precast concrete building construction process …
TRANSCRIPT
PRECAST CONCRETE BUILDING CONSTRUCTION
PROCESS COMPARISON
Tian Xiaosheng, Graduate Student, Civil and Environmental Engineering Dept., University of Alberta, Canada, [email protected]
Farook Hamzeh, Associate Professor, Civil and Environmental Engineering Dept., University of Alberta, Canada, [email protected]
Agenda:
• Introduction
• Methodology
• Results
• Conclusions
2
• Previous research applied Lean
thinking to improve production to
solve the common problems.
(0311xue.com,2019)
Introduction
• Seldom research focuses on
comparing process status of PC
construction between developing
countries and developed countries.
3
Long lead times
Jumbled flow
Process waste
Methodology
Case study analysis
4
“How” and “Why” process differences occur in selected cases
Case selection Cases analysis using VSM Conclusion
Current state map
ComparisonFuture
state mapIdeal state
map
• Multifamily PC projects• Accessible information• Local typical implementation
methods
CURRENT STATE
MAPPING OF CASE 1.
Case 1
Location: Alberta, Canada
Project type: 6 story multifamily building
Precast concrete supplier (PS): Local large company
PS’s scope of work : design, produce, delivery, erection
Use 3D modeling in Design
5
Owner
Design 3D structure
drawingModify PC cells shop drawings
Produe PC cells Deliver PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
InstructionPrecaster
requirement
Project
schedule
Precast Consultant
Production
plan
Contract
Order
Project
schedule
100%
0-1 days
30%
0-1 days
50%
0-1days
0%
5-10 days
70%
30 days
Standard product inventory CT= 40-80hrs/building
Resource =2 worker
CT= 95-270 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
CT= 30-50 days/building
Resouces = third party
transportation
1 to 2 weeks inventory
CURRENT STATE
MAPPING OF CASE 1.
Current problems:
• Extra shop drawing modification ranges from 5 minutes to 1.5 hours was needed to modify each drawing.
• The lead time between the production and delivery could be 1 to 2 weeks.
• The lead time before erection was one-month long, which was caused by the slow production rate and the fast erection rate
6
Owner
Design 3D structure
drawingModify PC cells shop drawings
Produe PC cells Deliver PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
InstructionPrecaster
requirement
Project
schedule
Precast Consultant
Production
plan
Contract
Order
Project
schedule
100%
0-1 days
30%
0-1 days
50%
0-1days
0%
5-10 days
70%
30 days
Standard product inventory CT= 40-80hrs/building
Resource =2 worker
CT= 95-270 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
CT= 30-50 days/building
Resouces = third party
transportation
1 to 2 weeks inventory
CURRENT STATE
MAPPING OF CASE 2.
Case 2
Location: Beijing, China
Project type: 12 story multifamily building
Precast concrete supplier (PS): Local large company
PS is subcontractor
PS’s scope of work : design (2D drawings), produce, delivery
7
Contractor
Design 2D pc shop drawings
Modify PC cells shop drawings
Produe PC cells Deliver PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirement
Precast
Design
standards
Precaster
requirement
Project
schedule
Production
plan
Subcontract Order
Project
schedule
Precast Engineering
house
2D
structure
drawings
Contractor s erection team
2D
structure
drawings
CT= 6-10
days/level
Resources
=12-18
workers
60%
10-30 days
90%
0-1 days
50%
0-1days
0%
10-15 days
CT= 400-800 hrs/building
Resource 4-8 worker
CT= 5-10 hrs/ building
Resource = 1 worker
CT= 40-60 days / building
Resource = two shift
CT= 20-30 days/building
Resouces = third party
transportation
2 to 3 weeks inventory
CURRENT STATE
MAPPING OF CASE 2.
Current problems:
• Long lead times before the start of shop drawings caused by the subcontract agreement.
• Long shop drawing design duration caused by traditional 2D-drawings.
• 2- 8 hrs. per drawing
• The complex connection method increased the erection duration.
8
Contractor
Design 2D pc shop drawings
Modify PC cells shop drawings
Produe PC cells Deliver PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirement
Precast
Design
standards
Precaster
requirement
Project
schedule
Production
plan
Subcontract Order
Project
schedule
Precast Engineering
house
2D
structure
drawings
Contractor s erection team
2D
structure
drawings
CT= 6-10
days/level
Resources
=12-18
workers
60%
10-30 days
90%
0-1 days
50%
0-1days
0%
10-15 days
CT= 400-800 hrs/building
Resource 4-8 worker
CT= 5-10 hrs/ building
Resource = 1 worker
CT= 40-60 days / building
Resource = two shift
CT= 20-30 days/building
Resouces = third party
transportation
2 to 3 weeks inventory
COMPARISON OF THE
CURRENT STATE PROCESSES
9
CaseCase 1 in Alberta,
CanadaCase 2 in Beijing,
ChinaBenefit
Involvement time Early late Better synergies, less error and rework
Components design More standardized Less standardized Shorter lead time, lower cost
Project participation Whole project cycle Limited project phases Better synergies and productivity
Engineering designThird party consultant
In-house engineering Better shop drawings quality
√
√
√
√
FUTURE STATE
MAPPING OF CASE 1.
Kaizens ( Improvement suggestions):
• Enhance the cooperation through an inhouse engineering department to improve quality of shop drawings
• Improve the shop drawing export function to reduce modification.
• Introduce a supermarket to
• Reduce the lead time (duration)
• Change the push system into a partial pull system
Owner
Design 3D structure
drawingModify PC cells shop drawings
Produe PC cells Deliver PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
InstructionPrecaster
requirement
Project
schedule
Precast Consultant
Production
plan
Contract
Order
Project
schedule
100%
0 days
80%
0-1 days
75%
0-1days
0%
5 days
90%
15days
Improved export
fucntion
Closer cooperation
CT= 40-80hrs/building
Resource =2 worker
CT= 50-100 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
CT= 30-50 days/building
Resouces = third party
transportation
Standard product inventory
10
FUTURE STATE
MAPPING OF CASE 2.
Kaizens ( Improvement suggestions):
• Apply BIM to improve the designefficiency.
• The precast supplier should positively participate in the project from early project phase to drive the design.
• Standardize the components design to improve efficiency and reduce cost.
Contractor
Design shop drawings
Produe PC cells Deliver PC cells
Project Control
Owner
specification
Architecture
requirement
Structure
requirement
Precast
Design
standards
Precaster
requirement
Production
plan
Subcontract
Order
Project schedule
Precast Engineering
house 3D structure
model
3D
structure
model
60%
5 days
90%
0-1 days
0%
3-5 days
Shared BIM
model
New informatic
tools
Contractor s erection team
Standardize precast design Standard product
inventoryCT= 100-400 hrs/building
Resource 4-8 worker
CT= 40-60 days / building
Resource = two shift
CT= 20-30 days/building
Resouces = third party
transportation
Shared project
schedule
11
IDEAL STATE MAPPING FOR
FUTURE PROJECTS
Owner
Design 3D structure
drawing
Export and modify shop
drawing
Produe PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
Instruction
Precaster
requirement
BIM&Lean
Production
system
Precast Engineering
House
Contract
Order Project
Master
schedule
PLM with FRID tracking
MR enhanced
equipment
Project simulation
CT= 40-80hrs/building
Resource =2 worker
CT= 50-100 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
ADCA/Autonomous
vehicle
Withdraw Kanban
Production Kanban
Industry 4.0
12
IDEAL STATE MAPPING FOR
FUTURE PROJECTS
13
Owner
Design 3D structure
drawing
Export and modify shop
drawing
Produe PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
Instruction
Precaster
requirement
BIM&Lean
Production
system
Precast Engineering
House
Contract
Order Project
Master
schedule
PLM with FRID tracking
MR enhanced
equipment
Project simulation
CT= 40-80hrs/building
Resource =2 worker
CT= 50-100 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
ADCA/Autonomous
vehicle
Withdraw Kanban
Production Kanban
• Kaizens( Improvement suggestions):• Combine BIM &
Lean to improve production system.
• Use data driven simulating to inform project duration and cost.
13
IDEAL STATE MAPPING FOR
FUTURE PROJECTS
14
Owner
Design 3D structure
drawing
Export and modify shop
drawing
Produe PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
Instruction
Precaster
requirement
BIM&Lean
Production
system
Precast Engineering
House
Contract
Order Project
Master
schedule
PLM with FRID tracking
MR enhanced
equipment
Project simulation
CT= 40-80hrs/building
Resource =2 worker
CT= 50-100 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
ADCA/Autonomous
vehicle
Withdraw Kanban
Production Kanban
• Kaizens :• Use RFID and other
sensors to collect data in the value chain for product lifecycle management.
14
IDEAL STATE MAPPING FOR
FUTURE PROJECTS
15
Owner
Design 3D structure
drawing
Export and modify shop
drawing
Produe PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
Instruction
Precaster
requirement
BIM&Lean
Production
system
Precast Engineering
House
Contract
Order Project
Master
schedule
PLM with FRID tracking
MR enhanced
equipment
Project simulation
CT= 40-80hrs/building
Resource =2 worker
CT= 50-100 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
ADCA/Autonomous
vehicle
Withdraw Kanban
Production Kanban
• Kaizens :• Use autonomous
vehicles to improve logistics
• An integrated system to utilize technologies in Industry 4.0 to improve the productivity
15
IDEAL STATE MAPPING FOR
FUTURE PROJECTS
16
Owner
Design 3D structure
drawing
Export and modify shop
drawing
Produe PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
Instruction
Precaster
requirement
BIM&Lean
Production
system
Precast Engineering
House
Contract
Order Project
Master
schedule
PLM with FRID tracking
MR enhanced
equipment
Project simulation
CT= 40-80hrs/building
Resource =2 worker
CT= 50-100 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
ADCA/Autonomous
vehicle
Withdraw Kanban
Production Kanban
• Kaizens :• Use virtual reality (VR) or
augmented reality (AR) to educate and assess the workers’ skills and improve safety
16
IDEAL STATE MAPPING FOR
FUTURE PROJECTS
17
Owner
Design 3D structure
drawing
Export and modify shop
drawing
Produe PC cells Erect PC cells
Project Control
Owner
specification
Architecture
requirementStructure
requirementPCPI
Instruction
Precaster
requirement
BIM&Lean
Production
system
Precast Engineering
House
Contract
Order Project
Master
schedule
PLM with FRID tracking
MR enhanced
equipment
Project simulation
CT= 40-80hrs/building
Resource =2 worker
CT= 50-100 hrs/ building
Resource = 2 worker
CT= 50-60 days/building
Resources =6-8 workers
CT= 30-40 days / building
Resource = two shift
ADCA/Autonomous
vehicle
Withdraw Kanban
Production Kanban
• Kaizens :• Educate students with lean
construction concepts can reduce the knowledge barrier as lean experts are critical to the success of lean improvements for the precast supplier.
17
Conclusions
• Compared the current processes of the two selected precast construction projects in Canada and China, both have some places for future improvement.
• The project in Canada has less rework, shorter lead time and better productivity because of the earlier PS involvement, application of BIM and higher ratio of standardized precast design.
• The project in China has higher quality of shop drawings because of the in-house engineering capability.
• Enhanced cooperation and improved shop drawing export function are suggested to the Canadian PS to reduce the design duration and shorten the lead time, and applying BIM to design precast elements from the project early phase is the solution for the Chinese PS.
• A comprehensive future state map is proposed for future precast projects using a combination of new technologies in industry 4.0.
18