pre-approval inspections a case study steve pondell 28 nov 2007

20
Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Upload: melvin-hancock

Post on 29-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Pre-Approval InspectionsA Case Study

Steve Pondell

28 Nov 2007

Page 2: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Topics

• Pre-Inspection

• The Inspection

• Outcome

Page 3: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Pre-Inspection - Situation

• API manufacturer in Sweden

• Second site

• Process transferred from first site

• Process validation underway

• First inspection (of four that ultimately happened)

Page 4: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Supply Chain

Primary API Manufacturer (US)

Secondary API Manufacturer

(Sweden)

Formulator (US)

Packager (Canada)

INSPECTIONS

FDA (3)

FDA (1)

FDA (2)EMEA (MHRA)

NONE

Page 5: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Pre-Visit Inspection

• Notification received approximately 2 months prior to inspection– Four days planned, two inspectors

• Two day site pre-visit planned with Encysive and manufacturer

• All major systems reviewed• Validation documentation reviewed• Major issues discussed and strategized• Final check

Page 6: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Pre-Visit Inspection

• Logistics of inspection discussed– Who would be with inspectors– How would information be processed– What would sponsor’s role be

Page 7: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Planned Logistics - People

• Two inspection rooms prepared• Two site people in each room

– One QA person as direct interface– One scribe

• Back room headed by QA with ample support staff

• Selected sponsor representatives permitted in inspection room and back room

Page 8: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Planned Logistics – Communications

• Dedicated chat room set up for site

• Scribe in inspection rooms set up with interface

• All key site departments to monitor continuously

• Back room set up with individual monitors as well as projection to screen

Page 9: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Planned Logistics - Roles

• Site QA – primary response to all questions

• Sponsor – – in inspection room, only as requested by

site QA– For questions related to filing– In back room, to provide input as needed

and requested

Page 10: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Planned Logistics - Information

• All process documents, SOPs and validation documents collected into back room

• One copier dedicated for inspection team, loaded with “confidential” watermark paper

• Two copies made of any requested information

• Dedicated person for copies• Dedicated runners for information

transmission

Page 11: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

The Inspection

• Two sponsor representatives arrived one day early– Final check on arrangements

• FDA arrived with two inspectors

• After introduction, immediately separated

Page 12: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

How It Worked• Wonderfully!• Chat room was successful beyond

expectations– Back room had heads-up on incoming

information requests– Information was being prepared as FDA

request was being voiced– Frequently had information or person

available outside of room within seconds of request

Page 13: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

How It Worked

• Sponsor in back room was able to see flow of information from both rooms in real time (but in Swedish!)

• Site had people assigned to both FDA and sponsor for breaks and meals– Segregation was assured

Page 14: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Sponsor Role

• Discussion of filing topics

• Discussion of site transfer activities

• Excused from topics regarding other products

Page 15: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Major Unresolved Topic

• Technical Transfer Protocol– Not a specific requirement– Topic addressed by sponsor each day– Protocol did not exist as specific

document

Page 16: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Outcomes

• Inspection lasted most of four days

• Site answered all topics

• Site committed to change tech transfer SOP

• Sponsor committed to issue final tech transfer report at end of validation

Page 17: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Outcomes

• NO FDA-483 OBSERVATIONS

• “Approval” letter recommended and later received

Page 18: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Observations

• Site was completely engaged with inspection– All personnel– Entire QA group

• Interaction with sponsor seen as positive by all

• End result achieved• Model used successfully for other

audits

Page 19: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Who is This Manufacturer

• Cambrex Karlskoga

– Karlskoga, Sweden

Page 20: Pre-Approval Inspections A Case Study Steve Pondell 28 Nov 2007

Questions or Comments?