Funding Received under North Dakota Century Code Section

57-51-15

3/7/2014 1

Page 2: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

The funds received under § 57-51-15 have been used to finance infrastructure related to growth.

None of these funds have been deployed to flood recovery.

3/7/2014 2

Page 3: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

Hub City Funding from Three Sources in Gross Production 5% Tax Distribution: ◦ 1. Mining Employment Formula

◦ 2. Energy Impact Grant Funding Infrastructure

Airport

◦ 3. Production Formula

3/7/2014 3

Page 4: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

3/7/2014 4

Page 5: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

Legislative Estimated Amount = $1.5 million per fiscal year ◦ Received through February - $1.125 million

Formula base on percent of mining employment as determined by Job Service

Sanitary Lift Station Upgrades – Six Upgraded ◦ Lift Stations at Capacity Because of Minot’s Growth

◦ Total Project Cost - $11,949,916

◦ Provides added capacity until new trunk sewer line is constructed (total estimated cost $30 million)

3/7/2014 5

Page 6: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

3/7/2014 6

Page 7: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

Amount Received - $5 million (Minot is capped at this amount for the biennium)

Southwest Sewer Improvements Phase I ◦ Installation of 24” Sewer Main

◦ Total Project Cost - $6,400,900

3/7/2014 7

Page 8: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

Amount Received - $21,218,395

Total Project Costs - $100,075,161 ◦ Terminal $18,500,000

◦ SRE Building 163,395

◦ Furniture 100,000

◦ Terminal Apron 805,000

◦ Access Roads & Parking 1,650,000

$21,218,395

3/7/2014 8

Page 9: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

3/7/2014 9

Page 10: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

Legislative Estimate Amount to be Received - $4.570 million

Amount Received To-date - $1,719,603.87

Total Project Costs – ◦ BNSF Sewer Relocation $1,670,597

◦ Puppy Dog Sewer Phase IV $3,372,610

3/7/2014 10

Page 11: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

2014 Capital Improvements Plan ◦ Water & Sewer $ 32,824,408

◦ Street Improvements $ 21,787,346

◦ Airport $ 43,844,118

◦ Fire, Landfill, Cemetery, Other $ 29,921,471

$128,377,343

3/7/2014 11

Page 12: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

Servicing a Population in excess of 50,000

Water & Sewer Rates1 ◦ Minot $66.73 ◦ Fargo $56.05 ◦ Mandan $55.09 ◦ Dickinson$54.00 ◦ Bismarck $47.96 ◦ Williston $33.47

South Minot – Retail, Residential, and New Hospital

North Minot – Retail, Residential, New School

Regional Service Area

City Goals: Keep Property Tax Reasonable, Debt Load Manageable, and Water and Sewer Rates Affordable

1SOURCE: AE2S Annual Water Rate Study 2013 – For Cities with population over 5,000

3/7/2014 12

Page 13: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

Current debt bonded long-term for 10, 15, and 20 years

3/7/2014 13

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

$1,800

$2,000

2008 2009 2010 2011 2012 2013

Total Debt Per Capita

Total Debt Per Capita

Page 14: PowerPoint Presentation - Minot... · 2017. 11. 7. · Title: PowerPoint Presentation Author: Cindy Hemphill Created Date: 3/14/2014 2:11:44 PM

The funds received under § 57-51-15 have been used to finance infrastructure related to growth.

None of these funds have been deployed to flood recovery.

3/7/2014 14