prefeasibility report - welcome to environment€¦ · · 2014-12-08prefeasibility report for...
TRANSCRIPT
PREFEASIBILITY REPORT
FOR
“Proposed capacity expansion of existing
facility”
BY
Indian additives LTD
AT
VILLAGE: Manali
Taluk: Thiruvottiyur
DISTrict: Thirvallur
STATE: TAMIL NADU
i
Table of Contents 1. EXECUTIVE SUMMARY ........................................................................................................ 1
2. INTRODUCTION OF THE PROJECT ................................................................................... 3
2.1 Introduction about the company .................................................................................................. 3
2.2 Brief Description of the Project ..................................................................................................... 3
2.3 Project Benefits ...................................................................................................................................... 4
3. PROJECT DESCRIPTION ...................................................................................................... 5
3.1 Type of the Project ............................................................................................................................... 5
3.2 Project Location ..................................................................................................................................... 5
3.3 Products Manufactured ..................................................................................................................... 7
3.4 Manufacturing Process Description ............................................................................................ 7
3.4.1 Succinminde unit ......................................................................................................................... 7
3.4.2 PIBSA (Poly Iso Butylene Succinic Anhydride) unit ................................................... 8
3.4.3 Phenates/Sulfonate Unit .......................................................................................................... 9
3.4.4 Blending Unit .............................................................................................................................. 11
3.5 Raw Material Requirement ........................................................................................................... 12
3.6 Utilities .................................................................................................................................................... 13
3.7 Power and Fuels ................................................................................................................................. 14
3.8 Water Requirement .......................................................................................................................... 15
3.9 Landuse .................................................................................................................................................. 16
3.10 Manpower ............................................................................................................................................. 16
3.11 Liquid Waste Management ........................................................................................................... 16
3.11.1 Treatment of Lquid Waste ................................................................................................... 17
3.11.1.1 Effluent Treatment Plant (ETP) Description .......................................................... 17
3.12 Air Pollution Control Measures................................................................................................... 21
3.13 Hazardous and Solid waste Management .............................................................................. 23
3.14 Greenbelt Development .................................................................................................................. 24
3.15 Environment, Safety and Health Monitoring ........................................................................ 24
4. SITE ANALYSIS ................................................................................................................... 27
4.1 Connectivity.......................................................................................................................................... 27
4.2 Land form, land use, land ownership ....................................................................................... 27
4.3 Existing land use pattern ............................................................................................................... 27
ii
4.4 Climatic Conditions ........................................................................................................................... 27
4.5 Social infrastructure available..................................................................................................... 28
5. Conclusion ........................................................................................................................... 30
List of Tables
Table 1.1 List of products – Existing and Proposed ............................................................................... 2
Table 3.1 List of Products existing and Proposed ................................................................................. 7
Table 3.2 List of Raw materials ..................................................................................................................... 12
Table 3.3 Capacity of DG, Boilers and Thermic fluid Heaters ......................................................... 13
Table 3.4 Power and Fuel requirement ..................................................................................................... 14
Table 3.5 Water Requirement and Recycling ......................................................................................... 15
Table 3.6 Land Use within the Site .............................................................................................................. 16
Table 3.7 Wastewater Generation ............................................................................................................... 16
Table 3.8 Existing APC Measures for the production. ........................................................................ 22
Table 3.9 Hazardous wastes Generation ................................................................................................. 23
Table 3.10 Non-Hazardous wastes ............................................................................................................ 24
Table 4.1Nearby areas from site Boundary ............................................................................................ 27
Table 4.2 Meterological Observations ....................................................................................................... 28
Table 4.3 Proposed project surrounding features ............................................................................... 29
List of Figures
Figure 3.1 Location of Proposed Project Site............................................................................................. 6
Figure 3.2 Satellite Image of the Site & its 10Km Radius ..................................................................... 6
Figure 3.3 Dispersants process flow diagram ........................................................................................... 8
Figure 3.4 PIBSA process flow diagram ....................................................................................................... 9
Figure 3.5 Phenate process flow diagram ................................................................................................ 11
Figure 3.6 Blending process flow diagram ............................................................................................. 11
Figure 3.7 ETP and STP Process Flow Disgram ..................................................................................... 20
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
1
1. EXECUTIVE SUMMARY
Indian Additives Limited (IAL) is a 50:50 joint venture company of Chennai
Petroleum Corporation Limited (CPCL) and Chevron Oronite Company LLC. On
24th May 1989, Chevron Oronite Company LLC, USA (then Chevron Chemical
Company) and Chennai Petroleum Corporation Limited, Chennai (then Madras
Refineries Limited) signed an agreement to form a Company to engage in the
development, manufacture and marketing of certain additive intermediates,
(components) and packages for Lubricating Oils. The Company, christened as
‘Indian Additives Limited’, was thus born legally on 13th July 1989,the plant has
been operational since 1993. IAL was originally incorporated as a government
company to foster domestic manufacture of lubricating oil additives so as to
reduce reliance on import of such products. IAL’s operation has, therefore, has a
bearing on increasing national foreign exchange savings through import
substitution.
The manufacturing facilityis located at SF No. 265(P) Manali Village,
AmbatturTaluk, Tiruvallur District, and Tamil Nadu in a spread of 23.57 acres
land. The site is located about 4 km away from Thiruvottiyur Town and it is in the
express highway connecting Thiruvottiyur and Ponneri. The site is located south
of this road. The nearest railway station is Thiruvottiyur.
IAL proposes to expand the capacity of its existing manufacturing facilityto meet
the growing market demand in lubricating oil additives. The proposed expansion
activity is planned through debottlenecking with some minor investments, with
out change in process, raw materials and products. The expansion project scope
mainly involves addition of inline blenders, pumps and enhancement of vessels/
storage tanks.The cost estimate for the proposed capacity expansion will be
around Rs.12 crores and implementation period will be 10-12 months.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
2
Table 1.1 List of products – Existing and Proposed
S.No Product Existing Proposed
MT/annum
1 Automotive, Marine,
Industrial, Rail Road
and Natural gas
engine Lubricating Oil
additive packages.
25000 60000
2 Succinimides 10000 25000
3 Phenate/sulfonate 10000 20000 4 PIBSA 8500 20000
5
By product (Mix of sodium sulphide, sodium hydrogen sulphide& caustic)
3500 7000
IAL has valid consent orders under Air & Water Acts for the manufacturing of
products against existing capacities.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
3
2. INTRODUCTION OF THE PROJECT
2.1 Introduction about the company
Indian Additives Limited (IAL) is a 50:50 joint venture company of Chennai
Petroleum Corporation Limited (CPCL) and Chevron Oronite Company LLC.
The plant has been operational since 1993. IAL, an ISO 14001 certified
company, is one of the leading manufacturers of lubricating oil additives for
Automotive, Marine, Industrial, Rail Road & Natural gas engines lubricating
oils. These lubricating oil additives play a crucial role in engine performance
parameters like high specific power outputs, improved fuel-efficiency norms,
improved driveability, extended drain Intervals, fuel economy and longer and
trouble - free engine life.IAL primarily caters to sectors of national and public
interest as a majority of IAL’s products are manufactured to meet the
requirements of the Indian Railways, and government companies such as
Indian Oil Corporation, Bharat Petroleum Corporation Limited and Hindustan
Petroleum Corporation Limited.IAL’s operation has, therefore, has a bearing
on increasing national foreign exchange savings through import substitution.
IAL has been operating with valid consent orders under Air & Water Acts
from TamilNadu Pollution Controal Board and complying with all
environmental legislations. IAL has initiated many Environmental
improvement actions towards improving its Environment standards like
installation of online pollution monitoring systems and hooking up to
Pollution Control Board for real time monitoring.
2.2 Brief Description of the Project
IAL’s existing manufacturing facility consists of intermediates (components)
and blending facilities for making different lubricating oil additive packages .
The intermediates (components) manufacturing involves batch processes to
produce Dispersants(Succinimides), Detergents(Phenates/Sulfonate), PIBSAs.
Blending is the key operation where the aboveintermediates (components)
made within IAL and other intermediates (components) imported from other
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
4
Chevron Oronite facilities are blended to make different lubricating oil
additive packages based on market requirements. IAL is planning to expand
the capacity of all the above manufacturing facilities through debottlenecking
to meet the growing market demand in lubricating oil additive segment. The
expansion project scope mainly involves addition of inline blenders, pumps
and enhancement of vessels/ storage tanks.. Utility & off-site requirements
will be met by existing units which have enough capacity margins to support
proposed expansion. The cost estimate for the debottlenecking items
involved in proposed capacity expansion will be around Rs.12 crores and
implementation period will be 10-12 months.
The proposed capacity expansion does not require any new process or new
raw materials. Hence there will not be any new pollutants on account of this
expansion except for increase in loads due to high volumes. The existing
effluent treatment plant and other treatment systems have adequate design
capabilities to handethe additional pollutant loads from expansion as there
are no changes in characteristics.
2.3 Project Benefits
The proposed capacity expansion will enhance the Indigenous availability of
lubricating oil additives to meet the growing rquirements in automobile,
marine and industrial segments. This expansion will also help to boost the
economy of the countrythrough additional revenues and import substitutions.
The existing Plant has around 120employees and 200contract workmen
supporting all operational activities and there will be a marginal increase in
manpower after proposed capacity expansion, 140employees and 260
contract workmen. Apart from this, there will also be a considerable increase
in indirect employment on account of this proposed expansion.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
5
3. PROJECT DESCRIPTION
3.1 Type of the Project IAL proposes to expand the capacity of all the existingmanufacturing facilities
through debottlenecking with some minor investments. The expansion
project scope mainly involves addition of inline blenders, pumps and
enhancement of vessels/ storage tanks.. Utility & off-site requirements will be
met by existing units which have enough capacity margins to support
proposed expansion.The proposed project falls under the schedule 5 (f) as per
the EIA notification dated September 14, 2006 and its amendments. There is
no interlinked project.
3.2 Project Location The proposed expansion project is planned with in the existing manufacturing
facility located at SF No. 265(P) Manali Village, Thiruvottiyur Taluk, Tiruvallur
District, and Tamil Nadu. The site is located about 4 km away from
Thiruvottiyur Town and it is in the express highway connecting Thiruvottiyur
and Ponneri. The site is located south of this road. The nearest railway station
is Thiruvottiyur. The location of the site is shown in Fig. 3.1. The plot plan of
the site with facilities is enclosed in Annexure-4.
The Project site with coordinates isgiven in Figure 3.1. The 10 Km radius
map from the project is given in (Fig 3.2).
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
6
Figure 3.1 Location of Proposed Project Site
Figure 3.2 Satellite Image of the Site & its 10Km Radius
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
7
3.3 Products Manufactured The list of products proposed is given in Table 3-1 below.
Table 3.1 List of Products existing and Proposed
S.No Product Existing Proposed
MT/annum
1 Automotive, Marine,
Industrial, Rail Road
and Natural gas
engine Lubricating Oil
additive packages.
25000 60000
2 Succinimides 10000 25000
3 Phenates/sulfonates 10000 20000 4 PIBSAs 8500 20000
5
By product (Mix of sodium sulphide, sodium hydrogen sulphide& caustic)
3500 7000
3.4 Manufacturing Process Description The process units built for Additives manufacturing are as under:
Dispersant ( Succinimides) plant
Detergent (Phenate / Sulfonate) plant.
PIBSA Plant (Raw material for Dispersant plant)
Blending plant (final blended products -Automotive, Marine, Industrial,
Rail Road,& Natural gas lubricating Oil engine additive packages. )
A brief process description is given below:
3.4.1 Succinminde unit
The Succinimides unit consists of a batch agitated reactors and overhead
collection systems. Succinimides are produced by reacting Poly Iso Butyl
Succinic anhydride (PIBSA) and Heavy polyamine (HPA) mixture in typical
proportions. PIBSA and HPA are reacted in the reactor at typical process
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
8
conditions. The reactor overhead systems collects water formed during the
reaction, along with the nitrogen used in the reactor to help sweep water
vapour. A vent stream consisting of nitrogen is produced from the overhead
system which is discharged through a high point vent system. The product
from the reactor is stored in storage tanks and used in blending plant for
making finished lubricating oil additive packages.Different types of
succinimides are manufactured in this unit by based on the requirement in
blending plant.
Figure 3.3 Dispersants process flow diagram
3.4.2 PIBSA (Poly Iso Butylene Succinic Anhydride) unit
PIBSA is an intermediate chemical that is used as key raw material for the
production of succinimides. PIBSA is formed by reacting poly iso-butene with
maleic anhydride. The operation is done in batches.
The PIBSA plant includes a hot oil coiled reactor, a reactor overhead system
with steam ejectors and a filtration section. Polybutene is charged with
excess maleic anhydride to the reactor. After the reaction, excess Maleic
anhydride is stripped and reused back in next batches. A condensate stream
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
9
containing trace quantities of Maleic acid and a vent stream consisting mostly
of air leaks into vacuum system are discharged to the overhead system which
is been scrubbed with water being discharged through vent. From the
reactor, crude PIBSA is transferred to intermediate tank and then filtered.
The filtrate is transferred to the intermediate storage tanks. The remnants
left in the filter are filter cake which was collected in barrels and disposed as
hazardous wastes as per authorization approval from PCB. Different grades
of PIBSA are manufactured in this plant.
Figure 3.4 PIBSA process flow diagram
3.4.3 Phenates/Sulfonate Unit
Phenates are classified functionally as detergents. This is produced by
reacting alkyl phenol with lime, sulfur and carbon dioxide in the presence of
promoters such as ethylene glycol, Do Decyl alcohol, and sulfonic acid /
Sulfonate. The Phenate plant consists of hot oil coiled reactors, reactor
overhead system with steam jet ejectors a recovery section to recycle the
promoters, and a filtration section.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
10
The Phenate manufacturing operation is a batch process. The promoters and
diluents oil are premixed with alkyl phenol before charging to the reactor.
The remaining ingredients are charged in subsequent steps to form the
active Phenate.
Hydrogen sulfide and water are formed during part of this reaction sequence.
They are stripped through the overhead system.
Waste Gas containing Hydrogen Sulfide (H2S) is scrubbed in Caustic
scrubber unit, where H2S is fully absorbed in Caustic Lye and a byproduct
Spent Caustic is produced. Glycol, water, alcohol and oil are recovered from
the reactor overhead system and are separated in a water-glycol-oil
separator. The alcohol- oil stream is sent to an alcohol-oil recycle tank. The
wet glycol is sent to a glycol tank for recovery. The recovered alcohol and
glycol are being reused in the process. From the reactor the crude Phenate
product is sent to the filtration section for filtration. The final product is
stored in intermediate storage tanks and being used in blending plant for
making lubricating oil additives. The remnants left in the filter are filter cake
which was collected in barrels and disposed as hazardous wastes as per
authorization approval from PCB. Different types of detergents are
manufactured in this plant using similar raw materials.
In the same unit, Sulfonate is manufactured by reacting Sulfonic acid with
Lime, 2 Ethyl Hexanol, Calcium Chloride, Acetic acid and Formic acid in a
similar process. From the reactor, the crude Sulfonate is sent to the filtration
section for filtration. The final product is stored in intermediate storage
tanks and being used in blending plant for making lubricating oil additives.
The remnants left in the filter are filter cake which was collected in barrels
and disposed as hazardous wastes as per authorization approval from PCB.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
11
Figure 3.5 Phenate process flow diagram
3.4.4 Blending Unit
Various components both manufactured within IAL and imported from other
Chevron Oronite facilities are blended in batch and continuous inline
blenders to make different lubricating oil additive packages. The product is
pumped in to finished storage tanks, or directly loaded in road tankers or
packed in MS barrels for dispatch to customers.
Figure 3.6 Blending process flow diagram
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
12
3.5 Raw Material Requirement
The raw material requirementsaredetailed in the Table3.2.
Following list of raw materials are used in the manufacturing of lubricating oil
additives and related intermediates. Raw materials are sourced locally as well
from global locations based on the requirement.
Table 3.2 List of Raw materials
S.No Raw Material Existing After Expansion
MT/Annum
1. 2 Ethyl Hexanol 43.0 86.0
2. Acetic Acid 6.0 13.0
3. Alkyl Phenol 3157.0 6314.0
4. Boric Acid 52.0 130.0
5. Calcium Chloride 7.0 14.0
6. Carbon-di-Oxide 434.0 869.0
7. Caustic Lye (100%) 708.5 1415.4
8. D.M. Water 1.8 3.6
9. Ethylene Carbonate 729.0 1823.0
10. Filter Aid-Coarse 105.3 210.7
11. Filter Aid-Fine 75.4 173.8
12. Formic Acid 2.4 5.8
13. Heavy Polyamine-HPA/DETA Mix 55.0 138.0
14. Heavy Polyamine-Pure 338.0 845.0
15. HR PIB 1000MW 758.0 1782.0
16. HR PIB 2300MW 4838.0 11384.0
17. IsoDecyl Alcohol 130.0 261.0
18. Maleic Anhydride 452.0 1064.0
19. Molybdenum Tri Oxide 60.2 150.5
20. Mono Ethylene Glycol 484.1 988.2
21. Mono Methyl Amine-MMA 18.1 36.1
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
13
S.No Raw Material Existing After Expansion
MT/Annum
22. Paraformaldehyde 25.0 50.0
23. Slaked Lime 1548.6 3098.2
24. Sulfonic Acid 862.0 1726.0
25. Sulfur 491.3 982.9
26. Lube Oil 150N 8562.0 22543.0
27. Imported Additive Components 3000.0 7200.0
Note: All raw materials consumptions are subject to change based on change in
product mix depending on market demand.
3.6 Utilities
The utility requirements for the proposed capacity expansionwill be met from
existing facility which have capacity margins. Details of the utilities are listed in
Table 3.3
Table 3.3 Capacity of DG, Boilers and Thermic fluid Heaters
Details Capacity Fuel
Existing Proposed
Boilers 1x 5.0 TPH
1x 6.5 TPH
1x 5.0 TPH
1x 6.5 TPH
Furnace Oil
Thermic Fluid Heaters 2x 0.6MMKCal/hr
1x 2.0 MMKCal/hr
2x 0.6 MMKCal/hr
1x 2.0 MMKCal/hr
Furnace Oil
DG Sets 2x 550 kVA
1x 1010 kVA
1x 1500 kVA
2x 550 kVA
1x 1010 kVA
1x 1500 kVA
HSD
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
14
3.7 Power and Fuels
Power requirement is being met from TNEB and third party producer.However,
DG sets are available to back-up power requirement during power restrictions
by TNEB. The current power requirement is 5,50,000 KWH/month. After
proposed capacity expansion, the power requirement will be 7,50,000
KWH/month. However existing DG sets are adequate for future back up
requirements in case of power disturption.
The unit uses furnace oil as the main fuel for its package steam boilers and
thermic fluid heaters. Diesel fuel is used for DG generators based on the
utilization. Currently, the unit consumes around 250KL/month of FO and around
60*KL/month of Diesel. After proposed capacity expansion, FO consumption will
be around 400 KL/month and Diesel consumption will be around 80*KL/month.
Details of the power and fuel requirements are listed in Table 3.4
Table 3.4 Power and Fuel requirement
Details Capacity Source
Existing Proposed
Power Requirement 550000
KWH/Month
750000
KWH/Month
TNEB/ Third party
producer
Fuel oil for Diesel
generators (HSD)
60* KL/month
80* KL/month
PSU Oil companies
Fuel oil for Boilers &
Thermic Fluid heaters
(Furnace Oil)
240 KL/month
400 KL/month PSU Oil companies
* Consumption based on current power restrictions and may varybased on
changes in restrictions from TNEB.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
15
3.8 Water Requirement
The total requirement of raw water for the existing unit is 175 KLD and after
proposed capacity expansion, the raw water requirement will be 245 KLD.
Entire water requirement will be met from Chennai Metro Water Corporation
(CMWSSB) and there is no bore well source inside the Plant premises. Water
requirement for the proposed project is given in Table 3.5 . The agreement for
water supply is enclosed in Annexure-5
Table 3.5 Water Requirement and Recycling
S.
No
Description Existing
KLD
Proposed KLD
A Quantity of raw water consumption
1 DM plant 47 66
2 Cooling tower 83 104
3 Caustic scrubber 15 30
4 Potable water 30 45
5 Floor washings &
Miscellaneous
0 0
6 Total raw water consumption 175 245
B Quantity of effluent generation
1 Effluent from Process 140 196
2 Cooling tower blow down
3 DM plant washings
4 Boiler blow down
5 Sewage 27 40
Total effluent generation 167 236
C Effluent Recycle
1 Water recycle to DM plant 63 89
2 Water recycle to CT plant 16 23
D Water for Gardening 88 124
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
16
3.9 Landuse
There is no change in land distribution after proposed capacity expansion as all
the new equipment will be installed in the spare slots within existing buildings &
layouts. The existing land distribution details are as given in below:
Table 3.6 Land Use within the Site
Land allocation details Area in acres
Building Area 2.10
Roads and drains Area 3.39
Tank farm and yards 4.94
Effluent treatment plant 2.78
Greenbelt development 8.56
Vacant land 1.80
Total Area 23.57
3.10 Manpower
The existing Plant has around 120employees and 200 contract workmen
supporting all activities and there will be a marginal increase in manpower after
proposed capacity expansion, 140 employees and 260 contract workmens.
3.11 Liquid Waste Management
Table 3.7 Wastewater Generation
S.No. Waste Water Details Quantity (in KLD)
Existing After Expansion
1 Effluent from Process
140 196 2 Cooling tower blow down
3 DM plant washings
4. Boiler blow down
5. Sewage (STP) 27 40
Total 167 236
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
17
3.11.1 Treatment of Lquid Waste
Trade effluent streams of total quantity 196 KLD generated from process
are treated in ETP of 300 KLD capacity. Sewage stream of quantity 40 KLD
is treated in STP of 60 KLD capacity. Treated water is partially used for
green belt development and the remaining water is sent to RO plant for
further treatment and recycled to CT and DM plant.
The existing effluent treatement plant and STP facilities are adequate
enough to handle increased effluents from the proposed capacity expansion.
3.11.1.1 Effluent Treatment Plant (ETP) Description
The unit has well established ETP Plant where the combined effluent
from process units and Utility systems are treated through Activated
Sludge aerobic process as detailed below. Sewage effluent is treated
separately in exclusive sewage treatment plant. The treated effluent
meeting PCB norms is then treated in multi stage Reverse Osmosis Plant
for recycle into process while the rejects are concentrated to salts in
multiple effect evaporators for disposal.
There are three effluent streams generated in the plant depending upon
the place of origin.
a) Stream A
Basically consist of process waste water, wash/storm water from
curbed process area, process wash downs, and streams from lab,
pump leakage, storm water from truck loading and tank farm
areas. This stream contains oil and other Chemicals.
b) Stream B
Consist of cooling tower blow down, Boiler blow down and DM
plant regeneration wastes.
c) Stream C
Sanitary waste water – Treated in a Separate Sewage Treatment
Plant (STP)
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
18
The effluent treatment plant basically consists of three sections:
Oil/water separation and oil recovery.
Treatment of separator water and its disposal.
Sludge Digestion, thickening and dewatering
The free-floating oil in the process effluents from various unit
processes is removed by skimmers and corrugated float separator
units. The emulsified oil in the effluent stream is removed by
dissolved floatation techniques. These various steps of oil removal
enable a reduction in the Bio-chemical Oxygen demand
contributed by the oil.
In the oil –water mixture, the free oil due to its relative lower
specific gravity, floats on the surface which is removed by
mechanical skimming. The collected process effluent is pumped to
cross flow separator (CFS) where further free oil is removed. The
effluent from CFS bearing certain amount of emulsified oil and free
oil is sent to Dissolved Air floatation unit (DAF) through a Surge
Pond. The DAF unit acts as secondary treatment in the removal of
oil.
The out let of the DAF unit is sent to Equalization basin where the
utility stream is mixed. The combined effluent is subjected to
biological treatment based on activated sludge system.(Aerobic
Process) An activated sludge unit consisting of an aeration basin
and a clarifier removes dissolved organic contaminants. The waste
biological sludge is sent to a sludge digester where it is further
degraded the water from the digester is sent back for treatment
and the digested sludge is sent to dewatering facility. The
dewatered sludge is sent to solar ponds for drying. The treated
water is pumped to surge pond (west) The treated water is used
for firefighting, gardening. The treated water is partially sent to RO
plant for further processing &recycle to plant for usage in DM
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
19
plant and Cooling Tower and the remaining water is used for
gardening/green belt activities.
The Sanitary waste water (Stream C) is separately treated in a
Sewage Treatment Plant (S.T.P). The treated water is transferred
to Surge pond (West).
The Process flow Diiagram of ETP and STP are given in Figure 3.7
Online monitoring of parameters (pH & TDS) for treated effluent
from ETP done and it is also connected with CAC, TNPCB.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
20
Figure 3.7 ETP and STP Process Flow Disgram
Oxidation Ditch
(T-819)
Chemical sump
(T-802)
Process plant (N-Pit, Hot well)
Utility sump (T-
811)
Sanitary sump (T-
812)
Boiler Blow down & DM Plant
Sanitary waste from plant &
Non plant area
Cross flow
separator
(T-803)
Surge pond
(East)
(T-804)
Dissolved
air
floatation
(T-805)
)
Alum Dosing Poly electrolyte Dosing
Equalization basin
(T-813) Aeration Tank(T-814
aeration tank)
Surge Pond (West)
(Treated water)
9Treated
VAZ Solution
dosing
Sludge for
drying
Final Clarifier (T-820)
Intermediate Sludge
Sump T-818
Sewage
Treatment Plant
Urea & DAP
Over flow sump RO Plant
Recycle
to plant
Gardening
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
21
3.12 Air Pollution Control Measures
The existing package boilers, thermic fluid heaters and DG sets are of high
efficient in terms of combustion control and are featured with in-built pollution
control design. Hence the pollutant load from theseunits will be minimal which
finally been vented through chimneys of appropriate height.
The process vents from intermediates (components) manufacturing facilities are
scrubbed in scrubersfor key pollutants before being discharged to atmosphere.
The unit has also installed online stack monitoring station (CEMS) for Hot oil
stack and boiler stack and connected with Care Air Center (TNPCB). PM, SOX &
NOX are being analyzed. 12 Nos of H2S sensor installed in different areas of plant
permises to monitor H2S. H2S sensor at the caustic scrubber vent is hooked upto
CAC, TNPCB.
The unit has installed Online Ambient Air Quality (AAQ) monitoring station and
it is connected with Care Air Center (CAC), TNPCB. PM10, SOX, NOX, CO, NO, NO2
& 03 are the parameters which are being analyzed. The unit has also installed
continuous VOC monitors in the plant.
Particulars of stacks and vents are detailed in Table 3.8:
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
22
Table 3.8 Existing APC Measures for the production.
Stack No 1 2 3 4 5 6 7 8
Material of
Construction
Carbon
Steel
Carbon
Steel
Carbon
Steel
Carbon
Steel
Carbon
Steel
Carbon Steel Carbon
Steel
Carbon
Steel
Stack
attached to
Common
Stack to 2
Nos. of oil
fired
Boilers
Common
Stack to 3
Nos. of Oil
fired
Thermic
fluid
heater
Exhaust
pipe to
D.G set
550
KVA
Exhaust
pipe to
D.G set
550
KVA
High Point
discharge
via water
scrubber
for PIBSA
reactor
vent
High point
discharge to
Succinimides
Reactor
Vent from
Phenate
reactor
through
Caustic
scrubber
Common
Exhaust
Stack to
1DG set
of 1010
KVA
& 1DG set
of 1500
KVA
Stack Height
(Above the
ground
level)
47 m 30 m 16 m 16 m 22 m 17 m 27 m 30 m
Stack dia at
top (Circular
inside
dimensions)
0.80 m 0.3 m 0.2 m 0.2 m 0.15 m 0.1 m 0.1 m 0.4 m
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
23
There are no additions/changes in existing stacks or process vents on account of
this proposed capacity expansion. How ever, existing air pollution control
measures are adequately sized to handle the increased pollutant loads.
3.13 Hazardous and Solid waste Management
Hazardous wastes from the existing to proposed are increasing, the details of
Hazardous wastes generated are given in Table 3.9. The hazardous wastes
generated from this unit are collected, stored and disposed through authorized
disposal cum recycle facilities as per the authorization from PCB and the unit has
agreements with all waste disposal facilities for the same. There is no internl
disposal facility availability within the site.
The Authorization Letter from TNPCB is enclosed as Annexure-6.
Table 3.9 Hazardous wastes Generation
Category
No. Hazardous wastes
Quantity (MT/ year) Method of Disposal
Existing Proposed
20.3 Distillation residue 800 1250
Collection, Storage and
Disposal for incineration & co-
incineration at authorized
TSDF facilities
5.1 Used/ Spent oil 100 150
Collection, Storage and
Disposal to Authorized
Recycling Agencies.
5.2 Wastes/ residues
containing oil
7 10.5
Collection, Storage and
Disposal incineration & co-
incineration at authorized
TSDF facilities
34.3
Chemical sludge
from waste water
treatment
10 15
Collection, Storage and
Disposal for land fill at
authorized TSDF facilities.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
24
Category
No. Hazardous wastes
Quantity (MT/ year) Method of Disposal
Existing Proposed
34.2
Toxic metal
containing Residue
from used ion
exchange material
in water
purification
0.5 1
Collection, Storage and
Disposal for land fill at
authorized TSDF facilities.
33.3 Discarded
Containers 2500 3500
Collection, Storage and
Disposal to Authorized
Recycling Agencies.
Table 3.10 Non-Hazardous wastes
Details of waste Quantity (MT/ year)
Method of Disposal Existing Proposed
Used paper waste 0.32 0.48 Sold as scrap to authorized
buyers
Food waste 1.08 1.44
Taken back by outsourced
catering service provider for
appropriate disposal
3.14 Greenbelt Development
Greenbelt is already developed inside the factory premises covering a total area
of about 8.56 acres which is more than 33% of the total area. The species and
plantation norms are followed as per the CPCB/ PCB directions.
3.15 Environment, Safety and Health Monitoring
The environment, safety and health-monitoring programme in the factory are as
follows:
Daily monitoring of water and wastewater
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
25
Online monitoring of stack, ambient air, weather and effluent parameters
Fortnight monitoring of ambient air
Monthly monitoring of noise and work place air
Monitoring of occupational safety
Yearly monitoring of occupational health.
To prevent air pollution, IAL has designed and installed the stacks of Boilers, Hot
oil units and DGs asper the guidelines of the central pollution control board
(CPCB). IAL has a robust and a highly reliable caustic scrubber system to prevent
the release of H2S vapours from Detergent plant to the atmosphere.
Online H2S sensor provided in caustic scrubber vent is hooked up with CARE
AIR CENTRE, TNPCB for continuous monitoring. IAL has totally 12 Nos H2S
sensors located in different areas of the plant to monitor and prevent H2S
emissions.
IAL has installed Onlineambient air quality station (AAQ) and online stack
monitoring station (CEMS) and is connected with the Care Air Center, TNPCB. ,
PM10, SOX, NOX, CO, NO, NO2, VOC & 03 are the parameters which are
continuously monitored and displayed. IAL has installed LED display for Online
monitoring of stack, AAQ and effluent parameters in the main gate for public
viewing. IAL has implemented various process improvement measures to reduce
the generation of hazardous wastes in each category. IAL’s hazardous waste
generation has and continues to be well within the limits authorized by the
TNPCB.
In line with IAL's commitment towards environmental protection, IAL has made
considerable amount of investment of around Rs.400 lakhs in the past 2 years
towards various environmental improvement initiatives. Being a company with
significant government investment, IAL is proactive and committed towards
ensuring environmental compliance with applicable laws and standards. IAL has
never failed in complying with the environmental legislations and has always
shown a proactive approach in making its plant one of the best plants in terms of
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
26
environmental management. Local TNPCB officials showcase IAL as a role model
to their counterparts from other States.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
27
4. SITE ANALYSIS
4.1 Connectivity
The proposed site on the SH – 56 and it is in the express highway connecting
Thiruvottiyur and Ponneri. The site is located south of this road.
4.2 Land form, land use, land ownership
The Plant is located at SF No. 265(P) Manali Village, Thiruvottiyur Taluk,
Tiruvallur District, and Tamil Nadu. The present land use is industrial. The land
documents related to the site is enclosed in Annexure-2.
4.3 Existing land use pattern
The present land use is in industrial.zone. The details of sensitive areas from
the site boundary is given in Table 4.1. The site does not fall with in CRZ area.
Table 4.1Nearby areas from site Boundary S.No Name km
Water Bodies
1.
Surplus canal from
Korttalaiyar River
0.13 Km (North)
2. Buckingham canal 0.63 Km (East)
3. Retteri 7.56 Km(South-west)
4. Madhavaram Lake 3.57Km (South West)
5. KadapakkamPanchayat Lake 4.56 Km (North West)
6. Periyathoppu Lake 3.1Km (South West)
7. Bay of Bengal 3.13Km (East)
4.4 Climatic Conditions
The study region receives rainfall predominantly during monsoon season with
an average annual rainfall of about 1211 mm per year. The South west monsoon
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
28
season is from July – September and North east monsoon is from October to
December. The relative humidity recorded in the district is about 49-79%. The
wind directions during the study period are SW-W-WSW and SE. Accordingly,
the impact zone will be spread in NE-E-ENE and NW directions. The average
wind speed observed during the study period is 3 m/sec with the considerable
frequency of a wind range of calm to about 22 km/hour. Due to its proximity
with the Bay of Bengal, the ambient temperature at project site ranged between
25-40°C. The area has a tropical climate with the highest and lowest
temperatures recorded is Maximum of 40.3°C and Minimum of 25°C
respectively.
Table 4.2 Meterological Observations
S.No Parameter Observation
1 Wind Direction SW-SE-W-WSW
2 Wind Speed Range 2 to 8.8 m/sec
3 Annual Average Rainfall 1211 mm
4 Average Wind Speed 3 m/sec
5 Temperature Range Max. Temp: 40°C
Min. Temp: 25°C
6 Average Temperature 32°C
7 Humidity Range (24hr) 49 to 79 %
8 Cloud cover Partly cloudy
4.5 Social infrastructure available
The social infrastructure facilities available near the site are given in Table 4.3.
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
29
Table 4.3 Proposed project surrounding features
S.No. Name km
Schools & Colleges
1. CPLC Polytechnic College 1.70
2. ThirunthangalNadar Arts College 4.05
3. Tamil Nadu Horticulture Institute 4.5
4. Tamil Nadu Veterinary and Animal Sciences
University
4.34
5. Institute of Poultry Production and Management 5.00
Religious Places
1 ThyagarajaSwamy Temple 2.08
2 KalyanaVaradarajPerumalKoil 2.46
3 St. Marys Orthodox Syrian Church 2.58
Hospital
1 Aakash Hospital 2.35
2 Sugam Hospital 2.33
3 Mary Clinic 3.69
4 Vasan Eye Care Hospital 8.17
Prefeasibility Report for Proposed Capacity Expansion of Existing Facility by Indian Additives Ltd.
30
5. Conclusion
Since the proposed project is coming up in the existing plant Industrial area,
there will not be any change in land use.
The proposed project is only expansion of existing capacity so no new pollutants
are added to the environment. However, the increase in pollutant loads are
appropriately handled through dedicated pollution control measures.
The treated waste water will be partly reused for gardening with in the facility
and rest will be recycled for process reuse like Cooling Towers and boiler feed
water make-up after treatement through RO system.
There will be positive impact on Social conditions in and around the site due to
the proposed project.
The marginal impact of proposed capacity expansion with in the existing facility
will be fully mitigated by the Environment Management Plans (EMP).