prepared for the ministry of public works and utilities of ...€¦ · or minimize adverse...
TRANSCRIPT
1
KIRIBATI GRID CONNECTED SOLAR PV POWER STATION PROJECT
ENVIRONMENTAL IMPACT ASSESSMENT
Prepared for the Ministry of Public Works and Utilities of
the Republic of Kiribati and the World Bank
Prepared by:
TRAMA TECNOAMBIENTAL TTA (BARCELONA, SPAIN)
6th Revision
August 30th, 2012
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 1
TABLE OF CONTENTS
I. EXECUTIVE SUMMARY ........................................................................................ 3
II. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK .................................... 10
A. WORLD BANK SAFEGUARD POLICY ............................................................ 10
B. KIRIBATI’S ENVIRONMENTAL ACT............................................................. 10
C. ENVIRONMENTAL LEGISLATION, REGULATIONS AND INSTITUTIONS ....... 10
D. OTHER RELEVANT LEGISLATIONS ............................................................. 12
E. OTHER RELEVANT COUNTRY-BASED LEGISLATION .................................... 13
F. LEGISLATIVE OBLIGATIONS UNDER INTERNATIONAL CONVENTIONS ....... 14
III DESCRIPTION OF THE PROJECT ..................................................................... 15
A. INTRODUCTION ......................................................................................... 15
B. THE EXECUTING AGENCY ........................................................................... 16
C. THE IMPLEMENTING AGENCY .................................................................... 17
D. THE OPERATING AGENCY .......................................................................... 17
E. PROJECT RATIONALE ................................................................................. 18
IV DESCRIPTION OF THE ENVIRONMENT ............................................................. 19
A. PHYSICAL ENVIRONMENT ......................................................................... 19
B. BIOLOGICAL ENVIRONMENT ...................................................................... 24
C. SOCIO-ECONOMIC ENVIRONMENT ............................................................. 28
V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ........ 33
A. DESIGN/PRE-CONSTRUCTION PHASE ........................................................ 34
B. CONSTRUCTION PHASE ............................................................................. 36
C. OPERATION PHASE .................................................................................... 40
VI. ANALYSIS OF ALTERNATIVES ........................................................................ 41
VII. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION .......... 43
VIII. GRIEVANCE REDRESS MECHANISM ............................................................. 45
IX. ENVIRONMENTAL MANAGEMENT PLAN .......................................................... 47
A. OVERVIEW ................................................................................................. 47
B. ENVIRONMENTAL MANAGEMENT PLAN ...................................................... 47
C. ENVIRONMENTAL MONITORING PLAN ....................................................... 53
D. INSTITUTIONAL IMPLEMENTATION AND REPORTING ARRANGEMENTS .... 53
X. CONCLUSIONS AND RECOMMENDATIONS ........................................................ 54
REFERENCES ........................................................................................................ 56
ABBREVIATIONS.................................................................................................. 57
ANNEXES ............................................................................................................. 58
ANNEX 1 - ENVIRONMENT LICENSE APPLICATION FORM .................................... 58
ANNEX 3 - MINUTES OF THE MEETING 110926 SCHOOLS .................................... 61
ANNEX 4 - MINUTES OF THE MEETING 110928 KIT ............................................. 64
ANNEX 5 - MINUTES OF THE MEETING 110928 SPORTS COMPLEX ....................... 67
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 2
ANNEX 6 - MINUTES OF THE MEETING 110928 HOSPITAL ................................... 69
ANNEX 7 - MINUTES OF THE MEETING PRELIMINARY REPORT PRESENTATION -
11102011 ............................................................................................................ 72
ANNEX 8: ENVIRONMENTAL MANAGEMENT PLAN (EMP) ...................................... 77
ANNEX 9: ENVIRONMENTAL MONITORING PLAN ................................................. 87
ANNEX 10: FIELD MONITORING CHECKLIST ........................................................ 92
ANNEX 11: MINUTES OF FINAL CONSULTATION MEETING ON EIA_EMP 6 July 2012 100
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 3
I. EXECUTIVE SUMMARY 1. The proposed Kiribati Grid Connected Solar PV Power Station Project objective is to evaluate the
technical/economic/social and environmental feasibility in order to install a maximum of 900kWp PV
solar power directly connected to the electricity grid of South Tarawa. A low to high cost options have
been ranked in order to facilitate the capital costs evaluation. Technically speaking a total of 49 solar
PV basic units can be installed in five locations distributed over the island. The project will be build on
best practices in designing and implementing grid connected solar power plants and civil works by
implementing physical investments and capacity building.
2. Following the World Bank’s safeguard policies, the presented Environmental Impact Assessment
(EIA) aims to assure the proposed project's environmental and social soundness and sustainability.
Potential project impact at short-, middle- and long term will be predicted and the quality of the
impact (positive, neutral or negative) will be assessed. Concomitant potential risks of the
implementation will be evaluated and mitigation measures will be proposed. The objective of the EIA
is to prevent, minimize or mitigate adverse impacts, where the preference lays on preventive
measures, and to enhance the positive project impacts. Social and environmental aspects will be
assessed in an integrative way taking into account different levels (local, regional, national, global).
3. According to the World Bank’s operational policies, the present Environment Management Plan
(EMP) as integral part of the EIA consists of a set of mitigation, monitoring and institutional
measures, to be applied during the design, implementation and operation phase in order to eliminate
or minimize adverse environmental or social impacts. Prior to implementation of the project, and
upon completion of the detailed design, the EMP should be reviewed and updated to ensure that it
complies with the proposed final design and any additional changes made at the design stage (e.g.
location, scale, materials, safety, etc.) and which will have an impact on the environment.
4. The applied methodology of the Social and Environmental Impact Assessment consists of the
revision of existing studies, especially from WB, ADB and other official sources, site visits, meetings
and consultations with local stakeholders. The findings will be presented in the report. Protocols of the
meetings will be annexed as well as other relevant documents.
Environmental aspects
5. The Republic of Kiribati and specially the southern part of the atoll Tarawa is extremely vulnerable
to effects of climate change, as they are the raising sea level or droughts, to changes of the fragile
ecosystem, as coastal erosion or salinity of the freshwater lens, and to hazardous events like oil spills.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 4
6. The major environmental threats on this island are directly or indirectly linked with climate change,
population growth and unsustainable urbanization processes. The main risks are related to soil
(erosion of coastal areas due to raised sea level and coral mining), waste (waste disposal on beaches,
polluted lagoon, poor waste management) and fresh water (scarcity of fresh water, poor quality of
well water). The pollution of lagoon, wells and groundwater as well as the lack of sanitary installations
leads to problems of public health (high infant mortality due to diarrhea and respiratory diseases).
7. The proposed Project is committed to contribute to an infrastructural improvement, to have a
positive environmental impact on the island, and not to cause or increase environmental problems on
the island. The Environment Management Plan (see Annex 6 for details) proposes the following
measures, amongst others, in order to fulfill this commitment:
No use of gravel from the beaches (avoiding coral mining)
Predominantly use of imported timber for support structure if requested(avoiding waste and
later need of scrap metal recycling)
Enable rainwater harvesting (as an added value to power generation)
Selection of near-by material suppliers in order to shorten transport ways and minimize
transport needs (also assuring the regional availability of spare parts and technical service)
Adequate waste management and recycling during construction phase (avoiding pollution)
Reduction of dust and noise during construction work
Recycling plan for construction material (local use, storing, shipping out)
Recycling plan for old parts (avoiding waste and assuring recycling during and after the
operation period of the PV system)
8. The proposed project is expected to have the following environmental impact:
a) The PV Solar plant (considering a maximum installed capacity of 900kWp) will save up to
6.98% of the needed fuel for diesel generators during a maximum period of 20 years (yearly
about 396.300l)
b) The PV Solar plant will save up to 6.98% of CO2 emissions during a maximum of 20 years
(about 1000t CO2 yearly)
c) Kiribati becomes more independent from external fuel imports, using local and renewable
energy sources that are environmentally friendly, save and “for free”
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 5
d) Less fuel transport by vessel and fuel transfer will be needed: There will be a saving of 6,98%
of heavy oil, of CO2 emissions, and a reduced risk of oil spills
e) Reduced fuel transport on road from Betio to Bikenibeu (estimated yearly savings of 200-300l
diesel, about 268.000 kg CO2 emissions saved)
f) Reduced risk of road accidents with fuel trucks (saving of about yearly 1000 km of road
transport)
g) Rainwater collection will be possible from all PV surfaces with a total of about 11.000 square
meters. All roofs where systems are to be mounted are still equipped with rainwater
harvesting systems; the new-to-built supporting structures (4.200 square meters) can be also
used for this purpose.
h) The new-to-built PV support structures will provide about 4.200 square meters of shading,
providing an additional space for meetings and outdoor activities.
i) The PV plants with its maximum extension will cover about 6.800 square meters of roof-top;
they will have a cooling effect on the indoor climate.
9. There is no adverse impact on soil, groundwater, air, coastal area, ocean, lagoon, local flora, local
fauna expected by the implementation of the project. No trees need to be cut off; no medicinal plants
will be affected.
10. The temporal environmental impact during the construction work (disturbance through noise,
dust, transport, waste) will be minor, reversible and manageable if the mitigation measures as
proposed in the EMP are properly implemented. The effective implementation of the EMP will be
audited as part of the grant conditions. The Implementing MPWU/PUB, with the support of a Technical
Assistant, will guide the Contractors in the implementation of the EMP.
11. No hazardous waste (as defined in the Basel Convention) will be generated during implementation
and operation.
Social aspects
12. South Tarawa is suffering an extremely high and still increasing population density (the census
2005 counted 2557.8 persons per km², 40.311 persons on 15.76 km²). Especially the islet of Betio is
one of the most crowded areas in the world (2005: 10.400 persons per km², 12.509 persons in 1.2
km²), (Kiribati National Statistics Office, 2005).
13. The next census will be realized in November 2011, but according to the annual growing rate of
4.4% since 2005 (ADB, 2011) we can estimate the actual number of inhabitants of South Tarawa of
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 6
about 50807 people with a population density of 3224 persons per km². In Betio, the estimated
actual number of inhabitants is 16.197 persons with a density of 13.497 persons per km². Figures
should be revised after the next census.
14. This increasing number of inhabitants leads to an increasing demand of such scarce resources as
they are fresh water and electricity that can’t be met by the actually existing supply system.
15. About 60% of all formal job opportunities are in South Tarawa; this is one of the main reasons of
the migration pressure from Outer Islands. As the private sector is at an early stage of development,
almost 80% of all formal jobs are in the public sector. There is a high unemployment rate (2005 in
South Tarawa 32.6%), especially between young people (2005 in South Tarawa 61.5%) and women
(2005 in South Tarawa 40.6%) (Rallu, undated).
16. The economic development of Kiribati is constraint by a shortage of skilled workers, inefficient
management, weak infrastructure, and geographic remoteness. The PDP per capita (PPP) for 2010 is
estimated in 6.100 US$.
17. There is no gender equality of job opportunities and political influence.
18. The proposed Project is committed to offer qualified job opportunities during implementation and
operation of the PV Solar system. Professional training for PUB staff will be provided in order to
assure efficient operation and maintenance of the solar system. The Contractor will elaborate an
Operation Manual, wherein the necessary procedures of operation and maintenance of the PV system
will be explained to local staff in a comprehensive manner.
19. The solar energy plant will be the first experience of a grid connected PV Solar system. In
addition to its contribution of the local power supply, there will be several added values: Solar energy
has a predominantly positive image as “green” or “clean” energy. Innovative technology will be used
for generating power from a local renewable resource – the sun. In this sense, Kiribati with a relative
stable radiation of about 6kWh/m²/day (NASA) is a very resourceful country. Renewables are
worldwide seen as the energy sources of the future; the visibly installed solar energy system in
Kiribati can be recognized as a symbol of progress showing that the capital of Kiribati forms part of a
modern society. The new PV-systems, installed in public places, can form part of local awareness
rising programs dealing with “clean” energy, the importance of a rational use of energy, the relation
between energy and climate change and the general role of energy in environment, society and
development.
20. The PV plants as real-world examples can be used for educational purposes; they can be included
as a test field for teaching, investigation, monitoring in secondary schools and technical institutes as
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 7
the Kiribati Institute of Technology. For this purpose, different institutes and public organizations
could cooperate, e.g. creating a common training program on solar energy. Professional training
courses for future local “solar engineers” can be developed.
21. The PUB staff will gain experience with PV grid connected systems and their skills on operation
and maintenance of the PV plant will increase due to appropriate training and information provided by
the Contractor. This pilot experience can be used to prepare a second step towards decentralized
grid-feeding solar systems in the future.
22. During the construction of the support structures an implementation of the solar plants, there will
be created some job opportunities for local construction workers providing them an income and
probably some new skills on civil works. This will be a short term impact of the project.
23. We assume that for the proper operation and maintenance of the PV plants, the utility in charge –
PUB – will need to increase its staff and create some additional jobs for operators, mechanics and
electricians. The creation of new work places would be a middle or long term impact of the project.
24. As PUB, through the implementation of solar power generation in its grid, will increase slightly its
independence from price fluctuations of the international fuel market and from governmental
subsidies, it becomes easier for the utility to keep the electricity price stable for costumers. The saved
money from fuel (yearly about 500.000 AUD) can be used to cover part of the gap between the actual
cost of produced kWh (0.52 AUD) and the price of sold kWh (0.40 AUD for private customers).
25. The proposed project is not expected to cause any adverse social impact.
26. All selected locations are either on Government leased land or reclaimed land. As leasing
contracts are long term contracts and the use of the land doesn’t change substantially, no conflicts
with landowners due to modified or additional land use are expected.
27. All implementations are planned at public buildings or institutions and all benefits will be shared
by the whole population. Therefore, there are no conflicts of interests with or between neighborhood
communities expected. There will be no interferences in private properties (land or other assets).
28. No interferences between the project and any religious or cultural values have been detected.
There is no impact on areas of cultural heritage or religious interest on the island.
29. There will be no involuntary resettlements necessary, except the eventual necessary two-day
evacuation of hospital patients during the replacement of the roof and the implementation of the PV
modules. The Government of Kiribati, according to the Hospital indications, should be responsible for
organizing and operating the patient’s evacuation into a pre-foreseen site. In the past already
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 8
occurred patient evacuation, as mentioned during the meeting at the Tengaru Central Hospital, so the
Hospital/Government is the best actor to be responsible for this. An external Project Supervision
Engineering service (PSE) will be in charge for evacuation supervision as responsible of the fulfillment
of the EMP. To be discussed if PUB or the Hospital or both should cover evacuation costs. If no
evacuation of the operating theatre can be undertaken to the satisfaction of the hospital, as noted
during final consultations, then the PSE will identify suitable alternative location(s) for the panels
within the defined project area.
30. The Environmental Management Plan foresees some measures to minimize the impact of
construction work on surrounding neighborhoods (like noise, material transport, material storage, and
waste disposal).
31. All locations will need some additional security measures against theft and vandalism, like
security fences, cages surrounding the inverters or the service of security staff.
32. The EMP foresees procedures for conflict solving or for dealing with upcoming complaints in a
culturally sensitive way in accordance to and respecting local traditions.
33. The EMP contains the following recommendations regarding the implementation and operation of
the planed system:
a) In each PV plant structure should be equipped with a rainwater collection system. As this
equipment is not foreseen in the budget of the proposed project, we propose to create links with
another WB funded ongoing project dealing with water (KAP III) and to look for possible
synergies.
b) The implementation process should be supervised on ground by a Technical Assistance (TA) to
which this document refers as “Project Supervision Engineering” in the person of an International
Environmental Management Expert, who assures the fulfillment of the requirements of the EMP by
the contractor.
c) Technical assistance for Operation and Maintenance will be provided during the first three years,
to PUB.
d) It would be useful to include also staff from the Solar Energy Company Ltd. and from the Kiribati
Institute of Technology in the professional training, in order to exchange the existing expertise
and to contribute to a broader local capacity building. Maybe there are potentials for future
cooperation between the institutions that can be detected.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 9
e) The waste and recycling management plan as described in the EMP should be planned and
prepared before the arrival of material and the start of civil works.
34. Several information and consultation meetings with local stakeholders were realized (see
protocols of the meetings in the annex 3,4,5,6,7):
a) Presentation of the Inception Report to the MPWU staff at 21st of September 2011
b) Information and consultation of local stakeholders from the five selected sites about the proposed
project design (four sessions) at 26th and 28th of September 2011
c) Presentation of preliminary findings of the feasibility study (common meeting with all stakeholders)
at 5th of October 2011
35. The objective of the consultation sessions was to obtain the stakeholders’ expression of no
objection to the proposed project. Questions were raised and clarifications were made (for details se
protocols). The institutions presented their own plans of future constructions and the team was
looking how to integrate the projections of both sides in an acceptable compromise for all parties. As
a result, all parties agreed to continue with the proposed project and to stay in touch for further
information.
Changes in Version 6
35a. The following changes have been made between version 5 and version 6 of the EIA, following final public consultation:
(i) A requirement that the solar panels and associated equipment should be made from non-toxic materials or appropriate mitigation measures should be put in place, to prevent contamination of drinking water collected from the
roofs where the equipment will be installed. Updates to the EMP section and
Annex 8 and 9.
(ii) An agreement that another site will be used for the installation of panels if the relocation of patients and / or the operating theatre of the Tungaru Central Hospital cannot be undertaken without undue disruption or risk. Updates to the executive summary and Annex 8.
(iii) Clarifications regarding roof upgrades / replacements and the ownership of the energy generated. Updates to Section III.
(iv) The solar PV installations will be on a subset of the sites, as approved by the Government of Kiribati, for which the EIA was conducted. The project now involves only four sites: (1) Tungaru Central Hospital in Nawerewere (roof-top installations on 9 existing buildings); (2) Kiribati Institute of Technology (KIT) in Betio (one roof-top installation on existing building and
two installations on the proposed new buildings following construction); (3)
Betio Sports Complex in Betio (one roof-top installation on existing building); and (4) King George V Secondary School in Bikenibeu (five roof-top installations on existing buildings). All installations are to be on existing roofs except at Tungaru Central Hospital and King George V Secondary School, where some roofing is to be replaced where the roofs show signs of rust prior to the solar PVs being installed.
(v) A new Annex 11: Minutes of the Consultation meeting of 6 July 2012.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 10
II. POLICY, LEGAL, AND ADMINISTRATIVE
FRAMEWORK
A. World Bank Safeguard Policy
36. The EIA has been carried out to ensure that potential environmental impacts are addressed
according to the World Bank Safeguard Policy Statement from May 2011, updated in August 2011,
including the Operational Policies OP 4.01 Environmental Assessment from January 1999, revised in
February 2011, with Annex A – Definitions, Annex B - Content of an Environmental Assessment
Report for a Category A Project, and Annex C - Environmental Management Plan, and OP 4.12 on
Involuntary resettlement from December 2001, revised February 2011. The World Bank’s Safeguard
Policy Statement has been used to classify the project as a Category C project which doesn’t requires
an EIA.
B. Kiribati’s Environmental Act
37. The country’s statutory framework requiring compliance to the Environmental Impact Assessment
(EIA) System for all projects is embodied in the Environment Act 1999 (No. 9 of 1999), “Act to
Provide for the Protection Improvement and Conservation of the Environment of the Republic of
Kiribati and for Connected Purposes”.
38. According to the Amended Act 2007, environmental impact assessment of all public or private
development projects is a legal requirement under Part III of the Act, Development Control,
Environmental Impact Assessment, Review and Monitoring, of the Kiribati Environment Act of 1999.
The present document was accepted by the lead agency for administering the Act (MELAD) as
requirements for the safeguard clearance process.
39. The Amendment includes lessons learnt in the implementation of the Environment Act since it
entered into force in March 2000 and to allow for its application in a more effective and functional
manner. In addition, it contains legislative provisions necessary for the implementation of the
following international agreements: the Convention for the Protection of the World Cultural and
National Heritage, the Convention on the Prevention of Marine Pollution by dumping of Wastes and
Other Matter, and the Convention on Biological Diversity.
C. Environmental Legislation, Regulations and Institutions
(Source: Government of Kiribati. 2004. Kiribati’s IWP, POPS, NBSAP-Add on and NBP Projects –
Information Paper Review of Kiribati Laws. Tarawa.)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 11
1. Kiribati Constitution Act
40. The Kiribati Constitution Act is the basis of all laws in Kiribati. Some references are made in the
constitution to environment related matters:
(i) Preamble: The natural resources of Kiribati are vested in the people and their Government. The
customs and traditions of Kiribati shall be cherished and upheld.
(ii) Section 8: Some exemptions to the protection from deprivation of property relate to the need to
protect human health; impose town or country planning requirements; carry out works of soil
conservation or the conservation of other natural resources, carry out agricultural development or
improvement works which the owner has refused to undertake; acquire property which is injurious to
the health of human beings, animals, and plants; and allow prospecting and mining of minerals.
(iii) Section 9: The guaranteed protection for privacy of home and other property does not prevent
the entry into a home for any proposed related to public health, town and country planning and the
development of mineral resources.
(iv) Section 14: The guaranteed protection of freedom of movement does not prevent laws applying
restrictions on movement or residence which are in the interests of public safety or public health and
relate to environment conservation or the fulfillment of international treaty obligations.
2. Environmental Legislation
41. Environmental impact assessment of all development projects whether public or private is a legal
requirement under Part III of the Environment (Amendment) Act 2007 (Obligations), Division 2:
Environmentally-Significant Activities.
42. The Environment and Conservation Division (ECD) of the Ministry of Environment, Land and
Agricultural Development (MELAD), will decide if the Kiribati PV Solar Grid Connected Power Station
Project requires a basic environmental impact assessment.
3. The Ministry of Environment, Lands and Agricultural Development (MELAD)
43. The MELAD is constitutionally responsible for the formulation and management of government
policies in relation to lands acquisition, environmental and conservation matters, and agricultural
development. The Minister, acting in accordance with the advice of the Cabinet, is responsible for the
administration and implementation of the Environment Act.
4. Environment and Conservation Division
44. The Environment and Conservation Division (ECD) is a mandatory authority for the Government
of Kiribati to safeguard the natural environment; air, water, land – upon which life depends, and to
protect human health (Source: http://www.environment.gov.ki/).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 12
45. The Environment Act 1999 (Amendments 2007) assigns various functions to the ECD including
the following:
(i) Protect, restore and enhance the quality of the environment of Kiribati, balanced against the need
to promote sustainable development;
(ii) Develop, establish and administer systems of prevention and control of pollution in both the
industrial and non-industrial sectors, and to monitor through environmental auditing;
(iii) Assist in developing legislation for systems of environmental planning at national, provincial and
local level, and the development of national, provincial and local environment plans;
(iv) Collaborate with relevant public authorities in assisting in the conservation and management of
areas of national and international significance;
(v) Promote the participation of the community in environmental decision making;
(vi) Ensure freedom of and access to information on environmental matters, and in particular to
ensure that the community has access to relevant information about hazardous substances arising
from, or stored, used or sold by any industry or public authority, private person or private enterprise
or any other person;
(v) Conduct public education and awareness programs about the environment;
(vi) Promote the study of the environment through research, surveys, listing and classification;
(vi) Comply with and give effect to regional and international conventions and obligations relating to
the environment.
D. Other Relevant Legislations
1. Land Planning Ordinance 1972 (Amended 1973, 1974, 1977, 1979, 1980 (2
amendments), 2000
46. The objective is to apply controls over land use and developments within designated areas. Land
use planning has important implications on environmental management and must be considered in
the context of other development controls such as those applied under EIA requirements. Some
reference to environment related matters include:
(i) Section 11: The Central Land Board must arrange for the preparation of a General Land Use Plan
for each designated area. These may be single plans or a series of plans. Village representation is
required when plans are prepared.
(ii) Section 10: Provisions is made for the public scrutiny of plans. Plans may be approved under this
section.
2. Local Government Act 1984
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 13
47. Section 45. The functions listed in the Schedule and which may be vested in Local Government
Councils include some environment related responsibilities relevant to the civil works required in the
project.
(i) Regulating the erection, construction, demolition, conversion, alteration, repair, sanitation and
ventilation of buildings and structures
(ii) Providing for building lines and layouts of buildings
(iii) Prescribing conditions for the siting of buildings
(iv) Providing for the demolition of dangerous buildings
(v) Regulating the making of bwabwai-pits and other excavations
(vi) Regulating the use of natural building materials
(vii) Preventing the erosion of land
(viii) Engaging in and promoting land reclamation
(ix) Carrying out sanitary services dealing with rubbish and excreta and prohibiting acts detrimental
to the sanitary condition of the area
(x) Providing for public water supplies
(xi) Preventing water pollution
(xii) Regulating the storage of inflammable and offensive materials
(xiii) Preventing and removing public nuisance
(xiv) Making and maintaining roads, paths, bridges, drains and watercourses
(xv) Regulating the planting and destruction of vegetation along the roads or in public places
(xvi) Providing for the owners and occupiers of land to maintain it, clear it and keep it free of
vegetation and rubbish
(xvii) Preserving and controlling the removal of any antique artifacts
3. Penal Code (Cap. 76 1977)
48. Some offences in the Code are relevant to the environment and to its enforcement. These
include:
(i) Trespassing on burial places – section 125
(ii) Polluting or obstructing watercourses - section 172
(iii) Posting placards – section 173
(iv) Fouling the air – section 179
E. Other Relevant Country-Based Legislation
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 14
49. Other legislation that has implications for resource development and management include the
following:
Act Date Main Objectives
Marine Pollution Prevention Bill 2000 To implement the provisions of the MARPOL Convention and to make comprehensive provision for matters relating to marine pollution and responses to marine pollution incidents.
Wildlife Protection 1975 To provide for matters related to the conservation of wildlife. Prohibition of hunting, killing or capturing are applied during the closed seasons. So too can prohibitions against possessing, acquiring, selling or giving any which have been unlawfully killed or captured,
or any part or product of them.
Recreational Reserves Act 1996 To make provision in relation to recreation reserves. This is one of a series of laws in Kiribati related to land reserved for public purposes.
Public Health Ordinance 1926 To make provision in relation to matters of public health. Regulations for the purpose of protecting and advancing
public health, and specifically relating to among others, latrines, dustbins, and drains; scavenging, cleaning and disinfecting; removal and disposal of night-soil and house refuse; abatement of nuisances injurious to public health.
Public Health Regulations 1926 All premises and land must be kept clean; no stagnant water may lie on land for more that 24 hours; no person
may deposit or cause to be deposited any empty bottle or other receptacle in any street, road or public
Table 1: Other legislations
F. Legislative Obligations under International Conventions
50. The following conventions, protocols and regional agreements are relevant and to apply in
Kiribati:
(i) The Convention on Biological Diversity
(ii) Cartagena Protocol
(iii) World Heritage Convention
(iv) Framework Convention on Climate Change
(v) Regional Seas Convention
(vi) Convention to Combat Desertification
(vii) The Vienna Convention and Montreal Protocol on Ozone Depleting Substances
(viii) Basel Convention and Waigani Convention to control the trans-boundary movements and
disposal of hazardous wastes
(ix) CITES (International trade in endangered species)
(x) WTO and GATT
(xi) PICTA an PACER (Pacific trade agreements)
(xii) Stockholm Convention
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 15
III DESCRIPTION OF THE PROJECT
A. Introduction
51. The proposed Kiribati Grid Connected Solar PV Power Station Project involves the installation of a
grid-connected PV system with a maximum PV capacity of 800 kWAC (900 kWp), in order not to
cause negative impact on grid stability and operation. This PV capacity will be distributed in 49 Solar
PV basic units at five different locations (this number is according to the preliminary design but still
pending of confirmation by the WB and the GOK). The number of decentralized locations should not
exceed five in order to assure an efficient installation and maintenance.
52. The MPWU has identified previously some candidate locations taking into consideration land
ownership, which can become a critical issue for infrastructure projects in small island states, as well
as the projected new load growth.
53. As a result of the feasibility study, the following sites in South Tarawa have been identified as
suitable for the installation of the components and selected to form part of the project:
a) Tungaru Central Hospital in Nawerewere (roof-top installations on 9 buildings)
b) Kiribati Institute of Technology KIT in Betio (one roof-top installation and one free-standing
PV structure)
c) Betio Sports Complex in Betio (one roof-top installation and two free-standing PV structures)
d) Temaiku Primary School in Temaiku (two roof-top installations and one free-standing PV
structure)
e) King George V Secondary School in Bikenibeu (two roof-top installations and one free-
standing PV structure)
54. The overall size of the installed PV capacity will be determined by either the limit of PV capacity
that can be connected to the grid without negatively impacting grid stability and operation, or the
available funding. A technical suitable maximum power of 900kWp (800 kW AC) has been defined.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 16
Figure 1: Project area
55. All solar PV basic units are decentralized systems, independently if they are roof-top-
implemented or installed on free-standing structures.
56. The technical feasibility study carried out in order to determine the locations took into account the
impact on cost, maintenance, impact on grid stability, proximity to loads and other relevant factors.
57. The EIA took into account the environmental and social implications of the proposed project; its
findings are reflected in this report. Preliminary environmental and social reports prepared by the WB
team and other available relevant sources were consulted and taken into account while considering
the site selection. The findings of the EIA are expected to be used as the basis for determining the
need for further social and environmental studies to adhere to national laws and standards and World
Bank safeguard policies.
57a. Building roofs will be replaced or upgraded where necessary in order to avoid the removal solar
panels and equipment for roof repairs in future.
57b. The output from the solar installations will be owned by the PUB and then sold to the consumers
at standard tariff rates.
B. Grant Agreement
58. The Grant Agreement for the project will be the Ministry of Finance and Economic Management
(MFEM).
The Project Management Unit (PMU) in the MFEM will be responsible for the Fiduciary Supervision.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 17
C. The Implementing Agency
59. The Implementing Agency will be PUB. It is recommended that they received assistance from a
TA (the PSE) for the supervision of the procurement, installation and commissioning and in
cooperation with the MPWU on day to day technical management. During the project implementation,
the PSE will supervise the contractor according to the approved final project design, supervising on
ground the compliance of relevant legislations and of the requirements of the EMP.
D. The Operating Agency
60. After implementation, the Public Utility Board (PUB) will be in charge of operation and
maintenance of the PV solar systems. Under the contract framework it is foreseen that during the first
three years of operation, PUB will receive support and supervision from a “post commissioning
services assistance” contracted firm. After the initial operation period of three years, the installation
will officially hand over to the PUB. Since commission till decommission, the PV solar system will form
part of the assets of PUB.
1. Public Utility Board (PUB)
61. All electrical power generation and supply plus piped water and sewage services are provided on
South Tarawa by the Public Utilities Board (PUB), a Government owned company established in 1978
under the Public Utilities Ordinance (CAP 83).
PUB only operates on South Tarawa as it is the only island with a commercial grid based electrical
supply. In the proposed project, PUB’s responsibilities regarding water and sewage are not of
concern, only its energy services. A stated goal of the PUB is to provide South Tarawa with an
efficient, affordable and sustainable electricity supply and the concept of increasing the generation
from solar energy fits into that goal.
62. The PUB is governed by a Board of Directors who are appointed by a panel of three ministers
which includes the Minister of Public Works and Utilities as chairman. The other two ministers are
appointed by Cabinet. The Secretary for Public Works and Utilities acts as the Secretary to the
ministerial panel. The Chief Executive Officer (CEO) of the PUB in turn reports to the Board of
Directors and is appointed by the Board on a three year renewable contract basis.
63. For electricity supply management, directly under the Chief Executive Officer is the Power
Engineering Manager who is responsible for power generation and distribution, the Finance Manager
who is responsible for accounting and finance, and the Human Resources Manager who handles
administration and personnel.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 18
64. The PUB has a staff of around 170 persons with nearly half of those focusing on support functions
in Finance and Administration. In 2000, the PUB was given autonomy for personnel matters and has
its own conditions of service.
E. Project Rationale
65. The Global Environment Facility (GEF) has indicated support following a request from the
Government of Kiribati (GOK), for grant financing under its Medium Size Project (MSP) window for a
“Grid Connected Solar PV Power Station Project” on the South Tarawa grid system of the Public
Utilities Board (PUB). Additionally, grant co-financing for the proposed project investment and TA is
likely to be sourced from the Pacific Region Infrastructure Facility (PRIF).
66. The proposed project responds to a systemic issue in the electricity sector with significant
economy-wide implications for Kiribati. The Kiribati economy is marked by an overarching near-total
dependency on one energy source, oil. About half of the imported oil (Automotive Diesel Oil or ADO)
in Kiribati, is used for electricity generation on PUB’s electricity grid system in South Tarawa atoll. The
expenditures of fuel represent actually 66% of PUB’s budget.
67. The electricity grid system’s operational performance coupled with the high cost of diesel
generation (0.52 AUD/kWh) adds up to the high cost of energy supply service for households and
businesses. PUB’s retail electricity tariffs (domestic rate 0.40AUD/kWh, commercial rate
0.55AUD/kWh, industrial rate 0.70AUD/kWh) have not been sufficient to recover all operating costs,
thereby imposing a fiscal burden on the GOK.
68. The Government has so far managed the situation by a combination of substantial direct budget
subsidy transfers to the sector as well as significant amounts of indirect subsidies.
69. Restoring fiscal sustainability of the national budget within the medium-term is a top national
priority of the GOK. A significant contribution to lowering the fiscal burden is lowering the ADO
dependence in the electricity grid system, by implementing lower cost generation alternatives to the
maximum extent feasible.
70. The use of indigenous and renewable energy sources to reduce the amount of imported fuel for
electricity generation is considered the main goal this project is focused on.
71. The proposed PV solar plant will be the first grid connected plant in Kiribati. Although there
existing experiences with solar plants on Outer Islands (EDF8 Project Solar Energy for Outer Islands),
operated by the Solar Energy Company Ltd., this PV plant will represent a new step, with much more
complex technology and with completely different requirements on the operation and the
maintenance side. As a lesson learnt from the former project, the regular and proper maintenance of
the installations is crucial for its operation.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 19
72. The proposed project will invest in local capacity building, offering to PUB staff, but also to other
interested entities professional training and the opportunity to obtain new skills.
IV DESCRIPTION OF THE ENVIRONMENT
A. Physical Environment
1. Location and Geography
73. Kiribati is composed of 32 small coral atolls and one raised limestone island with a total surface
of 811km², scattered over 3.55 million km² in the Central Pacific Ocean, 4.200km from East to West
and 2.000km from North to South. The country is located between Longitude 170 degrees East and
150 degrees West on both sides of the Equator at the intersection of the International Dateline and
the Equator. Only 18 of the 33 islands are inhabited. All islands are surrounded by an extensive reef.
Figure 2: Location of Kiribati (Source: United Nations Development Assistance Framework, 2002)
74. The islands are divided into three groups, the Gilberts, the Line and the Phoenix. The Gilbert
Group is comprised of 17 islands and has a total land area of 286 square kilometres. Tarawa, an atoll
in this group, is the home of the Kiribati government in Ambo, the port of entry in Betio, and the
international airport in Bonriki. The national capital Bairiki is located on the Tarawa atoll. Eight
inhabited islands and atolls constitute the Phoenix Group. The Line Islands consists of a total of 8
islands and atolls covering an area of 497 square kilometres, including Kiritimati with a land area of
384.5 square kilometres, which is the largest atoll in the world. Except Banaba (78m asl), none of the
islands raises more than 3 meters above sea level.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 20
Figure 3: Tarawa Atoll (Source: United Nations Development Assistance Framework, 2002)
2. Climate
75. Due to its geographical location, Kiribati has predominantly hot dry equatorial climatic conditions
with prevailing South Easterly trade winds most of the year. A gentle breeze from the easterly
quarter is predominant. Temperature varies between 25°C and 33°C with a maximum annual
sunshine of 4134 hours. During the wet season from December to May humidity is high. Occasional
gales occur on the islands, even though they lie outside the tropical hurricane belt.
Table 1 below displays the average monthly temperature in Tarawa (1°35”S, 172°93”E, 4m asl)
based on 8 years of historical weather readings.
Table 2: Average monthly temperature in Tarawa (Source: ADB Road Rehabilitation Project. IEE
2010)
76. The rainfall differs from year to year and from island to islands. Near the equator, annual rainfall
averages 1.020mm, and in the extreme north and south, it averages 3.050mm. The islands also
face the possibility of severe droughts. Prolonged drought periods were encountered in 1988 to
early 1989 and followed by another in 1998 extending into mid-1999 and resulting in the loss of
many valuable food crops including coconuts (Cocos nucifera) and breadfruits (Artocarpus sp.).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 21
3. Soils
77. Like other coral atolls and islands, the nature of the soil is derived from limestone which has been
formed as a result of coral formation over thousands of years. The soil is alkaline and therefore it
does not support the growth of certain plants and trees. The poor and infertile nature of the soil is
due to its alkalinity, porosity and lack of essential elements which makes it unable to support plant
life. Consequently, it is incapable of supporting intensive agricultural activities.
78. The topsoil which is composed of decaying or composted organic matter mainly decaying leaves
and plant materials is thinly spread over most of the area with plant cover and other areas covered
with wild bushes. Due to their ability to withstand the harsh atoll conditions, the predominant plant
species that survive are coconuts (Cocos nucifera), pandanus or screw pine (Pandanus tectorius), salt
bush (Scaevola sericea), and other tolerant indigenous plants and trees. Only 2.74% of the territory
is arable land, half of it used for permanent crops.
4. Water Resources
79. Freshwater resources exist underground as water lenses floating on seawater. These are derived
from the infiltration of rainwater into the water table below the ground. The lens resembles the
appearance of a convex lens which is thickest at the center and thinnest on the sides facing the ocean
or lagoon throughout the length of the atoll or island. The lens is formed where the width of the island
is sufficiently wide so as to reduce the outward flow of the accumulated underground lens. The
freshwater lenses in low coral atoll and islands are extremely vulnerable to occasional environmental
influences.
80. Shallow groundwater (te ran) is the principal source of fresh water in Kiribati. Urban or South
Tarawa water supply originates from water wells located in water reserve areas with restricted use
and access in the villages of Bonriki and Buota. Well water is pumped from wells and conveyed
through a system of pipes to consumers. Chlorination without preliminary treatment of urban water
supply is carried out at the source.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 22
Figure 4: Cross section through a small coral atoll showing the freshwater lens (Source: White, 2010)
81. Climatic conditions have a major influence on fresh water resources in Kiribati. For example,
underground freshwater lenses are recharged by rainfall and households frequently use rainwater
catchments to supplement other water sources. Thus for many reasons, prolonged periods of low or
zero rainfall (i.e. droughts) have serious implications for human well-being. The droughts associated
with well-developed La Niña conditions are clearly evident. During La Niña the Intertropical
Convergence Zone moves away from the equator, reducing rainfall in most parts of Kiribati. It is not
yet possible to make consistent predictions about the future nature of La Niña events, or of the
opposite warm event, the El Niño.
5. Sea level
82. A long term trend of increasing sea level is evident. The observed long term trend in sea level for
Betio is 5mm/yr (National Tidal Centre, Australian Bureau of Meteorology). This is greater than the
estimated range of global sea-level rise over the past century, namely 1 to 2mm/yr. As Tarawa has a
maximum of 3m asl, the raising sea level represents a serious environmental threat for the island.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 23
Graph 1: Daily sea level for Betio (1993 to 2005), relative to mean sea level. Also shown is the linear trend in sea level over the same period (5 mm/yr). (Source: ADB 2006)
Figure 5: Effect of raising sea level in Eita, South Tarawa (Photo: M. Fisk)
Long-term elevation of the surrounding sea level due to climate change is a serious concern for whole
Kiribati, which reportedly has already lost two uninhabited islands.
6. Coastal Processes
83. The coastal process regime (waves, tides, currents, sediment transport) of South Tarawa varies
considerably between different islet shorelines and between the ocean and lagoon. It is important to
recognize such differences in the assessment of coastal change (erosion and accretion) and flooding.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 24
84. Tidal flow is an important mechanism of water exchange between the open ocean and lagoon.
The tidal characteristics of Tarawa lagoon are semi-diurnal (2 high tides every 24 hour period) with
the tidal range (difference in tidal elevation between low and high tide) ranging from 2.4m under
spring tide conditions to 0.5m under neap tide conditions. Notably there is considerable difference in
the height of successive high tides.
85. The wind regime is important in forcing surface currents in atolls; wind also plays a major role in
the generation of waves that can affect shorelines (Kench et al., 2006). Incident ocean swell at the
ocean reef edge is generated by wind systems in the Pacific Ocean. These waves are the largest (1-
3m) to impact the atoll on the ocean reef and have a long period (10-14seconds). The interaction of
wind with the lagoon surface generates local wave energy. These waves are typically lower than
ocean waves and have a shorter period. In Tarawa the wind regime is dominated by winds from the
easterly quarter.
86. Coral reefs are working as a filter of incident waves and control the energy that leaks on to reef
platform surfaces. At the reef edge, waves are breaking and the energy of the incident swell can be
reduced up to 97%. Despite dramatic energy losses at the reef edge, residual wave energy still leaks
onto reef flat surfaces. Transmission of this energy onto reef surfaces and toward shorelines is
strongly influenced by tidal stage, being greatest at higher tidal stages (Brander et al., 2004).
87. The coastal process regime in South Tarawa represents a synthesis of the wind, wave and current
processes that are able to influence the coastline transport of sand and gravel, causing coastal
erosion or coastal accretion (land building). The reef platform at Tarawa is considered to be elevated;
it is exposed at lower tidal stages and is efficient at breaking incident wave energy.
B. Biological Environment
1. Coastal Resources
88. The coastal areas of Kiribati are characterized by white sandy beaches, reef flats, reef patches,
lagoons, mangrove forests, extensive reef mud flats and sea grass beds. These areas contain a
variety of habitats, numerous eco systems and marine organisms. The coastal areas support fishing,
recreation, trade and communication. With constant mining of beach sand and gravel for construction
purposes, the coastal areas are greatly threatened. The European Union (EU) is currently funding a
project on Environmentally Safe Aggregates for Tarawa (ESAT) Project, implemented by SOPAC. The
ESAT project aims to protect the vulnerable beaches of South Tarawa from damage caused by
aggregate mining and provide an alternative supply of material through environmentally safe lagoon
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 25
dredging. However, the earliest implementation of the ESAT Project is expected to be December
2011.
89. The Ministry of Fisheries and Marine Resources (MFMR) is responsible for the management of
marine resources including production of aggregates and sand from the coastal areas. Preventing the
destruction of marine resources including coral reefs is necessary. Therefore, the project will ensure
that material to be used for the ground will not cause significant adverse environmental impact on the
coastal and marine environment. The proposed project will not use the reef mud from the EU funded
project, but instead will import construction material (pre-fabricated concrete blocks, sand for
concrete) from Nauru, Fiji Islands or elsewhere abroad. As the project doesn’t include the
construction of new buildings, the environmental impact of construction works will be minimal.
Nevertheless, the project will take any necessary precautions to ensure that the construction
activities will not pollute the lagoon environment.
2. The Coral Reef
(Source: National Oceanic Atmosphere Administration, 2008)
90. All atolls are surrounded by an extensive reef. Coral reefs are tremendously important economic
and environmental resources. They provide habitat to a number of fish and marine species,
supporting a complex and bio-diverse community. Reefs protect harbors and beaches from the heavy
wave action of coastal storms, keeping shorelines from being washed away and creating safe
anchorages for boats. In Kiribati, people use coral reefs for fishing and collecting seafood during low
tides.
Figure 5: Atoll: Circular-shaped reef that form on the rim of a submerged volcanic island (Mann,
1982; Source: NOAA)
91. Coral reefs are extremely vulnerable to environmental impacts, naturals or human-made, and
suffer degradation from a variety of causes, including climate change, pollutants, over fishing,
physical disturbances, and oil spills.
Certain types of stressors, such as increased sea surface temperatures or toxic exposures to oil, can
cause coral polyps to lose their pigmented zooxanthellae, or to "bleach." Bleaching can damage or kill
corals.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 26
92. Climate change detrimentally impacts coral in several ways. Levels of atmospheric carbon dioxide
are increasing, causing rises in sea surface temperature (SST). The rise in SST, in turn, increases the
frequency and severity of coral bleaching. Levels of carbon dioxide are also increasing in seawater,
resulting in weaker coral skeletons, reduced coral extension (growth) rates, and an increased
susceptibility to erosion on reefs. Climate change is also linked to greater frequencies of severe
storms, which are a major cause of physical damage to reefs.
93. Land based runoff, including excess nutrients, pollutants, and sediments, can harm coral,
particularly when these impacts are ongoing. Especially the patch reef of Tarawa’s lagoon is
threatened by land runoff and pollution (waste disposal at the beach).
94. Oil can kill corals, depending on species, life stage, and exposure. Branching corals are more
sensitive to oil impacts than are massive or plate-like corals. The time of year when a spill occurs is
critical, because coral reproduction and early life stages are particularly sensitive to oil. Longer
exposure to lower levels of oil may kill corals, as well as shorter exposure to higher concentrations.
Chronic oil toxicity impedes coral reproduction, growth, behavior, and development. Fish and
invertebrates that live in and use the reef may also be impacted by oil. In addition to toxic impacts
from spilled oil, vessel accidents can hurt coral reefs in other ways, including groundings and other
physical impacts, anchor damage, and release of ballast water or hazardous materials.
95. One of the proposed project’s impacts is the saving of about 7% of fuel. Therefore, 7% less fuel
transport, 7% less heavy oil for the vessel is needed, and the risk of a ship accident or an oil spill will
be reduced by 7%. Maybe, the impact of this project is small, but it can be seen as a first step in the
right direction, towards less fuel imports and fuel consumption in Kiribati.
3. Forest Resources
96. Except for a few uninhabited islands in the Northern Line Islands and the Phoenix Group, where te
buka (Pisonia grandis) and other wild trees grow, there are no natural forests of major significance in
terms of size, age and biological diversity. Forests in the Lines and Phoenix are resting and nesting
places for long distance flying migratory birds all the year round.
97. Mangrove forests also exist on muddy shores and coastal beaches where water is calm and in
areas that are protected from waves and strong currents. Mangrove rehabilitation is undertaken by
the Government under the World Bank funded project, Kiribati Adaptation Project (KAP II and KAP
III). It includes planting of mangrove seedlings in selected areas prone to coastal erosion and in
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 27
areas to protect causeways in Tarawa and Outer Islands. Mangroves, although considered a 'soft'
option when compared to seawalls, contribute to the building of coastlines and can be one of the most
effective forms of coastal protection.
Several types of the mangroves are found in Kiribati namely the white mangroves (Sonneratio alba),
te tongo buangui (Bruguiera gymnorhiza), te aitoa (Lumnitzera littores), and the red mangrove
(Rhizophora stylosa).
98. The selected sites for the proposed the project are located inside built up areas with no natural
vegetation. There is no forest area located nearby and no mangrove will be adversely affected by the
proposed project.
4. Wildlife
99. Kiribati has a very rich marine wildlife, with abundant fishing grounds, especially tuna.
100. Wildlife is prolific in the islands of Line and Phoenix groups where are nesting and feeding
grounds for 19 species of wild sea birds (18 species of tropic seabirds and 1 endemic species of land
bird native to Kiritibati). Large numbers of migratory wild birds are also seen on the islands during
September to May. Nesting turtles and crabs (coconut crabs, hermit crabs & land crabs) are found in
large numbers.
101. Kiribati has declared the creation of Phoenix Islands Protected Area (PIPA) at the 2006
Conference of the Parties to the Convention on Biological Diversity in Brazil. In January 2008 Kiribati
formally adopted regulations for PIPA that more than doubled the original size to make it the largest
marine protected area in the world. PIPA conserves one of the Earth's last intact oceanic coral
archipelago ecosystems, consisting of eight coral atolls and two submerged reef systems in a nearly
uninhabited region of abundant marine and bird life. The 410.500-square-kilometre protected area
also includes underwater mountains and other deep-sea habitat for 120 species of coral and 500
species of fish. Phoenix Island Protected Area also supports an extensive bird colony and nesting
habitat.
102. Kiritibati Island is a sanctuary and breeding ground in the Pacific for seabirds, supporting 18
different species of birds, including the endemic Christmas Island Warbler. The island is also home,
and a population stronghold, to the endangered Phoenix Petrel and the White Throated Storm Petrel.
Nine protected zones are designated to support the breeding and nesting of the various bird species.
103. According to a 2006 report issued by the International Union for Conservation of Nature and
Natural Resources (IUCN), threatened species in Kiribati include five species of birds, one type of
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 28
reptile, four species of fish, and one type of mollusk. Endangered species included the green sea
turtle, the coconut crab, the giant grouper, the tiger shark, the pygmy killer whale, and the mukojima
boning honeyeater.
104. The Wildlife Conservation Ordinance, Chapter 100, revised edition 1977, provides legal
protection to Kiribati’s wildlife, under the responsibility of the Ministry of Environment, Lands and
Agricultural Development.
105. The proposed project will be realized in urban areas of South Tarawa and will not affect Kiribati
wildlife.
C. Socio-Economic Environment
1. International relationships
106. The Republic of Kiribati became an independent state in July, 12th of 1979. Before, the Gilbert
Islands were a British colony since 1915.
107. Kiribati was admitted to the United Nations (UN) on 14 September 1999 and is a member of
several non-regional specialized agencies, including the FAO, ICAO, the World Bank, IMF, IFC, ILO,
UNESCO, and WHO. The country participates in the Asian Development Bank, the ACP Group, the
Pacific Island Forum, and the Alliance of Small Island States (AOSIS). The nation is also part of the
Organization for the Prohibition of Chemical Weapons. In environmental cooperation, Kiribati is part
of the Basel Convention, the Convention on Biological Diversity, the London Convention, the Kyoto
Protocol, the Montréal Protocol, and the UN Conventions on the Law of the Sea, Climate Change, and
Desertification. (Worldmark Encyclopedia of the Nations. 2007)
2. Population
108. 98.8% of the Kiribati population belongs to the Micronesian ethnic group. The last census at
November, 7th of 2005 enumerated a population of 92.533 people: 45.612 males and 46.921
females. This is an increase of 8.039 persons in 5 years compared to the 2000 census (84.494) with
an annual rate of growth of 1.8%. In July 2011, the estimated number of inhabitants was 100.743
persons. Kiribati’s population has steadily increased since the 1930s when the first census was
conducted. With a population of just under 30.000 people in 1931, 56.000 people in 1978, and over
90.000 in the year 2005, the Kiribati population more than tripled in size during the last 80 years.
109. Population growth varied extensively by island and island groups. While the overall growth rate
of Kiribati was 1.8% per annum, the Gilbert Group grew only at a rate of 1.4% while the Line and
Phoenix Group grew at a very rapid rate of 6.7% per annum. Islands that experienced significant
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 29
population increase include: South Tarawa (3.594), Kiritimati (1.684), Tabuaeran (782); Makin (694),
Abemama (262), and North Tabiteuea (235).
110. The census 2005 counted a total 13.999 private households with 88.644 household members,
which are 6.3 persons per I-Kiribati household on average. In South Tarawa 7.5 persons share a
household on the average. Almost a third (26.798) of all persons that live in private households live
in households with 10 persons or more, and 7.191 persons live in households with 15 persons or
more.
111. The life expectancy of the total population is 64.39 years, 62.03 years for men and 66.88 years
for women. The population is very young, with an average age of 22.5 years; 33.9% are under 14
years and only 3.7% is over 65 years old.
112. Religion plays an important role in the Kiribati society: everybody belongs to any of the Church
communities. 55% of the I-Kiribati is catholic; 36% is protestant and 9% belongs to other religious
groups as Mormons or Baha’i (census 2005).
113. 44% (40.311 persons in 2005; estimated 50.000 persons in 2011) of the I-Kiribati population
lives in an urban environment in South Tarawa. The highest population density is found in Betio with
12.509 persons in 2005, estimated 16.000 persons in 2011, living in a little islet of 1.2km². The
annual growth rate is 4.4% (ADB, 2006). The next census will be carried out in November 2011;
these figures should be revised and actualized with the official numbers.
Graph 2: Population density in South and North Tarawa, 2000 and 2005 (Source: Rallu, undated)
114. The migration pressure from Outer Islands to South Tarawa is high because the majority of
remunerated income opportunities, education and health services are located here. Due to this
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 30
overcrowding effect, South Tarawa faces serious environmental and social problems, as pollution of
ground water, polluted lagoon and beaches, scarcity of freshwater and high unemployment.
115. The long term trend of migration to South Tarawa has eased. The 2005 census data show a net
flow of people from the Gilbert Group Islands towards the Line Islands during the inter-census period
2000-2005. These figures should be revised after the new census 2011.
Graph 3: Population in Kiribati and South Tarawa (Source: Kiribati National Statistics Office)
3. Economy
116. The country's economy is predominantly subsistence, with copra, seaweed and fisheries being
the main source of foreign exchange earnings. Except abundant fish grounds, Kiribati has very few
natural resources; the only phosphate deposit on Banaba was exhausted before getting the national
independence in July 1979. The estimated GDP per capita (PPP) is US$ 6.100; the total GDP for the
country is estimated in US$ 618 Mio. (2010). Revenues from the licensing of foreign vessels in the
Kiribati Exclusive Economic Zone (EEZ) contribute some US$ 2-3 Mio. per annum. Tourism plays a
fairly modest role in the Gilbert but in the Northern Line Islands, especially Kiritimati, tourism is high
and contributes with more than 20% to the GDP.
117. About 60% of formal jobs are located in South Tarawa, about 80% most of them in the public
sector. The average wage is about AUD 200 per fortnight.
118. Economic development in Kiribati is constrained by a shortage of skilled workers, weak
infrastructure, inefficient management and remoteness from international markets. The proposed
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 31
project will provide professional training and management skills for PUB staff and other interested
institutions. The proposed PV-installation will provide yearly saving of about AUD 500.000 for the
national economy that can be used to decrease the subsidies of energy supply.
119. Private businesses are in the early stages of development. Foreign financial aid from the EU, UK,
US, Japan, Australia, New Zealand, Canada, UN agencies, and Taiwan accounts for 20-25% of GDP.
Remittances from seamen on merchant ships abroad account for more than US$ 5 Mio. every year.
Kiribati receives around US$ 15 Mio. per annum for the government budget from an Australian trust
fund.
4. Infrastructure, Public Services and Utilities
120. The infrastructure of Kiribati is generally rudimentary. There are only two paved roads on South
Tarawa and Kiritimati. A program to construct causeways between North and South Tarawa was
completed in the mid-1990s. In 2008 the road in Betio and Bairiki was improved with Japanese aid. A
new ADB and WB funded Kiribati Road Rehabilitation Project involves the rehabilitation of an
estimated 27.5 kilometers of main road and approximately 6 kilometers of principal feeder and access
roads on South Tarawa, from Bairiki to Tanaea. The implementation of this project is supposed to
start in early 2012.
121. Kiribati has 21 airports; two of them (Bonriki and Kiritimati) served by international flights, only
four of them with paved runways. The country has two small CASA airplanes to serve domestic
flights.
122. Per each 1000 inhabitants there are 0.297 physicians (2006) and 1.8 hospital beds (2008)
available. In 2004, the under-five child mortality rate was 65 per 1000 live births, mostly caused by
diarrhea and respiratory diseases, while in the Western Pacific Region, it was 31 (WHO, 2006). For
2011, the estimated infant mortality rate (under one year) is 38.89 per 1000 live births (The World
Fact Book, 2011). There are currently sixteen doctors providing specialized medical care in Kiribati,
with sixteen more scheduled to join them. Cuban doctors have reportedly provided a dramatic
improvement to the field of medical care in Kiribati, reducing the child mortality rate in the country by
80%.Cubans have also offered training to I-Kiribati doctors. In December 2010, thirty-one I-Kiribati
were studying medicine in Cuba. (wikepedia.org, 25.09.2011)
123. 62% of the whole population (77% of urban and 50% of rural population) has access to an
improved drinking water source (2000). Only 33% (47% of urban and 22% of rural population) has
access to an improved sanitation facility.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 32
124. The existing public water supply system is operated by Public Utilities Board (PUB) for about
50.000 people in South Tarawa. The supply system is in poor condition. An estimated fresh water
demand for South Tarawa is 3.500 – 4.000m³/day whereas PUB is currently extracting 1.900 m³ per
day from its Bonriki gallery. Buota gallery normally produces 350m³/day but currently awaits major
renovations. The water resource issue of shortage of clean water of 1.500 – 2.000m³/day is
compounded with the rapid increase in population on South Tarawa and the numerous water leakages
in the reticulated system. There is also the need to explore fully the potential of rainwater harvesting
to provide alternate source of drinking water and thereby reducing the use of well water that is often
of poor quality and becomes a threat of public health. Therefore, the project recommends and
enables by technical design the rain water collection of all PV systems, whether installed on roof-top
or on a free-standing roof structure.
125. PUB is responsible for the electricity supply on South Tarawa. There are 6.331 households
connected to grid with a contracted power per household of about 500 to 700 watts. The average
monthly consumption of electricity lays between 150 and 200kWh; with monthly bills for electricity of
AUD 60 to 80 per household. Taking into account an average weekly income of 100 AUD and the high
unemployment rate, electricity, even subsidized, is fairly expensive for the customers. The number of
illegally connected households is not known; PUB is just planning an investigation. Beside the
domestic connections, there are 897 commercials and 408 industrial companies connected to the
grid. Yearly there are 10 to 12 black-outs, caused by technical problems and with an average
duration of 1-2 hours. In addition, costumers suffer eventual short shutdowns of the energy supply,
caused by failures of the distribution system, the poor state of wiring or the deficient internal
electrical installation. The proposed project will have a positive impact on the energy supply in South
Tarawa as there were made some recommendations in order to increase general grid stability.
5. Education
126. The Government of Kiribati has gradually taken over control of primary education from the
missions. Education is free and compulsory for children between the ages of 6 and 14. I-Kiribati
receive seven years of primary education and five years of secondary education. The net enrolment
ratio at secondary level is 68%, and gross enrolment ratio for all levels combined 75% (2005). The
pupil-teacher ratio for primary is 25:1 and secondary 17:1 (2005). 93% of the I-Kiribati is literate in
his/her own language.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 33
127. In the Kiribati Institute of Technology (KIT), (formerly known as Tarawa Technical Institute;
TTI), 32 teachers offers courses in technical and vocational subjects for 257 fulltime students, that
finish their studies with a certificate. The Marine Training Centre (MTC) runs 18-month courses in
deck, engine-room and catering work on merchant-shipping lines; it trains about 200 students each
year. There is also the Kiribati Teachers College (KTC) based in South Tarawa, offering training for
primary teachers. Kiribati is a partner in the regional University of the South Pacific, which has its
main campus in Suva, Fiji Islands, and a campus in Tarawa, Kiribati, with some 3.000 students,
enrolled for a wide range of courses using the university's distance learning facilities.
128. The Ministry of Education, Training and Technology (METT) collaborates with civil society, and
particularly the churches, towards delivering universal basic education. It has identified some key
areas for improvement: early childhood development and non-formal education; primary teacher
education; upgrading schools and classroom resources; and literacy and numeric.
(www.commonwealth-of-nations.org, 2011)
129. The proposed project will provide professional training regarding the operation and maintenance
of the PV solar system to PUB staff and other interested institutes and companies as KIT and SEC. As
part of the PV solar system will be installed in educational institutes (Temaiku Primary School, King
George V Secondary School, KIT), these institutes can include the system in their teaching plans, e.g.
as a monitoring field.
V. ANTICIPATED ENVIRONMENTAL IMPACTS AND
MITIGATION MEASURES
130. Safeguard measures have been incorporated in the project as follows:
(i) Design-Preconstruction Phase, the period before the actual project implementation when
designs are being prepared (Section A). This allows the designers to incorporate the Environmental
Management Plan (EMP) in the project design, technical specifications and contract documentations;
(ii) Construction Phase, the period since the “Notice to Proceed” is given to the Contractor until the
issuing of the “Certificate of Completion” (Section B). The Contractor will implement the project
following the design and technical specifications of the EMP; and
(iii) Operation and Maintenance Phase, the period starting with the issuing of the “Certificate of
Completion” issued by the MPWU until the end of the 20 year lifetime of the project (Section C).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 34
A. Design/Pre-Construction Phase
1. Protection of Sensitive and Ecologically Important Areas
131. The proposed project will not traverse any environmentally sensitive areas, and no adverse
irreversible or enduring impacts caused by the implementation of the PV solar systems are
anticipated. However, during the preparation of the detailed design for the project, attention will be
given to protect potential environmental sensitive areas and to minimize negative impacts on
sensitive ecosystems, or the natural environment. Suggested measures to achieve this objective are:
Identify environmentally sensitive or ecologically fragile areas (if any);
Ensure construction personnel are aware of locations and importance of the sensitive areas and
avoid disturbing them;
If the proposed construction is located close to these areas, take necessary measures to
avoid/minimize disturbance.
2. Environmentally Sound Design
132. The proposed project is committed to have a positive environmental impact on the island and
not to cause or increase environmental problems on the island. In order to fulfill this commitment,
the following measures are proposed to be taken into account in the project design:
No use of gravel or sand from the beaches, avoiding coral mining and soil erosion. Consider
possible alternatives for construction materials (aggregates) that should be imported from
abroad, from Banaba or from other save locations
In case of usage of free standing structure, a proper structural design that is environmental
friendly and requires less maintenance is suggested. In order to avoid waste and later need of
scrap metal recycling after finishing the system’s lifespan, the predominantly use of timber as
material for support structures is proposed if the project will require it.
Enable rainwater harvesting from all installations as an added value to power generation. A
separate project, Kiribati Adaptation Project (KAP III), financed by the World Bank is dealing with
issues of freshwater supply for the inhabitants of in South Tarawa. The two projects should seek
to coordinate the implementation of the rainwater harvesting equipment to maximize the synergy
from the Projects.
Selection of material suppliers in order to shorten transport ways and minimize transport needs
(also considering availability of spare parts and technical service).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 35
Choice of the location that gives the best economy in terms of excavation and fill in order to avoid
or minimize soil erosion during excavation works for the construction of the stand-alone PV
structures
3. Cultural Heritage
133. Historical sites from the World War II consisting large canons and bunkers are located along the
beach in Betio area. However, these sites are located outside the project area. No specific cultural
archeological sites have been identified inside or around the selected project locations. However, in
case a cultural/historical heritage site is identified during the construction, the Contractor will be
asked to stop work immediately and notify the MPWU supervision consultant who in turn will notify
the relevant Government agencies.
4. Social or Community Concerns (Pre-Construction)
134. Because the project is concentrating on the installation of PV solar grid connected systems, little
concern regarding its negative effects is expected.
135. Solar energy has a predominantly positive image as “green” or “clean” energy from a local
renewable resource – the sun. Renewable are worldwide seen as the energy sources of the future;
the visibly installed solar energy system in Kiribati can be recognized as a symbol of progress
showing that the capital of Kiribati forms part of a modern society.
136. During the preliminary phase of the project 5 location sites were selected in order to guarantee
space availability enough for installing the maximum PV capacity according to technical grid limitation
(900 kWp). All the selected site locations are included in Government Leased Land, except Temaiku
School, which is on a reclaimed area. No need of additional land is required by the project execution
so all the lease arrangement currently in place are covering the project needs.
Therefore, no conflicts with landowners due to modified or additional land use are expected.
138. All implementations are planned to be implemented at public buildings or institutions and all
benefits will be shared by the whole population. Therefore, there are no conflicts of interests with or
between neighborhood communities expected.
139. There will be no interferences in private properties (land or other assets) of surrounding
neighborhood communities, like additional shading, covered views, noise, increased traffic, during
operation of the systems.
140. There will be no involuntary resettlements necessary, except the eventual necessary two-day
evacuation of hospital patients to a near-by hospital owned mwaneaba (local meeting house) during
the replacement of the roof and the implementation of the PV modules.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 36
141. The project has no need of land acquisition and compensation of loss of crops so no measures to
minimize the social impact for this scope are requested.
B. Construction Phase
During this phase the PSE in the person of the International Environment Management Expert (IEME)
will be responsible to supervise that the Contractor’s works follow the EMP procedures and overall
recommendation indicated in this document and approved by the WB/GOK.
1. Social or Community Concerns (Construction)
142. The objective is to minimize social disturbance and maximize community benefits from the
Project. Measures to achieve this objective are:
Inform local neighborhood community before construction activities start about planned civil
works how they could be affected by them;
Avoid or minimize disturbances by construction activities in near living areas, e.g. avoiding works
at nighttime, minimizing transports of material, noise control;
Apply adequate waste management and avoid run-off of waste, e.g. littering off packaging
material;
Offer employment and training opportunities for local people. The general practice is that
Contractors employ workers from the communities. The clan leaders (unimwane) will be
consulted when recruiting workers for the Contractors;
Include women and other community groups in project activities whenever there is any
opportunity;
143. Neighborhood communities are not directly affected by project implementation; indirect
disturbances due to construction works will be minor and temporary. The Contractor will make
appropriate arrangements during the construction period to minimize them.
2. Soil Erosion
144. Proper application of mitigation measures will ensure that impacts of surface erosion are
temporary and minimized to acceptable levels. Measures to achieve these objectives are:
Minimize work areas;
Keep vegetation clearing at the necessary minimum;
Keep vehicles on defined tracks;
Construct the necessary temporary/permanent control structures;
Encourage re-vegetation as soon as the construction activities finish, or plan to immediately
rehabilitate the disturbed sites after use.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 37
3. Controlling Sediment
145. Implementation of proper mitigation measures will ensure that the impacts are temporary and
minimized to acceptable levels. The proposed mitigation measures are:
Installing silt traps or other control structures at the outset of the construction
Preparing all disturbed areas for re-vegetation or for natural re-vegetation;
Phasing and limiting ground disturbance to areas of a workable size;
Scheduling construction to limit disturbance of large areas of soil during wet seasons;
Avoid discharging of contaminated water to the lagoon.
4. Controlling Storm Water
144. The objective to control storm water is to minimize the impact of contaminated run-off water.
Implementation of proper mitigation measures will accordingly ensure that impacts can be minimized
to acceptable levels. Measures to achieve the objective are:
Pass storm water run-off from construction areas through rocks or hay traps to remove soil and
petroleum-based organic pollutants before disposal;
Store oil and bituminous products at a contained location away from drainage ditches.
5. Management of Stockpiles and Spoil-heaps
145. To minimize dust and sediment run-off, material stockpiles and spoil heaps (if any) require
proper management. Suggested measures are:
Discuss dumping locations with the government officials and local landowners including plans for
future use of the spoil materials;
Include all drainage provisions suggested for construction sites in the site plans;
Choose the locations of waste spoil piles to avoid blocking surface run-off or drainage ditches;
Cover all spoil heaps or stockpiles during rainy season to prevent erosion and sediment run-off;
6. Air Quality and Dust Control
146. Dust problems created civil works or transport of materials can be a nuisance but not a very
critical issue. However, to control unnecessary dust, the Contractor will:
Spray water on spoil-heaps if there are dust generating materials accumulated during dry periods
especially near schools, hospitals, rural communities, etc.;
Cover all dust generating loads carried in open trucks. This is overall due in the Tungaru Central
Hospital site where patients’ conditions requires special attention. Specific arrangements should
be defined with the Hospital personnel (doctors, etc.).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 38
7. Noise Control
147. Noise mainly affects urban areas, villages, hospitals, schools, etc. In order to minimize noise
during construction works, the suggested measures for the contractor to follow and supervised by the
PSE, are:
Use modern and well-maintained equipment (with mufflers where appropriate);
Use noise screens or mounds near residential areas, when appropriate;
Carry out noise construction activities and transports during normal working hours, never at night
time or Sundays.
Negotiate with schools/hospitals a schedule of noisy work, taking into account the needs of
students/patients.
Inform previously, when there will be unusual or unavoidable noise.
8. Aggregate Management
148. Aggregate for the ground construction is not necessary for the project but, just to take into
account this possibility, they should be sourced considering potential environmental impacts which
are:
Avoid overloading trucks and cover trucks to minimize dust and loss of load from trucks during
transportation;
Use water sprays or covered chutes to reduce dust emission during loading and unloading of
materials from barges;
Maintain crushing and mixing plants in good working condition so as to reduce emission from the
plant;
As far as possible, plan truck trips during low traffic hours;
Implement safety procedures during transport to reduce the potential for road accidents in village
or urban areas;
149. The Contractor will have to obtain the requisite permits and clearances from the ECD prior to
starting the construction work.
9. Off-site and Waste Management
150. The objective of waste management is to avoid contamination from solid wastes and sewage.
The Contractor is required to minimize the environmental impact of its work by adopting respectful
waste management behavior and fulfilling national norms and regulations. Among others, the
Contractor is recommended to:
Store wastes with respect for health and environment and being responsible for their recycling;
Contain all stored wastes within construction sites, avoid littering and runoff;
Use recycled or renewable building materials (e.g. timber) where possible;
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 39
Optimize and reduce waste production. Avoid mix of different waste and minimize waste disposal
into the landfill;
Not produce hazardous waste;
Shipping out hazardous waste.
Sort waste according to its type and origin. Store selected materials in safe place in order to
avoid contamination, especially if they will be shipped out for recycling;
Encourage the recycling of waste. Follow the hierarchy: Prefer local recycling or reuse before
shipping out for recycling, in case the recycling in Tarawa is not feasible, before waste disposal in
the landfill;
Properly dispose of all used fuel and lubricant oils in environmentally sound manner, either by
recycling or for other use such as fuel for hot mix plant, etc.;
Crush and bury all inorganic solid waste in an approved solid waste disposal area;
After construction has finished, remove all disabled machinery and waste from the project area;
Utilize, if available, public toilets at construction sites;
Compost all green or organic wastes or use as animal food.
10. Safety and Health
151. Occupational health and safety (OH&S) risks of construction works can be limited by clearly
defining procedures for handling construction materials, operating heavy equipment, installing PV
material etc. The providers of equipment and materials shall provide information about the proper
handling and safety of their products. The Project Supervising Engineering (PSE), contracted to
support the Implementing Agency for project implementation supervision, will supervise the
requirements for OH&S and personal protective equipment (PPE) outlined by the contractor. The
Contractor is responsible for the implementation of safety and health protection measures. The PSE is
responsible for the supervision of the proper implementation of the measures.
“As an example for OH&S requirements on construction sites, see the standards of European Agency
for Safety and Health at Work (http://osh.sm.ee/legislation/construction.stm).
An example for PPE requirements (Australian standards) can be found under http://www.safety.uwa.edu.au/policies/personal_protective_equipment_guidelines.”
The PSE will be called to list specific equipment and training needed to:
Ensure all occupational health and safety requirements are in place on construction sites (The PSE
should indicate also how to monitor the respect of these measurements).
Understand the use of (PPE) and make sure that it is used properly;
Install lights and cautionary signs in hazardous areas;
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 40
Ensure safety and inspection procedures;
Safe handling of toxic materials and other hazardous substances;
Implement a system of penalties for violation of rules and regulations to be included in the EMP;
152. General Health and Safety Awareness for construction workers will include:
• Introduction to health and safety issues in construction sites by the Contractor;
• Education on basic hygienic practices to minimize spread of tropical diseases, including information
on methods of transmission and protection;
• Prohibition of drugs, kava and alcohol on construction sites;
• Assure availability of medical assistance in emergency or non-emergency situations and availability
of other health-related assistance.
11. Site De-commissioning
153. To minimize ongoing impacts after construction is completed, the Contractor will be responsible
for the proper decommissioning of the temporary construction sites. Suggested measures to achieve
this objective are:
Assure all waste and remaining material for recycling has been removed from the construction
site;
Rake or loosen all compacted ground surfaces;
If necessary, implement revegetation / rehabilitation of the construction sites involving, where
possible, local women’s and community groups.
C. Operation Phase
1. Safety
154. The proper protection of the installations is very important in order to avoid accidents, damaging
or unauthorized removal of the technical equipment. The contractor will be responsible for
implementation and PSE for monitoring of proper safety measures. In order to meet safety
requirements, the following protection measures are proposed:
Inhibit unauthorized access to the PV modules on roof-top or at the free-standing structures by
construction design and eventually necessary technical protection measures (fences, gates,
locks);
Cover inverters with a locked metal cage firmly attached to the wall in order to avoid
unauthorized manipulation (especially by playing children with the risk of accidents) or theft;
Mark sites with comprehensive and visible signs (pictograms) indicating danger and no-go-areas;
Put the wiring underground in order to avoid accidents and damage (accidentally or intentioned
by vandalism);
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 41
Advice to the public institutions where the PV installations are implemented about special risks
and security needs (security fence, safeguard at nighttime);
Inform the administration of the public institutions where the PV installations are implemented
that they should report immediately to the PUB any case of damage of any component of the PV
system.
2. Maintenance and repairs
155. Only few maintenance activities on site will be necessary (See chapter 192 for a detailed
description of required maintenance).
During the first three years, PUB will get advice and trained from the Post Commissioning Services
responsible experts contracted for training and O&M support program. The Contractor will provide the
necessary knowledge and skills for proper maintenance and repairs of the system, in form of a
Operational Manual and professional training. The PUB itself will ensure that there is sufficient funding
available to carry out periodic maintenance and repairs of the PV installations. This will be addressed
by a technical assistance activity to be done under the project.
VI. ANALYSIS OF ALTERNATIVES 156. Prior to the feasibility study, the Government of Kiribati has had selected several candidate sites
for the possible implementation of the project. All candidate sites were visited and checked taking
into account the following selection criteria:
a) Site location: the location has been characterized by specific practical qualities as well as some
qualities related to the land property, that is whether the land is government owned (reclaimed
land), government leased with an existing government building or facility (school, offices, etc.),
government leased without any building or activity, or private land. This includes also the
accessibility of the site for inspection and maintenance by PUB staff.
b) Electrical characteristics of the site location: This includes the distance to the transformer as
connection point to the grid, as well as transformer technical properties, among other aspects to
evaluate.
c) Photovoltaic properties: The size of the available surface is the main aspect to consider here For
this initial introduction to grid connected PV systems operated by PUB it is preferable to have few
larger sites rather than many distributed sites.
d) Added value: A set of site locations properties has been selected in order to give to the added
value of each site a weight in the final decision, e.g. the expected social and environmental
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 42
impact/benefit for each site as well as security aspects. For instance if a site has already some
activity or it is guarded there is less risk to suffer damage or theft.
After a preliminary data gathering visit done by the consultants, the sites have been characterized
and evaluated according to the scores. An evaluation matrix with a ranking of sites was developed
during the inception phase in order to select the most suitable.
Location Name Location
Installable PV A-Si (kWp)
PV AC rated Power A-Si (kW)
Electrical properties
PV properties
Added Value
TOTAL PV Sum
Betio Sport Complex rooftop 7 145 130 11,7 27,65 6 52 145
Temaiku Primary School 5,75 176 159 9 29,8 6 51 321
Tungaru Central Hospital 7 225 203 10,5 26,95 6 50 546
Betio Sport Complex Field 7 443 399 11,7 24,5 6 49 989
Kiribati Institute of Technology 4,5 218 196 9 25,2 4 43 1207
King George V Secondary School roof-top 6 308 277 9,9 20,5 6 42 1515
Bikenibeu Power Station 7 98 88 10,8 19,6 4 41 1613
King George V Field 3,5 689 620 7,5 24,5 5 41 2302
TAMOA Place 4 81 73 3,9 20,3 5,5 34 2383
Table 3. Prioritization of the selected candidate site locations
0
10
20
30
40
50
60
Betio S
port
Com
ple
x
rooftop
School
Sate
llite
Hospital
Betio S
port
Com
ple
x
field
Technolo
gy
Cente
r
Kin
g
Georg
e V
Secondary
Bik
enib
eu
PS
Kin
g
Georg
e V
Fie
ld
TA
MO
A
Pla
ce
Added Value Usage
PV carcterization
Electrical Caracterization
Location Characterization
Graph 4. Prioritization of the selected candidate site locations
157. In case one or two of the selected sites would drop out due to any yet unforeseen reason, the
project designers could have a look on rejected sites if they would be suitable for the project, but
having in mind that they will not be the best choice. As well, in cooperation with GoK, a new
screening of potential candidate sites could be made.
158. If necessary, due to financial, technical or administrative constraints, alternatives regarding the
design of the PY system, the design of the support structures or the selection of materials could be
considered. All implications of the alternative solution (cost, technical details, environmental and
social impact, etc.) should be evaluated. There are some examples for possible alternatives: The PV
capacity to be installed could be reduced easily thanks to the high modularity of the design. This just
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 43
considering a lower number of solar PV basic Units (the maximum capacity of 900 kWp cannot be
increased);
Alternative suppliers for technical equipment (PV modules, inverters, etc.) can be selected, taking
into account technical, financial and environmental specifications;
The design of the support structure can be modified (e.g. height, floor, water-proof structure
under the PV arrays);
Alternative materials can be selected for the civil works (e.g. gravel instead of concrete floor, the
free standing poles can be fixed directly into the ground without concrete block as basement).
159. The proposed project is supposed to have a general positive technical, financial, social, and
environmental impact on South Tarawa (see details in chapter III and IV). Without the
implementation of the project, the situation will remain as it is now: PUB will remain without new
assets and new skills, PUB will not get a financial benefit of yearly about AUD 500.000. The demand
imported fuel will probably increase in the future; more money will be spent on fuel. Probably, PUB
will be forced in the future to increase the tariff of sold electricity. There will be no additional training
and teaching opportunities for schools and institutes, as well as no professional training for PUB staff.
South Tarawa will not enjoy the benefits of the modern PV technology.
VII. INFORMATION DISCLOSURE, CONSULTATION,
AND PARTICIPATION
160. As required by the World Bank Safeguards Policies, information and consultation meetings were
held with the local stakeholders and Ministries during the preparation of EIA.
161. Preliminary consultations were undertaken between 16th and 30th of September 2011 during the
field visit to South Tarawa.
162. Several information and consultation meetings with local stakeholders, including representatives
from the involved institution, the Ministries and the utility, were realized (for details, see Minutes of
the Meetings in Annex 3,4,5,6, and 7):
a) Meeting with the Energy Planning Unit of MPWU: Presentation of the Inception Report at 21st of
September 2011. First approach, key points and findings were presented, discussed and approved
between WB, GOK and TTA. In particular the site prioritization was agreed as well as the technical PV
maximum capacity installable into the grid. The methodology, work plan and work schedule were
confirmed during these meetings and approved by the stakeholders (Please refer to the Inception
Report for more details).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 44
b) Information and consultation meetings with local stakeholders from the five selected sites (four
sessions with a total of 22 assistants) at 26th and 28th of September 2011 with the following agenda:
1. Welcome and introduction (purpose of the meeting)
2. Institutional and personal introduction of assistants
3. Presentation of the purpose of the feasibility study and preliminary results
4. Presentation of plans for a possible implementation of a solar system into the building complex
5. Discussion and presentation of possible alternatives
6. Clarification of open questions from all parties
7. Feed-back: Expression of No-Objection to the proposed implementation
8. Outlook: How to go on, what will be needed?
9. Final statement and closure
The objective of the consultation sessions was to obtain the stakeholders’ expression of no objection
to the proposed project. Questions were raised and clarifications were made (for details see protocols
(MoM, Annex 1 to 4). The institutions presented their own plans of future constructions and the team
was looking how to integrate the projections of both sides in an acceptable compromise for all parties.
As a result, all parties agreed to continue with the proposed project and to stay in touch for further
information.
c) Presentation of preliminary findings of the feasibility study (common meeting with all stakeholders)
at 5th of October 2011 with 14 assistants.
162. As all selected sites are inside public institutions and no major irreversible adverse impact on the
surrounding communities are expected by the implementation of the proposed project, there was no
need for additional public consultations.
163. The EMP will be disclosed to the public and will be available locally to the interested public at the
MPWU office.
164. Beneficiary consultations will be conducted during the preparation and construction phases, and
records of environmental and social issues raised and complaints received during consultations, field
visits, informal discussions, formal letters, etc., will be followed up and the records will be kept in the
project office at MPWU.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 45
VIII. GRIEVANCE REDRESS MECHANISM
Taking into account the fact that the implementation of the project is not expected to affect lands,
trees or the social community in general, it is reported here a mechanism which should be followed in
case of any concerned were raised by the people. This procedure should be discussed with the MPWU
prior to start the executive part of the project. In the operational phase of the project it is
recommended that the Implementing Agency inform local neighborhood and community about this
mechanism for registering comments, suggestions or grievances, for example publishing and exposing it
at each of the selected site locations.
165. The Local Environmental Expert named by MPWU project to follow EMP, will receive and
document issues and concerns that the local people and stakeholders will raise regarding to the
project and its implementation. Resolution of these issues and concerns will be undertaken
expeditiously in order to minimize any adverse impact that may affect the project implementation.
166. The following process will be followed to address the issues and concerns that stakeholders and
Affected Person/People (AP) may raise regarding the proposed development:
The first step towards resolution of issues and concerns relevant to project is the filing of a formal
notice/complaint by the AP with the MPWU – Energy Planning Unit.
For minor complaints such as excessive dust, noise, safety violation, the Project Supervising
Engineering (PSE) in the person of the International Environmental Expert, assigned to supervise
environmental and social aspect, will respond within 96 hours of lodging the complaint and a
resolution will be conveyed to the AP within 8 working days.
For more substantial complaints about land occupation, damage by Contractor’s equipment, etc.
the PSE will respond within 96 hours and set up, with Implementing Agency support, further
discussion / meetings with the complainant to reach a satisfactory resolution acceptable to all
parties within ten working days
The MPWU in the person of the Local Environmental Expert will maintain a register where all
complaints are logged by: date, name and contact address and details of the complaint. A
duplicate copy of the register entry will be given to the AP for their record. The AP may, if so
desired, discuss the complaint directly with the PSE or his representative at a mutually convenient
time and location.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 46
If the complaint of the AP is dismissed, the AP will be informed of his/her rights in taking the
complaint to the next step. However, every effort will be made to resolve the issue to the mutual
satisfaction of both the parties.
Should the AP be not satisfied with the decision of the MPWU, the AP may file a written complaint
with the Secretary of the Ministry of Public Works and Utilities. The time horizon for the
investigation and resolution of the complaint will vary and is dependent on the investigating
officer of the MPWU.
Till this step, the MPWU will take over the costs of grievance procedures (protocols, meetings with
AP, responses). The reparation costs for damages will be duly evaluated. A percentage of the
project's budget will be destined to a funds in order to cover these costs. The amount of the fund
has to be determined.
In case the responsibility of the Contractor for the damages has been proven, the MPUW can seek
costs of the grievance redress mechanism from the Contractor.
• Should the AP still be not satisfied with the decision of MPWU, the AP may then take the
grievance to the Kiribati Judicial System. This will be at the AP’s cost, but if the court shows that
MPWU have been negligent in making their determination, the AP may seek costs.
167. For any concern or complaint, where a community is involved, it is recommended to search for a
culturally sensitive solution, according to I-Kiribati culture and traditions. E.g., the complaint could be
raised in a community meeting in the mwaneaba (local meeting house) and the unimwane (old men)
could be asked for advice.
The affected community should present their complaints to the Local Environmental Expert (LEE). If
required for cultural sensitivity, a female LEE should be available. Affected persons may take a
supporter, and if a complaint is upheld and requires legal redress, will be entitled to legal
representation at no cost to them. The LEE will discuss the issue within the MPWU/PUB/Contractor
and PSE. The PSE will be the coordinator of conflict resolving measures, like a meeting between the
community representatives and the contractor. Community should be informed by the implementing
agency about this mechanism.
The costs of these procedures should be covered from the grievance fund, mentioned in paragraph
166. This advice should be taken into account for the conflict solution, if possible.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 47
IX. ENVIRONMENTAL MANAGEMENT PLAN
A. Overview
168. There are no specific risks expected by the implementation and operation of the proposed
project, aside from possible minor disturbances to the adjoining areas caused by the construction
work. Possible impacts were detailed above and will be mitigated by appropriate measures during the
design/pre-construction, construction, and operation phases, as summarized in the Environmental
Management Plan (EMP).
169. According to the Kiribati Government’s Environmental Act, 2007, An Act to Amend the
Environment Act 1999, the project does not require the preparation of a Basic Environmental Impact
Assessment, which is equivalent to the World Bank’s Environmental Impact Assessment (EIA).
According to the Act, MPWU will need to comply with environmental requirements as detailed in the
EMP.
170. The Environmental Impact Assessment of the proposed installation of grid connected PV solar
system in South Tarawa led to the conclusion that any adverse impact of construction and operation
will be minor, reversible and manageable if the mitigation measures as given in the EMP are properly
implemented. The EMP (Annex 6) is based on the type, extent and duration of the identified
environmental impacts. The EIA has been prepared by close reference to best practices and in line
with the World Bank’s safeguard policies.
171. The effective implementation of the EMP will be audited as part of the Grant conditions. In this
regard, the PSE will guide the PUB (the Implementing Agency), and the Contractors on the
implementation of the EMP. For this reason the PSE must include in its structure the International
Environmental Management Expert.
172. Prior to implementation of the project, and upon completion of the detailed design, the EMP will
be reviewed by the PSE contracted to support PUB to ensure also that it complies with the proposed
design and any additional changes made at the design stage (e.g., location, scale, source of
materials, safety, etc.) and which could have any impact on the environment as reflected in the EMP.
B. Environmental Management Plan
173. The findings and proposed mitigation measures have been compiled into an EMP. It summarizes
all the anticipated environmental impacts and its associated mitigation measures during the design,
construction and operational phases. It makes reference to the relevant law and contract documents,
approximate location, time-frame, mitigation costs (in US$), and the responsibility for its
implementation and supervision.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 48
174. The recommendations and proposed mitigation measures will be attached to the Project Bidding
Documents and subsequently the Contractors’ contracts. There are no additional environmental
mitigation costs as these are incorporated in the civil work design and included in Contractor’s
contract. Many of the mitigation measures will be incorporated as part of the standard design and
construction practices and as such their costs will be included in the construction cost. This will be
refined during the detailed design stage.
1. Design/Pre-Construction Phase
175. Experience shows that inadequate application of the EMP by the Contractor may occur due to
weak linkages of the EMP with the contract documents. The EMP is a part of the work program and its
fulfillment is part of the Grant agreement, and as such it must be addressed by the Contractor and
carried out as required.
176. In the Bid and Contract section “Special Conditions of Contract”, the Project Supervision
Engineering (PSE) will, prior to the tender being called, revise and update the EMP as it is forming
part of the Bid and Contract document. The Contractor will use this document to cost his compliance
with the EMP.
177. During the bid evaluation and selection of Contractor, the Contractor will be required to provide
a short statement confirming that:
Costs to fulfill conditions of EMP have been included into the bid price;
Contractor has experience of working with an EMP;
Contractor counts with a qualified and experienced person on its team who will be responsible for
the environmental compliance of requirements of the EMP.
2. Construction Phase
178. During the construction phase, the Contractor will work according to the requirements of the
EMP. Supervision and monitoring activities will be undertaken as follows:
(i) The Contractor has the initial responsibility for implementing the EMP as part of the works
contract.
(ii) The Project Supervising Engineering in the person of the International Environmental Management
Expert will direct the Contractor with regard to compliance with the EMP.
(iii) The Project Supervising Engineering will carry out independent monitoring of the work and can
issue Defect Notices to the Contractor.
(iv) The Project Supervising Engineering will report to the MPWU regarding the work progress and
fulfillment of the EMP.
(v) The Contractor will have his own representative on site – the Site Engineer (SE) - who will be
responsible for implementing the contract and complying with the EMP.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 49
179. Before starting the construction work, the Contractor will assign a Site Engineer who is
responsible for the fulfillment of EMP during the construction work.
180. The PSE will supervise the construction works and give advice to the Site Engineer. It will have
regular meeting with the SE.
181. Preparation of site and establishment of Contractor’s facilities: this applies to all of the
Contractor’s facilities, storage areas, workshops, labor camps (when needed), concrete batching
areas, etc. Before starting the work, the contractor should arrange meeting and briefing with
MPWU/PUB through Local Environmental Expert to facilitate and guide the project staffs to be aware
and respect local culture and customs. The location and development of the Contractors’ facilities will
be approved by the PSE. The sites will be selected following these criteria:
they must not interfere with the environment and social well-being of the surrounding
communities with noise, dust, vibration, etc.;
the size of Contractor’s facilities is limited to absolute minimum to reduce unnecessary clearing of
vegetation;
sanitary waste and grey waters, if any, have to be treated before release into surface water
systems;
fuel storage areas are not located within 20m of a water course;
the Contractor’s facilities are to be protected by adequate security measures and adequately
indicated (comprehensive and visible signs (pictograms, Gilbertese and English language)
indicating danger and no-go areas).
182. Clearing of sites and removal and disposal of vegetation:
• The area to be cleared should be limited and excessive machine disturbance of the topsoil should be
avoided.
• Cleared material is to be piled into manageable sized heaps according to disposal or re-use
requirements.
183. Prevention of soil erosion on construction site: The Contractor will be responsible for ensuring
that the erosion is contained by appropriate soil conservation protection methods. This is particularly
important since the work location is close to the lagoon. The Contractor will:
Limit the extent of excavation to reduce soil erosion potential;
Apply soil conservation protection methodology to susceptible areas to prevent / minimize storm
water runoff carrying eroded materials off-site;
Avoid excavation and operating machinery in wet ground conditions;
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 50
Upon completion of works, the Contractor will ensure that all excavated areas are properly
stabilized. This includes the rehabilitation of all disturbed areas by the most appropriate and
effective method.
184. Storage and handling of construction materials, fuel and lubricants: Construction materials will
include cement for concrete manufacture, timber posts, steel and other construction materials, fuel
and lubricants, etc.
Fuel will be stored in bounded areas at least 20m away from the lagoon areas;
Not recyclable material (oil) should be removed from Tarawa at contractor’s costs.
All workshops would be provided with oil and water separators;
Vehicles and machinery will not to be refueled within 20m of the lagoon;
The Contractor must have trained personnel who are competent in fuel handling procedures and
for cleaning up accidental spills;
Any major spill in the vicinity of the lagoon will be reported to MELAD;
Waste oil, oil and fuel filters will be collected and recycled- If recycling is not possible, they should
be removed from Tarawa. These materials are not allowed to be disposed in landfill areas;
At the closure of the site, all contaminated soil will be excavated, removed and replaced with
fresh topsoil.
185. Noise and vibration: This applies to night works for all machinery, vehicles and construction sites
where noise and vibration may affect susceptible receptors. The Contractor will be responsible for
ensuring that noise and vibration does not affect the adjacent communities. While it is unlikely that
noise and vibration will be an issue due to the large distances between the activities and the
communities the Contractor will confine all work to daylight hours (6am to 6pm).
186. Dust management: During construction, when dust may be generated, the Contractor will
monitor the work-site conditions and apply dust control measures, which include reducing
construction traffic movements and spraying water on exposed areas.
187. Community safety from increased vehicle movements: This applies to all vehicles and
particularly to material transporting trucks that pass through villages. The Contractor will ensure that
all vehicles which pass through villages are operated safely without endangering these communities.
The Contractor is to ensure that:
All trucks and equipment are maintained in a safe operating condition;
All drivers and machinery operators are properly trained and act responsibly;
All loads are secured and all loads with potentially dust generating materials will be covered with
tarpaulins;
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 51
The Contractor will immediately remove any driver that ignores any of the community safety
requirements.
188. Safety and Hazard: Before starting construction work, the Contractor will be required to identify
potential hazards and, if necessary, prepare an emergency response plan to address serious accidents
and nominate a person who will be immediately contacted in case an accident occur. The emergency
response plan will be submitted to the PSE and PUB for approval one week prior to starting work.
The Contractor will be required to keep the construction site free of drugs, kava and alcohol;
The Contractor will be required to provide a safe work environment and provide safety measures
and protective equipment to all workers including; hand, head, eye and ear protection and safety
footwear. The PSE will assure that the personal protection equipment will be utilized correctly;
The Contractor will provide first aid facilities on-site and employ a trained first aid person;
The Contractor will provide potable water, toilets and wash water to the workers, or lease these
facilities from institution at the construction site.
189. Disposal of waste materials: all construction waste materials including packaging material, cable
cutoffs, cement bags etc. are to be suitably disposed of, by the contractor under the PSE supervision
(see below). If these cannot be recovered for reuse or scrap value these materials should be taken to
an approved landfill sites for safe disposal.
189a. Alternatives to moving patients and / or the operating theatre: If it is not practical to safely
relocate patients from the operating theatre at the Tungaru Central Hospital site for the duration of
construction, the PSE shall find an alternative site or sites to install the solar panels, within the
existing project area, and with all of the necessary approvals.
190. Clearance and rehabilitation of construction sites and removal of Contractor’s facilities: It is the
Contractor’s responsibility to address site clean-up.
This includes the removal of all waste materials, machinery and, in case, any contaminated soil;
All construction sites and work areas will be rehabilitated so that these can be returned as close
as possible to their previous uses. This includes the stabilization and landscaping of the
construction site, if necessary;
No waste will be left on site after the work is completed. Should the Contractor fail to remove the
waste, the MFEM is entitled to withhold payment, arrange the clean-up and deduct the cost of the
clean-up and appropriate administrative charges from the final payment.
3. Operational Phase
191. People Safety: During operation, the following safety measures should be taken in order to avoid
accidents or damage to the system:
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 52
Protect PV modules from unauthorized access by appropriate technical and non-technical
protection measures (fences, gates, locks, safeguard);
Cover inverters with a locked metal cage firmly attached to the wall or protect the inverter area
with a secure enclosure in order to avoid unauthorized manipulation (especially by playing
children with the risk of accidents) or theft;
Mark sites with comprehensive and visible signs (pictograms) indicating danger and no-go-areas;
Control the state of wiring in order to avoid accidents and damage;
Advice to the public institutions where the PV installations are implemented about special risks
and security needs (security fence, safeguard at nighttime);
Inform the administration of the public institutions where the PV installations are implemented
that they should report immediately to the PUB any case of damage of any component of the PV
system.
192. The following maintenance activities on site should be realized on a regular base by staff of PUB
as Operating Agency:
Under normal climate conditions with regular rainfall, the slope of the installation will enable the
self-cleaning of PV modules by rinsing rainwater. During droughts, the dust of the panels should
be removed twice a year. The cleaning can be made easily with a hose pipe;
Adjacent trees or shrubs should be trimmed in order to avoid shading over the panels or damage
by falling fruits (especially coconuts);
Wiring should be revised once a year in order to make sure that there is no damage (e.g. rotten
cables, damages by rats). This activity should be carried out by authorized PUB staff only;
Inverters should be revised regularly to assure their perfect operation (replacement of rusted
components). This activity should be carried out by authorized PUB staff only;
Security measures should be revised regularly (e.g. replacement of rusty locks, closing of fence
holes);
The state of all installations should be revised by PUB staff after special climate events, as heavy
rainfalls, storms or floods in order to detect damages on the support construction or on the PV
installation itself;
The institution where the PV installation is installed should immediately report any damage on the
structure to the PUB Staff in order to assure repairs or replacement of damaged components;
All repairs or manipulation of the PV system should be carried out exclusively by authorized staff
of PUB that previously has got instructions and training.
The maintenance protocol should be revised by the Contractor and PUB before the Operational
Phase is starting.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 53
C. Environmental Monitoring Plan
193. An Environmental Monitoring Plan for the proposed project (Annex 9) has been prepared,
including the following components:
Environmental issue to be monitored and the means of verification;
Specific areas, locations and parameters to be monitored;
Applicable standards and criteria;
Duration, frequency and estimated monitoring costs;
Institutional responsibilities for monitoring and supervision.
194. A Field Monitoring Checklist has been prepared based on the EMP and Environmental Monitoring
Plan (Annex 10). The Field Monitoring Checklist will be used by the PSE in the person of the
“International Environment Management Expert” (IEME). The signed checklists will be provided to the
MPWU in the person of the “Local Environmental Expert” (LEE) who will be responsible for the
appropriate follow-up and compliance reporting. The IEME, according to the MPWU and LEE
suggestions and recommendations, will be responsible for taking potential corrective actions if some
are requested to meet EIA/EMP requirements.
195. The PUB/MPWU, in the person of the LEE will maintain a Complaints Database, which will contain
all the information on complaints received from affected persons, communities or other stakeholders.
This would preferably include: Short description of the complaint, location, time, actions to address
this complaint, acceptance of the proposed solution.
D. Institutional Implementation and Reporting Arrangements
1. Project Implementation
196. PUB is the Implementing Agency for the proposed project and will be responsible for the
implementation and compliance with the EMP and Monitoring Plan. Day-to-day implementation and
compliance will be the task of PSC.
2. Reporting Arrangements
197. The findings of the regular monitoring activities, as specified in the Monitoring Plan (Annex 9)
and following the Monitoring checklist will be included in the quarterly PSE progress reports. The
person assigned for environmental and social affairs of the PUB/MPWU (Local Environmental Expert)
will be responsible for distributing the reports to ECD (MELAD) and for the reviewing of Environmental
Safeguard sections of the quarterly progress reports. This will include an overview of the status of the
implementation of the EMP and compliance to the national environmental regulations. The progress
reports will be submitted for information to MPWU-Energy Planning Unit and the World Bank.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 54
3. Budget
198. The budget for the Environmental Management Plan is shown in Table 4. The Environmental
Management Plan shows that there are no environmental mitigation costs, since this is incorporated
in the civil work design and included in Contractor’s contract. Costs that are shown are for national
and international staff for a two-year project implementation period. Total costs, including a 10%
contingency, amounts to US$50.500. The budget should be revised before starting the project.
In order to guarantee the correct execution of this Plan, as mentioned previously through this
document, it is recommended that the PUB foresees to include in its team a local expert (Local
Environmental Expert) who is responsible for following all the phase of the activities of the Plan and
to be the reference person for the International Environmental Management Expert. This last expert
should be included in the contracted PSE expert responsible for super visioning the EMP.
item Rate
(US$/Month)
Year 1 Year 2 Total
International
Environmental
Management Expert
(PSE)
20.000 20.000 10.000 30.000
Local Environmental
Expert (PUB/MPWU)
4.000 4.000 2.000 6.000
International travel
and support costs
6.000 6.000 12.000
Local travel and
support costs
1.000 1.000 2.000
Contingencies 10% 3.100 1.900 5.000
Table 4: Environmental Management Costs
X. CONCLUSIONS AND RECOMMENDATIONS
199. During the implementation of the project, the construction works can cause minor reversible and
temporary environmental disturbances (e.g. noise, dust, waste, increased traffic) that will be
mitigated by operational procedures following the Environmental Management Plan. The fulfillment of
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 55
the EMP will be supervised by the PSE and monitored by the Local Environmental Expert
(PUB/MPWU).
200. No involuntary resettlement, no acquisition or leasing of land is needed; no interferences in
private land and properties are expected for the project.
201. There are no environmental risks or negative impact expected during the operation of the
system.
202. The balance between social and environmental risks and benefits is clearly positive. The project
will have a positive environmental, social, technical and financial impact, as described in detail in
above, e.g.:
- PUB can save up to AUD 500.000 per annum;
- Fuel, transport and emissions can be saved;
- New opportunities for professional training will be created;
- Creation of short term employment during construction work;
- Creation of new jobs in PUB (long-term impact);
- New opportunities for teaching and awareness rising;
- Added value by second use of the PV structures (meeting place, outdoor activities, shade, rainwater
harvesting, indoor climate improvement etc. …).
202. The EMP concludes that any adverse environmental or social impact can be managed and kept
within an acceptable level following the mitigating measures described above. No further detailed
study or Environmental Impact Assessment will be needed. The EMP needs to be revised and
actualized after defining the final project design. Provisions will be made in the Project Budget to
cover the environmental mitigation and monitoring costs.
203. The EMP contains the following recommendations regarding the implementation and operation of
the planed system:
In each PV plant structure should be equipped with a rainwater collection system. As this
equipment is not foreseen in the budget of the proposed project, we propose to create links with
another WB funded ongoing project dealing with water (KAP III) and to look for possible
synergies.
The procurement, implementation and commissioning process should be supervised permanently
on ground by a technical assistant (indicated in this document as PSE), who assures the
fulfillment of the requirements of the EMP under the profile of the International Environment
Management Expert (IEME).
Support for Operation and Maintenance will be provided during the first three years.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 56
It would be useful to include also staff from the Solar Energy Company Ltd. and from the Kiribati
Institute of Technology in the professional training, in order to exchange the existing expertise
and to contribute to a broader local capacity building. Maybe there are potentials for future
cooperation between the institutions that can be detected.
The waste and recycling management as described in the EMP should be planned and prepared
before the arrival of material and the start of civil works.
References
ADB (2006). Technical Assistance Consultant’s Report. Project Number: 38031.December 2006.
Mainstreaming Environmental Considerations in Economic and Development Planning Processes in
Selected Pacific Developing Member Countries. Climate Risk Profile for Kiribati.
ADB (2010). Road Rehabilitation Project (RRP KIR 44281). Initial Environmental Examination. August
2010.
Brander, R.W., Kench, P.S. and Hart, D. (2004). Spatial and temporal variations in wave
characteristics across a reef platform, Warraber Island, Torres Strait, Australia. Marine Geology, 207:
169-184. Stephenson, W. and Brander, R.W. (2004). Coastal geomorphology. Progress in Physical
Geography, 28 (4): 1-12.
Government of Kiribati (2004). Kiribati’s IWP, POPS, NBSAP-Add on and NBP Projects – Information
Paper Review of Kiribati Laws. Tarawa.
He, C., 2001. Assessment of the vulnerability of Bairiki and Bikenibeu, South Tarawa, Kiribati, to
accelerated sea-level rise. SOPAC Technical Report 322.
Kench, P.; Brander, R.; Parnell, K.; McLean, R. (2006). Wave energy gradients across a Maldivian
atoll: Implications for island geomorphology. Geomorphology, Vol. 81, Issues 1-2: 1-17.
Lovell, E. (2011). Environmental Impact Assessment Report for the ESAT Dredging Project. Suva, Fiji,
July 2011.
Rallu, J.L. (undated). Urban drift, urban growth, urban youth. UNFPA Suva.
The World Fact-book at https://www.cia.gov/library/publications/the-world-factbook/index.html (last
update 27.09.2011)
World Bank (2011). E2766 Kiribati Adaptation Programme – Phase III. Environmental Management
Plan. February 2011.
White, I. (2010). Tarawa Water Master Plan. Te ran – Groundwater. Kiribati Adaptation Programme –
Phase III. December 2010.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 57
Abbreviations
asl – above sea level
AUD – Australian Dollar
ECD – Environment and Conservation Division
EIA – Environmental Impact Assessment
EMP – Environmental Management Plan
GoK – Government of the Republic of Kiribati
KIT – Kiribati Institute of Technology
KOIL – Kiribati Oil Company Ltd.
kWp – Kilowatt Peak
MELAD – Ministry of Environment, Lands and Agricultural Development
METT - Ministry of Education, Training and Technology
MISA – Ministry of Internal and Social Affairs
MPWU – Ministry of Public Works and Utilities
MTC – Marine Training Centre
PUB – Public Utility Board
SEC – Solar Energy Company Ltd.
SOPAC - Pacific Islands Applied Geoscience Commission
US$ - US Dollar
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 58
ANNEXES
Annex 1 - Environment License Application form
Office Use only
GOVERNMENT OF KIRIBATI
MINISTRY OF ENVIRONMENT LANDS AND AGRICULTURAL DVELOPMENT
P.O. Box 234, Bikenibeu, Tarawa, Republic of Kiribati
Tel. No. (686) 28000/28425 Fax: (686) 28334
Email: [email protected]
Environment License Application Form
1. Contact Information
Name of applicant _______________________________________________________
(must be an individual person, corporation or government body)
Contact Address
_______________________________________________________________________
Telephone ____________ Mobile _____________ Fax ____________
Email: _________________________________________________________________
2 Background Information
Name of project (ESA)______________________________________________
Project No.
Date of receipt
RR number
Review date
Site visit date
Status
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 59
Type of project
(government/private/commercial) ___________________________________________
Location of the project ______________________________________________
(attach site plan if applicable)
Proposed implementation date ______________________________________________
3. Site description detailing the state of the environment
4 Project Description
Purpose of the project (attach supplement information if available) _______________________________________________________________________
Size of the project (design specifications to be provided if applicable) ________________________________________________________________________
Persons or contractors who will undertake the activity ____________________________
5. Specify activity/activities below if they are going to involve or be part of this proposed
Project.
Activities Tick below
Activities involving significant coastal and marine impact
extraction of aggregates, minerals, stones or shingles, sand, reef mud and beach
rock—
clearance of live corals, mangroves and sea grass
construction work below the high water mark
construction of seawalls
land reclamation
establishment of boat channels
dredging
Activities requiring significant materials
brick manufacture
land filling
Activities involving significant waste products
operation of waste disposal plants including recycling and collection systems
operation of drainage, disposal or sewerage systems
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 60
chemical treatment of timber
Other Activities – Refer to ESA
list
Specify if any
Activities using
significant natural
resources
Activities involving
harmful chemicals
Activities involving a
significant alteration of
the environment
I certify that the above information is true.
Signature ________________________
Name of person (providing information)_______________________
Date________________
Note: It is an offence under section 30 of the Environment Act 1999 to provide false or misleading information
Attach any other relevant information (in the form of Project document, Study report, etc.)
Lodgment Requirements/Conditions.
1. 1.For seawall and mining activities (sand and gravel, reef mud dredging), please
obtain license forms from Land Management Division(LMD) before applying for an
Environment License.
2. Application fee of $10.00
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 61
Annex 3 - Minutes of the Meeting 110926 schools
Date: 26 of September 2011, 10:15 am to 12:00 am
Location: Sacred Heart Secondary School, Bikenibeu, Tarawa
Assistants: Mr. KaureBabo,Project Officer of Ministry of Education ([email protected])
Mrs. Zita Lopez, Principle of Sacred Heart Secondary School (Host)
Mrs. RuutaTekeraoi, Deputy Principle of King George V Secondary School, ([email protected]), Bikenibeu
Mrs. KittieMangkia, Principle of Temaiku Primary School,Temaiku
Mr. Matteo Briganti, Team coordinator
Mr. Wolfgang Meike, Electrical engineer
Mr. Matt Fisk, Civil and Structural engineer
Mrs. Claudia Villalobos Montoya, Social and Environmental expert
Agenda:
1. Welcome and introduction (purpose of the meeting)
2. Institutional and personal introduction of assistants
3. Presentation of the purpose of the feasibility study and preliminary results
4. Presentation of plans for a possible implementation of a solar system into the building complex
5. Discussion and presentation of possible alternatives
6. Clarification of open questions from all parties
7. Feed-back: Expression of No-Objection to the proposed implementation
8. Outlook: How to go on, what will be needed?
9. Final statement and closure
Purpose of feasibility study:
Contracted by the World Bank and in cooperation with the Ministry of Public Works and Utilities of Kiribati, this team is carrying out a feasibility study for a future WB-funded project with the goal to install several solar energy systems in South Tarawa.
Purpose of the meeting:
- Inform all relevant parties about the possible project and the possible involvement of their
institutions
- Clarify doubts and exchange information
- Obtain the expression of No-Objection to the proposed measures from the responsible part
Results of the meeting:
- Clarification: The solar systems will feed the grid, not supply directly the school.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 62
- Plans for KGV School:
o Modules on the roof-top of 5 buildings
o Impact on indoor climate (cooling by air flow between modules and roof)
o Roof structure is OK, no need for modification
o Need of installation of inverters and cables
o Suggestion: Replacement of metal structure, because roof should carry the solar
modules during 25 years
o Roof will have the similar color, but probably not the same shape
o There is one gardener. We recommend keeping trees short in order not to shade the
modules.
o School will still pay the bills, but the solar systems help to keep price for energy low
(less fuel, the produced energy will be cheaper)
o Advantages for the school: modernized roofs (material) and knowledge about solar
energy, educational aspect (non-material)
o Cable Internet in offices
o Security fence, movement sensors, recommended
o Relative save surroundings, about 20 households, neighbors mostly GOK employed
- Temaiku Primary School:
o Use the roof of two buildings and the central free-standing structure
o A need of mwaneaba as meeting place
o Roof structure should be rainwater-proof and protected from downstairs
o 4m high roof, place for meetings and outdoor games
o Request: concrete floor under the roof
o Sloped roof, in the middle 4m, in the end 3m high
o 300 students + 10 teachers must fit under the rainproof roof
o Center area: 6x12m rainproof roof with concrete floor
o Kids should not climb at posts
o Cable internet in offices
o No save place, isolated, there is a need for more protection, security fence, security
lighting recommended
o In Temaiku, Solar energy will stabilize the grid, benefit for all residents of Temaiku
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 63
o Use the store room for inverters (18 in total), one wall in one room would be enough
o Conflictive neighbors, high unemployment rate, thefts of construction material
- Data of solar system in a computer (WIFI connection) for educational purposes
- Land leasing contract for KGV (Tameiku School is on a Government reclaimed area): addressed
by Government, no problem in case of increasing leasing rates would request by the owner for
land different use.1
Final comments:
- Mrs. Zita: nice project, hopefully the price of energy will decrease, energy is expensive
(80$/month/household). School has 2 panels for the water pump. School uses well water,
water quality is good; after 3 weeks it becomes brackish.
- Our Thanks to Mrs. Zita for being our host and offers the premises, food and drinks!!! Korabwa!
- Mr. Kauri: It’s a good start. No objection to proposed actions.
- Mrs. Ruuta: No comments, no objection to actions.
- Mrs. Kittie: She agrees; no objection to proposed actions.
This Protocol has been elaborated by:
Claudia Villalobos Montoya, 26.09.11
1 This was mentioned because of the possibility that the owner would require to re-arrange the leasing rate. This possibility is not realistic at the moment.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 64
Annex 4 - Minutes of the Meeting 110928 KIT
Date: 28 of September 2011, 11:00 am to 12:30 am
Location: Kiribati Institute of Technology, Betio, Tarawa
Assistants: Mrs. AkkaRimau, Ministry of Labor ([email protected])
Mr. Antoine Barnaart, Principal of KIT ([email protected])
Mr. RokobatiTearo, Deputy Principal of KIT ([email protected])
Mr. Philip Hutchinson, Lecturer of KIT ([email protected])
Mr. Philip Brooks, Facilities Manager of KIT ([email protected])
Mrs. Miriam Tikana, Assistant Energy Planner of Ministry for Public Works and Utilities ([email protected])
Mr. Kiriati Birita, Power Engineering Manager, Public Utility Board ([email protected])
Mr. Matteo Briganti, Team coordinator ([email protected])
Mr. Wolfgang Meike, Electrical engineer ([email protected])
Mr. Matt Fisk, Civil and Structural engineer ([email protected])
Mrs. Claudia Villalobos Montoya, Social and Environmental expert
Agenda:
10. Welcome and introduction (purpose of the meeting)
11. Institutional and personal introduction of assistants
12. Presentation of the purpose of the feasibility study and preliminary results
13. Presentation of plans for a possible implementation of a solar system into the building complex
14. Discussion and presentation of possible alternatives
15. Clarification of open questions from all parties
16. Feed-back: Expression of No-Objection to the proposed implementation
17. Outlook: How to go on, what will be needed?
18. Final statement and closure
Purpose of feasibility study:
Contracted by the World Bank and in cooperation with the Ministry of Public Works and Utilities of
Kiribati, this team is carrying out a feasibility study for a future WB-funded project with the goal to install several solar energy systems in South Tarawa.
Purpose of the meeting:
- Inform all relevant parties about the possible project and the possible involvement of their
institutions
- Clarify doubts and exchange information
- Obtain the expression of No-Objection to the proposed measures from the responsible part
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 65
Results of the meeting:
- Presentation of the proposed design (solar modules on top of the roof)
- Search for additional space for installation
- Criteria for selection:
o Ownership of land
o Electrical power limit 300 kW/installation
o Available surface on roofs, orientation of roof
- Training possibilities for KIT on demonstration site
- New buildings are planned
- Introduction of PV in Kiribati, feeding the grid in a second step
- Next step: WB will have the tender at 3rdquarter 2012
- Represent best practice: visibility of the operating, training opportunities, teaching unit
- Request: a small wind turbine (200W) could be included in the project?
- No weather station at KIT
- Fit the design of the new buildings with the requirements of the solar installation
- Request: Backup system for PCs, sewage pumps
- 100 kW power are expected to be installed in KIT
- 4 units on the existing building roof (73kWp)
- 2nd installation of 30kWp to be introduced in the new building roof, to fit with the master plan
- Presentation of proposed design
- More class rooms, more student capacity, raised to 500 (actual 340)
- Master plan: extension on the technology block, 4 new class room buildings and a mwaneaba,
funded by AusAid, Start October 2012
- Matt will calculate the capacity of the 4 class room buildings
- Move planned capacity from Sports Centre to KIT?
- KIT wants a traditional mwaneaba, no installation is possible
- Roof in additional space with a gym under it? Height 10m
- Installation on new building roofs will be suitable
- No plans for additional independent solar systems
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 66
- KIT is at the end of the energy supply grid, an additional transformer is planned, change internal
installation to bring it to Australian standard
- Impact of solar roof on indoor climate, cooling, preference to teaching buildings
Final comments:
- To prepare a report for next week, present as preferred option the installation on the new
building roofs
- “We are excited.” No objection to proposed project.
- Thanks to our host
This protocol has been elaborated by:
Claudia Villalobos Montoya, 28.09.11
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 67
Annex 5 - Minutes of the Meeting 110928 Sports Complex
Date: 28 of September 2011, 9:00 am to 10:30 am
Location: Sports Centre, Betio, Tarawa
Assistants: Mr. DepwehKanono, Secretary of Ministry of Internal and Social Affairs ([email protected])
Mr. Kautu Temakei, Program Manager of the Sports Program (Kiribati Community Club) ([email protected])
Mr. Bokai Kaitu, BCC Coordinator ([email protected])
Mr. Willy Uan, Sports Development Officer ([email protected])
Mrs. Miriam Tikana, Assistant Energy Planner of Ministry for Public Works and Utilities ([email protected])
Mr. Kiriati Birita, Power Engineering Manager, Public Utility Board ([email protected])
Mr. Matteo Briganti, Team coordinator ([email protected])
Mr. Wolfgang Meike, Electrical engineer ([email protected])
Mr. Matt Fisk, Civil and Structural engineer ([email protected])
Mrs. Claudia Villalobos Montoya, Social and Environmental expert ([email protected])
Agenda:
19. Welcome and introduction (purpose of the meeting)
20. Institutional and personal introduction of assistants
21. Presentation of the purpose of the feasibility study and preliminary results
22. Presentation of plans for a possible implementation of a solar system into the building complex
23. Discussion and presentation of possible alternatives
24. Clarification of open questions from all parties
25. Feed-back: Expression of No-Objection to the proposed implementation
26. Outlook: How to go on, what will be needed?
27. Final statement and closure
Purpose of feasibility study:
Contracted by the World Bank and in cooperation with the Ministry of Public Works and Utilities of Kiribati, this team is carrying out a feasibility study for a future WB-funded project with the goal to install several solar energy systems in South Tarawa.
Purpose of the meeting:
- Inform all relevant parties about the possible project and the possible involvement of their
institutions
- Clarify doubts and exchange information
- Obtain the expression of No-Objection to the proposed measures from the responsible part
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 68
Results of the meeting:
- Presentation of the idea related to the Sports complex (roof-top installation and 2 free-standing
installations at east and west side)
- Roof-top installation was accepted
- Proposal: to put more panels on the side wings of the roof
- An extension of the side wing over the parking area is not possible as it would reduce the
number of parking places
- West-side pergola: in this area, new office buildings are planned, but not as large in surface as
the proposed pergola
- East-side pergola: in this area, a new building complex is planned, with meeting rooms and
dormitories for the soccer federation and meeting places for the Kiribati National Olympic
Committee.
- Request: to put a roof under the solar panels in order to collect rainwater and to build the
needed rooms and assembly space under the solar roof, combining both projects
- A slightly sloped (5-10°) roof structure for the panels was presented and were well accepted.
- There are problems of security (vandalism, thefts); therefore, the Management of the Sport
Complex will hire a Security company for 24h.
- Recommendation: security fence
- Request: Build a high structure that solar panels are not visible from outside the court (no
target for stones)
Final comments:
- The new design options will be presented at the next meeting at 05.10.11
- No objections to the proposed project
This Protocol has been elaborated by:
Claudia Villalobos Montoya, 28.09.11 (reconstructed version)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 69
Annex 6 - Minutes of the Meeting 110928 Hospital
Date: 28 of September 2011, 2:15 pm to 3:30 pm
Location: Tungaru Central Hospital, Nawerewere, Tarawa
Assistants: Mr. RiwataObetaia, DS ([email protected])
Mrs. Agnes Yeeting, SAS ([email protected])
Dr. TuriaTekaai, AgDHS ([email protected])
Mrs. Miriam Tikana, Assistant Energy Planner of Ministry for Public Works and Utilities ([email protected])
Mr. Kiriati Birita, Power Engineering Manager, Public Utility Board ([email protected])
Mr. Matteo Briganti, Team coordinator ([email protected])
Mr. Wolfgang Meike, Electrical engineer ([email protected])
Mr. Matt Fisk, Civil and Structural engineer ([email protected])
Mrs. Claudia Villalobos Montoya, Social and Environmental expert ([email protected])
Agenda:
28. Welcome and introduction (purpose of the meeting)
29. Institutional and personal introduction of assistants
30. Presentation of the purpose of the feasibility study and preliminary results
31. Presentation of plans for a possible implementation of a solar system into the building complex
32. Discussion and presentation of possible alternatives
33. Clarification of open questions from all parties
34. Feed-back: Expression of No-Objection to the proposed implementation
35. Outlook: How to go on, what will be needed?
36. Final statement and closure
Purpose of feasibility study:
Contracted by the World Bank and in cooperation with the Ministry of Public Works and Utilities of Kiribati, this team is carrying out a feasibility study for a future WB-funded project with the goal to install several solar energy systems in South Tarawa.
Purpose of the meeting:
- Inform all relevant parties about the possible project and the possible involvement of their
institutions
- Clarify doubts and exchange information
- Obtain the expression of No-Objection to the proposed measures from the responsible part
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 70
Results of the meeting:
- Added value of solar installation, benefits for all inhabitants of South Tarawa (y saving fuel the
energy prices can be kept stable, makes the energy grid more stable), but there is no direct
influence on the energy bills of the Hospital
- Selection of sites:
o Orientation of roofs, surface
- Except one building, they have no problem of water leaking
- Roofs of ten buildings were selected. Recommend to replace the roof as it is 20 years old and is
must last almost 25 years longer
- Roofs are used for rainwater collection. Quality and quantity of rain water will not decrease
through the solar system.
- Some roofs are rusty, in the future there will be to be replaced
- Maintenance for the roof is funded? For the first years, the new roof will not need so much
maintenance. Panels will protect roof structure from climate impact
- The replacement of the roof will be part of the project and the implementing company will do
it.
- Maintenance of the Solar Panels by PUB
- Roof will be of a good material in order to last
- Inverters with display, propose to put them on an external wall, 3 inverters and a meter at each
building.
- Better to protect inverters from vandalism, or put them inside any store room.
- Fenced cage around it, in order to avoid damage.
- Solar energy will not supply the hospital, it will feed the grid in order to save diesel
- In a future next step, solar energy can be installed and the producer itself could feed into the
grid
- Advantage for the hospital: backup for the hospital to save diesel from the backup generator.
- How long will last the construction in order to replace patients?
- The hospital beds are always full (30 beds per building)
- Hospital should work out an evacuation plan
- Implementer should provide provisional shelter (tent?)
- Selected buildings include sensitive areas (operating theatre, emergency unit)
- How to organize the construction:
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 71
- A big mwaneaba, part of the hospital, can be used to evacuate patients, capacity for 30 beds
and power supply available
- Work at night, week-ends, half roof…
- Construction work will start in October/November 2012
- Bring in temporary facilities, there is an open space (extended ward area)
- Two or three days buildings should be unoccupied, about one week per house (rolling shifts:
mayor work, minor work, solar installation, wiring)
- Some buildings are only used during working hours and at daytime, at night and at week-ends
they are unoccupied
- The 6 at bottom line are with beds, 24h occupied
- Noise from the construction work will have to be addressed
- The system will not directly influence in the energy bills, but it helps to keep all the bills low
- Further discussion with the secretary from the Ministry needed
Final comments:
- No objection to proposed project
- The design of the project will be presented and described in the report
- Comment of Mr. Riwata:
(a) In general MHMS sees the proposal as good however further discussions of the proposal with our Secretary and rest of Senior Management team will be made with our feedbacks conveyed to your team and MPWU, who is coordinating the proposed project.
(b) A meeting next week at MPWU may involve us being invited to share our final views and concerns (if any).
This Protocol has been elaborated by:
Claudia Villalobos Montoya, 28.09.11
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 72
Annex 7 - Minutes of the Meeting Preliminary Report Presentation - 11102011
Date: 5th of October 2011, 10:15 am to 12:30 pm
Location: Ministry of Public Works and Utilities MPWU, Betio, Tarawa
Assistants: Mrs. Matereta Raiman, Secretary of the Ministry of Public Works and Utilities
Mrs. Bintonga Even, Deputy Secretary of the Ministry of Public Works and Utilities ([email protected])
Mr. Rota Onorio, General Secretary, Kiribati National Olympic Committee ([email protected])
Mr. Erta Metai, Ministry of Works ([email protected])
Mr. Antoine Barnaart, Principal of Kiribati Institute of Technology ([email protected])
Mr. Philip Brooks, Facility Manager of KIT ([email protected])
Mr. Rokoboti Tearo, Deputy Principal of KIT ([email protected])
Mr. Kiriati Birita, Power Engineering Manager, Public Utility Board PUB ([email protected])
Mr. Kautu Temakei, Program Manager, Kiribati Community Sport Clubs Program, MISA
Mr. Kevin Rouatu, CEO of PUB ([email protected])
Mr. Kaure Babo, Project Officer, Ministry of Education ([email protected])
Mr. Willy Uan, Sport Development Officer, MISA ([email protected])
Mrs. Agnes Yeeting, SAS, MHMS ([email protected])
Mrs. Miriam Tikana, Energy Planning Unit, MPWU ([email protected])
Mr. Matteo Briganti, Team coordinator
Mr. Wolfgang Meike, Electrical engineer
Mrs. Claudia Villalobos Montoya, Social and Environmental expert
Agenda:
37. Welcome and introduction
38. Presentation of the preliminary findings of the feasibility study
39. Discussion of findings, questions
40. Closure
Purpose of the meeting:
- Inform all relevant parties about the preliminary findings of the feasibility study
- Clarify doubts and collect comments
Results of the meeting:
- Welcome by Mrs. Matereta Raiman, Secretary of MPWU
- Introduction by Mr. Matteo Briganti
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 73
Wolfgang Meike: Electrical considerations (for details see presentation)
- When the grid is off, the PV plant is off, too
- The maximum of PV power that will not interfere in the stability of the actual grid is 800 kW AC
- Response time of the operator is lower than the response time of the PV system when clouds
are passing,
- Max. 900kWp; 300kWp installed in one geographic area
- In order to increase the capacity of the PV system further, additional technical adjustments are
needed (not part of our project)
- Question (Q): How could more PV power be introduced in the grid?
- Answer (A): It is technically possible, but it needs further investment and technical adjustment,
which are not part of our project. The project is a first step towards grid-connected PV systems,
to be increased in next steps in the future.
- Q: How to improve the communication between the two power stations?
- A: We propose to introduce monitor screens to see what’s happening, see the total load, there
would be no need to talk, just to see from both sides.
- Q: From where are the fuel savings coming?
- A: It’s a simulation tool for all 4 generators, without PV, only improving the efficiency of the
generators.
- Q: Old generators and new PV systems. The cost of fuel will be the same?
- A: Solar will decrease the fuel consumption, it gives “energy for free”. The generators will need
more and more fuel when they get old, there are overhauls needed. As longer you leave the
services, the more fuel is needed. Also black outs, independently from the solar, can occur.
With the solar plant, 2 generators will run fewer hours, but not so much less.
- Q: Replacement of diesel generators is foreseen in the project?
- A: We will not supply new generators, only the PV plant forms part of the project.
- Q: If there would be an additional generator, will it interfere with the PV-plant?
- A: There more load you have, there more PV you can connect to the grid. If load goes up, you
will have no problems with PV.
- Q: What about wind energy?
- A: The wind profile of Tarawa is not brilliant, it can be done, but not very efficient, we have not
made the calculations. Offshore turbines would bring environmental issues.
- Q: The wind speed in Tarawa is 4m/s. Is it enough for a small wind turbine?
- A: small wind turbines start at 2-3m/s. But commercial turbines run at 3,5 m/s.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 74
It’s a problem of trees, space, maintenance, but we have not done a detailed feasibility study
on wind energy.
- Q: If later would come another source of energy, cost efficient of other new sources?
- A: WB will only finance the solar plant, but not additional technical investment. I can
recommend you some measures, make some estimation for you.
- Q: Training for staff will be needed; will it be included in the project?
- A: Yes, training for staff is foreseen.
- Q: I am very interested in wind energy.
- A: We will not make a feasibility study for wind.
Matteo Briganti: Equipment, civil works, financial data (for details see presentation)
- Max. capacity of 900 kWp in normal conditions
- About 300 kW AC (340kWp) for one site
- Technical and financial constraints (the proposed design is made for the maximum of power),
WB will decide about the implementation of the project or possible modifications, adjustments.
- Selection of PV sites and criteria of selection
- Meteorological data
- PV component selection: small size inverter for flexible design and easy maintenance, sealed for
marine environment, regional technical support available, previous experiences in the Pacific
region; PV modules compatible with inverters, PV Basic Unit (approx. 25m x8m)
- Betio Sports Centre: 20 basic units
- Temaiku Primary School: 8 basic units
- Tungaru Central Hospital: 9 basic units roof-top, recommended replacement of tin roof cover
- KIT: 6 PV units roof-top
- King George V Secondary School: 6 basic units roof-top, recommend the replacement of the tin
roof cover
- Total: 49 basic units, 903kWp, 147 inverters
- Project costing: Total costing 11,77 Mio. AUD (57% of civil works, 30% PV generator, it is a
preliminary cost which will need to be revised in the next step.
- Current diesel generation cost: 0.52 AUD/kWh
- Saved fuel 396,312 l/yr, saved 503,316 AUD/yr, that can be used for cover the gap between cost
of produced and sold kWh (0,40 AUD/kWh)
- Leveled electricity cost (LEC) to be provided in a next step
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 75
Q: Total cost per installed kWp PV?
A: It is quite high, about 13 AUD/Wp. We made a special design for the structure, the remoteness of the island and other factors. But, still, we need to get back on the preliminary cost and double-check them once back to the office.
Q: I know from my experience that the cost in other projects is about 4AUD/Wp.
A: The total cost includes also the ground mounted structure, civil work for it, which is, quite expensive; the PV only would cost about 3 AUD/Wp.
Constraints for the project: space, financing, stability of the grid. Space was the main constraint, complicate to find places (good orientation, no shadow, Gov. owned land, big surfaces).
PV is expensive, but there are additional benefits. It’s a proposal, WB will decide if they are modifications needed.
Q: What are the expected costs for operation?
A: All the savings are diesel fuel. We cannot save at this stage running hours, oil, or maintenance of
the generators. This would be possible with further technical adjustments.
Q: Average wind speed is 8m/s.
A: Uncertain at what height the wind speed was measured. One event in the last 100 years (peak of 32m/s). Wind turbines will bring more instability into the grid. On the causeway would be the location for wind power, not between the houses. Good equipment needed for harsh climate, environmental issues expected.
Q: Maintenance requirements of the solar panels?
A: If it rains often, the rain will wash the dust away. The slight slope of the structure makes that the rain washes away the dust. There is no air pollution (sticky dust), here is fairly clean air. During periods of drought, you have to wash the panels twice the year. But even unwashed they will not lose
very much efficiency.
Q: No solar energy can be stored?
A: No, there is no storage system (batteries) foreseen, it feeds directly into the grid. In a stand-alone system there is a battery included, in the grid connected system not.
Claudia Villalobos: Environmental and social aspects (for details see presentation)
Q: Solar energy should be included in the awareness raising program.
Q. Is there a possibility of private users to have a grid connected solar system?
A: The savings would be only for the consumer. PUB would save diesel, but PUB is only paid for the consumed kWp, not for its infrastructure. If the customer would produce enough PV energy for its demand, PUB will not get paid for the infrastructure (wires), even if the customer uses the PUB grid.
Fixed costs should be included in the monthly bill, not only variable costs (consumed kWh). If the
solar power is paid at the same rate as grid power (1-1 rate), it is technically easy to calculate the balance with one energy meter going fore-and backwards. There is a more detailed study of impact of private PV-system feeding the grid needed.
A rules and laws set is requested to be analyzed, discussed and introduced by the GOK in order to promote and regulate the private solar PV home system connected to the grid for distributing generation.
Q: What’s about warranties of the PV plant?
A: Most of solar panels come from the supplier with 20-25 years warranty, the inverters come with 1-2 years warranty, the structure’s warranty depends on the contractor. Almost two years will be foreseen in the contractual agreements.
Q: What would be the correct rate?
A: It should be calculated.
Q: Can the panels contaminate the harvested rainwater?
A: No. The surface is made of glass, the panel inside is sealed, it is totally safe.
Q: We have a big problem with water. Rainwater tanks will be included in the project?
A: No. But just know a new WB funded project has started in Kiribati dealing with water problems (KAP III). Maybe it is possible to link both projects and to look for synergies with the KAP III project.
Q: Traditional maneabas look very different from your proposed structures, the new structure is not traditional.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 76
A: This was a big concern of the team. The steep slope of the maneaba is not suitable for PV. We
proposed this structure as a compromise, in order to provide a roof for shading, a place for meetings, but suitable for the PV-system. The compromise was accepted be the local stakeholders. Maybe, we should not call it “maneaba” in order to not cause confusion, but name it “Multi purpose complex” (proposal of Kevin) instead of maneaba.
Q: You should include in the project education tools for kids to respect the PV structure as it would be a maneaba.
Q: No gravel and no sand will be used for the civil works?
A: For the ground of the central part of the free standing structure at Temaiku School will be used concrete. In all other places, prefabricated concrete from abroad will be used, no gravel and no sand. Materials will come from over-seas. The local ground is good, it will be opened for the works, after the material will be refilled in the ground and the concrete blocks will be put on top. No need for local material.
Q: The PV plant will be a good opportunity for capacity building, for professional training, for monitoring.
A: It would be a good opportunity for cooperation between involved institutions and organizations.
Q: Speaking about the space constraint, have you considered Temaiku area for the installation of the PV plant?
A: Yes, it was supposed to be the main area when the study has started. But, as we learnt that the whole area should be lifted up, WB refused this option due to the environmental impact. The civil cost
would be very high, and we would take away future land for other purposes.
Q: There are possibilities for upgrade the IT-system of PUB?
A: Not through this WB project.
Q: Electronic mapping of the network?
A: No.
Q: What about the replacement of the equipment?
A: In case that panels will be destroyed (e.g. by vandalism), they must be replaced. We have chosen
small inverters that are easy to replace. The inverters should be protected from vandalism, but also for the security of persons. They will be surrounded by cages.
Q: In case MISA would have plans for new buildings or double-stored buildings for get more beds, what will happen with the PV-plant?
A: It would be the responsibility of the Ministry. If there would be concrete plans now, we would take this building out of our plans.
Q: The Betio Sports Complex is the only space for sports; we have to be careful using the space. Can be a gym installed under the new roof?
A: Offices are foreseen to be installed under the roof, a gym would also fit, it has a normal roof. The lowest point is 4m, the highest point 6m. You can build walls and ceiling inside as in any normal building.
Q: There is a special need for safety of the PV panels in the Betio Sports Complex?
A: Dropping soccer or tennis balls cannot break the panels. Thrown stones can break them.
If somebody wants to destroy the plant, he will find a way to do. There is no absolute security possible.
Closure of the meeting by Mrs. Matereta Raiman, Secretary of MPWU.
Thanks MPWU to be the host of the meeting.
Thanks to all participants to take your time to come and to have a very fruitful exchange.
All participants will receive a copy of this MoM protocol and a copy of the PowerPoint- presentation by Email.
We are looking forward to cooperate with you again!
Korabwa, tiabo ao tekeraoi!
This Protocol has been elaborated by Claudia Villalobos Montoya, 5th of October, 2011
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 77
Annex 8: Environmental Management Plan (EMP)
Note: The mitigation measures should be revised and actualized after final project design.
Environmental Issue & Objective Mitigation Measures Locations Timeframe Estimated
Costs
Implementer(
s)
Supervisor(s)
DESIGN / PRECONSTRUCTION PHASE
Protection of Sensitive and Ecologically Important Areas
To minimize negative impacts on sensitive ecosystems, or the natural
environment.
Identify environmentally sensitive or ecologically fragile areas (if any);
Ensure construction personnel is aware of locations and
importance of the sensitive areas and avoid disturbing
them;
If the proposed construction is located close to these areas, take necessary measures to
avoid/minimize disturbance.
In all implementation sites and surroundings
During project preparation and design.
Minimal (part of standard design practices).
PUB, Contractor (Site Engineer [SE], Project
Supervising Engineering
[PSE] (International Environment Management Expert)
MPWU, and World Bank
Environmentally Sound Design
To have a positive environmental
impact and not to cause or increase environmental problems on the island.
Panels and other equipment procured for the project shall be made with non-toxic materials;
No use of gravel or sand from the beaches, avoiding coral mining;
Consider alternatives for construction materials;
Environment-friendly structural design for support structure,
that requires less maintenance
Predominantly use of wood as material for support structures
Enable rainwater harvesting (use synergy with KAP III)
Selection of material suppliers in
In all implementation sites and
surroundings
During project preparation
and design.
Within contract documents.
Minimal (part of standard
design
practices).
PUB, Contractor (Site Engineer
[SE],
Project Supervising Engineering [PSE] (International Environment
Management Expert)
MPWU, and World Bank
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 78
order to shorten transport ways and minimize transport needs
Choice of the location that gives
the best economy in terms of excavation and fill
Cultural Heritage
To protect and preserve cultural,
historical and religious sites
To ensure project staff respect local culture and custom
If cultural/historical heritage site is identified during the construction, the Contractor will be asked to stop
work immediately and notify the PSC who will inform the relevant Government agencies.
Arrange briefing with MPWU/Local
Environmental Expert [LEE]
In all implementation sites and
surroundings
During project preparation
and design.
Mobilisation
Minimal (part of standard
design practices).
No
incremental cost
PUB, Contractor (Site Engineer
[SE], Project Supervising Engineering [PSE] (International
Environment
Management Expert) Local
Environmental Expert [LEE]
MPWU, and World Bank
Environmental Issue & Objective Mitigation Measures Locations Timeframe Estimated Costs
Implementer(s)
Supervisor(s)
CONSTRUCTION PHASE
Social or Community Concerns
To minimize social disturbance and maximize community benefits from the project.
Inform local neighborhood community before construction activities start about planned
civil work show they could be affected by them;
Avoid or minimize disturbances by construction activities in near living areas, e.g. avoiding works
In all implementati
on sites and surroundings
During whole construction work.
Minimal (part of standard
design practices).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World
Bank and Project
Supervising Engineering [PSE]
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 79
at nighttime, minimizing transports of material, noise control;
Apply adequate waste management and avoid run-off of waste, e.g. littering off
packaging material; Offer employment and training
opportunities for local people. The general practice is that
Contractors employ workers from the communities. The clan leaders (unimwane) will be consulted when recruiting workers for the Contractors;
Include women and other
community groups in project
activities whenever there is any opportunity.
Inform local neighborhood and community about mechanism for registering comments, suggestions or grievances
(International Environment Management
Expert)
Patient safety and hospital operations
If it is not practical to safely relocate patients from the
operating theatre at the Tungaru Central Hospital for the duration of construction, the PSE shall
find an alternative site or sites to install the panels, within the existing project area, and with all of the necessary approvals.
Tungaru Central
Hospital
During construction
phase
Moderate, but unlikely
(to be determined if required)
PSE PUB, World Bank
Public Safety
To avoid accidents and meet safety
requirements
Mark construction impact areas with comprehensive and visible signs (pictograms, Gilbertese
and English language) indicating danger and no-go areas
During whole construction
work.
Minimal (part of standard
design practices).
Contractor (Site Engineer [SE], support
from LEE for adaptation and translation to local
language).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 80
Soil Erosion
To ensure that impacts of surface
erosion are temporary and minimized to acceptable level.
Minimize work areas; Keep vegetation clearing at the
necessary minimum;
Keep vehicles on defined tracks; Construct the necessary
temporary/permanent control
structures; Encourage re-vegetation as soon
as the construction activities finish, or plan to immediately
rehabilitate the disturbed sites after use.
In all implementation sites and
surroundings
During whole construction work.
Minimal (part of standard
design practices).
Contractor (Site Engineer [SE])
PUB (Local Environmental Expert), World
Bank and Project Supervising
Engineering [PSE] (International Environment
Management Expert)
Controlling Sediment
To ensure that the impacts are temporary and minimized to acceptable levels.
Installing silt traps or other
control structures at the outset of the construction;
Installing silt traps or other control structures at the outset of the construction
Preparing all disturbed areas for re-vegetation or for natural re-
vegetation if requested; Phasing and limiting ground
disturbance to areas of a workable size;
Scheduling construction to limit
disturbance of large areas of soil during wet seasons;
Avoid discharging of contaminated water to the lagoon.
In all
implementation sites and
surroundings
During whole
construction work.
Minimal
(part of standard
design practices).
Contractor
(Site Engineer [SE])
PUB (Local
Environmental Expert), World
Bank and Project Supervising Engineering [PSE]
(International Environment Management Expert)
Controlling Storm Water
To minimize the impact of
contaminated run-off water to acceptable levels.
Pass storm water run-off from
construction areas through rocks or hay traps to remove soil and petroleum-based organic pollutants before disposal;
Store oil and bituminous products at a contained location away from drainage ditches.
In all
implementation sites and surroundings
During whole
construction work.
Minimal
(part of standard design
practices).
Contractor
(Site Engineer [SE],
PUB (Local
Environmental Expert), World Bank and Project
Supervising Engineering [PSE]
(International Environment
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 81
Management Expert)
Management of Stockpiles and Spoil-heaps
To minimize dust and sediment run-off.
Discuss dumping locations with the government officials and/or local landowners including plans
for future use of the spoil materials;
Include all drainage provisions suggested for construction sites in the site plans;
Choose the locations of waste spoil piles to avoid blocking surface run-off or drainage
ditches; Cover all spoil heaps or
stockpiles during rainy season to prevent erosion and sediment run-off.
In all implementation sites and
surroundings
During whole construction work.
Minimal (part of standard
design practices).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World
Bank and Project
Supervising Engineering [PSE] (International Environment Management
Expert)
Air Quality and Dust Control
To avoid and to control unnecessary dust nuisance.
Spray water on spoil-heaps if there are dust generating materials accumulated during dry periods especially near schools, hospitals, etc.;
Cover all dust generating loads carried in open trucks.
In all implementation sites and surroundings
During whole construction work.
Minimal (part of standard design practices).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World Bank and Project Supervising Engineering
[PSE] (International Environment Management Expert)
Noise Control
To minimize noise during construction works.
Use modern and well-maintained equipment (with mufflers where appropriate);
Use noise screens or mounds
near residential areas, when
appropriate; Carry out noise construction
activities and transports during normal working hours, never at
In all implementation sites and
surroundings
During whole construction work.
Minimal (part of standard
design practices).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World Bank and
Project
Supervising Engineering [PSE] (International
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 82
night time; Advise schools, hospitals,
churches, etc., when there will
be unusual or unavoidable noise.
Environment Management Expert)
Aggregate Management
To minimize potential environmental impact.
Avoid overloading trucks and cover trucks to minimize dust
and loss of load from trucks during transportation;
Use water sprays or covered chutes to reduce dust emission during loading and unloading of materials from barges;
Maintain crushing and mixing plants in good working condition
so as to reduce emission from the plant;
As far as possible, plan truck trips during low traffic hours;
Implement safety procedures during transport to reduce the potential for road accidents in
village or urban areas.
In all implementati
on sites and surroundings
During whole construction
work.
Minimal (part of
standard design
practices).
Contractor (Site Engineer
[SE],
PUB (Local Environmental
Expert), World Bank and
Project Supervising Engineering [PSE] (International Environment
Management Expert)
Offsite and Waste Management
To avoid contamination from solid wastes and sewage
To minimize the environmental impact of its work by adopting respectful waste management behavior and fulfilling national norms and regulations.
Store wastes with respect for health and environment
Support, when practical, recycling of waste;
Contain all stored wastes within construction sites, avoid littering and runoff;
Use recycled or renewable building materials (e.g. timber) where possible;
Optimize and reduce waste production. Avoid mix of different waste and minimize waste disposal into the landfill;
Not produce hazardous waste; Sort waste according to its type
and origin. Store selected
materials in safe place in order to avoid contamination,
In all implementation sites and
surroundings
During whole construction work.
Minimal (part of standard
design
practices).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World Bank and
Project Supervising Engineering [PSE] (International Environment
Management Expert)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 83
especially if they will be shipped out for recycling;
Encourage the recycling of
waste. Follow the hierarchy: Prefer local recycling or reuse before shipping out for recycling
before waste disposal in the landfill;
Properly dispose of all used fuel and lubricant oils in
environmentally sound manner, either by recycling or for other use such as fuel for hot mix plant, etc.;
Crush, burn, and bury all
inorganic solid waste in an approved solid waste disposal
area;
After construction has finished, remove all disabled machinery and waste from the project area;
Utilize, if available, public toilets at construction sites;
Compost all green or organic wastes or use as animal food.
Safety and Health
To minimize occupational health and
safety risks of construction works.
To raise general health and safety
awareness.
Ensure all occupational health and safety requirements are in place on construction sites;
Understand the use of personal protection equipment (PPE) and make sure that it is used properly;
Install lights and cautionary signs in hazardous areas;
Ensure safety and inspection procedures;
Safe handling of toxic materials and other hazardous substances;
In all implementation sites and
surroundings
During whole construction work.
Minimal (part of standard
design practices).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World
Bank and Project Supervising Engineering
[PSE] (International
Environment Management Expert)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 84
Implement a system of penalties for violation of rules and regulations
Introduction to health and safety issues in construction sites by the Contractor;
Education on basic hygienic practices to minimize spread of tropical diseases, including information on methods of
transmission and protection measures for sexually transmitted diseases;
Prohibition of drugs, kava and alcohol on construction sites;
Assure availability of medical
assistance in emergency or non-
emergency situations and availability of other health-related assistance
Site De-commissioning
To minimize ongoing impacts after construction is completed.
Assure all waste and remaining
material for recycling has been removed from the construction site;
Rake or loosen all compacted ground surfaces;
If necessary, implement revegetation / rehabilitation of
the construction sites involving, where possible, local women’s and community groups.
In all
implementation sites and surroundings
After
construction work is completed.
Minimal
(part of standard design practices).
Contractor
(Site Engineer [SE],
PUB (Local
Environmental Expert), World Bank and Project Supervising
Engineering [PSE]
(International Environment Management Expert)
Environmental Issue & Objective Mitigation Measures Locations Timeframe Estimated Costs
Implementer(s)
Supervisor(s)
OPERATION PHASE
Safety Inhibit unauthorized access to
the PV modules on roof-top or at In all implementati
During whole operation
Minimal (part of
PUB, during the first three
MPUW-, and World Bank
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 85
To avoid accidents, damaging or unauthorized removal of the technical
equipment. To meet safety requirements.
the free-standing structures by construction design and eventually necessary technical
protection measures (fences, gates, locks);
Cover inverters with a locked
metal cage firmly attached to the wall in order to avoid unauthorized manipulation (especially by playing children
with the risk of accidents) or theft;
Mark sites with comprehensive and visible signs (pictograms) indicating danger and no-go-areas;
Put the wiring underground in
order to avoid accidents and damage (accidentally or intentioned by vandalism);
Advice to the public institutions where the PV installations are implemented about special risks
and security needs (security fence, safeguard at nighttime);
Inform the administration of the
public institutions where the PV installations are implemented that they should report immediately to the PUB any case
of damage of any component of the PV system.
on sites time of the system (20 years).
standard design practices).
years supported by Post
Commissioning Services Contracted
Company.
(during the first two years)
Maintenance and repairs
To ensure the correct and efficient operation of the system.
To avoid technical failures and accidents.
To avoid impacts on the quality of
Under normal climate conditions with regular rainfall, the slope of
the installation will enable the self-cleaning of PV modules by
rinsing rainwater. During droughts, the dust of the panels should be removed twice a year. The cleaning can be made easily with a hose pipe;
PV modules and equipment shall
In all implementati
on sites
During whole operation
time of the system (20
years).
Minimal (part of
standard design
practices).
PUB, during the first three
years supported by
Post Commissioning Services Contracted Company.
MPUW-, and World Bank
(during the first two years)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 86
drinking water.
be maintained so that there is no risk to drinking water collected from the roof and panels.
Adjacent trees or shrubs should be trimmed in order to avoid shading over the panels or
damage by falling fruits (especially coconuts);
Wiring should be revised once a year in order to make sure that
there is no damage (e.g. rotten cables). This activity should be carried out by authorized PUB staff only;
Inverters should be revised once a year to assure their perfect
operation (replacement of rusted
components). This activity should be carried out by authorized PUB staff only;
Security measures should be revised once a year (e.g. replacement of rusty locks,
closing of fence holes); The state of all installations
should be revised by PUB staff
after special climate events, as heavy rainfalls, storms or floods in order to detect damages on the support construction or on
the PV installation itself; The institution where the PV
installation is installed should immediately report any damage on the structure to the PUB Staff in order to assure repairs or
replacement of damaged
components; All repairs or manipulation of the
PV system should be carried out exclusively by authorized staff of PUB that previously has got
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 87
instructions and training.
Annex 9: Environmental Monitoring Plan
Note: The estimated costs should be revised and actualized after final project design.
Environmental Issue & Objective Ways of Verification Locations Standards/
Criteria
Duration, Frequency, Estimated Costs
Implementer(s)
Supervisor(s)
CONSTRUCTION PHASE
Social or Community Concerns
To minimize social disturbance and to maximize community benefits from the project.
To ensure culturally appropriate avenues of grievance redress are
Registration of verbal
or formal complaints Project progress
reports
In all
implementation sites and surroundings.
World Bank
Renewable Energy Tool kit: Best Practices and Lessons Learnt
Continuous
(Minimal costs as part of standard supervision).
Contractor
(Site Engineer [SE] and as required, MPWU via their Local Environmental Expert,
including a female officer if necessary for gender sensitivity
PUB (Local
Environmental Expert), World Bank and Project Supervising Engineering [PSE]
(International Environment Management Expert)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 88
available, especially for women
Soil Erosion
To ensure that impacts of surface erosion are temporary and minimized to
acceptable level.
To minimize sediment losses.
Visual check for sediment load and waste management procedures
Verbal or formal
complaints
All construction sites where groundwork is required.
Construction material and waste should be controlled and protected.
Continuous (Minimal costs as part of standard
supervision).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World Bank and Project
Supervising Engineering
[PSE] (International Environment Management Expert)
Controlling Sediment
To ensure that the impacts are temporary and minimized to acceptable levels.
Visual checks and field inspections
Verbal or formal complaints
All construction sites where
groundwork is required.
Erosion should be controlled.
Continuous (Minimal
costs as part of standard
supervision).
Contractor (Site Engineer
[SE],
PUB (Local Environmental
Expert), World Bank and Project
Supervising Engineering [PSE] (International Environment Management Expert)
Controlling Storm Water
To minimize the impact of
contaminated run-off water to acceptable levels.
Visual checks for water and drainage management
All construction sites where groundwork is
required.
No increase of drainage problems or water logged
areas.
Waste can only be disposed of in approved sites.
Continuous (Minimal costs as
part of standard supervision).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World
Bank and Project Supervising Engineering [PSE] (International
Environment
Management Expert)
Management of Stockpiles and Visual checks, field
In dumping Construction Continuous Contractor PUB (Local
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 89
Spoil-heaps
To minimize dust and sediment run-off.
inspections. Verbal or formal
complaints
areas. material and waste should be controlled and
protected. Waste can only be disposed of in
approved sites.
Waste should be properly selected and stored.
(Minimal costs as part of
standard supervision).
(Site Engineer [SE],
Environmental Expert), World Bank and
Project Supervising Engineering
[PSE] (International Environment Management
Expert)
Air Quality and Dust Control
To avoid and to control unnecessary
dust nuisance.
Visual checks, field inspections.
Verbal or formal complaints
In all construction
areas.
Local Government Act 1984, Section
45;
UK Environmental
Health Services: Guidance for the control of noise and pollution from demolition and
construction sites,
Corbitt, R.A. (1999) Standard Handbook for
Environmental Engineering. 2nd ed. New York:
McGraw-Hill.
Continuous (Minimal
costs as part of
standard supervision).
Contractor (Site Engineer
[SE],
PUB (Local Environmental
Expert), World Bank and
Project Supervising Engineering [PSE] (International
Environment Management Expert)
Noise Control
To minimize noise during construction works.
Visual checks, field inspections.
Verbal or formal complaints
In all construction
areas.
Local Government Act 1984, Section
45;
UK Environmental Health Services: Guidance for the control of noise and pollution from demolition and
Continuous (Minimal
costs as part of
standard supervision).
Contractor (Site Engineer
[SE],
PUB (Local Environmental
Expert), World Bank and
Project Supervising Engineering [PSE] (International
Environment
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 90
construction sites;
Corbitt, R.A. (1999) Standard
Handbook for Environmental Engineering. 2nd
ed. New York: McGraw-Hill.
Management Expert)
Aggregate Management
To minimize potential environmental impact of aggregate transport and
processing.
Visual checks, field inspections
Formal and verbal complaints
In areas where groundwork is required.
Local Government Act 1984, Section 45;
UK Environmental Health Services:
Guidance for the control of noise and pollution from demolition and construction sites;
Corbitt, R.A. (1999) Standard
Handbook for Environmental
Engineering. 2nd ed. New York: McGraw-Hill.
Continuous (Minimal costs as part of standard
supervision)
.
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World Bank and Project
Supervising
Engineering [PSE] (International Environment Management Expert)
Offsite and Waste Management
To avoid contamination from solid wastes and sewage.
To minimize the environmental impact
of its work by adopting respectful waste
management behavior and fulfilling national norms and regulations.
Visual checks, field inspections
Formal and verbal complaints
In all implementation sites and surroundings;
In dumping areas
Waste Management Plan.
WB EHS Guidelines for Waste Management
Continuous (Minimal costs as part of standard supervision)
.
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World Bank and Project Supervising
Engineering
[PSE] (International Environment Management Expert)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 91
Safety and Health
To minimize occupational health and
safety risks of construction works.
Ensure maximum safety of construction personnel, local staff and residents.
Avoid disturbance by the construction workers.
To raise general health and safety awareness.
Registry of work accidents
Registry of rule
violations and applied measures
Verbal and formal
complaints Field inspections
In all implementation sites, work
camps, and surroundings
WB Environmental, Health and Safety
Guidelines (2007);
Public Health
Ordinance 1926
Continuous (Minimal costs as
part of standard supervision)
.
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World
Bank and Project Supervising
Engineering [PSE] (International Environment
Management Expert)
Site De-commissioning
To minimize ongoing impacts after construction is completed.
Visual checks, final field inspection
Verbal and formal
complaints
Documentation of re-vegetation measures
Involvement of local communities in re-vegetation activities
In all implementation
sites and surroundings
Assure the proper cleaning, removal
of waste, remaining
materials and tools.
Address all adverse environmental impacts of construction work
(soil, water,
ground)
After completion
of implementa
tion work (Minimal costs as part of standard supervision).
Contractor (Site Engineer [SE],
PUB (Local Environmental Expert), World
Bank and
Project Supervising Engineering [PSE] (International Environment Management
Expert)
Environmental Issue & Objective Ways of Verification Locations Standards/
Criteria
Duration, Frequency,
Estimated Costs
Implementer(s)
Supervisor(s)
OPERATION PHASE
Safety
To avoid accidents, damaging or unauthorized removal of the technical equipment.
Regular inspections Additional checks after special
climate events (heavy rainfall, storm)
Verbal and formal complaints
In all implementation sites
As listed in the EMP; Additional information of contractor
and suppliers
Regular after implementation (Minimal
costs as
PUB, during the first three years supported by Post
Commissioning
MPUW-, and World Bank (during the first two years)
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 92
To meet safety requirements. part of standard supervision)
.
Services Contracted Company.
Maintenance and repairs
To ensure the correct and efficient operation of the system.
To avoid technical failures and accidents.
To avoid contamination of drinking water.
Regular checks (Registry of maintenance work)
Additional checks after special climate events (heavy rainfall,
storm) Verbal and formal complaints
In all implementati
on sites
As listed in the EMP
Maintenance protocol as
part of the Operation Manual provided by the contractor
Regular after
implementation
(Minimal costs as part of standard supervision).
PUB, during the first three
years supported by
Post Commissioning Services Contracted Company.
MPUW-, and World Bank
(during the first two years)
Annex 10: Field Monitoring Checklist
NAME OF THE INSPECTOR:
ORGANISATION:
DATE OF INSPECTION:
GENERAL OBSERVATIONS:
RESULTS WILL BE SHARED WITH:
Environmental Issue & Objective
Mitigation Measures Locations Timeframe Level of Achievement
(0 – No,
1 – Partly,
2- Yes)
Detected problems and potentials of Improvement
Recommendations, proposed measures
CONSTRUCTION PHASE
Social or Inform local neighborhood community
before construction activities start about In all
During whole construction
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 93
Community Concerns
To minimize social disturbance and maximize community
benefits from the project.
planned civil work-show they could be affected by them;
Avoid or minimize disturbances by
construction activities in near living areas, e.g. avoiding works at nighttime, minimizing transports of material, noise
control; Apply adequate waste management and
avoid run-off of waste, e.g. littering off packaging material;
Offer employment and training opportunities for local people. The general practice is that Contractors employ workers from the communities. The clan leaders (unimwane) will be consulted when recruiting workers for the Contractors;
Include women and other community
groups in project activities whenever there is any opportunity.
implementation sites and surroundings
work.
Soil Erosion
To ensure that impacts of surface erosion are
temporary and minimized to acceptable level.
Minimize work areas; Keep vegetation clearing at the necessary
minimum; Keep vehicles on defined tracks; Construct the necessary
temporary/permanent control structures; Encourage re-vegetation as soon as the
construction activities finish, or plan to immediately rehabilitate the disturbed
sites after use.
In all implementation
sites and surroundings
During whole construction
work.
Controlling Sediment
To ensure that the impacts are
temporary and minimized to acceptable levels.
Installing silt traps or other control structures at the outset of the construction;
Installing silt traps or other control structures at the outset of the construction
Preparing all disturbed areas for re-vegetation or for natural re-vegetation;
Phasing and limiting ground disturbance to areas of a workable size;
Scheduling construction to limit
disturbance of large areas of soil during wet seasons;
In all implementation sites and
surroundings
During whole construction work.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 94
Avoid discharging of contaminated water to the lagoon.
Controlling Storm Water
To minimize the impact of contaminated run-off
water to acceptable levels.
Pass storm water run-off from construction areas through rocks or hay traps to remove soil and petroleum-based organic pollutants before disposal;
Store oil and bituminous products at a contained location away from drainage
ditches.
In all implementation sites and surroundings
During whole construction work.
Management of Stockpiles and
Spoil-heaps
To minimize dust and sediment run-off.
Discuss dumping locations with the government officials and/or local
landowners including plans for future use of the spoil materials;
Include all drainage provisions suggested for construction sites in the site plans;
Choose the locations of waste spoil piles to avoid blocking surface run-off or drainage ditches;
Cover all spoil heaps or stockpiles during rainy season to prevent erosion and sediment run-off.
In all implementation
sites and surroundings
During whole construction
work.
Air Quality and
Dust Control
To avoid and to control unnecessary dust nuisance.
Spray water on spoil-heaps if there are
dust generating materials accumulated
during dry periods especially near schools, hospitals, etc.;
Cover all dust generating loads carried in open trucks.
In all
implementation
sites and surroundings
During whole
construction
work.
Noise Control
To minimize noise
during construction works.
Use modern and well-maintained equipment (with mufflers where appropriate);
Use noise screens or mounds near
residential areas, when appropriate; Carry out noise construction activities and
transports during normal working hours, never at night time;
Advise schools, hospitals, churches, etc., when there will be unusual or unavoidable
In all implementation sites and surroundings
During whole construction work.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 95
noise.
Aggregate Management
To minimize potential
environmental impact.
Avoid overloading trucks and cover trucks to minimize dust and loss of load from trucks during transportation;
Use water sprays or covered chutes to reduce dust emission during loading and
unloading of materials from barges; Maintain crushing and mixing plants in
good working condition so as to reduce emission from the plant;
As far as possible, plan truck trips during low traffic hours;
Implement safety procedures during transport to reduce the potential for road
accidents in village or urban areas.
In all implementation sites and surroundings
During whole construction work.
Offsite and Waste
Management
To avoid
contamination from solid wastes and sewage
To minimize the environmental impact
of its work by adopting respectful
waste management behavior and fulfilling national norms and regulations.
Store wastes with respect for health and
environment Support, when practical, recycling of
waste;
Contain all stored wastes within construction sites, avoid littering and runoff;
Use recycled or renewable building materials (e.g. timber) where possible;
Optimize and reduce waste production. Avoid mix of different waste and minimize
waste disposal into the landfill; Not produce hazardous waste; Sort waste according to its type and origin.
Store selected materials in safe place in order to avoid contamination, especially if they will be shipped out for recycling;
Encourage the recycling of waste. Follow the hierarchy: Prefer local recycling or reuse before shipping out for recycling before waste disposal in the landfill;
Properly dispose of all used fuel and lubricant oils in environmentally sound manner, either by recycling or for other
use such as fuel for hot mix plant, etc.;
In all
implementation sites and surroundings
During whole
construction work.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 96
Crush, burn, and bury all inorganic solid waste in an approved solid waste disposal area;
After construction has finished, remove all disabled machinery and waste from the project area;
Utilize, if available, public toilets at construction sites;
Compost all green or organic wastes or use as animal food.
Safety and Health
To minimize occupational health
and safety risks of construction works.
To raise general health and safety awareness.
Ensure all occupational health and safety requirements are in place on construction sites;
Understand the use of personal protection
equipment (PPE) and make sure that it is used properly;
Install lights and cautionary signs in hazardous areas;
Ensure safety and inspection procedures; Safe handling of toxic materials and other
hazardous substances;
Implement a system of penalties for violation of rules and regulations
Introduction to health and safety issues in
construction sites by the Contractor; Education on basic hygienic practices to
minimize spread of tropical diseases, including information on methods of
transmission and protection measures for sexually transmitted diseases;
Prohibition of drugs, kava and alcohol on construction sites;
Assure availability of medical assistance in emergency or non-emergency situations
and availability of other health-related assistance
In all implementation sites and
surroundings
During whole construction work.
Site De-commissioning
Assure all waste and remaining material for recycling has been removed from the construction site;
In all implementation sites and
After construction work is
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 97
To minimize ongoing impacts after
construction is completed.
Rake or loosen all compacted ground surfaces;
If necessary, implement revegetation /
rehabilitation of the construction sites involving, where possible, local women’s and community groups.
surroundings completed.
Environmental Issue & Objective
Mitigation Measures Locations Timeframe Level of Achievement
(0 – No,
1 – Partly,
2- Yes)
Detected problems and
potentials of Improvement
Recommendations, proposed
measures
OPERATION PHASE
Safety
To avoid accidents, damaging or unauthorized removal
of the technical equipment. To meet safety
requirements. To avoid contamination of drinking water.
Inhibit unauthorized access to the PV modules on roof-top or at the free-standing structures by construction design and eventually necessary technical protection measures (fences, gates,
locks); Cover inverters with a locked metal cage
firmly attached to the wall in order to avoid unauthorized manipulation
(especially by playing children with the risk of accidents) or theft;
Mark sites with comprehensive and visible
signs (pictograms) indicating danger and no-go-areas;
Put the wiring underground in order to
In all implementation sites
During whole operation time of the system (20 years).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 98
avoid accidents and damage (accidentally or intentioned by vandalism);
Advice to the public institutions where the
PV installations are implemented about special risks and security needs (security fence, safeguard at nighttime);
Inform the administration of the public institutions where the PV installations are implemented that they should report immediately to the PUB any case of
damage of any component of the PV system.
The collection of drinking water shall cease until the panel(s) is / are replaced or fixed. Contaminated water shall be treated as hazardous waste.
Maintenance and repairs
To ensure the correct and efficient
operation of the system.
To avoid technical
failures and accidents.
Under normal climate conditions with regular rainfall, the slope of the installation will enable the self-cleaning of PV modules by rinsing rainwater. During droughts, the dust of the panels should be removed
twice a year. The cleaning can be made easily with a hose pipe;
Adjacent trees or shrubs should be trimmed in order to avoid shading over the panels or damage by falling fruits
(especially coconuts); Wiring should be revised once a year in
order to make sure that there is no damage (e.g. rotten cables). This activity should be carried out by authorized PUB staff only;
Inverters should be revised once a year to assure their perfect operation
(replacement of rusted components). This activity should be carried out by
authorized PUB staff only; Security measures should be revised once
a year (e.g. replacement of rusty locks, closing of fence holes);
The state of all installations should be
revised by PUB staff after special climate
In all implementation sites
During whole operation time of the system (20 years).
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 99
events, as heavy rainfalls, storms or floods in order to detect damages on the support construction or on the PV installation itself;
The institution where the PV installation is installed should immediately report any damage on the structure to the PUB Staff
in order to assure repairs or replacement of damaged components;
All repairs or manipulation of the PV system should be carried out exclusively
by authorized staff of PUB that previously has got instructions and training.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 100
ANNEX 11 MINUTES OF THE FINAL CONSULTATION MEETING OF THE DRAFT EIA / EMP 6 JULY 2012
Kiribati Grid Connected Solar PV Project Consultation Minutes
Held on Friday, 06 July 2012 in Ministry of Public Works and
Utilities Boardroom at 1005 hours
Present: Mr Kevin Rouatu, PUB CEO Chairman
Mr Eita Metai, Secretary – MPWU,
Mr Rokobati Tearo, Principal, KIT,
Ms Teea Tiira, ADB,
Mr Rekenibai –AUSAID,
Mr Teurakai Ukenio-NGO,
Mrs Miriam I Toatara, Energy MPWU,
Mr Mike Foon-OB Climate Change,
Mr Puta Tofinga-ECD-MELAD,
Ms Iaona Kanimako-MOE,
Ms Banny Teuea-MHMS,
Mr Tiaon Aukitino, Energy MPWU,
Mr Kiriati Birita, Power Engineering Manager, PUB
In attendance: Ms Kirita Aaron, PUB – Secretariat
The meeting was opened with short prayer by the Chairman, Mr Kevin Rouatu and opening remarks by the Secretary for the Ministry of Public Works and Utilities, Mr Eita Metai.
1.0 BACKGROUND
The consultation began with an over view explanation of the project and its purpose which is to
help PUB financially. The project which involved the incorporation of solar energy into PUB power grid was regarded the best choice based on the fact that it is clean; it increases capacity, uses
less fossil fuel and is proven to be long lasting, approximately 20 years. Other factors that contributed to opting to this project was the use of Government existing buildings. With this, the complications of landowner consultation and other related issues are avoided. Mounting these solar panels on these buildings would be a saving to Government regarding roof replacement for the selected buildings accounted for in the project.
The selected Government buildings include Kiribati Institute of Technology, KGV & EBS, Ministry of Health and Medical Services, and Sport Complex. The solar panels on these four buildings would inject into PUB power grid additional capacity of 516 kW without increase in fossil fuel
consumption.
For sustainability, stakeholders were informed that Kiribati Institute of Technology would provide
necessary training package and other capacity building requirements of both PUB and Solar Energy Staff to ensure sustainability of the project.
Stakeholders and members of the public represented were informed that the project would be handed over to PUB when completed.
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 101
2.0 EIA and EMP.
Stakeholders and participants were informed that the assessments carried out by the Ministry of Environment, Lands and Agriculture Development had gone into every detail to ensure adverse
impact that may exist are avoided as much as possible. And if there are, it would be minimal. At the same time stakeholders and public represented at the consultation were informed that plans were already in place to minimize hazards and disruptions to the public and environment during the process of installation and progress of the project.
3.0 Concerns Raised
After the detailed explanation of EIA and EMP, some issues were raised. Concerns that arose included the following:
1. Safety of Substance Use in Solar Panels
The fact that the solar panels would be on roofs whose rainwater is used for drinking, raised a
concern. A question was raised on the safety of the substances used in the solar panel in case
the panels break open or corrode away from sea spray (particularly at MOH and KGV) and
leakage from the panels eventuates.
Despite explanations that panels would withstand impacts of heavy falling objects and the fact
that corrosion from sea spray are already taken into consideration in the initial state of the
project to avoid corrosion, the public still demand that they be given assurance that the
substances used in solar panels are certainly safe.
Given the value of the project and the need to sustain it, an awareness team would be organized and mobilized in advance to change the mindset of public to responsible and active in looking after public properties. The awareness program should also stress citizens’ duty of care.
2. Difficulty to Relocate Operating Theatre
Representative from the Ministry of Health and Medical Services raised a concern on the
relocation of a patient in the medical theatre based on the fact that there is only one operating
theatre.
Given the validity of the concern raised, the team agreed that a consultation with the Ministry
of Health and Medical Services is necessary for replacement plan especially for an operating
theatre. The World Bank may be approached for this. The sooner; the better.
3. Private Installation of Solar Panels at private home and selling of surplus to Operator
As a means to help increase capacity, private householders requested if they be allowed to run own solar system and be also allowed to sell their surplus to PUB. PUB CEO said that as yet they do not have the capacity to do that but when PUB has capacity to take this on board, it will do it. The recent project would be good exercise to build capacity of PUB staff to
venture in buying surplus energy from private solar operators. The idea though had been incorporated in the plan.
4.0 Comments Invited
4.1 Ministry of Environment, Land and Agriculture Development –
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 102
The Environment Division had studied and is now satisfied with the document made.
4.2 Correction of Figure in Page 53
An error was noted on the budget for the Environmental Plan as shown in Table 4, page 53. Contingency costs for Year 1 should be 3100 instead of 250 and for Year 2 should be 1900 instead of 250. Therefore total contingency cost should be 5,000 instead of 50,500. With amendments made, the EMP was adopted.
4.3 Work on License - Outstanding
It was noted that the license had not been submitted to Environment yet. Given the urgency
and important role of the license to support the project, PUB was asked to speed up work on license. CEO undertook to do complete the application form and submit it as soon as practicable.
There being no further issue to discuss, the meeting ended at 12.30 pm.
Confirmed by: Mr Kevin Rouatu, CEO, PUB and meeting Chairman
Date: 6 July 2012
DISCLOSURE PRIOR TO CONSULTATIONS
The Environmental Impact Statement and the Environmental Management Plan, and a Project Information Bulletin (in English and Gilbertese) were disclosed at the following locations prior to the consultations:
Public Utilities Board, Betio
Energy Unit/Ministry of Works and Public Utilities, Betio
Ministry of Environment, Lands and Agricultural Development, Bikenibeu
Kiribati Institute of Technology, Betio
Betio Sports Complex, Betio
Tungaru Central Hospital, Nawerewere
King George V Secondary School, Bikenibeu
Environmental Impact Assessment for Kiribati Grid Connected PV Solar Power Station Project 103