practical hydraulics on a large wastewater treatment works

12
Practical Hydraulics on a Large Wastewater Treatment Works Rob Wilson Flow distribution chambers with weirs Flow distribution without weirs Manifold distribution Flow distribution to inlet screens Examples

Upload: ledung

Post on 05-Jan-2017

222 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Practical Hydraulics on a Large Wastewater Treatment Works

Practical Hydraulics on a Large Wastewater Treatment WorksRob Wilson

Flow distribution chambers with weirs

Flow distribution without weirs

Manifold distribution

Flow distribution to inlet screens

Examples

Page 2: Practical Hydraulics on a Large Wastewater Treatment Works

Flow distribution chamber with weirs

2 m diameter pipe – velocity requirement of 1.1 m/s

6 m deep chamber –6 degree jet angle

Large chamber width to ensure maximum average velocity of 0.35 m/s

Flow distribution chamber with weirsConstruction Photograph

Page 3: Practical Hydraulics on a Large Wastewater Treatment Works

Flow distribution chamber with weirsConditions at the weirs

Flow distribution without weirs

Flow splitter

Page 4: Practical Hydraulics on a Large Wastewater Treatment Works

Flow distribution without weirs Flow splitter

Flow distribution without weirs Flow splitter

Equal flow split in each feed channel verified by downstream flumes

Flow splitter is over to one side

Page 5: Practical Hydraulics on a Large Wastewater Treatment Works

Flow Distribution Without WeirsInvestigation

Flow splitter

Unequal outlet weir levels on the tanks

Partial blockage in the feed channel

Partial blockage in the feed pipes

Difference in geometry e.g. channel widths

Flow Distribution Without WeirsInvestigation

Detailed level survey showed 30 mm discrepancy in weir levels between PST 7 and PST 5, 6 & 8

Unequal flow distribution is more pronounced at low flows than at high flows

Flow Split to PST 5-8 Comparison Plot

0

5

10

15

20

25

30

35

5 6 7 8

Primary Settlment Tank

Flow

to P

ST

as a

per

cent

age

of th

e to

tal f

low

Dry Weather FlowPeak FlowIntermediateAverage Day Flow

Page 6: Practical Hydraulics on a Large Wastewater Treatment Works

Flow Distribution Without WeirsInvestigation

Velocity meter used to check flow rate from each primary tank

Flow Distribution Without WeirsInvestigation - Further work

Automate the flow splitter on flow measurement

Monitor the position of the flow meter

Advise Process Controller that PST 7 will be treating approximately 9% less flow than the other tanks during dry weather 6% less in average day conditions

Only real solution is to adjust the weirs

Page 7: Practical Hydraulics on a Large Wastewater Treatment Works

Manifold Distribution

Electromagnetic flow meter

Plug valve

Manifold DistributionCommissioning Issues

Adjustment of one valve to achieve the target flow (equal split)produced unequal distribution to the other lanes

5 Operators with radios to coordinate

Approximately equal flow distribution was achieved at a given total flow rate and with all 12 lanes operating

Achieving a equal flow distribution at a lower total flow rate or with lanes out for maintenance is not practical

Page 8: Practical Hydraulics on a Large Wastewater Treatment Works

Manifold DistributionAlternatives

Ideally have a distribution chamber with a weir (space, cost)

Physical modelling or CFD to size manifold pipework (valves only used for fine tuning)

Automate the valves to control using the flow measurement.

Screw the valves right down to minimise the velocity in the manifold – issues with the pump

Distribution to inlet screens

Low Flows Storm Conditions

Page 9: Practical Hydraulics on a Large Wastewater Treatment Works

Raise Inlet Overflow and Coping Levels

Increase Flooding in the Network

Storage Required

Network Pumping

Modifications to Pipe Bridges

Inlet PS

Site is a complete gravity works

Pump up to 4500 l/s - OPEX

Carbon footprint

Available space

Possible Solutions

Chosen Solution

New screen bay

Existing screen bay

Inflow from the catchment

Preferential feed to the existing bank of screens

Page 10: Practical Hydraulics on a Large Wastewater Treatment Works

Physical Modelling

Physical Modelling – Grit Settlement

Sediment Build Up

Page 11: Practical Hydraulics on a Large Wastewater Treatment Works

Engineering Success?

Positives

No more flooding

Can pass consented flow rate before spill

Greater flexibility/redundancy with screens

No increase in network flooding or expensive modifications to the network

Gravity solution

Negatives

Long term issues with grit i.e. grit in the primary sludges, wear on mechanical equipment, reduction in hydraulic capacity of inlet works

Further work with Operations to resolve the grit issue

Summary

Variety of methods for distributing flow on a large WwTW

When it comes to flow distribution simpler is usually better –passive control over active

Be aware of the impact of hydraulic design on other engineering disciplines

When selecting a solution you may not be able to satisfy every design requirement but the affect of not meeting that requirement can be far reaching

Page 12: Practical Hydraulics on a Large Wastewater Treatment Works

Questions