Technical Specification and BOQ
PREAMBLE
The Bill of Quantities shall be read in conjunction with the Instructions to Bidders, General
Conditions, Particular Conditions of Contract, Works Requirement (Technical Specifications, and
Drawings).
The quantities given in the Bill of Quantities are estimated and provisional and are given to provide
a common basis for bidding. The basis of payment will be the actual quantities of work ordered and
carried out including spares to be handed over to Railway, as measured by the Contractor and
verified by the Engineer and valued at the rates and prices tendered in the priced Bill of Quantities,
where applicable, and otherwise at such rates and prices as the Engineer may fix within the terms of
the Contract. If any quantities which have been supplied by the contractor and paid by RVNL
are determined to be surplus by the Engineer (except those quantities which become
surplus due to change in planning/scheme by Railway/RVNL) during the progress of
the work or at the completion of the work, shall be taken back by the contractor, and the
payment made for such materials shall be recovered from the pending claims. The
materials which have become surplus due to change in planning/scheme by
Railways/RVNL and are still in usable condition shall be taken over by RVNL and any part
payment still to be made shall be released to the contractor.
In the Bill of Quantities, quantity and unit rates and thereby the amount against each item have been
indicated. From this, the estimated price of each bill has been worked out and indicated in the
summary sheet in BOQ. The Bidder shall quote rates as percentage above/below/at par for each
schedule in the summary sheet. If no percentage as above, below or at par is indicated for any
particular bill, the same will be considered as percentage at par.
The rates for each bill shall be written in indelible ink or type written in the summary sheet against
each bill, in both words and figures, while clearly indicating whether the percentage quoted is
above/below/at par over the estimated rate in the respective columns. The price for each bill shall
accordingly be calculated and written against each bill in both words and figures. The total price, as
the sum of prices of all bills shall be shown at the bottom of the summary sheet. The total price
shall also be written in both words and figures.
General directions and descriptions of work and materials are not necessarily repeated or
detailed in the Bill of Quantities. References to the relevant specifications and sections of the contract
documentation should be made before quoting rates in the Bill of Quantities.
The rates and prices Bid in the priced Bill of Quantities shall, except as otherwise provided under the
Contract, include all construction equipment, plant, labour, supervision, materials, erection,
maintenance, insurance, profit, royalty, octroi, taxes and duties, together with all general risks,
liabilities and obligations set out or implied in the Contract
7
8
9
10
11
12
12.1
12.1.1
12.1.2
The rates are deemed to be inclusive of all lead (except as otherwise specifically provided in the
description of the particular item), lifts, ascend, descend, handling, rehandling crossing of
nallah/streams/tracks any other obstructions.
BILL NO.1 FOR EARTH WORK INFORMATION
The earth work in formation and blanketing has to be executed as per latest RDSO guidelines for
earthwork in railway projects with upto date correction slips. If naturally available material in the
project area is not suitable for using as blanketing material directly then the blanketing material
conforming to RDSO specification has to be produced by blending various naturally available materials
in required proportion in a pug mill.
Obtaining prior permission for felling of trees including payment of royalty and taxes etc shall be
contractor’s responsibility and deemed to be included in the rates.
All enabling works for executing the work e.g. approach road to site, launching arrangements,
procuring right of way, arrangement of water and electricity etc is to be arranged by the
contractor at his own cost and deemed to be included in the quoted rates.
Storage of Material: All the material at site will have to be properly stacked & stored so as to facilitate
inspection. The material should be properly protected from the detrimental effects of nature and fire,
theft etc. The contractor shall be responsible for watch & ward and any loss or deterioration on
account of above shall lead to rejection of material and contractor has to replace the same at his
own cost.
The method of measurement of completed work for payment shall be in accordance with provisions
in Works Requirements (Specifications) except as otherwise specifically provided in the
description of item or particular bill of quantities or explanatory notes to the particular bill of
quantities.
(a) In items of Bill No. 6: (Building and related items) and Bill No.9: (Site facilities), the rates are
inclusive of cost of all materials including cement, steel, etc. required to deliver the final product.
(b) In items of bill No.2: (Bridges), Bill No.5: (track linking), and Bill No.7: (Platforms, passenger
amenities and Misc works) where ever cement, reinforcement steel and HTS wire (strands) are
required to be consumed in the item, the rates are exclusive of cost of these materials and the same
shall be paid separately under relevant items for supply of these materials.
(c) In items of Bill No.4: (P.Way supply) the rates are inclusive of all materials including
cement, steel and HTS wire (strands). Rails required for manufacture of item under Bill No.4 shall
be issued free of cost by RVNL.
NOTES SPECIFIC TO EACH BILL OF QUANTITIES.
12.1.3
12.1.4
12.2
12.2.1
12.2.2
12.2.3
12.2.4
12.3
12.3.1
12.3.2
12.3.3
12.3.4
All material, equipment, labour, casting beds, stress frames, form work, staging, scaffolding, etc is to
be arranged by the contractor within the quoted rates.
1:4:8, 1:3:6 and 1:2:4 indicates concrete prepared using volumetric mix in proportion of cement:
coarse sand: stone aggregate of specified size, respectively.
All design mix concrete shall be machine batched with automatic weigh batcher, machine
mixed and machine vibrated or Ready Mix Concrete prepared in depot and transported by transit mixer
to the site of work.
Prior to demolishing of any structure measurements have to be taken, scheme of dismantling has to be
got approved from the Engineer.
Joining of new formation with existing embankment has to be done with benching of 30 cm (V), 60 cm
(H) in the existing bank slope. The rate of earthwork includes the cost of benching.
Locations where blasting is warranted, prior permission of the employer must be obtained to
ascertain whether blasting is permitted or prohibited. Rate of rock cutting includes the cost of all
precautionary measures necessary for safety during blasting of rock.
BILL NO.2: BRIDGES AND BILL NO.7: PLATFORM, PASSENGER AMENITIES AND
MISCELLANEOUS WORK FOR CC, RCC AND PSC ITEMS.
BILL NO.4: (PERMANENT WAY SUPPLY)
If the rails required for manufacture of the finished material are to be issued free of cost by the
Employer, as specified in the description of item, the employer shall issue such rails either in
project area or from Bhilai or from any place near to the manufacturer’s workshop depending upon
availability. The quoted rates include cost of handling and transportation of rails to the manufacturer’s
workshop and finished materials from the manufacturer’s workshop to the site of work
The price quoted also includes RITES/RDSO inspection and testing charges unless otherwise specified
in the bill of quantities or Technical Specification. In case of change of inspection from
RDSO/RITES to RVNL/Consignee, 1% of cost of material will be deducted by RVNL, as inspection
charges.
All P. Way materials shall be inspected by the inspecting authority as prevalent over zonal railway for
the particular material. However, employer reserves the right to nominate any authority or its own
representative to inspect the material.
All P. Way materials shall be procured only from suppliers included in part I list of RDSO approved
suppliers for the particular item. Where, such a list is not maintained by RDSO, prior approval of source
of supply shall be obtained from the employer.
12.3.5
12.4
12.4.1
12.4.2
12.4.3
12.4.4
BILL NO.5: (PERMANENT WAY LINKING)
All P. Way material shall be neatly stacked and stored in the project area and protected
against loss/ deterioration by proper watch and ward staff, insurance, etc, the cost of which is
deemed to be included in the rates.
Painting of rails shall be done before fixing in position and touching to be done after laying in position.
Rates include day as well as night working and lighting arrangement as per requirement and
to the satisfaction of the engineer.
The welds found defective in USFD, shall have to be replaced by the contractor at his own cost.
For Mechanized laying of track only service rails will be made available by RVNL. All other materials
such as wooden blocks, fish plates, rail screw etc will have to be arranged by contractor. The
rails will be provided at convenient location within the project jurisdiction. All leads, lifts &
transportation etc shall have to be done by contractor including depositing back after completion of
works at his own cost.
Note: Cement consumption for any item if not mentioned above is to be worked out as per CPWD
DSR 2012.
Annexure-I
1 GENERAL
2
2.1
2.1.1 Live load 0.75 kN/m2 as per IS 875-2-1987 Code of practice for design loads (other
than earthquake) for buildings and structures, Part 2: imposed loads
2.1.2 Wind load Basic wind speed as per IS 875-3-1987 Code of practice for design loads
(other than earthquake) for buildings and structures, Part 3: wind
loads
Probability factor k1 as per codal provision
Terrain, height & structure size factor k2 as per codal provision
Topography factor k3 as per codal provision
2.1.3 Seismic Zone As per IS 1893-2002 (or latest)
2.1.4 Crane load Capacity of crane mentioned in Bid Document. Effect of two cranes working
under full load in different combination, i.e., same, adjacent and different
bays should be considered for vertical loads, lateral surge, tractive effort etc.
2.1.5 Dead load All possible weight of building components, electrical cables, pneumatic
pipelines, gas pipelines, water pipelines, machinery, equipment, fittings etc
should be considered
2.1.6 Load combination All possible load combinations should be considered, i.e., dead load,
imposed load, wind load, seismic load, temperature load etc as per relevant
IS codes.
2.6 DEFLECTIONS
Main frame As per IS 800-2007 (or latest)
Vertical L/180 as per IS 800-2007 (or latest)
Lateral L/150 as per IS 800-2007 (or latest)
Purlins L/180 as per IS 800-2007 (or latest)
2.3 APPLICABLE CODES
a
b
DESIGN SPECIFICATIONS
DESIGN LOADS (LIVE/ WIND)
IS 875-1987 (or latest) Design loads (other than earthquake) for buildings and structures.
SPECIFICATION FOR PRE ENGINEERED BUILDING (PEB) SHED
Applicable for Bill #2B- Bill of Quantities for Civil Engineering Works
The scope covers proof checked design, fabrication, inspection, supply, erection and commissioning of
Building should be designed and analyzed for all possible combinations of live load, dead loads, gravity
loads, earthquake loads, crane loads if any, wind loads etc for mean probable life of structure for 50
years.
Relevant BIS Codes with latest revision should be used. Wherever other than BIS codes/ manuals are
mentioned equivalent BIS Codes may also be used.
c
d
e
f
g
h
2.4 COLUMN DESIGN
3 SCOPE OF WORKS
a
b
c
d
e
f
g
h
3.2
3.3
IS 1893-2002 (or latest): Criteria for earthquake resistant design of structures c) IS 800-2007 (or
latest) General construction in steel
Anchor bolts and template
Crane girders/ beams, bracket, catwalk with hand rails at gantry level and staircase/ ladder to gantry
Framed opening, sliding doors, gravent, louver , turbo vent
Structural members with one coat of factory applied primer and paint, final painting
Manual of Steel Construction, 9th Edition, American Institute of Steel Construction (AISC)
IS 801-1975 (or latest) Cold formed light gauge steel structure members in general building
construction
IS 12843-1989 (or latest) Tolerances for erection of steel structures
Cold-formed Steel Design manual, 1996 Edition, American Iron and steel Institute (AISI)
Rigid frame structural for column, rafters with end plates, purlin, girt, bracing preferably piped bracing
Roof and wall cladding sheet, day light panel, flashing, trim, gutter, downspout
Structural hardware, sheeting fastener, end lap sealant
American Welding Society (AWS D 1.1.2008), Structural Welding Code– Steel
Column design should be such that crane gantry load is vertically transferred directly to ground. Design
of gantry girder on brackets fixed on column is not permitted for EOT crane capacity more than 5T.
Scope covers execution of complete PEB shed as per GAD of shed enclosed and specifications detailed
in Bid Document and comprising items mentioned hereunder. However, the list is not exhaustive and
may require some more items, which are not included in the list but are essentially required for
completion of the work
False ceiling panel, door, window, ventilator, rolling shutter, masonry brick wall, partition wall
etc
Scope covers submission of GAD of sheds including architectural drawings detailing plan, elevation and
sections of PEB shed and design basis report of shed as per specification detailed hereunder by bidder
for approval of the employer within key dates mentioned in Bid Document.
Scope covers submission of proof checked design and drawings of PEB shed including foundation
design and details by bidder to the employer for execution. Bidder should ensure that PEB shed
and foundation design and drawings are proof checked from reputed Government engineering college
within key dates mentioned in Bid Document.
3.4
3.5
3.6
3.7
4
4.1 STRUCTURAL
4.2 FASTENERS
4.3 PAINTING
Scope covers interior partition walls, electrical, plumbing, cooling, heating, foundation, masonry
walls, doors, windows, ventilators, concrete flooring, rolling shutters etc as per GAD of shed.
Rolling shutters should normally be motor operated with provision for manual operation. However, cost
of these items/ materials not specifically mentioned in this specification and executed by bidder will be
paid as per relevant items of BOQ in Bid Document.
Relevant BIS Codes latest revision should be used. Wherever other than BIS codes/ manuals are
mentioned equivalent BIS Codes may also be used.
Built-up sections should be fabricated from hot rolled plates conforming to ASTM A572 Gr50 (345MPa)/
Primary structural connections should be made with electro galvanized (silver) high strength
bolts Gr8.8 steel conforming to IS 3757. Purlins and girts should be connected to supporting
members by machine bolts Gr4.6 steel conforming to IS 1363 electro-galvanized (yellow). Anchor
bolts should be made from rods conforming to ASTM F1554 with a minimum yield strength of
250 MPa. Roof and wall panels should be fastened by No12 carbon steel self-drilling screws
hot-dip galvanized with polymer- coated finish with an integral washer head to which an EDPM
elastomer layer is bonded.
STANDARD MATERIAL SPECIFICATIONS
Scope covers design and execution of foundation and horizontal ties as per design loads of PEB shed.
Bidder should submit design duly proof checked by Government engineering college to the employer
before execution. Design should be prepared based upon site soil conditions. Anchor bolts should be
set strictly as per approved setting plan unless otherwise specified
Scope covers necessary tests conducted in-house and from approved recognized testing center
and submission of test certificates for chemical and mechanical properties as per approved quality
assurance plan for fabrication and erection.
Scope covers submission of quality assurance plan including source of materials for fabrication
and erection of PEB shed by bidder to the employer for fabrication and execution. Bidder should
ensure that standard code of practice and recommended installation methodology of erection of PEB
shed are adopted during erection at site. Bidder should ensure necessary tackles and tools like torque
wrench, power drill/ screw driver etc are used during erection. Bidder should ensure proper
scaffolding, man lift, road mobile crane etc are deployed and used at site during erection
4.4 SHEETING
4.5 DAY LIGHT PANEL
4.6 LOUVER
Scope covers painting of structural members. Primary steel should be shot blasted and cleaned
thoroughly before applying primer coat. One primer coat of red oxide zinc chromate as per IS 2074
should be applied in shop after fabrication with an average dry film thickness (DFT) of 35 microns.
Painting covers one shop primer coat and two coats of synthetic enamel paint (RAL 5010) of total DFT
thickness of 100 microns on all structural members.
Base metal should be high strength steel of 550 MPa yield strength with hot dip metallic coating of
aluminum zinc alloy (55% Al, 43.4% Zn & 1.6% Si) as per ASTM A792M/ AS1397 & AZ150 of 150
gm/m2 total on both sides with super durable polyester quality paint coat conforming to AS/ NZS 2728
Type-4. Painting should have total coating thickness of nominal 35 micron comprising nominal
primer coat of 5 micron on both surfaces, external coat of nominal 20 micron on top surface (RAL
5012) and reverse coat of nominal 5 micron on back surface (RAL 9002). Color shade for roof and wall
cladding sheets should be selected from standard color shade with approval of the employer. Paint for
exposed coat should be super durable polyester with inorganic pigment and free of lead. Conversion
coating should be applied on both surfaces of metallic coating before application of paint as per AS-
2728. Sheets should have marking details on backside of sheet at regular intervals indicating steel
manufacturers name and product details.
Sheeting should be fastened with nominal 40 micron zinc coated or nominal 25 micron zinc-tin alloy
coated Hex head self-drilling screw as per AS3566 2002 Class-3 fasteners of approved make with
EDPM washer as per requirement considering profile shape and design load. Fastener size should be
selected as per design/ manufacturers recommendations
Scope covers supply and fixing of louvers as per GAD of shed with fixed louver blades and border
flashings manufactured from same sheeting material with outer side (RAL 9002) and inner side (RAL
5012) as per color scheme approved by the employer.
Scope covers supply and erection of 0.60 mm thick zincalume/ galvalume steel trapezoidal sheeting
from reputed manufacturer with nominal 28 mm deep ribs. End ribs should be designed for anti-
capillary action to avoid seepage of water through lateral overlap. Feed material of profiled
sheet should be zincalume/ galvalume steel with base metal thickness (BMT) of 0.55 mm and total
coated thickness of 0.60 mm.
Scope covers supply and fixing of UV protected polycarbonate day light panel minimum 2 mm thick
conforming to classification 14443 PCISP LH49 2521 as per IS 14443 1997 with all flashings, trim
closures, caps etc from reputed manufacturer. Profile of day light panel should match roof and wall
sheeting panel. Closure strips should match sheeting profile.
4.7 TURBO VENT
4.8 ROOF EXTENSION
4.9 STRUCTURAL CANOPY
4.1
4.11
5 SOURCES
Scope covers supply and fixing of accessories like louver blades, flashings, gutters, down take pipes,
trims, ridges, capping, liner panels etc fabricated from same sheeting material used for roof and wall
cladding application. Accessories should be fixed properly with roof and wall sheeting to ensure
weather tight PEB shed. Down-take pipes/ downspout should be fabricated in square section
(equivalent to 6” diameter pipe) from same sheeting material. Gutter and down-take pipe system
should ensure no water accumulation and stagnation at gutter level. Color on outer side of accessories
should be RAL 9002
ACCESSORIES (TRIMS, FLASHINGS, GUTTER, DOWNSPOUTS, RIDGE, CAPPING AND LINER PANEL)
FASCIA AND PARAPET
Note: RVNL reserves the right to reject or alter any part of works executed by bidder, which in the judgement of
RVNL does not comply with requirements of above specifications. The decision of RVNL shall be final and
conclusive for all purposes and contractor shall have no claim on this account whatsoever.
Scope covers supply and fixing of gravity flow ridge type turbo roof vents with 600 mm throat and
manufactured from same sheeting material. Turbo vents should be lightweight wind driven turbine
based roof vents manufactured from light weight, rust resistant aluminum alloy suitable to wind speed
up to 200 km/hr. Light weight roof vent structure should also assist in producing a low starting torque
to initiate ventilation function. Double row ball bearings should be sealed and prepacked for
maintenance free operation. Throat diameter of ventilation should be 600 mm with base plate of
aluminum alloy. Color of turbo vents should match with color of roof sheeting (RAL 5012). Turbo roof
vent should cover warranty for a period of 10 years guarantying ventilator turbine to spin when
subjected to direct wind under normal conditions.
Sidewalk roof extension should be 900 mm cantilevered roof members located at eave and
sloped at same pitch as main structure roof slope. End wall r oof e xtension should be 900 mm
cantilevered C and Z sections which are continuous span extensions of main building end bay purlins
and eave struts. Roof extension structural members (except rafters) should be concealed
completely when soffit panel is specified.
Vertical and curve line fascia should be bracket mounted type. Vertical fascia should consist of hot
rolled I section or cold formed C section fascia post supported by hot rolled section bracket that is
cantilevered from rigid frames columns at side walls and from end well posts at end walls with cold
formed
Likely manufacturers and suppliers of PEB shed complete in all respect are M/s Kirby Building System,
M/s Pebs Pennar, M/s Tata Bluescope, M/s Zamil Steel Building and M/s Tiger Steel Engineering.
Sidewall canopy should be 1500-2000 mm cantilevered rafter attached at eave or any point below
eave supporting 200-250 mm deep Z purlins. Soffit panel should conceal canopy purlins leaving
rafters exposed unless otherwise specified.
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
1,001 Earthwork in filling in Embankment Fill and Prepared
Subgrade of formation including guide bunds, around buried
type abutments, bridge approaches, trolley refuges etc using
contractor's earth of approved quality as per RDSO
guidelines for design /Construction of formation on Indian
Railway track issued vide letter no. RS/G/108/Heavy Axle
Load dated 26.10.2016 (using A/B1/B2 group soil (with CBR
value of 5 or more generally but not less than 4 in isolated
cases) or C group soil (with CBR value of 3 or more generally
but not less than 2 in isolated cases) compacted at 97% of
MDD in Embankment Fill and using A/B1/B2 group soil with
CBR value of 7 or more generally but not less than 6 in
isolated cases compacted at 98% of MDD in prepared
subgrade), procured from outside railway land including site
clearances, setting out and demarcation, benching, initial
compaction of subsoil after levelling the surface after site
clearance, spreading loose earth in layers of maximum 30
cm thickness using grader up to extra width of 0.5 m beyond
designed profile, compaction using vibratory compactors, top
and side dressing and removal of extra earth from sides to
provide final formation as per designed profile as per RDSO
1001 (a) Embankment fill and prepared subgrade with Group A Soil 100.00 Cum 352.50 35,250.46
Note for Item 1001:
1. The group of soil to be used in embankment fill shall be
locally available soil in different stretches along the
alignment.
2. Please note that Shrinkage Allowance shall be deducted
as per provisions of para 7.1.1.5 of RVNL Standard
Specifications.
3. The Latest guidelines for Design / Construction of
formation on Indian Railway track, issued vide RDSO lr. No.
RS/G/108/Heavy axle load dated 26.10.2016 shall be
adopted for this item. The basic instructions (other than
those contained in the latest guidelines dated 26.10.2016)
detailed in GE: G-1 of 2003 and GE:0014 of 2009 shall
continue to apply.
4. In case embankment fill is made using A group soil,
prepared subgrade of 500 mm thick shall also be made with
A group soil and no blanket layer shall be provided.
5. In case embankment fill is made using B1 group soil, 350
mm thick prepared subgrade shall also be made with B1
group soil and 150 mm thick blanket shall be provided over
the prepared subgrade. Payment for blanket layer shall be
made under item No. 1005.
6. In case embankment fill is made using B2 group soil, 500
mm thick prepared subgrade shall be made with B2 group
soil and 250 mm thick blanket shall be provided. Payment
BILL No.1 : Earthwork in formation
10 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
1,002 Earthwork in excavation by mechanical means (Hydraulic
excavator) in cutting, in formation, trolley refuges, side
drains, yard drains, catch water drains, etc. including leading
usable cut spoils up to 200 M and making formation in filling
(as detailed in item no. 1001) using the cut spoils, site
clearances, setting out and demarcation, disposing off
surplus unusable cut spoils as per directions of the engineer,
and top and side dressing and compaction of cutting
formation to provide final formation as per designed profile.
The rate shall include compaction of cutting formation and
initial compaction of sub-soil where cut-spoils are used in
filling. The rate shall not include cutting of trees with girth
above 30 cm and compaction of cut spoils in filling, which
shall be paid separately.
Note-
(1) Rock spoils such as stones, boulders, pebbles, gravels etc
available from excavation, if are found suitable for use in
works as per required specifications even after modifications
etc., can be used free of cost but the legally payable royalty
and taxes are to be paid by the contractor to the concerned
authorities.
(2) Payment for earthwork in excavation for pucca drains
shall not be payable under this item and the same shall be
paid under item no. 7005.
1002 a Soil excluding rock. 10,000.00 Cum 189.04 18,90,415.52
1002 b Rock not requiring blasting. 13,000.00 Cum 301.35 39,17,518.21
1002 d Hard Rock requiring blasting, but blasting not permitted
hence to be excavated by chiselling.
32,000.00 Cum 628.27 2,01,04,756.03
1,003 Incremental rate for every Km or part thereof over item
1002 for leading cut spoils beyond 200 M for making
formation in filing.
40,000.00 Cum Km 4.45 1,78,011.21
1,004 Earthwork in excavation manually in formation, side drains
etc., in the alignment including leading usable cut spoils up
to 200M and making formation in filling using the cut spoils,
site clearances, setting out and demarcation, disposing off
surplus unusable cut spoils as per directions of the Engineer
and top and side dressing to provide final formation as per
designed profile. The rate shall not include cutting of trees
with girth above 30CM and compaction, which shall be paid
separately.
2,000.00 Cum 294.67 5,89,344.27
1,006 Mechanical Compaction of Earth and Blanket materials in
layers of about 30 CM (or more or less) in loose state using
vibratory compactor (of adequate capacity) so as to achieve
compaction as per RDSO Guidelines and Specification for
Design of Formation for Heavy Axle Load - Nov 2009.
Minimum EV2 Criteria as mentioned in the guidelines is not
applicable. Note: The payment for compaction shall be
based on the computed
quantityofearthwork/blanketworkfromthecrosssections.
Thepayment, however, will be restricted only to the
approved design profiles furnished by the Engineer; or the
actual quantity executed whichever is less.
100.00 Cum 17.79 1,779.05
1,007 Turfing / planting, including all lead and lift, and watering as
required until properly rooted, with. Note - Initially payment
of only 40% will be made. Balance 60% will be paid only
after 3 months of maintenance period if the turfing is
properly rooted.
a) Turfing with sods laid edge to edge as per specifications 100.00 Sqm 81.18 8,117.52
11 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
1,016 Providing barricading with the help of fencing along the
running track where the work is to be done in close vicinity
of the track. The fencing shall be minimum 1.5m high with
MS angle posts 1.8 m height of size 50 x 50 x 6mm provided
with hooks etc. placed every 2.0m apart, embedded in
cement concrete (1:2:4 ) blocks of size 0.23 x 0.23 x 0.23M
and every 15th post (or nearer, if there is abrupt change of
ground slope), last but one end post and corner post shall
be strutted on both sides and end post one side only and
struts embedded in cement concrete (1:2:4) block of size
0.23x0.23x0.23 M, provided with 5 horizontal lines and two
diagonals of G.I. barbed wire 9.38 kg/100m (min) between
the two posts fitted and fixed with G.I. staples driven into
the posts including 2 bands(red and white) 300 mm long
shall be painted with water bound paints on the ballies from
top and two bands (100 mm apart) of yellow illumimous tap
of width 50 mm shall be pasted on top white band. The rate
includes cost of all materials including cement. After
execution of all works requiring safety fencing in particular
stretch, the fencing shall be removed with the approval of
the Engineer-in-charge and formation shall be repaired to its
profile and
500.00 meter 567.11 2,83,557.03
Total for Bill No. 1 2,70,08,749.31
12 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
2,001 Earth work in excavation in foundation of bridges to desired
profile including backfilling, compaction of back fill, and
disposal of surplus earth as per directions of the Engineer.
2001 a Soil excluding rock. 750.00 Cum 268.47 2,01,351.34
2001 b Rock not requiring blasting. 100.00 Cum 284.27 28,426.70
2001 d Hard Rock requiring blasting, but blasting not permitted,
hence to be excavated by chiselling.
1,500.00 Cum 566.67 8,50,003.55
2,005 Providing and laying Design mix control concrete
M25/M30/M35/M40 in cast-in-situ RCC works of raft, pile
cap, pier, abutment, well steining, RCC well kerb, well cap,
pier cap, Jacketing, dirt wall, return wall, wing wall, fly wing
wall, retaining wall, approach slab, foot path slab, wearing
course, ballast retainers, RCC railing, inspection platform,
pedestal, boxes and other miscellaneous works using well
graded stone aggregate of 20 MM nominal size.
Note: Extra @ 32% of the rate for concreting done for the
jacketing work under this item shall be payable and shall
deem to include cost of surface preparation, drilling of holes,
insertion of dowel bars and grouting of holes etc. required
for the work but exclude cost of dowel bars which shall be
payable separately under relevant BOQ item.
4,800.00 Cum 6,427.51 3,08,52,038.96
2,042 Providing & laying non pressure NP-4 Class RCC pipe with
collars, jointing with 1:2 Cement and ordinary sand mortar
including testing of joints but excluding earth work with all
labour and material as a complete job. Cement for mortar
will be paid separately.
2042a 450mm dia 20.00 Meter 3,273.68 65,473.58
2042b 600mm dia 20.00 Meter 3,860.78 77,215.54
2042c 750mm dia 20.00 Meter 4,894.72 97,894.30
NS-1 Providing and laying 300mm dia NP4 class R.C.C. hume
pipes including collars, jointing with 1:2 Cement and
ordinary sand mortar including tesitng of joints but excluding
earth work with all labour and material as a omplete job.
The rate is including cost of Cement used for mortar.
60.00 RM 1,795.69 1,07,741.29
Total for Bill No 2A 3,22,80,145.27
Note:
Bill No. 2A: Bridge work (Other than Steel items)
1. Item no. 2005 is applicable for Building works also.
2. The above rates includes Structural design & drawing charges.
13 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
NS-1 Complete Pre-Engineered Building (PEB) Shed in all respect
as per relevant tender drawings and technical specification
as per Annexure-I, approved shop drawings and/ or
instructions. The contractor shall be responsible for design
and proof checking by recognised Govt. Engg College/
University approved by the Employer. The contractor shall
submit GADs, architectural drawings of sheds for approval of
the Employer as per key dates. After approval of GAD/
architectural drawings, the contractor shall submit design
basis report, structural designs and drawings including
foundation design based on soil investigation report of RVNL
for approval of the Employer as per key dates. Thereafter,
the contractor shall submit complete proof checked design
and drawings including foundation details from a recognised
Government Engineering College/ University (with prior
approval of the Employer) as per key dates. Rate is inclusive
of complete design, drawing and proof checking and no
separate payment will be made on this account. Rate is
inclusive of all materials including wastages, all
consumables, fasteners, both temporary and permanent
(a) Design, fabrication, supply, transportation, painting, erection
and commissioning of all structural steel works and items
required for completion PEB shed including purlins, rafters,
gantry, catwalk, stairs, frames, fasteners etc as per proof
checked design and drawings and as per specification at
Annexure-I. The rate shall include supply, fastening, cutting,
drilling, handling, riveting/ welding with supply of electrode,
rivet, bolt, nut, washer, supply of all labour, materials, tools
and plants, scaffolding, staging complete in all respect. For
assurance of quality of PEB structure most of the fabrication
should be done in contractor's workshop/ factory premises
located other than work site. Hence, part payment at various
stages is enumerated hereunder.
i) Procurement of materials (on receipt at fabrication
workshop of contractor, subject to maximum of quantities as
indicated in approved fabrication drawing) -30%
ii) On completion of fabrication members as per specification
and approved drawing, marking and its passing, application
of primer and certification by Engineer and final passing of
the fabrication components by RVNL- 20%
iii) On receipt of fabricated materials in good condition at
site and certification by the Engineer regarding receipt of
fabricated materials- 20%
iv) On erection and completion of riveting/ bolting/ welding
of members and on certification of proper line and level as
880.00 MT 91,848.20 8,08,26,418.04
Payment in stages as prescribed in Para (i) & (ii) shall be
released subject to submission of Bank Guarantee of
equivalent amount. Bank Guarantee bond should initially be
valid for minimum period of 12 months, which should
subsequently be extended from time to time depending up
on progress of work. Bank Guarantee bond given to cover
for payment for Para (i) and (ii) shall be released after
erection is completed. Complete responsibility of safe upkeep
and custody of materials at contractor's workshop, during
transit and on receipt at site shall be of contractor and the
Employer will not have any responsibility on this account for
loss or damage. Contractor shall make good any loss or
damage of materials at his own cost.
Bill No. 2B:Bridge Work (steel items involving fabrication and erection)
14 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
(b) Supply and fixing of galvalume/ zincalume sheeting including
fasteners as per approved proof checked design and drawing
and as per specification at Annexure-I. Rate shall include
supply, fastening, cutting, drilling, handling, riveting/
welding with supply of electrode, rivet, bolt, nut, washer,
supply of all labour, materials, tools and plants, scaffolding,
staging complete in all respect. Payment will be made on the
basis of net exposed area and no payment will be made for
overlaps.
i) Payment for roof sheeting will be made on the basis of
measurement of net exposed slant area
ii) Payment for wall sheeting will be made on the basis of
measurement of net exposed vertical area
iii) Payment for gutter will be made on basis of
measurement of plan area
iv) Payment for downspouts/ down take pipes will be made
on basis of measurement of net exposed circumferential
area
v) Payment for louvers will be made on the basis of
measurement of 1.25 times of plan area .
vi) Payment for sheeting used for flashing, trim, ridge,
capping, canopy etc will be made on the basis of
measurement of surface area.
Part payment at various stages is enumerated hereunder.
i) On receipt of sheeting material in good condition at site
8,100.00 sqm 668.38 54,13,870.94
(c.) Supply and fixing of polycarbonate sheeting including
fasteners as per approved proof checked design and drawing
and as per specification at Annexure-I. Rate shall include
supply, fastening, cutting, drilling, handling, riveting/
welding with supply of electrode, rivet, bolt, nut, washer,
supply of all labour, materials, tools and plants, scaffolding,
staging complete in all respect. Payment will be made on the
basis of net exposed area and no payment will be made for
overlaps.
810.00 sqm 2,422.56 19,62,276.10
Part payment at various stages is enumerated hereunder.
i) On receipt of sheeting materials in good condition at site
and certification by the Engineer regarding receipt of
sheeting material- 50%.
ii) On fixing and completion of sheeting work as per
approved drawing- 50%
(d) Supply and fixing of turbo vent including fasteners as per
specification at Annexure-I. Rate shall include supply,
fastening, cutting, drilling, handling, riveting/ welding with
supply of electrode, rivet, bolt, nut, washer, supply of all
labour, materials, tools and plants, scaffolding, staging
complete in all respect.
100.00 Each 8,350.40 8,35,040.01
Total for Bill No. 2B 8,90,37,605.09
15 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
2,076 Supplying TMT Fe-500/Fe-500D* reinforcement steel
conforming to IS:1786-1985 including decoiling,
straightening, cutting, bending, placing in position, binding
with 1MM dia GI binding wire.
720.00 MT 51,488.96 3,70,72,050.85
Note : 1. Reinforcement, shall be measured in length for
different diameters used in the works and then paid as per
standard weights as per IS 1732. Wastages, overlaps,
coupling, welded joints, space bars, chairs and binding wire
shall not be measured and cost of these items shall be
deemed to be included in the rates.
2. * For seismic zone III, IV &V, only TMT Fe-500D steel
shall be used.3. Payment will be made on completion of scope of the item
and the same is not linked to concreting.Total for Bill No.2C 3,70,72,050.85
Bill No. 2C: Supply of Steel
16 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
3,001 Supply of machine-crushed stone ballast on cess as per
RDSO specifications for track ballast: IRS-GE 1 of June, 2004
from outside railway limits stacked in specified quantities
alongside the proposed alignment on either side of track, in
yards and at locations as per site requirement as directed by
the Engineer.
Note 1: Payment will be made on actual stack measurement
for gross quantities without any deduction for voids in
following stages: (i) 95% on receipt at site, acceptance,
measurement, account, proper storage and protection
against loss, damage or deterioration; and (ii) balance 5%
after training out.
Note 2:
i) Wherever sufficient railway land is not available, contractor
will have to arrange land for supply and stacking of ballast at
his own cost for which extra payment as per item no. 3001a
will be admissible.
ii) The rate also includes levelling, dressing of ground for
stacking of ballast.
5,750.00 Cum 1,748.54 1,00,54,083.96
Total for Bill No 3 1,00,54,083.96
BILL No.3 : Ballast supply
17 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
4,001 Supply of P.Way Components
4001 a GFN Liners to RDSO Drg. No. T-3706. 1,600.00 Each 18.38 29,414.23
4001 c Composite Grooved Rubber Sole Plates (CGRSP) to RDSO
Drg. No. T-6618
9,340.00 Each 73.55 6,86,921.33
4,002 Supply of glued insulated rail joints G3 L 6.5 M long with 10
MM thick end post on PSC sleepers. Rails will be issued free
of cost by the Employer @ 6.5 M for each joint.
- -
4002 a 60 KG Kg rail section as per RDSO Drg No. RDSO/T-5843 10.00 Each 22,791.31 2,27,913.06
4,012 Supplying at site of work including leading, loading,
unloading and stacking PSC turnout sleepers and approach
sleepers for fanshaped layout of 60kg 1in 8.5 turnout for B.G
60 Kg. (UIC) rail/52 kg rails to RDSO Drg. No. T-4865 Alt-5
(for general layout) and drawings thereof with latest
alterations if any, complete set with contractor's labour,
materials, tools & Plant, equipment and machinery, transport
etc complete .
10.00 Set 5,01,029.32 50,10,293.24
4,017 Supply of Grooved Rubber Sole Plates for 1 in 8.5 turnouts
for layout Drg no. T-4865 with latest alterations if any,
complete set for the turnout as per IRS specification for
Grooved Rubber Sole Plate (6mm thick) for placing beneath
rails Sl. No. T-47-2006 with up to date corrigendum if any
10.00 Set 61,078.88 6,10,788.79
Total for Bill No. 4A 65,65,330.65
Bill No. 4 A: P.Way supply (other than steel items)
Payment Conditions for items of this Bill:
(1) 90% payment shall be made on receipt, acceptance, accountal and taking into custody of complete materials. The invoices shall be
accompanied by the following :
a) Supplier's challan and manufacturer's challan.
b) Inspection certificate issued by Employer's/Engineer's nominated inspecting agency.
c) Quality Assurance documents.
d) Indemnity bond for entire cost of material supply.
(2) The remaining 10 % payment shall be made after commissioning of the portion of the work or handing over of the material to the
employer's / Railway's Representative, required for maintenance purposes.
Note: The transportation charges from sleeper manufacturing plant to supply point in the project area as directed by Engineer are inclusive in
the rates of special sleepers. Item No. 5031 of Bill No. 5 is for the further movement of the sleeper in project area if required as per the site
conditions.
18 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
4,021 Supply of P.Way Components
4021 a ERC to RDSO Drg. No.T-3701 18,700.00 Each 101.17 18,91,873.51
4021 b ERC "J" to RDSO Drg. No.T-4158 360.00 Each 111.29 40,063.97
4021 c Metal Liners to RDSO Drg No. T-3740 9,350.00 Each 27.32 2,55,406.89
4021 d Supply of rail screws to RDSO Drg. No.T-1035/10675 720.00 Each 45.52 32,774.41
4,022 Supply of Fish plates
4022 a 60 KG as per Drawing No. T -1898 1,076.00 Each 1,910.06 20,55,224.91
4,024 Supply of fish bolts with nuts for 60 KG, 52 KG rails as per
RDSO Drawing No.T-1899, T-11501.
2,160.00 Each 89.03 1,92,297.89
4,025 Supply of joggled fish plates (2 No. per set) with 4 pair
clamps, 4 No. Bolts & Nuts and 8 No. special washers.4025 a For 60 KG as per RDSO Drawing No. T -4016/T-5849 54.00 Set 5,224.35 2,82,115.10
4,026 Supply of Fish plates one meter long as per standard
drawing of RDSO4026 a 60 KG rail (As per RDSO Drg.No.T-5916/T-5851 ) 170.00 Each 2,304.63 3,91,787.21
4026 c Supply of screw clamps for fish plates as per RDSO Drg No.
T-5856
170.00 Each 1,545.86 2,62,795.84
4029 a Supply of 60 kg 1 in 8.5, 6400mm Overriding Curved Switch
confirming to RDSO Drg. No. T-4966/T-5353 with latest
alteration, if any complete with all parts as listed in the
drawing with check rails (excluding fish plates, Fish bolts
&nuts, GRSPs, Liners and ERCs). Note: Rails will be issued
free of cost by the employer.
10.00 Set 1,23,978.38 12,39,783.79
4,034 Supply of 60 kg CMS Crossing for 1 in 8 ’/ PSC Layout
conforming to Drg No. T-4967 with latest alterations
complete with all parts as listed in the drawing (excluding
fish plates, fish bolts & nuts, GRSPs, Liners and ERCs).
10.00 Set 2,85,060.42 28,50,604.19
NS-1 Hand operated lever mechanism for operating points,
inclussive of all accessories, materials and Taxes complete.
10.00 Set 10,554.75 1,05,547.51
Total for Bill No. 4B 96,00,275.20
Bill No. 4 B: P.Way supply (Steel items)
c) Quality Assurance documents.
d) Indemnity bond for entire cost of material supply.
(2) The remaining 10 % payment shall be made after commissioning of the portion of the work or handing over of the material to the
employer's / Railway's Representative, required for maintenance purposes.
Payment Conditions for items of this Bill:
(1) 90% payment shall be made on receipt, acceptance, accountal and taking into custody of complete materials. The invoices shall be
accompanied by the following :
a) Supplier's challan and manufacturer's challan.
b) Inspection certificate issued by Employer's/Engineer's nominated inspecting agency.
19 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
5,001 Leading upto 100m lead and putting in track/formation of
ballast from measured stacks by contractor's own means and
putting the same into track uniformly to form profile as per
IRPWM in following phases: (i) Laying of first layer to form
level bed for sleepers with top surface dressed including
mechanical compaction; (ii) Filling ballast in cribs and
making up shoulders; and (iii) Recouping shortages after
each packing and finally making profile as per IRPWM.
5,750.00 Cum 128.04 7,36,235.31
5,003 Transporting of ballast from measured stacks by means of
contractor's own road lorry or rail wheel lorry that can run
on BG track including loading, leading and unloading either
by mechanical means or manually by contractor at required
site and putting the same into track/formation uniformly to
form profile as per IRPWM in following phases: (i) Laying of
first layer to form level bed for sleepers with top surface
dressed including mechanical compaction; (ii) Filling ballast
in cribs and making up shoulders; and (iii) Recouping
shortages after each packing and finally making profile as
per IRPWM (All labour, lorry, fuel, consumables etc. by
contractor) Note: 1. Payment by pre stack measurements.
(a) Lead beyond 100 m but up to 5km 500.00 Cum 251.29 1,25,646.25
5,004 Cutting of 60 KG, 52 KG, 90 R rails with contractor's Abrasive
Disc Cutter complete including men, material, fuel etc. true
to square.
120.00 Each 407.98 48,958.17
5,005 Drilling 26.5 MM, 32 MM diameter holes with Rail Drilling
Machine in web of 60 KG, 52 KG, 90 R rails in track or on
cess at correct locations including chamfering.
2,600.00 Each 98.41 2,55,878.40
5,006 Transportation of rails, switches, crossings, etc. (supplied by
RVNL) from point of issue to their final location of laying in
track5006 a Average lead, from the place of issue upto the middle point
of location of laying in each KM, upto 10 KM
350.00 MT 382.19 1,33,768.01
5006 b Incremental rate for lead beyond 10 KM under item 5006 (a)
above
1,000.00 MT KM 7.75 7,745.61
5,007 Installation of BG track as per methodology specified in para
4.0 of Section 5: Specifications in the Bidding Documents or
any other methodology approved by the Employer in all
locations e.g. straight, curves, bridges, level crossings, yards
etc including installation of SEJ and glued joints including
installation and dismantling of auxiliary track.
Note:
(i) 70% of the rate shall be paid after placement of the
sleepers, rails, fastening, initial squaring and correcting
sleepers spacing.
(ii) Next 25% of the rate shall be paid after manual packing
and bringing the track parameters within the prescribed
tolerance limits and is certified so by the Engineer.
(iii) Balance 5% of the rate shall be paid after getting CRS
sanction. (iv) For the measurement and payment purposes,
the length of track from central line of first special sleeper to
central line of last special sleeper shall be multiplied by 2 in
case of bridge and level crossing provided with guard/check
rails and to be multiplied by 3 in case of SEJ.
2,600.00 Track Meter 680.30 17,68,778.76
5,008 Installation of PSC fan shape turnouts, derailing switches 60
KG / 52 KG including lead rails as per RDSO layout drawings
including katcha packing with bars or off track tampers for
20 KMPH speed. Activities of rail cutting, drilling of holes,
welding of joints and transportation are not included in this
item and shall be paid separately under relevant items.
5008 b Turnouts 1 in 8-1/2 10.00 Each 59,459.43 5,94,594.33
Bill No. 5A : P.Way linking (installation work)
20 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
5,011 Slewing of B.G. track comprising 60 KG, 52 KG, 90 R rails on
all types of sleepers to any density under traffic block upto a
lateral slew of 150 MM or part thereof including removing
and relocating existing ballast, packing with bars or off track
tampers to achieve alignment, longitudinal levels and cross
levels for running trains at a minimum speed of 20 KMPH on
restoring traffic after the block and dressing up to correct
profile.
200.00 Track Meter 164.34 32,868.50
5011 a Incremental rate over item 5011 for slewing beyond 1st
stage of 150 MM for each 100 MM or part thereof if done in
the same traffic block
100.00 Track Meter 64.96 6,496.35
5,012 Pre-tamping and post tamping works, reconditioning of
tamping tools, and providing all consumables for first-round
of packing by railway's heavy on track tampers and dynamic
track stabiliser of straight/curved main line and loop line
track, sidings, derailing switches, and turnouts.
Note:
1. For the purpose of payment: a. Length of turnout
assembly, measured from stock rail joint to heel of crossing,
shall be multiplied by 1.5 for conversion to equivalent
ordinary track; and b. Derailing switches, bridges, level
crossings, curves, etc shall be considered as ordinary track.
2. Transfer of machines from the existing running lines to
the place of work and back to the running lines after the
work is over shall be done at contract's expenses without
payment of extra cost.
3. Railways heavy on track machines along with
crew/operator shall be made available without any hire
charges.
4. 80% payment will be made if Dynamic track stabiliser not
used.
2,600.00 Track Meter 32.68 84,962.21
5,013 Pre-tamping and post tamping works, reconditioning of
tamping tools, and providing all consumables for second-
round of packing by railway's heavy on track tampers and
dynamic track stabiliser of straight/curved main line and loop
line track, derailing switches, and turnouts for raising speed
to sectional speed.
Note:
1. For the purpose of payment: a. Length of turnout
assembly, measured from stock rail joint to heel of crossing,
shall be multiplied by 1.5 for conversion to equivalent
ordinary track; and b. Derailing switches, bridges, level
crossings, curves, etc shall be considered as ordinary track.
2. Transfer of machines from the existing running lines to
the place of work and back to the running lines after the
work is over shall be done at contract's expenses without
payment of extra cost.
3. Railways heavy on track machines along with
crew/operator shall be made available without any hire
charges.
4. 80% payment will be made if Dynamic track stabiliser not
used.
2,600.00 Track Meter 21.79 56,641.47
5,014 Anticorrosive painting of 60 KG, 52 KG rails. Painting to be
done prior to installation on sleepers including touching of
paints in areas damaged during fixing.
3,500.00 Track Meter 64.96 2,27,372.24
5,016 Provision of Buffer stop of 60 KG, 52 KG, 90 R rail section as
per plan including painting with luminous paint etc. as
directed by the engineer. Note: Rail required for this item
will be issued free of cost by the Employer.
2.00 Each 44,360.97 88,721.93
21 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
5,019 Lifting of track in stages of maximum 75 MM at a time under
traffic block including making up formation and one round of
katcha packing for getting required longitudinal and cross
levels to make the track fit for 20 KMPH as per provisions in
IRPWM Para 233 and as directed by the Engineer. (Rate will
be for each stage lifting by 75 MM) .
200.00 Track Meter 32.68 6,535.55
5,020 Lowering of track in stages of maximum 75 MM at a time
under traffic block including removing ballast, cutting of
formation and disposing of surplus cut spoils as directed by
the engineer and one round of katcha packing for getting
required longitudinal and cross levels to make the track fit
for 20 KMPH speed as per provisions in IRPWM Para 234 and
as directed by the Engineer. Existing ballast shall be put
back into the track after screening without any extra
payment and shortage of ballast will be recouped and paid
for under the relevant item. (Rate will be for each stage of
lowering by 75 MM).
300.00 Track Meter 263.71 79,113.27
5,021 Painting of station number, super elevation and versine at
each station of curve on the inside web of outer rail with
stencils of specified height in black enamel paint on surface
of specified length painted with two coats of yellow enamel
paint over a primer coat painted after cleaning the surface
free from dust and dirt.
100.00 Station 77.39 7,739.25
5,026 Dismantling of existing BG track, turnouts, derailing
switches, dead ends, sand humps, etc. of any rail section
and any type of sleepers of any density and transporting all
released material including sleepers, rails, switches,
crossings and fittings & fastenings to the nearest station or
manned level crossing or road loading point as directed by
the Engineer.5026 a Plain track including SEJ and Glued Joints and track at level
crossing, bridge & bridge approaches and sharp curves with
check rails
450.00 Track Meter 147.15 66,215.40
5,030 USFD testing of 60 KG, 52 KG rail welds (Flash Butt/ SKV) as
per RDSO Manuals and submitting reports on proforma as
directed by the Engineer.
120.00 Each 170.07 20,408.99
22 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
5,031 Transportation of PSC sleepers including special sleepers for
SEJs, check rails, guard rails and turn out sleepers from the
place of issue (in case of sleepers issued free of cost by
RVNL)and from stacking place acceptable to Engineer at
work site (in case of supplied by the contractor) to their final
location of laying.
Note:
(1) For the purpose of payment each turnout sleeper will be
considered as 1.5 No. of ordinary line sleeper. All other
special sleepers shall be considered on par with ordinary line
sleeper.
(2) 100% payment shall be made on transportation to
designated site as directed by employer/engineer.
(3) The item is intended for transportation of sleepers issued
free of cost by the employer or supplied by the contractor in
P.Way supply schedule in the project area. However, if the
sleepers to be issued free of cost by the employer are made
available at the sleeper plant and loading of sleepers is done
by concrete sleeper plant even then the rate quoted in the
item shall be applicable subject to recovery @ Rs.10/- per
track sleeper.
(4) Rate includes multiple handlings except as indicated in
note (5).
(5) In case of sleepers issued free of cost by RVNL, the
transportation shall be paid twice i.e. (i) from place of issue
to stacking place at work siteacceptable to the Engineer (ii)
from stacking place at work site to their final location of
laying.
(6) Lead from stacking place at work site to final location of
laying shall be measured from place of stacking to middle
point of kilometer of laying in track.
5031 a Lead upto 2 KM 940.00 Sleeper 69.75 65,567.68
5031 b Incremental rate for lead beyond 2 KM for every km
additional lead upto 20 kms over item (a) above
26,320.00 Sleeper KM 2.38 62,748.95
5031 c Incremental rate for lead beyond 20 KM for every KM
additional lead over item (a) & (b) above
1,22,200.00 Sleeper KM 1.75 2,13,645.24
5,033 Painting of particulars of 1 in 16, 1 in 12 and 1 in 8 %
turnouts and derailing switches including turn in curves on
the inside web of outer rail with stencils of specified height
in black enamel paint on surface of specified length painted
with two coats of yellow enamel paint over a primer coat
painted after cleaning the surface free from dust and dirt.
10.00 Turn Out 1,089.24 10,892.38
5,034 Fouling marks of size 1500x250x225 MM in M20 grade
cement concrete including engraving the letters “FM”, white
washing with two coats and painting the letters in black
enamel paint indicating the numbers of vehicles duly fixed at
site.
10.00 Each 669.79 6,697.88
5,039 Collection and removal of P. Way materials viz. PSC sleeper,
rails, etc. from the proposed alignment, loading, into
Contractor's vehicles, leading to the nearest crossing station
as directed, unloading and stacking in a neat and countable
manner as directed by Engineer-in-Charge. Note: Weight of
PSC sleepers will be taken as 275 Kg & rails, P way fittings
etc., as 95% of standard weight
95.00 MT 370.73 35,219.31
5,045 Shifting of P. Way materials such as rails, sleepers, points
and crossings, fastenings etc. and stacking at the nominated
place upto 250 m lead as directed by Engineerin-Charge
including all lift, labour, tools and machinery etc. complete
a) For lead upto 50 m 60.00 MT 135.68 8,140.83
b) Extra for lead for every 50 m or part thereof beyond initial
50 m lead
60.00 MT 19.96 1,197.76
23 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
NS-1 Linking of BG track within shop premises and on washing
pits with single rail/three rail welded with 52Kg rails on MS
bearing plates/ACBP to be fixed on top of floor beam/pit
with (M+7) density and /60Kg rail complete with all fittings,
fishplates, fish bolts, and nuts as and where required as per
standard drawing. Rate includes drilling of holes in rails to fix
distance blocks and running tie bar as well as in fish plates,
removal of kinks in rails, maintaining proper gauge, aligning
and carrying the materials from godown by employing
contractor's own plants, labours & equipment all complete.
1,350.00 Trackmeter 166.25 2,24,437.17
NS-2 Supplying and Grouting SGCI inserts by epoxy resin mortar
(1:2:7) hardener HY-840 Araldite GY-257 and quartz sand
(all to be mixed by weight) including making holes of 65 mm
dia and 110 mm deep on concrete bed block with all labours,
materials, tools and plants, blow lamp for drying holes,
making proper line and level as per direction Employer.
7,150.00 Each 218.81 15,64,458.97
NS-3 Making levelling coarse average 10 mm thick with epoxy
resin mortar (1:2:10) Hardener HY-840, Araldite GY-257 and
quartz sand (all to be mixed by weight) on concrete bed
block with all labours, materials, tools and plants, blow lamp
, making proper line and level as per direction of Employer.
78.00 sqm 1,555.52 1,21,330.66
Total for Bill No 5A 66,63,016.85
NOTE:
1) In case of work being executed under traffic block, extra payment will be made for the item of work over and above the accepted rate of
the item @ 50% of the accepted rate of the item for day time working under traffic block and @ 100% of the accepted rate of the item for
night time working under traffic block for BOQ item no. 5007, 5008, 5010 & 5026. Rates include lighting arrangement as per requirement and to
the satisfaction of the Engineer
2) Rates for all the items of this bill except those mentioned in note 1) above include day as well as night working and lighting arrangement as
per requirement and to the satisfaction of the Engineer.
3) The welds found defective in USFD, shall have to be replaced by the contractor at his own cost.
4) Track laying -
a) For mechanized laying of track only service rails will be made available by RVNL. All other materials such as wooden blocks, fish plates, rail
screw etc. will have to be arranged by contractor. The rails will be provided at convenient location within the project jurisdiction. All leads, lifts
and transportation, etc. shall have to be done by contractor including depositing back after completion of works at his own cost.
b) Manual linking of track may be permitted by the Engineer where mechanical linking is not feasible due to constraints in working. Only 90%
of the accepted rates shall be payable in case of Manual linking.
5) During the maintenance of track after commissioning, all arrangement for transportation of labour, T&P etc will have to be done by
contractor at his own cost. Necessary T&P for track maintenance will be produced by the contractor including consumables. The rate includes all
such requirements.
6) The payment of rail cuts and drilling holes will be done as per final layout of mainline/loop line /sidings and turnouts etc. Rail cuts/ hole
drilling required for temporary working will not be paid.
24 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
5,053 Alumino thermit welding of 60kg/52 kg rail joints or
combination joints of 60kg/52kg rail by pre-heat (SKV)
welding technique using compressed air petrol/LPG for
preheating, three piece pre-fabricated moulds (Zircon
washed) single shot crucible fitted with automatic tapping
thimbles with all labour, materials including supply of
portion, tools and plants, aligning of rails, placing & fixing of
mould, preheating, welding, mechanised trimming, grinding
with profile grinder (including riser), testing, marking,
painting with one coat of high build epoxy paint (two pack
conforming to RDSO specification no. M&C/PCN-111/88) on
the welded area up to 10 cm on either side. The work is to
be completed in all respects as per IRS: T-19-2012 with
latest updates and in accordance with “RDSO Manual for
Fusion Welding of Rails by Alumino Thermic Process with up
to date correction Slips in free rails or 3/10/20 rail panels.
The work to be done under supervision of trained welding
supervisor and carried out by trained welder having valid
competency certificate from RDSO/TPP, Lucknow. Ultrasonic
testing of welded joints shall be paid separately under
a) for 52kg, 72/90 UTS rails 20.00 Each 8,492.30 1,69,846.01
b) for 60kg, 72/90 UTS rails 94.00 Each 9,018.76 8,47,763.25
5,054 Supplying and fixing Boards for LWR and curves, made of 16
gauge M.S. Sheet with ISA 40x40x5 MM frame and ISA
75x75x6 MM posts as per drawings duly painted and lettered
with luminous paint.
4.00 Each 2,743.18 10,972.74
5,055 Manufacturing supplying and fixing retro reflective sign
boards made up of 2mm thick aluminium sheet, face to be
fully covered with high intensity encapsulated type heat
activated retro reflective sheeting conforming to type-IV of
ASTM-D 4956-01 in blue and silver white or other colour
combination including subject matter, message (bilingual),
symbols and borders etc. as per IRC ; 67:2001, pasted on
substrate by an adhesive backing which shall be activated by
applying heat and pressure conforming to class-2 of ASTM-D-
4956-01 and fixing the same with suitable sized aluminium
alloy rivets @ 20 cm c/c to back support frame of M.S. angle
iron of size 25mmx25mmx3mm along with theft resistant
measures, mounted and fixed with 2 nos. M.S. angles of size
35mmx35mmx5mm to a vertical post made up of ISMC
100x50 @9.56kg/m welded with base plate of size
100mmx100mmx5mm at the bottom end and including
making holes in pipes, angles flats, providing & fixing M.S.
message plate of required size steel work to be painted with
two or more coats of synthetic enamel paint of required
shade and of approved brand & manufacture over priming
coat of zinc chromate yellow primer (vertical ISMC support
5055 d Caution Indicator board of fish tail type as per Annexure 8/4
para 807 and 808 of IRPWM of size 400x1400 mm with
support length of 3650mm
1.00 Each 9,094.24 9,094.24
5055 e Termination Indicator boards as per Annexure 8/4 para 807
and 808 of IRPWM of size 1.0m dia with support length of
3850mm
1.00 Each 10,709.96 10,709.96
5055 f Speed Indicator board as per Annexure 8/4 para 807 and
808 of IRPWM of size 1.0m side triangle for various speeds
of 10, 20, 30, 45, 60, 75, 80, 90 kmph with support length of
3600 mm
1.00 Each 8,449.30 8,449.30
Total for Bill No 5B 10,56,835.51
Bill No. 5B : P.Way linking (supply and installation works)
25 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
7,003 Cement Concrete 1:2:4 (cast in-situ/precast ) for Rail level
platform wall, coping of platforms, drains and in other
miscellaneous works.
400.00 Cum 3,261.28 13,04,512.80
7,005 Earth work in cutting in foundation, trenches, pucca drains in
station area/block section etc in all kinds of soil including
dressing of sides, ramming of bottoms, back filling of
trenches, getting out the excavated soil and disposal of
surplus excavated soil with all lead and lift as directed by the
Engineer.7005 a In all kinds of soil 3,000.00 Cum 151.71 4,55,136.53
7007 c Vacuum dewatered cement concrete 100 MM thick of M25
finished with screed board vibrator, vacuum dewatering
process and finally finished by floating, brooming with wire
brush etc complete.
820.00 Cum 6,073.95 49,80,642.72
7,017 Providing GI pipes including laying & jointing with all fittings
making connections to water hydrants including connection
to source along with excavation & refilling etc. complete.
(External Water supply only)7017 a 15 MM Dia 60.00 Meter 144.26 8,655.80
7017 b 20 MM Dia 60.00 Meter 178.70 10,722.00
7017c 25 MM Dia 60.00 Meter 241.99 14,519.36
7017d 40 MM Dia 60.00 Meter 339.72 20,382.92
7017 e 50 MM Dia 60.00 Meter 430.94 25,856.13
7017 f 80 MM Dia 60.00 Meter 705.50 42,329.80
7,021 Brick work with bricks of class designation 75 for
miscellaneous works in:7021 b Cement motor 1 : 4 (1 cement : 4 coarse sand) 2,200.00 Cum 2,722.40 59,89,269.94
7,022 Dismantling work including removal and disposal of
dismantled material outside railway boundary as directed by
the Engineer. Dismantled material will be removed by the
contractor at his own cost and the same will become the
property of the contractor. Note: Measurement will be done
before dismantling the structure.
7022 b Cement concrete 50.00 Cum 564.95 28,247.62
7022 c R.C.C. work 50.00 Cum 827.42 41,371.18
7022 d Brick work/stone work 100.00 Cum 524.01 52,400.99
7,023 Dismantling steel structures and taking away dismantled
materials as property of the contractor.
10.00 MT (21,179.33) (2,11,793.29)
7,024 Dismantling AC sheet roofing and taking away dismantled
materials as property of the contractor.
10.00 Sqm (7.07) (70.67)
NS-1 Supply, errection & commissioning of Zincalume steel Water
tanks designed to withstand 20m water head pressure
inclussive of providing Zincalume steel wall sheeting, "W"
stiffeners, non-silicate high grade inside reinforced liner,
provision of holes for pipe line fixing etc. complete. The rates
include all labour, materials, taxes etc as applicable.
1,50,000.00 liter 11.03 16,54,550.66
NS-2 Manufacturing ,supplying, fitting ,fixing in position Venetian
Blind in windows and any other location in approved design
and shade as per instruction of Engineer at Site. The rate
includes supplying and fixing the same in position with all
necessary fittings, labor,materials all complete.
100.00 Sqm 1,165.84 1,16,583.57
NS-3 For Concrete Road Work Items only
(a) Cement concrete 1:2:4 (1 cement :2 coarse sand : 4 graded
stone aggregate 40mm nominal size) in pavements, lad to
required slope, and camber in panels as required including
consolidation finishing and tamping complete. (DLC for
concrete road) Cement will be paid seperately under
schedule 8001. The payment of dowel bars as per
specification will be made separately under schedule 2C Item
No. 2076.
360.00 Cum 3,261.28 11,74,061.52
Bill No. 7A: Miscellaneous items (Other than steel items)
26 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
(b) Providing and laying design mix cement concrete of M-30
grade, in roads/taxi tracks/runways, using cement content as
per design mix, using coarse sand and graded stone
aggregate of 40 mm nominal size in appropriate proportion
as per approved & specified design criteria, providing dowel
bars with sleeve/tie bars wherever required, laying at site,
spreading and compacting mechanically by using finishing
with required texture, including steel form work with sturdy.
(PQC for concrete road) Cement will be paid seperately
under schedule 8001. The payment of dowel bars as per
specification will be made separately under schedule 2C Item
No. 2076.
550.00 Cum 6,662.19 36,64,202.43
(c) Providing, laying, spreading and compacting upto end in sub
base course in uniform layer on a prepared base with motor
grader and compactin with power roller complete as per
section 401 of Ministry of shiping, Roads, transport &
Highways(MSRT&H's) specification for road & Bridge works
(4th revision -2001)
(i) GRADE-1 GSB 300.00 Cum 1,970.36 5,91,108.49
(ii) GRADE-2 GSB 300.00 Cum 1,773.04 5,31,913.40
(d) Supplying Transpoting and laying in position separation
membren of 125 mm micro thickness between DLC and PQC
for concrete read as per MORTH Specification.
6,000.00 Sqm 17.68 1,06,107.40
NS-4 Providing and placing in position 25mm thick synthetic
Expansion Joint filler board (Dura Board HD 100 or
equivalent) for construction/expansion joint of RCC floor and
other structure.
200.00 sqm 1,121.53 2,24,306.84
NS-5 Making groove 5mm - 6mm wide x 20mm - 25mm depth in
concrete heavy duty flooring by mechanical diamond cutter
true to the line for expansion of floor, filling the groove with
the paste of polysulphide based sealant up to depth of
15mm from top level.
1,000.00 m 427.21 4,27,205.72
NS-6 Mixing and pouring of non-shrink grouting GP-2 including
shuttering etc.The rate includes the cost of all materials ,
labourcost , all taxes and all other incidental charges to
complete the work in all respect.
2,000.00 kg 29.79 59,570.18
NS-7 Providing & Fixing of Stainless Steel lettering of size 200 mm
to 300 mm with necessary screw, nuts, to be fixed on ACP
Panels with all transportation, lead, lift complete. Thickness
of steel letter will be 22 SWG and height will be 15 mm
above the back surface.
100.00 each 507.25 50,724.72
NS-8 Providing and applying Nitoflor Sl 2000 or similar flow
applied 2mm thick epoxy resin based floor topping high
strength self smooth underlay conforming to BS 6319 for a
compressive strength not less than 40N/mm2, flexural
strength 25N/mm2 and tensile strength 12N/mm2 in 7 days.
The scope of the work includes:-
2,300.00 Sqm 1,088.02 25,02,444.56
(a) Surface preparation : surface shall be prepared by mile
scarification to get mechanical key effect to the primer and
the concrete surface for ensuring maximim bonding strong
degrease shall be used to remove the oil depost on the
concerete. Dust and loose particles shall be cleaned using
vacuum cleaners. (b) Application of primer : -Supply and
aplicaion of primer NITOPRIME 25 M after mixing the base
and hardener mechaniclly using a slow speed heavy duty
drilling machine (400 to 500 rpm) fitted with a suitable
paddle to achieve homogeneous mix and applied on the
prepared surface. Application of NITOFLOR SL 2000 or
similar : Supply and application of Nitoflor SL 2000, over the
prepared surface after mixing mechanically the two
components using heavy duty drilling machine until
achieving a homogeneous mix and spread on the prepared
area using serrated trowel for a thickness of 2mm spike
roller shall be rolled over to remove the entrapped air.
27 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
NS-9 Supplying and installing and commissioning one number
"SEACLOR MAC" electro chlorinator model " SEACLOR MAC
100" or similar product along with dozing pump and sodium
hypochlorite storage tank at Railway filtration plant with
contractors labour, materials, lead, lift descent etc complete.
The rate includes insurance/freight pacing and forwarding
other Govt. excise charges, training of Railway's personnel
etc. complete.
a. Chlorinator SEACLOR MAC ® 100 or equivalent product. 1.00 Each 2,24,210.59 2,24,210.59
b. Sodium hypo chlorite storage tank. 1.00 Each 2,360.33 2,360.33
c. Dozing pump equivalent for matching to SEACLOR MAC 100
electro chlorinator.
1.00 Each 23,601.51 23,601.51
NS-10 Plastering
a) 20 mm thick plastering with 1 : 6 cement morter with all
materials & labour.
4,500.00 sqm 196.38 8,83,730.31
b) 15 mm thick plastering with 1 : 6 cement morter with all
materials & labour.
4,500.00 sqm 172.18 7,74,825.60
c) 10 mm thick plastering with 1 : 4 cement morter with all
materials & labour.
4,500.00 sqm 154.50 6,95,245.05
d) Net cement finish 1,500.00 sqm 41.89 62,828.42
NS-11 Providing and fixing false ceiling at all height including
providing and fixing of frame work made of special sections,
power pressed from M.S. sheets and galvanized with zinc
coating of 120 gms/sqm (both side inclusive) as per IS : 277
and consisting of angle cleats of size 25 mm wide x 1.6 mm
thick with flanges of 27 mm and 37mm, at 1200 mm centre
to centre, one flange fixed to the ceiling with dash fastener
12.5 mm dia x 50mm long with 6mm dia bolts other flange
of cleat fixed to the angle hangers of 25x10x0.50 mm of
required length with nuts & bolts of required size and other
end of angle hanger fixed with intermediate G.I. channels
45x15x0.9 mm running at the rate of 1200 mm centre to
centre to which the ceiling section 0.5 mm thick bottom
wedge of 80 mm with tapered flanges of 26 mm each having
lips of 10.5 mm, at 450 mm centre to centre, shall be fixed
in a direction perpendicular to G.I. intermediate channel with
connecting clips made out of 2.64 mm dia x 230 mm long
G.I. wire at every nction, including fixing perimeter channels
0.5 mm thick 27 mm high having flanges of 20 mm and 30
mm long, the perimeter of ceiling fixed to wall/partition with
(i) 12.5 mm thick tapered edge gypsum plain board conforming
to IS: 2095- Part I
800.00 Sqm 936.32 7,49,054.23
NS-12 Providing "Spartek/Naveen/Regency" or equivalent brand
ceramic tiles 6 to 8mm thick, 300mmx300mm and above in
size of approved colour, design, pattern and size over the
existing floor laid over a bed of cement mortar 1:6, 20mm
average thick and jointing with neat cement slurry at 4.40
Kgs. cement per Sqm mixed with pigment to match the
shade of the tiles including making the surface even to lay
the Spartek tiles etc., complete with all contractor's aterials,
OP cement, labour, tools, plant with all lead and lifts as per
specifications and as directed by the Engineer.
600.00 Sqm 1,316.05 7,89,632.31
NS-13 Providing and fixing concertina coil fencing with required dia
600mm having 50 nos. round per 6m length upto 3m height
of wall with existing angle iron ‘Y' shaped placed 2.4m or 3m
apart and with 9 horizontal R.B.T. stud tied with G.I. staples
and G.I. clips to retain horizontal including necessary bolts or
G.I. barbed wire tied to angle iron all complete as per
direction of Engineer-in charge with reinforced barbed tape
(R.B.T.)/Spring core (2.5mm thick) wire of high tensile
strength of 165 kg/sq.mm. with tape (0.52mm thick) and
eight 43.478 gm/m (cost of M.S. angle, C.C. blocks shall be
paid separately)
100.00 Metre 301.55 30,154.89
28 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
NS-14 Supplying , fitting , fixing Expansion Joint Treatment Work
.The rate includes supplying of all items, all labour cost, all
taxes, all transportation cost, all T &P and other ancillary
work to complete the work in in all respect .
i Up to 60 mm Gap 350.00 m 2,958.79 10,35,576.53
ii Covering Joint using Aluminium Plate for Protection/Aesthetic 350.00 m 1,111.29 3,88,950.79
iii Providing and filling Nitocote to treat controlling joint on the
floor.As per FOSROC specification
350.00 m 195.45 68,408.23
NS -15 Colour washing exterior for all heights of building/structure
of approved colour & shed as per colour scheme with 100%
acrylic water base emulsion paint of ICI's Dulux Weather
shield or equivalent, two or more coats to be applied, with
one base coat of white colour water proofing cement paints
over newly platered wall and one coat of cement primer over
water proofing cement paint (special primer for Weathers
shield or imilar paint) including preparation of surface and
painting as per direcetion or painting expert of concern paint
anufacturer and engineer's instruction.
8,000.00 m2 120.06 9,60,497.65
NS-16 uPVC Doors and Windows
a. Supplying, providing and fixing white colour uPVC Door
single Shutters complete, consisting of uPVC frame of size
60mmx60mm and uPVC shutter of size 104mmx60mm with
1.0mm thick GI section reinforcement in frame and 1.5 mm
in Shutter, produced by ISO 9001/2000 and ISO 14001;
2004 certified company. Door shutter will consist either of 5
mm thick float glass or galvanized wire guage or solid PVC
panel along with complete fittings, e.g. pulley/rollers,
transmission gear and handle for operating Door upto height
2.10m, including all taxes and cost of material and labour.
80.00 Sqm 9,862.59 7,89,007.58
b. Supplying, providing and fixing white colour uPVC Door
Double Shutters complete, consisting of uPVC frame of size
60mmx60mm and uPVC shutter of size 104mmx60mm with
1.0mm thick GI section reinforcement in frame and 1.5 mm
in Shutter, produced by ISO 9001:2000 and ISO 14001:
2004 certified company. Door shutter will consist either of 5
mm thick float glass or galvanized wire guage or solid PVC
panel along with complete fittings, e.g. pulley/rollers,
transmission gear and handle for operating Door upto height
2.10m, including all taxes and cost of material and labour.
60.00 Sqm 9,862.59 5,91,755.69
c. Supplying, providing and fixing white colour sliding uPVC
window on two track without mesh complete, consisting of
uPVC frame of size 60mmx58mm and uPVC shutter of size
2mmx66mm with 1.0mm thick GI sectionreinforcement in
frame and 1.5 mm in Shutter, produced by ISO 9001:2000
and ISO 14001: 2004 certified company. Window shutter will
consist either of 5 mm thick float glass or galvanized wire
guage along with complete fittings, e.g. pulley/rollers,
transmission gear and handle for operating Window upto
height 1.20 m, including all taxes and cost ofmaterial and
labour.
40.00 Sqm 5,353.97 2,14,158.93
d. Supplying, providing and fixing white colour sliding uPVC
window on three track with mesh complete, consisting of
uPVC frame of size 108mmx58mm and uPVC shutter of size
42mmx66mm with 1.0mm thick GI section reinforcement in
frame and 1.5 mm in Shutter, produced by ISO 9001:2000
and ISO 14001: 2004 certified company. Window shutter will
consist either of 5 mm thick float glass or galvanized wire
guage along with complete fittings, e.g. pulley/rollers,
transmission gear and handle for operating Window upto
height 1.20 m, including all taxes and cost of material
andlabour.
40.00 Sqm 7,326.50 2,93,059.86
29 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
e. Supplying, providing and fixing white colour sliding uPVC
window with double Shutter complete, consisting of uPVC
frame of size 60mmx60mm and uPVC shutter of size
60mmx78mm with 1.0mm thick GI section reinforcement in
frame and 1.5 mm in Shutter, produced by ISO 9001:2000
and ISO 14001: 2004 certified company. Window shutter will
consist either of 5 mm thick float glass or galvanized wire
guage along with complete fittings, e.g. pulley/rollers,
transmission gear and handle for operating Window upto
height 1.20 m, including all taxes and cost of material and
labour.
40.00 Sqm 8,340.95 3,33,637.94
NS-17 Construction and installation of a 200/150 mm dia deep tube
welli. Geophysical survey of two or more locations each by
electrical logging method to decide the best location of tube
well depending on water bearing strata for an approximately
yield of 25000 lt/hour.(only labour charge.The cost of
material is excluded)
1.00 Per Job 23,482.37 23,482.37
ii Drilling including ramming 675/500 mm dia bore hole in all
types of soil including sand, stone rocks boulder formation
etc. with contractors mechanical rib. From 0 to 50 meters
(only labour charge. The cost of material is excluded)
50.00 Per M 1,831.63 91,581.47
iii Drilling including ramming 500 mm dia Hole in all types of
soil including sand, stone, rock boulder formation etc. with
contractor's mechanical rib.From 50 to 200 Meters (only
labour charge. The cost of material is excluded)
150.00 Per M 1,737.70 2,60,654.51
iv Supplying, Lowering and fixing in position Housing pipe 200
mm dia as per IS:4270 ERW.
50.00 Per M 2,723.95 1,36,197.65
v Supplying, Lowering and fixing in position Plain pipe 150 mm
dia as per IS:4270 ERW.
90.00 Per M 1,925.56 1,73,300.59
vi Supplying, Lowering and fixing in position Slotted screen
pipe 150 mm dia as per IS:8110 ERW.
30.00 Per M 2,676.99 80,309.76
vii Supplying and Fixing of bail plug 150mm dia 1.00 Each 469.64 469.64
viii Supplying and Fixing of well cap 200mm 1.00 Each 469.64 469.64
ix Supplying and Fixing of Central guides 200mm dia 9.00 Per no. 281.79 2,536.09
x Supplying and Fixing of Central guides 150mm dia 25.00 Per no. 234.83 5,870.66
xi Supplying and Fixing 200/150 mm dia MSERW reducer 1.00 Each 375.72 375.72
xii Supplying and Fixing of holding/housing clamps 200mm 1.00 Each 375.72 375.72
xiii Supplying and Fixing RS Joist in cross to rest the housing
clamps.
1.00 Each 751.44 751.44
xiv Pea Gravel 2 mm to 4 mm size for surrounding of tube well
as per IS 4270-1967
40.00 Per Cum 6,575.07 2,63,002.67
xv Packing of tube well with pea gravel 200.00 Per M 122.12 24,423.56
xvi Charges for transportation of compressor unit to the site of
work and return. (Only labour charge. The cost of material is
excluded)
1.00 Job 16,907.30 16,907.30
xvii Charges for transportation of over pumping unit to the site
of work and return. (Only labour charge. The cost of
material is excluded)
1.00 Job 16,907.30 16,907.30
xviii Development of tube well with compressor unit by air
compressor 250 PSI compression. (Only labour charge. The
cost of material is excluded)
50.00 Per hour 1,972.52 98,626.16
xix Development of tube well by over pumping unit. (Only
labour charge. The cost of material is excluded)
70.00 Per Hour 986.26 69,037.94
xx Supplying, fixing and installation of ISI marked Submersible
pump of 7.5 HP including supplying fixing of switches and
boards etc. complete and testing. including the cost and
installation of 80mm dia GI pipe, B Class flanged joint, 42
Mtr column pipe, electric starter, cables & switch board etc.
complete
1.00 Each 79,840.06 79,840.06
NS-18 Providing and fixing Aluminium Strips of size 35mm x 3mm
for the Flooring with gray/white cement with colouring
pigments in joints of floors or as directed at site of work
100.00 RM 131.58 13,158.00
30 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
NS-19 Providing, supplying and fixing RCC pre-cast Boundary wall
with precast poles and panels of 75mm thick including -
Excavation of pit foundation of size of 350mm dia x 900 mm
and pre cast polls of M30 Grade of size 3.3 Mtr. Long -
200mmX 200mm X 3300 with tapered openings at sides,
precast panels of size (3350mm X 2400mm X 75 mm plank)
casting in fabrication yard, transportation, fixing at site with
MS angle of 50mm X 50mm X 5mm in "Y" shape with primer
silver paint and base plate 75mm X 75mm X 6mm, for fixing
of concenrtina coil fence along with GI barbed wire of 12
Guage with 5 horizontal rows for RVNL Project in Kurdha
Road, Odisha
950.00 RMT 8,841.95 83,99,857.00
NS-20 Wood work in door and window frame fitted and fixed in
position complete including a protective coat of painting at
the contact surface of the frame exluding cost of concrete,
Iron Butt Hinges and M.S clamps. (The quantum should be
correted upto three decimals).
1.00 Cum 1,20,682.46 1,20,682.46
(c) Sal : Siliguri. C
NS-21 Supplying solid flush type doors of deluxe decorative (both
side) quality, conforming to I:S 2202 timber frame consisting
of top and bottom rail and side styles of well seasoned
timber 65mm wide each and the entire frame fitted with
27.5mm wide battens places both ways in order to made the
door of solid core and internal lipping with teak, mahogony
or rose wood approved decorative veneers usingBphenol
formaldehyde as glue etc. complete, including fitting, fixing
the shutters in position but excluding the cost of hinges and
other fittings.
(a) 35mm thick shutters (single leaf) Sq 20.00 SQM 4,864.93 97,298.60
NS-22 M.S. round or square bar grating of windows etc. fitted and
fixed in holes of window frame and with intermediate flat bar
stiffener( with necessary holes for the grating bars and with
the ends turned and fixed to timber frame with necessary
screws)complete, as directed.
In ground floor(Steel materials will not be issued by the
Deptt.)
1,200.00 Kg 78.18 93,811.91
Note : Add extra @ 1% for each addl. floor upto 4thfloor
and @ 1.25% for each addl. floor above 4th floor.
NS-23 Supplying, fitting and fixing M.S. clamps for door and
window frame made of flat bent bar, end bifurcated with
necessary screws etc. by cement concrete(1:2:4) as per
direction. (Cost of concrete will be paid separately)
(a) 40mm X 6mm, 250mm Length 72.00 Each 35.37 2,546.58
NS-24 Supplying 'Godrej' mortice lock chromium plated with keys 6
levers including fitting & fixing complete
10.00 Each 2,403.15 24,031.51
NS-25 Brass hasp bolt of approved quality fitted and fixed complete
(oxidised) with 16mm dia rod with centre bolt and round
fitting.300mm long. 10.00 Each 807.87 8,078.74
NS-26 Godrej make Hydraulic door closer of approved quality or
similar as per I.S.I. standard fitted and fixed complete
25.00 Each 2,539.04 63,476.10
NS-27 Anodised aluminium barrel / tower / socket bolt (full
covered)of approved manufactured from extruded section
conforming to I.S. 204/74 fitted and fixed with cadmium
plated screws:(i)150mm long x 10mm dia. bolt. 10.00 Each 78.18 781.77
(ii)) 300mm long x 10mm dia. bolt. 10.00 Each 121.93 1,219.27
NS-28 Anodised aliminium D-type handle of approved quality,
manufactured from extruded section conforming to I.S.
specification (I.S. 230/72) fitted and fixed complete:
i) 125 mm grip x 12 mm dia rod 10.00 Each 126.58 1,265.79
NS-29 Door stopper (Anodised aluminium) 10.00 Each 85.64 856.36
31 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
NS-30 Supplying and laying true to line and level vitrified tiles of
approved brand (size not less than 600 mm X 600 mm X 10
mm thick) in floor, skirting etc. set in 20 mm sand cement
mortar (1:4) and 2 mm thick cement slurry back side of tiles
using cement @ 2.91Kg./sqM or using polymerised adhesive
(6 mm thick layer applied directly over finished artificial
stone floor/Mosaic etc without any backing course) laid after
application slurry using 1.75 Kg of cement per sqM below
mortar only, joints grouted with admixture of white cement\
and colouring pigment to match with colour of tiles / epoxy
grout materials of approved make as directed and removal
of wax coating of top surface of tiles with warm water and
polishing the tiles using soft and dry cloth upto mirror finish
complete including the cost of materials, labour and all other
incidental charges complete true to the manufacturer's
specification and direction of Engineer-in-Charge. (White
cement, synthetic adhesive and grout material to be supplied
by the contractor)
i) Deep colour & white colour 450.00 Sqm 2,076.47 9,34,411.06
ii)Light colour 450.00 Sqm 1,560.84 7,02,378.21
NS-31 (A) Rendering the Surface of walls and ceiling with White
Cement base WATER PROOF wall putty of approved make &
brand.(1.5 mm thick).
1,500.00 Sqm 150.78 2,26,169.60
(B) Add extra for each additional floor over the rate for
ground floor for the above item when used on External
Surface Upto 4th floor
1,509.00 Sqm 0.93 1,407.05
NS-32 Protective and Decorative Acrylic exterior emulsion paint of
approved quality, as per manufacturer's specification and as
per direction of Engineer-in- Charge to be applied over
acrylic primer as required. The rate includes cost of material,
labour, scaffolding and all incidental charges but excluding
the cost ofprimer
600.00 Sqm 103.31 61,986.05
Two Coat Premium 100% Acrylic Emulsion up to 4th floor
NS-33 Applying Exterior grade Acrylic primer of approved quality
and brand on plastered or cencrete surface old or new
surface to receive decorative textured (matt finish) or
smooth finish acrylic exterior emulsion paint including
scraping and preparing the surface throughly, complete as
per manufacturer'sspecification and as per direction of the
EIC.
600.00 Sqm 38.17 22,899.87
One coat up to 4th floor
NS-34 (a) Priming one coat on steel or other metal surface with
synthetic oil bound primer of approved quality including
smoothening surfaces by sand papering etc
40.00 Sqm 35.37 1,414.77
b) Priming one coat on timber or plastered surface with
synthetic oil bound primer of approved quality including
smoothening surfaces by sand papering etc.
50.00 Sqm 47.47 2,373.48
NS-35 Painting with best quality synthetic enamel paint of approved
make and brand including smoothening surface by sand
papering etc. including using of approved putty etc. on the
surface, if necessary :(a) On timber or plastered surface :
Two coats with any shade as approved by engineer. 50.00 Sqm 99.59 4,979.55
(b) On steel or other metal surface :
Two coats with any shade as approved by engineer. 50.00 Sqm 96.79 4,839.68
NS-36 Supplying, fitting and fixing E.W.C. in white glazed vitreous
chinaware of approved make complete in position with
necessary bolts, nuts etc with P- trap
6.00 Each 1,748.84 10,493.06
NS-37 Supplying, fitting and fixing Flat back urinal (half stall urinal)
in white vitreous chinaware of approved make in position
with brass screws on 75mm X 75 mm X 75 mm wooden
blocks complete.635 mm X 395 mm X 420 mm 6.00 Each 3,528.40 21,170.43
32 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
NS-38 Supplying, fabricating matt/glossy finished Stainless Steel
railing/hand rail as per design comprising of 50mm dia
Stainless steel Grade 304 fixing the same in required position
including angular assembly at every bend complete in all
respect and making good the wall as per specification.
30.00 Kg 612.42 18,372.66
NS-39 Supplying, fitting & fixing of partly glazed partly panelled or
fully glazed single leaf Aluminium swing door of all
aluminium sections viz door frame ( top and side frame),
shutter( top rail, bottom rail, lock rail, door vertical) , glazing
clip made of Aluminium Alloy Extrusions conforming to IS:
733-1983 and IS: 1285-1975, annodized conforming to
IS:1868-1983, fitted with all other accessories viz. EPDM
gusket,cleat, angle screws etc. including labour charges for
fitting and fixing of aluminium door with door
spring,/aluminium hinges, glass / Panel board all complete
as per architectural drawings and direction of Engineer-
incharge. ( Excluding cost of glass/ panel board, door spring/
Al hinges, door closer, door stoper, handle, tower bolt and
locking arrangment etc) 10-12 Micron thickness Annodizing
film Natural white.
100.00 Kg 473.74 47,374.29
NS-40 Supplying,fitting & fixing of 2-Track / 3-Track Aluminium
sliding Window of all Aluminium sections viz. window frame
(top,bottom & side frame), shutter(top, bottom, side &
interlock member) made of aluminium alloy extrusions
conforming to IS 733- 1983 & IS 1285-1975, annodised
conforming to IS 1868-1983, fitted with all other accessories
viz. PVC roller, EPDM gasket, maruti lock, screws etc.
including labour charges for fitting & fixing of aluminium 2-
track/3-track sliding window with fixing of glass (excluding
cost of glass) all complete as per architectural drawings and
direction of Engineer-in- charge. 10-12 Micron thickness
Annodizing film Natural white
250.00 Kg 551.00 1,37,749.42
Total for Bill No 7A 4,51,45,863.29
Note :
3. Prior to demolishing of any structure measurements have to be taken, scheme of dismantling has to be got approved from the Engineer.
4. Wherever, cement, Reinforcement steel are required to be consumed in the item at site, the rates are exclusive of cost of these materials
unless otherwise specified and the same shall be paid separately under relevant items for supply of these materials.
5. The above rates includes Structural design & drawing charges.
1. All materials, equipment, labour, casting beds, stress frames, form work staging, scaffolding, etc. is to be arranged by the contractor within
the quoted rates.
2. All design mix concrete shall be machine batched with automatic weight batcher, machine mixed and machine vibrated or ready mix concrete
prepared in depot and transported by transit mixer to the site of work.
33 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
7,061 Providing FOB, platform shelters, height gauge, columns,
beams, trusses and other steel components of miscellaneous
works duly launched in position with or without traffic block
as directed by Engineer with contractors steel conforming to
IS:2062-1999 including fabrication, assembly, erection,
launching, riveting/welding, bolting, initial coats of zinc
chromate priming conforming to relevant IS specification and
three subsequent coats of aluminum paint of approved
quality conforming to IS:2339 after final erection on all
surfaces complete. Rate is inclusive of supply and fixing of
MS holding down bolts for IRS type platform shelters and
FOBs with required angles.
Note: Payment under this item shall be done in following
manner;
(I) 60% of the rate shall be paid after fabrication, application
of priming coat of painting and transportation to the site,
(II) 30% of the rate on erection & launching of the complete
structure.
(III) Balance 10% of the rate will be paid after final painting
and other allied works complete in satisfactory manner as
detailed above.
15.10 MT 1,03,343.40 15,60,485.39
NS-1 Supplying and fixing rolling shutters of approved make as
per IS 6248 made of required size M.S.laths interlocked
together through their entire length and jointed together at
the end by end locks mounted on specially designed pipe
rhaft with brackets, side guides and arrangements for inside
and outside locking with push and pull operation complete
including the cost of providing and fixing necessary 27.5 cm
long wire spring grade No.2 and M.S. top cover of required
thickness for rolling shutters 80x1.25 mm MS laths with 1.25
mm thick top cover.
19.50 Sqm 2,220.14 43,292.71
Total for Bill No 7B 16,03,778.10
Bill No. 7B: Miscellaneous works steel items)
Note : OPC/PSC/PPC cement has to be supplied as per requirement of the work in terms of specifications for material and works. Payment
against supply will be made only after consumption of cement in the relevant items of work.
34 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
8,003 Supply of Portland Pozzolana Cement (PPC) conforming to
IS: 1489 with latest amendments and using the same in the
work as per RVNL's approved mix design as per RVNL's
prescribed rates of consumption including all lead lift, labour,
loading unloading, ascent, descent, crossing of Railway
lines(s), royalty, taxes, transport (contractor's own), tools
and plant complete.
1,10,000.00 Bag of 50kg. 254.35 2,79,79,018.50
Total for Bill No 8 2,79,79,018.50
Bill No.8 : Supply of Cement
35 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
9,001 Providing site offices for Employer with Contractor's material,
Labour, Tools and Plant, Equipment etc. including provision
of Water Supply, Drainage, Power arrangements, office
maintenance as per the details mentioned in clauses 3.1 to
3.2.8 & 3.5 to 3.5.2 of Chapter 3 (Site Facilities for the
Employer and the Engineer) of Section 5 (Work's
Requirement) of Tender Documents.
Note 1:
This item is provided with the contention that new site
offices will be constructed for this purpose and 75%
payment of the accepted rates will be made after making
available functional office, balance 15% payment shall be
made at the end of the completion period and the remaining
10% will be paid after clearance of site by the contractor.
Note 2:
Alternatively if suitable accommodation is available on hire
basis at suitable location acceptable to the employer, the
contractor can arrange the same under the item but in such
a case the payment shall be regulated as below. (a) 10%
payment shall be made on completion of one month from
the date of making available the office fit for functioning. b)
Remaining 90% payment shall be paid in equal monthly
instalments that is (0.9xQuoted rate) / (Stipulated
Completion period in months + defect liability period in
months).
Note 3: In case stipulated period gets extended, payment on
monthly basis, under this item, in such extended period,
shall be made as under;
(i) in case of new construction @ [(54% of Quoted rate) /
(Stipulated Completion period in months + defect liability
period in months)] per Sq.m. of Plinth area.
120.00 Per Sqm. of
Plinth area
19,726.37 23,67,163.88
9,002 Providing Furniture as given under clauses 3.3, 3.3.1 of
Chapter 3 (Site Facilities for the Employer ) of Section 5
(work's Requirement) of Tender Documents. Note: Payment
shall be made @ 75% of the accepted rate after making
available the furniture items in functional office, balance
15% payment shall be made at the end of the completion
period and the remaining 10% will be paid after clearance of
site by the contractor.
1.00 L S Per Site Office 15,32,147.52 15,32,147.52
9,003 Providing Road Vehicle mentioned below for the use of
Engineer/Employer as per the Conditions mentioned in
Clause 3.4.3, i.e 3.4.3.1 to 3.4.3.3 of Chapter 3 (Site
Facilities for the Employer and the Engineer) of Section 5
Work's Requirement) of Tender Documents.9003 a INNOVA, MAHINDRA XUV500 or similar 42.00 Vehicle months 82,352.65 34,58,811.29
9003 b BOLERO, SCORPIO, ERTIGA, MARAZZO or similar 126.00 Vehicle months 70,861.22 89,28,513.80
9003c Extra for running and maintenance of every additional km
over and above 4000 kms as specified in item 9003 (a)
1,000.00 per Km. 19.18 19,178.59
9003d Extra for running and maintenance of every additional km
over and above 4000 kms as specified in item 9003 (b)
1,000.00 per Km. 15.34 15,342.87
Bill No.9 : Site facilities
36 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
9,004 Providing Computers with software, Printers and other office
equipment as given under clause 3.6 of Chapter 3 (Site
Facilities for the Employer) of Section 5 (work's
Requirement) of Bidding Documents excluding (d) Large
Format Plotter.
Note:
(i) Payment shall be made @ 85% of the rate after making
available the office equipment in functional condition,
(ii) Next 10% of the rate shall be paid at the end of the
completion period.
(iii) The remaining 5% of the rate shall be paid after the
equipment is taken back by the contractor and the site is
cleared by the contractor.
1.00 L S Per Site Office 13,68,985.51 13,68,985.51
Total for Bill No 9 1,76,90,143.45
37 of 38
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
10,001 Execution of item(s) of works covered by chapters 1 to 25 of
USOR-2010 of E.Co. Railway. Note: This bill will be operated
for only those works which cannot be executed by operation
of BOQ items in bill no. 1 to 9.
33,19,042.00 LS 42,28,902.47 42,28,902.47
Total for Bill No 10 42,28,902.47
TOTAL OF CIVIL WORKS 31,59,85,798.50
Bill No.10 : Miscellaneous (other items of works not covered in Bill No1 to 9)
38 of 38