pre construction - national park service · before and after photos. photo point 9. channel and...

6
Photo Point 2 New Redwood Creek Channel Alignment & Off Channel Pond Complex POST PHASE 2 CONSTRUCTION November 9, 2010 PRE CONSTRUCTION March 10, 2009 Looking north from the Coastal Trail above, Phase Two included construction of 550 feet of new creek channel within a large flood plain. Phase ree activated the new creek alignment, including construction of the upstream and downstream tie-ins, construction of a backwater and off channel pond, and removal of the levee road. POST PHASE 3 CONSTRUCTION November 14, 2011

Upload: others

Post on 18-Oct-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRE CONSTRUCTION - National Park Service · Before and After Photos. Photo Point 9. Channel and Frog Pond Construction . POST PHASE 2 CONSTRUCTION. November 19, 2010. PRE CONSTRUCTION

Photo Point 2New Redwood Creek Channel Alignment & Off Channel Pond Complex

POST PHASE 2 CONSTRUCTIONNovember 9, 2010

PRE CONSTRUCTIONMarch 10, 2009

Looking north from the Coastal Trail above, Phase Two included construction of 550 feet of new creek channel within a large flood plain. Phase Three activated the new creek alignment, including construction of the upstream and downstream tie-ins, construction of a backwater and off channel pond, and removal of the levee road.

POST PHASE 3 CONSTRUCTIONNovember 14, 2011

cloning
Typewritten Text
Before and After Photos
Page 2: PRE CONSTRUCTION - National Park Service · Before and After Photos. Photo Point 9. Channel and Frog Pond Construction . POST PHASE 2 CONSTRUCTION. November 19, 2010. PRE CONSTRUCTION

Photo Point 9Channel and Frog Pond Construction

POST PHASE 2 CONSTRUCTIONNovember 19, 2010

PRE CONSTRUCTIONMay 18, 2009

Looking southwest, the new Redwood Creek channel alignment cuts through a larger flood plain at Green Gulch pasture. The frog pond constructed in 2009 is apparent in the foreground. A grove of cypress trees was toppled to allow for the construction of a second frog pond, with all trees reused as woody debris in the new channel (left).

POST PHASE 3 CONSTRUCTIONNovember 14, 2011

Page 3: PRE CONSTRUCTION - National Park Service · Before and After Photos. Photo Point 9. Channel and Frog Pond Construction . POST PHASE 2 CONSTRUCTION. November 19, 2010. PRE CONSTRUCTION

Photo Point 10New Pedestrian Bridge and Landing

POST CONSTRUCTIONDecember 8, 2011

PRE CONSTRUCTIONMarch 24, 2009

Looking northwest, the new pedestrian bridge spans the Redwood Creek floodplain. The levee road (right) has been removed, increasing the channel width and connection to the floodplain. The bridge landing includes benches and bike racks for park visitors.

Page 4: PRE CONSTRUCTION - National Park Service · Before and After Photos. Photo Point 9. Channel and Frog Pond Construction . POST PHASE 2 CONSTRUCTION. November 19, 2010. PRE CONSTRUCTION

Photo Point 31Off Channel Pond Complex & Downstream Tie-in

POST PHASE 2CONSTRUCTIONNovember 9, 2010

PRE CONSTRUCTIONJune 3, 2009

Looking northwest, from the hillside above the project site. Phase Three included the construction of a backwater and off channel pond. The existing levee was removed, allowing for construction of the downstream tie-in. The new pedestrian bridge is also shown.

POST PHASE 3 CONSTRUCTIONNovember 14, 2011

Page 5: PRE CONSTRUCTION - National Park Service · Before and After Photos. Photo Point 9. Channel and Frog Pond Construction . POST PHASE 2 CONSTRUCTION. November 19, 2010. PRE CONSTRUCTION

Photo Point 32New Redwood Creek Channel, Off Channel Pond Complex, & Frog Pond Construction

POST PHASE 2 CONSTRUCTIONNovember 9, 2010

PRE CONSTRUCTIONJune 3, 2009

Looking northwest, from the hillside above the project site. A new frog pond was also constructed during Phase Two, providing habitat for the endangered California red-legged frog. A grove of approximately 30 cypress trees were toppled in order to clear the site for pond construction. All toppled trees were reused as woody debris in the new channel construction. Phase Three included construction of the upstream and downstream tie-ins, construction of a backwater and off channel pond (left), and removal of the levee road.

POST PHASE 3 CONSTRUCTIONNovember 14, 2011

Page 6: PRE CONSTRUCTION - National Park Service · Before and After Photos. Photo Point 9. Channel and Frog Pond Construction . POST PHASE 2 CONSTRUCTION. November 19, 2010. PRE CONSTRUCTION

Photo Point 39New Channel Alignment and Connection to Green Gulch Tributary

POST CONSTRUCTIONDecember 12, 2011

PRE CONSTRUCTIONJune 9, 2009

Looking east, the new Redwood Creek channel alignment cuts through a larger flood plain at Green Gulch pasture. Cattails were removed to allow for construction, and large woody debris installed in the new channel.