An Overview of InControl
![Page 2: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/2.jpg)
� Established software company founded in 1985
�Focus on innovative project management solutions
�Tools for Project Teams
� Acquired by the WorleyParsons Group in 2001
�Australia’s largest Project Services Organisation
� InControl
�A mature product, based on sound PM practices
�Proven on thousands of projects worldwide
�Used by organisations and projects large and small
InControl and WorleyParsons
![Page 3: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/3.jpg)
3
Success of a Project depends on sound Project Management.
InControl can facilitate this through:
�Minimising the project control effort
�Increasing the accuracy of reporting
�Providing an assessment of final cost and schedule (forecast)
�Facilitating the collection of data for resource management
�Facilitating the management of changes to project scope
�Development and maintenance of ‘norms’ by collating data in a consistent manner
�Versatility – Can be used to manage Small/Medium/Large Projects
�Consistency – Promotes consistent Project Management across all projects
�Transparency - Provides comprehensive information on project status
InControl - Benefits
![Page 4: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/4.jpg)
4
Modular Approach
Estimating
& Proposal
Generator
Progress
Update
Module
Document
Control
Module
ProjectControl
Module
Variation
Control
Module
Primavera
Project Summary
Estimating
Financial
Procurement
Other Systems
Planning
Vendor
Data
Module
SPF / Encompass
![Page 5: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/5.jpg)
� Based on the principle of Control Account management:
● Work Breakdown Structure (WBS) Code
● Code of Account (COA)
● Activity Detail Code
� A project or activity is broken down into elements, defined in terms of:
Principle of Operation
– Resources (Revenue & Cost)
– Deliverables and Tasks
– Scope
– Inputs
� Control Accounts can define & control any aspect of the project.
� Control Accounts can be grouped, sorted and filtered using the Work
Breakdown Structure (WBS) as well as additional Report Grouping Codes.
![Page 6: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/6.jpg)
6
Project Control
![Page 7: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/7.jpg)
7
Project Control Module - PCM
� The Project Control Module is used for:
● Project Set-Up
● Access to all data
● Control functionality of other modules
� Import actual hours & costs from Oracle
� Interfaces with planning system (Primavera)
� Limited to use by Project Control personnel
� 3 flexible input screens
![Page 8: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/8.jpg)
Activity Details Screen
• Control Account Details
• Responsibility
• Schedule data
• Progress
• Forecast
![Page 9: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/9.jpg)
9
Resource Budget Screens for Labour and Non-Labour
• Current & Average Sell and Cost Rates
• Budget in terms of Manhours, Revenue and Cost
• Actuals Burned against each Budgeted Resource
• “To Complete and “At Complete”
![Page 10: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/10.jpg)
10
Deliverables
• Responsibility
• Schedule
• Progress Gates with Planned and Forecast Dates
![Page 11: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/11.jpg)
11
PCM- ReportsProductivity & Commitments
� Resource QTC
– Is calculated using the current budget and total to date figures for each Control Account. The Quantity to Complete (QTC) value is the value assigned based on a subjective review of the work to complete on the Control Account.
![Page 12: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/12.jpg)
12
PCM- ReportsProductivity & Commitments
� Resource Forecast 1 (Productivity)
– This calculates the forecast values based on the ‘Productivity’. This forecast assumes if you are tracking at a productivity of as shown in the product. column that you will continue to work at this productivity level for the remainder of the project.
![Page 13: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/13.jpg)
13
PCM- ReportsProductivity & Commitments
� Resource Forecast 2 (Bdgt-Earned)
– This forecast is calculated using a combination of the ‘Earned’ value and ‘Productivity’. The ’Final Forecast Cost’ is calculated on the assumption that productivity levels will be at ‘1’ for the remainder of the project. The ‘Earned’ valueis a calculation of ‘Physical % complete’ as a % of ‘Current Budget’.
![Page 14: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/14.jpg)
14
PCM – ReportsManhours Deliverable
� The Deliverable Manhour Details report provides information on each deliverable budget, forecast and progress.
● The report is grouped by Activity for the active project and is designed for in-house control and reporting of deliverable progress.
![Page 15: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/15.jpg)
15
PCM- ReportsEngineering Deliverable Status
� Provides a colour-coded visual representation of Planned, Forecast and
Achieved data for gated deliverables in any selected period. Can also show
Weightings and missing dates
![Page 16: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/16.jpg)
16
PCM – ReportsS Curve/ Histogram
� The Histogram and S-Curve reports provide visual representation of manpower budgets, forecasts, actuals and earned values including panned
cumulative spread of cost and hour expenditure.
– During project definition these reports in conjunction with the bar chart reports should be utilised to schedule work, during project execution they should be used for progress analysis and management reporting.
![Page 17: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/17.jpg)
17
PCM – Graphical Reports
![Page 18: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/18.jpg)
User Defined Reports
18
![Page 19: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/19.jpg)
Portfolio and Summary Reports
19
![Page 20: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/20.jpg)
20
Progress Update Module
![Page 21: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/21.jpg)
21
Progress Update Module - PUM
� The Progress Update Module:
● Records deliverable or task progress
● Collects forecast man-hours to completion
� Available to ALL users for ‘on-line’ updates
� Assigned delegate capability
� Allows users to generate deliverable control reports
� System allows remote access & updates
� Deliverables can be allocated to Work Packs
� Multiple Updates for similar gated deliverables
![Page 22: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/22.jpg)
22
Progress Update Module - PUM
Gates Sets can be applied per deliverable
Can update Multiple Deliverables with the same Gate Set
![Page 23: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/23.jpg)
23
Change Control
![Page 24: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/24.jpg)
24
Variation Control Module - VCM
The Variation Control Module:
� Integral with other InControl modules
� Generates change requests for approval by client
� Variations not client approved included as “Adjusted Budget” (ABQ)
� Manages Trends for inclusion in Forecast
� Allows multiple changes to a Control Account
� Pending change requests are included in quantity at completion
� Maintains variation control history
![Page 25: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/25.jpg)
25
VCM – ReportsChange Request
![Page 26: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/26.jpg)
26
Summary
� Control Account based
� Role Based
� Integrated modules
� Flexible
� Applied to any project function
� Allows remote access
� Promotes ownership
� Concept to completion
� Assists knowledge management
� Assists with making informed decisions
![Page 27: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/27.jpg)
27
Additional InControl Modules
� Contracts Control Module● Assists with the management and control of non-labour
commitments, contracts, costs and invoices from inception to completion of projects regardless of size.
� Project Summary Module● Allows access to ALL InControl reports, including a high
level summary report that can be generated for hours or costs.
● This report is generally used as the front page to summarise the project status when the InControl reports are forwarded to the client for review.
� Document Control Module● Tracking the status of deliverables and non-deliverables
from conception to completion. It produces reports and eleControl Accountonic transmittals and assists the Document Controller through timely and efficient execution of document management.
![Page 28: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/28.jpg)
28
Additional InControl Modules
� Vendor Data Module
● Designed to assist users with the management and control of project vendor data, that is, any data that forms part of an external Purchase Order or Contract which needs to be tracked. The VDM aids management by providing a controlled environment and a systematic approach to controlling vendor data.
� Phasing Module
● Enables users to generate phasing periods and hence cash flow data across the lifecycle of a project. The PHM provides users with the ability to normalise/spread costs across defined periods.
![Page 29: Powerpoint - InControl V10 Presentation](https://reader034.vdocuments.site/reader034/viewer/2022042516/55cf968a550346d0338c2d73/html5/thumbnails/29.jpg)