Prepared by SRA International, Inc. • Confidential
2009Web-Based Supply Chain Management
Overview Course
Prepared by SRA International, Inc. • Confidential
2009
3 • Prepared by SRA International, Inc. • Confidential
Agenda• WBSCM Overview
– Vision – Business Scope– Impacted Stakeholders– Goals & Objectives– Expected Benefits
•What is WBSCM – Commercial Off The Shelf (COTS) Enterprise Resource
Planning (ERP Technologies – Non-Integrated vs. Integrated System Scenario– Application Components – Portal– Process Model (Funds to Order, Source to Award, Ship to
Pay)
•WBSCM Status – Release 1 Program Timeline– Testing Timeline– Training Timeline
4 • Prepared by SRA International, Inc. • Confidential
WBSCM Overview
WBSCM Overview
5 • Prepared by SRA International, Inc. • Confidential
WBSCM - A Partnership With A Vision
FSAFSA
USAIDUSAID
FNSFNS
AMSAMS FASFAS
WBSCM will provide new capabilities and functionality to support doing business with USDA!
6 • Prepared by SRA International, Inc. • Confidential
WBSCM Business Scope
Farmers/Producers
US Freight Carriers
MARAD
US PortsCommodity Suppliers
Schools (27,000 school dists, 94,000 schools)Indian Tribal Orgs (92 ordering agencies)
Non- Profits (60 ordering agencies)
Domestic
Foreign
World Food Organization Foreign Governments (70 Nations)Private Volunteer Organizations (30+)
BUY DISTRIBUTE/SHIP
RECEIVEPRODUCE
FNS
FAS
USAID
Warehouse WarehouseAMS
FSA
Multi Agency EnvironmentIntegrating processes and technology
across the five U.S. agencies responsible for planning, procuring,
managing, and delivering commodities and food supplies domestically and
around the world…
7 • Prepared by SRA International, Inc. • Confidential
WBSCM Impacted Stakeholders
8 • Prepared by SRA International, Inc. • Confidential
Goals and Objectives
• Integrate, standardize, and streamline the way we manage the supply chain across government end-to-end – from planning and procurement to ordering, contract management, and delivery
• Leverage best practices and advanced Commercial Off The Shelf (COTS) technologies
• Enable focus on more value-added supply chain functions and less on administrative tasks
• Foster long-term business relationships with suppliers for better cost efficiency
WBSCM GoalsWBSCM Goals
FSA
FSA USA
ID
USAIDMARAD
MARADFN
S
FNS
AMS
AMS
FAS
FAS
To advance our capability to manage and share our nation’s food supply
To proactively forecast and plan supply and demand
To continually advance our partnership, collaboration, efficiency, and service with all business partners
To advance our capability to manage and share our nation’s food supply
To proactively forecast and plan supply and demand
To continually advance our partnership, collaboration, efficiency, and service with all business partners
9 • Prepared by SRA International, Inc. • Confidential
Expected BenefitsFor USDA
• One standardized, integrated, transparent, and efficient end-to-end process for U.S. supply chain management
• Built-in best practices for procurement, financial management, supply chain mgmt
• Single, authoritative, timely, easy-to-access source of data and automated, paperless workflow with few manual processes and reduced hand-offs
For Our Vendors / Customers
• Streamlined web-based, self service operations
• Simplified submission of orders, bids, invoices, quality certificates, Proof of Delivery..
• Improved real time tracking of business transactions
• Electronic notification of bid awards, shipments and business transaction exceptions
Easier to do business with USDA !Easier to do business with USDA !More efficiency for all involved !More efficiency for all involved !
Easier to do business with USDA !Easier to do business with USDA !More efficiency for all involved !More efficiency for all involved !
10 • Prepared by SRA International, Inc. • Confidential
What is WBSCM
What is WBSCM
11 • Prepared by SRA International, Inc. • Confidential11 • Prepared by SRA International, Inc. • Confidential
COTS ERP Technologies
COTS - Commercial Off-The-Shelf: Software or hardware products that are “ready-made” and available for sale to the general public used as an alternative to in-house development
ERP – Enterprise Resource Planning: Software to integrate all data and processes of an organization into a single unified system
OrderManagement
Financials
Manufacturing /Maintenance
HumanResources
MgmtReporting
Inventory
Operations
FacilitiesMgmt
Procurement CommonCommon DataData
• Embedded industry best practices to promote business process reengineering
• “Configuration” to adapt to specific processes vs. software development
• Rich functionality and capabilities• Real time, integrated business
transactions• Multi-platform, multi-language
support• Data sharing across all functional
areas
• Reduced Total Cost of Ownership – TCO• Vendor supported• Vendor enhanced
12 • Prepared by SRA International, Inc. • Confidential
Order ManagementBid Invitation
Procurement
Funds Management
A Business transactionA Business transaction
Interfaces
Interfaces
Non-Integrated System Scenario
13 • Prepared by SRA International, Inc. • Confidential
Order ManagementBid Invitation
Funds Management
Procurement
Interfaces
A Business transactionA Business transaction• Time delayTime delay until all entities are until all entities are aware of the occurrence of a aware of the occurrence of a business transactionbusiness transaction• InterfacesInterfaces must must bebe built and built and maintainedmaintained to ensure propagation to ensure propagation of informationof information• Risk of inconsistenciesRisk of inconsistencies of of information across entities due to information across entities due to duplication of data, timing and errorsduplication of data, timing and errors• Manual “adjustments”Manual “adjustments” possible possible throughout the processthroughout the process
• Time delayTime delay until all entities are until all entities are aware of the occurrence of a aware of the occurrence of a business transactionbusiness transaction• InterfacesInterfaces must must bebe built and built and maintainedmaintained to ensure propagation to ensure propagation of informationof information• Risk of inconsistenciesRisk of inconsistencies of of information across entities due to information across entities due to duplication of data, timing and errorsduplication of data, timing and errors• Manual “adjustments”Manual “adjustments” possible possible throughout the processthroughout the process
Non-Integrated System Scenario
14 • Prepared by SRA International, Inc. • Confidential
Funds ManagementFunds Management
Bid InvitationBid Invitation
ProcurementProcurement
A Business transactionA Business transaction
Order ManagementOrder Management
Integrated System Scenario with WBSCM
15 • Prepared by SRA International, Inc. • Confidential
Funds ManagementFunds Management
Bid InvitationBid Invitation
ProcurementProcurement
A Business transactionA Business transaction • Real time information available to all entities• Always consistent information – single sourced• Supply Chain Integration with Funds Management
• Real time information available to all entities• Always consistent information – single sourced• Supply Chain Integration with Funds Management
Order ManagementOrder Management
Integrated System Scenario with WBSCM
16 • Prepared by SRA International, Inc. • Confidential
PublicSector –
Proc.
PublicSector – Finance
WBSCM Application Components
Core ERP
• Funds management• Master Data• Inventory• Financials• Integration engine across all modules
Customer Relationship Management
• Web order entry• Web catalogs• Case management
Supplier Relationship Management
• Creation of Bid Invitations• Vendor Bid entry• Bid review• Supplier evaluation
Workflow & Records Management
• Alerting and notification of users• Central repository of documents
Business Intelligence
• Decision Support• Ad-Hoc Reporting• Management Reporting
Portal
• Common User entry point • Seamless navigation across application components
MS Office Integration Interactive Forms
•Productivity Tools• Forms processing
ERP
17 • Prepared by SRA International, Inc. • Confidential
WBSCM PortalEach participating agency site links to WBSCM splash page
Each participating agency site links to WBSCM splash page
WBSCM splash page links to ‘WBSCM Login’
which launches the WBSCM Portal
WBSCM splash page links to ‘WBSCM Login’
which launches the WBSCM Portal
18 • Prepared by SRA International, Inc. • Confidential
1Maintain Budget
13 Create Payment Request
eFMS4, 9
Manage Commitment & Obligation
8Create
Purchase Award
10Receive
Shipment Notification
2Enter Order
SDA / ITO / RA / PVO / WFP / FFW
Purchase Order
Order EntrySubstitutions Preferences
Markings
InvoiceQuality Certificate
NPS / NPSDW Payment RequestPayment Confirmation
Send Payment
Automated Fund Balances
ObligationDrawdown (FAS Only)
USAID Freight Excluded
Fund Balances
Receipts
AMSFNSFSA
AMSFNSFSA
AMSFSAFAS
7Bid
Optimization
Vendor Bid ConstraintsUSDA Bid Constraints
Award Recommendations
FSA
FNSFASUSAID
AMSFSA
CORE
Payment in Transit
Accounting
Ship Notice
Purchase ActualsShip Notice
Domestic & International Orders
Manual fund Entry Manual Fund Balances
11Receive
Material/ Freight
12 Post, Match & Approve
Invoice
Matched Invoice
Receipt Entry(Load & Discharge Ports)
14Periodic
Accounting Processing
Receipts
Accounting
Purchase OrderPayables
Purchase Actuals
Bid ResponsePO MaintenanceEnter Ship NoticeEnter Invoice, Quality Certificates, OBL
5Manage Bid Invitation
Bid InvitationBid Responses
6Evaluate Bid
and Optimization
Results
Bids Awards
3Create
Purchase Requisition
PRs
Commitment Drawdown (FAS Only)
USAID Freight Excluded
FPDS-NGOEO-FAADS/ FFATA
PPIRS
Award Notice
FNSFASUSAID
FSA
AMSFSA
AMSFSA
AMSFSA
AMSFNSFSA
NDBFPRS
Bonus Information
Fund AvailabilityFund Consumption
Accounting
AMSFNSFSA
1bManage Intl Agreements
FAS
FADS / FAIS
Agreements
Check Compliance (FAS only)
Obligate (FAS only)
Warehouse Order?
No
OBL
MARAD
Ocean Freight Diff
15Establish /
Clear Receivable
AMSFNSFSAFAS
NRRS / DW
Receivable
Damage & Shortage
Manual Claims Entry based on Receipts and Warehouse Processes
Accoun ting
Actual Expenditures
3aFulfill from Warehouse
YesManage Service
Contracts
16Manage
Warehouse Inventory
Replenishment Orders
Purchase Orders
Goods Issued
Vendor
FNSFAS
AMSFSAFAS
FNSFSAUSAID
1aManage
Entitlements
Entitlement Checking
FNSFASUSAID
FNS
WBSCM Process Model
F2OF2OFunds to OrdersFunds to Orders
F2OF2OFunds to OrdersFunds to Orders
S2AS2ASource to AwardSource to Award
S2AS2ASource to AwardSource to Award
S2PS2PShip to PayShip to Pay
S2PS2PShip to PayShip to Pay
MData – Master DataMData – Master DataSpecProc - Special ProcessSpecProc - Special ProcessTech - TechnicalTech - Technical
MData – Master DataMData – Master DataSpecProc - Special ProcessSpecProc - Special ProcessTech - TechnicalTech - Technical
19 • Prepared by SRA International, Inc. • Confidential
Baseline Process Flow
CRM SRM-PSERP
CaptureSubstitutable
CreateSales Order
CreatePR from
Sales Order
CommitFunds
CreateSales OrderOrdersOrdersOrdersOrders
Customers
BEOS
20 • Prepared by SRA International, Inc. • Confidential
Baseline Process Flow
CRM SRM-PSERP
CreateSales Order
CaptureSubstitutable
CreateSales Order
CreatePR from
Sales Order
CreateExternal ReqmtsIn SourcingCockpit
CommitFunds
Create& Release
Bid Invitation
AcceptBids
Bid InvitationBid InvitationBid InvitationBid Invitation
BidsBidsBidsBids
OrdersOrdersOrdersOrders
Customers
Vendors
BEOS
21 • Prepared by SRA International, Inc. • Confidential
Baseline Process Flow
CRM SRM-PSERP
CreateSales Order
CaptureSubstitutable
CreateSales Order
CreatePR from
Sales Order
CreateExternal ReqmtsIn SourcingCockpit
CommitFunds
Create& Release
Bid Invitation
AcceptBids
EvaluateBids
Optimize Bids
Commodities / Freight
Bid InvitationBid InvitationBid InvitationBid Invitation
BidsBidsBidsBids
OrdersOrdersOrdersOrders
Customers
Vendors
22 • Prepared by SRA International, Inc. • Confidential
WBSCM Status
WBSCM Status
23 • Prepared by SRA International, Inc. • Confidential
Search andSelection
• Business Requirements Definition
• RFIs, RFPs• Product
Evaluations & Selection
0Strategy
&Selection
0Strategy
&Selection
Requirements, Contract
• Scoping• Team Setup• Project Kick-
off• Planning &
Budgeting
1ProjectKick Off
1ProjectKick Off
Detail Design Specifications
(Blueprint)
• Process Design• Configuration Design• RICEFW Functional
Design• Data Mgmt Plan• Training &
Communication Plan• Technology Design• Planning &
Budgeting
2Design
2Design
Step by step process
Leads to strong structure
• Configuring• RICEFW Technical
Spec• Building:
• Processes• Training• Programs• Technology
• Testing• Go-live Planning• Communicating
3Build /Test
3Build /Test
Final Walk Through
• Acceptance Testing• Training• Planning &
Budgeting• Communicating• Production Cutover!
4Deploy
4Deploy
Moving in!!
• Go-live!• Monitoring• Final Revisions• Support
5Go Live
5Go Live
A Home Building Analogy
WBSCM Release 1 Program TimelineWe are hereWe are hereWe are hereWe are here
Dec 31, 2009
24 • Prepared by SRA International, Inc. • Confidential
Testing Timeline
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
External TestingUSDA/USAID is responsible for:- Identifying external testers- Coordinating external tester training- Coordinating external test activities
UAT/Cutover Testing USDA/USAID is responsible
for:- Identifying UAT testers- Executing UAT tests- Executing Cutover tests
SIT Testing USDA/USAID invited to
participate in Integration Testing activities
25 • Prepared by SRA International, Inc. • Confidential
Training Timeline
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
ExternalTraining
SystemAdministratorGuide/Course
TrainingEnvironments
OverallWBSCMSchedule
InternalTraining
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
ExternalTraining
SystemAdministratorGuide/Course
TrainingEnvironments
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
ExternalTraining
SystemAdministratorGuide/Course
TrainingEnvironments
OverallWBSCMSchedule
InternalTraining
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
ExternalTraining
SystemAdministratorGuide/Course
TrainingEnvironments
OverallWBSCMSchedule
InternalTraining
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
ExternalTraining
SystemAdministratorGuide/Course
TrainingEnvironments
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
12/21ORR
12/10PRR
9/1TRR
12/31/09Go-Live
1/1/09 3/1/102/1/09 3/1/09 4/1/09 5/1/09 6/1/09 7/1/09 8/1/09 9/1/09 10/1/09 11/1/09 12/1/09 1/1/10 2/1/10
O&M
1/1/09 2/1/10
1/1/09 2/1/10
9/1/09– 1/1/2010External Training (4 mos)
1/1/09 12/31/09
1/1/09 11/1/09
3/1Integration Environment
Available for Test Execution
7/1Int. Training Environment
Ready for Data Load
7/1 Ext. Training Environment
Ready for Data Load
1/1/09 12/31/09
1/1/09 - 11/1/09Test Phase (10 mos)
11/1/09 - 12/31/09Deployment Phase (2 mos)
4/1 - 5/15Test Cycle 2
1/1 - 2/15Test Cycle 0
11/1 - 12/31Cutover Testing (2 mos)
2/15 - 4/1Test Cycle 1
5/15 - 7/1Test Cycle 3
9/1 - 11/1UAT (2 mos)
7/1 - 9/1End to End
2/12 - 8/1External User Interface Development (5+ mos)
9/1 - 10/1SME Trng
2/1 - 8/1Internal Training Documentation Reviews (6 mos)
12/31/09 - 2/1/10PD Trng (1 mo)
10/1 - 12/31Internal Training (3 mos)
11/1 - 12/31Cutover
1/1 - 11/1Deployment Planning & Preparation
8/1 - 11/1Ext. User Interface Testing (3 mos)
7/1 - 8/1Ext. Test Trng
8/1Int. Training Environment
Ready for USDA Access
8/1Ext. TrainingEnvironment
Ready for USDA Access
8/1 - 8/15SME Pilot
2/1 - 8/15External Training Documentation Reviews (6 mos)
8/15 - 9/1 Instr Pilot
ExternalTraining
SystemAdministratorGuide/Course
TrainingEnvironments
OverallWBSCMSchedule
InternalTraining
External TrainingUSDA/USAID is responsible for delivering external training using e-Learning courses
Internal TrainingUSDA/USAID is responsible for:- Identifying participants for instructor led training courses- Registering participants- Confirming participants