USDA-Natural Resources Conservation Service Connecticut Scenario Cost: Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new culvert greater than 30" in diameter. HDPE and CMP are acceptable materials under this scenario. For culverts less than 30" use Practice Standard 587 Structure for Water Control. Work includes dewatering, site preparation and removing any old crossing, acquiring and installing culvert pipe with gravel bedding and fill (compacted), and building headwalls. If a different travel surface is needed, refer to another appropriate standard for the surfacing. 36 inch Culvert installation with <75 cy of fill needed and < 2 yds rock riprap for headwalls. Pipe is 40 feet long.Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic. Use (587) Structure for Water Control instead, for ditch cross culverts and other intermittent flows and culverts less than 30" in diameter. Before Situation: Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel. After Situation: Access road and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization. Scenario Feature Measure: Culvert Scenario Typical Size: 1,440 Scenario Unit: Inch-Foot ID Component Name Cost Quantity Price ($/unit) Unit Component Description $5,185.79 Scenario Cost/Unit: $3.60 Cost Details (by category): Equipment/Installation 50 Earthfill, Manually Compacted Earthfill, manually compacted, includes equipment and labor Cubic yard $5.75 3 $17.25 931 Hydraulic Excavator, 1 CY Track mounted hydraulic excavator with bucket capacity range of 0.8 to 1.5 CY. Equipment and power unit costs. Labor not included. Hour $117.15 10 $1,171.50 Labor 233 Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons. Hour $33.69 10 $336.90 Materials 46 Aggregate, Gravel, Graded Gravel, includes materials, equipment and labor to transport and place. Includes washed and unwashed gravel. Cubic yard $35.73 50 $1,786.50 1248 Pipe, HDPE, CPT, Double Wall, Soil Tight, 36" Pipe, Corrugated HDPE Double Wall, 36" diameter with soil tight joints - AASHTO M294. Material cost only. Foot $36.03 40 $1,441.20 44 Rock Riprap, Placed with geotextile Rock Riprap, placed with geotextile, includes materials, equipment and labor to transport and place Cubic yard $84.90 2 $169.80 Mobilization 1139 Mobilization, medium equipment Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds. Each $262.64 1 $262.64 578 - Stream Crossing (Culvert Installation, >30 inch diameter) - Page 1 of 1 FY2015 - Compiled 10/27/2014

Upload: others

Post on 21-Mar-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #1 - Culvert Installation, >30 inch diameter

Scenario Description:Install a new culvert greater than 30" in diameter. HDPE and CMP are acceptable materials under this scenario. For culverts less than 30" use Practice Standard 587 Structure for Water Control. Work includes dewatering, site preparation and removing any old crossing, acquiring and installing culvert pipe with gravel bedding and fill (compacted), and building headwalls. If a different travel surface is needed, refer to another appropriate standard for the surfacing. 36 inch Culvert installation with <75 cy of fill needed and < 2 yds rock riprap for headwalls. Pipe is 40 feet long.Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic. Use (587) Structure for Water Control instead, for ditch cross culverts and other intermittent flows and culverts less than 30" in diameter.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access road and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Culvert

Scenario Typical Size: 1,440

Scenario Unit: Inch-Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$5,185.79 Scenario Cost/Unit: $3.60

Cost Details (by category):

Equipment/Installation

50Earthfill, Manually Compacted Earthfill, manually compacted, includes equipment and labor

Cubic yard

$5.75 3 $17.25

931Hydraulic Excavator, 1 CY Track mounted hydraulic excavator with bucket capacity range of 0.8 to 1.5 CY. Equipment and power unit costs. Labor not included.

Hour $117.15 10 $1,171.50

Labor

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 10 $336.90

Materials

46Aggregate, Gravel, Graded Gravel, includes materials, equipment and labor to transport and place. Includes washed and unwashed gravel.

Cubic yard

$35.73 50 $1,786.50

1248Pipe, HDPE, CPT, Double Wall, Soil Tight, 36"

Pipe, Corrugated HDPE Double Wall, 36" diameter with soil tight joints - AASHTO M294. Material cost only.

Foot $36.03 40 $1,441.20

44Rock Riprap, Placed with geotextile

Rock Riprap, placed with geotextile, includes materials, equipment and labor to transport and place

Cubic yard

$84.90 2 $169.80

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

578 - Stream Crossing (Culvert Installation, >30 inch diameter) - Page 1 of 1

FY2015 - Compiled 10/27/2014

Page 2: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #2 - Low Water Crossing, Riprap

Scenario Description:Stabilize the bottom and slope of a stream channel using rock riprap or cast in place concrete. This scenario includes site preparation, dewatering, acquiring and installing gravel or geotextile with rock riprap or cast in place concrete on channel bottom and approaches. Final travel surface shall be the rocks or concrete. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Typical stream has 30 foot bottom width and approaches. Width is 14 feet for a total area as 420sf. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Cubic Yards of Riprap Installed (In Place, Not Loose)

Scenario Typical Size: 16

Scenario Unit: Cubic Yard

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$1,897.61 Scenario Cost/Unit: $118.60

Cost Details (by category):

Equipment/Installation

48Excavation, Common Earth, side cast, small equipment

Bulk excavation and side casting of common earth with hydraulic excavator with less than 1 CY capacity. Includes equipment and labor.

Cubic yard

$2.36 16 $37.76

Materials

44Rock Riprap, Placed with geotextile

Rock Riprap, placed with geotextile, includes materials, equipment and labor to transport and place

Cubic yard

$84.90 16 $1,358.40

Mobilization

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 1 $501.45

578 - Stream Crossing (Low Water Crossing, Riprap) - Page 1 of 1

FY2015 - Compiled 10/27/2014

Page 3: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #3 - Low water crossing using prefabricated products

Scenario Description:To install a stable crossing medium on channel bottom and approaches. Medium includes but not limited to precast concrete blocks, geocells, pavers, and gabions. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Typical stream has 30 foot bottom width and approaches. Width is 14 feet for a total area as 420sf. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access road and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: low water crossing

Scenario Typical Size: 420

Scenario Unit: Square Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$4,937.79 Scenario Cost/Unit: $11.76

Cost Details (by category):

Equipment/Installation

1227Excavation, common earth, side cast, large equipment

Bulk excavation and side casting of common earth with hydraulic excavator with less greater than 1 CY capacity. Includes equipment and labor.

Cubic Yard

$1.85 18 $33.30

1215Truck, dump, 12 CY Dump truck for moving bulk material. Typically capacity is 16 ton or 12 cubic yards. Includes equipment only.

Hour $99.46 8 $795.68

Labor

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 40 $979.20

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 8 $269.52

Materials

46Aggregate, Gravel, Graded Gravel, includes materials, equipment and labor to transport and place. Includes washed and unwashed gravel.

Cubic yard

$35.73 18 $643.14

1054GeoCell, 4" Precast Manhole with base and top delivered. 4' diameter x 4' depth. Materials only.

Square Yard

$30.08 50 $1,504.00

45Aggregate, Sand, Graded, Washed

Sand, typical ASTM C33 gradation, includes materials, equipment and labor to transport and place

Cubic yard

$35.25 6 $211.50

Mobilization

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 1 $501.45

578 - Stream Crossing (Low water crossing using prefabricated products ) - Page 1 of 1

FY2015 - Compiled 10/27/2014

Page 4: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #4 - Low Water Crossing, River Rock

Scenario Description:Stabilize the bottom and slope of a stream channel using natural river rock to achieve a more natural low water crossing. This scenario includes site preparation, dewatering, acquiring and installing geotextile with river rock on channel bottom and approaches. Final travel surface shall be the river rocks. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Typical stream has 30 foot bottom width and approaches. Width is 14 feet for a total area as 420sf. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Cubic Yards of River Rock Installed (In Place, Not Loose)

Scenario Typical Size: 16

Scenario Unit: Cubic Yard

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$1,914.45 Scenario Cost/Unit: $119.65

Cost Details (by category):

Equipment/Installation

42Geotextile, woven Woven Geotextile Fabric. Includes materials, equipment and labor

Square Yard

$2.51 47 $117.97

931Hydraulic Excavator, 1 CY Track mounted hydraulic excavator with bucket capacity range of 0.8 to 1.5 CY. Equipment and power unit costs. Labor not included.

Hour $117.15 4 $468.60

40Clearing and Grubbing Clearing and Grubbing, includes materials, equipment and labor

Acre $316.37 0.1 $31.64

Labor

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 4 $97.92

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 4 $134.76

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 2 $81.64

Materials

1834Aggregate, river rock Well graded, rounded mineral substrates derived from local riverine settings. Includes materials and local delivery

Ton $29.97 24 $719.28

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

578 - Stream Crossing (Low Water Crossing, River Rock) - Page 1 of 1

FY2015 - Compiled 10/27/2014

Page 5: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #5 - Bridge with a span of less than or equal to 14 feet

Scenario Description:Install a bridge to allow stream flows to cross under access road or animal trail. Bridge opening determined by sizing for storm event dictated in standard. Scenario includes dewatering, abutments, girders, decking. Work consists of site preparation, dewatering, acquiring and installing abuttments, girders, decking with necessary hardware, backfilling abuttments, and armoring with geotextile and riprap. Riprap and geotextile are used to stabilize and protect abutments as needed. Scenario based on cast in place concrete abutments, steel girders, and timber deck. Travel surface shall be wooden deck surface. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Span is less than 14 feet. Load is H-20. Width is 14 feet including curbs. Abutments are <= 6 feet. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: square footage of bridge deck

Scenario Typical Size: 252

Scenario Unit: Square Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$18,268.26 Scenario Cost/Unit: $72.49

Cost Details (by category):

Equipment/Installation

1227Excavation, common earth, side cast, large equipment

Bulk excavation and side casting of common earth with hydraulic excavator with less greater than 1 CY capacity. Includes equipment and labor.

Cubic Yard

$1.85 75 $138.75

1215Truck, dump, 12 CY Dump truck for moving bulk material. Typically capacity is 16 ton or 12 cubic yards. Includes equipment only.

Hour $99.46 8 $795.68

969Water management, Flooding & dewatering

Includes equipment, power unit and labor costs. Acre Foot $232.61 15 $3,489.15

Labor

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 8 $269.52

230Skilled Labor Labor requiring a high level skill set: Includes carpenters, welders, electricians, conservation professionals involved with data collection, monitoring, and or record keeping, etc.

Hour $39.49 80 $3,159.20

Materials

1779Steel, structural steel members Structural steel, includes materials and fabrication. Pound $1.04 4200 $4,368.00

44Rock Riprap, Placed with geotextile

Rock Riprap, placed with geotextile, includes materials, equipment and labor to transport and place

Cubic yard

$84.90 20 $1,698.00

46Aggregate, Gravel, Graded Gravel, includes materials, equipment and labor to transport and place. Includes washed and unwashed gravel.

Cubic yard

$35.73 20 $714.60

1045Dimension Lumber, untreated Untreated dimension lumber with nominal thickness equal or less than 2". Includes lumber and fasteners.

Board Foot

$0.75 2000 $1,500.00

1496Block, pre-cast concrete, modular

Pre-cast concrete blocks, typically 2ft x 2ft x 6ft , includes installation and delivery.

Cubic Yard

$104.04 18 $1,872.72

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

578 - Stream Crossing (Bridge with a span of less than or equal to 14 feet) - Page 1 of 1

FY2015 - Compiled 10/27/2014

Page 6: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #6 - Bridge with cast in place abutments, span > 14 feet

Scenario Description:Install a bridge to allow stream flows to cross under access road or animal trail. Bridge opening determined by sizing for storm event dictated in standard. Scenario includes dewatering, abutments, girders, decking. Work consists of site preparation, dewatering, acquiring and installing abuttments, girders, decking with necessary hardware, backfilling abuttments, and armoring with geotextile and riprap. Riprap and geotextile are used to stabilize and protect abutments as needed. Scenario based on cast in place concrete abutments, steel girders, and timber deck. Travel surface shall be wooden deck surface. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Span is greater than 14 feet. Load is H-20. Width is 15 feet including curbs. Abutment height as needed from design. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Linear feet of bridge deck

Scenario Typical Size: 30

Scenario Unit: Linear Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$73,585.50 Scenario Cost/Unit: $2,452.85

Cost Details (by category):

Equipment/Installation

926Backhoe, 80 HP Wheel mounted backhoe excavator with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $57.52 40 $2,300.80

38Concrete, CIP, formed reinforced

Steel reinforced concrete formed and cast-in-placed in formed structures such as walls or suspended slabs by chute placement. Typical strength is 3000 to 4000 psi. Includes materials, labor and equipment to transport, place and finish.

Cubic yard

$499.74 32 $15,991.68

933Skidsteer, 80 HP Skidsteer loader with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $44.33 40 $1,773.20

932Hydraulic Excavator, 2 CY Track mounted hydraulic excavator with bucket capacity range of 1.5 to 2.5 CY. Equipment and power unit costs. Labor not included.

Hour $195.84 60 $11,750.40

1211Truck, Concrete Pump Concrete pump, normally truck mounted. Use this item in association with other concrete components when job requires placement by other than normal chutes. Include drive and setup time in quantity; therefore, do not include mobilization. Includes equi

Hour $192.58 8 $1,540.64

1400Truck, dump, 18 CY Dump truck for moving bulk material. Typically capacity is 25 ton or 18 cubic yards. Includes equipment only.

Hour $124.54 40 $4,981.60

Labor

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 60 $1,468.80

235Specialist Labor Labor requiring a specialized skill set: Includes Agronomists, Foresters, Biologists, etc. to provide additional technical information during the planning and implementation of the practice. Does not include NRCS or TSP services.

Hour $101.60 120 $12,192.00

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 140 $4,716.60

578 - Stream Crossing (Bridge with cast in place abutments, span > 14 feet) - Page 1 of 2

FY2015 - Compiled 10/27/2014

Page 7: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Labor

230Skilled Labor Labor requiring a high level skill set: Includes carpenters, welders, electricians, conservation professionals involved with data collection, monitoring, and or record keeping, etc.

Hour $39.49 40 $1,579.60

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 40 $1,632.80

Materials

1599Epoxy anchor Galvanized bolts anchored into concrete or stone using epoxy adhesive. Includes materials and labor to drill and install.

Each $18.73 12 $224.76

1044Dimension Lumber, Treated Treated dimension lumber with nominal thickness equal or less than 2". Includes lumber and fasteners

Board Foot

$0.85 2500 $2,125.00

44Rock Riprap, Placed with geotextile

Rock Riprap, placed with geotextile, includes materials, equipment and labor to transport and place

Cubic yard

$84.90 40 $3,396.00

2166Galvanized Bolts, large 5/8" x 12" galvanized timber bolts. Materials only. Each $4.51 24 $108.24

1779Steel, structural steel members Structural steel, includes materials and fabrication. Pound $1.04 5360 $5,574.40

2140Pipe, PE, 4", DR 9, perforated Materials: -4" - Perforated PE- 160 psi - ASTM D3035 DR 9 Foot $11.68 60 $700.80

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 2 $525.28

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 2 $1,002.90

578 - Stream Crossing (Bridge with cast in place abutments, span > 14 feet) - Page 2 of 2

FY2015 - Compiled 10/27/2014

Page 8: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #7 - Bridge with precast abutments, span > 14 feet

Scenario Description:Install a bridge to allow stream flows to cross under access road or animal trail. Bridge opening determined by sizing for storm event dictated in standard. Scenario includes dewatering, abutments, girders, decking. Work consists of site preparation, dewatering, acquiring and installing abuttments, girders, decking with necessary hardware, backfilling abuttments, and armoring with geotextile and riprap. Riprap and geotextile are used to stabilize and protect abutments as needed. Scenario based on precast concrete abutments, steel girders, and timber deck. Travel surface shall be wooden deck surface. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Span is greater than 14 feet. Load is H-20. Width is 15 feet including curbs. Abutment height as needed from design. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Linear feet of bridge deck

Scenario Typical Size: 30

Scenario Unit: Linear Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$58,306.38 Scenario Cost/Unit: $1,943.55

Cost Details (by category):

Equipment/Installation

1400Truck, dump, 18 CY Dump truck for moving bulk material. Typically capacity is 25 ton or 18 cubic yards. Includes equipment only.

Hour $124.54 40 $4,981.60

933Skidsteer, 80 HP Skidsteer loader with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $44.33 40 $1,773.20

932Hydraulic Excavator, 2 CY Track mounted hydraulic excavator with bucket capacity range of 1.5 to 2.5 CY. Equipment and power unit costs. Labor not included.

Hour $195.84 60 $11,750.40

926Backhoe, 80 HP Wheel mounted backhoe excavator with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $57.52 40 $2,300.80

Labor

235Specialist Labor Labor requiring a specialized skill set: Includes Agronomists, Foresters, Biologists, etc. to provide additional technical information during the planning and implementation of the practice. Does not include NRCS or TSP services.

Hour $101.60 120 $12,192.00

230Skilled Labor Labor requiring a high level skill set: Includes carpenters, welders, electricians, conservation professionals involved with data collection, monitoring, and or record keeping, etc.

Hour $39.49 40 $1,579.60

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 40 $1,632.80

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 140 $4,716.60

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 60 $1,468.80

Materials

578 - Stream Crossing (Bridge with precast abutments, span > 14 feet) - Page 1 of 2

FY2015 - Compiled 10/27/2014

Page 9: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Materials

1836Footing, concrete, precast Precast spread footing with stemwall, T-shaped, with channel built to accept arched culvert leg. Includes materials only.

Foot $56.33 40 $2,253.20

1044Dimension Lumber, Treated Treated dimension lumber with nominal thickness equal or less than 2". Includes lumber and fasteners

Board Foot

$0.85 2500 $2,125.00

44Rock Riprap, Placed with geotextile

Rock Riprap, placed with geotextile, includes materials, equipment and labor to transport and place

Cubic yard

$84.90 40 $3,396.00

1779Steel, structural steel members Structural steel, includes materials and fabrication. Pound $1.04 5360 $5,574.40

2140Pipe, PE, 4", DR 9, perforated Materials: -4" - Perforated PE- 160 psi - ASTM D3035 DR 9 Foot $11.68 60 $700.80

1599Epoxy anchor Galvanized bolts anchored into concrete or stone using epoxy adhesive. Includes materials and labor to drill and install.

Each $18.73 12 $224.76

2166Galvanized Bolts, large 5/8" x 12" galvanized timber bolts. Materials only. Each $4.51 24 $108.24

Mobilization

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 2 $1,002.90

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 2 $525.28

578 - Stream Crossing (Bridge with precast abutments, span > 14 feet) - Page 2 of 2

FY2015 - Compiled 10/27/2014

Page 10: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #8 - Bridge, Prefabricated for Stream Crossing

Scenario Description:Install a bridge to allow stream flows to cross under access road or animal trail. Bridge opening determined by sizing for storm event dictated in standard. Scenario includes dewatering, abutments, girders, decking installed as a prefabricated unit. Work consists of site preparation, dewatering, acquiring and installing the prefabricated unit with necessary hardware, backfilling abuttments, and armoring with geotextile and riprap. Riprap and geotextile are used to stabilize and protect abutments as needed. Scenario based on prefabricated bridge structure. Travel surface shall be part of the prefabricated bridge structure. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Load is H-20. Width is 15 feet including curbs. Abutment height as needed from design. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Linear feet of bridge deck

Scenario Typical Size: 30

Scenario Unit: Linear Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$72,793.37 Scenario Cost/Unit: $2,426.45

Cost Details (by category):

Equipment/Installation

1400Truck, dump, 18 CY Dump truck for moving bulk material. Typically capacity is 25 ton or 18 cubic yards. Includes equipment only.

Hour $124.54 10 $1,245.40

38Concrete, CIP, formed reinforced

Steel reinforced concrete formed and cast-in-placed in formed structures such as walls or suspended slabs by chute placement. Typical strength is 3000 to 4000 psi. Includes materials, labor and equipment to transport, place and finish.

Cubic yard

$499.74 18 $8,995.32

926Backhoe, 80 HP Wheel mounted backhoe excavator with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $57.52 40 $2,300.80

932Hydraulic Excavator, 2 CY Track mounted hydraulic excavator with bucket capacity range of 1.5 to 2.5 CY. Equipment and power unit costs. Labor not included.

Hour $195.84 20 $3,916.80

969Water management, Flooding & dewatering

Includes equipment, power unit and labor costs. Acre Foot $232.61 50 $11,630.50

Labor

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 80 $2,695.20

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 20 $816.40

235Specialist Labor Labor requiring a specialized skill set: Includes Agronomists, Foresters, Biologists, etc. to provide additional technical information during the planning and implementation of the practice. Does not include NRCS or TSP services.

Hour $101.60 80 $8,128.00

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 60 $1,468.80

578 - Stream Crossing (Bridge, Prefabricated for Stream Crossing) - Page 1 of 2

FY2015 - Compiled 10/27/2014

Page 11: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Labor

230Skilled Labor Labor requiring a high level skill set: Includes carpenters, welders, electricians, conservation professionals involved with data collection, monitoring, and or record keeping, etc.

Hour $39.49 34 $1,342.66

Materials

2193Bridge, steel or concrete, pre-Manufactured Bridge

A premanufactured steel or precast prestressed concrete bridge rated for an HS 25 highway loading. Typical width is 14', length is variable. Includes railing system. Includes materials and shipping only.

Square Foot

$63.04 450 $28,368.00

2165Painting, steel surface, Impermeable

Painting of steel surface with an impermeable coating. Includes materials and application

Square Foot

$0.89 1260 $1,121.40

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 1 $501.45

578 - Stream Crossing (Bridge, Prefabricated for Stream Crossing) - Page 2 of 2

FY2015 - Compiled 10/27/2014

Page 12: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #9 - Stream Simulation Culvert, with Headwalls

Scenario Description:Install a stream simulation culvert with a headwall where a particular culvert geometry is needed even though aquatic organism passage may not be the primary concern. For culverts less than 30" use Practice Standard 587 Structure for Water Control. Work includes dewatering, site preparation and removing any old crossing, acquiring and installing culvert pipe with gravel bedding and fill (compacted), and building headwalls. If a different travel surface is needed, refer to another appropriate standard for the surfacing. Pipe is 20 feet long and headwalls are included. Typical arch size may be 10' X 5'3" X 20' arch with 2'X3' precast footings Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic. Use (587) Structure for Water Control instead, for ditch cross culverts and other intermittent flows and culverts less than 30" in diameter.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access road and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Length of Multi-plate arch or box

Scenario Typical Size: 20

Scenario Unit: Linear Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$50,363.04 Scenario Cost/Unit: $2,518.15

Cost Details (by category):

Equipment/Installation

933Skidsteer, 80 HP Skidsteer loader with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $44.33 40 $1,773.20

1400Truck, dump, 18 CY Dump truck for moving bulk material. Typically capacity is 25 ton or 18 cubic yards. Includes equipment only.

Hour $124.54 40 $4,981.60

969Water management, Flooding & dewatering

Includes equipment, power unit and labor costs. Acre Foot $232.61 25 $5,815.25

932Hydraulic Excavator, 2 CY Track mounted hydraulic excavator with bucket capacity range of 1.5 to 2.5 CY. Equipment and power unit costs. Labor not included.

Hour $195.84 60 $11,750.40

42Geotextile, woven Woven Geotextile Fabric. Includes materials, equipment and labor

Square Yard

$2.51 100 $251.00

Labor

230Skilled Labor Labor requiring a high level skill set: Includes carpenters, welders, electricians, conservation professionals involved with data collection, monitoring, and or record keeping, etc.

Hour $39.49 40 $1,579.60

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 60 $1,468.80

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 100 $3,369.00

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 40 $1,632.80

Materials

1979Culvert, Multi-Plate arch Multi-plate arch culvert, typically 7 Gauge corrugated plate. Includes metal arch materials only, does not include footings.

Pound $1.40 8000 $11,200.00

578 - Stream Crossing (Stream Simulation Culvert, with Headwalls) - Page 1 of 2

FY2015 - Compiled 10/27/2014

Page 13: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Materials

1842Geocell, 6" 6-inch thick cellular confinement system, three-dimensional, expandable panels made from high-density polyethylene (HDPE), polyester or another polymer material. Includes materials, labor and equipment for the geocell only, does not include backfill.

Square Yard

$37.20 45 $1,674.00

1834Aggregate, river rock Well graded, rounded mineral substrates derived from local riverine settings. Includes materials and local delivery

Ton $29.97 45 $1,348.65

1836Footing, concrete, precast Precast spread footing with stemwall, T-shaped, with channel built to accept arched culvert leg. Includes materials only.

Foot $56.33 40 $2,253.20

Mobilization

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 2 $1,002.90

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

578 - Stream Crossing (Stream Simulation Culvert, with Headwalls) - Page 2 of 2

FY2015 - Compiled 10/27/2014

Page 14: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #10 - Stream Simulation Culvert, without Headwalls

Scenario Description:Install a stream simulation culvert without a headwall where a particular culvert geometry is needed even though aquatic organism passage may not be the primary concern. For culverts less than 30" use Practice Standard 587 Structure for Water Control. Work includes dewatering, site preparation and removing any old crossing, acquiring and installing culvert pipe with gravel bedding and fill (compacted). If a different travel surface is needed, refer to another appropriate standard for the surfacing. Pipe is 40 feet long and therefore headwalls are not included. Typical arch size may be 10' X 5'3" X 40' arch with 2'X3' precast footings Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic. Use (587) Structure for Water Control instead, for ditch cross culverts and other intermittent flows and culverts less than 30" in diameter.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access road and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Length of Multi-plate arch or box

Scenario Typical Size: 40

Scenario Unit: Linear Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$59,389.89 Scenario Cost/Unit: $1,484.75

Cost Details (by category):

Equipment/Installation

1400Truck, dump, 18 CY Dump truck for moving bulk material. Typically capacity is 25 ton or 18 cubic yards. Includes equipment only.

Hour $124.54 40 $4,981.60

969Water management, Flooding & dewatering

Includes equipment, power unit and labor costs. Acre Foot $232.61 25 $5,815.25

933Skidsteer, 80 HP Skidsteer loader with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $44.33 40 $1,773.20

932Hydraulic Excavator, 2 CY Track mounted hydraulic excavator with bucket capacity range of 1.5 to 2.5 CY. Equipment and power unit costs. Labor not included.

Hour $195.84 60 $11,750.40

42Geotextile, woven Woven Geotextile Fabric. Includes materials, equipment and labor

Square Yard

$2.51 200 $502.00

Labor

230Skilled Labor Labor requiring a high level skill set: Includes carpenters, welders, electricians, conservation professionals involved with data collection, monitoring, and or record keeping, etc.

Hour $39.49 40 $1,579.60

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 40 $1,632.80

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 60 $1,468.80

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 100 $3,369.00

Materials

1979Culvert, Multi-Plate arch Multi-plate arch culvert, typically 7 Gauge corrugated plate. Includes metal arch materials only, does not include footings.

Pound $1.40 10500 $14,700.00

1834Aggregate, river rock Well graded, rounded mineral substrates derived from local riverine settings. Includes materials and local delivery

Ton $29.97 90 $2,697.30

578 - Stream Crossing (Stream Simulation Culvert, without Headwalls) - Page 1 of 2

FY2015 - Compiled 10/27/2014

Page 15: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Materials

1842Geocell, 6" 6-inch thick cellular confinement system, three-dimensional, expandable panels made from high-density polyethylene (HDPE), polyester or another polymer material. Includes materials, labor and equipment for the geocell only, does not include backfill.

Square Yard

$37.20 90 $3,348.00

1836Footing, concrete, precast Precast spread footing with stemwall, T-shaped, with channel built to accept arched culvert leg. Includes materials only.

Foot $56.33 80 $4,506.40

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 2 $1,002.90

578 - Stream Crossing (Stream Simulation Culvert, without Headwalls) - Page 2 of 2

FY2015 - Compiled 10/27/2014

Page 16: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #11 - Concrete Box Culvert

Scenario Description:Install a concrete box culvertwhere a particular culvert geometry is needed even though aquatic organism passage may not be the primary concern. For culverts less than 30" use Practice Standard 587 Structure for Water Control. Work includes dewatering, site preparation and removing any old crossing, acquiring and installing concrete box culvert with gravel bedding and fill (compacted). If a different travel surface is needed, refer to another appropriate standard for the surfacing. Concrete box culvert is a 6' by 8' box and is 20 feet long.Headwalls are not included. Typical concrete box culvert size is 6' by 8' by 20'. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic. Use (587) Structure for Water Control instead, for ditch cross culverts and other intermittent flows and culverts less than 30" in diameter.

Before Situation:Water flow could not cross access road or trail without erosion; or access road or trail could not cross channel.

After Situation:Access road and waterflow are able to cross each other in a stable manner.Stream flow is not impeded and a stable base exists for equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Length of concrete box culvert

Scenario Typical Size: 20

Scenario Unit: Linear Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$43,838.44 Scenario Cost/Unit: $2,191.92

Cost Details (by category):

Equipment/Installation

1400Truck, dump, 18 CY Dump truck for moving bulk material. Typically capacity is 25 ton or 18 cubic yards. Includes equipment only.

Hour $124.54 40 $4,981.60

42Geotextile, woven Woven Geotextile Fabric. Includes materials, equipment and labor

Square Yard

$2.51 100 $251.00

932Hydraulic Excavator, 2 CY Track mounted hydraulic excavator with bucket capacity range of 1.5 to 2.5 CY. Equipment and power unit costs. Labor not included.

Hour $195.84 60 $11,750.40

969Water management, Flooding & dewatering

Includes equipment, power unit and labor costs. Acre Foot $232.61 25 $5,815.25

933Skidsteer, 80 HP Skidsteer loader with horsepower range of 60 to 90. Equipment and power unit costs. Labor not included.

Hour $44.33 40 $1,773.20

Labor

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 60 $1,468.80

230Skilled Labor Labor requiring a high level skill set: Includes carpenters, welders, electricians, conservation professionals involved with data collection, monitoring, and or record keeping, etc.

Hour $39.49 40 $1,579.60

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 100 $3,369.00

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 40 $1,632.80

Materials

2175Culvert, box, 6' x 8' Precast concrete box culvert, 6'X8'. Typically in 4' sections. Materials only.

Foot $346.43 20 $6,928.60

578 - Stream Crossing (Concrete Box Culvert) - Page 1 of 2

FY2015 - Compiled 10/27/2014

Page 17: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Materials

1842Geocell, 6" 6-inch thick cellular confinement system, three-dimensional, expandable panels made from high-density polyethylene (HDPE), polyester or another polymer material. Includes materials, labor and equipment for the geocell only, does not include backfill.

Square Yard

$37.20 45 $1,674.00

1834Aggregate, river rock Well graded, rounded mineral substrates derived from local riverine settings. Includes materials and local delivery

Ton $29.97 45 $1,348.65

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

1140Mobilization, large equipment Equipment >150HP or typical weights greater than 30,000 pounds or loads requiring over width or over length permits.

Each $501.45 2 $1,002.90

578 - Stream Crossing (Concrete Box Culvert) - Page 2 of 2

FY2015 - Compiled 10/27/2014

Page 18: Practice: 578 - Stream Crossing Scenario: #1 - Culvert ...Practice: 578 - Stream Crossing Scenario: #1 - Culvert Installation, >30 inch diameter Scenario Description: Install a new

USDA-Natural Resources Conservation Service Connecticut

Scenario Cost:

Practice: 578 - Stream Crossing

Scenario: #12 - Bridge, Light Weight Timber

Scenario Description:Light Weight Timber bridge is constructed of 6" x 10" timbers side by side bolted together by ASTM A307 Bolts to provide a deck for animal traffic and light weight equipment such as ATV's. Deck is fabricated into 3 - 4'x20' panels which are moved into position by an excavator. Bridge is placed accross a narrow incised stream where installing a ford or other type of crossing is not practical. Bridge deck is mounted on precast concrete blocks which are buried 1/2 to 3/4 into the ground. Approaches to both ends of the bridge are graded to meet the contour of the existing or proposed animal trail. Bridge opening determined by sizing for storm event dictated in standard. Streambanks and bed at crossing location are generally stable. Work consists of furnishing and installing four precast blocks to mount bridge, furnishing 24 - 6" x 10" timbers and assembling the bridge on site, necessary hardware, and lifting bridge panels into place by hydraulic excavator. Span is less than 14 feet. Bridge is intended for cattle passage and not for heavy weight equpment. Bridge width is 12 feet. Use (396) Aquatic Organism Passage instead, when the primary intent is biological concerns, not hydrologic.

Before Situation:Access to pasture is not possible without causing excessive erosion and other water quality water concerns.

After Situation:Access and waterflow are able to cross each other in a stable manner. Stream flow is not impeded and a stable base exists for light weight equipment, people and/or animals to cross. Associated practices could be (342) Critical Area Planting, (560) Access Road, (575) Animal Trails and Walkways, (566) Recreational Trails and Walkways, (500) Obstruction Removal, or (584) Channel Stabilization.

Scenario Feature Measure: Area of Bridge Deck in Square Feet (12' wide x 20' long)

Scenario Typical Size: 240

Scenario Unit: Square Foot

IDComponent Name CostQuantityPrice ($/unit)UnitComponent Description

$7,783.90 Scenario Cost/Unit: $32.43

Cost Details (by category):

Equipment/Installation

931Hydraulic Excavator, 1 CY Track mounted hydraulic excavator with bucket capacity range of 0.8 to 1.5 CY. Equipment and power unit costs. Labor not included.

Hour $117.15 8 $937.20

Labor

234Supervisor or Manager Labor involving supervision or management activities. Includes crew supervisors, foremen and farm/ranch managers time required for adopting new technology, etc.

Hour $40.82 2 $81.64

231General Labor Labor performed using basic tools such as power tool, shovels, and other tools that do not require extensive training. Ex. pipe layer, herder, concrete placement, materials spreader, flagger, etc.

Hour $24.48 16 $391.68

233Equipment Operators, Heavy Includes: Cranes, Hydraulic Excavators >=50 HP, Dozers, Paving Machines, Rock Trenchers, Trenchers >=12”, Dump Trucks, Ag Equipment >=150 HP, Scrapers, Water Wagons.

Hour $33.69 8 $269.52

Materials

2528Bolt, All Thread Rod, ASTM A307, 1" Dia. x 4'

Hot Dipped Galvanized All Thread Rod, ASTM A307, 1" Dia. X 4' Long with two - nuts and flat washers. Includes materials and shipping only.

Each $100.98 18 $1,817.64

1623Lumber, planks, posts and timbers, untreated

Untreated dimension lumber with nominal thickness greater than 2". Includes lumber and fasteners. Does not include labor.

Board Foot

$1.46 2400 $3,504.00

1496Block, pre-cast concrete, modular

Pre-cast concrete blocks, typically 2ft x 2ft x 6ft , includes installation and delivery.

Cubic Yard

$104.04 3.6 $374.54

Mobilization

1139Mobilization, medium equipment

Equipment with 70-150 HP or typical weights between 14,000 and 30,000 pounds.

Each $262.64 1 $262.64

1137Mobilization, very small equipment

Equipment that is small enough to be transported by a pick-up truck with typical weights less than 3,500 pounds. Can be multiple pieces of equipment if all hauled simultaneously.

Each $72.52 2 $145.04

578 - Stream Crossing (Bridge, Light Weight Timber) - Page 1 of 1