powerpoint presentation - aogaogexpo.com.au/wp-content/uploads/2015/03/polarled-36-optima-cla… ·...

10
Copyright © 2013 Freudenberg Oil & Gas Technologies AOG-2015 POLARLED 36” OPTIMA CLAMP CONNECTOR CASE STUDY Nicholas Long FO&GT Subsea Technical Authority Ståle Størkersen Statoil ASA Advisor Pipeline Technology NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Upload: nguyenthu

Post on 06-Feb-2018

222 views

Category:

Documents


2 download

TRANSCRIPT

Copyright © 2013 Freudenberg Oil & Gas Technologies

AOG-2015

POLARLED 36”

OPTIMA CLAMP

CONNECTOR CASE

STUDY

Nicholas Long

FO&GT

Subsea Technical Authority

Ståle Størkersen

Statoil ASA

Advisor Pipeline Technology

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 2Copyright © 2013 Freudenberg Oil & Gas Technologies

POLARLED PROJECT:-

The Polarled pipeline runs from Nyhamna Gas Terminal, some 500km north into

the Norwegian Arctic Circle and terminates at a PLEM in 1,265m water depth near

to the Aasta Hansteen SPAR Platform.

The pipeline crosses many difficult terrains subsea including steep slopes and

canyons.

The project also has a design life of 50 years, this creates

various design drivers that add additional requirements.

This presentation discusses the following subjects:-

• Conventional clamp design(4)

• Design drivers for large bore clamp connectors(5)

• Large bore clamp connector design(6)

• State of technology for large bore clamp connectors(7)

• Large bore clamp connector operating & installation philosophy(8&9).(?) = References to section in paper

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 3Copyright © 2013 Freudenberg Oil & Gas Technologies

Conventional Clamp Connector Design:-

Clamp connectors typically have the same features:-

i. Three clamp segments.

ii. Single leadscrew operation.

iii. Driven from API / ISO Drive Bucket.

There are some significant issues when increasing

size with conventional clamp connector design:-

i. Scaling from smaller sizes is not practical.

ii. How the clamp segments engage with the hubs, especially with pull-

in (misalignment) applications.

iii. Single leadscrew and middle clamp segment movement.

iv. Leadscrew design and load transfer.

v. Application of torque to close clamp.

vi. Sealring energisation load and section size.

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 4Copyright © 2013 Freudenberg Oil & Gas Technologies

Design Drivers For Large Bore Clamp Connectors:-

The design drivers for large bore clamps are:-

i. Evening out clamping load from leadscrew.

ii. Reducing relative clamp segment

movement.

iii. Choice of leadscrew and trunnion thread

form and material.

iv. Thread coefficient of friction.

v. Torque application method into leadscrew.

vi. Slender section sealring to reduce loads

and size implications.

A solution was needed that would take each

of design drivers into account to address the

issues with conventional clamp connector design.

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 5Copyright © 2013 Freudenberg Oil & Gas Technologies

Large Bore Clamp Connector Design:-

A design solution for the connector was created to give

the best solution possible:-

i. Change single leadscrew to twin leadscrew.

ii. Change from 3 to 4 clamp segments.

iii. Fully assessed dedicated design (no scaling).

iv. Robust leadscrew thread form was selected.

v. High strength CRA leadscrew & trunnions.

vi. Leadscrew torque application and direction of rotation.

vii. Leadscrew lubrication and coefficient of friction.

To the right is a picture of the pre-paint assembled

connector, which shows the twin leadscrew, four clamp

segment design, that was a result of the changes listed

above.

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 6Copyright © 2013 Freudenberg Oil & Gas Technologies

State Of The Technology For Large Bore Clamp Connectors:-

The Optima Connector for the Polarled Project was subjected to the

following assessments and testing:-

i. DMFECA according to DNV RP-A203.

ii. Technology Readiness Level (TRL) &

Categorization (TRC) Assessments.

iii. Materials Criticality Assessment.

iv. API-6A Annex F / ISO-10423 PR2 Testing(-20°C to +60°C, 0psig to 3,380psig).

v. Total of 48off bend test cycles (60% SMYS pipe yield in 3 orientations).

vi. 8off connector make & break cycles.

vii. Reverse integrity test of sealring to leak point.

The Optima connector performed perfectly under

each of the tests. The leadscrew and trunnions had

no visible degradation to the thread profile.

The 36” Optima Clamp Connector for Polarled has achieved TRL5 “Full scale

technology built and integrated into the environment where it is intended to

operate, with full interface and functionality tests”. TRL6 will be achieved in 2015.

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 7Copyright © 2013 Freudenberg Oil & Gas Technologies

Large Bore Clamp Connector Operating & Installation Philosophy:-

The biggest benefit to the operating philosophy is the design change to twin

leadscrew with 4 clamp segments. With two leadscrews, they can rotate in

opposite directions. This counter rotating philosophy offers the following benefits:-

i. Major reduction in clamp size and weight.

ii. Closed loop torque reaction.

iii. Elimination of torque reaction side loads.

iv. Reduction in structural plate box size on

clamp.

v. Minimal porch / support structure.

vi. ‘Floating’ clamp for ease of maintenance

(retrieval).

vii. Reduced timescales during subsea ops.

Due to the ‘floating’ clamp design, this allows the clamp

to move back exposing the hub face, offering:-

i. Visual inspection by ROV for hub alignment.

ii. Improved seal face cleaning and sealring

removal / replacement operations.

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 8Copyright © 2013 Freudenberg Oil & Gas Technologies

Large Bore Clamp Connector Operating & Installation Philosophy:-

During installation, the following will apply:-

i. Optima connector locked onto PLEM

ii. Tooling located in tool basket.

Once the PLEM has been installed on its structural

skid base, the following operations can happen:-

i. Optima Connector opened & moved back.

ii. Hub cleaned and Duoseal installed.

iii. PLEM is moved into place to close

hubs.

iv. Optima connector moved forward.

v. Optima connector closed.

vi. Backseal test completed.

vii. Tooling returned to tool basket.

In emergency operations, the Optima connector

can be retrieved on its own.

Tooling uses fixed features on Optima.

Subsea Division36’’ Optima Clamp Connector Equipment

Key:-

1 = 36” Optima Clamp

2 = Male Hub & Duoseal Seal Ring

3 = Female Hub

4 = Guide Structure

5 = Axial Shift Tool

6 = Twin Torque Tool

7 = Seal Removal / Seal Face Cleaning Tool

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 9Copyright © 2013 Freudenberg Oil & Gas Technologies

Closing Remarks:-

With trend towards larger export pipe diameters and longer service life projects,

reducing equipment size can offer significant benefits. By incorporating the design

drivers previously mentioned, the following are some of the significant benefits:-

i. Weight reductions for equipment.

ii. Use of smaller installation vessels.

iii. Improved reliability & maintainability.

iv. Operational Speeds.

v. Predictable, reliable performance by a good qualification process.

With a reduction in the size and weight of the equipment and the other benefits

listed above, the overall ‘through life’ costs of the equipment are also reduced.

Acknowledgements:-

FO&GT would like to thank Statoil for their support / backing on the Polarled project

equipment and also their permission for, and co-authoring of this paper.

References:-SCC2014-DW-Conference Paper by David Winfield of FO&GT

VI-PT-12-038 - Optima Hub FEA & Testing For A694-F65 Through Hardenability by N Long & I Smyth of FO&GT.

VI-PT-14-095 – Qualification Procedure for Statoil Polarled Optima Connector Equipment.

13ABD71825 Rev. 0 – Optima Connector Type Approval Certificate from Bureau Veritas UK.

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT

Slide 10Copyright © 2013 Freudenberg Oil & Gas Technologies

Thank You For Attending.

Any Questions?

Subsea Division36’’ Optima Clamp Connector Equipment

NO RE-PUBLICATION / DISTRIBUTION IS ALLOWED UNLESS AUTHORISED BY FO&GT