Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly and Safety Analysis Advisory Technical Directorate [email protected] [email protected] +55 21 2588-7938 May 2018

Upload: others

Post on 13-Mar-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Preliminary Plan for Decommissioning and Post

Shutdown Activities of Brazilian NPPs

Bruno Estanqueira Pinho Fuel Assembly and Safety Analysis Advisory Technical

Directorate

[email protected]

[email protected]

+55 21 2588-7938 May 2018

Page 2: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

1. CNAAA – Alvaro Alberto Admiral Nuclear Center - Description

2. Chronology of Brazilian Licencing - Decommissioning

3. Decommissioning in Brazil

4. PDP – Preliminary Decommissioning Plan of CNAAA

I. Table Of Contents Of PDP

II. Summary Schedule

III. Decommissioning Cost Estimate (DCE)

IV. Radioactive Waste Summary Foreseen:

a) Operacional

b) Decommissioning

5. Transition Period Preliminar Planning

I. Table Of Contents Of TPPP of Angra 1

II. Spent Fuel Management at CNAAA

III. Post Shutdown Activities for Angra 1- Summary

IV. TPA1 Cost Estimate – order of magnitude

2

TABLE OF CONTENTS

Page 3: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

1. Almirante Álvaro Alberto Nuclear Center

CNAAA

For sites with more than one facility, a site

strategy for decommissioning

shall be developed to ensure that

interdependences between the facilities

are

taken into account in the planning for

individual facilities that will lead to final

decommissioning plans for each facility

An important consideration when selecting

the decommissioning strategy

is the desired end state5 of the facility

following completion of the

decommissioning.

The preferred end state would be to

achieve a situation whereby the

site is released for unrestricted use (with or

without buildings) or a situation

whereby it may be released for restricted

use. Other end states could involve

partial release of a site or release of a site

under restricted conditions to control

its future use. The foreseen end states for

the three different strategies are

shown in Fig. 1.

The end state is defined as a

predetermined criterion defining the point

at which

a specific task or process (i.e.

decommissioning) will be considered

complete

GSR part 6 , Decommissioning of Facilities, IAEA, 2014)

INTERNATIONAL ATOMIC ENERGY AGENCY, Decommissioning of Facilities Using Radioactive

Material, IAEA Safety Standards Series No. WS-R- 5, IAEA, Vienna (2006).

Decommissioning Strategies for Facilities Using Radioactive Material, SRS no 50. IAEA, 2007.

São Paulo

220km

Belo

Horizonte

350km

Rio de Janeiro

130km CNAAA

ANGRA 1 PWR

Power: 640 MW

Technology: Westinghouse

Operation start: Jan. 1985

ANGRA 2 PWR

Power: 1,350 MW

Technology: KWU/ Siemens

Operation start: Jan. 2001

ANGRA 3 PWR

Power: 1,405 MW

Technology: KWU/ Siemens - Framatome Civil works reached ~67 %.

(illustrative view) ANGRA 1

ANGRA 2

RADIOACTIVE

WASTE STORAGE

CENTER 500kV Switchyard

Ilustrative picture

UAS (ISFSI) – 2020 Waste Monit. Building – New

Civil works – 95%

Page 4: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

NN CNEN 9.01

(Nov./2012)

ENERCON Contract

(Mar/2015)

UFABC University

(Feb/2017)

PDP rev0

UFABC University / ETN

(Nov./2014)

PDP rev. 0 REVIEW

Analising strategy / chapters / Data collection

>>> Develop the site specific Decommissioning

Cost Estimate Software (DCE)

PDP reviewed

(June/2018)

UFABC - End

2. Chronology of Brazilian Licencing in Brazil

PDP Improv. / DCE

(Sept/2017)

Enercon - End

Implementation of ENERCON comments /

Biography Research / Review and

release of new PDP >> English and

Portuguese

>>> Qualification of National Partner –

University of ABC

Submit to CNEN

PDP ver 1

(End of 2018)

NN CNEN 9.02

(Oct./2016)

4

Page 5: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

3. Decommissioning in Brazil

For sites with more than one facility, a site

strategy for decommissioning

shall be developed to ensure that

interdependences between the facilities

are taken into account in the planning for

individual facilities that will lead to final

decommissioning plans for each facility

An important consideration when selecting

the decommissioning strategy

is the desired end state5 of the facility

following completion of the

decommissioning.

The preferred end state would be to

achieve a situation whereby the

site is released for unrestricted use (with or

without buildings) or a situation

whereby it may be released for restricted

use. Other end states could involve

partial release of a site or release of a site

under restricted conditions to control

its future use. The foreseen end states for

the three different strategies are

shown in Fig. 1.

The end state is defined as a

predetermined criterion defining the point

at which

a specific task or process (i.e.

decommissioning) will be considered

complete

5

GSR part 6 , Decommissioning of Facilities, IAEA, 2014)

INTERNATIONAL ATOMIC ENERGY AGENCY, Decommissioning of Facilities Using Radioactive

Material, IAEA Safety Standards Series No. WS-R- 5, IAEA, Vienna (2006).

Decommissioning Strategies for Facilities Using Radioactive Material, SRS no 50. IAEA, 2007.

• Decommissioning: ADMINISTRATIVE AND TECHNICAL ACTIONS TO

ALLOW THE REMOVAL OF SOME OR ALL OF THE REGULATORY CONTROLS FROM A FACILITY (CNEN NN 9.01, 2012)

• With no unacceptable risk to the public, the workers or the environment

• Decommissioning Strategies for CNAAA:

Deferred Dismantling: Angra 1 and 2 NPPs

Immediate Dismantling: Angra 3 NPP

• Desired End State – Unrestricted use

• Important Issues

o Integrated National RW and SFAs Policy

o LLW / ILW Repository – under siting selection phase

o HLW and SFA Repository – waiting for political decision

Page 6: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Desmantelamento imediato

Desmantelamento protelado

Confinamento

4. PDP - PRELIMINARY DECOMMISSIONING PLAN

1. Introduction

2. Facility description

3. Decommissioning strategy

4. Project management

5. Decommissioning activities

6. Surveillance and maintenance

7. Waste management

8. Cost estimate and funding mechanisms

9. Safety assessment

10. Environmental assessment

11. Health and safety

12. Quality assurance

13. Emergency planning

14. Physical security and safeguards

15. Final radiation survey

SRS no 45 Standard Format and Content for Safety Related Decommissioning Documents. 2005, IAEA.

I - TABLE OF CONTENTS OF PDP

IMPROVEMENTS

NEW

CHAPTERS SRS45

SITE SPECIFIC

DCE

CNEN NN 9.01 Descomissionamento De Usinas Nucleoelétricas

ISDC International Structure for Decommissioning Costing (ISDC) of Nuclear Installations - 2012, NEA/OECD

6

Page 7: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

4. PDP – Preliminary Decommissioning Plan -II. Schedule - Life extension assumed

Transition Period Safe Storage ~35years

RV / Internals / Large Comp

Rem. and Decont Systems.

Demol / Site Restor.

7

Planning

2062 (2042 with no LTO)

2082

2093

• Transition Period Cost not included 1st DCE-

operational RW and SF.

>>> to be included – After CNEN requirement

• 40 years of operation + 20 years of life extension

• Angra 1/ 2 / 3 - reactor vessel and internals will

be removed sequentially.

2045 (2025 with no LTO)

Safe Storage ~20 years

Page 8: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Desmantelamento imediato

Desmantelamento protelado

4. PDP - III – Decommissioning Cost Estimate (DCE)

8

INPUTS OUTPUTS

1E, 1G 3A DECOM PLANNING S3

OUTPUTS 1E, 1G 3B ACTIVITY PREPARATION S5, S7

1A SCHEDULE S1, 6I

1B PRODUCTIVITY LOSS FACTORS 4A, 4B, 5A, 6E

1C TAX

1D CONSUMABLES 4A, 4B, 5A, 6*, 7E, 7F

1E UTIL STAFF RATES 3A, 3B, 7C INPUTS OUTPUTS

1F CONTRACTOR RATES 7D 1B, 1D, 1H 4A UCF CLEAN 4C

1G SKILLED LABOR RATES 1H, 1J, 7C, 7D 1B, 1D, 1H 4B UCF CONTAMINATED 4C

1H DISMANTLE CREW RATES 4A, 4B, 5A, 6*, 7E, 7F 4A, 4B 4C UCF SUMMARY 4D, 4F

1J COMPONENT CREW RATES 6B, 6C, 6G, 6H 4C, 1K, 2A 4D RAD INVENTORY 4E

1K DISPOSAL RATES 4D, 4F, 5D, 5F, 6F, 6J, 6K 4D 4E RAD SUMMARY S5, S6 INPUTS OUTPUTS

4C, 1K, 2A 4F CLEAN INVENTORY 4G 1A, S2 S1 ANNUAL COST

4F 4G CLEAN SUMMARY S7, S6 S3 - S10 S2 COST SUMMARY S1

3A, 7A, S11 S3 PLANNING S2

S11 S4 SAFSTOR PREP S2

3B, 4E, 5E, 6A, 7A, S11 S5 DISMANTLE S2

INPUTS OUTPUTS 4E, 4G, 5E, 5G, 6A, S11 S6 WASTE S2

OUTPUTS 1B, 1D, 1H 5A UNIT COST FACTORS 5C 3B, 4G, 5G, 6A, 7A, S11 S7 DEMOLITION & SITE RESTORATION S2

2A SYSTEMS 4D, 4F 5A 5C UCF SUMMARY 5D, 5F 7A, S11 S8 S&M S2

2B STRUCTURES 5D, 5F 5C, 1K, 2B 5D RAD INVENTORY 5E 7A, S11 S9 PROJECT MANAGEMENT S2

5D 5E RAD SUMMARY S5, S6 7A, S11 S10 MISCELLANEOUS S2

5C, 1K, 2B 5F CLEAN INVENTORY 5G S11 CONTINGENCY S3 - S10

5F 5G CLEAN SUMMARY S7, S6

COST FORMAT BASED ON WBS

INPUTS OUTPUTS

6B - 6K 6A SUMMARY S5, S7, S6

1D, 1J 6B STEAM GENERATOR 6A

1D, 1J 6C PRESSURIZER 6A

1D, 1H 6D FUEL RACKS 6A

1B, 1D, 1H 6E UCF Miscellaneous 6A

1K, 6B, 6C, 6D, 6F COMPONENT WASTE 6A

1D, 1J 6G Rx INTERNALS LABOR 6A

1D, 1J 6H Rx VESSEL LABOR 6A

1A 6I REFERENCE PWR 6J, 6K

1K, 6I 6J INTERNALS WASTE 6A

1K, 6I 6K VESSEL WASTE 6A

INPUTS OUTPUTS

1A, 7B 7A Total Cost S3, S5, S7, S8, S9, S10

7C - 7I 7B Monthly Cost 7A

1E, 1G 7C Utility Staff 7B

1F, 1G 7D DGC Staff 7B

1D 7E Equipment 7A, 7B

1D 7F RP Supplies 7A, 7B

7G Severence 7A

7H Insurance 7B

7I Permits and Fees 7A, 7B

TABS

TABS

TABS

TABS

TABS

TABS

TABS

TABS

SUMMARY

INPUTS

MATERIAL TAKEOFFS

UNIT COST FACTORS - SYSTEMS

UNIT COST FACTORS - STRUCTURES

UNIT COST FACTORS - LARGE COMPONENTS

PLAN AND PREPARE

PERIOD DEPENDENT

11 spreadsheets

Based on WBS of ISDC International Structure for Decommissioning Costing

(ISDC) of Nuclear Installations - OECD/NEA(2012).

• Order of magnitude -30% to +50% - PPD2014 - Is not site specific, and usually based on scaling up or

down other estimate similar plants. Is not based on

specific drawings or site information

• Budgetary -15% to +30% - PPD2018 - Based on system and building drawings, layouts and

equipment drawing for major components.

• Definitive -5% to +15% - Based on detailed building, system and equipment

drawings, characterization survey data, one line electrical

and system drawings and plot plants and elevation

drawings. Detailed review of scope and required activities

and their costs.

Methodology & Flowchart

Page 9: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Desmantelamento imediato

Desmantelamento protelado

Confinamento

Unplanned / Prematurely Shutdown - Decommissioning:

I.Voluntary Decision: ETN must meet the requirements laid down by the Regulator Agency in

order to ensure safe implementation of early decommissioning process of the Nuclear Facility and present the financial guarantee for the accomplishment of this activity.

II.Government action: I The Govern must complement the Decommissioning Trust Fund

(DTF)

III.Accident: US$ 500 million issurance for each plant to promote early decommissioning of the

plants.

9

4. PDP - III – Decommissioning Cost Estimate (DCE)

PDP 2014 (10CFR50.75 / NUREG 1307)

DCE

(ISDC)%

Angra 1 $431.600.000 $601.211.984 39%

Angra 2 $529.600.000 $708.292.836 34%

Angra 3 $529.600.000 $665.913.404 26%

Support

Buildings$14.922.904

Total $1.490.800.000 $1.990.341.127 34%

PDP 2014 x DCE 2017

Page 10: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Desmantelamento protelado

Confinamento

4. PDP – IV RADIOACTIVE WASTE AND SPENT FUEL SUMMARY FORESEEN (m3):

a) OPERATIONAL

Angra 1 Angra 2 Angra 3 Total

LLW 1920.52 515.82 574.56 3010.9

ILW 4938.48 405.28 451.44 5795.2

Total 6859 921.1 1026 8806.1

Planned SFAs 2095 2873 2845 7813

Ref.: GMO.O-007/17 – DPR.O / ACS.T

b) DECOMMISSIONING

Ref.: Based on the facility, system and equipment drawings; radiological survey data; past incident reports and plant visits - ENERCON

Angra 1 Angra 2 Angra 3 Support Buildings Total

LLW 7.319 12.941 12.839 639 33.737

LLW - HA 121 194 88 0 403

ILW 91 170 170 0 431

ILW – HA 37 7 227 0 271

HLW 13 62 299 0 374

Total 7.581 13.374 13.623 639 35.216

Clean 312.940 428.145 428.145 49.174 1.218.404

Total + Clean 320.520 441.519 441.768 49.813 1.253.620

10

Page 11: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Fill a detail Gap in the PDP of CNAAA and to attend a requirement of CNEN.

Reasons for Delay and Financial Trouble / Loss in the Transition Period (IAEA, 2004):

I. Unavailability of funds;

II. Early, unplanned and permanent shutdown of a plant - political, regulatory or

economic reasons;

III. Lack of a decommissioning strategy; Lack of infrastructure (Intermediate or Final

Repository) or technology;

IV - Lack of regulation for decommissioning;

V. Loss / demotivation of key people and adaptation to cultural changes;

VI. Lack of planning for the decommissioning made during the operation of the plant.

5. Transition Period Preliminar Planning – Angra 1

Page 12: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Motivos de Desligamento

dos Reatores

Região /

País EUROPA USA Rússia Japão Canadá Total

Reactors closed

having fulfilled

their purpose or

being no longer

economic to run

reatores 61 32 7 11 4 115

Reactors closed

prematurely by

political decision or

others

reatores 33 1 0 2 0 37

Total

reatores 94 33 7 13 4 151

% 62,3 21,9 4,6 8,6 2,6 100

EPRI / NRC + IAEA + International references ~84,2%

5. Main Referencees Research

Shutdown reactors in world- accidents excluded– (WNA, jan 2018)

Page 13: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. EPRI + IAEA – Referencees

2016

2004

2004

+ Lessons Learned

+ Other References

Page 14: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

4.1. Licencing

4.2. Human Resources and Organizational Struture

4.3. Communication Plan

4.4. Historical Site Assessment(HSA) e RW Characterization

4.5. Chemmical Decontamination of Systems

4.6. Cool and Dim planning

4.7. Removal of Inflamable material and transition to a Incipient Fire Brigade (IFB)

4.8. SPENT FUEL MANAGEMENT

4.9. Removal and Reduction of Hotspots

4.10. Asbestos Removal

4.11. Dismantling of systems and non radioactive buildings

4.12. Removal / retirement of systems and review of technical specifications

4.13. Safety Assessment for the TP

4.14. SUMMARY OF ACTIVITIES FOR THE NPP

4.15. COST ESTIMATE FOR TRANSITION PERTIOD – order of magnitude

4.16 Quality Plan and Administrative controls

5. I - Table of Contents of Angra 1 Transition Period Plan

Page 15: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. II - Spent Fuel Management

Figura 16 – Transfering route from Angra 1 and Angra 2 for UAS (Eletronuclear, 2016)

ISFSI to be constructed until 2020

– UAS (Unidade de Armazenamento a seco)

Under licencing and project phase

Plants Storage Capacity

(cels) Cels being used

SFA inside the

core

End of capacity

forecast

Angra 1 1.252 978 121 Dez/21

Angra 2 1.084 756 193 Jul/21

Page 16: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. II - UAS – ISFSI – Dry SF Storage

VERTICAL or Horizontal – BID to choose

Short Schedule

Worldwide implemented (+90 plants)

More than 2300 implemented

CNEN resolution 199 Jul/2016 >> Certified solution

following NRC licencing

- RG 3.62 (Std Format and Content for the SAR for Onsite

Storage of SFS Casks) -

NUREG 1567 (Std Review Plan for SF Dry Storage

Facilities) - 10

CFR 72 – Licensing Req for the ISSF and HLW)

Expandable – 15 >> 72 >> +2 x 90

HOLTEC INTERNATIONAL - BID Winner – Turn Key

33 NPPs >> 706 Canisters, >> 36.336 SFAs

Page 17: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. II - UAS – ISFSI – 1st phase

~ 5 operation cycles of Units 1 e 2:

Angra 1: 222 SFAs - 6 Overpacks

Angra 2: 288 SFAs - 9 Overpacks

Total: 510 SFAs - 15 Storage Overpacks

Transport cask Canister

Overpack

Storage

Angra 1

Angra 2

Traport Vehicle

Page 18: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. II - CNAAA - Spent Fuel Inventory

Storage place Angra-1

Capacity Occupied

New Fuel Storage Room 45 0

Region 1 Spent Fuel Pool 252 168

Region 2 Spent Fuel Pool 1,000 810

Reactor Core 121 121

Total of Spent Fuel (Reactor Core + SFP) 1099

Storage place Angra-2

Capacity Occupied

New Fuel Storage Room 75 0

Region 1 Spent Fuel Pool 264 44

Region 2 Spent Fuel Pool 820 712

Reactor Core 193 193

Total of Spent Fuel (Reactor Core + SFP) 949

Updated June/2018

Page 19: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. CNAAA - Spent Fuel Inventory – FAILED /DAMAGED

ANGRA 1 - FUEL ASSEMBLY RECONSTITUTION EQUIPMENT (FARE)

ANGRA 2 - FUEL ASSEMBLY RECONSTITUTION UNIT (FARU)

NPP FA FAILED / DAMAGED CYCLE ACTUAL STATUS Burnup during failure (MWD/MTU)

ANGRA 1 F27 FAILED 4 REPAIRED 5.909,60 ANGRA 1 M06 FAILED 14 FAILED 17.154,00

ANGRA 1 S05 DAMAGED 10 REPAIRED 14.263,70

ANGRA 1 T13 FAILED 13 FAILED 38.752,70

ANGRA 1 U06 FAILED 14A FAILED 37.526,70 ANGRA 1 U27 FAILED 14 FAILED 34.596,90 ANGRA 1 U37 FAILED 12 REPAIRED 18.242,10 ANGRA 1 V05 FAILED 14 REPAIRED 20.432,80 ANGRA 1 V24 FAILED 14A FAILED 23.377,60

ANGRA 1 W12 FAILED 14 FAILED 5.913,10 ANGRA 1 W16 FAILED 14 FAILED 5.849,10

ANGRA 1 W24 FAILED 14A FAILED 10.267,60 ANGRA 1 X26 FAILED 16 FAILED 31.573,90

ANGRA 1 AC02 DAMAGED 22 DAMAGED 46.462,60 ANGRA 1 AC38 DAMAGED 20 DAMAGED 29.567,70

ANGRA 1 AF40 DAMAGED 22 DAMAGED 20.519,40

ANGRA 2 106 FAILED 1 REPAIRED 19.603,21

ANGRA 2 144 FAILED 2 REPAIRED 31.359,29

ANGRA 2 C033 FAILED 4 REPAIRED 15.435,98

ANGRA 2 H036 FAILED 11 FAILED 42.784,30 ANGRA 2 J027 DAMAGED 11 DAMAGED 35.971,50

SFA - REPAIRED

Page 20: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. II - UAS Dry Storage Summary Schedule

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Planejado

Previsto

Realizado

Transferência Angra 1

Nota: Cronograma Executivo Geral - rev. 1

LEGENDA

2020 2021

CONTRATAÇÕES

LICENCIAMENTO

EXECUÇÃO DE PROJETOS

IMPLEMENTAÇÃO

2017 2018 2019

Obras Preparatórias

Implantação

Transferência Angra 2

Status: 31/12/17

A T I V I D A D E S

2015 2016

27/08/2020

14/01/2021

PROCUREMENT

LICENCING

SUMMARY

EXECUTION

Civil Works

Implementation

Angra 2 SF transfer

Angra 1 SF transfer

Executed

Planned updated

Planned

Aug./2020

Jan./2021

~11 months of margin until completion of SFP capacity

Page 21: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. III - Activities Summary – Transition Period of Angra 1

1. PRE-PLANNING 1.1. Licensing planning

• Certificate of Permanent Termination of Operation and Removal of SFA

• Post shutdown decommissioning activities report (PSDAR)

• Review of the DCE and Transition Period Costs

• Irradiated Fuel Management Plan (IFMP)

• License Termination Plan (LTP)

• Post Defueled Technical Specifications Request (PDTS)

• Permanent Shutdown Emergency Plan (PSEP)

• Physical Protection Plan for Permanent Shutdown and Exception Requests

• Prepare a Quality Management Plan without SFAs

• Requalification Program for Operators / Fuel Handling Training and Certification Program (CFH)

• Request exclusions from the nuclear insurance policy

• Specific Safety Analysis for the Transition Activities

• FSAR review considering permanent shutdown

1.2. Review of programs and procedures

1.3. Review and Analysis of HSA / Updated Radiometric Survey

1.4. Hazardous material survey and analysis

1.5. Preparation of contract with support consulting company

1.6. Planning for Cool and Dim Condition

1.7. Communication Plan

1.8. Human Resources Plan with organizational restructuring of the company during the TPA1.

2. PERMANENT SHUTDOWN ACTIVITIES 2.1. Plant Shutdown and Inspection

2.2. Removal of SF and materials

2.3. Draining and drying all systems that are unnecessary

2.4. Sampling for characterization of radiological inventory

2.5. Removal of fluids from systems (water, oils, etc.)

2.6. Chemical decontamination of systems for dose reduction (if applicable)

2.7. Removal of decontamination waste

2.8. Removal of combustible material

2.9. Removal of used resin

2.10. Removal of other radioactive waste from operations

2.11. Electrical isolation of equipment

2.12. Asset recovery: resale / transfer of plant equipment and components such as surplus stock to other licensed facilities (contaminated material) and

unlicensed (uncontaminated material)

Page 22: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

3. EQUIPMENT CONTRACTS AND GENERAL MATERIALS 3.1. General equipment for dismantling

3.2. General equipment for decontamination of personnel and tools

3.3. General equipment for radiological protection

3.4. General Physical Security Equipment and Maintenance for Long Term Storage Safe Storage

3.5. Acquisition of casks for SFAs

3.6. Acquisition of transfer casks for LLW / ILW / HLW to the final repository (to be built)

4. SAFE STORAGE PREPARATION ACTIVITIES 4.1. Decontamination of areas and equipment to facilitate dismantling (if decided for specific cases)

4.2. Drainage of the SFP and decontamination (if applicable)

4.3. Dismantling and transfer of contaminated equipment and material for long-term storage / Final repository of radioactive waste

4.4. Sampling for the characterization of the radiological inventory in the facilities for the safestorage

4.5. Site reconfiguration, isolation and protective structures

4.6. Characterization of the radiological inventory for decommissioning and decontamination

4.7. Preparation of the temporary RW storage area (if necessary)

4.8. Removal of fuel handling equipment (if necessary)

4.9. Personal training

4.10. Asset recovery: Sale / transfer of the metal or materials and equipment saved or components for recycling or reuse (partial)

4.11. Cool and Dim Condition Implantation

4.12. Evaluation and removal of hotspots (where applicable)

4.13 SITE PHYSICAL SAFETY PLANNING, MONITORING AND MAINTENANCE DURING SAFE STORAGE

4.13.1. Operation of physical security and site surveillance

4.13.2. Inspection and maintenance of buildings and systems in operation

4.13.3. Site conservation

4.13.4. Energy and water supply

4.13.5. Radiological and environmental periodic survey

5. III - Activities Summary – Transition Period of Angra 1

Page 23: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

5. PROCESSING RADIACTIVE WASTE, STORAGE AND DISPOSAL 5.1. Radioactive Waste processing, storage and safety analysis for disposal

5.2. Feasibility studies on waste transport

5.3. Special permissions, packaging and transportation

5.4. System fluids (water, oils, etc.) processing

5.5. Decontamination waste processing

5.6. Operation Fuel Material processing

5.7. Spent Resins processing

5.8. Other nuclear and hazardous materials from facility operations

5.9. Storage of waste from operation

5.10. Disposal

6. PROJECT MANAGEMENT, ENGINEERING AND SUPPORT 6.1. Mobilization and preparatory work

6.2. Project and engineering management services

6.3. Public relations

6.4. Support Services

6.5. Radiotiological Protection

6.6. Restructuring Human Resources

7. RESEARCH AND DEVELOPMENT 7.1. Research and development of the decontamination process, measurement of radioactivity and dismantling processes, tools and not usual equipment

7.2. Simulation and modeling of more complicated tasks

7.3. Search for international experiences and updated lessons learned

8. SPENT NUNCLEAR FUEL MANAGEMENT 8.1. SNF transportation to UAS

8.2. Transportation for final Disposal (when ready)

5. III - Activities Summary – Transition Period of Angra 1

Page 24: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Assumptions: • Experiences with the Transition from Operation to Decommissioning at NPPs on the U.S. (Kim &

McGrath, 2016)

>> 43,5% Human Resources - of the cost of the Decommissioning

• Actual Staff of Angra 1 operation and maintenance

• Medium Brazilian salary estimate + taxes and other tributes (still to be updated with

ETN real salaries)

• 3 to 5 years of Transition Period Duration

• Convervative estimative

5. IV - COST ESTIMATE FOR TPA1 – order of magnitude

Duração (meses) Total Cost TPA1 (order of magnitude) * 36 R$ 343.423.256 $ 105.668.694

48 R$ 457.897.674 $ 140.891.592

60 R$ 572.372.093 $ 176.114.490

>> Approximate staffing costs during transition period in U.S. - $25 Million/year

(Kim & McGrath, 2016)

* Transition Period Initial Planning for Angra 1 (Pinho, Bruno Estanqueira, 2018)

Link: http://www.con.ufrj.br/wp-content/uploads/2018/05/Disserta%C3%A7%C3%A3o-Bruno-Estanqueira-Pinho.pdf

Page 25: Preliminary Plan for Decommissioning and Post Shutdown ... · Preliminary Plan for Decommissioning and Post Shutdown Activities of Brazilian NPPs Bruno Estanqueira Pinho Fuel Assembly

Desmantelamento imediato

Desmantelamento protelado

Confinamento

Thank you!