prefeasibility report recd. from aia on...

21
Prefeasibility report AIA Engineering Limited 1 1 EXECUTIVE SUMMARY AIA Engineering Limited proposes expansion to install induction furnace for the manufacturing of Alloy Steel castings with production capacity of another 2,20,000 MT/year (existing capacity – 1,80,000 MT/year and additional proposed 2,20,000 MT/year to make a total proposed capacity of 4,00,000 MT/year) located at GIDC Kerala, Tehsil – Bavla, District Ahmedabad. The company has its exiting unit operative at Odhav, Moraiya, Kerala GIDC, Ahmedabad. Company now plans to put a expansion project at Plot No.: 1513, GIDCKerala Ind. Estate & Block No. 130, Vil.: Kerala , Ta.: Bavla, Dist.: Ahmedabad. The site is well connected with national highway 8 A and the nearest city is Ahmedabad located at distance of 30 Km. The nearest village is Kerala at distance of 0.5. There is no national park, sanctuary or forest land in surrounding 10 Km radius. The project doesn’t fall under CRZ boundaries. Stack with induction furnace and DG set will be installed for the proposed expansion project along with other utilities stack. The additional water consumption for the proposed expansion project is 700 m 3 /day and the waste water generation will be approximately 210 m 3 /day. The complete quantity shall be recycled back in the system and reused within the plant premises. Slag will be generated due to operation of induction furnace which shall be reused for road construction OR sold to its reusers/ recyclers. Employment shall be generated for local people in surrounding villages. The company is also involved in social activities in the surrounding villages. The detail project including site specific data, raw material consumption, product details, water consumption, socioeconomic structure etc is discussed in the upcoming sections. 2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT 2.1.1 Project Proponent AIA Engineering Limited (AIEL) was established in 1979 and is promoted by first generation entrepreneur Mr. Bhadresh K Shah. The company is second Largest HiChrome casting producer in the world with sales and services in around 75 counties round the globe. AIAEL is Public Limited Company with the shares traded on BSE (Bombay Stock Exchange) and NSE (National Stock Exchange of India) AIA Engineering Limited is niche player in the value added, impact, abrasion and corrosion resistant high chrome metallurgy segment. These components include products like grinding media, liners, diaphragms, vertical mill parts, etc. all manufactured in high chrome metallurgy. Collectively referred to as “mill internals” AIA Engineering, a certified ISO 9001 company, specializes in the design, development,

Upload: ngoquynh

Post on 17-Apr-2018

228 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 1

1 EXECUTIVE SUMMARY AIA Engineering Limited proposes expansion to  install  induction furnace for the manufacturing of Alloy Steel castings with production capacity of another 2,20,000 MT/year (existing capacity – 1,80,000 MT/year and additional proposed 2,20,000 MT/year to make a total proposed capacity of 4,00,000 MT/year) located at GIDC Kerala, Tehsil – Bavla, District Ahmedabad.   The  company  has  its  exiting  unit  operative  at  Odhav,  Moraiya,  Kerala  GIDC,  Ahmedabad. Company now plans  to put a expansion project at Plot No.: 1513, GIDC‐Kerala  Ind. Estate & Block No. 130, Vil.: Kerala , Ta.: Bavla, Dist.: Ahmedabad.  The site is well connected with national highway 8 A and the nearest city is Ahmedabad located at distance of 30 Km. The nearest village is Kerala at distance of 0.5. There is no national park, sanctuary  or  forest  land  in  surrounding  10  Km  radius.  The  project  doesn’t  fall  under  CRZ boundaries.   Stack with  induction  furnace and DG set will be  installed  for  the proposed expansion project along with other utilities stack. The additional water consumption for the proposed expansion project  is 700 m3/day and the waste water generation will be approximately 210 m3/day. The complete quantity shall be recycled back in the system and reused within the plant premises.  Slag will be generated due  to operation of  induction  furnace which  shall be  reused  for  road construction OR sold to its re‐users/ recyclers.  Employment  shall be generated  for  local people  in  surrounding villages. The company  is also involved in social activities in the surrounding villages.  The detail project including site specific data, raw material consumption, product details, water consumption, socioeconomic structure etc is discussed in the upcoming sections.  2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION  2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT  2.1.1 Project Proponent AIA  Engineering  Limited  (AIEL) was  established  in  1979  and  is  promoted  by  first  generation entrepreneur Mr. Bhadresh K Shah. The company is second Largest Hi‐Chrome casting producer in  the world with  sales  and  services  in  around  75  counties  round  the  globe. AIAEL  is  Public Limited Company with the shares traded on BSE  (Bombay Stock Exchange) and NSE  (National Stock Exchange of India) AIA  Engineering  Limited  is  niche  player  in  the  value  added,  impact,  abrasion  and  corrosion resistant high  chrome metallurgy  segment. These  components  include products  like  grinding media, liners, diaphragms, vertical mill parts, etc. all manufactured in high chrome metallurgy. Collectively referred to as “mill internals”  AIA  Engineering,  a  certified  ISO  9001  company,  specializes  in  the  design,  development, 

Page 2: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 2

manufacture,  installation  and  servicing  of  high  chromium  wear,  corrosion  and  abrasion resistant castings used in the cement, mining and thermal power generation industries. Products  find  application  in  the  ‘crushing  and  grinding’  operation  in mills  in  cement,  utility, mining and other industries.  High  chrome metallurgy offers a  lower wear  rate,  compared  to  conventionally used parts of manganese  steel,  nihard  iron,  hyper  steel  and  forgings.  Company  offers  customers  with complete solutions  in grinding  in order to optimize the productivity of the grinding mills. This includes advice on the operational parameters of the mills as well. Additionally, company offers services such as installation supervision and mill process optimization for maximum efficiency.  AIAEL  has  several  years  of  experience  in  supplying  products  to  a  cross‐section  of  industries nationally  and  internationally.  This  has  been  achieved  through  continuous  research  & development and product/ process development activity coupled with acquiring and adapting global  technologies  through  collaborations.  Company  has  a  technical‐cum‐financial collaboration  from  1991  to  2000  with  M/s.  Magotteaux,  Belgium,  a  multi‐national manufacturer of High‐chrome metallurgy based wear and  impact  resistant  cast  components. Presently, AIAEL have a technical collaboration with Southwestern Corporation UK for process improvements relating to Vertical mills. The major product profile includes two types of mills used for the grinding operation: tube mills (which are horizontal) and vertical mills. AIAEL  is  involved  in design, manufacture, supply and services of mill  internals for both vertical as well as horizontal type of mills. The company has existing unit at Odhav, Ahmedabad and not the company proposes to establish install induction furnace at Kerala GIDC, Ahmedabad region.  2.1.2 Identification of Project  The company has existing  foundry unit  located  in Kerala GIDC Plot No.: 1514, 103, 104, 105, 115, 116, 117, 118 and propose expansion of our foundry unit to  install  induction furnace for production of alloy steel castings at Plot nos 1514, GIDC‐Kerala Ind. Estate & Block no. 130, Vil. : Kerala, Ta.  : Bavla, Dist.  : Ahmedabad  (Block No. 130:  Land  is under process of  acquiring by company. And to be used only for green belt development)   The detail of same is given in the table below. 

Table 1: Detail of Proposed Product 

Sr. No. 

Production Item  Capacity as per EC granted (MT/Year) 

Proposed Capacity expansion  (MT/Year) 

Total proposed Capacity  (MT/Year) 

1  Alloy Steel Castings  180000 220000 400000

 

Page 3: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 3

2.2 BRIEF DESCRIPTION OF NATURE OF PROJECT The  project  fall  under  category  B,  section  5(K)  of  EIA  notification  September  2006  and amendment  thereof vide notification no. S.O 3067  (E) dated 1st December 2009. Accordingly the proposed project will be considered at State Level.  2.3 NEED OF PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR REGION With  the  increase  in  the  industrialization  there has been an  increase  in  the demand of  steel products.  The  proposed  product  is  of  alloy  steel  casting  which  will  be mainly  used  in  the grinding units and other utilities of the mining industries, power plants and cement industries. As  there  is  rapid  growth  in  these  industrial  sectors within  the  country  as well  as  globally; accordingly there has been increase in demand for alloy steel product. Henceforth the company proposes to establish unit of alloy steel casting at proposed project site.  2.4 DEMAND SUPPLY GAP In order to meet the requirement in timely manner the proposed project is undertaken. 2.5 IMPORTS VS INDIGENOUS PRODUCTION  Indigenous production will be cost effective as it will reduce the cost of transportation incurred due to import.  2.6 EXPORT POSSIBILITY  The product will be exported to different states of the country as well as to other countries as per the market demands.  The  company will market and  sell products on  the  international market  through  subsidiaries located  in  U.K.,  U.S.A  and  the  Middle  East.  Products  will  be  sold  to  global  cement manufacturers in major countries located in North and South America, Europe, Middle East, Far East and Africa. Company has supply contracts, with global cement manufacturers  like Holcim of  Switzerland,  Lafarge  of  France,  Cemex  of Mexico  through  our  overseas  subsidiaries  and commercial relationships with OEMs like FL Smidth of Denmark, etc. 2.7 DOMESTIC/ EXPORT MARKETS The alloy steel casting shall be exported in domestic market depending on the demand.  The major  client  list  for  cement  industries  in  India  including  ACC  Limited,  Gujarat,  Ambuja Cement Ltd., Ultra‐tech Ltd and Grasim  Industries Ltd.  In  the mining segment, customers will include ferrous and non‐ferrous mineral beneficiation plants like Kudremukh Iron Ore Company Ltd., High‐grade Pellets, Hindustan Zinc, Bharat Aluminium Company. In the utility segment the product shall be supplied to major thermal power plants and OEMs.  2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT The  total employments  (workers  and  staff)  including expansion will be  a 1400.  (Existing 550 employments + additional 850 employments).     

Page 4: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 4

3 PROJECT DESCRIPTION  

3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECT Proposed project is expansion of existing unit. 3.2 LOCATION  (MAP  SHOWING  GENERAL  LOCATION,  SPECIFIC  LOCATION,  AND  PROJECT 

BOUNDARY & PROJECT SITE LAYOUT) WITH COORDINATES  The location of site with type of land and boundary coordinates is as below:  

Table 2: Site location 

Feature  Description

Site  

AIA ENGINEERING LTD.Plot no. 103, 104, 105, 115, 116, 117, 118, 1513 and 1514, GIDC‐Kerala Ind. Estate & Block no. 130, (Block No.  130:  Land  is  under  process  of  acquiring  by company.  And  to  be  used  only  for  green  belt development)  Village: Kerala,  Tehsil: Bavala, Dist.: Ahmedabad.   

Type of land/ land use Industrial  land within the  limits of Gujarat Industrial Development Corporation (GIDC)  

Latitude  Longitude  

22°46'25.81"N72°19'39.98"E 

 Specific location of the plant is as shown in figure 1  

        

Page 5: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 5

 Figure 1: Map showing project location with surrounding features 

 The connectivity of the project site with the major road/ railways/ ports and human settlement is as given below.  

Table 3: Connectivity 

Description  Distance 

Transportation 

Road    : ~ 0.5 Km (NH 8A)           : ~ 0.1 Km (30 m wide GIDC Road) 

Railway : ~ 40 Km (Ahmadabad)  

Nearest Town/City  Ahmedabad city (~ 30 Km)

Nearest Village  Kerala (~ 0.5 Km)

 Satellite map showing the location of site and surrounding features of 10 Km radius  

  

Page 6: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 6

 Figure 2: Satellite map with 10 Km radius 

 The  detailed  lay  out  map  of  the  plant  showing  proposed  project  is  attached  herewith  as annexure 2. 3.3 DETAILS  OF  ALTERNATE  SITES  CONSIDERED  AND  THE  BASIS  OF  SELECTING  THE 

PROPOSED  SITE,  PARTICULARLY  THE  ENVIRONMENT  CONSIDERATIONS  GONE  INTO SHOULD BE HIGHLIGHTED  

No alternative site was considered for the proposed project.  The  suitability of  a  site was determined during  the  installing of  the proposed  facility by  the following major considerations. 

The proposed expansion project location is an adjoin to our existing plot no. 1514  The proposed project location is within the notified industrial estate  No  forest  land, National Park, Sanctuary, Historical Monuments etc present within 10 Km radius of project site. 

Page 7: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 7

Suitability of the land from topographical and geological considerations  Road/ Rail connectivity to the project site for transportation of raw materials, products and employees 

Proximity to human settlement  Availability and supply of water for domestic and industrial purpose from GIDC.    Availability of power from GEB grid  

3.4 SIZE OR MAGNITUDE OF OPERATION  The  company proposes expansion  for  installing  induction  furnace  for manufacturing of Alloy steel  casting with  the  production  additional  capacity  of  220,000 MT/Year  (additional  18333 MT/month).  3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS The details of raw material and the process description are given in this section:   3.5.1 Raw Material Details The major raw material used for the proposed alloy steel casting is metal scrap. The details of raw materials  along with  its  quantity,  source  and mode  of  transportation  is  given  in  table below: 

                   

Page 8: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 8

 Table 4: Details of Raw Materials 

 

           

Item  Quantity for EC granted (MT/Year) 

Quantity for proposed expansion (MT/Year) 

Total Quantity for proposed 

capacity (MT/Year) 

Direct Raw Material 

Various type of M.S. / SS Scrap   162000 198000 360000

Ferro Alloys  24120 29880 54000

Indirect Raw Materials 

Silica sand   109200  133800  243000 

Binders  28800 35200 64000

Secondary Raw Materials 

HSD (Stand by D.G. Set)  840 KL/year 1020 KL/year  1860 KL/year

L. D. O. / C9 (for heat treatment furnace) 

5,400  KL/year 10,200 KL/year  15,600  KL/year

PNG (Natural Gas) (for heat treatment furnaces, tandish, ladle preheating  

12544320 SCM/year 

14400000 SCM/year 

26944320 SCM/year 

Meta Quench Oil (for quenching process) 

840 KL/year 1060 KL/year  1900 KL /year

Salt for regeneration of Softening Plant 

24 MT/year 31 MT/year  55 MT/year

Page 9: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 9

3.5.2 Manufacturing Process

MANUFACTURING  PROCESS  WITH  FLOW – DIAGRAM 

Manufacturing of Alloy  steel castings  involves  the  following  sub processes which  take place in sequence.   

Melting Moulding Pouring & Cooling Heat Treatment Knock out and cleaningPacking and Dispatch 

 Melting :  

 

Metallic  raw materials, mainly  steel and alloy  steel  scrap with  ferro alloys are melted in electrically operated Induction Furnace. The advantage of  induction melting process is  clean melting  operation without  generation of noxious  fume  and  gas. At  full  level, sample  of  the  liquid metal  is  taken  out  and  polished well  and  the  chemistry  of  the metal  is checked on spectrometer before  the metal  is poured preliminary  in  ladle and ultimately poured  in mould/ mould boxes by overhead cranes. A suitable hood will be installed over the melting pot and duct will be connected to a vent along with suitable exhaust fan to vent out fumes of melting. The slag is formed to protect the metal from oxidation and to avoid reduce the melting loss. Excess slag is skimmed off periodically. 

 

Moulding :  

 

Sand moulds are made by preparation of a sand mix, consisting of silica sand with the help of appropriate binders. The mix sand  is sent  to  the appropriate mixer  for proper mixing  with  binder.  The  moulding  is  done  by  mould  making  horizontally  parted machine  or  vertically  parted  mould  making  machine  or  by  hand  moulding.  The prepared  sand  is  filled up  in mould boxes or different  size of mould boxes. which are placed on the vibrating table on the top of the wooden pattern or on floor. As required Top  and  bottom  boxes  OR  Top,  middle  and  bottom  boxes  are  then  closed  and transferred to pouring line. 

 

 

 

Page 10: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 10

Pouring  & Cooling:  

 

Liquid metal of correct temperature and chemical composition will be poured in the ladle from the furnace and then to different mould boxes which are  laid on pouring track. After required cooling of the mould boxes, the moulds are transferred to the knock off area with the help of Vibro process conveying system or E.O.T. crane or on transfer trolley.   

 

Knock out and cleaning:  

 

Cooled mould boxes are transferred to knock off area for separating casting from mould‐boxes and sand  in knock off machine  (Rotary shake out, Breaker drum and Product handling). After separation,  runners  and  risers  are  detached  from  the  casting  and  finally  if  required Grinding/chipping/cleaning  is done  to  remove  residual  sand. On need based,  shot blasting  is done on the casting. 

 

Heat Treatment   Cleaned castings now transferred to heat treatment  furnace. The castings are heat treated  in two different  stages. The quenching  treatment  is  carried out  in Natural gas  fired or Oil  fired continuous heat treatment furnace and in oil quenching tank or water based polymer tank. Also Air quenching  is carried out  in Natural gas fired   or Oil fire continuous heat treatment furnace and after taking out from the furnace cooling done by the industrial fan. Tempering treatment is  carried  out  in  electrically  heated  Tempering  furnace.  If  required  Bogie  furnace  or  Bell furnace is used for tempering and annealing process purpose.  

 

Packing and Dispatch:   

 

After heat treatment castings are  inspected by QC department and after  inspection packed  in iron drums or HDPE bags or wooden boxes and dispatched to the customers. 

  

Page 11: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 11

    

   

Page 12: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 12

 

 3.6 RAW MATERIAL DETAILS 

The  raw material  required  along with quantity  is  given  in  section 3.5.1,  likely  source  is  local market as well as from overseas also. Mode of transportation is by Road, Rail and Sea. Marketing area of finished products & Mode of transportation of finished products The details of marketing area of finished products is discussed in section 2.6 and 2.7  3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE PROJECT The waste water generated due to proposed project will be reused within the plan premises for green belt development and mould preparation. 100 % reused of waste water generated hence it’s a zero discharge plant. Slag will be generated as solid waste due to proposed project which shall be reused used for road construction OR sold to its re‐users/ recyclers.   3.8 AVAILABILITY & SOURCE OF WATER, AVAILABILITY & SOURCE OF ELECTRICITY  

3.8.1 Source of water and its availability  The water  shall be obtained  from GIDC. The water  consumption  for proposed project  is 700 KL/day. The detail bifurcation of water consumption and the waste water generation along with its disposal plant is mentioned in below table 5 & 6.  

Details of additional Water and Waste Water  

Water Requirement (Source of Water: GIDC supply) Table ‐5  

Sr. No. 

Water usage Total M3/day 

1  Domestic  65 

2  Industrial   

(a) Processing (Sand mould prep.) 235** 

(b) Cooling  375 

(c) Other use (Softening Regeneration) 25 

  Grand Total  700 

  

Page 13: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 13

Table – 6 Wastewater Generation 

Sr. No. 

Wastewater Total M3/day 

1  Domestic  60 *** 

2  Industrial   

(a) Processing NIL 

(b) Cooling (Blow down) 125* 

©  Other  use  (Regeneration  of  Softening Plant) 

25* 

  Grand Total  210 

 * This quantity of Industrial effluent will be blended with fresh water and used for preparation of  sand  moulds  and  sand  cooling  process  /  slag  cooling  process  to  the  maximum  extent possible. Excess quantity will be blended with treated sewage from STP and will be utilized for gardening within our premises. ** This is the quantity of fresh water required for preparation of sand moulds.  *** Domestic sewage will be  treated  in sewage  treatment plant and re‐used within premises for gardening purpose.  3.8.2 Source of electricity and its availability  Electricity shall be obtained from Gujarat Electricity Board. The total power requirement for the plant for existing and proposed project is given in table below. 

Table 8: Electricity allocation 

Source of Power  Quantum for Existing EC 

Quantum for Proposed Expansion project 

Total 

SEB /Grid  45 MW  50 MW 95 MW

 Details of DG set Additional  seven numbers of  stand by  silent enclosed  type DG  set each with capacity of 600 KVA shall be installed at the project location. 3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR 

MANAGEMENT/ DISPOSAL 3.9.1 Waste Water generation & Management plan The details of same is discussed in section 5.3.1 ( Table‐6)  3.9.2 Solid waste generation & Management plan The  solid waste generated due  to operation of  induction  furnace along with  its quantity and disposal plan is as mentioned below:  

Page 14: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 14

 Table 7: Detail of Solid Waste Generation (Non‐Hazardous waste)  

Following additional quantities of solid wastes will be generated from the proposed expansion: 

Sr. No.  Waste  Quantity Method of disposal 

1  Slag Residue  12,000  MT  / year 

Will  be  given  for  filling  –  up  in  low lying area, construction of roads etc. 

2  Moulding  sand  & Fine dust 

1,32,000  MT  / year 

‐‐do‐‐ 

3  Bio‐sludge  from STP 

18 MT/year(on dry basis) 

Will  be  used  as  fertilizer  in  our gardening area. 

 Table 8: Detail of Hazardous Waste Generation 

 Following  additional  quantities  of  hazardous  wastes  will  be  generated  from  the  proposed expansion :  

Sr. No. 

Waste  Quantity Category as per Schedule‐I of H.W. Rules 

Disposal 

1  Used Oil  Approx. 84.00 KL/Year 

5.1 Will be given to CPCB / GPCB registered recycler of oil. 

2  Waste  / residue containing oil  

Approx. 160MT/year 

5.2 Will  be  sent  to  common incineration facility. 

3  Discarded containers  

Approx. 6000 Nos./year  

33.3 Will be  given  to  registered decontamination facility. 

  3.9.3  Stack details and Air Pollution Control Measures The Flue gas stacks; process stacks and other utilities  in the proposed expansion project  is as given in the table below.      

Page 15: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 15

Table 9: Proposed Stack details and APC measures 

List of additional Flue Gas Stacks for expansion 

Sr. No 

Stack attached to  Height from GL (m) 

Dia. Of 

Stack (m) 

APCM Pollutant Concentration

PM mg/Nm3 

So2 ppm 

Noxppm 

1  Common  stack  of Induction Furnace No. 8, 9, 10 & 11 (consisting  Four  numbers of furnace crucible)  

30  1.450 Cyclone separator followed by Bag filter 

unit 

   

150 

   

100 

  

50 

2  Heat  Treatment  Furnace No. 08  

25 0.360 Not applicable 

3  Heat  Treatment  Furnace No. 09 

25 0.360 Not applicable 

4  Heat  Treatment  Furnace No. 10 

25 0.360 Not applicable 

5  Heat  Treatment  Furnace No. 11 

25 0.360 Not applicable 

6  Heat  Treatment  Furnace No. 12 

25 0.360 Not applicable 

7  Heat  Treatment  Furnace No. 13 

25 0.360 Not applicable 

8  Heat  Treatment  Furnace No. 14 

25 0.360 Not applicable 

9  Heat  Treatment  Furnace No. 15 

25 0.360 Not applicable 

10  Heat  Treatment  Furnace No. 16 

25 0.360 Not applicable 

11  DG Set No. 5 ( 600 KVA)   6 0.255 Not applicable 

12  DG Set No. 6 ( 600 KVA)  6 0.255 Not applicable 

13  DG Set No. 7 ( 600 KVA)  6 0.255 Not applicable 

Page 16: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 16

14  DG Set No. 8 ( 600 KVA)  6 0.255 Not applicable 

15  DG Set No. 9 ( 600 KVA)  6 0.255 Not applicable 

16  DG Set No. 10 ( 600 KVA)  6 0.255 Not applicable 

17  DG Set No. 11 ( 600 KVA)  6 0.255 Not applicable 

 List of Process Stacks  

 

Sr. No 

Stack attached to  Height from GL (m) 

Dia. Of 

Stack (m) 

APCM Pollutant Concentration

PM mg/Nm3 

So2ppm 

Noxppm 

1   

Common  stack  of  Rotary Shakeout  No.  3  and  Sand Plant No. 3  

30  2.250 Bag filter 

unit (2 nos.) 

   

150 

   

100 

  

50 

 2 

 Common  stack  of  Breaker drum No. 5 & 6 

30  1.250  Cyclone separator followed by Bag filter 

unit (2 nos.) 

 

 Note: Four numbers of Induction Melting Furnace along with four numbers of crucibles.  Additional Fuel consumption: 1. HSD (for stand by DG set):85 KL/month 2. Natural Gas (for heat treatment furnace, Tandish & ladle pre‐heating etc., ): 12,00,000       SCM/month 3.  LDO  /  C9  (for  heat  treatment  furnaces):  850  KL/Month  ‐ Optional  in‐case  of  PNG  is  not available.   

Page 17: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 17

4 SITE ANALYSIS 

4.1 CONNECTIVITY  National highway 8 A connects the site  location with Ahmedabad city  is  located at distance of 0.5 km  from  the project  location. The  road connecting  the  site with national highway  is well developed for transportation facility. Nearest railway station is of Ahmedabad city.  The nearest village is Kerala located at distance of approximately 0.5 km where as the nearest city is Ahmedabad located at distance of approximately 30 Km.  4.2 LAND FORM, LAND USE AND LAND OWNERSHIP The proposed project location is within the notified industrial estate. Hence the land form and land use of the project location is industrial area.  4.3 TOPOGRAPHY (ALONG WITH MAP) The topography map of the area will be submitted at the time of presentation. 4.4 Existing  land use pattern (agriculture, non agriculture, forest, water bodies –  including 

CRZ), shortest distances  from the periphery of the project to periphery of the  forests, national park, wild life, sanctuary, eco sensitive areas, water bodies (distance from HFL of  the  river),  CRZ.  In  case  of  notified  industrial  area,  a  copy  of  Gazette  notification should be given. 

The proposed project  is within the boundary of Kerala, GIDC ‐ Ahmedabad. There  is no forest, national  park,  wild  life  sanctuary,  eco  sensitive  areas  in  surrounding  10  Km  of  the  plant boundary. CRZ is not applicable to the project.  4.5 SOCIAL INFRASTRUCTURE AVAILABLE The project site is located within the notified industrial estate. Basic amenities of life are easily available in the area. Primary health centre, school, drinking water, electricity, communication, road network, transportation facility is available in the vicinity.  The existing infrastructure is sufficient to cater the additional load due to the proposed project.  5 PLANNING BRIEF 

5.1 PLANNING CONCEPT  (TYPE OF  INDUSTRIES, FACILITIES, TRANSPORTATION ETC) TOWN AND COUNTRY PLANNING/ DEVELOPMENT AUTHORITY CLASSIFICATION 

The propose project  is within  the notified  industrial  estate. Also  the  industrial  area  and  the related facilities are already developed hence no planning is envisaged. The nearby towns have all the modern facilities. 

Page 18: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 18

5.2 POPULATION PROJECTION  There would not be any  increase  in the population of surrounding area as the workers for the proposed project will come  from the  local residents  in the surrounding villages. There will be very  less  influx of people  in the area due to proposed project. Only skilled technical staff shall be  appointed  from different part of  the  state whereas  the  rest  shall be  appointed  from  the nearby city. 5.3 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL AND SOCIAL) The  basic  infrastructure  is  required  for  the  proposed  project  is  available  at  the  project  site. Apart  from  that  the  additional  infrastructure will  be  developed  by  the  company  as  per  the requirement.  5.4 AMENITIES/ FACILITIES  Major  basic  facilities  are  available  for  the  proposed  project.  Road,  electricity,  water, transportation facility etc are well developed in the surrounding area.  The major new amenity for the proposed project will be installation of induction furnace at site within  the premises  along with  all  the necessary  infrastructure  for  same  like  storage house, internal access roads, office buildings, equipment sheds etc.   6 PROPOSED INFRASTRUCTURE  6.1 INDUSTRIAL AREA (PROCESSING AREA) The total industrial area acquired by the company is 93500 sq m. 6.2 RESIDENTIAL AREA (NON PROCESSING AREA) No  labour  colony  is  envisaged  in  the  proposed  project.  Only  administrative  building  is  the residential area in the project activity.  6.3 GREEN BELT The green belt area of the project location is given below Proposed green belt area: 16897 sq m The green belt for the proposed project will consist of following green belt species  Neem, Badam, Kanel, other flowering plants, Gulmohar, Ashoka and other trees 6.4 SOCIAL INFRASTRUCTURE  Basic amenities of  life are easily available  in  the area. Primary health centre, school, drinking water,  electricity,  communication,  road  network,  transportation  facility  is  available  in  the vicinity.  6.5 THE EXISTING  INFRASTRUCTURE  IS SUFFICIENT TO CATER THE ADDITIONAL LOAD DUE 

TO  THE  PROPOSED  EXPANSION  PROJECT.  CONNECTIVITY  (TRAFFIC  AND TRANSPORTATION, ROAD/ RAIL/ METRO/ WATER WAYS ETC) 

The connectivity to the expansion project site is given in table below.  

Page 19: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 19

 Table 10: Connectivity 

Description  Distance 

Transportation 

Road    : ~ 0.5 Km (NH 8A)           : ~ 0.1 Km (30 m wide GIDC Road) 

Railway : ~ 40 Km (Ahmadabad)  

Nearest Town/City  Ahmedabad city (~ 30 Km)

Nearest Village  Kerala (~ 0.5 Km)

 6.6 DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER) GIDC water shall be used for drinking purpose. Existing bore well at the project location shall be used for the abstraction of ground water.  6.7 SEWERAGE SYSTEM Company  proposes  to  install  sewage  treatment  plant  for  the  treatment  of  domestic waste generated. The treated waste water shall be reused for gardening and plantation.   6.8 INDUSTRIAL WASTE MANAGEMENT  The  industrial waste generated  in  form of solid, hazard, water and  the management plan  for same is given in section 5.3.1 and 5.4.2 6.9 SOLID WASTE MANAGEMENT  The  solid waste generated due  to operation of  induction  furnace along with  its quantity and disposal plan is discussed in detail in section 5.4.2  6.10 POWER REQUIREMENT & SUPPLY/ SOURCE Electricity shall be obtained from Gujarat Electricity Board and the details of same are discussed in section 3.8.2.  7 REHABILITATION AND RESETTLEMENT (R & R) PLAN 7.1 POLICY  TO  BE  ADOPTED  (CENTRAL/  STATE)  IN  RESPECT  OF  THE  PROJECT  AFFECTED 

PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND LANDLESS LABORERS  Not applicable The proposed project is within the notified industrial estate.  8 PROJECT SCHEDULE & COST ESTIMATES 8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION  Likely date of start of construction: With in two months after obtaining EC Likely date of completion of construction: April 2017  8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY 

OF THE PROJECT Total project cost:  600 crores 

Page 20: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 20

 Annexure – A

Key Plan Showing Proposed Project Site and Surrounding Plots

Page 21: Prefeasibility Report recd. from AIA on 03-11-'15environmentclearance.nic.in/writereaddata/FormB/TOR/Brief_Summary/... · Cement Ltd., Ultra‐tech Ltd and Grasim Industries Ltd

Prefeasibility report AIA Engineering Limited 21

Annexure – 2

Layout plan of expansion project