![Page 1: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/1.jpg)
Social Monitoring Report
Project Number: 40052 October 2009
PRC: Kunming Qingshuihai Water Supply Project The 3rd External Resettlement Monitoring Report
Prepared by: Kunming University of Science & Technology
People’s Republic of China
For Kunming Municipal Government
This report has been submitted to ADB by the Kunming Municipal Government and is made publicly
available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.
![Page 2: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/2.jpg)
ADB-Financed
Kunming Qingshuihai Water Supply Project (KQWSP)
Analysis Report on Living Standard 3rd Follow-up Survey for Resettlement
(No.4)
Faculty of Management & Economics, Kunming University of Science & Technology
October, 2009
![Page 3: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/3.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
I
Content 1. Project Introduction ................................................................................................3
1.1 Project Brief Introduction ...................................................................................................3 1.2 Project Affected Area ..........................................................................................................4 1.3 Quantity of Land Requisition and Resettlement .................................................................5
1.3.1 Land Requisition ......................................................................................................5 1.3.2 House Demolishment ...............................................................................................6 1.3.3 Demolition for Other Auxiliary Facilities and Specific Facilities............................6
2. Monitoring Survey ...................................................................................................7 2.1 Range of Survey..................................................................................................................7 2.2 Survey Institutes..................................................................................................................8 2.3 Survey Approaches..............................................................................................................9 2.4 Process of Survey................................................................................................................9
2.4.1 Selection phase in survey sites .................................................................................9 2.4.2 Follow-up survey Phase ...........................................................................................9
3 Data Analysis of Follow-up Village........................................................................10 4 Data analysis on surveyed sample families...........................................................13
4.1 Demographical characteristics for the surveyed households.............................................13 4.1.1 Sex role ..................................................................................................................13 4.1.2 Age distribution......................................................................................................13 4.1.3 Distribution of nationalities....................................................................................14 4.1.4 Level of education (For Person aged 16 years or above) .......................................14 4.1.5 Marital status (For Person aged 16 years or above) ...............................................15 4.1.6 Status of employment (For Person aged 16 years or above) ..................................15
4.2 Living and Production status of surveyed household........................................................16 4.2.1 Property status of surveyed household...................................................................16 4.2.2 Public properties like water and power supply ......................................................17 4.2.3 Housing Conditions................................................................................................18 4.2.4 Residential environment.........................................................................................19
4.3 Financial status of surveyed households ...........................................................................21 4.3.1 Land area................................................................................................................21 4.3.2 Income....................................................................................................................22 4.3.3 Expenditure ............................................................................................................25 4.3.4 Number of out-town odd-jobbers among surveyed family members.....................26
4.4 Surveyed households’ evaluation of present living situation ............................................30 4.4.1 Evaluation of production conditions of individual household................................30 4.4.2 Evaluation of one’s own financial status in a context of the whole village............30 4.4.3 Evaluation of present residential environment .......................................................31 4.4.4 Evaluation of neighborhood relation......................................................................31 4.4.5 Evaluation of life satisfaction.................................................................................31 4.4.6 New-Added Economic Recovery Measure ............................................................32
5 Land Requisition and Resettlement ......................................................................33 5.1 Progress on land requisition and resettlement...................................................................33
5.1.1 Progress of Permanent Acquired Land...................................................................33 5.1.2 Progress of Temporary Land Acquisition...............................................................34 5.1.3 Progress of House Demolishment ..........................................................................35 5.1.3 Progress of Auxiliary Facility Demolishment ........................................................37
5.2 Compensation standards for land requisition and resettlement .........................................38 5.2.1 Compensation Standards for Permanent Land Acquisition....................................38 5.2.2 The Compensation Standard of Temporary Land Occupation ...............................40 5.2.3 Compensation Standards for Residential Houses and Auxiliary Facilities ............40 5.2.4 Scattered Trees .......................................................................................................42 5.2.5 The moving subsidies.............................................................................................42 5.2.6 Compensation for public infrastructure in the concentrated relocating place ........42 5.2.7 Subsidies of Building House ..................................................................................43 5.2.8 Subsidies of Poverty Household ............................................................................43
![Page 4: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/4.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
II
5.3 Payment Status on compensations for land requisition and resettlement..........................43 5.4 Payment progress on compensations for land requisition and resettlement ......................45
6 Management of Resettlement Funds & Disbursement........................................46 6.1 The Management of Resettlement Fund ...........................................................................46 6.2 The Appropriation and Payment of Resettlement Fund ....................................................47
7 Relocation ................................................................................................................49 7.1 Maichong Relocation Plot of Qinghai Village ..................................................................49 7.2 Haiwei Relocation Plot .....................................................................................................50 7.3 Renjiahou Relocation Plot in Laoba Village .....................................................................51 7.4 Ganchong Relocation Plot in Deshi ..................................................................................51 7.5 Other Scattered Relocation ...............................................................................................52 7.6 Rebuilding of Specific Units .............................................................................................53 7.7 Recovery of Communication around Reservoir................................................................53 7.8 Resolution of Transmission Line.......................................................................................54 7.9 Telecommunication and TV Cable ....................................................................................55 7.10 Water Conservancy Facilities..........................................................................................55
8 Public Participation and Grievance Redress........................................................56 9 Rehabilitation Measures.........................................................................................57 10 External Monitoring and Evaluation of Resettlement ......................................58 11 Conclusion..............................................................................................................63
11.1 Impact Degree Caused by Project ...................................................................................63 11.2 Future Efforts Suggested .................................................................................................64
Annex Ⅰ Survey Matrix of the follow-up survey on affected villages along Qingshuihai Water Supply Project...........................................................................66 Annex Ⅱ Survey Matrix of the household-survey on affected villages along Qingshuihai Water Supply Project...........................................................................77 Annex Ⅲ Survey sheet of economic rehabilitation on affected villages (from January to June 2009) ...............................................................................................88 Annex Ⅳ Status of public participation in Qingshuihai Water Supply Project.89 Annex Ⅴ Explanation of External Monitoring and Evaluation Index System of Resettlement for Qingshuihai Project (First) ( From January to June 2009) ......91
![Page 5: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/5.jpg)
Kunming Qingshuihai
Water Supply Project
(KQWSP) is one of the
most significant projects
financed by Asian
Development Bank (ADB)
in Kunming City. The
objective for Kunming
Qingshuihai Water Supply
Project (KQWSP) is to
provide domestic and
industrial water supply for the Eastern Development Zone (EDZ) and the New Airport
Development Zone (NADZ) in Kunming City. With a view to achieving a smooth
progress of land requisition and resettlement for this project, Qingshuihai Branch
Company of Water Development and Construction has entrusted the Advisory Panel
of Experts of the Faculty of Management and Economics of Kunming University of
Science and Technology with providing external monitoring and advisory service for
land requisition and resettlement for the project.
1. Project Introduction
1.1 Project Brief Introduction
During Phase I of KQWSP (The Project), the completed works will include:
increased storage capacity in Qingshuihai reservoir; rehabilitation of the Xintian River,
Tabizi Longtan Pool and Jinzhongshan reservoir; the development of new water
storage and diversion works on the Banqiao River and Shiqio River, and the
establishment of water conveyance tunnels from both Shiqiao Rivers to Qingshuihai,
and from Qingshuihai to Jinzhongshan. The project involves the submergence of land,
reservoir impoundment structures, the development of diversion and water
conveyance systems, and the establishment of permanent access roads. The
resettlement plan and land acquisition are only for Phase I of KQWSP (The Project).
![Page 6: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/6.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
4
Once the project has been completed, 96.84 million m3 of water will be supplied
annually to the new Kunming city development areas. The total investment for the
project is CNY 1.863 billion. A loan funded by Asian Development Bank (ADB) will
provide up to $ 80 million (about CNY 616 million at CNY 7.7 per US$) for the
project. It is anticipated that project construction will start in October 2007, and be
completed about June of 2012. The legal representative of this project is Kunming
Water Supply Group Co., Ltd. (KWSG).
1.2 Project Affected Area
According to relative items in < Outline of Land Acquisition and Resettlement
Plan > ratified by Bureau for Reservoir Immigration, and < Resettlement Plan of
Kunming Qingshuihai Water Supply Project> (January, 2009) drawn up by Project
Office of Qingshuihai Project of Water Supply and Water Source Environmental
Management, Land acquisition and house demolition of this Project will involve 2
counties, which are Xundian Autonomous County of Hui Minority and Yi Minority
and Songming County. In Xundian Autonomous County of Hui Minority and Yi
Minority, Jinsuo Township, Diansha Township, Yangjie Township and Liushao
Township; Dianyuan Township, Yangqiao Township, Songyang Township in
Songming County will be affected directly. Totally, there are 7 townships, 21
administrative villages, 41 village groups, 6426 persons, 5269 persons of which are
affected directly and 798 persons are affected temporarily. In Xundian County,
directly and temporarily affected population are 3147 and 798 respectively, and the
population of Songming County are 2121 and 360. In total, about 6577.1 mu of
collective land will be permanently acquired for the Project, which including 869.3
mu of farmland, timberland 2628.1mu; the temporary land acquisition is 2293.2 mu,
the area of farmland and timberland is 869.3 mu and 1252.2 mu.
In the design year of Project, Project will involve 1121 households and 4394
persons affected by land acquisition without demolishment, 208 households and 773
persons affected by demolishment without land acquisition, and 36 households and
102 persons affected by both demolishment and land acquisition. The total population
affected directly by project is 5269 (1365 households). And resettled non-agricultural
population is 14 persons.
In addition, as for the specific facilities, the demolishment and removal of project
![Page 7: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/7.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
5
will come down to 1 pumping station, 2 pumping dam, 3 converting stations, 12
bridges (culverts), 8.77km electricity transmit line, 41.42km water diversion channels,
27.3km rural road and 5.1km telecommunication lines. Table 1-1 Project Affected Area
County Township Administrative Village
Jinsuo Qinghai, Zetie, Xintian
Diansha Luliu、Haiwei
Liushao Enjia、Wu、Tuoqi、Maanshan Xundian
Yangjie Huangtupo、Sanyingzhuang、Daliusuo、Tianqiaodi、Dianxin、Dianlong、Duohe
Dianyuan Laoba、Zhouda
Songyang Shanjiao、Dong Songming
Yangqiao XiShan
1.3 Quantity of Land Requisition and Resettlement
1.3.1 Land Requisition
The total area of permanent land acquisition for Project is 15623.89 mu
(6.27km2): the earth area is 7343.71 mu, the waters is 8280.18 mu. Among earth area,
the area of farm land is 3096.94 mu, the garden is 71.76 mu, timberland 2877.62 mu,
pool is 42.91 mu, unused land 870.76 mu, the construction plot is 383.73 mu.
As for temporary acquired land, the total area is 2333.74 mu (2297.54 mu is
earth land and 36.2 mu is waters), and the farmland is 869.15 mu, timberland
1252.08 mu, unused land is 171.8 mu, the construction plot is 4.4 mu.
For this project, there are 5762.8 mu farm land will be acquired, which involve
1981.6 mu paddy field, 1111.9 mu dry land, 3.5 mu vegetable garden, 911.0mu
shield wood, 1.2mu bamboo, 992.2mu common timberland, 723.7 mu bush, 31.2 mu
fishpond and 6.6 mu orchard. The area of arable land is 3096.9mu, which account
47.1% of total. And the acquired area of building plot is 9.9 mu (public land) unused
land 804.4mu, which is 12.2% of total.
Up to June 30, 2009, according to the survey data from the all affected townships,
the quantity of land in permanent requisition were 5719.9 mu, 1823.21 mu of which
were paddy field, 1100.71 mu were dry land, 2182.19 mu were timberland, 4.52 mu
were garden, 466.44 mu were unused land, 111.53 mu were building plot and 31.3
mu were water area (Fishing pool).
![Page 8: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/8.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
6
As for temporary land acquisition, by the end of June 2009, the total area were
1605.9 mu, including 134.18 mu paddy fields, 721.46 mu dry land, 750.26 mu
timberlands. (Data source: Sheet on area and compensation on land acquisition and resettlement for
Qingshuihai Water Supply Project provided by Qingshuihai Branch Company of Water
Development and Construction, <Resettlement Plan of Qingshuihai Water Supply Project>
(January 2009), Supervision Report of Qingshuihai Water Supply Project (1st ,2nd Quarter 2009))
1.3.2 House Demolishment
According to the Resettlement Plan revised in January 2009, the house
demolishment of project will affect 850 persons from 238 households; the total
demolition area is 81292.06 m2, which involve 2838.73m2 of public building and
2651.00m2 owned by Water Bureau of Xundian County.
Up to end of June 2009, about 2095.02 m2 with frame, brick-concrete and other
kinds of houses had been demolished; the area of brick-concrete was 299.2 m2,
brick-wood was 854.79 m2 and earth-wood was 941.02 m2.
Totally, the demolishment area of auxiliary houses was 974.94 m2, which
involved stable (brick-wood and earth-wood structure) 777.82 m2, tobacco house
(brick-wood and earth-wood structure) 27.54 m2, firewood house (brick-wood and
earth-wood structure) 138.92 m2, toilet (brick-wood, earth-wood and brick-concrete
structure ) 30.66 m2
(Data source: Sheet on area and compensation on house demolishment and resettlement for
Qingshuihai Water Supply Project provided by Qingshuihai Branch Company of Water
Development and Construction, <Resettlement Plan of Qingshuihai Water Supply Project>
(January 2009), Supervision Report of Qingshuihai Water Supply Project (1st , 2nd Quarter 2009))
1.3.3 Demolition for Other Auxiliary Facilities and Specific Facilities
According to the Resettlement Plan, the main items of auxiliary facilities and
specific facilities demolishment for Project involved: 36784 scatter woods, 1 primary
school, Grade 4 road 3.8km, cultivation lane 23.47km, 12 bridges, 1 pumping station,
2 pumping dam, 3 converting stations, 8.77km electricity transmit line, 41.42km
water diversion channels, 27.3km rural road and 5.1km telecommunication lines,
![Page 9: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/9.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
7
stable houe (Brick-wood structure) 475.16 m2, firewood house 138.92 m2, toilet
(brick-wood structure) 26.66 m2,earth square 5318.04 m2, 2.51 m2 stone barricade, 1
iron gate, 1 methane-generating pit, 17.87 m3 water pool and 52.8 m2 brick-enclosure.
Up to June 30th, 2009, according to the data of survey from the townships,
2933.04 m2 square (earth 2334.38m2, cement 598.66m2), 2.51 m2 stone barricade, 1
iron gate, 1 methane-generating pit, 26.45 m3 water pool and 52.8 m2 brick-enclosure,
21 tombs, 1 fix-line telephone and 7 cable television had been demolished.
For specific facilities, there were 1.5km telecommunication lines and 0.2km
electric cable had been demolished at the end of June 2009. (Data source: Sheet on area and compensation on auxiliary facilities demolishment and
resettlement for Qingshuihai Water Supply Project provided by Qingshuihai Branch Company of
Water Development and Construction, <Resettlement Plan of Qingshuihai Water Supply Project>
(January 2009), Supervision Report of Qingshuihai Water Supply Project (1st , 2nd Quarter 2009))
2. Monitoring Survey
2.1 Range of Survey
Monitoring survey for this project was classified into 3 kinds: (1) Impact survey
on land requisition and resettlement; (2) Socio-economic survey in the
project-affected area; (3) Follow-up survey on the living standards of the
project-affected people.
(1)Impact inventory survey on land requisition and resettlement
a. Quantity of required land along alignment and connecting roads for the project, the
amount of demolished buildings and various special facilities, and number of affected
people by the project;
b. Quality, per mu yields and output value for the cultivated land acquired for the
project;
c. Costs for demolished buildings and facilities and their replacement price;
d. Economic profile of the affected households;
e. Economic profile on the affected villages;
f. Bearing capability of the affected people on land requisition and resettlement; g. Opinions and attitudes from the public on the Project
![Page 10: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/10.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
8
(2)Inventory survey on socio-economic in the project-affected area a. Brief account of the administrative areas, including the basic situations of Kunming
City and the project-affected Songming County and Xundian County under its
jurisdiction;
b. Major economic indices of the above-mentioned affected areas in 2007-2009;
c. Distribution of the impoverished people in the above-mentioned affected areas;
d. Living standards of the people of the ethnic minorities and women in the
above-mentioned affected areas;
e. Conditions of the highway networks in the above-mentioned affected areas.
(3)Inventory survey with follow-up way on the living standards of the affected
people:
a. Information about the affected village, including the populations, cultivated lands,
per capita incomes, and preparation and implementation of economic restoration plans
etc;
b. Information about the sample families, including occupation structure, the per
capita assets, per capita income, and the percentages of earnings from planting,
breeding, sideline and industrial productions etc;
c. Attitudes and opinions about the affected people on the project, particularly for the
policies of land requisition and resettlement, and economic restoration plans.
2.2 Survey Institutes
Yunnan Water Resources and Hydropower Survey, Design and Research Institute
(YDRI), Qingshuihai Branch Company of Water Development and Construction and
the governments of Xundian and Songming County were in charge of the survey work
in the project-affected area.
On March 2007, a Field-survey Investigation Group for land requisition and
resettlement had been organized and established, consisting of the members from the
Design Institute and each county and town, which involved conducting detailed
survey on the affected people, demolished buildings, acquired land and other affected
facilities in the project-affected area. After commencement of the project, the survey
work was undertaken by the Advisory Panel of Experts from the Faculty of
Management and Economics of Kunming University of Science and Technology and
![Page 11: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/11.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
9
also was assisted by Qingshuihai Branch Company of Water Development and
Construction and the governments of Xundian and Songming County.
2.3 Survey Approaches
Basic approaches adopted for impact survey for the project:
a. Documents survey and study;
b. Analysis of internal monitoring report;
c. Interviews with owners of projects and resettlement policy executive agencies at
various levels;
d. Family visit of P.R.A. (participatory rapid appraisal);
e. Consultation meeting;
f. On-site observation;
g. Investigation on typical cases
h. Sample survey
2.4 Process of Survey
2.4.1 Selection phase in survey sites
According to the major areas involved in land requisition and resettlement for the
construction of this expressway, the key sites for external monitoring and survey in
the project area were in the 4 administrative villages in Songming County and
Xundian County: 1 in Songming County (Laoba Administrative Village in Dianyuan
Township), 3 in Xundian County (Haiwei Administrative Village in Diansha
Township, Qinghai and Xintian Administrative village in Jinsuo Township). Every
village take out some village groups as survey sites based on the degree of effects of
planning and design on the project. Each village group take out some relocated
households in the respective as the objective of survey based on the types of
affections and the living standards with high, middle and low levels.
2.4.2 Follow-up survey Phase
After final design on the project is finished, surveyors from the Advisory Panel
of Experts from the Faculty of Management and Economics of Kunming University
![Page 12: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/12.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
10
of Science and Technology, and staff from the counties, towns and villages would
involve conducting survey on the affected units and rural people, i.e. socio-economic
survey on the affected villages and households including 21 administrative villages
and 287 affected households, accounting for 100% and 21.03% respectively in total
affected villages and total affected households.
At the end of June 2009, the Advisory Panel of Experts from the Faculty of
Management and Economics of Kunming University of Science and Technology
carried out monitoring survey on land requisition and resettlement for the project and
conducted household survey in the villages of collective resettlement. During the
survey, the expert panel had an all-round understanding on the land requisition and
resettlement in Songming and Xundian County, and held consultation meetings with
the people in charge of land requisition and resettlement from the counties, townships
and villages. The town/townships under survey are: Laoba Village in Dianyuan
Township Songming County, Qinghai Village in Jinsuo Township and Haiwei Village
in Diansha Township of Xundian County. It was totally 9 village groups and 274
relocated households. The major survey points for the external monitoring are:
progress on land requisition and resettlement, allocation and utilization for
compensations, as well as the status on economic restoration. But because of removal
or working at other place, there were actually 287 households had accepted survey.
Results from survey show that works for land requisition for Qingshuihai Project go
in smooth manner; various compensations are delivered timely to affected households
and without delay, appropriation with public funds; production and living of the
affected people by project construction are well arranged; and the living standards of
the villagers have been improved.
3 Data Analysis of Follow-up Village
Before starting of the project, among 21 follow-up surveyed villages, there were
134 village groups included, 38 of them are from 5 follow-up surveyed villages in
Songming County and rest 96 groups are in 16 follow-up surveyed villages in
Xundian County. Generally, there are 2642 households and 10198 persons from
Songming County, 10659 households and 41584 persons from Xundian County
included in follow-up villages. During January to December 2007, annual per capita
![Page 13: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/13.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
11
net income was RMB 1835.11 for surveyed villages, which of Songming County were
RMB 2318.52 and RMB 1351.7 for Xundian County.The land area of 21 follow-up
surveyed villages is 229244.37mu in total,area of Xundian County is 216157.37 mu,
area of Songming County is 13087 mu. The area of paddy field was 17880.2 mu(the
area of Songming County in 5150.5 mu,the area of Xundian County is 12729.7 mu),
the area of dry land is 43972.37 mu(the area of Songming County is 4901.5mu,the
area of Xundian County is 39070.87 mu),the area of woodland is 234441.4 mu(the
area of Songming County is 108849.9mu , the area of Xundian County is
125591.5mu),the area of garden is 3909.6 mu(the area of Songming County is
1476.1mu,the area of Xundian County is 2433.5 mu),the area of unused land is
30671mu(the area of Songming County is 19335 mu,the area of Xundian County is
11336 mu),the area of housing plot is 9808 mu(the area of Songming County is 485
mu,the area of Xundian County is 9323 mu),the area of building plot is 9838.8mu
( the area of Songming County is 353 mu, the area of Xundian County is
9485.8mu),the area of waters is 6498 mu(the area of Songming County is 320mu,
the area of Xundian County is 6178 mu). Average per capita area of farm land for
follow-up village is 1.31mu (the area of Songming County is 1.11mu,the area of
Xundian County is 1.51mu). Average per capita area of house for the follow-up
villages in Songming County is 35.9 m2,and which of Xundian County is 22.6 m2,
average area of all sample villages is 29.3m2.
Up to June 30th, 2009, 5719.9 mu (86.97% of planned area)of the land owned by
follow-up survey villages have been acquired permanently,in which 1823.21 mu
(92% of planned area) is paddy fields; 1100.71 mu (98.99% of planned area) is dry
land, 4.52 mu (44.75% of planned area) is garden, 2182.19 mu (83.03% of planned
area) is timberland, 466.44 mu (57.99% of planned area) is waste land, building plot
is 111.53 mu and 31.3 mu fishpond (100% of planned area).
By the end of June 2009, the total temporary acquisitive land area of 21
follow-up villages was 1605.9 mu, the progress is 70.02%, among which, 134.18 mu
is paddy field, 721.46 mu is dry land, 750.26 mu is timberland, the progress of them
was 99.97%,98.14%,59.88% respectively.
Individually, there are 5 villages in Songming County affected by the Project, the
![Page 14: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/14.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
12
total area of land acquisition of which is 2269.91mu (permanent land acquisition is
2193.82mu, temporary land acquisition is 73.09 mu). As for Xundian County, there
are 4993.6 mu land had been acquired, which include permanent acquisition 3526.08
mu and temporary acquisition 1467.52 mu.
The amount of acquired land in affected village during January to June 2009 is
increased comparing with that in the second half of 2008, but the measures have been
implemented with land reallocation, such as production structures readjustment,
popularization for agricultural technology, the vigorous supports from local
governments, and having a rise for marketing price of farm products adjusted.
Therefore, the economic incomes for all affected villages have not dropped greatly.
With the decrease by 9.75%, the average farmland area per capita is 1.1mu, but the
average per mu output value for the grain crops has reached RMB 987 yuan, 4.7%
higher than that in 2007 and increased 8.86% than the first half in 2008 and was
generally equal to that of the second half of 2008. Influenced by the market situation
and season, the average per mu output value for orchard has dropped to RMB 1440
yuan, 26.4% lower than that in Baseline described and 34.8% lower than that during
January to June in 2008. The average per mu yield value for economic crops has
reached RMB 1338.47 yuan, with a decrease by 14.75% than that in Baseline
described and 10.7% in the first half in 2008. The per capita for net income has
reached RMB 927.08 yuan, which is with decreasing by 5.83% in the same period in
the first half of 2008 and generally kept same with other period. Please refer to the
following diagram and AnnexⅠfor basic information on each affected village.
0
500
1000
1500
2000
2500
Output Value ofGrain per mu(yuan)
Output Value ofEconomic Crop per
mu(yuan)
Output Value ofOrchard per mu(yuan)
Average Net Incomeper capita(yuan)
Item
Amount
Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009
Figure 3-1 Diagram on the status of follow-up survey Villages (Average)
![Page 15: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/15.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
13
4 Data analysis on surveyed sample families
From January to June of
2009, the panel had
conducted household survey
on 287 sample households,
1057 villagers, the quantity
of which was decreased with
Baseline survey and the
survey during the first and
second half in 2008 due to
part of follow-up household
removed or the change of family member. Please refer to Annex II for details.
4.1 Demographical characteristics for the surveyed households
4.1.1 Sex role
Through the 287 household-survey, a total of 1057 persons, in which 542 persons
are males and 515 persons are females, accounting for 51.28 % and 48.72%
respectively, the ratio was 1.046:1. The figures are basically equal with those in the
baseline and 2008. Table 4-1 The Sex Ratio Comparison of Follow-up Household
Item
Survey Duration
Total Population
(Person)
Male Population
(Person)
Female
Population
(Person)
Male Ratio
(%)
Female Ratio
(%)
Baseline 1109 566 543 51.04 48.96
Jan.-June 2008 1103 564 539 51.13 48.87
July-Dec. 2008 1069 552 517 51.64 48.36
Jan.-June 2009 1057 542 515 51.28 48.72
4.1.2 Age distribution
During January to June 2009, most of the people in the surveyed households are
ranged from 16 to 60 years old, the population of them is 836, which take up 78.15%,
![Page 16: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/16.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
14
and there were 231 persons below 16 years and the proportion was 21.85%.
Compared with the baseline and the first and second half in 2008, the proportion is
almost equal.
Table 4-2 The Age Distribution Comparison of Follow-up Household Item
Survey Duration
Total Population (person)
The Population aged below 16
years (person)
The Population aged over 16
years (person)
The Proportion of The Population aged
below 16 years (%)
The Proportion of The Population aged
over 16 years (%)
Baseline 1109 243 866 21.91 78.09 Jan.-June
2008 1103 239 864 21.67 78.33
July-Dec. 2008 1069 236 833 22.08 77.92
Jan.-June 2009
1057 231 826 21.85 78.15
4.1.3 Distribution of nationalities
By the end of June 2009, among the 1057 survey subjects, Han nationality
consists of a majority enjoying 99% of the total while the number for the minority
nationalities is 6. And all of them are Yi nationality and who come from Village
groups of Haiwei No.5, Qinghai No.1 and Huaqing.
4.1.4 Level of education (For Person aged 16 years or above)
Gathered from survey data, among 826 survey subjects at and over 16 years, the
proportion of illiterate was 2.18% (18 persons), which over that described in the
second half of 2008 and baseline, because of change in the family members of sample
households. The proportion of primary school, middle school, high school and college
were 48.91%, 33.29%, 12.46% and 3.15% respectively, the change showed in follow
table. Table 4-3 The Education Level Proportion Comparison of Follow-up Household
Item Survey Duration
The total population aged over 16 years(person)
Illiterate(%)
Primary School (%)
Middle School (%)
High School (%)
College(%)
Baseline 866 1.85 50.66 34.42 10.62 2.45 Jan.-June
2008 864 2.43 50.65 34.40 10.63 1.89
July-Dec. 2008 833 2.16 50.42 33.4 11.04 2.52
Jan.-June 2009
826 2.18 48.91 33.29 12.46 3.15
![Page 17: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/17.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
15
4.1.5 Marital status (For Person aged 16 years or above)
The result from survey during January to June 2009 reflects that the population of
unmarried, who with spouse, divorced, bereft of spouse and other are 151,594,46,
33 and 2 respectively. The detail showed in following table. Table 4-4 The Marital Status Proportion Comparison of Follow-up Household
Survey Item
Survey Duration
The total population aged over 16 years(person)
Unmarried(%)
With spouse (%)
Divorced(%)
bereft of spouse (%)
Others(%)
Baseline 866 18.13 75.29 0.81 5.43 0.35 Jan.-June 2008 864 18.10 75.32 0.70 5.53 0.35 July-Dec. 2008 833 17.88 75.39 12.00 5.64 0.48 Jan.-June 2009 826 18.28 71.91 5.57 3.99 0.24
4.1.6 Status of employment (For Person aged 16 years or above)
(1)Employment situation
As the result from survey during January to June 2009 shows, population of
employment makes up the majority of all the 826 sample population above 16 years
of age with employed population being 630, accounting for 76.27% of the total, which
decreased by about 4 percentage point than that in the second half of 2008. And with a
high proportion, 86.51% of employed population involved in agriculture, forestry,
animal husbandry or fishery, while the structure of rest occupations is almost as the
baseline.
Table 4-5 Occupation Situation of Surveyed Family Members(%)
Time Workers
Laborers in the field of agriculture,
forestry, animal husbandry and
fishery
Commercial staff
Personnel involved in
culture, education and
sanitation
Employees in official organs and institutions
Other personnel
Baseline 2.69 91.37 3.96 0.57 0.42 0.99 Jan.- June
2008 2.53 90.86 4.22 0.84 0.42 1.13
July.- Dec. 2008 2.66 90.40 4.43 0.89 0.44 1.18
Jan.-June 2009 0.48 86.51 8.25 1.27 0.95 2.54 (2)Unemployed population
According to the result of survey during January to June 2009, among all the
surveyed family members at and over 16 years old, 23.73% is unemployed and the
figure of Undergraduate, House keeper, Idler, Retired, Labor force deprived and
Others were 78,10,1,3,59 and 5 respectively.
![Page 18: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/18.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
16
Table 4-6 Unemployed Population of Surveyed Households (%)
Time Undergraduate House keeper Idler Retired Labor force
deprived Others
Baseline 52.20 5.66 0.63 1.89 37.74 1.89 Jan.- June 2008 50.98 6.54 0.65 1.96 38.56 1.31
July.- Dec. 2008 50.00 6.41 0.64 1.92 37.82 3.21
Jan.-June 2009 45.41 5.61 11.73 2.04 30.10 5.10
Figure 4-1 Employment Distribution of Surveyed Family Members at and over 16 years (%)
4.2 Living and Production status of surveyed household
4.2.1 Property status of surveyed household
26 production materials are picked up for the property status survey, the production
materials of which include motorcycle, auto, livestock, sewing machine, tractor,
thresher, livestock-driven trailer, water pump, mechanical grain grinder, other
production machinery, and the living materials involve Color TV set, Black and white
TV set, DVD, Refrigerator, Washing machine, Computer, Microwaver, Water heater,
Air-conditioner, Water dispenser, Electric rice cooker, Fixed-line telephone, Mobile,
Bicycle, Electric fan, Furniture, Sewing machine. According to this category, the
amount of production materials and living materials owned by survey households
increased than that of baseline and in the first and the second half of 2008.
81.64
18.36
82.29
17.71
81.38
18.72
76.27
23.73
0
10
20
30
40
50
60
70
80
90
Employment Unemployment
Prop
ortio
n(%)
Baseline Jan.-June2008 July-Dec.2008 Jan.-June2009
![Page 19: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/19.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
17
Table 4-7 Possessions of Production and Subsistence Materials per Affected Household
Items
Survey
Duration
Average Possession of Production
Materials Per Household
(#/household)
±%
Average Possession of Living
Materials Per Household
(#/household)
±%
Baseline 6.64 -- 8.85 --
Jan.- June 2008
6.64 0.00 8.91 0.68
July.- Dec. 2008
6.30 -5.12 11.91 33.74
Jan.-June 2009
6.39 1.43 12.88 8.14
Figure 4-2 Possessions of Production and Living Materials of all sample household(%)
4.2.2 Public properties like water and power supply
The household-survey results conducted in the first half of 2009 show that
water-supply for the surveyed households were changed: the proportion of the
households who used water from river and pond was increased because the water
supply facilities of tap water were affected by the project. The situation of
power-supply for daily use had little worse than that of baseline, the proportion of
“Ensured” had decreased to 94.08%, but which improved comparing with the
situation in the second half 2008.
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
100%
Prop
ortio
n(%)
Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009
Survey DurationLiving Production
![Page 20: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/20.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
18
Table 4-8 Domestic Water Supplies for Surveyed Households(%)
Time Water Source Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009
Tap water 94.12 94.12 93.72 89.20 Well water 1.38 1.38 1.39 6.62
Water from river and pond 4.50 4.50 4.88 4.18 Total 100.00 100.00 100.00 100.00
Table 4-9 Status on Electricity-Supply for the Household-Survey Family(%)
Time Electricity- Supply Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009
Ensured 98.62 98.27 93.38 94.08 Have but not ensured 1.04 1.38 6.27 5.57
Have not 0.35 0.35 0.35 0.35 Total 100.00 100.00 100.00 100.00
4.2.3 Housing Conditions
(1)Housing Type
During the first half of 2009, the result of survey shows that possession
proportion of storey building had generally been equal with the second half of 2008. Table 4-10 Housing Type of Surveyed Households
Time Housing Type Baseline Jan.-June
2008 July-Dec.
2008 Jan.-June
2009 Bungalow(%) 36.00 13.15 13.55 13.78
Storey Building (%) 64.00 86.85 86.45 86.22 Total 100.0 100.00 100.00 100.00
(2)Housing structure
For 356 houses
owned by all sample
households, the total was
equal with the second half
of 2008. In terms of
housing structure, 75 of
the total sample
households live in a
brick-concrete structure
while those reside in a
structure of brick-wood, frame-concrete and earth-wood account for 70, 16, and 195
respectively. The proportion of each kind of housing structure is generally equal with
baseline and the first half of 2008 reported.
![Page 21: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/21.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
19
Table 4-11 Housing Structure of Surveyed Households(%)
Time Housing Structure Baseline Jan.-June
2008 July-Dec.
2008 Jan.-June
2009 Brick-concrete 20.51 20.83 21.03 21.03
Brick-wood 18.54 18.61 19.61 19.61 Frame-concrete 3.65 3.89 4.59 4.59
Earth-wood 57.30 56.67 54.77 54.77 Total 100 100 100 100
(3)Residential housing area
According to the survey result of the first half 2009, among the 287 surveyed
households with total housing area 77466 m2, the minimal residential housing area is
30m2 while the maximal registers 700m2. The average residential housing area per
household is 269.92m2, which is generally equal with baseline and that in the first and
second half of 2008 respectively. Refer to Table 4-12 for detailed information of
housing area for the surveyed households.
Table 4-12 Residential Housing Area for Surveyed Households(m2)
Time Housing Structure Baseline Jan.-June
2008 July-Dec.
2008 Jan.-June
2009 Brick-concrete 208.89 192.05 195.13 196.1
Brick-wood 190.43 160.69 162.45 165.2 Frame-concrete 204.52 118.57 118.57 118.6
Earth-wood 224.23 250.62 249.8 277.6 Note:This table is only for household with house
4.2.4 Residential environment
(1)To bus station
Compared with the baseline and 2008, the average distance to bus station
decreased to 5.45km. As for the ways of commute, 72% of the people chose bus;
while 25% of surveyed referred to by foot. The average time spent to bus station had
been 29.02 minutes, which was more 8 minutes than former survey result, due to the
construction of project and the national project named ‘Village to Village’.
Table 4-13 The Communication Status of Survey Household to Bus Station Survey Duration
Survey Item Baseline Jan.-June 2008 July-Dec. 2008
Jan.-June 2009
Distance(km) 4.26 4.26 6.08 8.45 On Foot (%) 16.94 16.95 42.16 25
Bus (%) 83.06 83.05 57.84 72 Bicycle (%) 0.00 0.00 0.00 0.00
The way of commute
Other (%) 0.00 0.00 0.00 2 Spend Time (min) 21.3 20.7 28.15 29.02
![Page 22: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/22.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
20
(2)To location of county government Comparing survey results conducted in the first half 2009 with the baseline and
2008, the average distance had decreased to 19.91km. The ways of accessible traffic
chosen by the local people had changed that there were 2% of surveyed residents had
selected other ways to the location of county government and the spent time was
increased to 44.04min.
Table 4-14 The Communication Status of Survey Household to County Government Survey Duration
Survey Item Baseline Jan.-June 2008 July-Dec. 2008
Jan.-June 2009
Distance(km) 17.03 16.98 19.97 19.91 On Foot (%) 0.00 0.00 0.00 4
Bus (%) 100.00 98.99 99.65 94 Bicycle (%) 0.00 0.00 0.35 0.00
The way of commute
Other (%) 0.00 1.01 0.00 2 Time (min) 53.5 53.5 39.05 44.04
(3)To towns
Comparing with baseline and the survey conducted in the 2008, the average
distance to town during January to June 2009 increased to 7.19km. Although majority
of local people also prefer to choose bus to go to town instead of on foot, the time cost
decreased to 27.18min.
Table 4-15 The Communication Status of Survey Household to Towns Survey Duration
Survey Item Baseline Jan.-June 2008 July-Dec. 2008
Jan.-June 2009
Distance(km) 7.16 9.57 7.14 7.19 On Foot (%) 0.00 0.00 25.78 10
Bus (%) 100.00 98.99 73.52 86 Bicycle (%) 0.00 0.00 0.00 0.00
The way of commute
Other (%) 0.00 1.01 0.00 4 Spend Time (min) 30.2 30.3 32.4 27.18
(4)To primary schools The average distance, which is also not over 1km, which was 0.99km, and time
cost by local people to go to primary school are generally same as the baseline
described; and all sample villagers go there on foot.
Table 4-16 The Communication Status of Survey Household to Primary School Survey Duration
Survey Item Baseline Jan.-June 2008 July-Dec. 2008
Jan.-June 2009
Distance(km) 0.86 0.85 0.98 0.99 On Foot (%) 99.31 100.00 99.3 99
Bus (%) 0.69 0.00 0.7 0.00 Bicycle (%) 0.00 0.00 0.00 0.00
The way of commute
Other (%) 0.00 0.00 0.00 1 Spend Time (min) 11.1 11.0 11.8 13.65
![Page 23: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/23.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
21
(5)To middle schools Compared with the baseline and the situation of 2008, the average distance had
decreased to 6.79km. The time cost to go to middle school reduced than the situation
described in baseline. There were 11% of surveyed residents had selected foot as the
way of commute, and the proportion of by bus increased to 85%.
Table 4-17 The Communication Status of Survey Household to Middle School Survey Duration
Survey Item Baseline Jan.-June 2008 July-Dec. 2008
Jan.-June 2009
Distance(km) 7.15 7.15 7.25 6.79 On Foot (%) 0.00 0.00 27.18 11
Bus (%) 100.00 98.99 72.82 85 Bicycle (%) 0.00 0.00 0.00 1
The way of commute
Other (%) 0.00 1.01 0.00 2 Spend Time (min) 31.4 31.2 31.87 27.23
(6)To hospitals Compared with the baseline and the first half of 2008, the average distance the
time spent to go to hospital generally increased, but the ways of communication had
been with some changes: the proportion of who choose on foot had decreased to
28%, but which of by bus had increased to 67%.
Table 4-18 The Communication Status of Survey Household to Hospital Survey Duration
Survey Item Baseline Jan.-June 2008 July-Dec. 2008
Jan.-June 2009
Distance(km) 4.37 4.36 5.35 5.21 On Foot (%) 23.18 59.29 42.16 28
Bus (%) 76.82 39.7 57.84 67 Bicycle (%) 0.00 0.00 0.00 3
The way of commute
Other (%) 0.00 1.01 0.00 2 Spend Time (min) 22.5 23 28.86 25.5
4.3 Financial status of surveyed households
4.3.1 Land area
Result from sample survey during the first half of 2009 reveals that the total area
of various kinds of land was 2505.84mu, which decreased 38.72% by baseline and
67.33% (1687.2 mu) of which was farming land (paddy field and dry land). As for
decreasing extent, building plot was with the maximum.
According to the outcome of survey conducted during January to June 2009, land
area per household is 8.73mu, which reduced 38.3% and 30.2% by described in
baseline and the second half of 2008. To be noticed, the area reflected in this report
![Page 24: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/24.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
22
includes all the land which cultivated in survey duration, no matter the land whether
to be acquired. Table 4-19 Total Land Area of Sample Households (mu)
Time
Land Type Baseline Jan.-June
2008 July-Dec.
2008 Jan.-June
2009
Comparing with Baseline
±%
Comparing with July-Dec.2008
±% Paddy
Field(mu) 797.64 706.54 695.4 434.1 -45.58 -37.58
Dry Land(mu) 2115.48 1940.43 1860.43 1253.1 -40.77 -32.64
Woodland(mu) 699.38 661.74 631.74 453.34 -35.18 -28.24
Garden(mu) 179.18 172.8 152.8 148.1 -17.35 -3.08
Waste land(mu) 167.62 170.19 168.19 139 -17.07 -17.36
Housing Plot(mu) 109.82 74.565 71.565 69.8 -36.44 -2.47
Building Plot(mu) 5.78 3 2.4 2.2 -61.94 -8.33
Water Area(mu) 14.45 8.86 6.86 6.2 -57.09 -9.62
Total(mu) 4089.35 3738.125 3589.39 2505.84 -38.72 -30.19
0%
20%
40%
60%
80%
100%
Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009
Survey Duration
Proportion(%)
Paddy Field Dry Land Woodland Garden Waste land Housing Plot Building Plot Water Area Figure 4-3 Total Contracted Land Area of Sample Household(%)
4.3.2 Income
(1)Average Total Income Per Household and Average Net Income Per Capita
Per household total income of the surveyed households during the first half 2009
is RMB 6359.59 yuan with Qinghai No.5 Group staying at the top (RMB 7424.5 yuan)
![Page 25: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/25.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
23
and Haiwei No.3 Group at the bottom (RMB 2991.11 yuan). 2 of the villages enjoy a
number of below 5000 yuan, which take up 18.18% of all sample groups. The
proportion of the household with income between 5000 to 7000 yuan is 72.73% (3
groups), and 1 village group are with per household total income over 7000 yuan. Table 4-20 Income Status of Surveyed Households (Yuan)
The average net income per capita during January to June 2009 was 1456.35
yuan of all sample households and with the minimum 651.92 yuan in Haiwei No.3
and the maximum 1785.37 yuan in Haiwei No.5, and the average was 1495.96 yuan.
There were 3 groups with the average income per capita below 1000 yuan, and the
proportion of the group with the income per capita between 1000 to 2000 yuan was
72.73%. Table 4-21 Average Net Income Per Capita of Surveyed Households (Yuan)
Average Total Income Per Household1
Village Group Baseline(yuan)
Jan.-June 2008 (yuan )
July-December 2008 (yuan )
Jan.-June 2009 (yuan )
Comparing with Jan.-June 2008 ±%
Deshi Group 15720.00 5869.51 3897.53 6286.49 7.10 Laoba Group 14742.86 6607.38 2675.75 7080.44 7.16 Haiwei No.2 7050.00 5131.25 3018.85 5492.13 7.03 Haiwei No.3 10588.89 2806.89 6744.44 2991.11 6.56 Haiwei No.4 13411.11 5012.78 6477.78 5364.65 7.02 Haiwei No.5 15980.55 6927.14 8526.50 7424.50 7.18 Haiwei No.6 13549.20 5617.00 3442.90 6014.79 7.08 Qinghai No.1 21031.82 5451.00 11794.50 5836.18 7.07 Qinghai No.2 17988.89 4812.61 14687.39 5149.27 7.00
Laohaitou 11766.67 6100.00 6566.70 6534.50 7.12 Huaqing 15108.33 4226.33 7684.17 4518.43 6.91 Average 14267.12 5937.44 6865.14 6359.59 7.11
Average Net Income Per CapitaVillage Group Baseline
(yuan) Jan.-June 2008
(yuan ) July-December 2008
(yuan ) Jan.-June 2009
(yuan ) Comparing with
Jan.-June 2008 ±% Deshi Group 3296 1576.14 1023.86 1475.62 -6.38
Laoba Group 2008 1904.51 859.89 1784.95 -6.28
Haiwei No.2 1624 1324.19 834.4 1238.29 -6.49
Haiwei No.3 1574 701.72 1195.16 651.92 -7.10
Haiwei No.4 2303 1099.71 1665.7 1026.83 -6.63
Haiwei No.5 2521 1904.96 700.32 1785.37 -6.28
Haiwei No.6 2549 1560.28 956.36 1460.68 -6.38
Qinghai No.1 3786 1131.33 2447.92 1056.61 -6.60
Qinghai No.2 3254 1056.43 3331.07 986.06 -6.66
Laohaitou 2705 1830 1970 1714.76 -6.30 Huaqing 2004 834.13 1470.87 776.65 -6.89 Average 2511.3 1555.68 1495.96 1456.35 -6.38
![Page 26: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/26.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
24
(2)Income Structure
From the perspective of income structure of survey household, by the end of June
2009, out of 6359.59 yuan of total income, 56.78% (3610.98 yuan) is derived from
grain planting, 16.78% (1067.21 yuan) from forestry or other crops planting and
5.01%(318.69 yuan) from fishery or poultry farming. Incomes proportions from other
industries are as follows: transportation 5.05%(321.02 yuan), construction 3.02%
(191.99 yuan), industry 0.04%(2.33 yuan), commerce and service industry 9.41%
(598.51 yuan), other sources of income is 3.91%(248.88 yuan).
Comparing with the survey result in the second half of 2008, with the increase with
the increasing in Grain Planting, Forestry or Other Crops Planting, Transportation,
Commerce and Service Industry, the proportion of rest of industries had reduced. Table 4-22 Income Source Distribution of Sample Village Group
Average Income Per Household(yuan)1 Proportion(%) Income Source
Baseline Jan.-June 2008
July-Dec. 2008
Jan.-June 2009 Baseline Jan.-June
2008 July-Dec.
2008 Jan.-June
2009 Grain planting 9286.34 2655.20 3814.12 3610.98 65.09 44.72 55.56 56.78
Forestry or other crops
planting 2553.33 783.05 942.76 1067.21 17.90 13.19 13.73 16.78
Fishery or poultry farming 854.92 308.36 281.75 318.69 5.99 5.19 4.10 5.01
Industry 37.27 32.87 2.36 2.33 0.26 0.55 0.03 0.04 Construction 199.05 266.19 169.58 191.99 1.40 4.48 2.47 3.02
Transportation 250.17 132.88 283.81 321.02 1.75 2.24 4.13 5.05 Commerce and
service 441.94 410.26 528.76 598.51 3.10 6.91 7.70 9.41
Others 644.10 1330.45 830.23 248.88 4.51 22.41 12.09 3.91 Total 14267.12 5937.44 6865.14 6359.59 100.00 100.00 100.00 100.00
0%
20%
40%
60%
80%
100%
Proportion (%)
Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009
Survey Duration
Others
Commerce andservice
Transportation
Construction
Industry
Fishery orpoultry farming
Forestry orother cropsplantingGrain planting
Figure4-4 Income Source Distribution of Sample Village Group (%)
![Page 27: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/27.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
25
4.3.3 Expenditure
During January to June 2009, the average expenditure per households of all
sample village groups was RMB 7628.47 yuan, 2524.28 yuan of which was operating
expenditure,which took up 33.09% of total, with a raising of 11.08 percentage
compared with the same period in 2008, the proportion of consumption expenditure is
66.91% with reduction of 1531.94 yuan comparing with which of the first half of
2008. Table 4-23 Per Household Expenditure of Each Village Group (Yuan,%)
Operating expenditure Consumption expenditure Total Item
Duration Amount (yuan)
Proportion (%)
Amount (yuan)
Proportion (%)
Amount (yuan)
Proportion (%)
Baseline 4441.18 28.86 10676.19 71.14 15117.37 100.00 Jan.-June 2008 1872.91 22.01 6636.13 77.99 8509.04 100.00 July.-Dec. 2008 2094.56 26.13 5920.77 73.97 8015.32 100.00 Jan.-June 2009 2524.28 33.09 5104.19 66.91 7628.47 100.00
Comparing with Jan.-June 2008 34.78 11.08 -23.08 -11.08 -10.35 0.00
Comparing with July-Dec. 2008 20.52 6.96 -13.79 -7.06 -4.83 0.00
Comparing with the second half of 2008, the average cultural expenditure per
household of the first half of 2009 was with the maximum reduction by 8.4%, but the
expenditures on Non-Staple Food and Fuel were increasing by 1.06% and 0.17%.
Differently, the proportion of Grain, Clothes and Socializing were decreasing by
0.55%、4.48% and 4.45% respectively.
Table 4-24 Per Household Consumption Structure of Surveyed Village Groups
Expense(yuan)1 Proportion(%)Time
Item Baseline
Jan.-June
2008
July-Dec.
2008
Jan.-June
2009 Baseline
Jan.-June
2008
July-Dec.
2008
Jan.-June
2009
Cultural Education 2257.44 1593.06 1415.16 791.15 20.03 24.01 23.90 15.50
Total 1809.18 890.42 957.7 639.77 17.57 13.42 16.18 15.63
Self-production 1066.48 644.92 543.66 328.83 10.73 9.72 9.18 8.03 Grain
Purchasing 742.7 245.49 404.22 307.69 6.83 3.70 6.83 7.52
Non-Staple Food 1483.22 387.39 275.64 292.20 11.31 5.84 4.66 5.72
Fuel 879.17 623.53 502.58 442.23 9.04 9.40 8.49 8.66
Clothes 1228.58 858.48 867.77 519.69 10.76 12.94 14.66 10.18
Health Care 1713.15 1252.25 944.29 813.05 14.67 18.87 15.95 15.93
Socializing 1850.45 1031.00 1022.37 654.43 16.63 15.54 17.27 12.82
Total 11221.18 6636.13 5920.77 5104.19 100.00 100 100.00 100.00
![Page 28: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/28.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
26
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009
Survey Duration
Proportion (%)
Cultural Education Grain Non-Staple Food Fuel
Clothes Health Care Socializing
Figure 4-5 Per Household Consumption Structure of Surveyed Village Groups(%)
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
Self-production Purchasing
Source of Grain
Proportion (%)
Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009
Figure 4-6 Grain Consumption Structure of Surveyed Households(%)
4.3.4 Number of out-town odd-jobbers among surveyed family members
(1)Family member distribution of out-town odd-jobbers
Generally speaking, during January to June 2009, there’re 65 family members
among 287 surveyed households staying out of town for odd job opportunities, which
decrease 3 persons by which of the second half in 2008 because of the influence from
financial crisis and the labor force demand for relocation plot construction. No
odd-jobbers are just observed for 4 village groups, which involved Haiwei No.3,
![Page 29: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/29.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
27
Qinghai No.1, Qinghai No.2, Laohaitou. (No analysis in the category of out-town
undertakings is given with the following descriptions being the same). Refer to Table
4-15 for detailed information. Table 4-25 Family Member Distribution of Out-town Odd-Jobbers
Total of out-town odd-jobbers Average population per capita Item
Group Jan.-June
2008 July – Dec.
2008 Jan.-June
2009 ±% Jan.-June 2008
July – Dec. 2008
Jan.-June 2009 ±%
Deshi 32 18 6 -66.67 0.39 0.23 0.07 -68.19Laoba 71 39 41 5.13 0.68 0.37 0.39 5.53
Haiwei No.2 3 0 5 -- 0.38 0 0.63 -- Haiwei No.3 0 0 0 -- 0.00 -- -- Haiwei No.4 4 4 1 -75.00 0.44 0.44 0.1 -77.27Haiwei No.5 7 6 9 50.00 0.32 0.27 0.41 51.52Haiwei No.6 0 1 2 100.00 0.00 0.11 0.25 127.27Qinghai No.1 0 0 0 -- 0.00 0 -- -- Qinghai No.2 0 0 0 -- 0.00 0 -- --
Laohaitou 0 0 0 -- 0.00 0 -- -- Huaqing 2 0 1 -- 0.17 0 0.083 --
Total 119 68 65 -4.41 0.5 0.3 0.26 -13.33
(2)Occupational distribution of out-town odd-jobbers
The survey has classified the variety of occupations that the odd-jobbers are
taking into 8 categories: grain planting, fishery or poultry farming, forestry or other
crops planting, industry, construction industry, transportation industry, commerce and
service industry as well as other trades. From an overall perspective, high
concentration of out-town odd-jobbers is found in construction and service industry
with a proportion of 16.92% and 55.38%, but the rate of grain planting, forestry,
industry, construction reduced in certain extent. Table 4-26 Occupational Distribution of Surveyed Out-town Odd-jobbers (%)
Based on an analysis by three-time industrial classification, namely, with grain
planting, fishery or poultry farming and forestry or other crops planting classified as
Deshi Laoba Haiwei No.2
Haiwei No.4
Haiwei No.5
Haiwei No.6 Huaqing Average
Village Group
Occupation Jan.-June 2009 Jan.-June
2008 July.-Dec.
2008 Jan.-June
2009 ±
Grain Planting 0 0 0 0 0 50 0 0.84 0 1.54 1.54Forestry or other crops
planting 0 2.44 0 0 0 0 0 2.52 0 1.54 1.54
Fishery or poultry farming 0 0 0 0 0 0 0 2.52 6.15 0.00 -6.15
Industry 0 2.44 0 0 11.11 0 0 10.92 3.76 3.08 -0.68Construction
Industry 50 12.2 20 100 11.11 0 0 27.73 8.12 16.92 8.8
Transportation Industry 0 4.88 20 0 0 50 0 2.52 33.24 6.15 -27.09
Commerce or service industry 50 60.98 0 0 77.78 0 100 44.54 29.44 55.38 25.94
Other trades 0 14.63 60 0 0 0 0 8.40 19.28 15.38 -3.9 Total 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
![Page 30: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/30.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
28
the primary industry, industry and building as the secondary industry and
transportation, commercial service as well as other industries as tertiary industry, the
following result can be obtained: the majority of out-town odd-jobbers take up
occupations in the tertiary industry with a proportion of 76.91%, which increased
21.45 percentage points compared with that in the first half of 2008, but decreasing
5.05 percentage points by the last survey result. Table 4-27 Industrial Distribution of Surveyed Out-town Odd-jobbers (%)
Deshi Laoba Haiwei No.2
Haiwei No.4
Haiwei No.5
Haiwei No.6 Huaqing Average Village Group
Industry Jan.-June 2009 Jan.-June
2008 July-Dec.
2008 Jan.-June
2009 Primary Industry 0 2.44 0 0 0 50 0 5.88 6.15 3.08
Secondary Industry 50 14.64 20 100 22.22 0 0 38.65 11.88 20
Tertiary Industry 50 80.49 80 0 77.78 50 100 55.46 81.96 76.91
Total 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
(3)Geographic distribution of out-town odd-jobbers
Geographic distribution of out-town odd-jobbers is analyzed from 5 aspects,
namely, in the local villages or towns, other villages or towns in the local county,
other counties in the local city, other cities in the local province, other provinces.
From a general sense, most of out-town odd-jobbers stay in the other counties in the
local city, taking up a 44.44% with a decreasing by 7.03 percentage points, and
followed by a 33.33% for those staying in the other cities in the local province. No
odd-jobbers are working in foreign countries. See also Table 4-28 for a detailed
description.
Table 4-28 Geographic distribution of Surveyed Out-town Odd-jobbers(%)
Deshi Laoba Haiwei No.2
Haiwei No.4
Haiwei No.5
Haiwei No.6 Huaqing Average Village Group
Location Jan.-June 2009 Jan.-June
2008 July-Dec.
2008 Jan.-June
2009 Local villages or
towns 0 4.88 60 100 11.11 100 100 9.24 10.29 11.11
Other villages or towns of the local
county 0 7.32 0 0 44.44 0 0 10.08 7.35 5.56
Other counties of the local city 66.67 65.85 40 0 44.44 0 0 52.94 51.47 44.44
Other cities of the local province 16.67 12.2 0 0 0 0 0 21.85 22.06 33.33
Other provinces 16.67 9.76 0 0 0 0 0 5.88 8.82 5.56 Foreign countries 0 0 0 0 0 0 0 0.00 0.00 0.00
Total 100 100 100 100 100 100 100 100.00 100.00 100.00
![Page 31: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/31.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
29
(4)Income status of out-town odd-jobbers
From a general prospective, the monthly income per capita of out-town
odd-jobbers from January to June of 2009 was equal to 869.3 yuan, which was less
0.31% than which during the first half of 2008, and reduced by 2.96% than which of
the second half of 2008.
Table 4-29 Income Level Distribution of Out-town Odd-jobbers from Surveyed Households
Village group
Survey Duration Deshi Laoba Haiwei
No.4 Haiwei No.4
Haiwei No.5
Haiwei No.6 Huaqing
Average monthly
wage
Baseline(yuan) 728.97 1231.77 -- 1400 406.25 -- -- 941.75
Jan-June 2008 (yuan) 827.26 1373.04 -- 625 642.86 -- -- 867.04
July –Dec. 2008(yuan) 615.43 1376.06 -- 803.5 658.33 1000 -- 890.66
Jan.-June 2009 (yuan) 708.49 999.21 876.30 1096.48 521.89 978.50 869.30 864.31
Comparing with the first half of 2008 ±% -14.36 -27.23 -- 75.44 -18.82 -- -- -0.31
Comparing with the second half of 2008 ±% 15.12 -27.39 -- 36.46 -20.72 -2.15 -- -2.96
0
200
400
600
800
1000
1200
Deshi Laoba HaiweiNo.4
HaiweiNo.4
HaiweiNo.5
HaiweiNo.6
Huaqing
Village Group
Mounthly Wage (yuan)
Figure 4-7 Monthly Wage Distribution of Out-town Odd-jobbers from Surveyed Households
(%)
![Page 32: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/32.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
30
4.4 Surveyed households’ evaluation of present living situation
4.4.1 Evaluation of production conditions of individual household
Production conditions are evaluated into 5 grades, namely: rather good, superior,
average, inferior and rather bad. Generally speaking, a 64.81% majority of people
think their production conditions are average while those who think of “superior” take
up 20.21%. The two ends of the criterion, rather good and rather bad, and inferior see
small proportions of 5.92%, 7.67% and 1.39% respectively.
Table 4-30 Evaluation of Production Conditions of Surveyed Households (%)
Evaluation Baseline (%)
Jan.-June 2008(%)
July-Dec.2008(%)
Jan.-June 2009(%)
± (Comparing
with Baseline)
± (Comparing
with the first half of
2008)
± (Comparing
with the second half
of 2008) Rather good 9.69 6.23 6.27 5.92 -3.77 -0.31 -0.35
Superior 13.84 12.80 15.33 20.21 6.37 7.41 4.88 Average 67.13 64.36 70.38 64.81 -2.32 0.45 -5.57 Inferior 7.27 13.15 6.62 7.67 0.4 -5.48 1.05
Rather bad 2.08 3.46 1.39 1.39 -0.69 -2.07 0 Total 100.00 100.00 100.00 100.00 0 0 0
4.4.2 Evaluation of one’s own financial status in a context of the whole village
As production condition, financial status is evaluated into 5 grades. Generally
speaking, a 63.41% majority of people think their production conditions are average
while those who think of “superior” take up 18.82%. The criteria rather good and
rather bad are only 5.23% and 1.05% respectively. Sample evaluation is proved
slightly over average. Table 4-31 Surveyed Households’ Evaluation of Their Financial Status in the Village
Evaluation Baseline (%)
Jan.-June 2008(%)
July-Dec. 2008(%)
Jan.-June 2009(%)
± (Comparing
with Baseline)
± (Comparing
with the first half of
2008)
± (Comparing
with the second half
of 2008) Rather good 1.38 1.04 2.44 5.23 3.85 4.19 2.79
Superior 10.73 8.65 11.15 18.82 8.09 10.17 7.67 Average 75.78 70.93 75.96 63.41 -12.37 -7.52 -12.55 Inferior 9.00 15.57 8.71 11.50 2.5 -4.07 2.79
Rather bad 3.11 3.81 1.74 1.05 -2.06 -2.76 -0.69 Total 100.00 100.00 100.00 100.00 0 0 0
![Page 33: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/33.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
31
4.4.3 Evaluation of present residential environment
In general, with regard to the present residential environment, the overall
evaluation of the residential environment is slightly improved due to part of surveyed
households had been positively affected by the construction for the Project. Table 4-32 Surveyed Households’ Evaluation of Present Residential Environment
Evaluation Baseline (%)
Jan.-June 2008(%)
July-December 2008(%)
Jan.-June 2009(%)
± (Comparing
with Baseline)
± (Comparing
with the first half of
2008)
± (Comparing
with the second half
of 2008) Rather good 11.76 6.92 6.97 9.76 -2 2.84 2.79
Superior 9.69 9.69 11.15 18.12 8.43 8.43 6.97 Average 64.36 59.17 68.99 59.23 -5.13 0.06 -9.76 Inferior 10.73 19.03 10.45 10.10 -0.63 -8.93 -0.35
Rather bad 3.46 5.19 2.44 2.79 -0.67 -2.4 0.35 Total 100.00 100.00 100.00 100.00 0 0 0
4.4.4 Evaluation of neighborhood relation
There’s a generally good evaluation related to a harmonious neighborhood
relation with “average” and “rather good” accounting for an individual 48.78% and
21.6%. Only 13.24% of surveyed households regard their neighborhood relation as
“inferior” or “rather bad” neighborhood relation, and which decreased than that of
2008.
Table 4-33 Surveyed Households’ Evaluation of Neighborhood Relation
Evaluation Baseline (%)
Jan.-June 2008(%)
July-December 2008(%)
Jan.-June 2009(%)
± (Comparing
with Baseline)
± (Comparing
with the first half of
2008)
± (Comparing
with the second half
of 2008) Rather good 36.33 34.26 40.77 16.38 -19.95 -17.88 -24.39
Superior 12.46 14.53 17.07 21.60 9.14 7.07 4.53 Average 50.52 43.94 40.42 48.78 -1.74 4.84 8.36 Inferior 0.00 6.57 1.74 8.01 8.01 1.44 6.27 Rather
bad 0.69 0.69 0.00 5.23 4.54 4.54 5.23
Total 100.00 100.00 100.00 100.00 0 0 0
4.4.5 Evaluation of life satisfaction
In general, 51.92% of surveyed households hold an “inferior” opinion toward
their present being, which increased 48.44% than which described in the second half
of 2008. The satisfaction extent of most of survey household had been inferior to
![Page 34: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/34.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
32
which of baseline and the 2008.
Table 4-34 Surveyed Households’ Evaluation of Life Satisfaction
Evaluation Baseline (%)
Jan.-June 2008(%)
July-December 2008(%)
Jan.-June 2009(%)
± (Comparing
with Baseline)
± (Comparing
with the first half of
2008)
± (Comparing
with the second half
of 2008) Rather good 13.50 9.69 5.57 5.23 -8.27 -4.46 -0.34
Superior 11.76 12.80 14.98 17.07 5.31 4.27 2.09 Average 65.05 57.79 60.28 17.07 -47.98 -40.72 -43.21 Inferior 5.54 14.53 3.48 51.92 46.38 37.39 48.44 Rather
bad 4.15 5.19 15.68 8.71 4.56 3.52 -6.97
Total 100.00 100.00 100.00 100.00 0 0 0
4.4.6 New-Added Economic Recovery Measure
According to the result of survey conducted during January to June 2009,the total
area of new-added orchard in 11 sample village groups are 10mu, and there were
newly 11 mu for planting economic crops, 42 is the quantity of new-added livestock.
In addition, there are 5 villagers as new-added out-town odd-jobbers. The total
income of above measures is 88000yuan. Table 4-35 Summary of New-Added Economic Recovery Measure in Surveyed
Households(Jan.-June. 2009)
New-Added Planting areas
for orchard
New-Added Cultivating area
for economic crops
New-added livestock
New-added out-town
odd-jobbers
New-Added Income Village Group
mu mu Capita Person yuan Deshi 3 4500 Laoba 1 5 4000
Haiwei N0.2 1 4800 Haiwei N0.3 1 Haiwei N0.4 2 2 2800 Haiwei N0.5 3 6 23 1 63000 Haiwei N0.6 1 3 4 1 5400 Qinghai No.1 Qinghai No.2
Laohaitou Huaqing 3 7 3500
Total 9 11 42 5 88000
![Page 35: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/35.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
33
5 Land Requisition and Resettlement
5.1 Progress on land requisition and resettlement
Construction of Qingshuihai Water Supply Project had begun October 2007. By
the end of June 2008, land requisition had been carried out in almost all of villages,
following tables reflect in detail.
5.1.1 Progress of Permanent Acquired Land
By the end of June 2009, there were 25 village groups of Xundian County and 15
village groups from Songming County had involved permanent land acquisition. Total
area of permanent acquired land was 5719.9 mu,account for 86.97% of total planned
area (6577.1 mu). And the acquired area of paddy field, dry land, garden, timberland,
unused land, building plots and fishpond is 1823.21mu, 1100.71mu, 4.52mu, 2182.19
mu, 466.44mu, 31.3mu and 111.53mu, which respectively account for 92%, 98.99%,
44.75%, 83.03%, 29.06% and 100% of plan. (Planned area of acquired paddy field,
dry land and fishpond is 1981.6mu, 1111.9mu, 10.1mu, 2628.1mu, 804.4mu, 9.9mu,
383.73mu, 31.3mu respectively)
0 20 40 60 80 100 120
Paddy Field
Dry Land
Timberland
Garden
Unused Land
Building Plot
Fish Pool
Total
Land Type
Progress(%)
Completed Incompleted
Figure 5-1 Progress of Land Requisition (From October 2007 to June 2009)
![Page 36: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/36.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
34
Table 5-1 Summary Sheet on Land Requisition From October 2007 to June 2009
Land in requisition (mu) Number of people actually affected County
Paddy Field Dry land Forestry Garden Waste Land Building Plot Fishpond/Pond Total Village Population
Songming 1097.05 293 546.21 4.52 130.03 111.53 11.48 2193.82 5 431
Xundian 726.16 807.71 1635.98 0 336.41 0 19.62 3525.88 16 833
Total 1823.21 1100.71 2182.19 4.52 466.44 111.53 31.1 5719.7 21 1264
Up to June of 2009, the total area of permanent land acquisition of Songming
County was 2193.82mu, which involved 431 villagers from 5 villages.
As for the Xundian County, total area of permanent land acquisition was
3525.88mu, which affected 833 villagers from 16 villages. Table 5-2 The Progress of Permanent Land Acquisition (Oct.2007~June.2009)
Songming County Xundian County
Planned Area Acquire Area (Up to 31st June of 2009) Progress Planned Area Acquire Area
(Up to 31st June of 2009) Progress
County
Land mu mu % mu mu %
Paddy Field 1253.4 1097.05 87.53 728.3 726.16 99.71Dry Land 301.1 293 97.31 810.8 807.71 99.62
Timberland 700.3 546.21 78.00 1928 1635.98 84.85Garden 5.4 4.52 83.70 5 0 0.00
Unused Land 155.1 130.03 83.84 649.4 336.41 51.80Building Plot 373.83 111.53 29.83 9.9 0 0.00
Fish Pool 0.00 11.48 -- 31.3 19.62 62.68Total 2414.9 2193.82 90.85 4162.2 3526.08 84.71
5.1.2 Progress of Temporary Land Acquisition
Up to the end of June 2009, there were 134.18 mu paddy field, 721.46 mu dry land
and 750.26 mu timberland; total in 1605.9 mu had been temporary land acquisition.
The total area of temporary land acquisition of Songming County was 138.38mu,
which involved 431 villagers from 5 villages.As for Xundian County, the total area of
temporary land acquisition was 1456.72 mu, which affected 833 villagers from 16
villages. Table 5-3 The Progress of Temporary Land Acquisition (Oct.2007~June.2009)
Songming County Xundian County
Planned Area Acquire Area
(Up to 31st June of 2009)
Progress Planned Area Acquire Area (Up to 31st June of 2009) Progress
Unit mu mu % mu mu %
Paddy Field 65.3 0 0.00 68.9 68.89 99.99 Dry Land 60 66.64 111.07 675.1 654.82 97
![Page 37: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/37.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
35
Timberland 496.6 6.45 1.30 756.1 743.81 98.37 Garden 0 0 -- 0 0 0
Unused Land 108.1 0 0.00 63.8 0 0 Building Plot 0 0 -- 0 0 0
Fish Pool 0 0 -- 0 0 0 Total 729.8 73.09 10.02 1563.9 1467.52 93.84
0
20
40
60
80
100
120
Paddy Field Dry Land Timberland Unused Land Total
Land Type
Progress (%)
Completed Incompleted Figure 5-2 The Progress of Temporary Land Acquisition (Oct.2007~June.2009)
5.1.3 Progress of House Demolishment
Up to 30th June 2009, including residential house and auxiliary houses,
2095.02m2 houses had been demolished, which is 10.47% by the area in
Resettlement Plan. (Planned area is 81917.5m2.) Among them, brick-concrete house
299.21 m2, brick-wood house 854.79m2, earth-wood house 941.02m2, which is
respectively 14.76%, 40.1%, 6.92% of the area in Plan. (Planned areas of
demolished house are: brick-concrete house 9185.9m2, brick-wood house 12822.2m2,
earth-wood house 34593.7 m2) By the end of June in 2009, the total area of house
demolishment of Xundian County was 1649.04m2, which affected 833 villagers from
16 villages. The area of Songming County is 445.98 m2 with the progress of 0.91%. Table 5-4 Summary sheet on demolished houses and relocation
From October 2007 to June 2009 Number of people affected by
house demolishment and removalArea of demolished houses (㎡)
County
Number of households Number of
people Frame Brick-concrete Brick-wood Earth-wood
Total
Songming 5 431 0 0 95.48 350.5 445.98Xundian 16 833 0 299.21 759.31 590.52 1649.04
Total 21 1264 0 299.21 854.79 941.02 2095.02
![Page 38: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/38.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
36
0 20 40 60 80 100
Progress (%)
Frame
Brick-concrete
Brick-wood
Earth-wood
TotalHouse Type
Completed Incompleted
Figure 5-3 Progress of House Demolishment (From October 2007 to June 2009)
Table 5-5 The Progress of House Demolishment
Songming County Xundian County
Planned Area Demolishment Area (Up to 31st June of 2009) Progress Planned Area
Demolishment Area (Up to 31st June of
2009) Progress
Unit m2 m2 % m2 m2 % Frame 3448.5 0 0.00 0.00 0.00 --
Brick-concrete 7830.3
0 0.00 1355.60 299.21 22.07 Brick-wood 7539.5 95.48 1.27 5282.70 759.31 14.37 Earth-wood 30205.8 350.5 1.16 4387.90 590.52 13.46
Total 49024.1 445.98 0.91 11026.30 1649.04 14.96
Besides of common house, there were 974.94m2 auxiliary houses had been
demolished, which is 4.46% by planned area. Among them, the demolishment
progress of Livestock House, Firewood house and Toilet reached 12.86%, 0.45%,
1.77% and 1.68% respectively. (According to Resettlement Plan, total area of
auxiliary house demolishment is 21867.2m2, including Livestock House 6048.6m2,
Firewood house 1819.8m2 and Toilet 7860.5m2). Table 5-6 The Progress of Auxiliary House Demolishment (From October 2007 to June
2009) Songming County Xundian County
Planned Amount
Demolishment Area (Up to 31st June of
2009) Progress Planned
Amount
Demolishment Area (Up to 31st June of
2009) Progress
Unit m2 m2 % m2 m2 % Brick-wood 807.90 51.12 6.33 1638.9 521.36 31.81 Stable Earth-wood 2934.60 113.5 3.87 667.2 91.84 13.76
![Page 39: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/39.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
37
Total 3742.50 164.62 4.40 2306.1 613.2 26.59 Brick-wood 227.20 0 0.00 0.1 0 0.00 Earth-wood 5899.60 27.54 0.47 11.5 0 0.00
Tobacco House
Total 6126.80 27.54 0.45 11.6 0 0.00 Brick-wood 2514.00 0 0.00 369.4 138.92 37.61 Earth-wood 4818.80 0 0.00 158.3 0 0.00 Firewood
Total 7332.80 0 0.00 527.7 138.92 26.33 Brick-wood 347.20 0 0.00 187.5 26.66 14.22 Earth-wood 1217.00 0 0.00 68.2 4 5.87 Toilet
Total 1564.20 0 0.00 255.7 30.66 11.99 Total 18766.30 192.16 1.02 3101.1 782.78 25.24
Table 5-7 Summary Sheet of Auxiliary House Demolishment (From October 2007 to June
2009)
Stable Tobacco House Firewood House Toilet County Affected
Situation Brick-wood Earth-wood Brick-wood Earth-woodBrick-wood Earth-wood Brick-wood Earth-wood
Village Population (m²) (m²) (m²) (m²) (m²) (m²) (m²) (m²)
Songming 5 413 51.12 113.5 0 27.54 0 0 0 0 Xundian 16 833 521.36 91.84 0 0 138.92 0 30.66 4
Total 21 1246 572.48 205.34 0 27.54 138.92 0 30.66 4
5.1.3 Progress of Auxiliary Facility Demolishment
Taking 30th June 2009 as the end, auxiliary facility demolishment involved 8 types,
included 1 gate, 1 methane tank, 26.45 m3 pool, drying yard 1762.08 m², stone
barricade 2.51 m3 and enclosure(brick) 52.8m², 21 tomb and 7 cable TV, and the
progress is 1.61%, 8.33%, 7.64%, 3.04%, 0.08%, 5.19%, 28.38% and 68%
respectively. (According to Resettlement Plan, the demolished quantities of above
auxiliary facilities are: 62 gates, 12 methane tanks, 346 m3 pool, drying yard 40921.7
m², stone barricade 3315.9 m3 and enclosure (brick) 1017.2 m²,74 tombs and 190
cable TVs. Table 5-8-1 Summary Sheet on Demolishment for Auxiliary Facilities (A)
From October 2007 to June 2009 Gate Drying Yard County Affected Situation
Wood Iron Methane
tank Pool Well Fix-line telephone
Cable TV Concrete Stone Earth
Unit Village Population No. Tank m3 Well Set Set (m²) (m²) (m²) Songming 5 413 0 0 0 0 0 1 1 80.96 0 1090 Xundian 16 833 0 1 1 26.45 0 6 0 517.7 0 1224.38
Total 21 1246 0 1 1 26.45 0 7 1 517.7 0 1224.38Table 5-8-2 Summary Sheet on Demolishment for Auxiliary Facilities (B)
From October 2007 to June 2009 Tomb Enclosure Stone
barricadeCounty Affected household Magnificent Stone Earth Brick Stone Earth
Unit Village Population Tomb Tomb Tomb (m²) (m²) (m²) (m3)
![Page 40: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/40.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
38
Songming 5 413 0 0 0 0 0 0 0 Xundian 16 833 2 19 0 215.8 181 0 2.51
Total 21 1246 2 19 0 215.8 181 0 2.51 Table 5-9 Demolishment Progress of Auxiliary Facilities(Xundian County and Songming
County) Songming County Xundian County
Planned Amount Demolishment Amount
(Up to 31st June of 2009) Progress Planned Amount
Demolishment Amount
(Up to 31st June of 2009)
Progress
Concrete 14412.4 80.96 0.56 2281.9 517.7 22.69Stone 373.7 0 0.00 0 0 -- Earth 24175.2 1090 4.51 16746.5 1244.38 7.43
Drying Yard (m²)
Total 38961.2 1170.96 3.01 19028.4 1762.08 9.26 Brick 801.4 0 0.00 215.8 52.8 24.47Stone 12.2 0 0.00 0 0 -- Earth 787.7 0 0.00 181 0 0.00
Enclosure (m²)
Total 1601.3 0 0.00 396.8 52.8 13.31Stone
barricade (m3)
Total 2683.9 0 0.00 632 2.51 0.40
Wood 4 0 0.00 0 0 -- Iron 54 0 0.00 4 1 25.00Gate(#)
Total 58 0 0.00 4 1 25.00Methane tank(#) 1 0 0 0.00 11 1
Pool(m3) 9.2 0 0 0.00 336.9 26.45Well(#) 0 0 0 -- 60 0
Decorated 0 0 -- 3 2 66.67Stone 0 0 -- 20 19 95.00Earth 0 0 -- 51 0 0.00
Tomd(#)
Total 0 0 -- 74 21 28.38Cable TV(#) 2 0 1 50.00 188 6
Fix-line telephone(#) 4 0 1 25.00 64 0
5.2 Compensation standards for land requisition and resettlement
5.2.1 Compensation Standards for Permanent Land Acquisition
(1)Paddy Field and Dry Land
The compensation standards for permanent land acquisition and inundated area
had been calculated according to relative policies and regulations issued by nation or
Yunnan Province. The calculation price referred to price in the third quarter 2007.
Based on <Regulations on Land Acquisition Compensation and Resettlement for
Large and Medium Size Water Resources and Hydroelectric Construction Projects>
(Command of State Council No.471) and <Regulation of Yunnan Province on Land
![Page 41: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/41.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
39
Administration>, standards of land compensation and resettlement subsidies for
requisition of farmland (including paddy field and dry land) is 16 times its Average
Annual Output Value (AAOV) of the latest three years, and standard of compensation
and subsidy for requisition of garden plot is 13 times its Average Annual Output Value
(AAOV) of the latest three years.
Based on the estimated annual output of paddy field and dry land of affected
villages that are all located in Xundian County and Songming County, the
compensation standard of this project is assured according to the average. The
compensation of paddy field and dry land are shown as Table 5-10.
Table 5-10 Compensation Standards for Permanent Land Acquisition(Paddy Field, Dry Land)
Paddy Field Dry Land Land TypeItem Standard Calculation Standard Calculation
Compensation Fee for Land Acquisition(yuan/mu) 24480 (AAOV)1530yuan ×16 17600 (AAOV)1100yuan×16
Standing Crop Compensation(yuan/mu) 765 (AAOV)1530yuan×0.5 550 (AAOV)1100yuan×0.5
Total(yuan/mu) 25245 18150 (2)Orchard, Vegetable Plot
Garden plot is mainly orchard with pears and apples cultivated. There are 70 to 80
fruit trees cultivated in one mu land, which brings the income of 1500 to 1800 yuan
annually. Therefore, the compensation standard is 21450 yuan/mu.
Table 5-11 Compensation Standards for Permanent Land Acquisition (Orchard, Vegetable
Plot)
Vegetable Plot Orchard Land Type Item Standard Calculation Standard Calculation
Compensation Fee for Land Acquisition(yuan/mu) 27200 (AAOV)1700yuan×16 21450 (AAOV)1650yuan×13
Standing Crop Compensation(yuan/mu) 850 (AAOV)1700yuan×0.5
Sunshade(yuan/m2) 7.5 Total(yuan/mu) 28050 21450
(3)Woodland The inundated area of forest land is mainly forestry land and bush forest. The
forest land is mainly conifer and sundry trees. The bush forest is mainly sundry forest
such as the new forest after felling. The compensation of woodland is fixed according
to <Regulation of Yunnan Province on Forest Land Administration.
Table 5-12 Compensation Standards for Permanent Land Acquisition(Woodland) Timber Tree Land Shrub Land Shelter Forest Land Land Type
Item Standard Calculation Standard Calculation Standard Calculation
Compensation Fee for Land Acquisition
4000 Value of forest storage×4 2400 CTTL1×60% 12000 CTTL1×3
![Page 42: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/42.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
40
(yuan/mu) Compensation Fee for
Trees Felling (yuan/mu) 800 Value of forest storage×0.8 480 4000 CTTL1×5
Subsidy for Resettlement (yuan/mu) 200 Annual Value of forest storage×2 120 200 CTTL1
Total (yuan/mu) 5000 3000 16200 Note: 1. CTTL is the abbreviation of Compensation of Timber Tree Land (4)Unused Land
According to Yunnan Province Approval for Non-use National or Collective Land
Compensation and Resettlement Subsidy of Large and Medium Size Water Resources
and Hydroelectric Construction Projects ( YZP[2003]53, Government of Yunnan), the
unused land is compensated by the half of compensation standard of dry land, which
is 8800yuan/mu.
5.2.2 The Compensation Standard of Temporary Land Occupation
The period of temporary land occupation for project construction is about
averagely three years. Therefore, the compensation standard is calculated according to
three years.
(1) Farmland. The compensation standard for temporary farmland occupation is 3
times of AAOV of the latest three years, the compensation standard for temporary
paddy field occupation is 4590 yuan/mu, the dry land 3300 yuan/mu.
(2) Forestry land. The compensation standard for temporary forestry land
occupation is assured in terms of the factual output of the period of occupation, which
contains the compensation fees of trees felling, timber land 1800 yuan/mu, and bush
forest 1080 yuan/mu, shelter forest land 2527 yuan/mu.
(3) Unused land. As for unused land that has no output, there is no relevant
compensation.
(4)For the temporary occupation near the entry of Maichong tunnel, which involve
land and houses of Holiday Club of Xundian Water Bureau, the compensation will be
paid according to standards of similar house and auxiliary facilities.
5.2.3 Compensation Standards for Residential Houses and Auxiliary Facilities
According to the current price, the construction cost of living rooms is
computed at full replacement cost respectively in terms of frame structure, brick
concrete structure, brick wood structure and earth wood structure. According to the
![Page 43: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/43.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
41
computed results, the compensation standards for house and auxiliary facility
demolition are as follow.
Table 5-13 Compensation Standards for Demolishment(Living House)
Item Unit Type Standard (yuan/unit) frame structure 700
brick concrete structure 500 brick wood structure 300 Living House m2
earth wood structure 230 Table 5-14 Compensation Standards for Demolishment(Auxiliary Facilities)
Table 5-15 Compensation Standards for Demolishment(Special Facilities)
Item Unit Type Standard (yuan/unit)
Channel Km - 100000 Water Supply Pipe Km - 30000
Power Transfer Station No. - 10000 Electricity Supply Line Km - 35000 Communication Line Km - 20000
Road Km - 200000
Item Unit Type Standard (yuan/unit) brick wood structure 270 Livestock House m2 earth wood structure 200 brick wood structure 220 House for Tobacco
Baking m2 earth wood structure 140 brick wood structure 200 Firewood House m2 earth wood structure 120
brick concrete structure 500 brick wood structure 300 Toilet m2 earth wood structure 230
Concrete 12 Stone 18 Drying Yard m2 Earth 3 Brick 23 Stone 30 Fence Wall m2 Earth 15
Protection Wall m3 160 wood 300 Door No. iron 600
Wire Television No. 300 Well No. 300 Pond m3 70
Magnificent 2000 Stone 1200 Tomb tomb Earth 800
Methane-generating pit No. 2000 Fix-line Telephone No. 108
![Page 44: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/44.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
42
Bridge No. - 50000
5.2.4 Scattered Trees
According to actual situation, the trees scattered nearby houses and fields will be
compensated based on the standards for fruit tree, economic tree and timber tree. Table 5-16 Compensation Standards for Scattered Trees
Age of Tree Scattered Trees Type Unit
Long (yuan/unit) Medium (yuan/unit) Short (yuan/unit)
Fruit Tree No. 150 80 5 Economic Tree No. 120 60 4
Timber Tree No. 60 30 3 Bamboo Forest No. 100 60 20
5.2.5 The moving subsidies
. The moving subsidies include the fares, moving time-lost compensation and
transition subsidies etc. The fares is 45 yuan per capita, the moving subsidy is 1200
yuan per household, is 660 yuan per capita ( in terms of the number of labor forces),
and transition subsidy is 300 yuan per household. In addition, every displaced person
can get 300 yuan for living support subsidy during the period of displacement so as to
alleviate their living burden during that period.
5.2.6 Compensation for public infrastructure in the concentrated relocating place
Compensation for public infrastructure in the concentrated relocating place,such
compensation includes charges for house site, ground leveling, water and power
supply facilities, streets, sewerage system, lighting, etc. The compensation standards
of four concentrated relocating places are as follow: Maichong relocating place of
Qinghai Village Committee: 11726yuan/person, Haiwei relocating place:
12633yuan/person, Renjiahou relocating place of Laoba Village: 15141yuan/person,
Deshi relocating place 10764yuan/person. The standard of other concentrated
relocating places are equal with which for Maichong relocating place of Qinghai
Village: 11726yuan/person。
![Page 45: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/45.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
43
5.2.7 Subsidies of Building House
According to the current price, the construction cost of living rooms is
computed at full replacement cost respectively in terms of brick concrete structure,
brick wood structure and wood structure. According to the computed results, the
compensation standards for house demolition are lower than replacement cost.
Therefore, the affected people have additional subsidies to rebuild their house after
they are compensated, which is 1500yuan/person and assured based on actual
situations of Yunnan Province.
5.2.8 Subsidies of Poverty Household
Through investigating, there are poverty households in project affected area, so
20% of total population affected by demolishment and removal will get the subsidies:
1600yuan/persone.
5.3 Payment Status on compensations for land requisition and
resettlement
Up to June 30, 2009, the payment progress on compensations for land requisition
and resettlement for the whole project had completed partly, the status of payment on
compensation are showed in following tables. Table 5-17 Summary on Compensation for Permanently Acquired Land in Affected Area
County Songming Xundian Total Administrative Village No. 5 16 21
Village Group No. 13 17 30 Affected Population Person 413 833 1246 Paddy Field Ten thousand yuan 2943.41 1780.98 4724.39Dry Land Ten thousand yuan 515.67 544.98 1060.65Woodland Ten thousand yuan 231.48 1425.14 1656.62
Garden Plot Ten thousand yuan 19.67 0 19.67 Unused Land Ten thousand yuan 98.15 296.04 394.19 Housing Plot Ten thousand yuan 0 0 0 Building Plot Ten thousand yuan 0 0 0 Ty
pe o
f Acq
uire
d La
nd
Water Area Ten thousand yuan 30.59 52.81 83.4 Total Ten thousand yuan 3838.97 4099.95 7938.92
![Page 46: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/46.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
44
Table 5-17 Summary on Compensation for Temporarily Acquired Land in Affected Area County Songming Xundian Total
Administrative Village No. 5 16 21 Village Group No. 13 17 30 Affected
Population Person 413 833 1246 Paddy Field Ten thousand yuan 29.97 4.59 34.56 Dry Land Ten thousand yuan 22 175.63 197.63Woodland Ten thousand yuan 70.61 112.51 183.12
Garden Plot Ten thousand yuan 0 0 0 Unused Land Ten thousand yuan 0 0 0 Housing Plot Ten thousand yuan 0 0 0 Building Plot Ten thousand yuan 0 0 0 Ty
pe o
f Acq
uire
d La
nd
Water Area Ten thousand yuan 5 16 21 Total Ten thousand yuan 122.58 292.73 415.31
Table 5-18 Summary on Compensation for Demolished House in Affected Area
County Songming Xundian Total Administrative
Village No. 5 16 21
Village Group No. 13 17 30 Affected
Population Person 413 833 1246 Concrete-frame
structure (yuan) 241.39 0 241.39
Brick-concrete structure (yuan) 383.39 67.79 451.18
Brick-wood structure (yuan) 169.1 128.48 297.58
Type of Demolished
House
Earth-wood structure (yuan) 694.73 46.99 741.72
Total (yuan) 1488.61 243.26 1731.87
Table 5-19 Summary on Compensation for Auxiliary Facilities in Affected Area County Songming Xundian Total
Administrative Village No. 5 16 21 Village Group No. 13 17 30 Affected
Population Person 413 833 1246 Livestock House (yuan) 66.25 24.23 90.48
House for Tobacco Baking (yuan) 84.36 0.32 84.68
Firewood House (yuan) 108.11 4.92 113.03 Toilet (yuan) 38.41 3.43 41.84
Drying Yard (yuan) 24.86 1.58 26.44 Fence Wall (yuan) 1.88 0.39 2.27
Protection Wall (yuan) 43.79 2.8 46.59 Door (yuan) 3.36 0 3.36
Type of Demolished
Facilities
Methane-generating pit (yuan) 1.4 0.4 1.8
![Page 47: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/47.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
45
Pond (yuan) 0.08 1.26 1.34 Well (yuan) 0.78 0.33 1.11
Fix-line Telephone (yuan) 0 0 0 Wire Television (yuan) 4.59 0.3 4.89
Tomb (yuan) 3.08 0 3.08 Total (yuan) 380.95 39.96 420.91
5.4 Payment progress on compensations for land requisition and
resettlement
Up to June 30th 2009, the payment progress on compensations for land requisition
and resettlement for the whole project had reached 60.18% in the planned
compensation sum, of which compensation sum for rural resettlement has got an
amount by 87.72%; compensation sum for other expenses had got an amount by
21.87%, and the payment progress of Compensation to enterprise, Fund for specific
facility rebuilding, Contingency, External Capital of Project is 75.81%, 5.26%,
21.87%, 54.85% respectively. Please refer to the following table below for details. Table 5-20 Payment Progress on Compensation Cost for Land Acquisition and Resettlement
Item
Planned compensation cost for land acquisition and
resettlement
Funds paid (before 30th June. 2008)
Funds paid (before 31st Dec. 2008)
Funds paid (before 30th June 2009)
Payment progress
(%) (before
30th June 2009)
Unit 10000 yuan 10000 yuan 10000 yuan 10000 yuan (%) 1 Rural Resettlement 15867.86 6559.29 8171.58 13442.84 84.72 2 Compensation to
enterprise 373.7 171.09 171.09 283.31 75.81
3 Fund for specific facility rebuilding 1901.55 40.00 100.00 5.26
4 Compensation for specific facility
restoring 100.93 0.00
5 Fund for reservoir bottom cleaning 52.64 43.7 83.02
6 Other Expenses1 1821.2 346.15 347.74 398.24 21.87 7 Environmental
Protection 40 0.00
8 Contingency 2025.0 73.5 337.50 1110.75 54.85 9 Taxes 2 3365.11 0.00
10 External Capital of Project3 25 12 12.00 12.00 48.00
Total resettlement compensation
(including taxes) 25572.99 7162.03 9079.91 15390.84 60.18
![Page 48: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/48.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
46
Note: 1. Other expenses include expense of survey and designing, monitoring, resettlement implementation
management cost;2. Taxes include tax for possession and use of land, expense of opening up wasteland for farming,
cost of forest recovery;3. External Capital is mainly for project investigation external expenses and compensation of
local coordinators.
6 Management of Resettlement Funds & Disbursement
6.1 The Management of Resettlement Fund
In order to enhance the
financial management of
resettlement fund and ensure the
safety and proper utilization of
the fund, during 8th July 2008 to
9th July 2008, Kunming Water
Supply Group Co. Ltd. (KWSG),
the project office of Kunming
Qingshuihai Water Supply
Project (KQWSP), Huaxin
Huakun Accountants Affairs Office, the audit office of KWSG and the financial
section of KQWSP had respectively checked and field investigated the situation of
accounting and financial management of resettlement offices in Songming County
and Xundian County of Qingshuihai Water Supply Project. Furthermore, in 16th July
2008, some relative problems and suggestions had been put forward in detail by
issuing the documents named < Rectify and Reform Notice of Inspection to
Resettlement Fund Management of Qingshuihai Water Supply in Songming County>
(QingYinShuiCai No.〔2008〕1) and < Rectify and Reform Notice of Inspection to
Resettlement Fund Management of Qingshuihai Water Supply in Songming County>
(QingYinShuiCai No.〔2008〕2). Currently, according to above documents, the
resettlement institutions of Songming County and Xundian County had improved the
financial management of resettlement fund, and during the process of land acquisition,
demolishment and resettlement, comply with the national and provincial financial
management regulations and < Resettlement Fund Management Regulations of
![Page 49: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/49.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
47
Large-Medium Scale Hydro-project in Yunnan Province > and <Practical Suggestions
of Yunnan Province People Government for Compensation and Resettlement of
Large-Medium Scale Hydro-project>, taking ‘Government Charge, Project
Management, Specific Account, Audit Monitoring’ as the management principles, the
report systems of construction process and fund distribution and usage had been set up
in order to ensure the safety of fund allocation and effective utilization.
6.2 The Appropriation and Payment of Resettlement Fund
Up to 30th June of 2009, Qingshuihai Company had allocated resettlement fund
for both Xundian and Songming County 157.8414million yuan(Xundian County
72.3056 million yuan,Songming County 85.5358million yuan),Among them, Rural
Resettlement fund 134.4284 million yuan(Xundian County 59.4566 million yuan,
Songming County 74.9718 million yuan),Compensation to enterprise 2.8331 million
yuan(Xundian County 2.8131 million yuan),Fund for specific facility rebuilding
1.00 million yuan(Xundian County 1.00 million yuan),Other Expenses 3.9824
million yuan(Xundian County 1.9324 million yuan,Songming County 2.05 million
yuan),Contingency 11.1075 million yuan(Xundian County 3.6935 million yuan),
External Capital of Project 0.12 million yuan(Xundian County 0.02 million yuan,
Songming County 0.1 million yuan).
By the end of June 2009, Qingshuihai Project had used resettlement fund for both
Xundian and Songming County 146.8384 million yuan(Xundian County 62.3862
million yuan,Songming County 84.4522 million yuan),among them, Rural
Resettlement fund 138.3880 million yuan(Xundian County 57.2721 million yuan,
Songming County 81.1159 million yuan),Compensation to enterprise 2.5733 million
yuan(Xundian County 2.5733 million yuan),Fund for specific facility rebuilding
1.6447 million yuan(Xundian County 0.4347 million yuan,Songming County 1.21
million yuan),Other Expenses 4.2325 million yuan(Xundian County 2.1062 million
yuan,Songming County 2.1263 million yuan),Fund for communication recovery of
reservoir 4.3476 million yuan(Xundian County 4.3476 million yuan)。
![Page 50: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/50.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
48
Table 6-1 Fund Appropriation of Resettlement Fund
0.00
5000.00
10000.00
15000.00
20000.00
Total 15784.14 14683.84 1100.30
Xundian County 7230.56 6238.62 991.94
Songming County 8553.58 8445.22 108.36
AllocationCapital
Capital Usage Remained
Figure 6-1 Usage of Fund(Xundian County, Songming County)
County Township Village Affected Population
Actual Amount (Up to 30th June 2009)
Wu 4 27.1 Tuoqi 12 86.3 Enjia 21 117.7 Liushao
Maanshan 8 52.8 Haiwei 197 542.3 Diansha Luliu 78 421.9 Xintian 0 110.5 Jinsuo 20 157.6 Jinsuo Zetie 271 442.5
Daliusuo 26 268 Duohe 6 38.7
Huangtupo 48 163 Sanyingzhuang 46 47.2
Tianqiaodi 50 89.9 Dianlong 0 55.7
Xundian
Yangjie
Dianxin 46 91.4 Shanjiao 0 0 Songyang Dong 17 41
Yangqiao Xishan 8 7.8 Zhouda 265 374.5
Songming
Dianyuan Laoba 141 622.8 Total 1264 3758.7
![Page 51: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/51.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
49
7 Relocation
Up to 30th June 2009, the accounting and compensation distribution for houses
and auxiliary facilities compensation of Haiwei Relocation Plot in Xundian County of
Kunming Qingshuihai Water Supply Project had not been completed, due to most of
affected villagers thought actual compensation standard was much lower than they
expected. However, affected villagers from Haitou Village involved in Qingshuihai
Reservoir had received the compensation for over 600mu acquired land, the
compensations of house and auxiliary facilities will distribute at the beginning of
building relocation houses. As for scatter resettlement 3 households from Huaqing
Village Group, 2 of which had accepted all compensations. 1 affected household in
Laohaitou Village Group had not relocated and accepted the compensation, but
another scattered affected in Xiaobeidang had removed to new relocation house and
obtained all of compensation for house demolishment. The situation of rebuilding
road from Qinghai Village to Haiwei Village had been investigated and checked by
Xundian County, the compensation had been generally distributed.
The resettlement of Ganchong and Renjiahou Relocation Plots in Laoba Village
had got the compensation gradually, and all of compensation can be distributed to
affected villagers with the closure of construction of houses, and specific facilities and
public infrastructure, can be funded according to actual construction progress.
7.1 Maichong Relocation Plot of Qinghai Village
According to
<Resettlement Plan>,
Qinghai Administrative
Village Maichong
resettlement plot will
relocate 50 villagers from
10 households in Qinghai
Village, the new plots are
planned to make a
requisition of dry land
![Page 52: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/52.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
50
7.36mu, the average area per capita is 98 m2, and there are totally 10 houses (1 A
Type, 3 B Type, 6 C Type) and 1 public room will be built.
Due to locate in runoff area, the location of Maichong Relocation Plot in Qinghai
Village had been re-selected by Resettlement Office in Xundian County. Currently,
the location had been fixed and by the coordination of Resettlement Office in Xundian
County, the formalities of timberland acquisition had been in progress. According to
planning, the construction of relocation plot will be triggered in September 2009.
7.2 Haiwei Relocation Plot
According to
<Resettlement Plan>,
the Haiwei
Relocation Plot was
planned to receive
104 villagers from 31
households in Haiwei
Village. The new
plots are planned to
make a requisition of
dry land 15.67mu, the average area per capita is 100 m2, and there are totally 31
houses (12 A Type, 15 B Type, 4 C Type) and 1 public room will be built.
The infrastructure of Haiwei Relocation Plot had stared at September 29th 2007,
and the roadbed had completed at October 25th 2007, followed with the completion of
ground flattering and shield wall at February 23 2008, the houses had been built from
15th August 2008. At present, the houses, roads, water supply facilities, power supply
and afforestation had completed in all. In order to provide proper living and
production circumstance, the construction of auxiliary houses are in preparation phase,
such as stable, firewood house, tobacco house.
![Page 53: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/53.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
51
7.3 Renjiahou Relocation Plot in Laoba Village
According to <Resettlement Plan>, the Renjiahou Relocation Plot in Laoba Village
of Songming County was planned to receive 363 villagers from 105 households in
Laoba Village. The new plots are planned to make a requisition of dry land 54.53mu,
the average area per capita is 100 m2, and there are totally 108 houses (33 A Type, 57
B Type, 18 C Type) and 1 public room will be built.
July 15th as the contract
beginning, the infrastructure
of Renjiahou Relocation
Plots in Laoba Village had
been completed and checked
in 24th March 2009, which
include ground flattering and
shield wall. By using the
housing plot in relocation
plot, affected households had begun to build new family since April 2009. Up to the
end of June of 2009, all of affected households of Renjiahou Relocation Plots had
involved in the construction of relocation plot, among them, the houses of 69
household had been completed (56 households with 3-floor building, 9 households
with 2-floor building, and 4 households with 1-floor building), the outside decoration
of 16 households had been close to end and inside decoration had been in progress,
another 10 households involved in outside decoration, the rest 9 household had taken
part in building house (6 households with 1 floor completion, 2 households with 2
floor completion, and 1 with the completion of foundation). For those problems, such
as fissure of wall and the backfill of foundation, Resettlement Office in Songming
County had carried out some measures and authorized monitoring unit and contractor
to resolve.
7.4 Ganchong Relocation Plot in Deshi
According to <Resettlement Plan>, the Ganchong Relocation Plot in Deshi
Village of Songming County was planned to receive 297 villagers from 77 households
in Laoba Village. The new plots are planned to make a requisition of dry land
![Page 54: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/54.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
52
43.69mu, the average area per capita is 98 m2, and there are totally 77 houses (14 A
Type, 42 B Type, 21 C Type) and 1 public room will be built.
May 27th 2008 as the
contract beginning, the
infrastructure of Ganchong
Relocation Plots in Laoba
Village had been completed
and checked in February
21st 2009, which include
ground flattering and shield
wall. By using the housing
plot in relocation plot,
affected households had begun to build new family since April 2009. Up to the end of
June of 2009, all of affected households of Ganchong Relocation Plots had involved
in the construction of relocation plot, among them, the houses of 47 household had
been completed (40 households with 3-floor building, 4 households with 2-floor
building, and 1 households with 1-floor building), the outside decoration of 15
households had been close to end and inside decoration had been in progress, another
9 households involved in outside decoration, the rest 5 households had taken part in
building house (2 households with 1 floor completion, 3 households with 2 floor
completion, and 1 had removed in new house).
7.5 Other Scattered Relocation
According to <Resettlement
Plan>, the sub-project in
Gegentang affected 35 villagers
from 12 households, 10 households
of which were affected by house
demolishment without land
acquisition, 2 households of which
were affected by permanent land
acquisition. For the former, cash
compensation and temporary
![Page 55: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/55.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
53
removal were the main way to resettlement, but permanent removal and cash
compensation were the measures for the latter. All of them were scattered resettlement
without united relocation plot.
Gegentang Scattered Resettlement: 2 of households affected by land acquisition
had generally completed the building of houses and will remove in this year. Another
10 households affected by temporary land acquisition will remove to former
residential after the completion of project construction.
Huaqing Scattered Resettlement: 3 of households affected by land acquisition
had generally completed the building of houses and 2 of them had removed into new
residential, another 1 will remove in this year.
Laohaitou Scattered Resettlement: 1 household affected by land acquisition had
relocated near the location of village committee without beginning of house building.
Xiaobeidang Scattered Resettlement: 1 household affected by land acquisition
had generally completed the building and decoration of houses, who will remove in
this year.
7.6 Rebuilding of Specific Units
Project Office of Qingshuihai Project had authorized Hydro-Electric Survey and
Design Institution of Yunnan Province to design the working drawing for rebuilding
of specific units involved in Qingshuihai Water Supply Project, which include
Primary School and Village Committee of Laoba Village. Currently, the design had
been completed, and the construction will start after professional check.
7.7 Recovery of Communication around Reservoir
Project Office of
Qingshuihai Project had
authorized Hydro-Electric
Survey and Design
Institution of Yunnan
Province to design the
working drawing for
recovery of road and
![Page 56: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/56.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
54
communication near reservoir involved in Qingshuihai Water Supply Project.
Currently, the design of rebuilt roads of Haiwei Village within inundated area had
been completed.
Hydro-Electric Survey and Design Institution of Yunnan Province had authorized
Sichuan Shuqiao Highway Survey and Design Company to draw up the working
drawing of rebuilt roads of Haiwei Village within inundated area, and which had
completed in February 2009. The rebuilt roads of Haiwei Village within inundated
area is throughout the southwestern part of Diansha Township of Xundian County,
with the beginning of junction near Qingshuihai vacation village in Diansha Township
and the end at Haiwei Village, the total mileage is 6.01039km. According to the work
drawing, the road is the rural 4-Grade road with double traffic lane and 20km/hour
permitted speed, 6.5m wide of roadbed and 6.0m wide of road surface. The main
work quantities are as follow: cubic meter of earth and stone 215500m3, cubic meter
of earth 142553 m3, cubic meter of stone 72947 m3, backfill 14747 m3, drainage
engineering 6326.55 m3, protection of roadbed 8334 m3, bridge and culvert
197.77m/13 culvert, stone slope wall 2921 m2.
In order to ensure the resettlement progress of Qingshuihai Water Supply Project,
Resettlement Office of Xundian County had prepared pre-phase tasks and coordinated
relevant departments positively; the construction makeshift road and the formalities of
land acquisition had been completed. As the basis, Resettlement Office of Xundian
County had held the bidding and selected contractor (Kunming Xishan Highway
Engineering Company) and monitoring unit (Yunnan Tuyuan Engineering Monitoring
Company) for the road rebuilding at March 28th 2009. May 2009 as the start, rebuilt
roads of Haiwei Village within inundated area is in the progress of cubic meter of
earth and stone.
7.8 Resolution of Transmission Line
According to the Resettlement Plan, the length of inundated transmission line
(10kV) is 1.4km, the recovery length is 2.5km, and the starting point and terminal
point is at Bailong valley and Haiwei Village respectively.
10th December 2007, Resettlement Office of Xundian County had signed contract
with Xundian County Qunyi Electric Facility Company for installation of electricity
supply facilities in Haiwei Village. After contracting, the line had been rebuilt and
![Page 57: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/57.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
55
mains transformers had been installed. 12th December 2007 as the beginning, the
entire work had been completed and brought into service in 20th December 2007.
7.9 Telecommunication and TV Cable
26th November 2007, Resettlement Office of Xundian County had signed contract
with Telecommunication Company of Xundian County for the line rebuilding and
recovery in Haiwei Village
(<Construction Cooperation
Agreement of Haiwei Relocation
Village in Diansha Township>). In
the program, 2km line from
P0261263 to P02612796 will be
built and former line from
P02612763 to P02612796 will be
demolished. Totally, 2km
telecommunication lines and 2km
telecommunication cable had been built by the coordination with Xundian County and
the whole work had gone into operation currently.
7.10 Water Conservancy Facilities
According to Resettlement Plan, main water conservancy facilities should be
rebuilt or improved of Qingshuihai Water Supply Project are the watering facilities in
relocation plots named Maichong, Haiwei, Renjiahou, Ganchong and Xintianhe.
(1) Watering facilities in relocation plots of Renjiahou and Ganchong
In the Resettlement Plan, there are 2 watering places in Renjiahou Relocation Plot.
The volume of principal watering place is 300m3, which is the water source of living
watering of Laoba Relocation Plot, irrigation of paddy fields at Huoshishan, and
living watering of Ganchong Relocation Plot. Another watering place is at Renjiahou
Relocation Plot with the volume of 100m3, which is the water source of living
watering of Renjiahou Relocation Plot and irrigation of paddy field in Huoshishan.
Currently, the principal watering place is in progress.
(2) Water Supply Facilities of Dagoumao Valley in Qinghai Village
![Page 58: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/58.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
56
According to Resettlement Plan, Dagoumao Valley Water Supply in Qinghai
Village had been planned to install small steel plate sand rushing dam at the water
source point, which with sluice gate of 1.5×1.5m as the area and length of 10m and
height of 2m. Then by the deposit pool near the water supply hole and pipe coded
DN100PE, the water will be diverted to Maichong Relocation Plot for the drinking
water and the sub-pipe network can provide drinking water for the administration
office of Qingshuihai and scattered households nearby. Currently, Xundian County
had organized relevant departments to implement the preparation for the construction
of Dagoumao Valley Water Supply Engineering.
(3) Water Supply Facilities of Haiwei Relocation Plot
According to Resettlement Plan, Water Supply Facilities in Haiwei Relocation Plot
had been planned to install steel plate dam at the water source point, which with the
sluice gate of 1.5×1.5m as the area, the length of 10m and height of 1.5m~2m, and
the sand deposit pool is with the length of 5.0m and width of 2.0m. Connected with
deposit pool, the water supply pipe will be buried and divert water to the water pool in
the relocation plot. Resettlement Office of Xundian County had triggered the
construction of this facility since August 2008, and which had been checked and put
into use.
8 Public Participation and Grievance Redress
According to the laws,
regulations and policies of
PRC, Yunnan Province and
ADB for land acquisition
and resettlement, in order to
safeguard the legal
entitlements of APs and
displaced units, as well as
minimize any complaints
and disputes, it is required
to further develop the relevant policies and implementation provisions for
resettlement, listen to the public opinions, prepare the resettlement plan and
![Page 59: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/59.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
57
practically attend to the implementation, thus to achieve the target of resettlement.
Public participation in the phases of preparation and implementation is of great
necessity.
During the first half in 2009, under the guidance of the PPTA consultants, KPMO,
KWSG and YDRI have organized a series of socio-economic survey and public
opinion consultation. The activities in this regard are detailed in Annex Ⅳ.
9 Rehabilitation Measures
External consulting expert team made an investigation on 21 affected villages
during January to June 2009. Economic rehabilitation plan includes adjustment plan
on industrial construction, reconstruction plan on hydropower and other infrastructure
facilities, the use plan on compensation for land acquisition, anticipated economic
benefit, etc. Part of affected villages have made respective economic rehabilitation
plan in accordance with the actual situation of respective village. Due to low level of
agriculture production technology, low production value for grains and corns before
land acquisition, in view of which the related authorities place more attention on
industrial construction adjustment in order to increase agriculture production value,
make up for the loss for lost land. The related measures have been taken as follows:
increase the planting areas for orchard, increase the cultivating area for economic
crops, develop the breeding industry and encourage surplus population to go out-
of-town and make a living.
In accordance with the incomplete statistics from related authorities, during
the period from January to June 2009, some track-survey villages have done actions
as the requirements of the industrial construction adjustment require, which can make
up with the losses from lost land by land acquisition. After land acquisition the
additional orchard area is 115 mu, resulting in increasing the production value with
92000 yuan RMB. 955 mu is added for economic crops planting, which increased
production value with 916800 yuan RMB. 1192 additional livestock are bred and
increased the production value with 655600 yuan RMB, if computed with the lowest
price 550 yuan RMB for each domestic animal. Outworkers far away from their
hometown is added to 216 persons and increased production value with 993600 yuan
![Page 60: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/60.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
58
RMB, if computed with average 4600 yuan RMB every half year for per person. The
total increased value for above-mentioned four items is 2658000 yuan RMB. Raised
income per year for each household is 195 yuan RMB. Details were showed in Annex
Ⅲ.
10 External Monitoring and Evaluation of Resettlement
Based on external monitoring and evaluation index system mentioned in baseline
report, by field inspection,
interview and investigation,
follow-up village survey
and sample household
survey, 10 objectives in 3
parts of project had been
evaluated quantitatively,
which showed in Table
10-1.
By scoring and
evaluating, the situation of
project implementation had
been valued 3.83 point, which is better than average. As the reasons, the progress of
land acquisition and demolishment had been affected by temporary removals,
relocation plot selection and other objective conditions, and some resettlements need
time to find reliable ways of relocation, the general progress of project had been
dragged.
With 3.68 point, the situation of resettlement had average evaluation.
Explanatorily, the economic and living conditions of resident involved in project had
not changed so much, which can basically keep the same with 2008. But Project
Office and relative departments should pay more attention on these issues in further
task.
By referring to relevant materials and field survey, it can be found that some risk
control measures and precaution schemes need improvement and establishment in
further. Facing 3.44 point rewarded to the situation of project risk, project office
![Page 61: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/61.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
59
should focus on laying down complete and comprehensive risk prevention and
warning program in order to ensure the implementation of the project.
General status of the project is marked 3.65 point, which demonstrated that there
are actually some problems in immature project operation and coordination at
starting phase, so each aspect should be enhanced by detecting problems
cooperatively.
![Page 62: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/62.jpg)
Table 10-1 External Monitoring and Evaluation Index System of Resettlement for Qingshuihai Project (January-June.2009)
ⅠProject Implementation Objective Criteria Basis of Evaluation Scoring grade Score
1.1 Implementation of preparation for land acquisition, demolition and resettlement 5.0
1.2 Progress of land acquisition and demolition 3.0 1.3 Construction progress of resettlement location 3.0
1.4 Progress of resettlement
Comparing with <RP>, actual progress matches plan: Qualified The difference between actual progress and plan is ±15%: Average The difference between actual progress and plan is ±30%: Unqualified 1.0
1 Project Progress
Evaluation of project progress Average marks of 1.1~1.4
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point 3.0
2.1 Quality of land acquisition and demolition 3.0
2.2 Quality of house and infrastructure in resettlement location
Constructive quality reaches the standard: Qualified Constructive quality basically reaches the standard: Average Construction with quality defects : Unqualified
5.0
2.3 Satisfaction of resettlement Most of villagers are satisfied: Qualified Part of villagers unsatisfied: Average Most of villagers are unsatisfied: Unqualified
3.0
2.4 Handling of relative quality problem Handling properly and timely: Qualified Handling properly but untimely: Average Handling improperly and untimely: Unqualified
3.0
2 Project Quality
Evaluation of project quality Average marks of 2.1~2.4
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point
3.5
3.1 Appropriation of Resettlement fund
Appropriation of resettlement fund on schedule: Qualified Appropriation of resettlement fund in quota but with delay: Average Appropriation of resettlement fund not on
schedule: Unqualified
5.0 3 Project Fund
3.2 Distribution of Resettlement compensation Distribution of resettlement compensation on schedule: Qualified Distribution of resettlement compensation in quota but with delay: Average Distribution of resettlement compensation not on
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point
5.0
![Page 63: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/63.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
61
schedule: Unqualified
3.3 Usage of Resettlement fund
Usage of resettlement fund on schedule: QualifiedUsage of resettlement fund with differences: Average Usage of resettlement fund not on schedule: Unqualified
5.0
Evaluation of project fund Average marks of 3.1~3.3 5.0 Evaluation of project implementation Average evaluation of 1~3 3.83
Ⅱ Situation of Resettlement and Rehabilitation Objective Criteria Basis of Evaluation Scoring grade Score
4.1 Productive materials and conditions 3.0 4.2 Living materials and conditions 3.0 4.3 Fixed assets owned by household 3.0 4.4 Economic Income 3.0 4.5 Expenditure
Comparing with Baseline, improved: Qualified unchanged: Average aggravated: Unqualified
3.0
4 Economic status of Resettlement
Evaluation of Economic status of Resettlement Average marks of 4.1~4.5
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point 3.0
5.1Traffic and communication conditions 3.0 5.2 Educational condition and enrolling 3.0 5.3 Health care 3.0 5.4 Infrastructure and public service
Comparing with Baseline, improved: Qualified unchanged: Average aggravated: Unqualified 3.0
5 Living condition of Resettlement
Evaluation of Living condition of Resettlement Average marks of 5.1~5.4
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point
3.0
6.1 Employment of family members 3.0 6.2 Education of family members 3.0
6.3 Marriage of family members
Comparing with Baseline, improved: Qualified unchanged: Average aggravated: Unqualified
3.0 6 Family status of Resettlement
Evaluation of Family status of Resettlement Average marks of 6.1~6.3
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point
3.0
7.1 Mechanism of grievance 5.0 7.2 Assistant tasks of relative government 5.0 7.3 Demand meeting 5.0 7.4 Response and feedback of villagers
Evaluating according to actual situation and the grade are: Qualified, Average, Unqualified
3.0
7 Rights Safeguard of Resettlement
Evaluation of Rights Safeguard of Resettlement Average marks of 7.1~7.4
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 4.0
![Page 64: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/64.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
62
point 8.1 Support of vulnerable groups 5.0 8.2 Extension of economic recovery measures 3.0 8.3 Stabilization of community life and culture 5.0 8.4 Life of minority 5.0 8.5 Poverty relief
Evaluating according to actual situation and the grade are: Qualified, Average, Unqualified
5.0
8 Social development of Resettlement community Evaluation of Social development of Resettlement
community Average marks of 8.1~8.5
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point 4.6
9.1 Afforestation of Resettlement place 3.0 9.2 Natural resources reservation of Resettlement place 5.0
9.3 Pollution prevention of Resettlement place 3.0 9.4 Soil and water conservation of Resettlement place
Evaluating according to reports and data provided by relative environmental protection departments and the grade are: Qualified, Average, Unqualified
5.0
9 Environmental protection of Resettlement place
Evaluation of Environmental protection of Resettlement place Average marks of 9.1~9.4 4.0
Evaluation of project resettlement Average evaluation of 4~9
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point
3.68 Ⅲ Project Risks
10.1 Project Risk of progress 1.0 10.2 Project Risk of quality 5.0 10.3 Project Risk of investment and fund 5.0 10.4 Project Risk of economic aggravation of resettlement 3.0
10.5 Project Risk of aggravation of living condition for resettlement 3.0
10.6 Project Risk of change of family of resettlement 3.0
10.7 Project Risk of right safeguard 3.0 10.8 Project Risk of social development 5.0 10.9 Project Risk of environmental protection
Evaluating according to actual situation and the grade are: Low possibility and with proper prevention measures: Qualified Medium possibility but with proper prevention measures: Average High possibility and without proper prevention measures: Unqualified
3.0
10 Project risks
Evaluation of project risk Average marks of 10.1~10.9
Qualified: 5.0 point Average: 3.0 point Unqualified: 1.0 point
3.44 General Evaluation of Project Average evaluation of 1~10 3.65
![Page 65: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/65.jpg)
11 Conclusion
11.1 Impact Degree Caused by Project
Up to June of 2009, the total area of permanent land acquisition of Songming
County was 2193.82mu, which involved 431 villagers from 5 villages.As for the
Xundian County, total area of permanent land acquisition was 3525.88mu, which
affected 833 villagers from 16 villages.
By the end of June 2009, there were 25 village groups of Xundian County and 15
village groups from Songming County had involved permanent land acquisition. Total
area of permanent acquired land was 5719.9 mu,account for 86.97% of total planned
area (6577.1 mu). And the acquired area of paddy field, dry land, garden, timberland,
unused land, building plots and fishpond is 1823.21mu, 1100.71mu, 4.52mu, 2182.19
mu, 466.44mu, 31.3mu and 111.53mu, which respectively account for 92%, 98.99%,
44.75%, 83.03%, 29.06% and 100% of plan. (Planned area of acquired paddy field,
dry land and fishpond is 1981.6mu, 1111.9mu, 10.1mu, 2628.1mu, 804.4mu, 9.9mu,
383.73mu, 31.3mu respectively)
Up to the end of June 2009, there were 134.18 mu paddy field, 721.46 mu dry
land and 750.26 mu timberland; total in 1605.9 mu had been temporary land
acquisition, which involved also involved 1264 villagers from 21 villages.
Up to 30th June 2009, including residential house and auxiliary houses,
2095.02m2 houses had been demolished, which is 10.47% by the area in
Resettlement Plan. (Planned area is 81917.5m2.) Among them, brick-concrete house
299.21 m2, brick-wood house 854.79m2, earth-wood house 941.02m2, which is
respectively 14.76%, 40.1%, 6.92% of the area in Plan. (Planned areas of
demolished house are: brick-concrete house 9185.9m2, brick-wood house 12822.2m2,
earth-wood house 34593.7 m2). The total area of house demolishment of Xundian
County was 1649.04m2, which affected 833 villagers from 16 villages. The area of
Songming County is 445.98 m2 with the progress of 0.91%.
Taking 30th June 2009 as the end, auxiliary facility demolishment involved 8
types, included 1 gate, 1 methane tank, 26.45 m3 pool, drying yard 1762.08 m², stone
barricade 2.51 m3 and enclosure(brick) 52.8m², 21 tomb and 7 cable TV, and the
![Page 66: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/66.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
64
progress is 1.61%, 8.33%, 7.64%, 3.04%, 0.08%, 5.19%, 28.38% and 68%
respectively. (According to Resettlement Plan, the demolished quantities of above
auxiliary facilities are: 62 gates, 12 methane tanks, 346 m3 pool, drying yard 40921.7
m², stone barricade 3315.9 m3 and enclosure (brick) 1017.2 m²,74 tombs and 190
cable TVs.
As for living standards, the general situation is basically equal with which in the
first half and baseline except the conditions of communication and employment.
11.2 Future Efforts Suggested
(1) Considering the completion of the timberland acquisition formalities of Maichong
Relocation Plot in Qinghai Village and in order to promote the building of houses and
removal, it is suggested that Resettlement Office of Xundian County should enhance
the performances on coordination and communication with relative departments for
the construction of relocation plot infrastructure and water supply facilities, which are
the necessary conditions to resettlement.
The resettlement houses and Qingshuihai Water Supply project are in the progress
currently, but there are some qualitative hidden perils of resettlement houses, which
built by affected households. So for the safety and the recovery of resettlement, it is
suggested that Resettlement Office of Songming County should authorize qualified
institution to monitor and check the quality of resettlement houses in order to ensure
the living safety of resettlement.
(2) At present, the houses, roads, water supply facilities, power supply network and
afforestation of Haiwei Relocation Plot had been completed, and the auxiliary houses
of households affected by demolishment are built. In order to accomplish the removal
as soon as possible, endure the safety of local people who affected by the Project and
recover living and production quickly, it is suggested that by coordinating the
department concerned, Xundian Government should make more effort to build
auxiliary houses and complete all of auxiliary facilities as soon as possible, which are
the basis of the removals and living recovery.
(3) Currently, the house engineering of Relocation Plot named Renjiahou of Laoba
Village is in the progress. According to the outcome of field survey, there are housing
plots of 3~4 households are backfilled, and the progress of one household had been
paused because of crack. In order to ensure the quality of relocation houses and safety
![Page 67: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/67.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
65
of resettlement, it is suggested that Resettlement Office and other connected
departments of Songming County should positively organize qualified institutions,
such as monitoring, designer of work drawing and Qingshuihai Company to analyze
the reasons and the resolutions of current problems, and then carry out effective
measures.
(4) According to the explanation of staff from Resettlement Office of Songming
County, Dianyuan Twonship, which administrated by Songming County formerly, had
been transferred to Panlong District of Kunming City since August 2008. In order to
reach the planned progress and complete construction of relocation plot qualitatively,
it is suggested that Kunming Municipal Government, Qingshuihai Company,
Government of Songming County, Resettlement Offices, Government of Panlong
District should decide and authorize the implementer of resettlement, fund
management and routine tasks for the progress of removal of resettlement from
Dianyuan Township.
![Page 68: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/68.jpg)
Annex Ⅰ Survey Matrix of the follow-up survey on affected villages along Qingshuihai Water Supply Project
Survey Matrix of the follow-up survey on affected villages (A)
Item Village Group(No.) Household(No.)
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±%
Qinghai 9 9 9 9 0.00 759 761 762 798 4.72
Xintian 10 10 10 10 0.00 974 974 978 978 0.00Jinsuo,Xundian
Zetie 11 11 11 11 0.00 1163 1172 1171 1171 0.00
Luliu 3 3 3 3 0.00 338 401 338 338 0.00Diansha,Xundian
Haiwei 15 15 15 15 0.00 635 640 639 641 0.31
Enjia 2 2 2 2 0.00 136 136 136 147 8.09
Wu 2 2 2 2 0.00 146 146 146 144 -1.37
Tuoqi 3 3 3 3 0.00 247 247 255 255 0.00Liushao,Xundian
Maanshan 2 2 2 2 0.00 141 145 145 421 190.34
Huangtupo 5 5 5 5 0.00 466 466 466 466 0.00
Sanyingzhuang 5 5 5 5 0.00 784 784 784 784 0.00
Daliusuo 2 2 2 2 0.00 712 712 712 713 0.14
Tianqiaodi 7 7 7 7 0.00 848 848 848 848 0.00
Dianxin 10 10 10 10 0.00 1291 1291 1290 1290 0.00
Yangjie,Xundian
Duohe 4 4 4 4 0.00 812 812 812 812 0.00
![Page 69: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/69.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
67
Dianlong 6 6 6 6 0.00 1207 1207 1207 1207 0.00
Laoba 4 4 4 4 0.00 436 436 437 437 0.00Dianyuan,Songming
Zhouda 5 5 5 5 0.00 402 403 408 473 15.93
Shanjiao 9 9 9 9 0.00 728 731 731 731 0.00Songyang,Songming
Dong 8 8 8 8 0.00 435 436 432 336 -22.22
Yangqiao,Songming Xishan 12 12 12 12 0.00 641 643 642 642 0.00
Total 134 134 134 134 0.00 13301 13391 13339 13632 2.20
Survey Matrix of the follow-up survey on affected villages (B)
Item Population(Person) Total Area of Land(mu)
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec2008 Jan.-June 2009 ±%
Qinghai 3012 3040 3048 2982 -2.17 21770 21770 21702.8 21635.6 -0.31 Xintian 4106 4108 4111 4118 0.17 36939 36939 36860.8 36779 -0.22 Jinsuo,Xundian
Zetie 4929 4949 4952 4963 0.22 37575 37575 37458.8 37342.6 -0.31 Luliu 1233 1279 1283 1280 -0.23 1726 1726 1638.2 1550.4 -5.36 Diansha,Xundian
Haiwei 2357 2368 2379 2370 -0.38 45002.5 44726.2 44274.1 43822 -1.02 Enjia 474 474 476 515 8.19 5012.9 3974 3591.3 3208.6 -10.66 Wu 609 609 611 838 37.15 7308 7308 7167.5 7027 -1.96
Tuoqi 894 894 897 1350 50.50 9167 9167 9013.6 8890.2 -1.37 Liushao,Xundian
Maanshan 508 510 514 583 13.42 4041 4036 3267.6 2499.2 -23.52 Yangjie,Xundian Huangtupo 1984 2006 2010 1970 -1.99 4255.3 4255.3 3951.5 3647.7 -7.69
![Page 70: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/70.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
68
Sanyingzhuang 3013 3018 3022 3055 1.09 5411.5 5411.5 5305.8
5200.1 -1.99 Daliusuo 2501 2501 2503 2527 0.96 8122 8122 7937.4 7752.8 -2.33
Tianqiaodi 3197 3200 3205 3255 1.56 2269.8 2272.2 2140.1 2007.9 -6.18 Dianxin 4987 4989 4993 4987 -0.12 7435.32 7435.32 7280.02 7079.92 -2.75 Duohe 3062 3064 3066 3095 0.95 11323.8 11323.8 11255.9 11188 -0.60
Dianlong 4718 4720 4726 4718 -0.17 8798.3 8798.3 8673.3 8548.2 -1.44 Laoba 1545 1555 1561 1576 0.96 24870 24695 24535.6 24535.6 -0.00 Dianyuan,Songming
Zhouda 1593 1596 1599 1633 1.43 23714 23714 23507.2 23457.7 -0.21 Shanjiao 2982 2998 3003 3018 0.50 3570 3536 3453.8 3410.1 -1.27 Songyang,Songming
Dong 1865 1867 1880 1416 -24.68 29411 29411 28742.9 28334.6 -1.42
Yangqiao,Songming Xishan 2213 2217 2220 2237 0.77 49306 49306 48740.7
48444.7 -0.61 Total 51782 51962 52059 52486 0.82 347028 345501 340498.9 336361.92 -1.21
Survey Matrix of the follow-up survey on affected villages (C)
Item Average Farm Land Area Per Capita (mu) Output of Grain(ton)
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±%
Qinghai 0.32 0.32 0.32 0.32 -0.31 1469.5 890 881.7 910 3.21 Xintian 1.52 1.52 1.51 1.51 -0.22 1430 730 858 745 -13.17 Jinsuo,Xundian
Zetie 0.75 0.75 0.75 0.75 -0.31 1302 750 781.2 760 -2.71 Luliu 1.4 1.3 1.29 1.22 -5.36 493.2 246.2 295.92 237 -19.91 Diansha,Xundian
Haiwei 1.48 1.38 1.32 1.31 -1.02 1165 736 699 724 3.58
![Page 71: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/71.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
69
Enjia 4.98 3.4 2.86 2.56 -10.66 60 46 36 47.5 31.94 Wu 2.37 2.37 2.37 2.32 -1.96 315 200 189 115 -39.15
Tuoqi 2.57 2.57 2.55 2.52 -1.37 52 52 31.2 53 69.87 Lishao,Xundian
Maanshan 1.49 1.47 0.52 0.40 -23.52 265 165 159 173 8.81 Huangtupo 0.58 0.64 0.63 0.58 -7.69 95 48 57 81 42.11
Sanyingzhuang 0.78 0.78 0.78 0.76 -1.99
963.5 310 578.1 931 61.04
Daliusuo 1.19 1.18 1.16 1.13 -2.33 314 167 188.4 155 -17.73 Tianqiaodi 0.65 0.6 0.59 0.55 -6.18 895.4 228 537.24 252 -53.09
Dianxin 0.64 0.64 0.64 0.62 -2.75 125 65 75 60 -20.00 Duohe 1.26 1.17 1.17 1.16 -0.60 1394.2 695 836.52 707 -15.48
Yangjie,Xundian
Dianlong 0.74 0.74 0.74 0.73 -1.44 1524.5 762 914.7 759 -17.02 Laoba 1.32 1.19 1.19 1.19 0.00 610.5 200 366.3 246 -32.84 Dianyuan,Songming
Zhouda 1.03 1.028 1.03 1.03 -0.21 240 128 144 160 11.11 Shanjiao 1.18 1.179 1.18 1.17 -1.27 1728 539 1036.8 515 -50.33 Songyang,Songming
Dong 0.46 0.46 0.41 0.40 -1.42 34 18 20.4 20 -1.96
Yangqiao,Songming Xishan 0.91 0.904 0.90 0.89 -0.61
897 538 538.2 504 -6.35
Total 1.33 1.22 1.22 1.10 -9.75 732.04 357.77 439.22 388.31 -2.77
Survey Matrix of the follow-up survey on affected villages (D)
Item Output Value of Grain per mu(yuan) Output Value of Economic Crop per mu(yuan)
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±%
Jinsuo,Xundian Qinghai 866 870 909.3 947 4.19 -- -- --
![Page 72: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/72.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
70
Xintian 900 900 945 980 3.71 1000 1000 900 987 9.67 Zetie 915 905 960.75 986 2.58 1794 1680 1614.6 1658.16 2.70 Luliu 665 1161 698.25 1264 81.07 1778 2028 1600.2 2001.636 25.09 Diansha,Xundian
Haiwei 1200 730 1260 795 -36.91 1500 960 1350 947.52 -29.81 Enjia 500 560 525 610 16.16 400 500 360 493.5 37.08 Wu 1350 1350 1417.5 1470 3.71 1580 1580 1422 1559.46 9.67
Tuoqi 850 685 892.5 746 -16.42 685 800 616.5 789.6 28.08 Lishao,Xundian
Maanshan 1500 1500 1575 1634 3.71 1100 1100 990 1085.7 9.67 Huangtupo 850 850 892.5 926 3.71 1100 960 990 947.52 -4.29
Sanyingzhuang 860 460 903 501 -44.52
970 470 873 463.89 -46.86
Daliusuo 850 600 892.5 653 -26.79 2000 1000 1800 987 -45.17 Tianqiaodi 700 700 735 762 3.71 1500 1500 1350 1480.5 9.67
Dianxin 800 800 840 871 3.71 750 750 675 740.25 9.67 Duohe 820 820 861 893 3.71 1500 1500 1350 1480.5 9.67
Yangjie,Xundian
Dianlong 780 780 819 849 3.71 -- -- -- Laoba 1500 1600 1575 1742 10.63 2200 2500 1980 2467.5 24.62 Dianyuan,Songming
Zhouda 650 540 682.5 588 -13.84 1400 1600 1260 1579.2 25.33 Shanjiao 1860 1860 1953 2026 3.71 6100 6100 5490 6020.7 9.67 Songyang,Songming
Dong 600 600 630 653 3.71 1275 1250 1147.5 1233.75 7.52
Yangqiao,Songming Xishan 775 770 813.75 839 3.05
1200 1200 1080 1184.4 9.67
Total 942.43 906.71 989.55 987 -0.22 1570.11 1498.84 1413.09 1338.47 -5.28
![Page 73: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/73.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
71
Survey Matrix of the follow-up survey on affected villages(E)
Item Output Value of Orchard per mu(yuan) Economic Income(Ten Thousands)1
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±%
Qinghai -- -- -- -- 692.3 451.7 479.76 468.86 -2.27 Xintian 1250 1200 1347.50 1206 -10.5 381.5 211.5 264.38 219.54 -16.96
Jinsuo, Xundian
Zetie 1453 850 1566.33 854 -45.46 1140 490 790.02 508.62 -35.62 Luliu -- -- -- 0 -- 114.8 74.07 79.56 76.88 -3.36 Diansha,Xundian
Haiwei 500 2500 539.00 2512 366.14 663.7 168 459.94 174.38 -62.09 Enjia 1000 800 1078.00 804 -25.42 34 25 23.56 25.95 10.14 Wu -- -- -- 0 -- 96.3 55.5 66.74 57.61 -13.68
Tuoqi -- -- -- 0 -- 71.8 61 49.76 63.32 27.25 Liushao,Xundian
Maanshan 1000 1000 1078.00 1005 -6.77 69.8 34.9 48.37 36.23 -25.11 Huangtupo 1000 1300 1078.00 1307 21.2 383 198 265.42 205.52 -22.57
Sanyingzhuang -- -- -- 0 -- 717 450 496.88 467.10 -5.99 Daliusuo 2000 -- -- 0 -- 974 845 674.98 877.11 29.95
Tianqiaodi -- -- -- 0 -- 1203 510.9 833.68 530.31 -36.39 Dianxin 1300 3000 1401.40 3015 115.14 2864 1604 1984.75 1664.95 -16.11 Duohe 1000 1000 1078.00 1007 -6.56 956 478 662.51 496.16 -25.11
Yangjie,Xundian
Dianlong -- -- -- 0 -- 649 324.5 449.76 336.83 -25.11 Laoba 500 500 539.00 505 -6.24 658 380 455.99 394.44 -13.50 Dianyuan,Songming
Zhouda 1100 1100 1185.80 1117 -5.77 1249 685 865.56 711.03 -17.85 Shanjiao 3200 3200 3449.60 3216 -6.77 6822 3545 4727.65 3679.71 -22.17 Songyang,Songming
Dong 10000 10000 10780.00 10111 -6.21 298.5 160 206.86 166.08 -19.71
![Page 74: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/74.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
72
Yangqiao,Songming Xishan 2100 2100 2263.80 2130 -5.89 2180 1610 1510.74 1671.18 10.62 Total 1957.36 2196.15 2110.03 1440 -5.89 1057.99 588.67 733.19 611.04 -16.66
Survey Matrix of the follow-up survey on affected villages(F)
Item Output of Labor Force(Ten Thousands)1 Average Area of Housing per capita(m2)
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec.2008 Jan.-June 2009 ±%
Qinghai 14 11 8.32 8.558 2.86 29 29 29 29 0.00 Xintian 15 8 8.92 6.224 -30.22 14 14 14 14 0.00
Jinsuo, Xundian
Zetie 50 30 29.72 23.34 -21.47 30 30 30 30 0.00 Luliu -- -- -- 0 0.00 10.7 10.34 10.34 10.34 0.00 Diansha,Xundian
Haiwei 9.7 6 5.77 4.668 -19.10 18 18 18 18 0.00 Enjia -- -- -- 0 0.00 15 15 15 15 0.00 Wu 5 2 2.97 1.556 -47.61 40 40 40 40 0.00
Tuoqi 4 3 2.38 2.334 -1.93 35 35 35 35 0.00 Liushao,Xundian
Maanshan 8 5 4.76 3.89 -18.28 30 30 30 30 0.00 Huangtupo 150 70 89.17 54.46 -38.93 20 20 20 20 0.00
Sanyingzhuang 126 66 74.90 51.348 -31.44 20 20 20 20 0.00
Daliusuo 46 23 27.34 17.894 -34.55 20 20 20 20 0.00 Tianqiaodi 66 30 39.23 23.34 -40.50 25 25 25 25 32.00
Dianxin 120 60 71.33 46.68 -34.56 25 25 25 25 0.00 Duohe 30.9 15.5 18.37 12.059 -34.35 20 20 20 20 0.00
Yangjie,Xundian
Dianlong 168 80 99.87 62.24 -37.68 20 20 20 20 0.00
![Page 75: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/75.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
73
Laoba 30 20 17.83 15.56 -12.73 68.5 68 68 68 0.00 Dianyuan,Songming
Zhouda 49 27 29.13 21.006 -27.89 23.5 21.6 21.5 21.5 0.00 Shanjiao 163 92 96.89 71.576 -26.13 28 27.8 27.7 27.7 0.00 Songyang,Songming
Dong 5 4 2.97 3.112 4.78 18.6 18.5 18.5 18.5 0.00
Yangqiao,Songming Xishan 519 350 308.51 272.3 -11.74 40.9 40 40 40 0.00
Total 83.08 47.50 49.39 33.44 -32.30 26.25 26.44 26.44 26.44 0.00
Survey Matrix of the follow-up survey on affected villages(G)
Item Class(No.) Shop(No.)
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009 ±%
Qinghai 10 10 10 10 0.00 11 11 11 11 0.00 Xintian 15 15 15 15 0.00 11 11 11 11 0.00 Jinsuo,Xundian
Zetie 14 14 14 14 0.00 25 25 25 25 0.00 Luliu 3 3 3 3 0.00 3 3 3 3 0.00 Diansha,Xundian
Haiwei 6 6 6 6 0.00 12 7 7 7 0.00 Enjia 4 4 4 4 0.00 5 5 5 5 0.00 Wu 2 2 2 2 0.00 3 3 3 3 0.00
Tuoqi 5 5 5 5 0.00 2 2 2 2 0.00 Liushao,Xundian
Maanshan 3 3 3 3 0.00 3 3 3 3 0.00 Huangtupo 8 8 8 8 0.00 9 9 9 9 0.00
Sanyingzhuang 11 11 11 11 0.00 10 10 10 10 0.00
Yangjie,Xundian
Daliusuo 8 8 8 8 0.00 6 6 6 6 0.00
![Page 76: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/76.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
74
Tianqiaodi 12 12 12 12 0.00 8 8 8 8 0.00 Dianxin 21 21 21 21 0.00 9 9 9 9 0.00 Duohe 10 10 10 10 0.00 8 8 8 8 0.00
Dianlong 15 15 15 15 0.00 8 8 8 8 0.00 Laoba 7 7 7 7 0.00 7 7 7 7 0.00 Dianyuan,Songming
Zhouda 7 7 7 7 0.00 3 3 3 3 0.00 Shanjiao 8 8 8 8 0.00 12 12 12 12 0.00 Songyang,Songming
Dong 7 7 7 7 0.00 3 3 3 3 0.00
Yangqiao,Songming Xishan 7 7 7 7 0.00 11 11 11 11 0.00
Total 183 183 183 183 0.00 169 164 164 164 0.00
Survey Matrix of the follow-up survey on affected villages(H)
Item Clinic(No.) Household equipped telephone(Household)
Township, County Administrative Village Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009 ±% Baseline Jan.-June 2008 July-Dec. 2008 Jan.-June 2009 ±%
Qinghai 3 3 3 3 0.00 260 265 273 280 2.70 Xintian 4 4 4 4 0.00 230 230 234 243 3.99 Jinsuo,Xundian
Zetie 4 4 4 4 0.00 1050 1100 1108 1164 5.04 Luliu 1 1 1 1 0.00 4 4 4 4 5.80 Diansha,Xundian
Haiwei 2 2 2 2 0.00 234 255 257 270 4.98 Enjia 1 1 1 1 0.00 103 113 118 120 1.32 Wu -- -- 136 140 142 148 4.31
Liushao,Xundian
Tuoqi 1 1 1 1 0.00 103 103 105 109 3.78
![Page 77: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/77.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
75
Maanshan 1 1 1 1 0.00 30 35 36 37 2.86 Huangtupo 1 1 1 1 0.00 370 390 397 413 3.93
Sanyingzhuang 1 1 1 1 0.00 460 460 464 487 4.89 Daliusuo 1 1 1 1 0.00 400 400 402 423 5.27
Tianqiaodi 1 1 1 1 0.00 650 655 657 693 5.48 Dianxin 1 1 1 1 0.00 615 615 620 651 4.95 Duohe 1 1 1 1 0.00 300 300 308 317 3.05
Yangjie,Xundian
Dianlong 1 1 1 1 0.00 460 460 467 487 4.21 Laoba 1 1 1 1 0.00 407 407 412 431 4.52 Dianyuan,Songming
Zhouda 3 3 3 3 0.00 268 270 279 286 2.39 Shanjiao 1 1 1 1 0.00 868 876 882 927 5.08 Songyang,Songming
Dong 1 1 1 1 0.00 400 400 403 423 5.01
Yangqiao,Songming Xishan 1 1 1 1 0.00 586 586 589 620 5.26 Total 31 31 31 31 0.00 7934 8064 8157 8532 4.59
Survey Matrix of the follow-up survey on affected villages(I)
Item Average Net Income per capita(yuan) Permanent Acquired Land
(Up to June.30th 2009) House Demolishment (Up to June.30th 2009)
Affected Population (Up to June.30th 2009)
Township, County Administrative
Village Baseline Jan.-June
2008 July-Dec.2008Jan.-June
2009 ±% Area
(mu) Compensation(yuan)
Area(m2)
Compensation(yuan) Household Population
Qinghai 1379 1000 1034.25 1058.30 2.33 67.2 27.1 0 0 1 4
Xintian 748 683 486.2 722.82 48.67 81.8 86.3 0 0 3 12
Jinsuo, Xundian Zetie 1478 800 960.7 846.64 -11.87 116.2 117.7 0 0 5 21
![Page 78: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/78.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
76
Luliu 847 460 550.55 486.82 -11.58 87.8 52.8 0 0 2 8
Diansha, Xundian Haiwei 1005 580 653.25 613.81 -6.04 452.1 267.3 2340.4 275 49 197
Enjia 800 405 520 428.61 -17.57 382.7 421.9 0 0 20 78
Wu 780 430 507 455.07 -10.24 140.5 110.5 0 0 0 0
Tuoqi 750 480 487.5 507.98 4.20 123.4 157.6 0 0 5 20
Liushao, Xundian Maanshan 913 540 593.45 571.48 -3.70 768.4 442.5 0 0 68 271
Huangtupo 1683.5 845 1094.275 894.26 -18.28 303.8 268 0 0 7 26
Sanyingzhuang 1749.1 849.1 1136.915 898.60 -20.96 105.7 38.7 0 0 2 6
Daliusuo 2363 1182 1535.95 1250.91 -18.56 184.6 163 0 0 12 48
Tianqiaodi 1576.5 789 1024.725 835.00 -18.52 132.2 47.2 0 0 12 46
Dianxin 1638.3 820 1064.895 867.81 -18.51 200.1 89.9 0 0 13 50
Duohe 2136 1069 1388.4 1131.32 -18.52 67.9 55.7 0 0 0 0
Yangjie,Xundian Dianlong 1780.4 830 1157.26 878.39 -24.10 125.1 91.4 0 0 12 46
laoba 2123 1114.5 1379.95 1179.48 -14.53 0 0 0 0 0 0
Dianyuan,Songming Zhouda 2266.6 1089.5 1473.29 1153.02 -21.74 49.5 41 0 0 4 17
Shanjiao 2787 1460 1811.55 1545.12 -14.71 43.7 7.8 0 0 2 8
Songyang,Songming Dong 2600 1400 1690 1481.62 -12.33 408.3 374.5 0 0 66 265
Yangqiao,Songming Xishan 2816 1570 1830.4 1661.53 -9.23 296 622.8 0 0 35 141
Total 1629.50 876.00 1065.74 927.08 -10.28 5719.9 3758.7 2340.4 275 316 1264
![Page 79: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/79.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
77
Annex Ⅱ Survey Matrix of the household-survey on affected villages along Qingshuihai Water Supply Project
Survey Matrix of the household-survey(A)—— Family Members Survey Duration Jan.-June 2009 Township,County Diansha,Xundian Jinsuo,Xundian Dianyuan,Songming
Administrative VillageTotal
Haiwei Qinghai Xintian Laoba
Village Group Baseline Jan.-June 2008 July-Dec.2008
Jan.-June 2009
Haiwei No.2
Haiwei No.3
Haiwei No.4
Haiwei No.5
Haiwei No.6
Qinghai No.1
Qinghai No.2 Laohaitou Huaqing Laoba Deshi
1. For all Family Members in Sample Household a. Household(No.) 289 289 287 287 8 9 9 22 10 11 18 3 12 105 80
b. Population 1109 1103 1069 1057 32 31 39 70 36 52 77 10 46 353 311 c.Ratio(%) 100 100 100 100 2.90 3.37 3.84 6.17 3.37 4.96 6.55 0.94 5.80 34.24 27.88
d. Sex role Male (Person) 566 564 552 542 19 17 17 39 20 27 38 9 33 187 146
Female (Person) 543 539 517 515 12 19 24 27 16 26 32 5 29 179 148 e. Age distribution
0-15 Years (Person) 243 239 236 231 3 7 8 24 13 10 9 4 18 73 67 Over 16 year (Person) 866 864 833 826 28 29 33 42 23 43 61 6 44 293 231
f. Nationality Han Nationality
(Person) 1102 1092 1063 1051 31 36 41 61 38 51 70 10 60 366 298
Ethnic minority (Person) 7 11 6 6 0 0 0 2 0 2 0 0 2 0 0
2.For 16 & above 16 years old a. Education level
Illiterate (Person) 16 21 18 18 1 1 2 0 8 1 3 0 0 1 1 Primary school
(Person) 439 439 420 404 8 18 8 15 9 26 28 4 38 146 120
Junior secondary school(Person) 297 292 279 275 14 9 11 19 6 15 27 2 4 92 80
Senior secondary school 93 92 92 103 1 0 6 7 0 1 2 0 2 46 27
![Page 80: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/80.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
78
(Person) Junior college or above
(Person) 21 20 21 26 4 1 6 1 0 0 1 0 0 5 3
Total (Illiterate Excluding)(Person) 850 843 812 808 27 28 31 42 15 42 58 6 44 289 230
b. Marital status Unmarried(Person) 157 153 149 151 7 5 6 6 0 14 22 0 5 43 41
With spouse(Person) 652 651 628 594 20 22 25 34 22 24 36 6 36 225 170 Divorced(Person) 7 8 10 46 0 0 1 1 0 1 2 0 0 5 0
Spouse died(Person) 47 48 47 33 1 2 1 1 1 4 1 0 3 13 20 Others(Person) 3 4 4 2 0 0 0 0 0 0 0 0 0 4 0 Total (Person) 866 864 833 826 28 29 33 42 23 43 61 6 44 290 231
c. Employment status 不在业人口(人) 159 153 156 196 7 8 9 8 4 6 8 0 2 50 51
在业人口(人) 707 711 677 630 21 21 24 34 19 37 53 6 42 240 180
小计(人) 866 864 833 826 28 29 33 42 23 43 61 6 44 290 231 d. Occupation Distribution for Employed
Worker(Person) 19 18 18 3 0 0 1 0 0 0 0 0 0 14 3 Laborer in agriculture,
forestry, animal husbandry and fishery(Person)
646 646 612 545 21 21 19 30 18 35 53 6 40 197 172
Business personnel(Person) 28 30 30 52 0 0 0 2 0 0 0 0 2 25 1
Person of culture, education or health
care(Person) 4 6 6 8 0 0 1 1 0 2 0 0 0 2 0
Person in organ or public
institution(Person) 3 3 3 6 0 0 3 0 0 0 0 0 0 0 0
Others(Person) 7 8 8 16 0 0 0 1 1 0 0 0 0 2 4 Total(Person) 707 711 677 630 21 21 24 34 19 37 53 6 42 240 180
e. Unemployment Undergraduate(Person) 83 78 78 89 6 5 4 3 0 3 6 0 2 21 28 House keeper(Person) 9 10 10 11 0 2 0 2 0 3 0 0 0 1 2
Idler (Person) 1 1 1 23 0 0 0 0 0 0 0 0 0 0 1 Retiree(Person) 3 3 3 4 0 0 2 0 0 0 0 0 0 0 1
![Page 81: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/81.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
79
Forfeit ability of labor(Person) 60 59 59 59 1 1 3 3 4 0 2 0 0 26 19
Others(Person) 3 2 5 10 0 0 0 0 0 0 0 0 0 5 0 Total(Person) 159 153 156 196 7 8 9 8 4 6 8 0 2 50 51
Survey Matrix of the household-survey(B)—— Household Property and Residential Conditions
Survey Duration Jan.-June 2009
Township,County Diansha Xundian Jinsuo Xundian Dianyuan
Songming
Administrative Villag
Total
Haiwei Qinghai Xintian Laoba
Village Group BaselineJan.-June
2008 July-Dec.2008 Jan.-June 2009
Haiwei
No.2
Haiwei
No.3
Haiwei
No.4
Haiwei
No.5
Haiwei
No.6
Qinghai
No.1
Qinghai
No.2 Laohaitou Huaqing Laoba Deshi
a. Household(No.) 289 289 287 287 8 9 9 22 10 11 18 3 12 105 80
b. Population(No.) 1109 1103 1069 1057 31 36 41 66 36 53 70 10 62 366 298
c.Ratio(%) 100 100 100 100 2.90 3.37 3.84 6.17 3.37 4.96 6.55 0.94 5.80 34.24 27.88 1. Household Property
Color TV(set) 269 269 272 274 8 7 9 22 6 10 17 3 12 99 79
Black-and-white
TV(set) 17 18 14 10 0 0 0 2 0 0 0 0 1 4 7
DVD(set) 191 192 201 189 4 0 3 20 5 5 0 0 11 90 63
Refrigerator(set) 43 45 40 32 0 0 1 5 0 1 2 0 2 17 12
Washing
Machine(set) 214 215 202 198 3 2 9 19 7 9 13 2 5 58 75
Computer(set) 9 8 5 818 0 1 0 0 0 0 0 0 0 4 0
Microwaver(set) 104 104 107 52 0 0 1 17 2 0 7 2 5 67 6
Water Heater(set) 81 84 77 70 0 0 4 17 3 1 7 0 5 26 14
![Page 82: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/82.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
80
Air Condition(set) 3 3 4 4 0 0 0 1 0 0 0 0 2 1 0
Water
dispenser(set) 127 128 131 103 0 0 4 4 0 0 2 1 4 59 57
Electric cooker(set) 390 393 393 309 8 8 11 40 11 12 18 3 15 186 81
Fixed phone(set) 121 120 120 184 4 1 2 2 7 0 10 0 6 39 49
Mobile phone(set) 364 368 377 297 9 6 15 34 10 10 8 2 11 192 80
Motorcycle(set) 87 87 95 96 0 0 2 8 3 5 8 2 10 29 28
Auto(set) 32 33 30 44 0 0 2 3 0 2 2 0 0 13 8
Bicycle(set) 40 42 45 7 0 0 1 0 0 1 1 1 2 7 32
Electric Fan(set) 64 61 59 52 0 0 1 4 0 0 8 2 9 31 4
Furniture(set) 393 398 386 563 5 5 9 53 19 9 10 2 41 157 76
Sewing
machine(set) 127 127 127 682 0 0 3 6 4 3 7 0 3 56 45
Livestock(set) 1289 1285 1286 929 19 44 87 148 151 16 27 5 192 297 300
Tractor(set) 3 4 6 2007 0 0 0 0 0 0 0 1 1 2 2
Thresher(set) 124 126 122 28 0 0 0 3 0 1 2 0 6 49 61
Trailer(set) 249 248 239 208 10 7 10 33 13 8 13 1 12 60 72
Water pump(set) 101 101 101 1511 0 0 1 1 0 0 0 0 1 55 43
Mechanical grain
grinding mill(set) 20 20 21 14 0 0 0 8 0 0 1 1 4 5 2
Other production
machines(set) 14 16 17 7 0 1 0 0 0 0 0 1 6 7 2
Living
Materials(set) 2676 2695 2685 3697 41 30 77 257 77 68 120 20 144 1135 716
Production Materials(set)
1786 1784 1775 1833 29 51 98 193 164 25 43 8 216 468 480
2. Residential Conditions
![Page 83: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/83.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
81
Domestic Water
1)Tap Water(%) 94.12 94.12 93.73 89.20 100.00 77.78 100.00 100.00 100.00 81.82 88.89 100.00 8.33 100.00 100.00
2)Well Water(%) 1.38 1.38 1.39 6.62 0.00 11.11 0.00 0.00 0.00 18.18 5.56 0.00 0.00 0.00 0.00
3) Water from river
and pond(%) 4.50 4.50 4.88 4.18 0.00 11.11 0.00 0.00 0.00 0.00 5.56 0.00 91.67 0.00 0.00
Power Supply 1) Ensured(%) 98.62 98.27 93.38 94.08 100.00 66.67 100.00 95.45 90.00 100.00 100.00 100.00 100.00 100.00 100.00
2) Have but not
ensured (%) 1.04 1.38 6.27 5.57 0.00 33.33 0.00 4.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3) Have not(%) 0.35 0.35 0.35 0.35 0.00 0.00 0.00 0.00 10.00 0.00 0.00 0.00 0.00 0.00 0.00 Housing Type
Bungalow(%) 36.00 13.15 13.55 13.78 12.50 44.44 55.56 13.64 50.00 54.55 16.67 100.00 58.33 0.95 0.00
Storey Building
(%) 64.00 86.85 86.45 86.22 87.50 55.56 44.44 86.36 50.00 45.45 83.33 0.00 41.67 99.05 100.00
Brick-concrete
Area(m2) 208.89 192.05 195.13 196.1 8.75 42.06 20.00 7.27 0.00 51.82 34.44 59.33 89.17 62.16 56.71
Age(year) 2 2.3 2.3 2.3 0.63 1.33 2.22 0.14 0.00 4.27 2.28 5.00 5.00 2.09 2.39
Brick-wood
Area(m2) 190.43 160.69 162.45 165.2 17.50 0.00 85.11 96.82 164.20 32.73 27.34 0.00 120.67 30.29 7.41
Age(year) 4.35 4.38 4.38 4.38 2.88 0.00 5.00 7.41 11.80 3.00 3.28 0.00 13.00 1.39 0.39
Frame-concrete
Area(m2) 204.52 118.57 118.57 118.6 0.00 0.00 0.00 0.00 38.00 0.00 21.11 0.00 26.67 3.81 2.20
Age(year) 2.1 2.2 2.2 2.2 0.00 0.00 0.00 0.00 3.90 0.00 3.94 0.00 7.42 0.10 0.18
Earth-wood
Area(m2) 224.23 250.62 249.8 277.6 65.00 89.22 66.67 25.45 49.30 24.55 114.97 26.67 93.50 324.46 128.54
Age(year) 13.9 14.8 14.8 14.8 18.50 23.89 11.78 4.59 13.00 5.27 15.22 13.33 30.75 14.68 11.76 Communication Conditions
![Page 84: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/84.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
82
1)To bus station
Distance(km) 4.26 4.26 6.08 8.45 30 2.3 3.74 7.00 1.69 0.75 4.44 0.93 5.00 5.00 1.00 Way of
Communication
1)On foot(%) 16.96 16.95 42.16 25 0.00 100.00 55.56 0.00 80.00 100.00 11.11 66.67 100 0.00 0.00
2)By bus(%) 83.04 83.05 57.84 72 100.00 0.00 44.44 100.00 20.00 0.00 88.89 33.33 0.00 100.00 100.00
3)By bicycle(%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4)Other(%) 0.00 0.00 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Spent Time(min) 21.3 20.7 28.15 29.02 56.00 36.6 12.11 15.68 6.80 13.63 23.61 48.33 60.00 30.00 5.00 2)To the Location
of County Government
Distance(km) 17.03 16.98 19.97 19.91 30.00 27.00 31.11 29.27 31.00 12.00 18.67 17.33 35.00 17.71 5.00 Way of
Communication
1)On foot(%) 0.00 0.00 0.00 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2)By bus(%) 100.00 98.99 99.65 94 100.00 88.89 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
3)By bicycle(%) 0.00 0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4)Other(%) 1.01 0.00 2 0.00 11.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Spent Time(min) 53.5 53.65 39.05 44.04 56.00 66.67 106.67 41.36 56.00 60.00 60.00 60.00 180.00 59.43 20.00 3)To Towns
Distance(km) 7.16 7.96 7.14 7.19 8.00 8.67 7.67 7.00 7.00 12.00 12.00 12.00 25.00 5.2 5.00 Way of
Communication
1)On foot(%) 0.00 0.00 25.78 10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2)By bus(%) 100.00 98.99 73.52 86 100.00 88.89 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
3)By bicycle(%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4)Other(%) 1.01 0.00 4 0.00 11.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Spent Time(min) 30.2 30.63 32.39 27.18 15.00 20.56 19.44 15.18 15.00 60.00 41.11 46.67 120.00 30.00 20.00 4)To Primary
School
![Page 85: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/85.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
83
Distance(km) 0.86 0.96 0.98 0.99 0.73 0.70 0.46 1.01 0.67 0.60 0.56 0.27 4.00 0.52 1.00 Way of
Communication
1)On foot(%) 99.31 99.41 99.30 99 100.00 100.00 100.00 100.00 100.00 100.00 94.44 100.00 100.00 99.05 100.00
2)By bus(%) 0.69 0.59 0.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.56 0.00 0.00 0.95 0.00
3)By bicycle(%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4)Other(%) 0.00 0.00 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Spent Time(min) 11.1 11.49 11.89 13.65 7.38 13.67 7.11 9.54 7.9 11.82 14.06 5.66 40.00 5.27 15.00 5) To Middle
School
Distance(km) 7.15 7.87 7.25 6.79 8.00 7.72 7.67 7.05 7.00 12.00 12.00 12.00 25.00 5.19 5.00 Way of
Communication
1)On foot(%) 0.00 0.00 27.18 11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2)By bus(%) 100.00 98.99 72.82 85 100.00 88.89 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
3)By bicycle(%) 0.00 0.00 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4)Other(%) 1.01 0.00 2 0.00 11.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Spent Time(min) 31.4 31.83 31.87 27.23 15.00 23.89 29.44 17.73 15.00 50.00 55.00 40.00 120.00 30.10 20.00 6) To Hospital
Distance(km) 4.37 4.24 5.35 5.21 8.00 2.50 0.66 7.05 1.77 0.64 0.49 0.53 4.00 5.00 5.00 Way of
Communication
1)On foot(%) 23.18 59.29 0.42 28 0.00 77.78 100.00 0.00 80.00 100.00 94.44 100.00 100.00 0.00 0.00
2)By bus(%) 76.82 39.70 0.58 67 100.00 11.11 0.00 100.00 20.00 0.00 5.56 0.00 0.00 100.00 100.00
3)By bicycle(%) 0.00 0.00 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4)Other(%) 1.01 0.00 2 0.00 11.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Spent Time(min) 22.5 22.13 28.86 25.5 15.00 23.11 9.44 17.50 8.90 14.09 10.67 10.67 40.00 30.00 20.00
![Page 86: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/86.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
84
Survey Matrix of the household-survey(C)——Financial Status
Survey Duration Jan.-June 2009 Township, County Diansha, Xundian Jinsuo Xundian Dianyuan Songming
Administrative Village Total
Haiwei Qinghai Xintian Haiwei
Village Group Baseline Jan.-June 2008 July-Dec.2008
Jan.-June 2009
Haiwei No.2
Haiwei No.3
Haiwei No.4
Haiwei No.5
Haiwei No.6
Qinghai No.1
Qinghai No.2 Laohaitou Huaqing Laoba Deshi
a. Household (No.) 289 289 287 287 8 9 9 22 10 11 18 3 12 105 80 b. Population(No.) 1109 1103 1069 1057 31 36 41 66 36 53 70 10 62 366 298
c. Ratio(%) 100 100 100 100 2.90 3.37 3.84 6.17 3.37 4.96 6.55 0.94 5.80 34.24 27.88 1. Land Area
1) Paddy Field(mu) 797.64 706.54 695.4 434.1 8.23 22.90 0.00 2.64 0.00 0.00 34.14 1.90 0.00 370.64 230.76 2)Dry Land(mu) 2115.48 1940.43 1860.43 1253.1 5.87 46.74 18.81 133.48 55.01 58.90 111.29 9.50 436.81 808.17 158.84 3)Woodland(mu) 699.38 661.74 631.74 453.34 18.72 43.70 6.27 287.09 93.58 14.06 14.29 0.00 17.96 129.39 3.61
4)Garden(mu) 179.18 172.8 152.8 148.1 0.00 0.48 0.00 0.00 0.48 0.00 0.00 0.00 10.26 42.18 110.77 5)Waste land(mu) 167.62 170.19 168.19 139 0.00 106.96 0.00 0.95 0.00 0.00 0.00 0.00 28.50 23.37 1.90
6)Housing Plot(mu) 109.82 74.57 71.565 69.8 0.00 1.43 0.00 4.47 0.00 0.95 0.95 0.00 1.90 60.58 0.57 7)Building Plot(mu) 5.78 3 2.4 2.2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.85 0.00 0.00 8)Water Area(mu) 14.45 8.86 6.86 6.2 0.00 0.00 0.00 0.00 3.80 0.00 4.62 0.00 0.00 0.00 0.00
Total(mu) 4089.35 3738.13 3589.39 2505.84 32.81 222.21 25.08 428.62 152.86 73.91 165.29 11.40 498.28 1434.33 506.45 2.Income
1)Grain planting(yuan) 9286.34 2655.20 3814.12 3610.98 39543.00 24266.76 29028.58 52417.26 25548.60 49761.46 84894.46 17934.00 38866.80 219618.00 170128.00 2)Forestry or other
crops planting(yuan) 2553.33 783.05 942.76 1067.21 0.00 490.00 0.00 34829.20 19321.68 7824.32 0.00 0.00 1187.76 50813.00 107310.00
3)Fishery or poultry farming(yuan) 854.92 308.36 281.75 318.69 0.00 0.00 0.00 39860.52 7236.32 0.00 0.00 0.00 7897.82 15680.00 16660.00
4)Industry(yuan) 37.27 32.87 2.36 2.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5880.00 3430.00 5)Construction(yuan) 199.05 266.19 169.58 191.99 0.00 0.00 2382.38 2450.00 0.00 0.00 0.00 0.00 0.00 23030.00 47530.00
6)Transportation(yuan) 250.17 132.88 283.81 321.02 0.00 0.00 5157.74 8663.20 0.00 0.00 0.00 0.00 0.00 13034.00 10780.00 7)Commerce and
service(yuan) 441.94 410.26 528.76 598.51 0.00 0.00 0.00 7561.68 2940.00 0.00 0.00 0.00 0.00 73843.00 31850.00
8)Others(yuan) 644.10 1330.45 830.23 248.88 686.00 0.00 7644.00 3567.20 0.00 1176.00 0.00 0.00 1749.30 278001.50 83986.00 Total (yuan) 14267.12 5937.44 6865.14 6359.59 40229.00 24756.76 44186.24 149349.06 55046.60 58761.29 84894.46 17934.00 50681.68 683109.00 472654.00
3.Out-town odd-jobbers
![Page 87: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/87.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
85
Number of out-town odd-jobbers(person) 126 119 68 65 5 0 1 9 2 0 0 0 1 41 18
Occupational distribution of
out-town odd-jobbers
1) Grain Planting (%) 1.59 0.84 0 1.54 0 0 0 50 0 0 0 2) Forestry or other crops planting (%) 0.79 2.52 0 1.54 0 0 0 0 0 2.44 0
3) Fishery or poultry farming (%) 8.73 2.52 6.15 0 0 0 0 0 0 0 0
4) Industry (%) 8.73 10.92 3.76 3.08 0 0 11.11 0 0 2.44 0 5) Construction
Industry (%) 23.02 27.73 8.12 16.92 20 100 11.11 0 0 12.2 50
6) Transportation Industry (%) 6.35 2.52 33.24 6.15 20 0 0 50 0 4.88 0
7) Commerce or service industry(%) 30.95 44.54 29.44 55.38 0 0 77.78 0 100 60.98 50
8)Other trades 19.84 8.40 19.28 15.38 60 0 0 0 0 14.63 0 Geographic
distribution of out-town
odd-jobbers(%)
1)Local villages or towns(%) 19.84 9.24 10.29 11.11 60 100 11.11 100 100 4.88 0
2)Other villages or towns of the local
county (%) 11.90 10.08 7.35 5.56 0 0 44.44 0 0 7.32 0
3)Other counties of the local city(%) 44.44 52.94 51.47 44.44 40 0 44.44 0 0 65.85 66.67
4)Other cities of the local province (%) 15.08 21.85 22.06 33.33 0 0 0 0 0 12.2 16.67
5)Other provinces(%) 8.73 5.88 8.82 5.56 0 0 0 0 0 9.76 16.67 6)Foreign countries
(%) 0.00 0.00 0.00 0 0 0 0 0 0 0 0
Average Income (yuan) 941.75 867.04 890.66 864.31 876.3 1096.48 521.89 978.5 869.3 999.21 708.49
4. Expenditure Expenditure for
Production (yuan) 2257.44 1593.06 1415.16 2524.28 793.75 1555.56 3088.89 1266.82 635.00 1245.45 713.89 933.33 1433.33 1690.48 2098.13
![Page 88: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/88.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
86
Expenditure for Living (yuan) 1809.18 890.42 957.7 5104.19 5285 5264.44 7946.22 7965.45 4228.00 4236.36 3730.56 1983.33 5015.83 5923.81 4691.68
1) Cultural Eduction(yuan) 2257.44 1593.06 1415.16 791.15 2300 883.33 1994.44 715.45 1840.00 545.45 1200.00 200.00 1691.67 2857.14 783.17
2)Grain(yuan) 1809.18 890.42 957.7 639.77 1075 972.22 943.11 1272.73 860.00 945.45 683.33 550.00 891.67 428.57 1153.03 Self-production(yuan) 1066.48 644.92 543.66 328.83 287.5 116.67 305.56 256.36 230.00 418.18 477.78 166.67 891.67 428.57 1086.78
Purchasing(yuan) 742.7 245.49 404.22 307.69 787.5 855.56 637.56 1016.36 630.00 527.27 205.56 383.33 0.00 0.00 66.25 3)Non-Staple Food(yuan) 1483.22 387.39 275.64 292.20 38.75 205.56 266.67 1252.27 31.00 209.09 66.67 0.00 175.83 238.10 364.20
4)Fuel(yuan) 879.17 623.53 502.58 442.23 443.75 631.11 1216.67 943.18 355.00 690.91 588.89 466.67 950.00 571.43 397.77 5)Clothes(yuan) 1228.58 858.48 867.77 519.69 296.25 305.56 750.00 1100.45 237.00 454.55 472.22 233.33 575.00 847.62 451.52
6)Health Care(yuan) 1713.15 1252.25 944.29 813.05 687.5 1816.67 1925.33 1478.18 550.00 772.73 230.56 166.67 98.33 447.62 650.27 7)Socializing(yuan) 1850.45 1031.00 1022.37 654.43 443.75 450.00 850.00 1203.18 355.00 618.18 488.89 366.67 633.33 533.33 891.74
Survey Matrix of the household-survey(D)—— Evaluation of present living situation and Economic Recovery
Survey Duration January-June.2009 Township,
County Diansha Xundian Jinsuo Xundian Dianyuan Songming
Administrative Village
Average/Total
Haiwei Qinghai Xintian Haiwei
Village Group Baseline Jan.-June 2008 Baseline Jan.-June.2009
Haiwei No.2
Haiwei No.3
Haiwei No.4
Haiwei No.5
Haiwei No.6
Qinghai No.1
Qinghai No.2 Laohaitou Huaqing Laoba Deshi
a. Household (No.) 289 289 287 287 8 9 9 22 10 11 18 3 12 105 80
b. Population(No.) 1109 1103 1069 1057 31 36 41 66 36 53 70 10 62 366 298
c. Ratio(%) 100 100 100 100 2.90 3.37 3.84 6.17 3.37 4.96 6.55 0.94 5.80 34.24 27.88 Evaluation of present living situation 1.Evaluation of production conditions
Rather good(%) 9.69 6.23 6.27 5.92 0.00 0.00 0.00 0.00 0.00 0.00 5.56 0.00 0.00 5.71 13.41 Superior(%) 13.84 12.80 15.33 20.21 0.00 0.00 0.00 31.82 20.00 0.00 0.00 0.00 0.00 7.62 24.39 Average(%) 67.13 64.36 70.38 64.81 100.00 22.22 33.33 54.55 50.00 90.91 88.89 100.00 66.67 72.38 52.44 Inferior(%) 7.27 13.15 6.62 7.67 0.00 55.56 11.11 13.64 30.00 9.09 5.56 0.00 16.67 14.29 8.54
Rather bad(%) 2.08 3.46 1.39 1.39 0.00 22.22 55.56 0.00 0.00 0.00 0.00 0.00 16.67 0.00 1.22 2. Evaluation of Their Financial Status in the Village
![Page 89: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/89.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
87
Rather good(%) 1.38 1.04 2.44 5.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.95 2.44 Superior(%) 10.73 8.65 11.15 18.82 0.00 0.00 11.11 18.18 10.00 9.09 0.00 0.00 0.00 4.76 15.85 Average(%) 75.78 70.93 75.96 63.41 50.00 11.11 44.44 72.73 60.00 81.82 94.44 100.00 66.67 77.14 68.29 Inferior(%) 9.00 15.57 8.71 11.50 50.00 44.44 11.11 9.09 30.00 9.09 5.56 0.00 33.33 15.24 10.98
Rather bad(%) 3.11 3.81 1.74 1.05 0.00 44.44 33.33 0.00 0.00 0.00 0.00 0.00 0.00 1.90 2.44 3. Evaluation of Present Residential Environment
Rather good(%) 11.76 6.92 6.97 9.76 0.00 11.11 0.00 18.18 0.00 9.09 33.33 33.33 0.00 1.90 6.10 Superior(%) 9.69 9.69 11.15 18.12 0.00 0.00 0.00 18.18 0.00 0.00 11.11 33.33 0.00 3.81 20.73 Average(%) 64.36 59.17 68.99 59.23 100.00 0.00 11.11 63.64 70.00 90.91 55.56 33.33 25.00 75.24 46.34 Inferior(%) 10.73 19.03 10.45 10.10 0.00 44.44 11.11 0.00 10.00 0.00 0.00 0.00 66.67 19.05 25.61
Rather bad(%) 3.46 5.19 2.44 2.79 0.00 44.44 77.78 0.00 20.00 0.00 0.00 0.00 8.33 0.00 1.22 4. Evaluation of Neighborhood Relation
Rather good(%) 36.33 34.26 40.77 16.38 0.00 22.22 22.22 81.82 80.00 27.27 27.78 100.00 16.67 7.62 58.54 Superior(%) 12.46 14.53 17.07 21.60 0.00 0.00 22.22 13.64 0.00 18.18 16.67 0.00 25.00 6.67 26.83 Average(%) 50.52 43.94 40.42 48.78 100.00 66.67 55.56 4.55 20.00 54.55 50.00 0.00 50.00 69.52 13.41 Inferior(%) 0.00 6.57 1.74 8.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.33 16.19 1.22
Rather bad(%) 0.69 0.69 0.00 5.23 0.00 11.11 0.00 0.00 0.00 0.00 5.56 0.00 0.00 0.00 0.00 5. Evaluation of Life Satisfaction
Rather good(%) 13.50 9.69 5.57 5.23 0.00 0.00 0.00 36.36 0.00 18.18 22.22 33.33 0.00 3.81 10.98 Superior(%) 11.76 12.80 14.98 17.07 0.00 11.11 11.11 31.82 20.00 36.36 0.00 0.00 0.00 2.86 23.17 Average(%) 65.05 57.79 60.28 17.07 100.00 0.00 22.22 31.82 20.00 45.45 77.78 66.67 66.67 73.33 51.22 Inferior(%) 5.54 14.53 3.48 51.92 0.00 66.67 44.44 0.00 0.00 0.00 0.00 0.00 8.33 20.00 12.20
Rather bad(%) 4.15 5.19 15.68 8.71 0.00 22.22 22.22 0.00 60.00 0.00 0.00 0.00 25.00 0.00 2.44
![Page 90: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/90.jpg)
Annex Ⅲ Survey sheet of economic rehabilitation on affected
villages (from January to June 2009)
Follow-up Village
Newly-added area
for orchard(mu)
Newly-added area
for economic crops(mu)
Newly-addedlivestock(each)
Additional outworkers
through doing odd
works for others(person)
Additional income for per
household(yuan)
Worked for
Qingshuihai
Project
(Person)
Qinghai Xintian 147 15 58 58 Jinsuo
Zetie Luliu 31 160 160
Diansha Haiwei 15 180 200 20 20 20 Enjia Wu 32 103 103
Tuoqi Liushao
Maanshan Huangtupo
Sanyingzhuang Daliusuo
Tianqiaodi Dianxin 27 50 50 Duohe
Xun
dian
Yangjie
Dianlong 18 30 30 laoba 350 35 60 60
Dianyuan Zhouda Shanjiao
Songyang Dong 50 100 38 20 20 So
ngm
ing
Yangqiao Xishan 50 325 845 Total 115 955 1192 216 501 501
![Page 91: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/91.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
89
Annex Ⅳ Status of public participation in Qingshuihai Water Supply Project (From January to June 2009)
Time Location Subject Participant Issues
6th March 2009
Haiwei Relocation Plot in Xundian
County, Ganchong, Renjiahou
Relocation Plot in Songming County
Field Survey on relocation plot
Vice monitor of relocation plot construction,
monitoring staff, the representatives of
Qingshuihai Company and Resettlement Office
Field Survey on the situation of house building, road recovery, Water supply, power supply and afforestation in Haiwei Relocation Plot, and the construction progress of ground
flattering, stone barrier, housing plot distribution of Deshi Ganchong, Laoba Rejiahou Relocation Plot
12th March 2009
Resettlement Office of Qingshuihai
Project in Songming County
Survey and check of the usage of resettlement fund
Monitoring staff, the representatives of
Qingshuihai Company and accounting staff of
Resettlement Office
Survey and check of the usage of resettlement fund and communication with relevant staff
24th March 2009
Renjiahou Relocation Plot in Songming County
Field Survey on relocation plot
Vice monitor of relocation plot construction,
monitoring staff, the representatives of
Qingshuihai Company and Resettlement Office
Putting forward suggestions about temporary drainage, design change, improvement on document collection
8th April 2009
Resettlement Office in Xundian County
Coordination and resolving problems involved in
resettlement
Monitoring staff, the representatives of
Qingshuihai Company, affected village, village
committee and Resettlement Office
Field Survey on the situation of house building, road recovery, Water supply, power supply and afforestation in Haiwei Relocation Plot
9th April 2009
Resettlement Office in Songming
County, Renjiahou
Field Survey on relocation plot and water supply facilities
Monitoring staff, the representatives of
Qingshuihai Company,
Field Survey for the progress of relocation plot and water supply facilities, and carrying out interview with financial staff
and monitors
![Page 92: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/92.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
90
Relocation Plot in Songming County
affected village, village committee of Dinayuan
Township and Resettlement Office
13th April 2009
Resettlement Office in Xundian County
Field Survey on resettlement and removals
Monitoring staff, the representatives of
Qingshuihai Company, affected village, village
committee and Resettlement Office
Communicating with the staff of resettlement offices for surveying the situation of resettlement, and introducing the evidence, tasks, working organization of resettlement to staff from Resettlement Office of Xundian County, and providing suggestions about resettlement removal, water supply facilities
27th April 2009
Resettlement Office in Xundian
County,Relocation Plots of Haiwei, Haitou, Huaqing and Xiaobeidang
Field Survey on resettlement and removals
Vice monitor of relocation plot construction,
monitoring staff, the representatives of
Qingshuihai Company and Resettlement Office
Field Survey on the situation of house building, road recovery, Water supply, power supply and afforestation in Haiwei
Relocation Plot, and the construction progress of location selection, house building of Scattered Relocation Plot
![Page 93: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/93.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
91
Annex Ⅴ Explanation of External Monitoring and Evaluation Index System of Resettlement for
Qingshuihai Project (First) ( From January to June 2009)
ⅠProject Implementation Objective Criteria Explanation of Criteria Fulfilled Items and Problems Evaluation and Score
1.1 Implementation of preparation
for land acquisition,
demolition and resettlement
Main Involved Items: ⑴RP Preparation: ①Establish resettlement office ②Entrust RP compiler ③ Detailed socio-economic survey ④
Compiling RP ⑤Renewing of RP according to the Detailed Design ⑵ Information Disclosure and Public Participation: ①
Consultation with relevant departments and APs ②
Disclosure draft RP to APs ③Disclosure of revised RP and RIB to APs ④Uploading RP on ADB website ⑤Uploading the renewal RP on ADB website ⑶RP Approval: ①RP approval MWR ②RP approval by ADB ③The updated RP approval by ADB ⑷Procedures for Construction Land ①Land preliminary examination ②Approval of land use (Partial) ③Approval of land use (Partial)
Fulfilled Criteria as following: (1)RP Preparation (2)Information Disclosure and Public Participation (3)RP Approval (4)Procedures for Construction Land Generally matching
with scheme and plan Evaluation: Qualified
Score: 5.0
1 Project Progress
1.2 Progress of land
acquisition and demolition
Main Involved Items: ①Progress of temporary land acquisition and demolition ②Progress of permanent land acquisition and demolition ③Progress of reservoir bottom cleaning
Progress of permanent temporary land acquisition and demolition matched schedule in RP No implementation of reservoir bottom cleaning
Generally matching with scheme and plan Evaluation: Average
Score: 3.0
![Page 94: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/94.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
92
1.3 Construction progress of resettlement
location
Main Involved Items: ①Implementation of the scheme in RP ②Delay and shutdown within resettlement location construction
Construction progress of relocation site matched schedule in RP without delay and shutdown
Generally matching with scheme and plan Evaluation: Qualified
Score: 3.0
1.4 Progress of resettlement
Main Involved Items: ①Appropriate arrangement and relocation of affected people ②Entering and being stationed in relocation site
Part of temporary resettlement had not found appropriate relocation site, removal had been delayed
The difference between plan and actual progress is
about 30% Evaluation: inferior
Score: 1.0
2.1 Quality of land
acquisition and demolition
Main Involved Items: ① Task quality of temporary land acquisition and demolishment ②Task quality of permanent land acquisition and demolishment ③Task quality of reservoir bottom cleaning ④Major accident during land acquisition and demolishment
Task of permanent temporary land acquisition and demolition matched scheme in RP but with some changes in land type No major accident
Task quality basically reaches the standard Evaluation: Average
Score: 3.0
2.2 Quality of house and
infrastructure in resettlement
location
Main Involved Items: ①Implementation of the program in Resettlement Plan ②Standardization of quality of house and infrastructure in resettlement location ③Report or tip-off about quality of house and infrastructure in resettlement location
Construction of relocation site matched schedule in RP but without quality test and report or tip-off about quality of house and infrastructure in resettlement location
The quality basically reaches the demand of
RP Evaluation: Qualified
Score: 5.0
2 Project Quality
2.3 Satisfaction of resettlement
Main Involved Items: ①Complain or appeal about land acquisition and demolishment from resettlement ②Complain or appeal about relocation site and approach from resettlement ③Complain or appeal about economic recovery approach from resettlement ④Complain or appeal about resettlement of vulnerable group
There were some complain and dissatisfaction about compensation standard and the house of relocation site
Part of affected people were dissatisfied to
resettlement Evaluation: Average
Score: 3.0
![Page 95: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/95.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
93
and minority ⑤Public participation
2.4 Handling of relative quality
problem
Main Involved Items: ①Handling of dispute or problem about land acquisition and
demolishment ② Handling of dispute or problem about resettlement production and living
The scheme for resolving the problem about the house of relocation site had been put forward but without consensus
Appropriate handling but not prompt
Evaluation: Average Score: 3.0
3.1 Appropriation
of Resettlement fund
Main Involved Items: ①Situation of appropriation of resettlement fund according to budget ②Situation of appropriation of resettlement fund according to schedule ③Procedure of appropriation of resettlement fund according to certain regulations ④Tip-off of appropriation of resettlement fund
The appropriation of resettlement fund according to budget, schedule and regulations without complain and tip-off
The task of appropriation of resettlement fund was qualified. Evaluation: Qualified
Score: 5.0
3.2 Distribution of Resettlement compensation
Main Involved Items: ①Situation of distribution of resettlement fund according to budget ②Situation of distribution of resettlement fund according to schedule ③Procedure of distribution of resettlement fund according to certain regulations ④Tip-off of distribution of resettlement fund
The distribution of resettlement fund according to budget, schedule and regulations, but some affected people had not received compensation because who worked at other cities No complain and tip-off
The distribution of resettlement fund is
basically qualified but with delay
Evaluation: Good Score: 5.0
3 Project Fund
3.3 Usage of Resettlement
fund
Main Involved Items: ①Situation of usage of resettlement fund according to plan and certain regulations ②Tip-off about diverting of resettlement fund
The usage of resettlement fund according to budget, schedule and regulations without complain and tip-off
Evaluation: Qualified Score: 5.0
Ⅱ Situation of Resettlement and Rehabilitation Objective Criteria Explanation of Criteria Fulfilled Items and Problems Evaluation and Score
4 Economic Status of
Resettlement 4.1 Productive materials and conditions
Main Involved Items: ①The quantity of productive materials and conditions owned
by surveyed households
The levels of quantity, types, quality of productive materials and conditions owned by surveyed households are
Basically equal with Baseline
Evaluation: Average
![Page 96: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/96.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
94
②The types of productive materials and conditions owned by surveyed households ③The quality of productive materials and conditions owned by surveyed households
generally equal with those of Baseline Score: 3.0
4.2 Living materials and conditions
Main Involved Items: ①The quantity of living materials and conditions owned by
surveyed households ②The types of living materials and conditions owned by surveyed households ③The quality of living materials and conditions owned by surveyed households
The levels of quantity, types, quality of living materials and conditions owned by surveyed households are generally
equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
4.3 Fixed assets owned by household
Main Involved Items: ①The quantity of house owned by surveyed households
(area) ② The types of house owned by surveyed households (bungalow, storied building) ③The quality of house owned by surveyed households (structure and age)
The levels of quantity, types, quality of houses owned by surveyed households are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
4.4 Economic Income
Main Involved Items: ①Sum of income of surveyed household ②Sources of income of surveyed household ③Stability of income of surveyed household
The levels of total income, income source and stability earned by surveyed households are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
4.5 Expenditure
Main Involved Items: ①Sum of expenditure of surveyed household ②Structure of expenditure of surveyed household ③ Comparability between income and expenditure of surveyed household
The levels of total expenditure, expenditure structure, comparability for surveyed households are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
5 Living condition of Resettlement
5.1Traffic and communication
conditions
Main Involved Items: ①Communication ways of surveyed household ②Communication distance of surveyed household ③Communication time-cost of surveyed household
The situation of communication ways, distance and time-cost to main public location taken by surveyed household are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
![Page 97: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/97.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
95
5.2 Educational condition and
enrolling
Main Involved Items: ①Quantity of educational institutions in project affected area ②Complete situation of educational institutions in project affected area ③Enrollment of local children in project affected area ④Teaching conditions of educational institutions in project affected area
The quantity, complete situation, teaching conditions of educational institutions and enrollment of local children in project affected area are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
5.3 Health care
Main Involved Items: ①Quantity of medical institutions in project affected area ② Complete situation of medical institutions in project affected area ③Medical convenient conditions of local people in project affected area ④Medical levels of medical institutions in project affected area
The quantity, complete situation, medical convenient conditions and medical levels of medical institutions in project affected area are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
5.4 Infrastructure
and public service
Main Involved Items: ①Domestic water supply situation in project affected area ②Domestic energy supply situation in project affected area ③Domestic road situation in project affected area
Domestic water, energy supply and road situation in project affected area are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
6.1 Employment of
family members
Main Involved Items: ①Employment status of family members from surveyed households ②Industries of employed family members from surveyed households
The employment status and industrial distribution of family members from surveyed households are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
6.2 Education of family members
Main Involved Items: Educational degree and structure of family members from surveyed households
The educational degree and structure of family members from surveyed
households are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
6 Family Status of
Resettlement
6.3 Marriage of family members
Main Involved Items: Marriage situation of family members from surveyed households
The Marriage situation of family members from surveyed households
are generally equal with those of Baseline
Basically equal with Baseline
Evaluation: Average Score: 3.0
![Page 98: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/98.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
96
7.1 Mechanism of grievance
Main Involved Items: ①Establishment of relative system and organization ②Implementation and execution of system ③Efficiency of problem resolving
Establishment of relative system and organization had been complete, but with adjustment and running-in
Evaluation: Average Score: 3.0
7.2 Assistant tasks of relative
government
Main Involved Items: ①Establishment of relative system and organization ②Matching and execution of system ③Efficiency of problem resolving
Relative system and departments had been established, but with adjustment and running-in
Evaluation: Average Score: 3.0
7.3 Demand meeting
Main Involved Items: ①Expression and receiving of expectation of resettlement ②Feedback of expectation of resettlement ③Meeting of expectation and demand of resettlement
The expectations and requests can be expressed freely and accepted by official but with inadequate feedback
Evaluation: Qualified Score: 5.0
7 Rights Safeguard of Resettlement
7.4 Response and feedback of villagers
Main Involved Items: ①Formulation of response and feedback system
②Operation and implementation of response and feedback system
The system and mechanism of appeal and feedback are still established and adjusted
Evaluation: Qualified Score: 5.0
8.1 Support of vulnerable
groups
Main Involved Items: ①Layout of support measures ②Implementation of support measures ③Effects of support measures
Certain support measures had been put forward and implemented with the process of resettlement
Evaluation: Qualified Score: 5.0
8.2 Extension of economic
recovery measures
Main Involved Items: ①Layout of economic recovery measures ②Implementation and extension of economic recovery measures ③Effects of economic recovery measures
Certain support measures had been put forward and implemented with the process of resettlement but the extension for them is weaker
Evaluation: Average Score: 3.0
8 Social Development
of Resettlement Community
8.3 Stabilization of community life
and culture
Main Involved Items(Community stability): ①Community public order ②Neighborhoods of community Main Involved Items(Community culture): ①Cultural activities of community ②Harmony of community culture
Current community public order is stable and with harmony neighborhoods There are community cultural activities carried out regularly
Evaluation: Qualified Score: 5.0
![Page 99: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/99.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
97
8.4 Life of minority
Main Involved Items: ①Conservation of culture of minority ②Layout of specific support measures for minority ③Effects of specific support measures for minority
Economic and cultural support measures had been put forward and implemented with the process of resettlement
Evaluation: Qualified Score: 5.0
8.5 Poverty relief
Main Involved Items: ①Layout of specific measures for poverty relief ③Effects of specific measures for poverty relief
Poverty relief measures had been put forward and implemented with the process of resettlement
Evaluation: Qualified Score: 5.0
9.1 Afforestation
of Resettlement place
Main Involved Items: ①Afforestation ②Natural forest reservation
There are some barren region lack of afforestation
Evaluation: Average Score: 3.0
9.2 Natural resources
reservation of Resettlement
place
Main Involved Items: ①Water resources reservation ②Land resources reservation ③Mineral resources reservation ④Biological resources reservation
Natural resources of Resettlement place had been reserved well.
Evaluation: Qualified Score: 5.0
9.3 Pollution prevention of Resettlement
place
Main Involved Items: ①Prevention of water pollution ②Prevention of soil pollution ③Prevention of air pollution ④Garbage disposal
The ways and measures of garbage disposal were not incomplete
Evaluation: Average Score: 3.0
9 Environmental protection of Resettlement
place
9.4 Soil and water
conservation of Resettlement
place
Main Involved Items: ①Measures of soil and water conservation ②Prevention and control of mud-rock flow and hill-creep
Measures of soil and water conservation had been implemented and mud-rock flow and hill-creep had been prevented and controlled effectively.
Evaluation: Qualified Score: 5.0
Ⅲ Project Risk Objective Criteria Explanation of Criteria Fulfilled Items and Problems Evaluation and Score
10 Project risks 10.1 Project Risk of
progress
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management
Possibility of risk is medium because part of interim resettlement had not been complete according to plan Evaluation:
Unqualified Score: 1.0
![Page 100: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/100.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
98
measures ③Implementation conditions of measures
10.2 Project Risk of quality
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures ③Implementation conditions of measures
There are some defects of land acquisition, demolishment , but which can be resolved by proper measures in order to reduce risk possibility
Evaluation: Qualified Score: 5.0
10.3 Project Risk of investment and fund
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures ③Implementation conditions of measures
The risk possibility is medium because there are some defects of compensation distribution, and which can not be resolved by current measures
Evaluation: Qualified Score: 5.0
10.4 Project Risk of economic aggravation of resettlement
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures ③Implementation conditions of measures
Although there is generally no change in resettlement economic situation, inadequate extension of economic recovery measures may induce risk of economic aggravation of resettlement
Evaluation: Average Score: 3.0
10.5 Project Risk of aggravation of living condition for resettlement
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures ③Implementation conditions of measures
Although there is generally no change in resettlement living conditions, project construction and demolishment may induce risk of living condition aggravation of resettlement
Evaluation: Average Score: 3.0
10.6 Project Risk of change of family of resettlement
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures ③Implementation conditions of measures
Although there is generally no change in employment of affected people, macro economic environment and crisis of employment may induce unemployment of resettlement
Evaluation: Average Score: 3.0
10.7 Project Risk of right safeguard
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures
No occurrence of injury of affected people’s right and interest, there are risks induced by the system of accepting and handling dispute was incomplete
Evaluation: Average Score: 3.0
![Page 101: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/101.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
99
③Implementation conditions of measures
10.8 Project Risk of social development
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures ③Implementation conditions of measures
The governments and Project office issued some development measures for resettlement, and affected people were willing to accept and taking part in positively, possibility of risk was relatively low
Evaluation: Qualified Score: 5.0
10.9 Project Risk of environmental protection
Main Involved Items: ①Possibility of risk ②Layout of comprehensive control and management measures ③Implementation conditions of measures
There were some risk of environmental protection induced by lagging of afforestation and garbage disposal Evaluation: Average
Score: 3.0
![Page 102: PRC: Kunming Qingshuihai Water Supply Project...Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project 4 Once the project has been completed, 96.84](https://reader033.vdocuments.site/reader033/viewer/2022050506/5f97d38b818cdd28ba4548bf/html5/thumbnails/102.jpg)
Analysis Report on Living Standard Follow-up Survey for Resettlement of Qingshuihai Project
100
Kunming Water Supply Group Co., Ltd. (KWSG) Head of Consultation Expert Team of the External Monitoring
Kunming Qingshuihai Water Development Company (KQWSP) and Evaluation Institution for Resettlement
ChenGang Wang Songjiang
Deputy manager ,Senior engineer
(Signature)
Professor, Dean of Business Administration Department in Faculty of Management & Economics,
Kunming University of Science & Technology
(Signature) Wang Song Jiang
Date: October 16,2009
Date: October 8,2009