rates the severity of the potential effect of the failure.– Occurrence

• Rates the likelihood that the failure will occur.– Detection

• Rates the likelihood that the problem will be detected before it reaches the end-user/customer.

– RPN rating scales range from 1 to 5 or from 1 to 10, with the higher number representing the higher seriousness or risk.

Page 29: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

RPN Considerations

• Rating scale example:– Severity = 10 indicates that the effect is very

serious and is “worse” than Severity = 1.

– Occurrence = 10 indicates that the likelihood of occurrence is very high and is “worse” than Occurrence = 1.

– Detection = 10 indicates that the failure is not likely to be detected before it reaches the end user and is “worse” than Detection = 1.

1 5 10

Page 30: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

30

Block Diagram

Page 31: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

31

Page 32: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013
Page 33: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

33

Page 34: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

34

Single Chiller Plant Example

Page 35: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

35

Single Chiller Plant Example

Page 36: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

36

Utility Gas Distribution

CityGate B

 

LPG

HPG

CampusSubstation

13.8kV46kV

4160V

480V

Power Generation

Gas Turbine Generator SteamGeneration

GAS

CityGate A

Utility Substation A

Utility Substation B

50,000lb/ hr 50,000lb/ hr 50,000lb/ hr 50,000lb/ hr

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

7300 Tonhr

2000T 2000T2500 T

2000T2500 T

850 T

Public Utilities Plant Campus Utilities

Cooling Towers

Legend

Water

Electric Power

Steam

Chilled Water

Well

Storage Tank

Gas TurbineGenerator

Ice Storage

Pump

Boiler

Cooling Tower

Chiller

Switchgear

Transformer

Sewer

To WWTP

Campus Utility Systems Preparedness Planning

Page 37: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

37

Campus Utility PreparednessElectrical Concepts

• System Drawings• Operational Knowledge• Know Your Loads– Load priorities– Metering

• Spare Parts– Breakers– Electronic components

• Standby Generation

Page 38: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

38

Radial System

Source: IEEE Redbook

Page 39: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

39

Primary Selective System

Source: IEEE Redbook

Page 40: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

40

Primary Loop System

Source: IEEE Redbook

Page 41: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

41

EMERGENCYLOADS

COMBINED HEAT AND POWER ENGINE(S)

Campus Power Concept

Page 42: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

42

Utility Gas Distribution

CityGate B

 

LPG

HPG

CampusSubstation

13.8kV46kV

4160V

480V

Power Generation

Gas Turbine Generator SteamGeneration

GAS

CityGate A

Utility Substation A

Utility Substation B

50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

7300 Tonhr

2000T 2000 T2500 T

2000 T2500 T

850 T

Public Utilities Plant Campus Utilities

Cooling Towers

Legend

Water

Electric Power

Steam

Chilled Water

Well

Storage Tank

Gas TurbineGenerator

Ice Storage

Pump

Boiler

Cooling Tower

Chiller

Switchgear

Transformer

Sewer

To WWTP

Campus Utility Systems Preparedness Planning

Central Water and Sewer Concepts

Multiple Municipal Feeds

Networked Distribution

On-Site Production

On-Site Storage

Lift Stations

Back Up Power

Bypass Pumping

EPA Table Top Tools

Page 43: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

43

Utility Gas Distribution

CityGate B

 

LPG

HPG

CampusSubstation

13.8kV46kV

4160V

480V

Power Generation

Gas Turbine Generator SteamGeneration

GAS

CityGate A

Utility Substation A

Utility Substation B

50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

7300 Tonhr

2000T 2000 T2500 T

2000 T2500 T

850 T

Public Utilities Plant Campus Utilities

Cooling Towers

Legend

Water

Electric Power

Steam

Chilled Water

Well

Storage Tank

Gas TurbineGenerator

Ice Storage

Pump

Boiler

Cooling Tower

Chiller

Switchgear

Transformer

Sewer

To WWTP

Campus Utility Systems Preparedness Planning

Central Heating and Cooling Concepts

Parallel Process Trains

Looped Distribution

Satellite Plants

Dual Fuel Sources

Page 44: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

44

Utility Gas Distribution

CityGate B

 

LPG

HPG

CampusSubstation

13.8kV46kV

4160V

480V

Power Generation

Gas Turbine Generator SteamGeneration

GAS

CityGate A

Utility Substation A

Utility Substation B

50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

7300 Tonhr

2000T 2000 T2500 T

2000 T2500 T

850 T

Public Utilities Plant Campus Utilities

Cooling Towers

Legend

Water

Electric Power

Steam

Chilled Water

Well

Storage Tank

Gas TurbineGenerator

Ice Storage

Pump

Boiler

Cooling Tower

Chiller

Switchgear

Transformer

Sewer

To WWTP

Campus Utility Systems Preparedness Planning

Central Heating and Cooling Concepts

Parallel Process Trains

Looped Distribution

Satellite Plants

Dual Boiler Fuel Sources

Thermal Storage

Standby Water

Standby Power

Page 45: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

45

Utility Gas Distribution

CityGate B

 

LPG

HPG

CampusSubstation

13.8kV46kV

4160V

480V

Power Generation

Gas Turbine Generator SteamGeneration

GAS

CityGate A

Utility Substation A

Utility Substation B

50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr 50,000 lb/ hr

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

125 HP

3000T

125 HP

7300 Tonhr

2000T 2000 T2500 T

2000 T2500 T

850 T

Public Utilities Plant Campus Utilities

Cooling Towers

Legend

Water

Electric Power

Steam

Chilled Water

Well

Storage Tank

Gas TurbineGenerator

Ice Storage

Pump

Boiler

Cooling Tower

Chiller

Switchgear

Transformer

Sewer

To WWTP

Campus Utility Systems Preparedness Planning

Combined Heat and Power Concepts

Island from Utility

Load Shedding Scheme

Generate Power & Heat

Dual Fuel Sources

Page 46: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

46

Page 47: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

47

Hurricane SandyPrinceton University

• 4 day Public utility outage• Load switching strategy• Campus CHP provides 15 MW power and heat

to campus• Campus utility meets its mission– Establishes emergency response center– Offers food and shelter– Provides cell phone charging site

Page 48: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

48

Questions?

Page 49: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

49

Page 50: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013

BE PREPARED

Page 51: Preparedness Planning Campus Utility System RMA Webinar Feb 28, 2013